Kinross Gold Corporation (K) Earnings Call Transcript & Summary

July 30, 2026

Toronto Stock Exchange CA Materials Metals and Mining earnings 67 min

Earnings Call Speaker Segments

Operator

operator
#1

We appreciate everyone holding, and we’re glad to have you join Kinross Gold’s conference call and webcast for second quarter 2026 results. Every line is currently muted so that background noise won’t interfere. Once the speakers finish their comments, we’ll open a question-and-answer session. Should you wish to pose a question then, just press * and then 1 on your phone’s keypad. Thanks. At this point I’d like to hand things over to David Shaver, Executive Vice President. Please go ahead.

David Shaver

executive
#2

Thanks, and good morning to everyone. Joining us in the room today on this call are Paul Rollinson, our CEO, along with members of the Kinross senior leadership team: Andrea Freeborough, Claude Schimper, Will Dunford, Geoff Gold, and Bernard Vessels, who is our incoming Chief Operating Officer. If you'd like a full discussion of the risks and uncertainties that could cause actual results to differ from the estimates in our forward-looking information, please see page 3 of this presentation, our news release dated July 29th, 2026, the MD&A covering the period ending June 30th, 2026, and our most recently filed AIF — all of which can be found on our website. I'll now hand the call over to Paul.

Paul Rollinson

executive
#3

Thanks, David, and I appreciate everyone being on the call today. This morning I'll go over the results for our second quarter, share some high-level updates from across the portfolio, touch on sustainability accomplishments, and reaffirm our outlook. After that, I'll pass things back to the team so they can walk you through more detail. Before we get into the quarter itself, I want to call attention to a few changes on our senior leadership team. I'm happy to share that Bernard Vessels has been appointed Chief Operating Officer, taking over from Claude Schimper, who is set to retire later this year. Claude has played an essential role at Kinross for over 16 years, which includes the last 5 years on our senior leadership team and 4 years serving as COO. Throughout his time with us, he has guided our operations with unwavering dedication to safety, operational excellence, and continuous improvement, and he has helped secure meaningful, lasting benefits right across the business. To make sure the transition goes smoothly, Claude will stay on with the company for a period of time and work closely alongside Bernard. On behalf of the board and the whole Kinross team, I want to thank Claude for his exceptional leadership and the many contributions he has made to the company, and I wish him the very best in his retirement.

Paul Rollinson

executive
#4

Bernard comes to us with over 25 years in mining, having taken on progressively senior operations and leadership positions at Sibanye-Stillwater, Harmony Gold, Anglo American Platinum JV, and, most recently, Newmont. We're delighted to have Bernard join Kinross, and we look forward to benefiting from his deep operational leadership. Now moving to our second quarter results. After a robust Q1, we posted a robust Q2, giving us a superb first half and putting us in good position to meet our full-year guidance. We kept up our discipline on costs and produced robust operating margins. Consequently, we generated free cash flow exceeding $725 million in Q2 and surpassing $1.5 billion across the first half of this year. Our business is in superb shape, and our pipeline of growth projects, including Great Bear and Lobo-Marte, keeps progressing nicely. Our financial position and cash flow outlook stay superb, and during Q2, we kept returning extra capital to shareholders via both buybacks and our quarterly dividend, consistent with our goal of returning 40% of our free cash flow. On the operations side, Q2 was yet another robust quarter, with output of 492,000 ounces. Tasiast and Paracatu both made key contributions, jointly representing over half of our production and generating substantial free cash flow.

Paul Rollinson

executive
#5

On the projects side, we keep delivering solid progress right across the portfolio. In the US, the team is continuing to push forward our three new high-quality projects at Phase X, Redbird, and Curlew. Over at Great Bear, things are going well on both the advanced exploration and the main project. Turning to AEX, now that the remaining permits are in place, we recently carried out the first blast of the exploration decline. On the main project, detailed engineering and permitting are both moving along nicely. We're continuing to work with the authorities as their review of the impact statement moves forward. We're also continuing to engage with local stakeholders and Indigenous partners through regular community meetings, ongoing collaboration, and transparent communication. Moving across to Chile, as a reminder, we submitted the Lobo-Marte Environmental Impact Assessment in March, which marked an all-important milestone and formally launched the permitting process. Then, in May, we welcomed the newly elected president of Chile, President Kast, to our local offices in Copiapó. During his visit, he acknowledged Kinross's longstanding commitment to the Atacama Region and declared his support for our development plans in the region, including our world-class project, Lobo-Marte. We appreciate President Kast's support for the responsible operation and the development of our assets in the region.

Paul Rollinson

executive
#6

Yesterday evening, we shared news about Lobo-Marte, a top-tier asset in our portfolio that boasts a solid output profile, a low-cost structure, and outstanding economics. Will will go into more detail on that during this call. Now moving to sustainability: during Q2, our annual sustainability report came out. That document gives a thorough rundown of what we have accomplished and what we intend to do next. One thing that stood out for me was Mauritania. Back in June, we provided humanitarian assistance to farming communities in remote areas that are dealing with food insecurity brought on by drought and higher transport expenses. Shifting to our outlook: after a robust first half, we are still positioned to hit our production, cost, and capital guidance for the full year. As we noted three months ago, we keep enjoying a favorable relative cost position, underpinned by our disciplined handling of cost pressures via input cost hedging, productivity efforts, and our grade enhancement strategy. Going forward, our attention stays on steady operational delivery, cost control and capital allocation, plus ongoing progress on our high-quality resource base. We aim to keep producing strong margins, solid free cash flow, and long-term value for every one of our shareholders. With that said, I will hand the call to Andrea now.

Andrea Freeborough

executive
#7

Thanks, Paul. This morning I'll walk through the financial highlights for the second quarter, give an overview of our balance sheet and return of capital, and offer some comments on the outlook. As Paul mentioned, Q2 was another strong quarter for us. We produced 492,000 gold equivalent ounces, as planned. Cost of sales for Q2 came in at $1,336 per ounce, and all-in sustaining cost was $1,821 per ounce — both on plan as well. Margins were robust, above $3,100 per ounce. Adjusted earnings came to 71 cents per share, and adjusted operating cash flow was once again more than $1.1 billion. Attributable free cash flow totaled $727 million, after $406 million in capital expenditures and $327 million in tax payments. Moving now to our balance sheet. During the second quarter we kept strengthening our financial position, adding more than $470 million in cash while returning $275 million to shareholders. We closed the quarter with new records: $2.7 billion in cash and $1.9 billion in net cash. On return of capital, as a reminder, we're targeting 40% of free cash flow returned through a combination of dividends and share buybacks. Our shares continue to offer a strong return on invested capital, given our attractive valuation and free cash flow yield.

Andrea Freeborough

executive
#8

During the second quarter, we bought back 7.9 million shares in total, spending $230 million on those repurchases, and we kept paying our quarterly dividend, which comes to roughly $50 million. Taken together, capital returned during the first half came to about 37% of our attributable free cash flow, and we're still on course to hit our 2026 goal of 40%. After the quarter closed, we repurchased another $40 million worth of shares. I'm glad to share as well that, starting from when we resumed buybacks in Q2 2025, we've now repurchased more than $1.1 billion in shares, which works out to roughly 4% of the shares we have outstanding. Counting our quarterly dividends, we've returned about $615 million so far in 2026 and about $1.4 billion since the beginning of 2025. These figures speak to how strongly we generate cash flow and to our continued dedication to giving shareholders meaningful returns while we further reinforce our balance sheet. Moving on to guidance: after a strong first half, we remain firmly on track to produce approximately 2 million ounces at a cost of sales of $1,360 per ounce and an all-in sustaining cost of $1,730 per ounce, and we're likewise on track with capital guidance in the range of $1.5 billion. As for production, we anticipate the third quarter will match the first two quarters as we keep transitioning to Phase S at Round Mountain, and we expect the fourth quarter to come in higher.

Andrea Freeborough

executive
#9

When it comes to operating costs, looking ahead to the second half of the year, we anticipate somewhat higher costs, driven by a larger contribution from our US operations. Across the full year, we expect to land in line with our cost guidance. As Paul mentioned earlier, thanks to our disciplined cost management, we begin from a competitive cost position compared with our peers. We stay focused on controlling costs so that we can sustain strong margins and free cash flow generation. Over the near to medium term, our fuel hedging program keeps delivering meaningful protection against elevated oil prices, with substantial hedges in place for 2026 and 2027 alike. I would also restate that the fuel cost sensitivities we set out alongside our first quarter results have not changed, and the effect on our overall cost structure stays manageable and inside our guidance ranges. As a reminder, our guidance assumed $70 oil. For each $10-per-barrel move in the oil price, we expect an impact of roughly $10 per ounce, plus a possible additional $4 per ounce from secondary effects like freight and other consumables, as oil markets remain volatile. For added context, should recent oil prices hold through the rest of the year, the impact on all-in sustaining cost would be under 2%.

Andrea Freeborough

executive
#10

When it comes to supply, we keep getting fuel and other essential consumables delivered on a regular basis, and no disruptions have hit any part of our operations. Going ahead, we expect our grade enhancement strategy to deliver organic offsets against inflationary pressure and to help build a stronger cost profile over time. As an example, Phase X and Curlew should both start adding higher-grade ounces into our production profile beginning in 2028. Great Bear and Lobo-Marte, our two world-class development projects, are expected to add roughly 850,000 ounces each year of high-grade, low-cost ounces to our future production profile. With that said, I'll hand the call over to Claude now.

Claude Schimper

executive
#11

Thank you, Andrea. I want to begin by talking about how we approach safety. During this quarter, we kept putting money into safeguarding our employees via training efforts that are proactive and that support our safe-ground brand. Our program for managing critical risks keeps growing more robust throughout all our sites, and leaders are interacting with the workforce in effective ways and confirming the critical controls for tasks that carry high risk. Now moving to operations, beginning with Paracatu, which delivered a superb quarter, as robust output generated considerable free cash flow. Output of 158,000 ounces alongside a cost of sales of $1,108 per ounce matched the previous quarter. Paracatu is still positioned to hit its guidance of 600,000 ounces and a target cost of sales of $1,240 per ounce. Tasiast delivered yet another solid quarter. Output of 133,000 ounces rose compared with the prior quarter thanks to greater throughput, and cost of sales came in at $990 per ounce, matching the previous quarter. Tasiast is still positioned to hit its guidance of 505,000 ounces and a target cost of sales of $1,050 per ounce. At La Coipa, output reached 59,000 ounces with a cost of sales of $1,395 per ounce. Output rose compared with the prior quarter thanks to planned higher grade and throughput.

Claude Schimper

executive
#12

Our cost of sales came down versus the previous quarter, and that was driven by increased production. Before continuing, I want to recognize the serious winter storm that hit Northern Chile recently. Our thoughts go out to the nearby communities and to our employees who felt the effects of that event. Although we saw some impact, La Coipa is still on track to meet its annual guidance of 210,000 ounces, with a target cost of sales of $1,320 per ounce. Turning to the US operations, output was lower quarter-over-quarter as we ramp up ore mining at Round Mountain Phase S during the second half of the year. Taken together, the US sites produced 142,000 ounces at a cost of sales of $1,871 per ounce. At Fort Knox, production of 95,000 ounces matched the prior quarter. Cost of sales of $1,596 per ounce was lower than in the prior quarter, reflecting the timing of ounces processed through the mill. At Bald Mountain, production of 27,000 ounces was in line with the prior quarter. Cost of sales of $1,770 per ounce was lower, thanks to the ramp-up of capital stripping at Redbird in Q2 and more ounces placed on the heap leach pads. At Round Mountain, we are presently in a phase of higher waste mining and a lower-grade, lower-volume ore supply as we strip Phase S.

Claude Schimper

executive
#13

We anticipate that Phase S will deliver ore of both greater grade and greater recovery during the latter half of this year. Now, shifting the focus to how we performed overall. Here at Kinross, continuous improvement and innovation are deeply ingrained in our culture across every part of the company, and every site has a committed team whose job is to assess, roll out, and maintain gains in efficiency along with stronger cost-control methods. I'd like to highlight several of these initiatives to show the way they assist us in countering inflationary and cost-related pressures. Beginning at Paracatu, the recovery-enhancement initiatives, which have been under development for the past 2 years, are at this point producing measurable outcomes. We upgraded the CIL circuit, brought in new gravity concentrators, strengthened process controls and carbon-management methods, and made focused gains in the performance of the acacia reactor — every one of these is helping drive better recoveries and stronger operating results. Over at Tasiast, our attention has been on enhancements to mining and mill throughput, plus our solar power. On the mining side, we concentrated on loading productivities, focused training, and bringing larger equipment into service. At the same time, we raised how effectively our hauling fleet is used by better balancing rosters, managing shift changes, and optimizing dispatch. Combined, these gains helped produce a record month in May, when Tasiast achieved the greatest tonnes mined and moved in its history.

Claude Schimper

executive
#14

At the mill, the team is concentrating on ongoing reliability gains, and a few illustrations include putting procedures in place that have cut rip belt changeout time by 50%, redesigning the SAG panels to be lighter in weight, and adding oxygenation so recoveries are more consistent. On the power side, the solar facility keeps supplying roughly 23% of the site's power needs, which brings lower energy consumption and lessens the effects of the recent spike in oil prices. At Bald Mountain, the shovel optimization program has produced better loading efficiency, yielding reduced mining costs while boosting equipment productivity. We've also brought in a relief operator program, and since the start of the year it has added about 2.1 million productive tonnes during break coverage. At Round Mountain and Fort Knox alike, we have fine-tuned haul routes and truck dispatching methods, which trims unnecessary engine hours and fuel use. Those efforts have delivered fuel savings of roughly 6.4 million liters while cutting haul cycle times at Fort Knox by about 7 minutes. Across every one of our sites, we are adopting artificial intelligence and machine learning to strengthen predictive maintenance, optimize schedules, and improve mine planning and fire response management. All told, our continuous improvement and innovation efforts keep producing measurable benefits throughout the portfolio, backing safety, productivity gains, and enhanced efficiency, and helping counter inflationary cost pressures.

Claude Schimper

executive
#15

Ahead of turning things over to William, I want to say that my time with Kinross has been an extraordinarily rewarding journey. Working with such a talented and dedicated team has been both a privilege and an honor. As I hand my responsibilities to Bernard, I do so with great confidence. His extensive operational experience, together with the strength of our team, puts Kinross in a good position for continued success. Thank you to everyone I've had the chance to work with over the years. Bernard, welcome to Kinross. With that, I'll now hand the call to William.

Will Dunford

executive
#16

Thanks, Claude. Working with you has been a real pleasure. Bernard, welcome to Kinross. I'm looking forward to collaborating closely as we keep pushing our operating and growth initiatives forward throughout the portfolio. Now, on to our resource base and project pipeline. A substantial gold resource inventory anchors our portfolio — over 27 million ounces of M&I, plus another 17 million ounces of inferred. Beyond our near-term growth projects, our technical services teams keep moving forward a number of attractive medium-term mine life extension opportunities drawn from this resource base, among them Phase 11 at Fort Knox, Top pit at Bald Mountain, resource pit extensions at Paracatu, open pit and underground extensions at Tasiast, and the La Coipa oxide extensions in Chile. Those projects could further strengthen our production profile, extend mine lives, and build shareholder value well into the next decade. The three high-quality projects in the US that we announced earlier this year are excellent illustrations of how we're drawing on our extensive resource base to create long-term value. I'm happy to say our teams are making solid progress on all three projects, and they continue to move them ahead on plan.

Will Dunford

executive
#17

Over at Phase X at Round Mountain, underground work is running a bit ahead of plan — more than 8,400 meters have been finished so far, which lowers the risk on our route to first production in 2028. Engineering for the surface and underground infrastructure is coming along nicely, and that includes kicking off detailed engineering on a paste backfill plant. Procurement is moving forward well too, with packages handed out for a lot of the critical items, like the mobile equipment, ventilation fans, and the CRF plant. Operations readiness has also been a big focus for us: 21 Kinross miners are getting underground experience alongside our contractor, and we've brought on board a highly experienced underground mine manager. At Bald Mountain, mining at Redbird is going well and getting a boost from the efficiency gains, and we expect Redbird output to keep ramping up for the remainder of this year. Building out the heap leach pad extensions that support Redbird came a long way in the first half of the year, helped by a milder winter — earthworks on the first leach pad extension are now done and lining is well underway. Engineering on the SART plant and the rest of the process infrastructure has moved ahead as well, and long-lead procurement is in progress for some of the key infrastructure. Now to our Curlew project in Washington: we made substantial progress in Q2 on the tailings dewatering plant, with the building finished and mechanical equipment installation getting started.

Will Dunford

executive
#18

Work on refurbishing the mill is beginning to accelerate — the contractor has been brought on board and has commenced the first demolition work. Development and infrastructure at the underground mine are likewise progressing nicely: construction of the primary ventilation and escape raises via raise boring is finished, and underground advancement is running ahead of plan. We're happy with how this set of opportunities is moving forward and will keep sharing updates as the projects proceed toward production. Moving on to Lobo-Marte, which is our next high-margin cornerstone development project after Great Bear. We carried out a high-level refresh of the feasibility study economics, reflecting inflation since 2021 as well as additional improvements to the execution strategy. As background, this historically operated project sits in the Atacama Region of Northern Chile, roughly 50 kilometers away from each of our two assets, La Coipa and Maricunga. Among the project's main attributes are a long forecast mine life, a high heap leach grade, and a low strip ratio — placing Lobo-Marte toward the lower end of the industry cost curve and strengthening its potential to be a meaningful contributor to long-term shareholder value. On production, using solely the initial mine plan and the current reserve, Lobo-Marte should produce about 4.6 million ounces across an initial 15-year operating life.

Will Dunford

executive
#19

We expect annual output to come in at roughly 350,000 ounces per year on average once steady-state operations are reached, which gives our portfolio a significant, long-lasting supply of low-cost production. Those characteristics, together with the considerable scale of production, generate excellent returns on the $1.8 billion of initial capital: an all-in sustaining cost of $1,000 per ounce, an NPV of $4.3 billion, an IRR of 26%, and a payback period of about 2 years, all of it calculated at a gold price of $4,100 per ounce. Even if gold prices fall, the project holds up well. Thanks to its high grade, low strip ratio, and low cost structure, Lobo-Marte should play a significant part in our grade enhancement strategy together with Great Bear, and it has the potential to become a cornerstone asset, contributing higher-margin production and robust free cash flow during the 2030s and on into the 2040s. The project also fits Kinross very well strategically, since it extends our mine life in Chile, a country where we have more than 20 years of production history and where the government strongly supports responsible mine development via large-scale open pit mining and heap leach processing — fields in which we have extensive experience in Chile as well as in the US. One major reason the cost structure is so low and the margin so high is the layout and scale of the two open pit mines at Lobo-Marte.

Will Dunford

executive
#20

The pit dimensions and the widespread mineralization make it possible to deploy a large-scale fleet, which under the current mine plan is designed to achieve mining rates reaching as high as 50 million tonnes per annum. Mining costs projected across the life of mine at $3.25 per tonne also gain an advantage from building conveyors that carry ore out of the open pits to the crushing facilities, which lowers operating costs for material movement. Above all, on the mining side, both the overall cost structure and all-in sustaining costs should see substantial benefit from the low strip ratio of 2:1, a result of the broad nature of the mineralization found in these porphyry deposits. What is planned under the current economics from the 2021 FS envisions developing the two open pits in sequence, starting with Marte, which has been mined before, thereby reducing the strip ratio and initial CapEx. As the project advances, we will keep studying the optionality surrounding the sequencing of the two open pits. Turning to processing, the project is designed around a nominal throughput rate of roughly 35,000 tonnes per day, with ore put through a conventional three-stage crushing circuit before heap leaching. The ore's amenability to heap leaching, together with a strong forecasted heap leach recovery of 69%, is also central to the strong margin and low expected cost of production at Lobo-Marte, since heap leach processing at an estimated $12.30 per tonne would be significantly cheaper than a conventional mill and CIL circuit.

Will Dunford

executive
#21

At Lobo, the reserve's average grade of 1.3 g/t stands well above what most heap leaches in operation today can claim, and that grade drives most of the project's robust margins, economics, and returns, with an estimated all-in sustaining cost of $1,000 an ounce. Thanks to this grade, Lobo has the potential to generate 300,000 to 400,000 ounces annually from a fairly uncomplicated 35,000-tonne-per-day, three-stage crush and heap leach facility. Turning to capital and site infrastructure, the refreshed 2021 FS points to initial project capital of roughly $1.8 billion, mostly attributable to processing facilities and site infrastructure, comprising approximately $1.1 billion in direct capital plus $700 million for indirects and contingency. Beyond the processing facilities, key infrastructure needed to support the project encompasses a 75-kilometer access road, a 60-kilometer power line, and a 40-kilometer water pipeline, which should deliver water from our existing operating wells that presently supply La Coipa. We also built substantial investment into the capital estimate to guarantee best-in-class environmental controls and initiatives, including options like covering all of our conveyors to minimize dust and employing regenerative braking on the conveyors to save energy. This high-level refresh was issued to account for inflation since 2021 and to reflect the current execution strategy, which has progressed over the prior years to improve constructability and reduce development and execution risk.

Will Dunford

executive
#22

We're moving into detailed engineering, and once that work is largely finished, we'll give you a comprehensive capital update. The estimated initial capital is manageable at $1.8 billion, and we plan to fund it from operating cash flow, consistent with our disciplined approach to capital allocation. What makes this project a central focus in our grade enhancement strategy is the combination of low mining cost, low processing cost, high heap leach grade, and the size of the resource. Importantly, the impressive economics in this update are only a starting point for Lobo-Marte. Beyond the current mine plan, the project holds significant upside potential, and it captures just a portion of the broader mineral endowment identified across the property. The current open pit mine designs in this update are unchanged from the 2021 feasibility study and include only the 2021 reserve, which was done at a $1,200 gold price. The 2021 mine plan was kept as the base case for the EIA submission, since baseline studies had advanced on this plan, helping to facilitate an earlier submission of the EIA, and the plan already provides production well into the 2040s. However, at higher prices, significant potential remains to further unlock value at Lobo-Marte through mine life extensions from the 2.8 million ounces of indicated resource and approximately 700,000 ounces of inferred.

Will Dunford

executive
#23

On the slide you'll see that this inventory could potentially be captured by laying each pit back further, which might extend the mine life in a meaningful way. You'll also notice that the mineralization stays open at depth, running past the resource pits, and in the end it is constrained only by insufficient drilling at depth. Beyond that optionality at the Lobo and Marte pits, we see potential across our wider land package to find additional open pit deposits through exploration, which might enhance the mine life and production profile even more. This land package is highly prospective and lies on the prolific Maricunga Trend, where two porphyry deposits and a substantial resource inventory have already been identified. We know deposits of this kind occur in clusters along structural corridors, and once we bring Lobo-Marte into operation we will focus exploration on discovering additional deposits. To wrap up on the Lobo-Marte economic update, we are excited about this project's quality and about the potential to bring it online to advance our grade enhancement strategy in the early '30s, driving high-grade, low-cost heap leach production in Chile well into the 2040s, with significant value creation potential for our shareholders. With that, I'll now hand it over to Geoff for an update on permitting at Lobo-Marte and Great Bear.

Geoff Gold

executive
#24

Thanks, Will. On the permitting front at Lobo-Marte, Chile's Environmental Assessment Service accepted the project's Environmental Impact Assessment in April 2026 — a significant milestone for Lobo-Marte and the team. Permitting is still on the critical path, and from the very beginning we've taken a rigorous approach, building environmental and community considerations into both the project design and the capital estimate. That includes using the best available technologies and measures aimed at protecting water resources, cutting down dust generation, and optimizing where infrastructure is placed so the project footprint is reduced. We keep working closely with the Chilean regulatory authorities to move the permitting process forward, with our aim set on first gold production in the early 2030s. Turning now to advanced exploration at Great Bear, as mentioned previously, we've received all the remaining AEX permits, and construction is going well, which William will cover later. Turning to the main project, we're continuing to advance permitting with both federal and provincial authorities. On the federal side, after submitting the third and final phase of the impact statement in April to the Impact Assessment Agency of Canada, which we refer to as IAAC, we entered the information request phase of the impact assessment process. IAAC is currently gathering and consolidating all third-party input comments on our impact statement, and we'll respond to those on a timely basis.

Geoff Gold

executive
#25

We’ll keep collaborating with IAAC to move the impact assessment forward, so that the final impact statement report IAAC issues lines up with the timeline we’ve set for the main project. Just to reiterate, getting that final impact assessment report from IAAC — and having it ultimately approved by the Federal Minister of Environment and Climate Change — is the essential first step toward securing the extra federal and provincial permits we need in order to build and run the Great Bear mine. As we’ve said before, we need this final impact assessment approval plus certain provincial early works and construction permits in the spring of 2027, which would let us use the summer construction season and keep targeted first gold production in late 2029. On the provincial side, we’re continuing to work with Ontario authorities to move the main project’s permitting along under the One Project: One Process — known as 1P1P — which the Ministry of Energy and Mines oversees. We’re glad that in early May the ministry deemed the final 1P1P project definition complete, and after that issued the integrated authorization and permitting plan for the main project. Individual Ontario permit applications have been submitted in line with that plan. Coming next is finalizing the integrated Indigenous consultations plan, which was also submitted under 1P1P.

Geoff Gold

executive
#26

Now, a quick update on the Indigenous community side. Work on negotiating impact benefits agreements is still moving forward. We're happy to share that we signed a community benefits agreement not long ago with the Northwestern Ontario Métis Community, and it locks in the main economic pieces, financial accommodations included. As for Lac Seul and Wabauskang First Nations, whose traditional territory the project sits on, talks on the impact and benefits agreement keep moving ahead, built on the foundation of the memorandum of understanding we signed at the end of last year. With that, I'll hand things back to Will for a technical update on the Great Bear project.

Will Dunford

executive
#27

Thanks, Geoff. At Great Bear, both the AEX program and the main project are moving along nicely. After we received the final AEX permits in April, surface construction at AEX has reached 93% completion, and we recently carried out the first blast at the exploration decline. As a reminder, that decline is going to give us drilling access for exploration and for extending the underground resource, along with delineation work. On the main project side, we keep making meaningful headway on procurement, contracts awarded, and requests for proposal issued, and selection of the open pit mining fleet is nearing completion. On detailed engineering, we are well advanced, at roughly 50% complete. Once detailed engineering wraps up, we will give an update on the initial capital in the first half of 2027, and that will include the impacts from inflation since the 2024 PEA as well as the impacts of any scope changes and enhancements we make as we move through detailed engineering. As detailed engineering progresses, we are working to make sure we are building a robust, reliable, world-class operation, given the multi-decade, high-margin production potential we see at this asset. Turning now to exploration, we are continuing with our 2026 55-kilometer planned drill program. In Q2, drilling carried on at the Strider zone, a recently identified zone of mineralization 2.4 kilometers along strike from the southeast edge of the LP resource.

Will Dunford

executive
#28

Additional drill results are going to be shared by us at a later point in this year. Having said that, I'll now hand things back over to Paul so he can offer some closing remarks.

Paul Rollinson

executive
#29

Thanks, Will. Following a solid first half, we're in good shape to hit our 2026 targets. We've got a strong slate of milestones coming up this year, including: continued strong operational performance, free cash flow generation, ongoing return of capital through our dividend and share repurchases, further strengthening of our balance sheet, advancing our projects pipeline, and continued exploration and studies of our resource inventory intended to bring in new projects to extend mine lives. Looking ahead, we're excited about what's to come. Our production profile is strong. Our relative cost position is attractive, and we're holding the line on costs. We're generating significant free cash flow. Our balance sheet is excellent. Our return of capital is attractive. We've got an exciting pipeline of both exploration and development opportunities. We're growing our net asset value and our per-share metrics. We take real pride in our commitment to responsible mining, which keeps us a leader in sustainability. To close, we believe our shares offer attractive relative value across a number of metrics. With that, operator, I'd like to open up the line for questions.

Operator

operator
#30

Thanks. We’re moving into the Q&A portion now. To ask a question, just press *1 on your phone’s keypad. If you want to take your question back, press *1 once more. Our first question is from Fahad Tariq at Jefferies. Your line is open.

Fahad Tariq

analyst
#31

Hello, and thank you for taking my questions. Regarding Lobo-Marte, could you perhaps discuss what the next steps might be and how we ought to be thinking about a possible pit redesign at current gold prices, when the CapEx spending would occur, and how that would line up against the timing of Great Bear? I'm just trying to work through what comes next over the coming few years. Thanks.

Will Dunford

executive
#32

As we said, the EIA has just been filed, making it the crucial path forward and the main next step. That process takes roughly 2 to 3 years, and it's where our attention is. Following that, we move into construction. Construction really lands at the end of the decade, and peak spending at Great Bear will be past its high point by then. On the redesign, as what we've put out shows, there's substantial upside not just in M&I but in cut-off grades and things of that nature. Given that a 15-year mine life of quite high quality is already in place, this is genuinely something we'll concentrate on once operations begin.

Fahad Tariq

analyst
#33

Okay, so maybe we just shift over to the broader cost picture. Kinross has clearly done a really solid job keeping costs in check. I guess my question is whether there are any spots where you're feeling cost pressure. It doesn't sound like diesel is necessarily a major factor at this point, but are you seeing anything when it comes to consumables, or even any labor negotiations coming up that we ought to know about that might lead to some inflation? Thanks.

Andrea Freeborough

executive
#34

Okay, this is Andrea, and I’ll handle that question. Just to remind everyone, our guidance for the year incorporated a 5% inflation factor, and we continue to feel fairly confident about it. That assumption was made before oil prices rose, but as you pointed out, the effect from those increases has been fairly limited, and we anticipate it will keep having no major impact. If fuel prices stay elevated, the total expected effect is roughly under 2%. On other inflation fronts, as I mentioned, everything remains within what we built into our guidance, though to offer a few concrete examples, we are experiencing increased power costs in Alaska, and on the labor front, Nevada is consistently a tight market—not notably worse than what we’ve seen lately, just continuing labor pressure in Nevada. That is really the main area of attention and what we’ve been observing on the ground, but once again, we expect to land comfortably inside our guidance, close to the midpoint for the year based on where we stand today.

Fahad Tariq

analyst
#35

Thanks a lot — that's great.

Operator

operator
#36

Josh Wolfson with RBC Capital Markets has the next question. Your line is open.

Josh Wolfson

analyst
#37

Thanks a lot. Going back to Lobo-Marte for a moment — I get that inflation is a factor in that environment, obviously, but could you share any further insight, perhaps into what pushed inflation up beyond simply industry trends? Thank you.

Will Dunford

executive
#38

I think clearly what drove the shift from the 2020 FS to the 21 FS was mostly inflation, so we were sitting at roughly 1.1 in 2021. That pushed us to above 1.5. Of the extra roughly 250 on top of inflation, some of it lands in 2021 — obviously a different gold price environment, and we had been planning to reuse some equipment from Maricunga. With the gold price environment as it is now, we want to be sure we hold on to that equipment for Maricunga, and we figured it makes sense, given the mine life, to purchase new equipment instead. That accounts for about $100 million of the added increase beyond that, simply to make it a higher-quality life-of-mine plan. Then there was also some advancement of the execution strategy, as the team has really dug into the details and reached the planning stage. Indirect costs are the other piece that brings us up to the 1.8. We have also raised the contingency from roughly 14% to 19%, simply because we are quite far away from when we had the detailed estimates back in 2021.

Josh Wolfson

analyst
#39

Understood, thanks. So turning to Great Bear and a few of the AEX disclosures: regarding the main permit, is there any approach that could reduce some of that uncertainty, and perhaps what might the risk profile look like? Thank you.

Paul Rollinson

executive
#40

I’ll hand it over to Geoff to address that, but the question concerned reducing uncertainty around the main project. Josh, our view is that we have two tracks running in parallel. AEX, clearly, is meant to take us underground so that drilling extensions at depth become more efficient and more cost-effective. Then there’s the main project—and I’ll let Geoff cover it—but really, the main project has been launched, so to speak, under this 1P1P, and I have to say that from the government side, things under the 1P1P are going really well. They are definitely meeting deadlines and moving items through the system. Geoff, is it fairly straightforward on the main project? I guess and

Geoff Gold

executive
#41

Josh, I believe you already know this, but to repeat, we have never described AEX as a critical path, and as Paul mentioned, those are two separate processes. AEX is purely a provincial matter, while the main project involves both federal and provincial levels. We are doing very well on both the federal and provincial sides. On efficiencies, we are already realizing the advantages of 1P1P at the provincial level, and we have come quite far with the federal agency that oversees the key permit we need in late spring of 2029, namely the final impact statement approval report. We have been collaborating closely with the federal and provincial authorities. They know our timelines well, and at this point, and again I will remind you, we are aiming for first production at the end of 2029. At this stage, certainly, what we are observing with some of the matters on the AEX side is not getting in the way of that timeline.

Josh Wolfson

analyst
#42

Thanks a lot. Appreciate it.

Operator

operator
#43

Anita Soni from CIBC World Markets has the next question. Your line is open.

Anita Soni

analyst
#44

Hi, good morning. First off, Claude, congratulations on retiring. Your time here was certainly exemplary when it comes to the operating track record. Best of luck in your retirement. Then I think my questions on Lobo-Marte were mostly asked just about the timing. I just wanted to get a sense on Round Mountain of how we could see the back half of the year play out. I think there was an update, I think, a couple of years ago regarding Phase X, and I thought production was going to be somewhat in the 150 to 200,000 ounces per year range this year, and it's kind of tracking a little bit behind. Are we looking for really strong grades in the back half of the year, or was that production profile shifted understandably from 2 years ago from that chart?

Claude Schimper

executive
#45

Morning, Anita — appreciate it. For Round Mountain, I'd say the 150 forward has consistently been the goal. Naturally, we're building toward it now that we're stripping into Phase S and reaching the ore during this year's second half. Once Phase X comes on later, that will add its own contribution and push things nearer the 200 range. The 150 was always meant as an average, with a ramp-up period included. We do expect output to rise toward the end of this year as we enter the Phase S ore and also move into higher-grade feed. Earlier in this year, production was drawn from heaps and historical mining. At this point we're transitioning into the ore over the latter half of this year. My view is that we're aiming at the 120 to 130 range for Round this year, and after that it should climb through next year and the years beyond.

Anita Soni

analyst
#46

All right. So when it comes to the kinds of grades we might expect out of Phase S, would that be roughly in the mid 1 1 grams? Is that what we ought to be seeing?

Will Dunford

executive
#47

My recollection is that when we published the average grade a couple of years back, it came in slightly under 1 gram on average, and I believe we're now moving toward 0.7, and then further along in the phase, at greater depth, we reach the 1-gram material.

Anita Soni

analyst
#48

Right. I was referring specifically to the deeper material, not what goes to the heap leach — that part stays consistent, more or less.

Will Dunford

executive
#49

We're going to roll that material out in the order 0.2, then 0.3.

Anita Soni

analyst
#50

Alright, thanks a lot.

Operator

operator
#51

Daniel Major from UBS is up next with a question. Your line is open.

Daniel Major

analyst
#52

Hello, and thank you for the questions — nice work on the quarter. My first one is about the balance sheet and capital returns. It's encouraging to see cash going back to shareholders in a sustainable way, but you now hold $2 billion in net cash, and sticking with that 40% payout ratio means the balance obviously keeps growing. Is there some ceiling on cash you'd be comfortable holding before you'd commit to returning a higher rate? That's the first part. The second part: with asset values having recovered, how does the M&A piece of the capital allocation framework look right now? Are there any opportunities you're currently working on? That's the first part of my question.

Andrea Freeborough

executive
#53

Okay, let me begin with the cash balance. That's correct. Our net cash position sits at a little below $2 billion, and we anticipate that figure rising further as we move through this year. We entered the year with a commitment to return 40% of free cash flow to shareholders, and we intend to keep moving forward on that, then we'll see how things wrap up by year-end. We feel good about where the cash balance stands. We feel good about it continuing to climb. Having a solid balance sheet really does help as we keep advancing our pipeline of projects, along with further opportunities running through that pipeline. On top of that, we're paying considerably higher taxes — we've paid a substantial amount of tax this year — and those liabilities will keep carrying forward. Our expectation is to grow the cash balance while we simultaneously keep investing in the business and returning capital. For the time being we're holding to the 40%, though that's something we'll keep evaluating as we move through this year and on into early next year.

Paul Rollinson

executive
#54

Let me address the M&A question. Once more, I'd simply state that our stance hasn't changed from what it has always been. We sit in a genuinely strong position, where—as Will mentioned—we hold a substantial resource inventory sitting behind our 2P reserve. You saw it earlier this year, when we shifted the US projects from that resource classification into development. There's plenty for us to keep examining within our own organic portfolio. To us, that's the core focus. It's the area we know best, and our team keeps working on additional drilling, on understanding the figures better, and on steadily advancing items from the resource side of the ledger across to development decisions. Watch this space. Regarding the external environment, we routinely monitor what's available out there and what might come up for sale, but once more, we're operating from strength, with no sense of necessity. If you glance in the rear-view mirror, our M&A track record speaks for itself. Across the last 10 years, we've completed only a couple of deals—a few deals. We are highly selective. We believe we can create value at either end of the scale, be it through development or through operational improvements.

Paul Rollinson

executive
#55

There's plenty we're able to draw on in terms of resources, but above all, the focus stays on creating value for our shareholders, and on whether any transaction is out there. We're watching closely, and discipline will remain our approach as we keep moving ahead.

Daniel Major

analyst
#56

Thanks. Perhaps I could squeeze in a few quick follow-ups. First, just one regarding Lobo-Marte. How much sustaining CapEx across the life of mine is included in that $1,000 AISC figure?

Will Dunford

executive
#57

That's something I'll need to follow up with you on. We can look into what portion of that is specifically sustaining.

Daniel Major

analyst
#58

All right, and if I could just ask one more. With prices running higher, what's the timeline for another pushback at Tasiast? When would you be considering that, along with a decision to extend the profile?

Will Dunford

executive
#59

So I take it you all have a revised technical report — what it shows is that output really begins declining once more in the early '30s, following the period when we're working through the core of West Branch 5. The key thing is making certain we're properly ready ahead of that point. Naturally, studies are moving forward right now so we can reach a stage where we feel confident enough to decide on carrying on mining during the '30s and then continuing with output at a higher grade.

Daniel Major

analyst
#60

Okay, many thanks.

Will Dunford

executive
#61

To follow up on that, the team has responded to us regarding this. We have roughly $1.5 billion in sustaining CapEx over the life of mine. Roughly half of that amount is stripping for Lobo.

Daniel Major

analyst
#62

I appreciate that.

Paul Rollinson

executive
#63

I might be adding a little more here, but really it comes down to—as you can appreciate, Dan—in a layback, we're simply examining economies of scale and what might be achievable with larger trucks, larger shovels, and truck optimization. What can we do to accelerate things when it comes to waste removal? A lot of the analysis at present is centered there, and on what we can do to shorten the schedule for how long the layback takes. That's our focus.

Operator

operator
#64

Tanya Jakusconek with Scotiabank has the next question, and her line is now open.

Tanya Jakusconek

analyst
#65

Oh, wonderful. Good morning, everyone. Thanks a lot for taking my questions. Claude, congratulations on your upcoming adventure. Claude, perhaps I could begin with you. I wanted to return to the cost side, since I'm quite impressed by the cost controls you have in place, given your open pits and low-grade mining, which is low-grade relatively speaking, obviously. I'm just trying to grasp this: you have those productivities that you mentioned. Andrea also noted that apart from labor and, I believe, power, and fuel, you aren't really seeing anything else inflating your costs. I'm just trying to work out whether your productivity gains can offset inflation. Do you think you can achieve 4, 5% from these productivity improvements to offset inflationary pressures on your costs? As I said,

Claude Schimper

executive
#66

Tanya, thanks so much — but like I mentioned, when we make these productivity gains, our long-standing view is that if we don't have continuous improvement efforts running at our operations, those gains will ultimately slip away from us. We put a lot of emphasis on running these various initiatives at each site. Another crucial piece is that whenever an initiative succeeds at one site, we roll it out to the remaining six sites so they adopt it too. It's a massive, complicated strategy — covering everything from tire management, where we've moved from the very bottom in that area to being at the leading edge. Those represent big dollars that bring your costs down. The other piece is simply our grade optimization strategy and how we select the right locations for shifting production. That's a help. On inflation — again, we operate in a global setting. We're in various jurisdictions. The level differs. As you watch FX and inflation, do I personally believe you can consistently stay ahead of inflation? That's the hard challenge. That's what we set for the teams. As you've observed, we've enjoyed considerable success in keeping our cost structure aligned with what we expected.

Claude Schimper

executive
#67

Achieving that demands relentless ongoing improvement plus an innovative culture inside the company.

Tanya Jakusconek

analyst
#68

Nice work on the cost front. Perhaps I can shift over to Great Bear. I have a few questions about some of the items to look forward to. First, I wanted to ask about the bulk sample. At what point should we be thinking about that bulk sample for metallurgical testing? When ought I to expect that it's coming?

Will Dunford

executive
#69

That is still some distance away. I don't have a precise date for it, but we need to reach the point where we're ready to take the bulk sample. We are clearly advancing the twin declines, and we'll begin driving some exploration headings either late this year or early next year. The initial priority is essentially to start drilling. My sense is that the bulk sample will likely happen late next year or at some point the year after. We can follow up with a more detailed schedule for that.

Tanya Jakusconek

analyst
#70

All right. Then it’s simply that.

Will Dunford

executive
#71

Honestly, the timing of when you decide to open up those middle levels is really what matters.

Tanya Jakusconek

analyst
#72

All right. Turning to the next topic — I believe permitting has come up quite a bit, and ideally every permit will be secured by spring of next year so that construction can begin after that. Perhaps 50% of the engineering work has been completed so far, and I think someone mentioned that you'll be able to give us an updated capital figure next year once you have a clearer picture. There could be some changes to scoping — may I ask whether you're seeing any at this stage, and what those are at this point?

Paul Rollinson

executive
#73

Yeah, I believe that's accurate. An inflation piece is always going to be in there, Tanya. As I think about other parts when we examine capital within the waterfall, it comes down to a mix of inflation plus discretion. Is there any spot where we might have overlooked something or come in a bit light? In that latter case, I don't think there's anything raising concern for us that we failed to anticipate. As a 10,000-tonne-per-day mill situated right off the highway outside of town, this is fairly straightforward. We consistently examine optimizations or enhancements that could prove more favorable with respect to environmental regulations, that kind of thing. An update will be coming. To me, this isn't a project that is especially capital-sensitive at all. Just keep watching for that. It'll be a fairly normal course adjustment, largely driven by inflation.

Tanya Jakusconek

analyst
#74

Right, Paul, that’s the point I was trying to make. I just wanted to clarify whether it was simply inflation plus something, and then whether a scope change would mean we’d need to make an adjustment for that—but it looks like it’s only inflation.

Paul Rollinson

executive
#75

It will be a mix, though generally I believe that more capital isn't automatically negative. When capital goes up, ideally that means we're getting something too. It's a matter of weighing the trade-off, whether that's a return, an efficiency, or a better standard. We'll take you through it once things are more finalized.

Tanya Jakusconek

analyst
#76

Perfect. I appreciate it.

Operator

operator
#77

The next question is from Matthew Murphy with BMO. Your line is open.

Matthew Murphy

analyst
#78

Hi there. I just have a quick clarifying question about Lobo-Marte. That $1,200/oz reserve pit is more or less your base case in this submission, and do you intend for it to eventually be adjusted to a more current gold price, sooner rather than later? If that's the case, how should we think about that $1,000/oz AISC? Does it go together with the 1,200, or is that the level you're targeting to get this into production at?

Will Dunford

executive
#79

That's the target we have in mind for getting this into production. First, as you can see, the bulk of that extra resource is located deeper, so it'll generally be extracted nearer the end of the mine's life. Among the areas we'll want to adjust once value engineering begins are the production rate and similar factors. Our design is built around a 35,000-tonne-per-day facility, since all our baseline work has been done on that basis, though naturally we'll examine whether there's room to improve it. The cut-off grade will decline, and the real question becomes when you can ideally place more of those tonnes on the pad without diluting that ASIC. Moving to a higher production rate is an effective way of achieving that. Those are the kinds of items we'll be reviewing. Pit sequencing too. At present, Marte is sequenced first. We'll also assess options for shifting Lobo around and possibly producing from two pits simultaneously. Every one of those optimizations will aim not just at extending mine life, but also at keeping that ASIC low and growing the scale of the asset.

Matthew Murphy

analyst
#80

Understood — I appreciate you clearing that up.

Operator

operator
#81

That brings us to the end of the question-and-answer session. At this point I'll hand things back to Mr. Paul Rollinson, who has a few closing remarks to share with us.

Paul Rollinson

executive
#82

Great. Thanks, operator. And thanks to all of you for being with us this morning. We're looking forward to getting together with everyone face to face over the next several weeks and months. Thanks for calling in. Thank you.

Operator

operator
#83

That brings us to the end of today's conference call. We appreciate everyone joining us. You're welcome to disconnect at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Kinross Gold Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Kinross Gold Corporation earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Kinross Gold Corporation or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.