Keller Group plc (KLR) Earnings Call Transcript & Summary

August 2, 2022

London Stock Exchange GB Industrials Construction and Engineering earnings 58 min

Earnings Call Speaker Segments

Michael Speakman

executive
#1

Alright. Morning, everyone.

David Burke

executive
#2

Morning, everyone.

Michael Speakman

executive
#3

Good morning, and welcome to Keller's presentation of interim results for 2022. First, on safety: there are no fire alarm tests scheduled today, so should the alarm sound, it will be genuine, and we will follow James out of the building using the usual routes. May I ask everyone to set their mobile phones to silent for the duration of the presentation? I come before you today a happy CEO — in fact, a very happy CEO. Since we assembled our 2022 plans in the autumn of 2021, the world has altered considerably. It has altered enormously, in truth. Inflation, as you know, is rampant. Russia has invaded Ukraine. We have situations in which supply chains are growing more problematic, and although labor appears to have loosened somewhat, there is definitely a considerable scattering of material shortages across the regions in which we operate. Confidence — among our clients and in the markets as well — appears to rise and fall fairly swiftly. All of this is something our operations confront daily. Yet in spite of all of it, today we are announcing a record set of results for the first half of 2022, and as we look toward the second half, we are confident that we will meet our expectations for the full year.

Michael Speakman

executive
#4

Today we'll stick to the usual agenda. I'll provide a quick summary. After that, David will walk you through the details on the financial results, and then I'll come back with a general business update, a summary and outlook, and finally we'll open it up for questions and answers. So, to the summary. As I mentioned, this is a record performance, given the environment we're operating in. Revenue in the first half is up 31%. Broadly, that breaks into three parts. The first is acquisitions. The second is passing through inflation, which, as I'd remind you, is something every one of our businesses has had to contend with. And then finally, pure organic growth, spread fairly much across all of our divisions. On profits, they're up 19%, driven by exactly those same three factors as revenue, plus it has faced headwinds from the lingering effects of inflation, which, as you know, we haven't fully passed on. The operational drag from disrupted supply chains — I'll get to that a bit later — and there are some other operational challenges. Debt stands at GBP 194 million.

Michael Speakman

executive
#5

I’ll let David address that part, since it involves a few moving pieces. Still, it’s a solid story, though a bit below what we expected a month ago. On safety: performance there is somewhat disappointing. Regarding activities, I’ll go into more detail on that shortly. On activities, I’m very pleased with what we achieved during the period, and I’m fairly confident we’ll keep making steady progress over time. Strategically, we’re continuing to make quiet progress on execution. One exciting element of that is NEOM, which I’ll also discuss in more detail later. It clearly has all the hallmarks of what could be an enormous project. Our record order book gives us confidence that, as we enter the second half and carry that momentum forward, we’ll be well placed to deliver our expectations in 2022. The board’s confidence, shown by the increase in the interim dividend, really reflects that. With that, I’ll hand things over to David, who will cover the financial details.

David Burke

executive
#6

Thanks, Mike. And I’d also like to welcome everyone here in the room as well as those joining us on the webcast. The layout of the financial slides today follows the same approach you’ve seen previously. First, I’ll give a few comments on the income statement for the half year, covering both underlying and non-underlying items. I’ll provide a waterfall analysis that sets out the main bridging items from underlying operating profit in half year 2021 to half year 2022. After that, I’ll discuss the cash flow and several balance sheet highlights, including net debt, and then point out some modeling considerations to keep in mind for the second half. Let’s begin with the income statement. This slide presents the summary income statement for the half year 2022, with the 2021 comparative on the right. It comes from the income statement included in this morning’s announcement. Let’s look at underlying profit first. Revenue rose by GBP 353.3 million between the half years, or 36%, equivalent to 31% on a constant currency basis. That figure includes the effect of the RECON acquisition, which is roughly GBP 112 million. On an organic constant currency basis, the increase was 20%.

David Burke

executive
#7

We saw volume rise across every division, since activity picked up as markets continued recovering from the pandemic’s effects. At constant currency, North America was up 39%, or 22% once you strip out the RECON acquisition. Europe rose 26%, and EMEA 7%. Alongside that volume growth came solid profit growth: a 26% rise to GBP 49.6 million, which is 19% higher at constant currency. As Mike said, these profits are records for us, and the fact that we achieved them amid major macro, social, and economic headwinds shows how resilient the business is — and that makes it even more satisfying for our teams around the world. Margins fell 30 basis points to 3.7%. The main cause is that when we pass through inflationary costs, it doesn’t always come with a markup, so margins get diluted. We also faced some operational difficulties in the North America foundations business, which hurt profitability and the margin rate too. I’ll cover that in more detail later when I walk through the operating profit bridge slide. Among the other highlights is the tax rate coming down to 25%, which reflects the mix of profits across jurisdictions.

David Burke

executive
#8

Earnings per share rose 31%, thanks to better profitability and a lower tax rate. As we flagged earlier, the interim dividend goes up 5% to GBP 0.132, putting us back on a growth path. Let's turn now to the operating bridge slide. It lays out the main factors behind the profit movement between the two half-years. You should recognize this format from earlier presentations. Going left to right, we begin at the 2021 half-year profit of GBP 39.5 million and show the FX effect, which came to GBP 2.1 million. Then we get to the North America division, which is lower by GBP 11.1 million at constant currency. The first item concerns the one-off claim that fell in the first half of 2021 and does not recur this year. The second bar shows a net decline in the division's business profitability, driven by a range of factors. RECON's contribution sits inside this bar, but it has been offset by weaker profitability in our foundations business stemming from some difficult operational issues in the half. These include labor and material availability, which hurt productivity, along with cost increases. Although we do pass through inflationary cost increases, there is a lag, and that hits the bottom line.

David Burke

executive
#9

And lastly, there were project execution problems that caused us to absorb some losses. We had one sizable contract issue during the first half that demanded substantial remediation and rework. As we typically do in such situations, we've prudently booked the entire rework cost before filing a claim with the client, and that claim is still ongoing. The next bar highlights Suncoast's improved profitability, powered by single-family home volumes that stayed high through the half, partly offset by higher steel prices affecting the high rise business after war broke out in Ukraine. Now turning to Europe, which came in up GBP 8.2 million. Across every business unit in Europe, volume growth was healthy. Nothing major to flag, simply solid execution following the logistical difficulties COVID created in early 2021. Every business is handling any fallout from the Ukraine war really well. HS2, that large project, is still being executed in line with plan. The acquisition included there concerns the NordPile business in Finland, acquired in H2 last year. The AMEA division is enjoying a fantastic year, up GBP 11.1 million. That is mainly a turnaround story rather than one of volume growth.

David Burke

executive
#10

Let's go through the bars one by one. The suspended contracts from 2021 were mostly tied to Mozambique. During the first half of 2021, we incurred costs without any revenue, and the settlement agreement was signed in the second half of 2021. COVID continued to weigh heavily on the Middle East and Africa in early 2021, so the improvement you see reflects emergence from those difficulties, together with gains from the restructuring carried out in 2021. The Australian rebound stems from coming out of the COVID-related difficulties that affected 2021. A modest rise in central costs brings you to GBP 49.6 million of operating profit for the first half. Turning to the following slide, I'll walk through non-underlying items. Once again the income statement, though this time we're looking at the middle column. Non-underlying operating costs came to GBP 6.1 million in the first half. You can see the breakdown of those costs in the box at the top right. GBP 3.5 million is attributable to an exceptional contractual dispute. GBP 1.2 million is linked to costs tied to the ERP rollout. Because this is a cloud-based software as a service solution, we cannot capitalize it and so will present it as an exceptional item over the years ahead. The restructuring charge stems from exiting two small non-core geographies during the half.

David Burke

executive
#11

One more standout item is the amortization of acquired intangibles on RECON, and this is the first time it appears in this table. Adding together every line under underlying and non-underlying performance, we get a post-tax statutory profit of GBP 24.4 million for the half year. Now I'll turn to cash flow. On this page you'll see the cash flow summarized from operating profit all the way down to net debt. Free cash outflow before interest and tax came to GBP 41.6 million in the half, mainly because of the working capital required to support the growth of the business. Please look at the working capital box on the right, where the analysis sits. We've noted repeatedly over time that this is a positive working capital business, so an outflow trend should be anticipated as the business expands. The analysis here is interesting for the gap between receivables growth and payables growth versus the first half last year. With material and labor availability and the strain that placed on the supply chain during the half, suppliers have taken the opportunity to push for tighter payment terms, in some cases including payment on delivery. We expect that trend to persist in the short term, with a return to normalcy next year.

David Burke

executive
#12

Additional notable items include acquisition spending totaling GBP 15.6 million. Of that figure, GBP 8.6 million is tied to contingent consideration for RECON, GBP 3.4 million relates to GKM from the May 2022 acquisition, and GBP 3.8 million represents the final payout on Bencor after last year's contract settlement in North America. Also worth flagging is the foreign exchange movement. We're seeing a tailwind on revenue and profit, but a headwind on debt, since most of it is denominated in U.S. dollars. In the bottom right box, we show net debt of GBP 194 million on an IAS 17 covenant basis. Leverage at the half year, on a lender covenant basis, stood at 1.1x — comfortably inside our target range of 0.5x-1.5x. We'll come back to net debt in more detail later. Moving on, here's the summary balance sheet, which shows the half years alongside the position at the end of 2021. The tables lay out the analysis of the movement from the end of 2021. There aren't really any highlights to call out beyond noting the significant FX movements, driven by the strengthening U.S. dollar and the scale of our activity in that region. The following slide gives a bit more detail on how the net debt profile evolved during the year.

David Burke

executive
#13

If you follow the graph's trend, the rise in net debt is visible, and it comes from activity levels ramping up plus acquisition outflows during the first half of the year. Net debt went up by GBP 80.6 million, and average levels rose by 76%. As I said, working capital requirements are mainly what drive that. Throughout the year we have operated well within our covenants, with leverage at 1.1x at period end versus a limit of 3x, and interest cover at 27.5x versus a minimum of 4x. At the half year, we hold GBP 215.7 million of undrawn borrowing facilities together with GBP 85.8 million of cash and cash equivalents. On the next slide you'll find some look-ahead modeling considerations. The purpose of this slide is to give some insight into how certain drivers of actual reported financial performance ought to be thought about as we move through the second half of 2022. Some closed profits. Residential volume should taper off, driven by the macro environment of increased interest rates. For high-rise contracts, though, we don't anticipate any further increases in steel prices. Large projects similar to H1. Portfolio, we will keep concentrating on bolt-on acquisitions. Operating profit percentage, we do expect that to improve versus H1.

David Burke

executive
#14

On profit phasing, we do still anticipate a moderate bias toward H2. We expect interest in H2 to rise, given the higher interest rates. The tax rate we're reporting here at the half is 25%, and that's what we consider it to be for the full year. On cash and working capital, we're aiming at roughly the 1x leverage, comfortably inside the 0.5x-1.5x target range. That's all from me. Thank you for your attention, and I'll hand you back to Mike now, who will walk you through the business performance update.

Michael Speakman

executive
#15

Thanks, David. Now to the business update, beginning with safety. On performance, safety, somewhat disappointingly, we went slightly backwards on both AFR and TRIR. I think that genuinely serves as a good wake-up call that we can't afford complacency. We've built up some momentum here. We need to keep it up. I would point out, and I'll say it to this audience, though I certainly wouldn't say it to the team, that those rates are significantly better than any of the industry comparatives in terms of averages wherever we are present. As I say, we really set our own targets. It's important we continuously improve on those. If nothing else, just from the cultural viewpoint, I think that momentum is important. On actions, I'm very pleased with the way the safety leadership team and indeed at the divisional level, the teams at that level and BUs are actually working together. They've worked together this year and actually worked on an updated induction program, which is being rolled out at the moment, which actually sets a higher level of expectations in terms of people joining the company.

Michael Speakman

executive
#16

This matters a lot, especially as we return to growth mode and start bringing people back on. From day one, it's crucial that folks receive the highest possible standards, with safety designed in right from the start. We've kept up our emphasis on near-miss reporting so we can stay ahead of incidents, and also on visible leadership — making sure people are physically out there and seen conducting safety leadership tours. A few practical measures: blind spot cameras on rigs. That's not standard practice. In Europe it is standard, but it hasn't been elsewhere. For us, that's part of what you might call a leveling up program — ensuring every piece of our equipment and every new rig actually has blind spot cameras installed, plus enhancements beyond that wherever we can. Virgin Pulse, I think, is a good example of one of many wellbeing initiatives across the company. David was out this morning trying to get his steps in because he's on one of the — his particular team is being especially competitive, the Legal Eagles.

Michael Speakman

executive
#17

The nice thing about it is that it draws everyone in, gets people talking, and above all, gets everyone out there being somewhat active. Ongoing backing for UNICEF. You'll find further particulars on that in the brief. I think it is — while we do back plenty of local initiatives, and indeed, we have, you know, a trust in Europe and Poland so our Ukrainian employees get support, that kind of thing. I think it also matters at a corporate level that we acknowledge our wider stakeholders. When it comes to climate change, there's a great deal of information on this slide. From that angle it's a very rich slide. Indeed, I think the original version of this one was in four fonts. There was so much in it. There's plenty of, you know, keen activity here. A few things to pull out. You know, we've stated specifically that we're working across all three of these areas. Scope 3 is by far the largest for us, but it's also the hardest to get at. You know, we're rolling out the education of the carbon calculator. We're getting embedded in our bidding processes. As far as practically possible, trying to influence clients in that regard, to take solutions which have a lower carbon footprint.

Michael Speakman

executive
#18

Honestly, the reaction to that varies quite a bit depending on which clients and which regions you look at. We'll play our part, though it's definitely not a magic solution. More practically speaking, the piece we can actually control right now is Scope 2, and from having started at zero, we're making solid progress there. I believe — and you'll see the blue box down at the bottom — that right now, at the half-year mark, our Scope 2 emissions are down by over 20% against the 2019 pre-COVID baseline of ours, which comes to double the target we'd set. That's good to see. My expectation is that this momentum carries on, and I very much hope we're firmly on course to reach our 2020 target — sorry, 2030 — when it comes to net zero emissions for Scope 2. Turning to the order book, it has reached an all-time high. Obviously, inflation accounts for part of that. FX plays a role too. Yet what's also encouraging is that it's broad-based — spanning just about every part of the business. One or two business units have gone backwards year-on-year, but mostly, just about everywhere holds coverage of at least six months, and that coverage is of decent quality.

Michael Speakman

executive
#19

From where I sit, more specifically, many of the business units have—through fair means and foul—responded to the instruction to, you know, seek out more secure revenue over the short term. Here, for example, you know, there's GBP 25 million on an oil and gas facility in Assam, in India. You know, that will keep going, and in fact, it's in play right now. There are, you know, three significant infrastructure projects in Australia. There's, you know, Tangenvika, a bridge project in Scandinavia, and, you know, another couple of Polish infrastructure projects. Now all of these things matter to us because, unlike some of the private and commercial work, you know, we can count on these being completed in the medium term against, you know, an uncertain economic outlook. Moving on to the divisions. First of all, North America. North America, the revenue was up, you know, almost 40% there, benefiting from RECON, benefiting from the increase to the pass-through revenue and inflation, and also some growth across the board. Operating profit, unfortunately, was backwards at 27%, driven by everything to do with the revenue drivers just discussed.

Michael Speakman

executive
#20

That GBP 7 million claim we benefited from in the prior period, which David touched on earlier — it doesn't repeat. You know, the lingering effects of inflation we haven't recovered, plus inefficiencies brought on by shortages of materials. I'd say North America, more than any other region, has really been hurt by local availability of cement. That's created major operational difficulties for us. Honestly, we probably underestimated that earlier in the year. It's something our sites have always had to contend with, you know, historically. All contractors do. But over the last six months especially, I think it's become particularly troublesome. And unfortunately, the inefficiencies you incur, you can't recover. Because if people are standing around waiting for materials to show up, you know, that is frantic. It's not something you can recover from the supplier or indeed from the client. As for the other businesses, Suncoast, Moretrench, RECON — all of those performed very well and very pleasingly during the period, which, you know, I think is very good to see. Moving on to Europe. Yeah, steady as she goes, really, Europe. They've had a good rebound from the previous period in terms of, you know, 2021, the early part of that was quite severely hit by COVID.

Michael Speakman

executive
#21

They've bounced back this year. There's a bit of momentum behind them now, you could say. They've landed some solid wins and made decent strides right across the board. Northeast Europe — mainly Poland, I'd say — has taken the biggest hit from the Ukraine war. A number of projects there were pushed back or scrapped early in the year, either because they sat near the border or because funding looked uncertain. That created something of a drag. Still, there's plenty of strong work and real momentum in other parts of the region, which is good to see. The one exception we'd flag is safety performance. There's no pattern behind that rise. We've examined it quite closely. Even so, it's something the team, culturally, wants to tackle and make sure they reverse. Turning to AMEA, I'd say this one is especially encouraging — the rebound here, as you know, is a big step up on revenue, but an even bigger one on operating profit. Obviously, versus the prior year, we have. Last year we took a GBP 4.8 million write-off tied to the suspended contracts, which David highlighted on the bridge slide earlier.

Michael Speakman

executive
#22

On top of that, there's a couple of million tied to branches in Africa, which, frankly speaking, were marginal and loss-making. Those were closed last year as part of our portfolio rationalization. So that incrementally contributed year-on-year. Then you've had forward momentum, mainly in Australia but elsewhere too, and all of that produced the half one performance of 2022. On margins, I'd say 6% in this area is roughly what I'd expect going forward. Also pleasingly, across the whole region, we've got a pretty decent spread of order coverage. Australia has attracted some very good infrastructure projects that are just on the verge of starting. Austral has a good bank of prospects that actually replaced the Cape Lambert project, which we've now completed. ASEAN's a little bit thin, to tell you the truth. Malaysia and Indonesia, I think, are still recovering from the travails of COVID. Whereas India just goes from strength to strength. They are very selective about what they do. They pick quality targets with quality clients, and they seem to be increasingly successful at doing so.

Michael Speakman

executive
#23

And then, the Middle East. We have some opportunities over there that we still need to sort out, particularly when it comes to locations. The major one is obviously NEOM. Speaking of that, this slide is probably the one I use most. When you bring up NEOM, it really aligns with our strategy — extremely well, in fact. We've shown this slide to the client to illustrate why what they want and what we want line up so closely. If you look at the top part, it's a highly appealing project. It comes with some strong technical challenges. There's solid engineering and solid architecture in it, and it matches what we do. From where we sit, it's something where we can draw on the scale and expertise of the group. Considering how large the project is, it matters to the client that we're able to mobilize and actually provide the resources they require. When it comes to delivering solutions to them, we can offer the complete suite of engineering solutions and get them out to site. As you've seen with the major projects we've taken on before, securing resources and putting logistics in place is a strength of ours, and we're in a strong position for that.

Michael Speakman

executive
#24

As for the project itself, well, it's obviously still taking shape. I'm certain every one of you has come across some of those press releases over the past two weeks. We're at a very early stage, and I'm reluctant to attach figures to it internally, never mind publicly. Still, it's fair to say we're moving quickly to prepare for the first works order, and in fact, if it hasn't happened already within the coming week or so, the initial item of new equipment tied to that first works order will be landing in the country. Across the following two months, the rest of the kit will show up. No matter how you slice it, this is a huge project. It's an extremely ambitious one. To us, this client matters a great deal. We possess the capabilities and the resources needed to satisfy their requirements. Momentum on this is building fast. Once we learn more and feel more assured regarding the schedule and so forth, well, naturally we'll pass that along to you. That was encouraging news. Now, to bring you back down to earth, I wanted to walk you through this slide. I realize some of you have already laid eyes on it.

Michael Speakman

executive
#25

Bringing this up felt necessary given the uncertain world we live in. Keller has faced uncertainty before—with COVID, and with financial crises both local and global. It has simply weathered those well. There's a list there of some of the traits that make this company more resilient than most. We aren't recession-proof; resilient to recession is how I'd put it. We can shift between different sectors—from private and commercial into public and infrastructure. Our geographic spread is good. Whatever Mr. Putin does with gas supplies in Europe probably won't hit our North American business that much. So we do have these natural buffers and counters. The graph on the right-hand side shows all of this—the fact that we've generated cash and have been paying dividends for effectively 28 years, growing them over that period. In these uncertain times, I think that's something people should know. Finally, summary and outlook.

Michael Speakman

executive
#26

To sum up, we achieved a record performance for the first half, even with the conditions we face. Not only did we accomplish that, but we've also kept carrying out our strategy. Now, we haven't discussed new M&A much during this presentation. That isn't to say we haven't been examining opportunities, but we remain highly disciplined about it. We're also pressing ahead with the restructuring and simply ensuring the portfolio is properly shaped. We are mobilizing on NEOM, and we currently have significant momentum in the business, backed by a very strong order book. Clearly, all the confidence in that is demonstrated by the dividend increase. Honestly, I don't anticipate the world improving much in the second half. There may be, perhaps, some leveling out in the degree of uncertainty, but from where we sit, I don't believe it's going to get much easier during the second half. My hope is that near the end of the year, it will start to ease. Still, I believe we have enough in the tank to certainly deliver H2 and give us good momentum heading into 2023.

Michael Speakman

executive
#27

So as we approach the close of the year, obviously the board is going to be considering the final dividend too. And finally, I want to repeat that the board expects us to come in line with full year expectations. We're saying that with growing confidence. From that standpoint, it's a good spot to wrap up the presentation. Now we'll move to questions and answers.

Joe Brent

analyst
#28

Morning. Joe Brent here from Liberum, with three questions, if that's alright. First, regarding LNG and NEOM, can you tell us what news flow to anticipate and what we should be watching for? Second, might you provide a schedule for the expected cash exceptionals — that is, the timing of cash exceptionals from here on? Third, exceptionals include a GBP 3.5 million contract disputes item. Could you offer a bit more detail on that, and is it usual for you to classify contract disputes as exceptionals?

Michael Speakman

executive
#29

Absolutely. I’ll take the first one. I’ll have David handle the second.

David Burke

executive
#30

And third, I’m glad to do that.

Michael Speakman

executive
#31

Sure, I’m glad to address the third one too. When it comes to LNG and NEOM — on LNG, I’d say that beyond the usual, routine LNG-style projects, we’re actively searching out every prospect that exists, and not only in LNG but in other energy infrastructure programs too. Germany, for example, is discussing doubling its wind farm count. We don’t handle everything — it depends on where those farms are sited — and some of that work will represent prospects we’ll pursue as well. As for LNG specifically, the Gulf Coast of North America is clearly a primary area in terms of export facilities, and Northern Europe is another region we’ll be examining. In Northern Germany there are 3 separate facilities that the German government is aiming to develop further. Near term, they’re pursuing temporary installations, yet they are also constructing permanent ones. Other export facilities will emerge elsewhere globally where FEED studies and similar work are finished and parties want to move faster. We’ll assess every single opportunity on its own merits to determine what we can deliver.

Michael Speakman

executive
#32

A number of these will be more appealing than others, depending on who the GC is and whether they have a track record with alliances or actually self-perform. We won't pursue everything, you know, but we'll do it selectively. As for NEOM, it all hinges on the client. I expect that as we move through quarter three and quarter four, we'll really start building momentum on the first works order. By Christmas, I expect we'll be at run rate in terms of delivering the volume on that. I also expect — and this is pure guess, but it's based on working through the pattern of our interactions with the client to date — my expectation is that late Q3, early Q4 is when they'll start gearing up for the second round of works orders, which by that time, I think, will be materially bigger than the first works order.

David Burke

executive
#33

Yeah. On the underlying piece, I think the emphasis there—specifically the cash element of that non-underlying figure—is the GBP 6.1 million of operating costs. If you look at those items individually, the restructuring has already been spent. On the ERP costs, roughly GBP 0.2 million of that has been spent, and some remains to come. The exceptional contract dispute represents a future outflow. That relates to a very old project that probably predates Mike and myself. It's simply something that has arisen over this past six months. It is commercially sensitive, which is the reason we aren't opening up too much about it.

Clyde Lewis

analyst
#34

Morning, this is Clyde Lewis from Peel Hunt. I'll also go with three. First, on materials availability — you've clearly called out cement, especially in the U.S. Could you update us on where things stand and how you expect that to flow through, and whether there have been any issues with steel, which is obviously another key input. My second one was on margins in the order book. It'd be helpful to hear your view on what's in there, and again, the momentum upwards or downwards on that side. The last one was really about the portfolio restructurings. You've obviously flagged a couple of small ones done in the first half. What's left, if anything now, on that front?

Michael Speakman

executive
#35

All right. I’ll take care of these, and you jump in whenever you think it’s useful.

David Burke

executive
#36

Yeah.

Michael Speakman

executive
#37

When you look at availability of materials, there's something quite interesting there. The three largest consumables for us are cement, steel, and diesel that goes into the rigs, as you know. Considering those three, each has its own financial and logistical profile. Fuel, for instance, essentially when the oil price rose, we were hit right across all of our operations in roughly a month. That was widely understood, and on most of it you could actually secure recovery. It impacted everyone, yet the availability was there. With steel, whether it's rebar or strand, and whether it's tied or welded, availability differed around the world. Europe was struck by steel shortages in quarter one, though they recovered very quickly. With Suncoast, strand availability — more specifically pricing — was somewhat of an issue. It has been, and frankly still is, very volatile even now. It's leveling out and, if anything, is becoming more certain where the orders we are placing are concerned. What's harder in some respects — frankly, I hadn't quite got my head around this at the start — is the cement. Because cement delivery and concrete, you know, the aggregate built up from that, is very much a local matter.

Michael Speakman

executive
#38

The material is supplied locally. Although the vendors may carry international names, they actually provide and run operations locally. So you observe varying traits, varying availability, and in fact varying pricing — substantially varying pricing — around the globe. In the U.K., you pay approximately double, and always have, for cement compared with France. That has persisted indefinitely. You find a similar pattern across borders between Austria and certain states to the east. There are quirks to it. One thing that magnifies this in North America is that we're usually working on smaller projects there, so we'll depend on the supplier instead of a local batching plant or a GC's batching plant. On a large civil project in Europe, for example, or in Australia, the client supplies the cement. Even when you're the one paying, they'll have a facility to guarantee it's there. In North America, typically apart from Hampton Roads, that isn't the situation. So you're much more dependent on outside suppliers. Though conditions are improving, we're still not through the difficulties. There remain certain areas of North America where even now, you know, it's still an issue.

Michael Speakman

executive
#39

Way less than at the start of quarter two, though there’s still some difficulty. I figure it will improve as the year goes on, since things are going to loosen up. Regarding order book margins, my sense is they are broadly getting better. That is partly because we saw in the early part of the year that people were starting to reach capacity — not only us, but the market overall — and deliberately starting to push it up a bit. It will take a little time before all of that flows through. As David said earlier, there will be some catch-up when it comes to material pricing. My view is that in 2023 and 2024 we may actually see some margin uptick and margin recognition on the material pass-through too. But all of this behaves somewhat like a hysteresis effect. Working it through takes a little time. I don’t know whether you have anything to add on that.

David Burke

executive
#40

No, I'd say that's roughly accurate. What I see as the truly limited factor is the significant effect on the bidding activity we have underway at present. As for availability, that's simply the point where we're telling the guys they ought to build more margin into their bids.

Michael Speakman

executive
#41

On the portfolio restructuring side, I’d rather not get into too many specifics. What I’ll do instead is explain the philosophy behind it. Our strategy statement is essentially that we want positions where market share is higher. The reason is that higher market share means less risk for us, and it means better margins, which show up in greater utilization of assets, people, and fixed costs. That is what we’re after. Since post-COVID, it has become clear to us that some parts of our portfolio sit at the lower end of that spectrum, and no path is visible to actually bring them to the higher end. So, naturally, we are looking to see whether someone else would be a better business owner. That is what we’re working through.

Analyst

analyst
#42

Thanks. It's Jonny Cooper from Numis. On the replacement ratio, which was lower year-over-year in H1, I'd just like to hear why you're able to be more disciplined on CapEx during the period. Thinking about NEOM, if orders come through at the magnitude that's been suggested, what would your expectations be there in terms of CapEx? You mentioned that you've got new kit arriving on site. Will that require a lot of investment in kit? Thanks.

Michael Speakman

executive
#43

You’re welcome to discuss the replacement ratio, and I’ll cover NEOM.

David Burke

executive
#44

Yeah, I think on the replacement ratio, with it coming under pressure from a working capital standpoint, we're looking at CapEx more carefully, especially in the U.S. We're just letting that play out in terms of whether we choose to buy or lease. On NEOM, with the equipment utilization we expect on that job, we'll be running 24/6. We do expect that we'll actually buy that CapEx.

Michael Speakman

executive
#45

It's pretty fascinating when you look at NEOM, because if you stack it up against, let's say, a city in Europe — and over there, if you're fortunate, you might get five working days per week, plus there's a curfew, and it's fairly rigid about when operations can run. Under those rules, you can't even get the rigs started. When it comes to something as basic as maintenance, you're genuinely restricted. Now set that beside NEOM, where, as David mentioned, work carries on 24 hours a day, for at least six days per week, and should the need arise, they can also put in the seventh. Our plan is essentially to make the rigs standardized. As we grow the fleet in that location, we'll always, you know, keep one rig in maintenance. The crew is going to be operating at an intensity that's far, far greater. In fact, to reflect that, we'll be shortening the lifespans — from a depreciation standpoint — of all those assets. Still, it's a pretty demanding period, because given how the work is structured, you must pour everything and complete all the piling — the pouring side of things — during the night, purely because of the temperatures.

Michael Speakman

executive
#46

So you’re essentially operating on a day-by-day production rhythm. That’s something that, as you know, will accumulate over time.

Analyst

analyst
#47

Hey there, everyone. Regarding the operating margin in North America, it sounds like quite a few factors came into play during the first half that were one-time in nature, and then obviously there are the questions around the availability and.

Michael Speakman

executive
#48

Yeah.

Analyst

analyst
#49

On the supply side, I was hoping you might be able to lay out a bit more detail for us. Margins in the second half ought to get better on their own as those one-time items drop out. So then, what do you view as the medium-term operating margin? Since, as you know, historically it has reached as high as 9%. Presumably you don't expect a return to that level anytime soon, but what would the medium-term target be?

Michael Speakman

executive
#50

Sure. Regarding what we anticipate for margin improvement — as you mentioned, some one-off items affected the first half. My view is that during the second half we'll move toward roughly 6%, perhaps slightly above or below that, depending on how cement supply develops. Going forward, once that recovers, and once margin on pass-through materials is recognized, or prices for certain materials come down, those margins will rise over time. I'd expect it to climb to 6%-7%. I don't think it will reach 9%. Should a super project come along at some point, it could get there. The business is large enough now, with sufficient run rate, that sustaining 9% is probably a bit too ambitious, even for me.

David Burke

executive
#51

Yeah, regarding that earlier point about the order book and bringing more quality into it — I think that should help get those margins back to where they ought to be.

Clyde Lewis

analyst
#52

Could you give us a bit of detail on Mozambique and where things stand there? It seems as though it won't get underway this year, but here's hoping for next year.

Michael Speakman

executive
#53

It's quite interesting, actually, because two weeks ago the French stated they were definitely not going to restart or issue remobilization orders to anyone. The Rwandan army is positioned around the facility, and in that sense it's semi-secure, but not secure enough for Total to remobilize. I don't expect anything this year, and even if it were to happen next year, it will take time before anything actually happens. We're adopting an increasingly hawkish stance on this. Technically speaking, building a facility on land isn't the only option available to them. Given the pressure on LNG and production at the raw end, I would have thought there'd be something of an imperative for them to act. I'm still scratching my head, trying to work out what they're going to do. Because naturally, you'd get after it, but they aren't. On balance, from our perspective, we're just being a bit cautious about it at the moment.

Clyde Lewis

analyst
#54

Could I ask one more thing regarding the U.S. and the kinds of orders you’re seeing come in — the inquiry levels, I suppose — and how that differs across end markets, you know, public sector, commercial, and housing in particular is what I’m thinking about. Well, public, commercial, industrial.

Michael Speakman

executive
#55

Absolutely. And please jump in if needed. I’d say Suncoast is experiencing some softening when it comes to individual family homes.

David Burke

executive
#56

Right.

Michael Speakman

executive
#57

You know, over the past month or so, we’re going to see that. I don’t think we’ll experience it as severely as the overall statistics suggest, because, you know, the bulk of our activity is in the Texas, Dallas area, and a huge swathe of building is still underway there. I mean, if you go down there or sit down in San Antonio right now, there are lots of cranes, lots of construction happening in terms of industries and activities. You know, they’ll need people, and people need houses. I think, you know, it will come off, but it won’t be as disastrous as it was in 2008, put that way. That said, high-rise is beginning to grow, which is fine. We, you know, both come out of the same factory. We’ve got a natural hedge there. Beyond that, I think we’re seeing a reasonable set of activities across the patch. There’s probably less compared to a year ago. There’s probably less data center work and less logistics, you know, storage type of work. I mean, there’s less of that coming through. Certainly if you look around the coastal areas and some of the deep basements there, in Florida in particular, there’s a lot more activity going on there.

David Burke

executive
#58

Yeah, I’d say I do, at least somewhat.

Michael Speakman

executive
#59

Oddly enough, there’s some recovery showing up in the prairies. After we reduced the size of the business in Canada, in the prairies, it has actually improved. The remaining fixed cost base that we have there is performing quite well. Vancouver is performing well. Toronto is performing very well following, you know, the labor union problems throughout the state earlier in the year. All of that has resolved itself. The operation we have in Quebec is simply steadily gaining momentum, which is positive.

Analyst

analyst
#60

I have a couple of follow-up questions, if I may. First, regarding the ERP system, I believe you said earlier that it would be something like a five-year project.

Michael Speakman

executive
#61

Yeah.

Analyst

analyst
#62

It's obvious that a sizable amount of investment is being made this year. I'd just like to hear how that's progressing and whether you've identified any early initiatives as part of the rollout. And then second, can I just get clarity on the steel price point? When you say you expect no further impact in H2, does that assume they stay where they are — with an impact if they rise — or have you hedged it?

Michael Speakman

executive
#63

All right. I'll take the ERP, and you can handle steel. To me, ERP is similar to setting up a scrum: everyone lines up correctly, gets tightly bound together, packs against the other side, and then you advance in small increments. With each small increment, you squeeze and push, squeeze and push, squeeze and push, and eventually you can drive it across the five-yard line for a score. That is precisely our approach, since you know we are doing it. Whenever we discuss ERP, I never miss the chance to state that the project manager and the site supervisor are what this is all about. It is not about him and his consolidation. It is not about bays. Those will come to us at no cost if we handle things properly on-site. What matters is ensuring this system is centered on the project manager. The reasoning behind that is extremely straightforward. We handle roughly 7,000 projects each year, which amounts to 7,000 small P&L accounts. We ought to run it in an entrepreneurial way along those lines, ensuring they receive the highest-quality, most pertinent, most precise, and most prompt information available, so they can make a call every day.

Michael Speakman

executive
#64

If we do that—and we will—then those 7,000 projects are going to succeed, and they'll be more successful tomorrow than today. What that means is everything past that point, which is essentially cost, whether it's divisional overhead or central overhead, you know, we can handle it more sharply, and it will be, you know, a benefit to everyone. But there's some very good stuff here. We have some excellent people working on this. We have some excellent IT specialists who've been through this many times before. We have some excellent people from the business—the best and brightest, in fact—pulled out of the business to work on the project. You know, we have proper assurance processes in place from the board and the ExCom. We aren't rushing. We're simply proceeding one step at a time.

David Burke

executive
#65

In terms of where we stand on that journey, the blueprint phase is still where we are. Last year we did a piece of work, I think, in which we convinced ourselves as an organization that since the way we go to market is fairly similar around the globe, there ought to be no reason our processes shouldn't be similar too. What the blueprint phase we're going through now involves is walking through those processes in greater detail, as Mike says, through the lens of the project manager and site supervisor, and figuring out what we want those processes to be and getting the best of what people are doing in some parts of the world that they aren't doing in others, pulling all of that into one process for the different areas. We're currently doing the fit gap between what comes out of the box with respect to the system and the processes that we want. Our watch word from both Mike and myself is that we want to keep customization to a minimum so as to keep that system as agile as possible. That blueprint phase continues through to the end of this year, and we'll run a pilot in early next year where we'll really test those processes and the technical side, the system that underpins it, to make sure it's fit for purpose.

David Burke

executive
#66

So after that, we'll expand it throughout the remainder of the group. On the topic of steel pricing, if we look back to the start of the year, prior to the war in Ukraine, we held a certain view of the steel cost curve, especially as it relates to high rise. Again, the distinction between slab on ground and high rise is simply that high rise carries a longer lead time regarding the steel strand you strike under that contract. Once war broke out in Ukraine, we needed to shift that cost curve, and that produced a bit of a hit during the first half of the year. What we're telling you now about the second half is that, with steel prices having declined, provided they remain at current levels, we'll be year-on-year or half on half.

Michael Speakman

executive
#67

Your point about hedging is pretty interesting, actually, because with strand as a commodity, finding something to hedge against it was really tough. In practice, the sole option available to you is to purchase it and hold inventory, since, as you know, no derivative exists that correlates strongly with it. Right now, suppliers won't accept purchase orders going past three months. Yes.

David Burke

executive
#68

Yeah. In certain situations, spot.

Michael Speakman

executive
#69

Yes.

David Burke

executive
#70

Spot prices.

Michael Speakman

executive
#71

Yeah. For the domestic U.S., it's spot on.

David Burke

executive
#72

My view is that if someone purchases it with the intention of stockpiling, a specialized warehouse would be required to store it, considering how heavy it is. In fact, we believe the cost-benefit analysis of doing that does not really push us in that direction. There is no question that we have raised our inventory levels. That is visible in the figures. I also believe that stockpiling is not the solution either.

Michael Speakman

executive
#73

Is there anything else? Well, thank you so much. Those were some really good questions. I believe we'll adopt this format going forward, and in fact try to keep the presentation somewhat tighter so that we have more time for questions. So thank you so much. Thank you all. Thank you everyone on the web.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Keller Group plc transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Keller Group plc earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Keller Group plc or any ticker on your watchlist.