operatorIf you'd like to see the materials for today's meeting, including fuller guidance on using the platform, just click the Documents icon. That brings up a list showing every document that's available. Once you pick one, it opens right inside Lumi. You can keep listening to the meeting at the same time as you look through those documents. You're welcome to send in written questions whenever you like, and the audio line for questions is open now. At this point I'll pass things over to Mr. Tony Ottaviano.
Tony Ottaviano
executiveThank you, Billy. Good morning to all of you. I appreciate everyone joining the call between the Easter and Anzac Day holiday. I'm proud to report today that we have an excellent suite of results to share with the market. Joining me today to help present these results are Jon Latto, our CFO, and Adam Smits, our Chief Operating Officer. Billy, without spending too much more time, can we go into the slide, please? The first slide is the disclaimer, or the important information, followed by the summary slide. If we start with the summary slide, again, it begins with safety. You will see from the highlight side that we've had another strong quarter of safety. This safety is usually a precursor to good performance. Good safety almost always aligns with good performance. That underpins the plant's improved performance. We're seeing that through our confidence that, as we previously alluded to, we've been trialing a lot of the high-contamination, lower-grade material through the plant because the plant can take it, and it's performing very, very well. When we get to the section in the plant that Adam will present, you will see that for yourself. We've reinitiated the ore sorting, and we've also done some underground trials, which have given us very good results.
Tony Ottaviano
executiveWe keep making solid progress on the ramp-up. During our half-year results, we noted that commercial production had been declared at the processing plant. Underground production has now begun, right on schedule. Sales volumes are rising, and that is bringing operating costs down, giving us positive net operating cash flow. For 2 quarters running now, we have generated net cash flow from operating activities, and that has left us with a very strong, robust cash balance at quarter-end. And since we started up, we have turned out more than 200,000 tons of spodumene at a 5.2% grade — again, that is after 8 months of operation. Billy, let's go to the next slide, where we show our ESG performance. Our lost time injury frequency rate and our TRIFR are both up a little, for 2 reasons, mainly because total working hours have fallen off as part of construction demobilization. Once operations normalize, we will see that return to the zone we need it in. The other item I wanted to raise is renewable power. We reached over 80% penetration this quarter. That is very encouraging, since it holds our power cost at a very attractive level.
Tony Ottaviano
executiveIf you look to the right-hand side, there's a photo I'd like to point out. This is a joint company named NPH, led by a truly impressive young man in Troy. He's the second person from your left. I've been to this operation myself. All maintenance on every one of our light vehicles will be handled by NPH. Among the contracts given to an Aboriginal Corporation in the Goldfields, this ranks as one of the biggest. Billy, could we have the next slide, please. Just to emphasize, I want to point out a few key items. First, concentrate production. We lifted it another 12% versus the prior quarter. Once again, a really solid result. The second item I'd like to highlight is net cash from operating activities. What makes this even more satisfying for the team is that during this quarter we didn't have the advantage of capitalized commissioning costs, and a full quarter of royalties has been incurred. That's an especially strong result when measured against our competitors. The next thing I want to point out is lithium recovery. This matters a great deal — it's a clear rise, 10%. As we've noted in earlier disclosures, in this quarter, through the underground trials, we achieved recoveries above 70% and produced concentrate at over 1,700 ton a day.
Tony Ottaviano
executiveIt's really encouraging to think about what lies ahead once we're operating fully underground. We view the underground as a source of competitive advantage. Another thing worth noting about this lithium recovery is that it's achieved at an average mine grade, or lithium grade, feeding the plant of 1.3. The usual assumption is that a higher feed grade delivers better recovery. Our plant is performing in a way where we can feed it lower-grade material and still achieve very strong recoveries. The next two items I'd like to point out are cash on hand and, well, cash on hand first: there's AUD 173 million in the bank as of the end of March. Even better, we have 23,000 tons of concentrate sitting at the port ready to go onto a ship. Lastly, operating costs. What I want to highlight here is that this operating cost figure is calculated on a 6% basis. I'd ask the analysts to normalize competitors' costs to a 6% standard and then compare us. Measured in US dollars, it comes to AUD 512 a ton FOB. In Australian dollar terms, that's 18% lower than the prior quarter. If we run it on a 5.2% basis for comparison purposes, it's AUD 708 a ton.
Tony Ottaviano
executiveMoving to the following slide, I'll now pass the production portion of this quarter's report over to Adam Smits, our Chief Operating Officer.
Adam Smits
executiveThanks, Tony. I'd say it was another solid quarter for the open pit, with slightly less than 2.5 million tons of ore mined — or ore plus waste — coming out of the pit. Within that, roughly 550,000 was ore, at a stripping ratio a bit above 3. Grade control drilling wrapped up during the quarter. That matters a great deal for locking in the wire frames and for the continuing extraction of what's left of the pit. The pit remains on track for completion around January or February of next year. I'll go into more detail on that later regarding the move from open pit to underground. At this point we have more than 1 million tons — 1.3 million tons of ore, that is ore and OSP material — sitting on the ROM pad. That breaks down into approximately 800,000 tons of OSP and a little over 400,000 of clean ore. I think the picture at the bottom of the page captures it. You're able to see the different fingers of ore across the ROM pad. There's also a big stockpile of additional ore to the right in that picture. We'll move on to the next slide.
Tony Ottaviano
executiveLet me just tack on a couple of extra points here.
Adam Smits
executiveMy apologies.
Tony Ottaviano
executiveThat's fine. I believe the analysts and investors who have registered their interest on our site will be visiting in June, and they'll see for themselves how well organized this ROM Pad is. The aerial photograph shows it. Another thing I want to emphasize — and again, we've made considerable effort to explain this — is the strategic stockpile: 1.3 million tons and an investment of AUD 103 million. Regarding the operating cost, since many accounting adjustments arise through inventory and non-cash items, this is an investment in which the capital and the cash have already been sunk. Going forward, we can draw from this stockpile, and that will then wash through our operating costs, because that's how the accounting treatment works. It does not affect our cash balance. It's an investment we've already sunk.
Adam Smits
executiveThanks, Tony. On the underground side, we had another solid quarter — 1,850 meters of development, 53,000 tons of clean ore, and slightly more than 100,000 tons of waste. That clean ore came from development, with stoping beginning in the April quarter. Jumbo productivity was again strong, at a bit over 300 meters per jumbo. We anticipate that will drop back somewhat this quarter, now that stoping is underway and there's considerably more interaction happening underground. Key infrastructure projects — the heart and soul of an underground mine — moved forward over the month, over the quarter, with the accessway raised bores finished and the underground re-tech finished. The underground paste plant is set to be fully commissioned in May. On top of that, we operated that plant. Around 60% of the plant ran throughout the quarter, generating dry stack tailings material, which went into our tailings dam upgrades. It's really, really encouraging that this section of the plant is fully staffed, fully manned, and fully operational. Raise boring work carried on through the quarter for ventilation. The first raised bore should be complete in the first week of May. We expect the first fan to go in during the June quarter.
Tony Ottaviano
executiveThere are just a couple more things I'd like to mention in addition to that excellent recap, and the first is this photograph of the pegmatite drive. I mean, looking at this image, it is 100% ore. This is not narrow vein gold mining. That whole drive consists of ore that we'll capture as part of our stoping sequence. The second thing we point out is that when slides like this are presented, people show the absolute result. But how does it compare with our plan? In this quarter, we are ahead of plan — 160 meters ahead of plan. The team on site are doing a very good job managing the preparation and what we need to remain ahead of in order to deliver the production.
Adam Smits
executiveMoving to the next slide, Billy. Regarding how the plant performed, the strongest way to capture it is probably through the high availability we achieved, which came in at 91% during the quarter, along with steady gains in recovery. We moved up from 58% during the December quarter to 64% during the March quarter. That came with 600,000 tons — or just under that — of ore processed over the quarter. March gave us our best production month on record. Recovery during March came in at 68% on average, and there were days in March — likely three or four — where the average exceeded 70%. That includes the underground ore trials, the OSP ore trials, and ore blends. I'll go into a bit more detail on that during the slides ahead. As for where we stand going forward, several key initiatives are currently in progress. One involves examining the regrinding of a portion of our tile stream and the measurable recovery that comes with it. We anticipate having that installed and operating in July. A great deal of effort has gone into advancing that during the quarter. There are also comminution and classification upgrades that we're carrying through, including the first particle size distribution system of its kind online. We'll actually have cameras inside pipes measuring particle sizes.
Adam Smits
executiveThere's a brand-new lining system on the way for the SAG mill. The lead time on that is 26 weeks. It's already been designed and built. We're installing a proprietary control system in the mill, and it's all aimed at, if you like, better control of the grind. Flotation circuit improvements are also underway, targeting coarse and fine recovery. You can see there's a genuine focus here — yes, we're doing fine on recovery, but there's a drive to reach that 70%. What's really encouraging, and Tony mentioned this a bit earlier, is that when we feed it that roughly 1.5 underground dirt, my God, we get some incredible recoveries. We hit 70% plus with no optimization at all. There's plenty of upside there once you pair it with the other initiatives we're pursuing.
Tony Ottaviano
executiveThe one additional thing I'd mention beyond that summary is that with the improvements we've now identified — these optimization initiatives — we have a pathway to 70. What these initiatives do is reinforce that pathway to 70, making it sustainable and strong, but also go beyond, well beyond 70.
Adam Smits
executiveAll right. Moving to the next slide. Thank you, Billy. Regarding the underground transition, the major priority there, as Tony mentioned earlier during the presentation, involves building that stockpile of 1.3 million tons of ore. That stockpile is what underpins the 15-month ramp-up of the underground operation. Establishing that stockpile and configuring it so the material can be reclaimed has been a genuine focus for us, giving the underground the opportunity to ramp up toward the run rate contained in our plans. Key activities during the March quarter, which I have already touched on, included treatment of OSP. For those in the AUD ience, OSP is essentially diluted or contaminated ore with contamination ranging from 5 to 30%. The contaminant is the host rock, known as gabbro. It is rich in iron, calcium, and various other elements that affect recovery. We put substantial focus on trials examining how to process that OSP material, along with blends of it, so that recovery is maximized while grades stay above 5%. We also ran some trials in March using straight underground ore. As I mentioned, we achieved a massive step-up in recovery with very little optimization. On the first day of those trials we jumped to 70%, which is very, very encouraging.
Adam Smits
executiveA few problems came to light, and we already have projects in motion to fix them—chiefly concerning steel. We also put substantial effort into combining OSP with clean ore. Because of that, we have restarted sorting, as Tony mentioned. Over the coming 15 months, our blend will consist of a mix of underground ore as it emerges from the underground, sorted material, and straight OSP blended in. We have a very clear plan for what we are doing with that 1.3 million tons.
Tony Ottaviano
executiveI'd like to stress this point again. During the prior quarter, we mentioned that we're trying out a range of blending approaches at this plant. What we're seeing is that the plant holds up well. Compared with what others are encountering, we're able to feed the plant greater percentages of this gabbro. That's a genuine competitive edge. We intend to push it as far as we possibly can. So this OSP material — typically, at open pit mines, 30% of what they mine falls into the OSP category — we're able to blend it through our plants together with some material that has been ore-sorted, and the plant can handle it, which is a tremendous benefit.
Adam Smits
executiveYeah. Early trials are showing that we can handle this material at a rate at least double what the plant was built to do. And there’s still room to push that further.
Tony Ottaviano
executiveSo with this product and by raising the gabbro share in the blend, we hope our recovery trajectory keeps climbing. Depending on how that plays out and how the plant runs, it could taper off somewhat.
Adam Smits
executiveAll right, let's move to the next slide. On the sales side, I believe we had 93,000, with five shipments at 5.2 shipped during the quarter, and the largest of those was 36,000 tons shipped in January, based on 96,000 tons produced at 5.1. We also sold tantalite — 221 dry metric tons at roughly 5% grade, priced at Argus spot levels. Tantalite is likely among the larger additional optimization opportunities for us at the plant. There's significant attention here, and a project focused on enhancing tantalum recovery has just gotten underway, period.
Operator
operatorAll right, thanks, Adam. At this point we’ll pass things over to Jon Latto, and he will walk everyone through the operational side and, well, mostly the financial metrics.
Jon Latto
executiveAll right. Thanks, Billy. Let's move on to the following page, if everyone's ready. Okay. At the top of page 13, you'll find a summary covering several of the key metrics. As Tony mentioned, during the March quarter production rose 12% to 95,709 dry metric tons, while sales climbed 15% to 93,940 DMT. Grade shift held steady versus the prior quarter at 5.2%. On an SC6E basis, the average realized price we achieved edged up slightly, going from AUD 806 per ton sold in the December 2024 quarter to AUD 815 per ton sold in the March 2025 quarter. Turning now to a few key financial metrics, quarterly revenue came in at AUD 104 million, up 17% from the AUD 89 million in revenue reported for the previous quarter. Our cash balance stayed strong, sitting at AUD 173 million at the end of March. On an overall basis, our cash balance fell AUD 20 million, roughly 10% quarter on quarter, and most of that decline came from expenditure on underground activities, since we don't yet have the benefit of the material underground production, which will arrive in future periods. As for our cost metrics, we have unit operating costs in AUD terms.
Jon Latto
executiveThey brought it down 18%, from AUD 1,000 per DMT of SC6E sold in the December 2024 quarter to AUD 816 per DMT sold in the March 2025 quarter. AISC fell 8% in AUD terms, from AUD 1,170 per DMT SC6E in the December 2024 quarter to AUD 1,081 per DMT SC6E in the March 2025 quarter. You'll notice that the 18% quarter-on-quarter drop in unit operating costs was larger than the 8% quarter-on-quarter reduction in AISC. That gap comes down to sustaining capital. It happened because we pulled a TSF raise forward, moving it from FY 2026 into FY 2025. The reason was some changes to the underground schedule, which shifted when paste fill was needed, and that meant more material ended up reporting to tailings.
Tony Ottaviano
executiveSo that came out of the strategy review we did in November, and it's part of the plan for stopping.
Jon Latto
executiveThat's right. The main driver behind the drop in our unit operating cost metric and the AISC metric for the March 2025 quarter was a 15% rise in ton sold in the March quarter — ton sold went from 81,341 DMT in the December 2024 quarter up to 93,940 DMT in the March 2025 quarter. On top of that, gross mining costs came in 7% lower in the December quarter, since we moved 8% less material from the open pit, which was driven by a scheduled reduction in our open pit mining fleet under the new mining plan we told the market about back in November 2024. As we've noted in the presentation and the ASX announcement put out today, we expect to trend toward the upper end of our cost guidance. With an AISC of AUD 1,081 per DMT SC6E sold for the March quarter, we're actually below our guidance range right now, which sits between AUD 1,170 per ton of SC6E and AUD 1,290 per ton of SC6E sold. A couple of factors will push us higher in Q4. These include the introduction of ore sorting in April 2025, which Tony has spoken to. Also, in Q4, we will draw down on our stockpiles as we ramp up our underground activities.
Jon Latto
executiveWe anticipate a charge rather than a credit to our AISC, along with the unit operating costs we have recorded so far. In addition, our sustaining capital projects show an underspend for the year to date in our forecast. For Q4, we have forecast a catch-up on that underspend. There is also a capitalized deferred waste charge for Q4, since the strip ratio in the open pit rises during the quarter as we mine down toward our next ore zone. Billy, if I could turn the question over to you.
Tony Ottaviano
executiveWe've just wrapped up those business optimization initiatives — sorry. As we mentioned to the market back in November, we had identified roughly AUD 100 million. We're on track to deliver them. AUD 60 million is already realized. That's the first point. The second point I'd like to add, just to further reinforce the guidance: now, we've introduced ore sorting. The plant is performing that well. I can't reassure the market more about its performance. Therefore, we want to throw in some of that OSP material while we can. That has an accounting impact where we've got to — while we draw from the stockpile, there's a charge on the operating costs. That's why we've given the market that guidance.
Jon Latto
executiveThanks, Tony. Billy, could you flip over to the following page, please, so we can spend a moment on the Cashflow Waterfall shown there. That waterfall presents, in chart form, the identical data contained in the Appendix 5B Cashflow Statement we released today. It is a fairly simple waterfall. I won't go through every component, but I will offer these remarks. First, we produced positive cash flow from operating activities of AUD 14 million for the quarter, as Tony noted. I'd like to give that a little context. We said previously that we had declared commercial production at the Kathleen Valley Processing Plant effective 1 January 2025. Consequently, this marks the first quarter since production began in which none of our operating costs tied to ramping up the processing plant have been capitalized. Every operating cost now flows through to cash flow from operating activities. On top of that, this is the first quarter in which we have paid royalties. That cash flow likewise appears within our operating costs for the quarter. For context on the royalty outflow, our first sale took place in September 2024.
Jon Latto
executiveWe got the proceeds from that sale in October 2024, plus additional sales receipts that came in during the December quarter. The royalty obligation becomes crystallized at the point revenue is received. Royalties tied to the December quarter get paid in January 2025. In this current quarter, we also include roughly AUD 6 million of cash outflow related to royalty payments within our payments for operating activities. With all of that factored in, we reported positive cash flow from operating activities of AUD 14 million for the quarter, which is a strong result. The one other piece of the waterfall I'll mention is cash flow through investing activities, which showed an outflow of AUD 27 million for the quarter. Most of that was development expenditure tied to the underground. The waterfall chart shows we ended the quarter with a strong cash balance of AUD 173 million. A few comments to add here. We also had a shipment go out on March 31, 2025 worth approximately AUD 12 million, and we received those funds in April. We also had roughly 23,000 tons of concentrate on hand at quarter end. We also hold AUD 25 million on deposit with Export Finance Australia in connection with a guarantee required under our power purchase agreement with Zenith.
Jon Latto
executiveThis has been backed by cash for a good while now. We keep working with the various parties involved to get those funds returned to us and swapped out for alternative security. That AUD 25 million is not included in the AUD 173 million of closing cash on hand we reported for 31 March 2025. With that said, I'll hand it back to Tony.
Tony Ottaviano
executiveThanks, Jon. Thorough as always. Now, if we go to the following slide, Billy, let's discuss the market. All right. I'd like to devote a bit of time to this. I believe you've observed, from the different other lithium producers that have reported their quarterly results, that we all agree — and the various forecasters have observed this too — that demand signals are strong. They're going to stay strong. Some segments of the battery market are performing better than others. Stationary batteries are among them. When we look at recent results from BYD and CATL, profit margins are strong for the end users of our product. If you consider the views of the world, Wood Mackenzie versus CATL — and we got this from their recent prospectus, where they listed on the Hong Kong Exchange — their view as a battery producer is far, far stronger than the forecasters'. They see an 83% increase in EV demand over the next five years. They see an even stronger increase in stationary batteries. What's happening here? Why aren't we seeing a corresponding rise in raw material prices? The fundamental reason, as we see it here at Liontown, is the length of the battery value chain.
Tony Ottaviano
executiveInventory is spread all along the value chain, and that inventory acts as a buffer. When demand rises, when a demand signal comes in, working through the inventory held within the battery value chain takes time. There's inventory sitting with the car manufacturers. There's inventory with the battery producers. There's inventory at the PECAM and so on, at the refineries. Until that gets worked through, we won't see a direct impact on price. The encouraging side is that the demand signal is strong. Now, regarding supply, I can tell you that at today's prices, there is no incentive signal whatsoever. It will discourage, and it has discouraged, exploration, brownfield expansions, and new projects. We know from having done this ourselves that bringing new greenfield capacity online takes years, even if they began today. At some point this will correct, and correct sharply, because you cannot keep raw material supply suppressed the way it is currently being done for as long as they anticipate without a material impact. We're seeing that now. We know a number of players throughout the battery value chain — the refiners, the PECAM producers — they aren't making money. We feel encouraged about the short to medium term when it comes to demand signals.
Tony Ottaviano
executiveA turnaround looks likely to us, since at such price levels no fresh supply is going to appear. That concludes our presentation. Thanks to all of you. We'll now take your questions.
Operator
operatorThanks, Tony. If you haven't sent in your written questions yet or gotten into the live audio queue, please do that at this point. I'll give each caller's name and then ask you to proceed. After that, a beep will sound to let you know your mic is live. Jon Bishop from Jarden Group Australia has our first question. John, once the beep sounds, please go ahead.
John Fisher
analystMorning, everyone, and many thanks for taking my questions. First off, congratulations on yet another impressive ramp-up. From a technical standpoint, the operation's performance is really commendable, and it's clearly showing through in the results. So, well done—well done to the team on that front. Obviously, lithium prices right now aren't doing you any favors. I suppose my first question concerns the guidance. You've said that at the top end of the cost range for the fiscal year, or for the June half, it came to roughly AUD 825 US per ton on an SC6 equivalent basis at current exchange rates. Fast markets, of course, are now printing with a seven handle. Your all-in sustaining cost is clearly affected somewhat by stockpile movements and accounting treatments. It also doesn't fully factor in the underground or the freight element. That was a very long-winded question. What additional elements are you looking to manage that cost and, I guess, ensure you can maintain operating free cash flow?
Tony Ottaviano
executiveThanks, Bish. I'll pick it up from there and invite the team to add anything. Your question has a couple of aspects to address. First, I'd like to get ahead of the underground cost concern. Three months of underground production is already included in our guidance. That's the first thing. Some level of underground production costs is incorporated in that. My second point is that right now we're carrying both open pit costs and underground costs at the same time. When this year wraps up — when this calendar year ends — the operating costs tied to the open pit will go away. I'm not certain the market has factored that in, that after this calendar year concludes we'll be mining solely underground. As for where we sit on cost structures, we think that, now that we're building an operating database and operating know-how, we'll keep searching for efficiencies and productivity gains. A number of initiatives are underway, or will be underway, in the new financial year to capture those operational benefits. We did a first pass in November when we released our strategic review. This is an ongoing exercise. We believe we have more room to move.
Tony Ottaviano
executiveTake reagents as one example. Between 20% and 25% of what we spend on processing goes to reagents. We're testing quite a few alternatives right now aimed at bringing those costs down. Then there's smarter purchasing, which we'll pursue, since many of our contracts got signed when the market was at its peak. Today there's a chance to renegotiate a great deal on consumables and input costs. Those are just a couple of illustrations, Bish, of additional operational gains and efficiencies we can capture. Okay?
Jon Bishop
analystOkay, may I just tack something on regarding the all-in cost? I realize guidance for fiscal 2026 is still pending, and I appreciate that it's a work in progress. Could you offer us some direction or an update on what you expect the capital figure to be through fiscal 2026 to establish a steady-state underground operation?
Tony Ottaviano
executiveFor an underground mine, the biggest expense is the development you have to fund up front. That CapEx is being spent right now, correct, so that by the time we begin operating, the headings and drives are already open. A substantial portion of that investment, Bish, is underway already. While next year — we've already referenced the market — is a transition year, and operating costs will trend higher. On the CapEx side for our development, we expect it to be sustained. Possibly later on, it comes down once we reach that higher margin zone within the ore body, which is thicker, and so the development work is already being carried out.
Operator
operatorThe next person in the queue to ask a question is Kate McCutcheon of Citibank. Kate, the floor is yours.
Kate McCutcheon
analystHello there. Good morning, Tony and everyone. Regarding the processing physicals, I just want to clarify the way they've been restated. Before, the December quarter showed 620,000 tons milled. It's now 555, so that's a 10% reduction in tons. What's behind such a large reconciliation gap? Has it been settled?
Tony Ottaviano
executiveYeah, a few things to address there. Yes, that matter has been settled. What we usually do as part of standard practice is regular reconciliation work and mass balance checks throughout the operation, from the ship through to the ROM Pad. During that complete reconciliation — after we declared commercial production on the 1st of January alongside our half-year results — we carried out the flyovers and surveys, and we checked the balances. We identified that certain pieces of instrumentation in the plant, specifically weightometers and conveyors, were overstating our production figures. That has now been rectified. Sold tons are unaffected — those figures stand as reported. We have disclosed it. Regarding mill feed, given the weightometer discrepancies, and on the concentrate conveyor feeding into the shed, there were some anomalies with the weightometers. We have made the necessary correction for that.
Kate McCutcheon
analystAll right, understood. It's fixed at this point. I was just considering where cash stands as we approach the close of the financial year, and you've pointed out that building those stockpiles cost AUD 103 million as such. When that material gets fed, there's an adjustment to cash. Could you shed some light on what portion of the stockpiles you anticipate feeding across the coming three, six, and nine months, or how that profile shapes up, so we can model that P&L versus cash adjustment correctly?
Tony Ottaviano
executiveYes, absolutely, Kate. We anticipate a fairly substantial reduction in inventories over the June quarter — roughly 500,000 tons, in that ballpark. Generally speaking, we expect that to level off, or rather, that brings you through to FY2025. A more modest reduction occurs as we head into FY2026. By more modest, I mean around 100,000 tons, give or take. That applies to the first half of FY2026. We keep reducing the stockpile throughout FY2026, but we still hold a.
Jon Latto
executiveA reasonable cushion.
Tony Ottaviano
executiveAt the end of June 2026, we had a reasonably healthy stockpile balance.
Jon Latto
executiveAll of that is going to be included when we provide our guidance.
Tony Ottaviano
executiveThat's right.
Operator
operatorThanks. We’ll take the next question from Adam Baker at Macquarie. Adam, the floor is yours.
Adam Baker
analystGood morning, Tony, John, and Adam. Regarding that Capitol Inn corner, things have worked out really nicely for you folks. It's good to hear it will continue through February of next year. I was just wondering, please, how many tons remain to be extracted from the pit — or tons?
Tony Ottaviano
executiveI'm trying to recall that, Adam, but I'll need to get back to you on it.
Adam Baker
analystSure, that's fine. I can follow up once we're done here. Just on sustaining CapEx, though — the guidance for the second half of FY2025 sits between AUD 55 million and AUD 63 million. I was just curious how much of that landed in 3Q. You've got the AUD 6 million in royalties, but for sustaining CapEx as its own line item, would roughly AUD 19 million be about right?
Tony Ottaviano
executiveRegarding quarter three, that would be the quarter ending March 25?
Jon Latto
executiveAbsolutely.
Tony Ottaviano
executiveAdam, that's not right — the figure is actually below what you said.
Adam Baker
analystThere's some catching up to do in the 40.
Tony Ottaviano
executiveYes. John touched on that. That’s right — we do. There’s certainly something there. We’ve had a kind of understanding regarding our CapEx. We’ve projected a catch-up, though we’ll have to see how much of it ultimately materializes.
Adam Baker
analystAll right, thanks.
Operator
operatorHayden Bairstow of Argonaut is up next with a question. Hayden, the floor is yours.
Hayden Bairstow
analystMorning, guys. Tony here — got a question about the underground. The reserve grade is lower than what you mentioned for the development grade you've already delivered, and you've only just begun stoping. Can you give us any guidance on the early grade profile underground as we move through this ramp-up phase? Or is it possible to focus on the higher-grade areas?
Tony Ottaviano
executiveOn the initial grades, I believe we're looking at 1.4 to 1.6, within that band. A portion of it falls in the upper zone.
Hayden Bairstow
analystWhat's the maximum period you could keep that going?
Tony Ottaviano
executiveI believe that covers essentially the whole of FY26, and the underground ore is comparable. Yes.
Hayden Bairstow
analystYeah. Okay. So turning to the conversation about the CapEx catch-up, I mean, what exactly are we spending on during the fourth quarter that you hadn't been, that got pushed out and is material? Or, as you kind of hinted at, is it more likely that on CapEx guidance, if anything, you'll come in under it, and there'll be a bit more in 2026?
Tony Ottaviano
executiveSo there are essentially two parts to that, Hayden. One is the sustaining CapEx at the plant, which is what we've historically seen and understood up to now. We've pulled some of that forward. The other part is, as we said, we're moving out of the ore zone. Our strip ratio goes up. We also have some capitalized deferred waste for Q4.
Operator
operatorThanks. We’ll take our next question from Glyn Lawcock at Barrenjoey. Glyn, the floor is yours.
Glyn Lawcock
analystGood morning, Tony, and to the team. First off, would you be able to share any thoughts on how things went with the blast in your first stope? Obviously, there's been a great deal of concern about how it might turn out, and whether it would fracture. You've spoken with us, of course, about that thin layer on the outside, which should bring some advantages. So how did it actually go, physically speaking?
Tony Ottaviano
executiveThat is a really great question, Glyn. Adam and I were both out at the site over the weekend — last weekend — so we could take a look at the first stope and the blast. We came away extremely pleased. The breaks were clean, precisely as we had anticipated. The team still has some additional fine-tuning and optimization to do. On fragmentation — I will let Adam comment on that — but it was almost, well, I think the word we're using is sugar. Sugar. Truly, truly, truly excellent fragmentation. Very clean breaks. They are considering changing some of the underground drilling approach when it comes to overdrill. They are reviewing how much of a skin they leave. Recovery from that stope was certainly excellent. There are plenty of lessons coming out of that stope. That first stope came in at roughly 12,000 tons. For context, it is a relatively small one compared with what lies ahead. Yes, very, very encouraging. Another thing we would highlight is, once again, this shows the difference between narrow-vein gold mining and what we are doing. That single stope, those 12,000 tons, amounts to two days of production from just one stope. That is a baby stope. We have stopes lined up in the coming financial year that come close to 80,000 tons.
Tony Ottaviano
executiveThere's a real chance here for this mine to achieve genuine economies of scale. We'll be putting together a short segment on that as part of the presentation we have coming up after the Macquarie conference, heading into Diggers.
Glyn Lawcock
analystAll right, thank you, Tony. Let me just add a quick follow-up here. When I examine the cash flow statement covering this quarter, roughly AUD 94 million was outlaid, not counting what went to CapEx. Some of that, clearly, reflects a modest amount of sustaining spend. Now, if I take that 94 million and divide it by your SC6 volume, the figure I come out with is nearer AUD 1,200 per ton rather than AUD 1,100. Does that stem from capitalizing certain costs that aren't flowing through? And on a genuine cash basis, would it in fact be higher than the number you're reporting?
Tony Ottaviano
executiveGlyn, maybe I'll ring you afterward — that one's hard to handle off the cuff. What I can say for sure is that we compute our AISC properly. And if certain gaps show up versus cash flow, well, that's plainly the gap between cash and accrual accounting.
Jon Latto
executiveIt gets affected when stocks are drawn down or when stockpiles are built up.
Tony Ottaviano
executiveYes, inventory does play a part here. Glyn, I wouldn't treat your skid calculations as a reliable indicator.
Operator
operatorThanks. We move now to Levi Spry of UBS. Levi, the floor is yours.
Levi Spry
analystYeah. Hello, everyone. Appreciate you making time. So as we look ahead to the FY26 guidance, could you walk us through a few of the factors on your mind? Recoveries clearly are moving in a good direction, though they sit at 5.2%. Is that where we begin?
Tony Ottaviano
executiveRight. Levi, I think where things stand is, as you remember, we’ve been examining what concentrate grade would be best for us to aim at going forward on a continuing basis. And the range of 5.2 to 5.3 is consistent with what our competitors do. Now, as for other matters.
Levi Spry
analystAll right, thanks.
Tony Ottaviano
executiveRegarding the other items we're signaling for FY26, we keep exploring methods to make the underground ramp-up happen with greater efficiency and effectiveness. That's a continuous enhancement effort. On the plant side, I've already mentioned several areas of the plant where we're seeking improvements. There are superior reagents, reagents that are more cost-effective. Every one of those will be incorporated as part of FY26. Once again, I want to emphasize that this is a transition year.
Levi Spry
analystYes. All right, thanks. A few of the earlier questions, I think, have been kind of skirting around the cash flow waterfall. We're trying to figure out how that might shape up this quarter and then, obviously, next year. Could you just walk me through what the waterfall for cash flow from investing activities looks like there? Underground development, sustaining project — what that might look like this quarter. I guess the lease items, we're assuming those repeat. What about the other items, like interest and that sort of thing?
Adam Smits
executiveMaybe let me pull back for a second, Levi. I think what you're really asking about is our cash position, if I'm reading that right. We've adopted a fairly cautious stance given where pricing sits today and what our internal models show. We've built in an assumption that spot stays where it is for a good while. Even with those assumptions baked in, our models indicate we still make it to 30 June. We'll still be sitting on a healthy cash balance, and beyond that as we move into FY2026. Of course, should today's pricing persist for years, then we — like every other lithium producer — would need to revisit things. As things stand right now, we've assumed current spot pricing carries on for an extended stretch, and we're still comfortable. Yeah.
Tony Ottaviano
executiveThere's another thing I want to mention about the coming quarter when it comes to sustaining capital. Regarding that AUD 27 million of cash burn in this category, John has already referred to the possibility that we've pulled forward some sustaining capital, and that some catch-up work remains. There could be slightly more in that area, though it won't be material.
Operator
operatorThanks. We move to Milan Tomic at JP Morgan for the following question. The line is yours.
Milan Tomic
analystYeah. Hi, team. Thanks for joining. I just have one question regarding the interest payments. I noticed that the figure is only AUD 1.2 million for the quarter. Your debt sits at roughly AUD 800 million. That implies a very low interest rate. Could you give us a bit more clarity on what those interest payments will look like going forward? Should we account for a catch-up payment at some future date, or not?
Tony Ottaviano
executiveYeah, absolutely. Appreciate the question. Look, right now every one of our interest payments gets capitalized. As a result, we aren't seeing any cash outflow tied to interest payments — whether that's under the Ford debt or the LG debt. When it comes to cash interest payments down the road, essentially, interest payments under the Ford debt facility will start once the off-take starts. So that's basically, I think, where things stand.
Adam Smits
executiveSeptember.
Tony Ottaviano
executiveThat lands in September, within the quarter ending September 25. As for interest payments over FY26, those are fairly small. Regarding cash interest payments, we'd expect roughly AUD 4 million per quarter, around that level. That 1 million — isn't that an inflow? It comes from interest on. The million dollars? Yes. It would be an inflow. It's a net inflow, right? Yes. On our accounts. Yes. Interest earned on our cash balance. Yes.
Milan Tomic
analystMuch appreciated. That's all from me.
Tony Ottaviano
executiveThat’s not a problem at all.
Operator
operatorThe next person in the queue is Anthony Barich with Platts. Anthony, the floor is yours.
Anthony Barich
analystYeah, on Anthony Albanese and the critical mineral strategic reserve — I'm just wondering if you believe lithium ought to be part of it, since they haven't yet announced any details about that. And do you think the idea is generally a good one, and whether it might encourage investment the way AMEC has? What's your view?
Tony Ottaviano
executiveYeah. Thanks for that question. Look, you can understand we've been concentrating on our quarter and getting it out there. They made their announcement today. We haven't gotten into the specifics of what the Prime Minister has laid out and revealed to Australians. Just allow us a bit of time to go through it, and after that we'll take a stance.
Anthony Barich
analystThat's fine. On the operational side, in terms of what's affecting your operations—I think Dale at PLS mentioned the other day that uncertainty tied to tariffs might have an impact on financing and the development of new lithium projects. I'm just wondering if you think that could also be the case here. And if so, could you give us a bit more detail on that?
Tony Ottaviano
executiveSetting tariffs aside for a moment — the price on its own, especially since you all reported it, is a strong enough deterrent when it comes to projects down the road. My view is that this deserves our attention before anything else.
Operator
operatorThanks. We have a written question now from Brad Johnson, who is a private shareholder.
Brad Johnson
analystHow do you see lithium demand shaping up over the coming 12 months?
Tony Ottaviano
executiveHi Brad, thanks for being a shareholder and for your support. From our standpoint — and we already touched on this in my market slide — demand looks extremely strong over the coming 12 months and really over the next decade as well. That isn't only our own read. We have an internal view, but consider what the market shows: the largest battery manufacturer globally is projecting very robust battery demand across the next 5 to 10 years. Even if CATL's projection were cut in half, that still represents an enormous growth trajectory. As I mentioned, it will take time before that ultimately works its way through a very lengthy supply chain to reach the raw materials, because of how much inventory sits at every stage along that chain. That has to clear through first before any effect shows up in raw material prices.
Operator
operatorThank you. Moving on, we have a written question from Anthony Barrage at Platts. The CEO of PLS remarked that uncertainty surrounding tariffs could pose headwinds for financing and development of new lithium supply. Would you concur?
Tony Ottaviano
executiveBilly, I believe Mr. Platts has already spoken on that, so I think that question has been addressed.
Operator
operatorMoving on to an audio question from Jon Bishop. John, go right ahead. Thanks for taking my follow-up. I have a couple of questions here, probably embedded. You were quoted recently in the press out in Western Australia regarding accessing the WA State Government lithium support package. Could you comment on where that stands?
Tony Ottaviano
executiveAbsolutely.
Operator
operatorSorry about that — we’re running into a few technical problems. Tony, are you able to hear me?
Tony Ottaviano
executiveYes, Billy, we can do that, though I didn’t catch the other question from Bish.
Operator
operatorThat's perfectly fine. John, would you mind repeating your question for us? Okay. Am I coming through clearly?
Tony Ottaviano
executiveYeah. Coming through loud and clear, Bish. That signal at Rhodo is not. I wish it were. It's not a great day over here either. Not a good day for Rhodo. Look, you were quoted in the press recently being flagged as potentially accessing the WA State Government critical minerals or lithium support package. Are you able to comment on where that process is at, please? Yes, I am. We've had a really positive engagement with the government on this, and we're working towards concluding those discussions, and we'll make an announcement on that in due course. Okay. Can I just have a quick follow-up to that? Just regarding your Ford payments, which start next fiscal year, are you also having discussions with Ford around potentially deferring the principal repayments? Look, I'm probably not at liberty to announce very confidential discussions, but we're in constant dialogue with all our customers around a whole range of things. Ford is not unique, but we are talking to all our customers about the current situation.
Operator
operatorThank you. That’s all the time we have for questions today. I’ll now hand things back to Tony, who will offer a few closing comments.
Tony Ottaviano
executiveThanks, Billy. And thanks to everyone who joined and asked those excellent questions. For anybody who reaches out afterward, we'll handle that. Leanne Koz will get back to you with those answers. So, to recap, I believe we're putting in maximum effort to bring the plant up to full rate and reach a steady state. That's now behind us. Our attention is shifting to the underground. Our goal is to make the underground a success. We genuinely believe that over the longer term, the underground will deliver a competitive edge for us, particularly when it comes to ore hygiene and fragmentation. The grades we're encountering underground, as Adam has already noted, run very well through the plant. I want to push all of this OSP material — all of this low-grade, high-contamination material — through the plant, since it can handle it, and then transition ourselves to 100% underground material and really let this plant fly. Thanks to all of you for listening, and we'll wrap up here.
Operator
operatorIf any follow-up questions come up, please get in touch with the Liontown team. You're welcome to log out at this point.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Liontown Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Liontown Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Liontown Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.