Good morning, everyone, and thanks for being with us for our half-year results presentations — both those of you here in person and those joining via webcast and audio, to whom I'd also like to extend a welcome. I'm Andrew Davies, Chief Executive of Kier Group, and with me today is Simon Kesterton, our Chief Financial Officer. This morning I'll take you through the highlights of the past six months to 31st of December 2022, and then I'll hand over to Simon, who will walk you through the group's financial performance. After that comes an operational review, an update on ESG, and we'll wrap up with our outlook. There will be an opportunity for questions and answers at the end. If we move on through the disclaimer and look at the half year 2023 highlights on Slide 4. We delivered a strong set of results in the first six months. We had positive momentum in the business; infrastructure services revenue grew by 5% and construction grew by 4%. We do, however, continue to see inflationary pressures in the business, and certain projects are having to be reappraised and therefore delayed due to cost pressures, in particular in our construction business.

Andrew Davies

executive
#2

Even so, we managed an adjusted operating profit of GBP 57 million, which is up 6% versus the prior period. Our adjusted operating margin came in at 3.7%, which leads the industry, and we keep beating our medium-term goal of roughly 3.5%. I feel immense pride in the whole Kier team for turning in yet another strong set of results, and Simon will go through the financial performance in greater depth later on. We remain sharply focused on carrying out the medium-term plan by growing in our core markets, with support from U.K. government spending commitments. So, hitting a 3.7% adjusted operating profit margin within the first 18 months of our 3 to 5-year plan gives me more confidence that the business will keep delivering for our shareholders. At 31 of December, the group's net debt stood at GBP 131 million. That net debt figure mirrors our normal seasonal working capital cycle and also the complete repayment of our CEPS facility. So GBP 131 million was a terrific result given that backdrop. For the year, average month-end net debt was GBP 243 million, against GBP 191 million a year earlier. Underlying positive cash flow is now showing through, and that has let us bring down our debt and our debt-like items.

Andrew Davies

executive
#3

The medium-term plan is well supported by our order book, and it shows we keep gaining from U.K. government spending. Year-on-year, the order book is up 26%, moving from GBP 8 billion to GBP 10.1 billion — a reflection of contract wins throughout our business that give us revenue visibility across multiple years. Underlying momentum in the business is strong. For FY 2023 revenue, 96% is already secured, which offers a high degree of certainty at a time when economic and political market uncertainty is wide. We have put significant effort into raising the quality of the order book. As a reminder, during the last three years we have exited contracts that were low-margin and loss-making. A great deal of time has gone into de-risking our portfolio, and our focus is on winning work within U.K. government and regulated authorities on negotiated terms with appropriate risk profiles. Long-term framework positions underpin our order book; frameworks are how we reach the market. We have maintained and grown our central and local framework positions. Long-term framework positions, however, are excluded from our order book, so they amount to an additional pipeline of opportunity. We remain committed to our sustainability framework and ESG targets, which we will discuss later in this presentation. At a strong GBP 10.1 billion, our existing order book has kept growing in the period, giving us confidence and healthy visibility for the full year FY 2023 and into FY 2024.

Andrew Davies

executive
#4

So with that said, I'm glad to be able to pass things over to Simon.

Simon Kesterton

executive
#5

Thanks, Andrew. Good morning, everyone. If you turn to Slide 6, that lays out a high-level income statement. Revenue for the first half, as Andrew said, is comparable to the prior year and shows volume growth in both infrastructure services and construction, which offset the anticipated decline in property transactions. I'll take you through this on the following slide. We delivered adjusted operating profit of GBP 57 million in the first half of the year despite inflationary pressure. The group is 20 basis points ahead of its medium-term plan margin target of 3.5%. The business made a statutory profit before tax of GBP 25 million. That's post adjusting items and amortization. Statutory profit has doubled compared to half year 2022. This shows period-over-period improvement and how the business continues to progress towards its medium-term value creation plan. We achieved adjusted earnings per share of 8.5 pence. That represents a 9% growth when compared to the 7.8 pence in the first half of last year. Net debt consistent with last year was GBP 131 million and reflects the usual seasonal working capital outflow. We achieved the GBP 131 million despite the repayment of our supply chain finance facility, CEPS, in July 2022. Average month-end net debt was GBP 243 million.

Simon Kesterton

executive
#6

That went against the prior period, yet it matched what we had anticipated, because of the repayment of our CEPS facility along with other debt-like items. Moving to Slide 7, beginning on the left-hand side, we begin with revenue of GBP 1.5 billion. Revenue from infrastructure services rose 5%, mainly because of the ramp up of capital works on High Speed Two. Construction revenue grew 4% as our order book begins converting into revenue. Our new prison in East Yorks, Yorkshire, Her Majesty's Prison Full Sutton, keeps ramping up production. It's worth noting we achieved this growth even though customer budget approvals were delayed, projects were reappraised, and value engineering was used to bring projects back in line with budgets, with public sector spending having been affected by cost inflation. Property revenue dropped by GBP 66 million as we saw the expected decline in property transactions, reflecting current market conditions. We took advantage of favorable market conditions at the end of our last financial year, knowing it would subdue property transactions for the next couple of years. Now moving to the adjusted operating profit bridge. We begin with the previous year's first half adjusted operating profit of GBP 54 million. Volume mix and price changes have produced an increase of GBP 4 million.

Simon Kesterton

executive
#7

Fewer property sales meant property profits came in GBP 6 million below the prior period. Cost inflation for the period was just under GBP 5 million. Inflationary pressure persists because of the macroeconomic backdrop, though we keep offsetting most of it. Target cost or cost reimbursable contracts account for over 60% of our order book. Where we do extend price certainty to customers, that happens only once the main risks and opportunities are clear. In construction our average order is just GBP 14 million, so contracts get repriced regularly. Finally, management actions total GBP 9 million. Those management actions mainly reflect cost-saving initiatives that are ongoing during the first six months of the year. As a result, adjusted operating profit rose to GBP 57 million. Adjusting items were GBP 20 million in the period, well under the GBP 30 million recorded in the first half of last year. Restructuring costs have fallen materially, as we expected. As a reminder, half of these items are non-cash, consisting of amortization tied to historical acquisitions of GBP 9.8 million. Restructuring costs, as I mentioned, are down significantly, from nearly GBP 12 million to under GBP 4 million.

Simon Kesterton

executive
#8

The costs during this period are tied to shrinking the international business to match its market opportunities. The comparative costs mostly stem from the regional restructuring and cost-cutting in our construction business, which wrapped up in FY 2022. A portion of these costs was disbursed in the first six months of this financial year. Within other items of GBP 5.5 million, GBP 4 million relates to fire cladding costs. Because of the type of construction projects we usually take on, and with regulation having changed, we estimate our exposure here could be a worst case of between GBP 10 million-GBP 20 million. Turning to free cash flow. Operating cash flow conversion met expectations, reflecting the seasonality of the business. Adjusted EBITDA for the period climbed from GBP 77 million to GBP 91 million. We had GBP 79 million of working capital investment, which is a substantial decrease versus the half year 2022 outflow of GBP 133 million. Working capital is seasonal in this business, since summer is a busier period than the winter months. Working capital came in better than the prior year, mainly because of volume growth in the business. The prior year comparative was additionally affected by VAT payments of GBP 10 million.

Simon Kesterton

executive
#9

For the back half of the year, the group expects the H1 working capital outflow to reverse and to get back to net cash. As we said earlier, we repaid the last GBP 50 million of CEPS in July 2022, so our total operating cash generation, along with proceeds from the equity raise and the sale of Kier Living, has enabled us to cut CEPS by GBP 201 million since the 31st of December, 2018, and by GBP 79 million since the equity raise, which shows the underlying cash being generated. CapEx for the first six months came to GBP 27 million. But GBP 22 million of that is tied to payments made and the leases now capitalized under IFRS 16. Most of the increase is for additional plant and equipment to support the ramp up of HS2. Net interest and tax rose by GBP 8 million in the first half because of interest payments of GBP 5 million, with a mark to market benefit of GBP 2 million from the hedge we took out in February 2022, tax of GBP 3 million and leases of GBP 2 million. We keep supply payments at 34 days on average, consistent with the prior period.

Simon Kesterton

executive
#10

Taking a step back to examine free cash flow for the first half, and excluding the CEPS effect of GBP 38 million, that outflow represented a substantial betterment versus the GBP 100 million outflow we would have posted a year earlier. So we can see the underlying cash generation, with adjusted EBITDA converting into free cash flow. Moving to Page 11, here's the net debt bridge. On the left-hand side we begin with closing cash of GBP 3 million at the end of June 2022. Then comes the free cash outflow of GBP 88 million that I just mentioned. Adjusting items were GBP 23 million. That figure includes payment of items accrued for in FY 2022 plus pension payments of GBP 7 million. Next is the purchase of Kier Group shares. This relates to the group's employee benefit trust, which buys Kier shares in the market to settle the long-term incentive plan share schemes when they vest. The net cost of that came to GBP 12 million. The remaining GBP 4 million mainly concerns net joint venture investments. All of this brings us to a net debt position of GBP 131 million, unchanged from the prior year.

Simon Kesterton

executive
#11

Turning now to financing and liquidity. The business's present debt structure, after the 2021 refinancing, appears on the right-hand side. As a reminder, most of our facilities were extended under last year's refinancing and come due in January 2025. Over the year's first six months, beyond caps, we paid down a total of $54 million across our revolving credit facility and U.S. private placement notes, with both having matured in December 2022. Those repayments came out of operating cash flow, and we still hold substantial headroom across our facilities. Slide 13 lays out where we stand on order book. That order book is of high quality and has grown considerably — by 26% — to GBP 10.1 billion, against 31 December 2021. As Andrew noted, 96% of our FY 2023 revenue is secured, and we keep winning work in the markets we have chosen. We have put significant effort into raising the order book's quality. Our focus is on securing work with U.K. Government and regulated authorities. We remain focused on managing risk and reward as we bid, negotiate, and deliver work. As was said earlier, 60% of our order book sits under target cost or cost reimbursable contracts.

Simon Kesterton

executive
#12

In our infrastructure segment, close to 100% of contracts are signed on either a target cost or a cost reimbursable basis, and that matters for keeping our risk and reward profile in balance. Over in construction, we make use of staged lump sum contracts so that, where it makes sense, risk is fixed with our clients and certainty is delivered. Two-stage contracts are also part of our approach, letting us negotiate favorable terms and keep risk managed. Our typical order comes in at just GBP 14 million. Because that average order size is relatively small, we end up repricing contracts on a regular basis. Significant long-term framework agreements keep underpinning the order book. Long-term framework positions of ours are not included in the order book. They amount to additional opportunities for the group. Turning to capital allocation. Optimizing shareholder returns is our focus. So as cash is generated from operations, we expect to put it to work in a number of ways. CapEx should be minimal, though we intend to invest more in our property business so as to produce consistent returns over time. This we will keep doing in a disciplined and controlled manner. Further deleveraging. As you know, a sustainable net cash position is what we are aiming for over the medium term. Our target is dividend cover of approximately three times earnings through the cycle.

Simon Kesterton

executive
#13

As soon as we can see what our sustainable net cash position looks like over the medium term, we recognize that resetting the dividend will be essential so that shareholders get their share of the group's growth benefits. On the M&A front, the group will keep looking at value-accretive acquisitions in core markets where there's a chance to speed up the medium-term plan. I'll now pass things back to Andrew for the operational review.

Andrew Davies

executive
#14

Thank you very much, Simon. Moving on to Slide 16, I'd like to provide some detail regarding operational developments during the past six months, beginning with the infrastructure services segment. Just to reiterate, this segment encompasses our highways, infrastructure projects, and utilities operations. Revenue has grown, rising by 5%, and that's mainly due to the ramp-up—as Simon mentioned—of HS2 capital works within our infrastructure projects business. We are a partner in the Eiffage Kier Ferrovial BAM, or EKFB, joint venture; Kier is carrying out the longest stretch of earthworks, 80 km stretching from the Chilterns to a point just south of Warwick. We hold the lead role for project management on that effort within HS2, EKFB/HS2, and we serve as the project integrator inside the joint venture. In this business, adjusting operating profit rose 3% to GBP 34 million. Adjusted operating margin for infrastructure services stays robust at 4%. Some of the volume gains from HS2 have been partly offset, however, by higher contract mobilization costs in our utilities business. Our utilities business has experienced greater activity in the telecom sector, reflecting the U.K. Government's commitment to rolling out 5G connectivity nationwide. Through our telecoms team, we are deeply engaged in installation and maintenance work on this as part of the broadband rollout.

Andrew Davies

executive
#15

With the telecoms operation having expanded, margins took a hit during the first half of the year. Because of that, we are in the process of reviewing expenses within that unit. Things keep getting better in our utilities division. Order book momentum has been favourable, rising nearly 30% to GBP 5.8 billion, as Simon mentioned. Our utilities arm—which handles long-term contracts for construction and maintenance work across water, energy, and telecom—was, as I noted, handed a 3-year extension to the Network Services Alliance framework by South West Water and Bournemouth Water together, a deal we figure is worth GBP 55 million annually to us. That framework assignment builds on a prior contract signed in April 2000 under the AMP7 cycle. With 97% of revenue already locked in for FY23, plus the wins we've landed lately, this gives solid support to revenue in the infrastructure services business for FY23 and past that. Turning to construction: this segment consists of the regional build operation, through which we put up schools, hospitals, prisons, and defense projects for the U.K. Government. It also takes in our strategic projects business along with Kier Places, our housing maintenance and facilities management operations.

Andrew Davies

executive
#16

Construction volumes rose 4% to GBP 709 million, reflecting the scaling up of work in East Yorkshire on a new prison, HMP Full Sutton, being built for the Ministry of Justice — the U.K.'s first net zero carbon prison. This category C, low security facility should accommodate 1,500 prisoners and will operate on electricity alone. Its design incorporates solar panels, heat pumps, and efficient lighting. Modern methods of construction are being used to build the prison, delivering benefits in both cost and program efficiency. Social value is likewise a central part of the project, with Kier committing to 50 sustainable employment opportunities for prison leavers, 50 apprenticeships, and upskilling 1,000 workers within its supply chain. Kier Places also recorded volume growth across facilities management and housing maintenance. The facilities management work is mainly for the Ministry of Justice and Home Office, showing the synergies between these two businesses. Adjusted operating profit grew 25% to GBP 33 million, with margins up 70 basis points to 4.6%, as the benefit from volume growth and a previously realigned cost base begins to flow through to the operating profit line. Simon said order book momentum has carried on in our construction business, with an order book up 23% to GBP 4.3 billion.

Andrew Davies

executive
#17

We were just recently named to the GBP 10 billion offsite construction solutions framework. Kier, together with our joint venture partners McAvoy and Metek, got appointed to all six lots, and it takes the place of the existing modular building framework and will run over the next four years. Kier has also been reappointed to the North West Construction Hub high-value construction framework. This new iteration of the framework will keep on supporting local authorities that are procuring construction and maintenance of public sector buildings in the area. We landed places on both lot 1, for projects valued at circa GBP 8 million-GBP 25 million, and lot 2, which covers projects GBP 25 million and above. Kier has operated within the framework since it began in 2009, working alongside many public sector organizations across the Northwest region through two-stage arrangements, meaning early contractor involvement to deliver projects such as schools, colleges, leisure and sporting facilities, and theaters. The Kier Places team has been given preferred bidder status by RHP Group on a GBP 75 million 10-year contract to deliver repairs, voids, and planned works across its housing portfolio of around 10,000 affordable homes in the boroughs of Richmond, Hounslow, Kingston and Hillingdon. As part of RHP Group's large-scale improvement plan, skilled teams at Kier Places will aim to carry out works to upgrade homes, including installing new kitchens and bathrooms, as well as making properties more energy efficient.

Andrew Davies

executive
#18

For FY 2023, 95% of revenue in our construction business is already secured. I'm extremely proud to report that the construction team has secured fresh, top-quality and profitable projects in the markets we serve, which shows the bidding discipline and risk management that are built into the business. As those orders turn into work on the ground, we anticipate the related revenue generation and working capital flow opportunities will come through afterward. Last, let me turn to our property business. This business of ours invests in and develops mainly mixed-use commercial and residential schemes and sites throughout the U.K. It is firmly established in the urban regeneration and property development sector, and we mostly work via joint ventures so that risk and opportunities are managed. As expected, operating profit declined because of fewer property transactions, which current market conditions have driven. Since we expected market conditions to slow, we managed to raise our completions and transactions toward the end of FY 2022 so that returns for our shareholders would be maximized. Where possible, we will keep seizing market opportunities with regard to land acquisition and the timing of build and selling, and we will do so while staying disciplined in how we use capital. Simon noted that the capital employed in our property business reflects Kier's equity, debt investment, capital appreciation and reinvestment of profits.

Andrew Davies

executive
#19

Capital employed rose to GBP 158 million, up from GBP 122 million that had been invested as of 30 June 2022. Return on capital employed for the first half of the year came in at 7%. As a reminder, as I said, we are aiming to grow capital employed to GBP 170 million over the medium term. We see this as a consistent pace of capital investment at a level we expect will help smooth the returns profile of the business. In our view, selective investment in sites, letting the capital season, and then transacting takes some time. Over the medium term, we expect a more consistent performance from our property business. Like the rest of Kier, the property business has done well in work winning, and the highlights include our Andover development in partnership with Test Valley Borough Council, which was fully let, and our Solum joint venture with Network Rail sold its final residential block at its Twickenham Gateway development. Moving on to ESG and sustainability. This is the slide which I hope most of you will recognize, but we thought we would remind you of Kier's key focus areas. Our purpose is to sustainably deliver infrastructure which is vital to the U.K.

Andrew Davies

executive
#20

Being a strategic supplier to the government means ESG sits at the heart of whether we can win work and hold onto places on those long-term frameworks. Take U.K. government contracts: anything above GBP 5 million demands net zero carbon and social value commitments. Earlier, we rolled out our new sustainability framework, building for a Sustainable World, and it addresses sustainability through an environmental lens as well as a social one. Our honest conviction is that being a responsible business and leading within our industry requires tackling climate change's impact while also leaving a lasting legacy in the communities where we operate. Moving to environmental matters on Slide 21. That slide sets out one of the initiatives aimed at cutting our carbon footprint. After engaging with our supply chain partner, we began using battery storage units next to generators on our sites. Since our sites frequently sit in locations lacking mains power supply, and because fossil fuels produce significant carbon emissions, we see battery storage units as delivering a reduction in our carbon emissions and a substantial cost-saving opportunity too. To date, we've brought the storage units onto just under 20 of our 400 live sites.

Andrew Davies

executive
#21

Turning to the social side, Kier is — and has consistently been — dedicated to putting money into training schemes that raise our people's skills, with the aim of tackling the skills gap the industry currently faces. Ours is a people-driven business, and how we perform hinges on our capacity to draw in and keep a committed workforce. Across the period, more than 500 apprentices took part in programs, which works out at 6% of our workforce. Right now, 7.5% of our people are enrolled in formal training programs. I'm pleased to say that this January, we pledged to set up 10 internships for talented Black students under the 10,000 Black Interns scheme. We are determined to make Kier a place where diversity and inclusion are real, and our aim is to grow the internships count as we move ahead. Let me turn now to the summary and the outlook. The group's results for the last six months show how much more resilient we have become and how our financial position has strengthened. We have kept beating our medium-term targets. Compared with the prior year, our order book has grown substantially, reaching GBP 10.1 billion, which mirrors a big number of contract wins right across our businesses. That gives us solid multi-year visibility on revenue. Such awards mirror the bidding discipline and risk management that are now part of how the whole business operates.

Andrew Davies

executive
#22

Despite inflationary pressures along with political and economic uncertainties, current trading is still tracking what the board expects. Going forward, we anticipate producing positive operating cash flow across the whole year and finishing the year with a net cash position. Our FY 2023 outlook is still the same. The group is in a strong position to keep gaining from U.K. government commitments on infrastructure spending, and we are focused on delivering a sustainable net cash position as well as a sustainable dividend, consistent with our medium-term value creation plan. With that, ladies and gentlemen, I would like to open the meeting up for any questions. Andrew.

Andrew Nussey

analyst
#23

Good morning. Andrew Nussey here from Peel Hunt. I have a couple of questions, please. First, on the inflation impact — there's clearly some commentary in the market that inflation pressures are starting to ease. Are you still encountering delays in construction that stem from inflation, or is it starting to improve a little? Second, regarding the management actions and the GBP 9.1 million benefit, how much of that was sort of an annualized effect from actions taken previously, as opposed to what was done during the period, and what might follow going forward?

Andrew Davies

executive
#24

Should I start, and Simon, would you like to cover the management action? On construction delays — yes, we're still experiencing them. I'd say they're easing, and I think you can see it in the order book, well, order book growth is solid, but construction revenue is rising, as we mentioned, 4%, 5%, and so on. I think that now reflects the easing. It also reflects the latency from earlier delays last year in construction working through. Those contracts have now been reappraised and are getting spades in the ground, so to speak. We are seeing an easing, but it does still exist, and inflation remains an issue in the business. I think it's fair to say it is easing, and the evidence for that, I'd say, is the construction revenue growth. Would you like to take the management actions?

Simon Kesterton

executive
#25

Yeah, on the cost side, the management actions rolling forward came to roughly GBP 5 — an incremental GBP 1, and then GBP 3 of that was really offsetting inflation. It wasn't a cost saving in itself. It was offsetting that inflation.

Andrew Nussey

analyst
#26

Appreciate it.

Andrew Davies

executive
#27

Johnny.

Johnny Cooper

analyst
#28

Thanks. Johnny Cooper from HSBC. My first question is about the construction margin — you noted that management actions and higher volumes gave it a lift. It would help to also get a picture of how margin behaves across the separate businesses inside construction, plus what separates Kier Places from Regional Build, and what effect that had?

Simon Kesterton

executive
#29

That's a fair question. Places carries a somewhat better margin, while our construction business has a lower one. Right now the mix leans toward our Places business, and that's where we'd anticipate growth, since construction is still in recovery. Once construction picks up, I'd anticipate that margin getting somewhat diluted.

Johnny Cooper

analyst
#30

Regarding the debt that comes due in 2025, what are you currently expecting in terms of how you'll refinance it?

Simon Kesterton

executive
#31

Sure, I mean, clearly right now the debt refinancing markets aren’t in good shape. You know, we have plenty of time at the moment, so we’ll just watch them closely. Once a window opens, we’ll look to make the most of it.

Andrew Davies

executive
#32

Turning back to the construction issue, you’ll notice that when we mentioned taking management action there last year, we kind of signaled in advance that this step was coming, since we expected somewhat softer volumes during that period as inflationary pressure pushed timelines out—and you can see those benefits now showing up. It’s a business where volume matters a great deal, which is exactly why we’re keenly focused on ensuring the cost structure fits the volumes you have. What I said about utilities is essentially the same idea: we actively make management moves so that the cost base matches the volume of the business.

Johnny Cooper

analyst
#33

Thanks. I’ll ask just one more. You said you’d be able to deliver a good performance even with political uncertainty. At this point, if a Labor government comes in next year, what do you expect the effect to be on your end markets?

Andrew Davies

executive
#34

I mean, clearly, just like everyone else, we've been affected to some extent by what's happened with the government. You know, different ministers get swapped out, and so on and so forth. That inevitably creates a bit of a lull in processes. It may well be one factor behind the delays, though I genuinely believe, you know, inflation has been the primary issue in that regard. I mean, our read on the current government is that they've said they intend to stand by the original manifesto, the one they were elected on in 2018, 2019. That represented a pledge to recapitalize infrastructure in the U.K. Every indication is that we're witnessing that pledge carrying on. I think at present, you know, the government stays very firmly committed, and I think the chancellor recently, you know, responding to an article, gave a commitment that HS2 would keep going to Euston. Strong support and commitment is what we're seeing from the sitting government, which is great. I think when it comes to a future government, I think every party, in a bipartisan approach to investment in housing, investment in schools and education, investment in transportation, hospitals and healthcare. You know, obviously, we'll need to see what their policies are once they roll them out as part of any election campaign.

Andrew Davies

executive
#35

My sense is that, you know, there appears to be a really solid bipartisan consensus that infrastructure in the U.K. does need recapitalizing.

Adrian Kearsey

analyst
#36

Good morning, everyone.

Andrew Davies

executive
#37

Good morning, everyone.

Adrian Kearsey

analyst
#38

Adrian from Panmure here, with a couple of questions. Considering the macro picture for property, which sorts of property deals and investments would you probably steer the capital toward? Maybe if you take that one first, I'll follow up with my second question afterward.

Andrew Davies

executive
#39

Should I handle that?

Simon Kesterton

executive
#40

Right.

Andrew Davies

executive
#41

We're going to keep on examining the opportunities out there, as we have been. I mean, one thing we focus on with properties is finding areas where there are strong synergies with our operating businesses. I brought up, you know, how well the Twickenham scheme did — Twickenham Gateway — a residential project we built together with Solum, our partner at Network Rail, on top of Twickenham station. You know, it let them redevelop the station the way they wanted to and then fund it through the skill set we brought in, which enabled them to develop the residential piece. We keep looking at those kinds of opportunities inside existing JV agreements. We keep looking at logistics, though as we mentioned, we did sell a fair few of those last year. We made the most of the market conditions and the opportunities. Transacting a little earlier to capitalize on that was the right thing to do. It's a broad spectrum. It's a good portfolio that we're looking at. We do look at areas where we have strong synergies with either customers in the operating businesses, you know, such as Network Rail or such as the various councils we work with. It's across the usual spectrum.

Adrian Kearsey

analyst
#42

This is probably one for Simon. Could you give us some sense of what the non-underlying items are likely to look like for the second half, and maybe for next year too?

Simon Kesterton

executive
#43

Well, yeah — regarding what I brought up about the fire and cladding, I think that's the item that could potentially fall through, and we're looking at potentially GBP 10 million to GBP 20 million there, with 4 in the first half, go. Those are the ones more likely going forward. Andrew mentioned a sort of cost-based review on utilities. There could be a little bit from that, but I don't see it as material. From a cash point of view, of course, we're still cash flowing that Cheshire West and Chester amount, which cash flows out until 2025.

Adrian Kearsey

analyst
#44

Appreciate it.

Alex O'Hanlon

analyst
#45

Morning, both. Alex O'Hanlon here from Liberum. I've just got one question, if I may. Regarding the construction order book, you said two-stage bidding is a process you use to manage the risk of cost inflation. Could you give us a sense of what share of work gets bid on that basis?

Andrew Davies

executive
#46

Phew. A %, I mean, we do target two-stage. Most of the frameworks, you know, by the very definition are two-stage negotiations, so you will get into them. Sorry, you can go next. Look, you know, certainly, you know, that's our preferred route to market, is working with the customer, get early engagement, work with the customer, work through the inflationary pressures. You may have to value engineer it. That's, of course, the slight delays, as we've always consistently said. You always get to an end result with a proper and, you know, correct allocation of risk between the client and the contractor if you do two-stage negotiation. Not saying we do always the two-stage negotiation. If we're building, something with a client off a framework with a known cost base, with certain elements de-risked, maybe land risk excluded or asbestos risk excluded, we will do a lump sum, D&B contract. You know, you know the risk in that. If it's an unknown unknown or a new client or a new type of, we will almost certainly go through a two-stage negotiation as our preferred route to market, but not exclusively. At the end of that, when you get into contract, as Simon said, once you get cost certainty and risk certainty around the projects, very often to give the client budget certainty, you will then fix it out at a point in time, in the, in the contract.

Andrew Davies

executive
#47

That works for both sides, and it leaves room for the margin to potentially expand under the contract.

Johnny Cooper

analyst
#48

That's great. Thanks a lot.

Andrew Davies

executive
#49

Anyone else? All right. So with that, I'll bring things to a close. Thanks so much, everybody, and enjoy the rest of your day.

Simon Kesterton

executive
#50

Appreciate it.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Kier Group plc transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Kier Group plc earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Kier Group plc or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.