Robert Samuels
executiveThank you, operator, and good afternoon to all of you, and welcome to the earnings call for MARA's third quarter of fiscal year 2026. We appreciate you being with us today. Joining me on this call are Fred Thiel, our Chairman and Chief Executive Officer, and Salman Khan, our Chief Financial Officer. This call contains forward-looking statements, including statements regarding our growth plans, liquidity, and financial performance. Such statements carry risks and uncertainties, and actual results could differ materially; we undertake no obligation to update them except as required by law. For further information, please refer to the risk factor section in our most recent 10-K and other SEC filings. We will also discuss non-GAAP financial measures such as adjusted EBITDA, which we consider important indicators of MARA's operating performance, as they exclude certain items that we do not believe directly reflect our core operations. Reconciliations to the most comparable GAAP measures are available in our earnings release; we hope you have had an opportunity to review our shareholder letter and we look forward to hearing your feedback; we will start with prepared remarks from Fred and Salman. Following their comments, we will open the line for Q&A. I will now hand the call to Fred to begin. Fred?
Fred Thiel
executiveGood afternoon, everyone, and thanks for being with us today. For MARA, the third quarter marked a major inflection point. In recent years we have assembled powered assets, strategic partnerships, operating infrastructure, and technical capabilities in a portfolio that competitors would find difficult to duplicate. We have achieved meaningful headway in carrying forward MARA's evolution into an enterprise designed to produce contracted returns along with durable free cash flow, and our simple objective is to get the most value out of every megawatt under our control. The market is becoming increasingly discerning regarding how AI infrastructure is financed and delivered. A position in an interconnection queue no longer satisfies tenants, lenders, and investors. They're looking for power they can get quickly, a site that fits, a solid development partner, tenants with strong credit, and a believable route to finishing. Those needs line up squarely with what MARA does well, and in Q3 we applied those strengths—growing our power footprint, advancing talks with tenants, and adding flexibility on the capital side. On the tenant side, we've moved ahead substantially, and negotiations are now quite far along. Prospective tenants have been brought by our engineering and operations teams to just about every one of our locations — Hannibal among them, which is next door to Long Ridge — and we take particular pride in what the development team has pulled off at Kearney, where permitting has moved along substantially, as the news has already reported; two lease signings remain our goal ahead of year-end, and given how fluid market conditions are, that timing might push into next year. The power, permitting, site, and financing work required to back those agreements and guarantee on-time delivery keeps moving forward. Now on the power side — at Long Ridge, FERC gave us the green light recently, and that was the final big hurdle left. We anticipate wrapping up that acquisition within the coming weeks, assuming the usual closing conditions are satisfied. We're thrilled to bring a very efficient natural gas facility into the fold; it's presently cleared to sell 485 MW, and we expect that to ramp up to the entire 505 MW nameplate capacity during the first half of 2027. Beyond immediately bolstering our financial picture through contracted cash flows from power generation, Long Ridge also hands us more than 1,600 contiguous acres with power, water, fiber, and rail access — a great foundation for a top-tier data center campus. When you add that to the Bitcoin mining we already run at the site, total potential capacity comes to more than 1 GW. We're eager to close the deal and move into the next stage of developing Long Ridge as part of our strategy. In addition, we obtained rights to a location in Matagorda County, Texas, able to access as much as 2 GW of power capacity, which has been designated study load through ERCOT's Batch Zero process. At present, we run roughly 1 GW across markets in the U.S. and abroad. Assuming Long Ridge closes and Matagorda gets energized, we anticipate the portfolio hitting more than 4 GW. Exaion produced early commercial validation during this quarter by securing a GPU-as-a-service contract running four years and valued at $79 million with a customer in the U.S., structured with 100% take-or-pay provisions. The pipeline Exaion has built up represents over $3 billion in total contract value, with approximately $1 billion of that expected to be delivered before 2027 ends; those numbers are demand indicators, not contracts that have been signed or committed. Even so, we view it as an early sign of demand for the bigger model Exaion is building as part of MARA's broader strategy. Regarding the balance sheet, after the quarter closed, we sold Bitcoin to pay down $750 million in debt that Bitcoin secured, which released 18,750 Bitcoin that had been pledged as collateral. Combined with the $1.4 billion, or 37%, of total debt we have cut since the start of the year, this has reinforced our balance sheet and our positioning for the coming growth phase. We'll keep managing our Bitcoin holdings, liquidity, and debt obligations in light of market conditions and the expected return on potential capital deployments, including opportunities in AI infrastructure. These milestones carry weight because investors are watching more closely the speed of AI adoption, elevated financing costs, and the credit structures underpinning individual projects. Such factors shape the timing and economics of development, yet they don't alter the fundamental need for power-ready infrastructure. What prospective tenants tell us is consistent. Demand stays robust for companies with a credible route to power and delivery. Since the election, demand for our sites has risen significantly, which we believe opens up opportunities for pricing power. The same holds for certain locations in our portfolio that previously might have been seen as peripheral, including portions of our international portfolio. That demand matters because it confirms the platform we've invested years in building. Our platform came about through Bitcoin mining. Operating a large mining fleet demands power procurement, modular deployment, infrastructure optimization, and real-time load management; those capabilities are precisely what's needed to run a broader digital infrastructure platform, particularly as modular data centers are being evaluated for innovative solutions that cut delivery timeframes and lower build costs, as demonstrated in the Bitcoin mining industry. We believe MARA ranks among the largest operators of modular Bitcoin mining digital infrastructure in the United States, and we plan to bring that experience to bear as we shift toward AI HPC. Bitcoin stays our operating foundation and a flexible means of monetizing power while we build out higher value infrastructure opportunities. That foundation provides optionality. We can leave each megawatt in Bitcoin mining or steer it toward AI or HPC when those applications deliver a better risk-adjusted return. That foundation underpins three complementary routes for deploying the platform. Mining produces near-term cash flow and keeps energized sites productive. AI and HPC campuses turn powered land into longer duration contracted infrastructure for hyperscalers and other large compute tenants. Modular data centers can bring compute online more quickly, where a smaller or faster deployment is appropriate. The right solution will hinge on the customer, the site, and the return profile. Conventional and modular solutions are able to co-exist throughout the portfolio. After a campus's first phase is finished, the toughest tasks involving land, interconnection, permitting, and core infrastructure are already done. A tenant might start at 200 MW and eventually need 400 MW, 600 MW, or more, which lets us raise the site's value without beginning again elsewhere. Big campuses can also accommodate a blend of hyperscalers, AI cloud providers, and enterprise workloads, which can boost utilization and lessen reliance on any one deployment. Our offering centers on speed, certainty, and reliability. Speed stems from controlling sites where power is already available or on a credible path to becoming available. Certainty stems from bringing together power, land, permitting, development, and financing into a project that can be underwritten. Reliability stems from years spent designing, owning, and operating large-scale compute infrastructure alongside strategic partners such as Starwood. Exaion lifts MARA beyond the infrastructure layer. It delivers private cloud infrastructure, open weight model orchestration, and inference as a service to customers needing more control over their data, infrastructure, and jurisdiction. Such needs matter especially for governments, regulated industries, and enterprises across Europe and other markets where sovereignty and security influence technological choices. We are commercializing Vertebrai, our flexible energy compute platform that draws on years of power-intensive operating experience.
Fred Thiel
executiveIt continuously rebalances power flows as supply and demand change—something we initially proved out at our Hansford County, Texas wind farm, where prices can turn negative and curtailment is frequent. From April through September 2026, we figure Vertebrai cut curtailment at that Texas wind farm by more than half. Without Vertebrai, roughly 46% of achievable wind output would have been curtailed. By using on-site computing to absorb electricity that otherwise would go to waste, Vertebrai lowered that figure to 22%, letting a greater share of the farm's generation go toward productive ends and creating an additional revenue stream. Now that Vertebrai is live, our attention is on extending this capability to other power producers as well as data center developers. We have been careful about which projects we take on. The initial wave of AI infrastructure brought aggressive pricing, climbing rates, and unpredictable delivery schedules that strained project economics; that lesson sharpened our emphasis on contracts capable of being financed, built, and operated at acceptable risk-adjusted returns; we care about the quality and durability of every opportunity, not growth merely for its own sake; the same discipline shapes capital allocation; we treat cash, Bitcoin, debt, and access to capital as components of one balance sheet. Bitcoin can serve as a strategic asset, be turned into cash when returns elsewhere look better, or be put up as collateral when that turns out to be the most efficient way to fund something. Salman will walk through this shortly, but Bitcoin has functioned as a distinctive instrument for managing capital. After the quarter closed, our board of directors gave the go-ahead to a share buyback program authorizing as much as $500 million of our common stock. That doesn't mean we'll halt investment in projects with high returns. Even so, in light of the market as it stands, we think an open repurchase program hands the company an additional tool with the potential to lift shareholder value. This authorization reflects the confidence that both the board and management have in MARA's long-term strategy, as well as in the considerable opportunities that lie ahead. Our direct spending will remain focused on site control, pre-development work, and selected project equity in cases where the expected return justifies it. The Starwood model reduces the corporate equity required for qualifying developments, while our liquidity gives us the flexibility to pursue opportunities without putting strain on the balance sheet. Our focus is on turning power and sites into tenant leases, getting projects online, and making the earnings potential of this platform visible in our results. Bitcoin built the foundation. Our power portfolio widened the opportunity. Our partnerships expand the ways we can capture value from each megawatt. Our job at this point is to carry things out rigorously and show what kind of returns these assets are capable of generating. With that said, I'll hand the call to Salman, who will take everyone through the financial results. Salman?
Salman Khan
executiveThank you, Fred. Good afternoon, everyone. Three major activities shaped Q3 for MARA. First, following the quarter's close, we obtained FERC approval for our Long Ridge acquisition, and we anticipate closing it within the coming weeks. Long Ridge ranks among the region's most efficient combined cycle natural gas plants, running at 485 MW at present, with expectations of reaching 505 MW during the first half of 2027. Long-term contracts hedge roughly 70% of its output, giving MARA a distinctive and diversified EBITDA value proposition relative to our peers. As previously disclosed, Long Ridge has historically recognized more than $140 million in annualized adjusted EBITDA. Second, we keep reinforcing our balance sheet, cutting total debt by $1.4 billion, or 37%, since the year began. In the quarter, we borrowed $750 million collateralized with Bitcoin to fund the Long Ridge acquisition, and after quarter end we fully repaid those loans, capitalizing on Bitcoin's substantial price appreciation. In August, we borrowed against Bitcoin while it traded near $64,000, and after quarter end we sold 13,597 Bitcoin at an average price of roughly $81,039, producing over $1.1 billion in proceeds. Disciplined and patient execution let us capture an estimated net benefit of $170 million. Third, we moved our Matagorda power portfolio forward. We possess development rights for a site larger than 1,200 acres, which ERCOT designated as study load under Batch Zero. We expect that site to provide up to 2 GW of grid-connected capacity. The deal terms also got better. In the quarter, we changed the purchase agreement and adjusted some milestones, which reduced our short-term cash obligation. To reiterate, MARA paid nothing upfront to enter this transaction, and no further costs will be owed to the seller until milestones are reached. After the quarter closed, our board approved a discretionary program to repurchase up to $500 million of our common stock. Given where we are today, we're constantly on the lookout for places to put our capital to work at the strongest possible return, and sometimes buying back our own stock fits that bill. Even with the markets pulling back, Bitcoin has held up well, and our balance sheet lets us move on those opportunities as they come up. For years we've been assembling a portfolio that sets us apart across power, land, and compute, and as Fred said earlier, our focus stays on converting that base into contracted returns and lasting free cash flow. Our approach to capital allocation will stay disciplined—we'll put it where we think it can generate the most value for our shareholders. Throughout the quarter, we kept streamlining operations and cutting out duplicate functions, bringing our cost base in line with the business we're building. That reflects patient, deliberate effort from our teams, and I want to thank the MARA team for it; with that context, let me move to Q3 financial results, and then liquidity and capital allocation. Average Bitcoin prices rose during the quarter, though they stayed below year-earlier levels. Despite that pricing environment, we reduced debt, progressed with the acquisitions of Long Ridge and Matagorda, and kept our cost structure tight — which positions us well for the years ahead as a digital infrastructure company. Third-quarter 2026 revenue came to $164.2 million, compared with $252.4 million in the same period last year, which works out to an $88.2 million decline. Of that drop, Bitcoin mining revenue made up $83.1 million. A 37% fall in the average Bitcoin price cut revenue by $94.8 million, though an $11.7 million gain from higher production partly made up for it. During the quarter we mined 2,247 Bitcoin, equal to 24.4 per day, roughly 103 more than a year earlier. Our block wins totaled 644, a 2% increase year-over-year but a 7% decline quarter-over-quarter. Thus far in the year, we've mined 6,916 Bitcoin. The energized hashrate we delivered came to 71.2 EH/s, an 18% increase over the 60.4 EH/s recorded in Q3 of 2025, driven largely by improved miner efficiency. We grabbed 5.4% of the mining rewards available, up from 5% in Q3 of 2025. Net income came in at $632.1 million, equal to $1.28 per diluted share, compared with $123.1 million, or $0.27 per diluted share, during the same period a year earlier. That number reflects an unrealized non-cash fair value gain of roughly $885.3 million on digital assets, tracking Bitcoin's price appreciation across the quarter. Adjusted EBITDA for the quarter, including that fair value gain, climbed to $857.7 million — a 117% increase from $395.6 million a year earlier. Our cost per petahash per day improved 2% year-over-year, landing at $30.8 versus $31.3 in Q3 of 2025. Over the past eight quarters, this metric has gotten 20% better. We believe it remains among the lowest at scale in our industry. At our own sites in Q3 of 2026, cost per kilowatt hour stayed at $0.04. Bitcoin purchase energy costs at those sites totaled $39,674, compared with $39,235 in Q3 of 2025, even though production grew 10% during that period. Third-party hosting and other energy costs — mostly co-location services at third-party hosted sites — came to $71.5 million, versus $75.7 million in Q3 of 2025. That $4.2 million reduction came mainly from lower hosting costs, partly offset by greater energy consumption at certain hosted sites. Going forward, our largest third-party hosting arrangements, accounting for roughly 29% of total energy capacity, start expiring in the third quarter of 2027 and should wrap up entirely by the first quarter of 2028. As those lapse, we anticipate removing third-party hosting costs and bringing our cost per kilowatt hour down over time. General and administrative expenses were $75.8 million, lower than the $85.3 million of a year ago. The 11% drop mostly reflects a $9.8 million decrease in stock-based compensation expense, partly offset by operating costs at Exaion, our recently acquired majority-owned subsidiary, and by administrative costs tied to our larger footprint. Moving on to the balance sheet and liquidity: we closed the quarter with $946.5 million in cash and cash equivalents, plus roughly $3.8 billion combining cash and Bitcoin. At quarter end our Bitcoin holdings came to 34,012, worth about $2.8 billion at a spot price of $83,556. Roughly 57% of that total — 19,260 Bitcoin — was loaned or pledged as collateral. Since the quarter ended, repaying loans has brought our total loaned or pledged Bitcoin down sharply, to under 5% of our BTC holdings. Combined, the cash we hold plus our Bitcoin provide the liquidity required to cover our obligations—the convertible note puts among them—as we keep putting capital into our operations. Our strategy still rests on power as its base. We have put together a 1 GW portfolio of sites we own and run, with an obvious route to more than 4 GW; we have locked in the groundwork for MARA's digital infrastructure transformation; and since power, partners, and capital are now secured, we are carrying out our plan to generate long-term shareholder value. With that said, I'll hand things back to Fred.
Fred Thiel
executiveThanks, Salman. As Salman mentioned, the results we posted and the steps we've taken on capital both back up the strategy we laid out earlier today. We're weighing liquidity, leverage, and dilution against each other, and steering capital toward the uses that can generate the most value from our infrastructure. The chance here goes beyond just monetizing a single megawatt. What matters is raising the value we get out of each megawatt as we progress from power to infrastructure to compute—and, where it makes sense, integrated cloud services. With that said, I'll hand things over to the operator so we can begin taking questions.
Paul Golding
analystThanks a lot for taking my question; I'm with Macquarie Capital, and I appreciate the opportunity to ask about all the progress—congratulations on everything accomplished so far. First, I wanted to ask about Long Ridge: when we consider the expansion opportunity there, could you shed some light on the emissions permitting backdrop, maybe, or any other regulatory factors we should keep in mind as we think about the recent election? Then I'll have a follow-up. Thank you very much.
Fred Thiel
executiveWhen we consider that specific project, it's clearly already producing power, and if anything, the utilities are asking us to keep feeding as much electricity as possible into the grid, and we're dedicated to doing exactly that. The bulk of the plant's output is tied up in long-term contractual commitments, as you're aware, and that's actually among the reasons this plant appealed to us so strongly. With its low operating costs and contracted revenues, it's a superb cash-flowing asset for our portfolio, and the land dovetailed very nicely with the Hannibal site we already own. At Hannibal, we can get 200 MW through a grid connection, and we also have the option of 200 MW behind the meter. The team has actually been working on that behind-the-meter piece for a good while now from a permitting standpoint, in anticipation of the deal closing. On top of that, there's more capacity available through plant expansions and extra grid capacity. So all told, that site has the potential to get to roughly 1 GW. We don't expect any meaningful regulatory problems there. It's a former aluminum smelter site, and that's where the data center would go. Based on everything we know as of today, we believe permitting at that site shouldn't face any significant delays.
Paul Golding
analystThanks a lot, Fred. Let me shift over to Exaion — congratulations on that new GPU-as-a-service deal. I wanted to ask a quick back-of-the-envelope question about the $1 billion of demand that lines up with the 30 MW, I believe, mentioned in the press release shareholder letter. Running some rough math on that, it works out to a fairly competitive mid-30s millions per megawatt of ARR. That's just a quick back-of-the-envelope calculation. Is the pricing environment you're describing actually coming through in GPU-as-a-service rental rates per GPU hour? Does this reflect shorter-dated contracts or longer-dated ones? How should we think about the discussions currently underway and how pricing strength plays into them? Thank you very much.
Fred Thiel
executiveAbsolutely, yes. So clearly, the shortage of capacity here in the U.S. has driven a lot of potential customers to look for power in other places. One benefit of running in France, and especially with Exaion, is how closely it's tied to EDF, and France is a nation where power is plentiful. Exaion is already running data centers that have capacity. This specific contract, the first one, is pretty small compared with the other demand that's been coming our way. The length of the deal, a bit over four years, is pretty typical, I'd say, for this kind of service in today's market; and the pricing looks quite strong. If you look at the demand curves, some customers clearly are eager to run Vera Rubin. A number of clients are perfectly content to keep using GPUs from an earlier generation. And in today's market, with the way pricing works, the lead times for delivery, and the exposure that comes with being an early adopter of Vera Rubin, we think that relying on something like B300s—as this particular contract does—is entirely logical financially, since the margins you get with that kind of technology are genuinely appealing. Exaion gains one more advantage here: for years it has run what amounts to an aging infrastructure setup, in which GPUs can first handle model building, then be shifted down to inference, and afterward shifted down again to rendering. One of Exaion's offerings is Exaion Studio — a GPU-powered rendering platform. Companies working on advanced media solutions rely on it to render 3D graphics, among other things. Take, for instance, the kind of visuals you'd encounter at the Sphere in Las Vegas — graphics along those lines. That covers real-time rendering for events of that sort, plus rendering used in films and similar applications. A GPU's useful lifespan can be stretched considerably by serving multiple customers in sequence. Essentially, Exaion has built an orchestration platform. It lets you simply rent GPUs, or do more complex orchestration spanning model selection, inference as a service, right through to a complete private cloud, plus the kinds of rendering services we've discussed. That's an excellent means of extending infrastructure's useful life, and it enables us to go from powered land, so to speak, right through to the private cloud.
Paul Golding
analystUnderstood. That pricing shows just how far up the stack Exaion is climbing too.
Fred Thiel
executivePrecisely. Yes.
Paul Golding
analystThanks so much.
Fred Thiel
executiveYep.
Michael Donovan
analystHey, guys. I appreciate you taking my question. Fred, now that Kearney Advanced is in pre-development and we have the conditional use permit in hand, what steps remain before a lease gets signed there? Are the outstanding items mostly about power, permitting, or the project economics?
Fred Thiel
executiveWithout drifting into MNPI territory, I'll just say the issues really have nothing to do with anything on our end; they're simply a few things on the customer side that need to be dotted and T's crossed. The moment they finalize that, the lease will move forward. Broadly speaking, that's what we're seeing across the portfolio: there's been a rush to get things done, and then at the last minute these conditions always crop up where the delay falls on the customer side, typically, or the tenant side. Since the election, we've seen what you might call a surge in demand, where tenants that normally wouldn't have looked at some of our peripheral sites, as I mentioned in my comments, are now saying, "Listen, if you have power availability, just let me come in." I think we're also seeing prospective tenants being very open to solutions that are a bit more innovative, which will let them deliver faster. I think the other thing we're really seeing — and this is feedback we're getting from hyperscalers, for example — is that they are spending an inordinate amount of time dealing with delays caused by first-time developers. That's one of the reasons we believe the Starwood partnership is so important, and so critical. Especially hyperscalers who have worked with Starwood before, they know what they are getting when they work with Starwood and, through Starwood, with us. Whereas when they work with one of our peers potentially, whose first time at doing this it is, there is no certainty. While many of them may have been attracted by promised timelines, they are now realizing that the promise does not necessarily resolve itself in delivery and in service on schedule. A lot of time is being consumed on the tenant side dealing with deals that have now gotten kind of delayed, or are stuck due to development constraints and other things. I am very optimistic about the fact that, by having waited and not jumped in from the very beginning — some of you may recall some of our early comments were very much about, if we go in and build the types of data centers people were talking about 18 months, two years ago, we said, "Hyperscalers will not work with a Bitcoin miner." I think hyperscalers have learned their lessons or are learning them now, and we are starting to see a different quality of conversation happening. We think having been patient will pay off in the long run for us.
Michael Donovan
analystGot it. You've discussed bringing your experience with modular deployment over to AI infrastructure. How are you thinking about the design and development side? Would MARA and Starwood create a standardized offering, or do you expect to partner with third-party providers on designs like NVIDIA's DSX pod?
Fred Thiel
executiveYeah. I mean, honestly, that hinges on the tenant, right? Building it and assuming they will come isn't our business. What we do is sign a lease with a tenant who has a very particular set of requirements for what they want, and who is ready to put their money, so to speak, behind the technology they intend to deploy. If they want to deploy NVIDIA's modular solution, or any of the other assorted solutions people are promoting, we're more than happy to deploy it on their behalf—but the risk sits with them if they're the ones making that call. We believe there are plenty of highly appealing solutions out there, but the key, I think, isn't merely the modular solution's design—it's how you construct a site for it and how you run a site for it. We run 250 MW of containerized solutions in the U.A.E; they rely on liquid immersion, and when built in 2023 they were state-of-the-art and still perform remarkably; we also have a very large—I'd almost call it one of the biggest containerized sites in the U.S., located in Texas—and over the years we've learned a great deal about how to pull this off. Operating these sites matters just as much as the technology inside the container—the racking, the cooling, et cetera.
Michael Donovan
analystExcellent. Thanks, Fred. Wishing you the best of luck.
Fred Thiel
executiveThanks.
Chris Brendler
analystHi, thanks for taking my questions. I apologize — I missed this. I'm doing a little multitasking, but have you given an update on Matagorda and what the election results could potentially mean there? I think there's, you know, sort of like there are incentives in the contract where you don't have to pay anything until they get approval, but how does the change in government there affect that outlook on Matagorda? Thank you.
Fred Thiel
executiveYeah. Hey, Chris. Yeah, it doesn't change anything in the contract. We did this deal very specifically to mitigate risk, and it has been proven that the way we did this was the right way to do it. Right now, we don't really have any commitments until Batch Zero gets full approval—that's the point when they kick in. Considering Governor Abbott's audit requirements along with the current climate, chances are that Batch Zero approval or studied load will likely deliver power around the same time, based on the timelines. As you're aware, Texas's new governor has stated that already-approved projects are going to proceed. Our view is that Texas will keep being quite supportive of this industry as a state, although they'll want to make sure consumers aren't harmed and so forth; we're eager to collaborate with Texas communities to advance this; still, Matagorda is a fantastic location. A nuclear plant sits very nearby. High-voltage infrastructure already runs into the site. The power pricing market there is excellent — good enough that mining Bitcoin on-site is profitable for us. So for us it's a terrific site. We're quite enthusiastic, and we think that over the course of this process it will turn into a fantastic campus for us.
Chris Brendler
analystThat's really useful, thanks. My follow-up question is really about the Bitcoin mining business. You're continuing to expand your hash rate, and then weather plus summer heat bring down the effective hash rate —
Fred Thiel
executiveYeah.
Chris Brendler
analyst— during Q3. It did land, though, I suppose, below my own expectations. At this stage, are you — I assume you're still optimizing the fleet. How do you view optimization once those hosting sites come off next year? Is much of that work already finished, with the older machines already sitting at some of the hosting sites, or is there still more to do when it comes to shifting the more efficient fleet into your current sites? Thanks.
Fred Thiel
executiveYes, good question. We've been gradually upgrading older systems. Given the age of our equipment, we started large-scale miner deployment back in 2022, so some of those earlier units are getting close to what you'd describe as the end of their useful life. Because of that, we've been upgrading to newer, more efficient machines, especially since Bitcoin mining hardware is priced extremely low at the moment. That explains why you've seen hash rate climb—more energy-efficient machines simply produce more hash rate per megawatt, right? That's the approach we've taken. If you consider the hosting contracts that expire beginning next year, a lot of that capacity is going to be substituted through equipment upgrades at different locations, and that will maintain the hash rate, if you will. Then, as additional sites are prepared for development into hyperscaler locations or AI campuses in general—where we intend to use modular technology—we can deploy Bitcoin mining in a modular format without difficulty and essentially move equipment between sites. That is part of the whole rationale for the advantages of modularity: think of the pad infrastructure as being quite comparable across the two. The containers themselves might differ, and what goes inside them could differ too, yet nearly everything else stays much the same. That is precisely where we believe our strength lies—being able to use sites with a great deal of flexibility.
Chris Brendler
analystGot it — that's clear. Many thanks, I really appreciate it.
Ben Sommers
analystGood afternoon, and thank you for taking my questions. To start with Exaion, I'm a bit curious: you talked about how you intend to scale power alongside your growth targets there, but could you speak briefly about GPU allocation and how you approach buying GPUs in order to support those targets?
Fred Thiel
executiveHere's one way to think about it. You've got customers whose demand for GPU capacity is substantial. Meanwhile, data center capacity isn't expanding at the same pace, simply because of the practical constraints involved in getting those sites permitted, energized, and brought online. There are GPUs that have been delivered but are stuck waiting — they won't be installed since the sites aren't ready yet. You're beginning to notice certain inventory buildups in which organizations that already bought GPUs are now considering selling off what they hold and then placing orders for next-generation hardware down the road, perhaps. At present, we aren't seeing any constraints in the GPU market. We've invested effort in developing ties with NVIDIA along with many of their partners. Not long ago I was at NVIDIA's headquarters, and we spent time — the Exaion team spent time — with NVIDIA's executive team at GTC in Berlin. We're very much in relationship-building mode with them. Our ties with that partner are strong, and up to now nothing has gotten in the way of securing the quantities we require.
Ben Sommers
analystReally helpful. I understand we currently have some access to power internationally and could potentially grow that. Are there any thoughts about developing properties together with Starwood and then having Exaion potentially plug in GPUs, sort of creating that fully vertically integrated stack?
Fred Thiel
executiveYes, I mean, that is precisely what the strategy amounts to, correct? Picture us as a developer of a strip mall, right? There's an anchor tenant that's a hyperscaler, and then perhaps you've got some smaller tenants that are enterprise customers. Exaion can run that infrastructure for them if they need it; and then in the middle, you might have tenants that simply deliver AI services. The entire model is essentially built around being able to begin with land and power at the base and extend all the way up to private cloud and running enterprise infrastructure. Or we have flexibility with Exaion such that they can come in and operate an enterprise's infrastructure, or basically deliver inference as a service and other services to enterprises and other providers as needed. One thing I did want to just kind of double-click on. The hosting capacity that Exaion has contracted with a U.S. customer is located in France. Meaning, the U.S. customer sits in the U.S., while the hosting takes place in France; that's an illustration of the kind of demand that exists out there among people. If you've got capacity and you can switch it on today, plenty of customers are waiting in line to take that capacity.
Ben Sommers
analystThat's really useful. Thanks for answering my questions.
Fred Thiel
executiveYes.
Mike Colonnese
analystHey there, good afternoon, and thanks for taking my questions. It's really encouraging to see all the progress. My first one is probably for Fred. Could you talk about how the lease terms you're negotiating have shifted, given what we've witnessed in the broader macro environment over recent months? Has the thinking around potential contracts changed in any way when it comes to the ownership stake MARA would be prepared to accept in a possible deal involving Starwood?
Fred Thiel
executiveThe way I'd frame it is that the majority of tenants aren't simply taking promises at face value anymore — they're double-clicking and triple-clicking, conducting thorough diligence to make sure a prospective developer can genuinely deliver on schedule. That means going deep on power contracts, going deep on environmental permitting risk, and so on. One way we stay ahead of that is by pushing forward on those items even without a signed lease. We have enough confidence in our ability to execute that regardless of whether that tenant signs or someone else does, all the work we do — the pre-development work — pays off on timing, meaning the site comes online even sooner, right? There's no point in waiting. We won't begin constructing a building absent a tenant, but we will handle power infrastructure, all of that, network, and so forth, so that we're ready to move with it. So customers and tenants are far more exacting during their diligence, which we see as a positive. We've had many site visits with prospective tenants' operations teams, engineering teams, network teams, and the like, which shows they're putting in their time and resources to try to validate that those sites are solid, and the feedback we're getting from that has been excellent. As I said earlier, some of what we're hearing, particularly from the hyperscalers, is that after signing deals with first-time developers, they're now spending considerable time repairing those deals and moving them along. So take the Kearney site as an example — it's public as far as the permitting goes. We've engaged very closely with the local community there. Our relationship with that community is strong. Things are progressing very well there, and we think that site will be among the first to get contracted.
Mike Colonnese
analystThanks for that color, Fred. Salman, here's maybe one for you. As you look to fund AI data center builds and possible buybacks, how should investors view the pace of Bitcoin sales going forward? Right now it looks like you're holding just over 35,000 coin on the balance sheet. I know the investment community has been very focused on this topic given your exposure to Bitcoin price moves. Any color you can share would be helpful.
Salman Khan
executiveYeah; we've said all along that Bitcoin is a strategic asset for us and a corporate asset held on our balance sheet, one that will be deployed for investing in our company and as a source of capital. What you've watched unfold since the quarter closed is that we've sold Bitcoin, repaid our borrowing secured by Bitcoin, and delevered the balance sheet by about 37% since the start of the year. Obviously, that further strengthens the balance sheet overall from a net liquidity standpoint, and it also builds a cash or capital source via the Bitcoin we already hold that can be put toward investing where that capital allocation is highest or best used, if you like, at that moment, which includes retiring debt, or as I mentioned in the prepared remarks, the puts, should they be put to us, we have sufficient cash and liquidity to be able to entertain that. Beyond that, we have tremendous projects, as Fred discussed a few moments ago, across diversified communities and diversified states, multiple countries. That provides us a plentiful amount of leeway or bandwidth to keep investing in high-return assets. Just as a reminder, given our partnership approach, which is unique to MARA versus our other peers, the strategy for us is capital light. If you run the math, we can pursue a multi-gigawatt build opportunity through the existing liquidity on the balance sheet, through the Bitcoin we hold and the cash we hold as of now. That places us in a very unique position without having to think about the financing, the traditional financing of these transactions. The net check that MARA has to write within a partnership scenario is a capital-light strategy, which leaves us a long ways to go from here from a development standpoint. All in all, look, Bitcoin is a strategic asset for us, and we're utilizing it methodically, and that gives us the opportunity to, as we also said in the prepared remarks regarding share repurchase. That is another option or a tool. Should the right opportunity arise, we will utilize that appropriately and responsibly as market conditions dictate.
Mike Colonnese
analystUnderstood. Thanks, and I hope the talks keep moving forward successfully.
Fred Thiel
executiveThanks.
Salman Khan
executiveThank you.
Kevin Dede
analystAppreciate the invitation to join this call, Fred and Salman.
Fred Thiel
executiveHi there.
Kevin Dede
analystI've got a question on the Exaion deal. We don't have an RFS date, and it isn't clear. I know you mentioned various classes of GPUs. That part isn't clear either. The power side isn't clear. The potential to scale up to $1 billion or $3 billion in contract value — I'm just wondering how those pieces fit together when the time comes to allocate power resources.
Fred Thiel
executiveYeah. Great question. I believe it's public that the GPUs powering this initial contract are B300s. Those are ordered, and delivery will begin this month and run through the first part of December, and we expect the RFS date for the first part of this contract to land before the new year. So a portion of this capacity will be up and running by year-end. That gives you a sense of how quickly we can move and how easily we can acquire GPUs as well; this goes into capacity Exaion can access in France that's already built and already ready to go. Again, part of what makes this strategy with Exaion beneficial is that in the U.S. there's enormous scarcity around capacity; in Europe, if you proceed the right way and partner with the right people, you can get access to capacity. You can get access to power. There are some quick paths to get things done. Also keep in mind that Exaion operates in Canada, and we have similar opportunities there around power and infrastructure; so the Exaion build plan, so to speak, isn't predicated on MARA developing anything in the U.S. for them. It's really predicated on them building capacity themselves in Europe and Canada, which they're highly experienced at doing.
Kevin Dede
analystAll right, that helps. As I understood it, there's a site over in Sherbrooke, I believe, though in megawatts it's de minimis, and I'm aware Hydro-Québec is fairly tight-fisted, so I'm sort of wondering whether you might add some color there.
Fred Thiel
executiveI won't be criticizing Hydro-Québec. Capacity is available to Exaion in Canada as well as in France. In fact, France offers some appealing availability. Another benefit of working with France is their superb internet infrastructure. The grid system there is extremely reliable. More than 60% of the power is clean nuclear. There's plenty of renewable energy as well; so basically, for companies where carbon footprint—which I believe will once again become a very significant matter in the years ahead following the election results—has suddenly turned into something quite important, and people want to make sure they can run AI infrastructure in a clean manner, one that doesn't produce needless carbon emissions. So that too is fueling some of this. France has substantial energy going unused today, and infrastructure was constructed that hasn't been fully utilized. We keep finding plenty of pockets where we can step in and secure capacity, which is excellent.
Kevin Dede
analystAll right, thanks. I appreciate that perspective, Fred. Thank you. It's difficult to make out the plants from this spot.
Robert Samuels
executiveThank you, operator, and thanks to all of you for being with us today. Should any questions remain that we didn't get to on today's call, don't hesitate to reach out to our investor relations team at ir.MARA.com. Many thanks, and enjoy the remainder of your day.
Operator
operatorThat brings us to the end of the teleconference for today. At this point, you're welcome to disconnect your lines. We appreciate everyone for joining us.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete MARA Holdings, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to MARA Holdings, Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in MARA Holdings, Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.