Liontown Limited (LTR) Earnings Call Transcript & Summary

April 30, 2026

Australian Securities Exchange AU Materials Metals and Mining earnings 40 min

Earnings Call Speaker Segments

Operator

operator
#1

Good morning, and thanks for joining the Liontown March quarterly call. After the formal presentation, we'll hold a Q&A session for investors and analysts. During today's call, participants can submit questions either in text form or as live audio. If you'd like to ask a text question, click the messaging icon, enter your question into the box near the top of the screen, and hit the send button. For a live audio question, click the request to speak button at the top of the broadcast window. The broadcast view will then be replaced by the audio questions screen. Please use the dial-in number and access PIN you were given to ask your question over the phone. Alternatively, if you're on a home or personal network, you can submit questions online by pressing join queue. Should a prompt appear, choose allow in the pop-up screen so your microphone access is granted. If you run into any trouble with the platform, dial-in details are also available on the homepage under asking audio questions. Text questions can be sent at any time, and the audio queue is now open. I'll now hand things over to Tony Ottaviano, Managing Director and Chief Executive Officer of Liontown.

Tony Ottaviano

executive
#2

Thank you, Luka, and good morning to all of you. Before I get into the presentation, I want to introduce the others who will be joining me for it. With us are Ryan Hair, our Chief Operating Officer; Greg Jason, our CFO; and Grant Donald, our Chief Commercial Officer. Let me begin by saying that this quarter has been a defining one for Liontown. Luka, could we move to the next slide, please? There are five key points I'd like you to take away from today, and they match what's shown on this slide. First, cash on hand increased by $33 million during the quarter, finishing at $424 million. Operating cash flow by itself came to $55 million, and Greg will walk through that on a later slide. For the first time since we began production, operating cash flow covered the business in full. Once capital investment in the asset and net financing flows are taken into account, we will still finish the quarter well ahead. This is the strongest financial quarter we've had since production commenced. It's also worth noting that the Port of Geraldton was shut for several days at the end of the quarter because of the cyclone threat from Cyclone Narelle. That delayed two of our shipments. One of them slipped into April, and the other departed on the last day of March.

Tony Ottaviano

executive
#3

Cash receipts tied to that shipment on 31st of March came to roughly $64 million. The business's underlying capacity to generate cash this quarter was actually even stronger than the $33 million we reported. Second, market conditions are strong, and our realized pricing reflects that. On an SC6 equivalent basis, our average realized price for the quarter came in at $1,845 per dry metric ton, which is up 87% quarter-on-quarter. The structural setup in the lithium market is compelling, and we're now capturing this through our contracted sales. Again, Grant will go through the market in some detail in his section. We are delivering on plan. We achieved our 1.5 million ton per annum underground run rate target early in the quarter, ahead of schedule. The ramp-up is tracking to plan. The orebody is performing as modeled, and the grade reconciliation against the resource model remains strong. Again, Ryan will go through this in some detail in his section. Fourthly, costs remain on track. Unit operating costs for the quarter were $981 per ton, and were within our FY26 guidance range. We're continuing to manage the ramp-up, the transition through a variable feed mix, and the fuel crisis by ensuring our business optimization focus remains strong and disciplined.

Tony Ottaviano

executive
#4

To wrap up, the route to 70% recovery has now been locked in. On clean ore and underground ore, we've shown 70% recovery, exactly as planned and as we told the market. That has held steady over three — the first three weeks of April. The plant is doing what it was designed to do and what we expected. Let me now take you into a bit more detail on the next slide, please. This slide shows you the quarter at a glance. As the subtitle puts it, we're delivering across the board while the underground ramp-up keeps going. Let me go through each of the tiles. Production came in at 96,000 tons. As we pointed out in our half-year results, Q3 had fewer calendar days, and we ran a planned plant shutdown in that window. Production is on track. Sales were 84,000 tons across five parcels. We ended the quarter with a significant inventory position in port — roughly 26,000 tons of salable concentrate. As I said earlier, that inventory build reflects the Cyclone Narelle impact at Geraldton. It comes down to timing, not the market. On pricing, I've already covered the $1,845 a ton. On costs, unit operating costs were $981 per ton. That's a fully loaded unit operating cost, right?

Tony Ottaviano

executive
#5

That figure includes leasing costs and inventory movements. It represents a fully loaded unit operating cost, which aligns with what we previously disclosed regarding unit operating costs. We want to ensure we're being compared on an apple-for-apple basis. That's an 8% increase on Q2, reflecting the transitional feed mix and the ramp-up. This remains within our FY26 guidance range. Finally, on cash — and again, the headline number of $424 million is the $33 million of positive net cash flow generated this quarter. I've already mentioned that operating cash flow fully funded our business for the first time. As the banner shows, FY26 guidance is maintained across all metrics: production, costs, all-in sustaining, and capital expenditure. I'll now hand over to Ryan for the health and safety and environment update.

Ryan Hair

executive
#6

Thanks, Tony. I'm actually at Kathleen Valley in person today, so I apologize ahead of time if any background noise comes through. Renewable power penetration for the quarter stayed at 85%, which reflects the money we've put into our wind, solar, and battery hybrid system and cuts our exposure to gas and diesel. Turning to safety: our TRIFR went from 11.55 to 10.53, but a shift like that sits well within the normal range of quarter-to-quarter variation. We aren't drawing any conclusions from it, and we remain focused on building a safety culture that prevents injuries and brings down high-potential incidents. A healthy volume of safety observations is a leading indicator of engagement, and we want to keep seeing that indicator and the quality of safety interactions strengthen. Next slide, thank you. I'll now take you through the operational story for the quarter, beginning with mining. As Tony said, we reached our 1.5 million ton per annum underground run rate ahead of schedule. The target had been set for the end of March. We got there early and held it across the quarter: 402,000 tons mined, a 31% increase on Q2. As we've noted before, and as Tony mentioned, the orebody keeps performing as expected, with grade reconciliation and stope dilution outcomes matching expectations.

Ryan Hair

executive
#7

We keep adding to our fleet capacity. One more jumbo and one more haul truck came in and started production in the quarter, which raised both development and haulage capacity. That gain and the boost in fleet capability will keep coming, especially as we move into developing the new development areas for the expansion at the Northwest Flats orebody. Going forward, continued level development will open up broader ore zones. We expect the next significant step-up in extraction rates in Q2 FY27 as we ramp toward the 2.8 million ton run rate by the end of FY27. Next slide, thank you. Moving to the plant, performance this quarter is exactly what we anticipate at this stage of the open pit to underground transition. Plant availability came in at 90%, which reflects the planned shutdown schedule. Together with fewer calendar days in the quarter, we processed 614,000 tons and produced 96,000 tons of concentrate. Global recovery for the quarter was 61%. Through Q3, the underground to open pit feed split was similar to Q2, but open pit material quality was lower than in the prior quarter, which led to a slightly lower recovery. As Tony mentioned in his opening remarks, at quarter end and into the first part of April, while processing clean underground ore, the plant achieved 70% recovery, exactly what it was designed to do.

Ryan Hair

executive
#8

Like we've mentioned in earlier updates, how well the plant recovers is really driven by the feed mix. Going forward, underground will make up the majority of the feed, with the leftover open pit stockpiles blended in during FY27 and Q4 of this year. Moving to the next slide, I'll walk through the recovery trajectory in a little more detail. On recovery, reading left to right across the full March quarter, the underground mix was 48%, and recovery, as we've said, was 61%. Across the entire March month, underground rose to 60% of the feed, and recovery climbed to 64%. During the first three weeks of April, underground accounted for 67% of feed, and recovery had been holding steady at 70%. These results are very clear. As underground ore becomes the dominant source across Q4 and beyond, which it is now, we expect to sustain that 70% recovery target. It validates the recovery pathway that we have been outlining for some time and underpins our confidence in delivering FY26 guidance, which we reiterated today. With that, I'll hand back to Tony to talk about guidance in more detail.

Tony Ottaviano

executive
#9

Thank you, Ryan. As I mentioned at the start, our guidance remains unchanged on every metric. We are still projecting concentrate production of 365 to 450,000 tons, and unit operating costs and all-in sustaining costs are unchanged as well. This comes amid conditions that have been quite difficult, given geopolitical unrest and the pressure we are feeling from a range of fuel-related input costs. There are three forward-looking items I think deserve mention. First, the feed mix is shifting. As Ryan explained today, underground ore is expected to become the main feed source in Q4. That trend has already picked up speed. During the first three weeks of April, we have observed better recovery. The second thing I want to highlight is that FY26 guidance is being held even with the geopolitical headwinds I referred to. In my view, higher fuel prices have affected Q3 costs only minimally. Our emphasis on business optimization stays strong and disciplined, as I noted at the start, and we will keep seeking ways to offset any of those headwinds as far as we can. Third, and this matters, we are reviewing 2027 costs as part of our budget process. That work is underway right now, and we are addressing both the geopolitical matters and how they affect our FY27 budget, along with how those matters interact with the planned brownfield expansion that we discussed in our announcement the other day regarding the early works.

Tony Ottaviano

executive
#10

What does that interaction look like when you're doing a brownfield expansion at a plant that's already running? We'll nail that down through our study work, along with how it affects the budget, when we come out with the scope and feasibility study in the quarter ending September. Then, on the early works side, we've just announced early works and procurement of long-lead items for the Kathleen Valley expansion. Those sit on top of the FY26 capex guidance we currently have. They aren't built into the unit costs or the capital figures we put out at the beginning of the year. We expect the $15 to $18 million of expansion-related capital expenditure in FY26 that we've referenced, which is separate from the numbers on this slide. I'll go through those figures in a bit more detail on the expansion slide. Let's move to the next one, please. At this point I'll pass things over to Greg Jason, our CFO.

Greg Jason

executive
#11

Thank you, Tony. Good morning, good afternoon, everyone, depending on where you are in the country. I'm going to begin with this cash flow slide. As Tony said, quarter three was the strongest financial quarter we've had since production commenced, with operating activities funding all investing and financing cash flows to give us a net cash flow of $33 million. Operating cash flow improved significantly again from break-even in quarter two to $55 million for this quarter. We had $165 million of receipts, which was a $37 million increase on the prior quarter, and it reflected the higher realized prices. As Tony also said, we'd have had another $64 million in the quarter if Cyclone Narelle hadn't delayed a shipment until 31st of March, and we subsequently received $64 million Aussie in April. Production and other operating cash costs decreased to $113 million, and that reflects the completion of open pit activities and the fact that the underground mine is still ramping up to 2.8 million by the end of FY 2027. Therefore, the amount of mining cost hasn't taken the place of the open pit that's come to an end. We had $22 million of growth capex in the quarter, very similar amount to Q2, and again, it predominantly related to underground development.

Greg Jason

executive
#12

Sustaining capex came in at $4 million, which was a couple of million dollars above the previous quarter, as different projects were carried out in each of those two quarters. A $10 million refund came to us from EFA, and that lowered a security bond arrangement with Zenith tied to the Kathleen Valley Power Station. A further $10 million of bond remains connected to that. We ended the quarter holding $424 million in cash along with 26,000 tons of salable product in inventory. This is old news, I realize, but we also booked the LGES conversion of debt into equity. At 31 December, $482 million of liabilities in debt and derivatives stood on our balance sheet, and those were removed in February. Net cash as of 31 March came to $61 million Aussie. Naturally, that leaves us in a really strong position for the ongoing ramp-up, the expansion we discussed in yesterday's announcement, and other growth projects. Please turn to the next slide, which covers the quarterly financial metrics. Beyond cash, looking at the other metrics, revenue rose by just over 50% to $197 million. The higher realized price more than offset the smaller tonnage shipped during the period. The cyclone additionally pushed back a 12,000-ton parcel from March into April, so roughly $30 million of revenue shifted from March to April as a result of that delay.

Greg Jason

executive
#13

Tony discussed the realized price increase—87% on an SC6 equivalent basis. The Aussie dollar figure came in somewhat lower, owing to the Australian dollar's appreciation against the US dollar. As usual, the realized price of 1,845 mirrors the contract mix, exposure to various indices across the mix of QPs, a portion of which look forward and a portion backward. Unit operating cost rose $71 to $981, driven principally by reduced production tons, which stemmed from the feed mix Ryan mentioned. Fuel prices affected unit costs only minimally during the quarter. Our supply is under contract. It hasn't been disrupted so far. We're monitoring it closely, as everyone is. We're holding full-year guidance for unit operating cost at $855 to $1,045. All-in sustaining rose $192 to $1,251. The $71 unit operating cost effect carried through into that. We saw almost $80 per ton higher from the higher price pushing royalties up, a couple of million dollars of additional sustaining capex, and the reduced tons explains the remainder of the gap. I'll hand it back now to Grant or Tony for the market outlook.

Grant Donald

executive
#14

Thanks, Greg. Moving to the next slide, please—appreciate it. So, the market has been really robust this quarter. We're seeing notable physical tightness, and that's reflected in the decline in weekly lithium carbonate inventories shown in the chart at the top right. It's even more striking once you translate that from total tons into days of inventory, given how the market has expanded. Normally, inventories sat at roughly 40 to 45 days. Today we're below one month—substantially under one month of inventories. I suppose this runs counter to the usual seasonality for this time of year, which you can see in the chart, with the yellow line diverging from earlier years. Some supply disruption has made this worse, and it keeps generating uncertainty around both volume and restart timelines. Brownfield restarts will begin to arrive toward the second half of this year. That's really the sole source of new supply with any near-term prospectivity, since greenfield supply requires three to five years of permitting, financing, and construction before reaching the market. On the demand side, as I mentioned, we've seen very strong demand from customers.

Grant Donald

executive
#15

We just got back from a trip to China, and I think demand there keeps being extremely strong — we have the ability to place far more tons than we actually produce under the current outlook. Importantly, I think we're also seeing pack sizes rise significantly across vehicles both in China and around the world. That is actually speeding up lithium demand beyond what pure EV sales growth alone would drive. We've also, I guess, gained from the uncertainty and higher fuel prices, in that these have helped push EV demand up. We've witnessed that in local markets, and we've witnessed that phenomenon globally as well. In my view, this isn't merely a short-term factor that disappears once oil prices return to normal — it's a fundamental step change in the demand profile for EVs and electrification. With that, I'll hand it back to Tony.

Tony Ottaviano

executive
#16

Thanks, Grant. That's a nice lead-in, and the market is strong. Here's what we've committed to as a company regarding early works for the Kathleen Valley expansion. Yesterday, we announced that we are moving forward with early works and the procurement of long-lead items for the Kathleen Valley expansion. This comes before FID, which we had planned to publish at the end of quarter one FY 2027. There are two elements to this. There's a strategic rationale, which I'll get to in a minute, but there's also a risk mitigation rationale. By committing to the long-lead items and mobilizing the team now, we mitigate schedule risk and equipment pricing risk in a tightening market. We've already seen the impacts begin to percolate through from the fuel crisis. We want to get ahead of that. It supports a robust capital cost estimate at FID by having some of these early things put away, and it positions us to execute immediately once the board approves the expansion. The committed program is set out on this particular slide. It has six elements covering the ball mill, which is a critical piece and part of the critical path; pre-development drilling; underground development at Northwest Flats, which we've been flagging to the market for some time regarding the optionality that gives us, plus accessing it from the bottom of the open pit, as this diagram here indicates.

Tony Ottaviano

executive
#17

Also, there’s stage one of the permanent mine services area — infrastructure we pushed back during the downturn so we could preserve capital. And then there’s the third paste pump we intend to install so that we can feed Northwest Flats and Mt Mann at the same time. Now, on the capital side: we’ve said these early works come in between $15 to $18 million, and we’re going to commit about $77 million of capital expenditure ahead of FID, right? More detail on capital and operating costs will come in the FID announcement. And then finally, the strategic logic. Right now, expansion at Kathleen Valley is our most value-accretive growth option. These commitments lay the foundation for growth and show our confidence in the market and, more importantly, in the operation. If I can go to the final slide, please. Just to recap the overall presentation — I won’t go through each of these — but just to say that in closing, Liontown is now a producing, cash-generating, self-funded, Tier 1 lithium operation. We’ve simplified our balance sheet. The market is structurally tightening, and we have a defined pathway to expansion with the early works program underway. The team is now building for what comes next.

Tony Ottaviano

executive
#18

We head into the June quarter with real momentum. With that said, I'll now move on to some Q&A, and along with the team, I'm glad to take your questions.

Operator

operator
#19

Thanks, Tony. If you haven't yet sent in your text question or gotten into the live audio queue, please do that now. I'll name each caller and then invite you to proceed. After that, a beep will sound to let you know your mic is live. Each caller gets a limit of two questions. Austin Yun of Macquarie is up first. Austin, go ahead.

Austin Yun

analyst
#20

Thanks. Morning to Tony, Ryan, and the team. I have just a couple of questions. The first concerns the run rate. It's good to see that it's already operating at 1.5 million tons underground. How should we think about the ongoing ramp-up? Is that a step change, or is it more of a linear progression out until you reach your target? Thank you.

Tony Ottaviano

executive
#21

Austin, Ryan’s answer will come from him.

Ryan Hair

executive
#22

Thanks, Tony, and thanks, Austin. Austin, I think the cleanest way to frame this is that across the coming two quarters we'll be consolidating that run rate. Part of what we wanted to show was that, in fact, when you do the math, it's slightly ahead of the 1.5 — at a 1.6 rate for the quarter. We'll consolidate that across the next two quarters while we keep developing out the levels below. As we said in the announcement, starting in Q2 FY27, you'll see another step change. From that point on, think of it as fairly linear. We'll have those levels developed, and then that will keep ramping to 2.8 by the end of the FY.

Austin Yun

analyst
#23

Okay, got it — thanks, that's clear. My second question is about recovery performance. I understand this quarter took a hit from the feed mix, and the early figures already point to a notable step-up in April. What I'd like to know is: once you're running entirely on the clean, high-grade ore from underground, what recovery rate do you think is achievable? Could we get near 75% or 78%? Thanks.

Ryan Hair

executive
#24

Thanks, Austin. That's a solid question. So, what I'd say in response is that the slide we put together—the one showing 67% underground and 70% recovery—reflects a blend. Effectively, it's 2/3 underground and 1/3 open pit material, and 70%. I think it's reasonable to extrapolate from that, at 100% clean ore, that the figure is above 70%. You're probably well aware of our DFS numbers, which sit around that mid range, maybe edging into the high 70s. I still believe the plant can achieve that. On any given day, with a clean underground mix, the plant does show that. Again, for anyone who operates these kinds of plants or has watched how they run, achieving that consistently is our focus. I think over the longer term, you can assume we'll be above the 70s and moving toward the DFS numbers as time goes on.

Operator

operator
#25

Thanks. We’ll take the next question from Stuart Howe at Bell Potter Securities. Stuart, the floor is yours.

Stuart Howe

analyst
#26

Appreciate it, Tony. Regarding guidance, production stays as it was, and looking at the year to date, that leaves a broad spread for Q4. I'm just curious: what risks do you see that justify keeping such a broad range for Q4?

Tony Ottaviano

executive
#27

Thanks, Stewie, and thanks for asking. Look, on our side, we have three quarters of actual results behind us, and with one quarter still to go, we can essentially extrapolate where we will land relative to guidance. As far as we are concerned, we remain in transition, as Ryan already said, and we are still ramping up. That guidance is something we feel quite confident about.

Stuart Howe

analyst
#28

Alright. Second point from me regarding fuel supply — you mentioned everything is locked in by contract and hasn't been disrupted. Could you expand on that a bit? Is there anything else that would give us more reassurance that supply will stay secure, and maybe some sensitivities if you've put anything in place?

Tony Ottaviano

executive
#29

That's a good question as well, Stewie. I'll split it into two parts. I'll take the first bit, and then Ryan or Greg can jump in on a few metrics. For us, what has been crucial, I think, is a systematic strategy right from the start. We wanted to partner with major strategic partners in the supply and construction of our operation. Our fuel contract is with Viva, so they're a Tier 1 producer, and therefore we have confidence in their schedule. Equally, our transportation is done by Qube, primarily for our product, and there are a number of others that do the supply of our consumables to site. Again, Qube has the size and the scale to manage their fuel supplies, we're very confident that they will continue to produce. Partnering with these large partners under proper contracts has served us well to this stage. Now, in terms of some of the financials, maybe I'll turn to you, Greg.

Greg Jason

executive
#30

Right. As Tony mentioned, when we examined diesel, it represents a minor portion compared with the whole operation, given the renewable power generation we possess. Even so, that expense exists for us, and prior to the Middle East crisis pushing prices upward, it accounted for under a couple of percentage points of our cost base. Measured in dollars per ton, roughly $1 per liter for diesel or Jet A-1 — which affects aviation for charter flights — equates to somewhere in the range of $25 to $30 per ton of unit operating cost for the finished product. That holds true for as long as the situation lasts.

Operator

operator
#31

Thanks. We'll take the next question from Jacob Li at Barrenjoey. Jacob, the floor is yours.

Jacob Li

analyst
#32

Morning, Tony, Ryan, team. Could you give us a bit of early insight into how you're thinking about the path to the 4 million ton per annum expansion? Assuming 4 million ton per annum remains the figure, I suppose my question breaks into two parts. First, you previously mentioned a capital-efficient incremental debottlenecking approach. It seems you now have key approvals and major infrastructure in place, along with some extra tonnage available from Mt Mann and Northwest Flats, which featured in your original 3 million ton per annum plan ahead of full expansion. Then, what about the other leading items needed to reach 4 million ton per annum — the additional ball mill, the paste pump you've already committed to, ventilation raises, paste fill plant works, water, and so on? In the last update, I believe we discussed $100 million for the process plant and $150 for the mine development. Does that still fall in the right ballpark? Apologies, I don't want to get ahead of things — I just hoped for some early insight into how you're thinking about your path to the 4 million ton per annum expansion, please. Thanks.

Tony Ottaviano

executive
#33

That question covered a lot, so thanks for it. On the capex front, here's what I'll say — I won't be making any early predictions. We're going to have the guys and girls do the work, and given how dynamic the market is, scope it properly and analyze the capital and operating costs properly. Once we're ready, in Q1 of next year, financial year, we'll give that to you. As for what the ultimate number is, well, again, that's part of the study, right? Capital costs — what I will say is that when we published those numbers you quoted, that was in the DFS. That's 5 years ago. Whether there's any inflation on that number, I'll leave it to you to decide. In our capital costs, there will be costs associated with the expansion. There are costs in these early works around accelerating. When we did the Northwest Flats piece, it wasn't just to service the 3 million tons, it was also to develop the operations for the 4 million, because we were going straight from 3 to 4. When the downturn came, we mothballed Northwest Flats. I think, to answer your question in conclusion, you've got to let us do the work first.

Jacob Li

analyst
#34

Okay, thank you, Tony. I have a quick follow-up question. Before the full expansion happens, is there a chance to unlock 3 million tons per annum within the next one or two years? That was likely what I was asking just a moment ago. Thanks.

Tony Ottaviano

executive
#35

Alright, and apologies — like I mentioned, that question covered quite a lot, so I'm sorry if I skipped over that part. I believe the way we've already described this expansion to the market is as a debottlenecking effort that frees up capacity. Items such as purchasing additional flotation cells, which fall within the area requiring an upgrade, are going to achieve that, and installing the ball mill is going to achieve that as well. If what you're asking me is whether we could potentially reach 3 million tons within the coming couple of years, well, that hinges entirely on how the underground ramps up, since we've stated that the underground will be running at a rate of 2.8 million tons per year by the close of financial year 27. Up until that level is achieved, we're constrained by the mine, and past that point, additional capacity will be freed up as we free up additional capacity from the underground.

Jacob Li

analyst
#36

Okay, got it. Thanks, Tony. I appreciate that.

Operator

operator
#37

Thanks. We move to Ben Lyons from Jarden Securities for the following question. Ben, the floor is yours.

Ben Lyons

analyst
#38

Thanks, Tony. Good to hear from you today.

Tony Ottaviano

executive
#39

Hello there, Ben.

Ben Lyons

analyst
#40

Perhaps I could add a bit more regarding that final question. On the subject of the mine constraints, you still have a substantial quantity of OSP material available, and presumably you simply weigh that against the roughly 1.5, 1.6 run rate being generated from underground. You can still operate the plant at what I'd describe as, say, 2.5, 2.6 capacity, once you account for your shutdowns and maintenance. Is that the correct way to view it — just steady processing of the OSP, which tops up whatever is produced from underground over the next 12 months or so?

Tony Ottaviano

executive
#41

Thanks, Ben. That's not quite right. We've drawn the OSP stockpile down considerably to reach the position we're in today. Going forward, we'll depend less on those OSP inventories, which is exactly why we're pointing to FY27—the end of FY27—for 2.8. It won't be topping up the feed all the way to that date.

Ben Lyons

analyst
#42

Alright. That’s helpful. Do you have a rough sense of whether the amount still left is perhaps 800,000 tons, or more like 600,000 or 700,000?

Tony Ottaviano

executive
#43

Ryan is going to take that one.

Ryan Hair

executive
#44

Right now, we have slightly less than 400,000 tons of OSP left. After sorting — keeping in mind that sorting separates ore from waste — the actual accepts feed will be a bit lower than that. It's probably around 200 to 250,000 tons. As Tony mentioned, we'll keep feeding that OSP accepts material through the plant, and it'll be blended in with the underground material, but it won't last until we've fully ramped up the underground mine, Ben. I hope that's clear.

Operator

operator
#45

Thank you. Since there are no further questions waiting, I'll turn things back over to Tony for some closing comments.

Tony Ottaviano

executive
#46

Thanks, Luka. To wrap up, from my perspective, what this quarter's figures show is timing rather than trajectory. The cyclone shut the Port of Geraldton, and without that, our results would have come in even stronger than what they are today. We're eager for the coming quarter and for the next 12 months. A great deal of work is going to be planned around the expansion and additional growth. We remain very strong, and we are fully committed to the next phase of our operations. Thank you all for listening, and I thank my team for the hard work that went into producing today's materials and the results.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Liontown Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Liontown Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Liontown Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.