Thanks for holding, and welcome to the Mineral Resources analyst call about the June 2025 Exploration and Mining Activity Report, which came out today. Joining us are Mark Wilson, Chief Financial Officer, and Chris Chong, General Manager, Investor Relations. Just a few housekeeping points before we begin. This is a sell-side call, and analysts can submit questions either by text or live audio. For a text question, click the messaging icon, enter your question in the box near the top of the screen, and hit Send. For a live audio question, click the Request to Speak button at the top of the broadcast window. The audio question screen will then replace the broadcast. Please use the dial-in number and access pin you were given to ask over the phone. Or, if you're on a home or personal network, you can ask online by clicking Join Queue. If a prompt appears, choose Allow in the pop-up so your microphone can be accessed. Should you run into any trouble with the platform, dial-in details are also available on the homepage under Asking Audio Questions. Text questions are welcome at any time, and the audio queue is now open.

Chris Chong

executive
#2

A recording is being made of this call, and a written transcript will be posted to the MinRes website later today. At this point I'll pass things over to the team from MinRes.

Mark Wilson

executive
#3

I've got a slide up from 1 July here. There was a board meeting yesterday — a group board meeting at MinRes — and Mel is in the office this morning, so I was just listening in on the call. As always, I'll begin by walking through a handful of highlights. This is our quarterly. Once again in this document we've aimed to provide a bit more detail than we've typically given, simply to keep advancing transparency. It went out to the exchange this morning, and we'll take questions at the end. Let me begin with the main highlights. On the whole, I'm glad to report that the business, across every segment, has met volume and cost guidance for FY 2025. I'd describe it as a solid performance right across every part of the business. We've driven plenty of positive change on a number of fronts over the past three months, and there's a continued emphasis on execution within the business. You'll have seen from various announcements that the board and governance refresh we've been flagging for some time is well progressed and underway. As I mentioned, Mel becomes Chair effective from the start of this new financial year, and she's also been joined by two non-executive directors, Ros Carroll and Lawrie Tremaine, both of whom attended yesterday's meeting for the first time.

Mark Wilson

executive
#4

That boardroom shift is driving a substantial governance overhaul, and it ranks among the top priorities for the incoming Chair, together with reinforcing the balance sheet. Throughout this entire effort, management is collaborating with the board to keep examining the levers at its disposal right across every part of the business, and we are undertaking a refresh of our capital allocation framework with the board's guidance. When it comes to bonds, though, happy to confirm it remains cash flow positive, at both mining services and the commodity level. I will walk you through that in somewhat greater detail shortly. During June, we reached an annualized run rate of 32.4 million tons per annum at Onslow, which was a tremendous result, especially given that we had only our last fifth, or a fifth trend shipper, operating there really for roughly the final week of that month. In today's report, we have in fact supplied some guidance for shipped tons out of Onslow Iron. Our share, 17.1 to 18.8 million tons, equivalent to 30 to 33 million tons on a 100% basis. Roadworks are the reason we are not hitting 35 million tons across the whole year, and once more, I will take you through that in somewhat greater detail as we get to Onslow.

Mark Wilson

executive
#5

The Hall Road upgrade should wrap up by the close of this quarter, and we're still on course to reach a 35 million ton per annum run rate, which we anticipate achieving around the end of September. As I believe most people understand, this operation is affected by seasonality, usually from November through March because of cyclone season. Once more, I'll walk you through that when I go over the numbers. On safety, the rolling 12-month TRIFR came in at 3.84. That's a slight increase. We recorded a few more injuries in the first half, and then our hours dropped considerably during the year as Onslow construction wound down and intercurrent maintenance ended at the Ball Hill and Yilgarn operations. At the corporate level, we're happy with how we closed the year on liquidity. We ended with more than $1.1 billion at 30 June, and because of that, net debt to EBITDA should keep coming down. We left a modest amount drawn on our revolving credit facility as of 30 June, but cash totaled over $400 million including that draw. To make sure everyone is clear, I anticipate having full access to that RCF facility going forward.

Mark Wilson

executive
#6

That aligns with what I've been saying across several quarters now. On net debt, we ended the year at $5.3 billion. Looking at the quarter, the main movements were a $200 million FX gain on the U.S. unsecured bonds. We had a couple hundred million dollars of interest payments during the quarter. There was a modest working capital outflow of roughly $50 million. We spent a couple hundred million dollars on CapEx. CapEx for FY 2019 — sorry, FY 2019, that was quite a while back — FY 2025 came in at $1.9 billion, below the $2.1 billion guidance. To be clear, roughly $100 million of that difference is a timing matter tied to Onslow and when certain payments fall. That $100 million will land in FY 2026, and the remaining $100 million reflects savings throughout the business. Let me offer a quick note on FY 2026 CapEx. We're still working through with the board on what that will look like, and as usual, we'll give more detail at guidance — more detailed guidance — with the FY 2025 result at the end of this month.

Mark Wilson

executive
#7

Like I mentioned before, we're looking for that CapEx figure to land slightly above 50% of what we spent in FY 2025 — so roughly $1 billion, give or take. Roughly half of that amount is going to be sustaining, and then there's some meaningful continuing investment at Onslow, which includes the transshippers, finishing the road, and bringing Upper Cane online as a satellite deposit. There's also some exploration spending in the mix, energy included. I'll walk you through all of that in greater detail roughly a month from now. When we think about CapEx, our historical practice has been to quote it net of asset finance. We've provided a bit more detail in this material regarding how the gross figures look, just as a helpful reference. On the FY 2026 numbers, we're anticipating roughly $150 million in asset finance across both yellow goods and transshipper six and seven. As we've discussed previously, those transshippers matter for getting us beyond 35 million tons. On leverage, in line with what we've been saying for some time, EBITDA keeps rising month over month, and because of that, our net debt to EBITDA ratio keeps coming down organically. Regarding the carry loan at Onslow — a key asset for the group, representing what we're owed for funding our partners into the project — that is being repaid with interest.

Mark Wilson

executive
#8

As of 30 June, the balance stood at $766 million, which represents a net reduction of slightly more than $20 million. During the quarter, that balance actually rose, since completing construction means the invoice gets added to the carry loan. The $20 million figure is a net amount. Regarding the full-year statutory report, it will come out at the end of August. We have provided some sense of the potential adjustments we have identified as we approach year-end. Naturally, all of that remains subject to audit and similar processes, but we are attempting to give you an early view of some of that material. Moving to the business, let me walk through this quickly so we can reach questions. Mining services delivered a very strong performance. On volumes, we landed right at the bottom end of the guidance range, though our EBITDA per tonne margin should come in at the upper end of the $2.10-$2.20 guidance range. We posted a record 83 million tons for the quarter, an increase of 21 million tons versus the prior quarter. The ramp-up of Onslow Iron is what drove that. I should mention as well that mining services — the externally focused crushing and haulage operations — have performed incredibly well over the past year, and over the last six months especially.

Mark Wilson

executive
#9

When it comes to iron ore, our total attributable output came to 8.9 million tons, with shipments at 8.3. Across both hubs we realized an average of $79, which works out to roughly an 80% realization. With our prior period adjustments included, that figure would have been 82%. As all of you have likely observed, iron ore prices have climbed back above $100 lately. The forward curve had a rather intriguing shape—it was pretty flat. So we've seized the chance to begin hedging a portion of our volumes for the coming six months, locking in some of that price improvement. Regarding Onslow specifically, I'm quite happy with how things went during the last quarter. As I mentioned, the fifth transhipper actually kicked off near the end of June. We loaded 30 vessels, shipping 5.8 million tons. Across the quarter we ran 147 trucks—83 of them our own and 64 contractors on average. 31,008 road train journeys were completed along that road, which many of you were able to observe during the quarter. This is a figure that never fails to astonish me. Over that stretch we covered a combined distance of nearly 10 million kilometers on that road. As for where we stand right now, we have 120 MinRes trucks—in fact, more than 120 MinRes units—commissioned on site, on our way toward the 140 we require.

Mark Wilson

executive
#10

We still intend to move the contracted trucks out once the road is finished at the close of this quarter. For Onslow in FY 2025, shipments came to 14 million tons on a 100% basis, with 8 million tons attributable to our 57% share, and FOB costs were $57 a ton during the quarter, with the full year at $63. At Yilgarn Hub, we shipped 2.5 million tons in total, which was another solid quarter. That brought shipments for the full year to just shy of 10 million tons, at 9.7 million tons. FOB costs came in at $76 a ton, at the low end of guidance. As we announced separately, during the quarter we closed the sale of Yilgarn to an unrelated third party, which was a positive result for the group and for the state of WA. Turning to lithium, I think this quarter again underlined the quality of the two assets at Wodgina and Mount Marion. We have kept working to introduce flexibility into the operations wherever possible. The average realized price across both sites was $642 per dry metric ton on an SC6 equivalent basis. Mount Marion's figures were affected because shipments were weighted heavily toward June in the quarter, and a discount also applies to it for the lower grade portion of its tons.

Mark Wilson

executive
#11

Average pricing came in roughly 8% under the average indices. On lithium prices — and I know you'll likely have a few questions for me on this — the market has moved around quite a bit. In early June, prices returned to around $600, just above $600. After that, we saw a strong rebound to between $800 and $900. On spod production, Mount Marion and Wodgina produced 145,000 tons and shipped 135,000, and our relationship with both JV partners, Eldon Island Game, remains very, very positive. Looking specifically at Mount Marion, FY 2025 shipments reached 203,000 tons on an SC6 equivalent basis, which came in above the top end of guidance. Full-year costs, again on an SC6 basis, with FOB costs, stood at $900. June quarter FOB costs, though, came to $717, which is consistent with the previous quarter and reflects the advantage of high feed along with ongoing plant enhancements. I can go into more detail on this during questions, but we've worked to add greater flexibility to operations at Mount Marion, keeping in mind that it is a DMS operation. What we're aiming to do — and you'd have seen this in the quarterly results — is target higher grades and concentrate on recovery rather than purely on volume.

Mark Wilson

executive
#12

Depending on which of those flexible options we pursue, there is potential for a modest cost increase next year—or in this new year, rather—but we'll get into that a bit later on. As I mentioned, further guidance will come with the full-year result, though we're very, very pleased with how Mount Marion is developing. Among the opportunities we see for the new year is continuing to pull the third strip out of it. Turning to Wodgina, another fantastic performance: production up 32%, better quality feed. We've spoken about how important that feed is for some time, and about the direct link through to recoveries; costs on an SC6 FOB basis fell to $641 at Wodgina, a significant reduction over the course of the year. That reflects continued laser focus on cost management and continued improved recoveries. In the quarterly we discussed some of the changes being made to the plant that will give us a little more flexibility again in operation, and we expect recovery rates to tip up above 65% through FY 2026. Just to give you a little background on the costs, we're right through stage two now in terms of the ore body development there.

Mark Wilson

executive
#13

That ore body has improved the further down we go through that stage. In FY 2026, we're only beginning to open up stage three, and at the top we tend to see a few more stringers and narrower veins, after which we expect quality to improve with depth. Keep that in mind when thinking about costs for next year. As before, we'll give explicit guidance in the result a month from now. Finishing with energy, just a day or so ago we received independent certification for Moriari Deep, which came in at 27 Bcf on a 2C contingent resource basis — just under the minimum threshold required for a contingent payment on that asset. Lockyer 6 has no minimum threshold in its arrangement. It is going through the same certification process, and we expect to know the outcome this quarter. To sum up, we're very pleased with the quarter, both on operations and on the continued performance of Onslow, on setting up the business as we move into FY 2026, and on integration with the new board and chair. The business is set up very well going into 26. There's great energy in the business and a very strong focus on continuing to take it forward and strengthen it up.

Mark Wilson

executive
#14

Given all that—and aware I've been speaking for a while—I'll turn it back over now for questions. Thank you.

Chris Chong

executive
#15

Thanks, Mark. If you haven’t sent in your written question yet or gotten into the live audio queue, please do that at this point. I’ll give each caller’s name as I bring them on and then ask you to proceed. Once you do, a beep will sound to let you know your mic is live. Today’s first caller is Paul Young. Please go ahead.

Paul Young

analyst
#16

Morning to Mark, Chris, and Mel—hope all of you are doing well, and thanks for being here. Mark, my first question concerns liquidity as we look at the December half, and I realize you've drawn part of the revolver and are currently working through the budgeting process for next year. When you look at your internal model right now, do you need to pull any additional amount from that revolver during the December half, and are you considering re-firing the $1.3 billion senior secured potentially early? I'm just trying to get a handle on how you're viewing liquidity in the December half. That's my first question. Thanks.

Mark Wilson

executive
#17

Yeah, hi, Paul. Thanks, and thanks for joining. So how I look at it is this. The first and third quarters of every quarter tend to be the tightest, since that's when we face fairly substantial royalty payments. In this new financial year, we've also got CapEx weighted toward the front end as we work to finish the road, and we make some milestone payments on transshippers and the like. We've also had a carryover payment from the acquisition of Iron Valley. There's a bit of cash moving around this current quarter. If we do another draw, it'll only be for a fairly short period. What I really want to emphasize is that it's a revolving credit facility. It exists for working capital purposes. We pay to keep it available so we can draw on it when needed, and then we pay it back when we don't need it. That's part of it. Bigger picture, I'm very comfortable with the liquidity position. I feel like the business is in good shape. Onslow is starting to generate a fair bit of cash, and we're coming to the tail end of that CapEx profile. We've got a pretty good grip on what the outflows will be over the next six months.

Paul Young

analyst
#18

Thanks, Mark. Regarding that $1.3 billion refinancing?

Mark Wilson

executive
#19

Apologies—regarding the $1.3 billion, are you referring to the $700 million in the U.S.? Do you mean the bonds, or something else?

Paul Young

analyst
#20

Yeah, the senior secured comes due in May 2027 — that's correct. Exactly right.

Mark Wilson

executive
#21

Correct, it’s unsecured. Right — US$700 million. There’s a bond of ours, US$700 million, maturing in May 2027. On that front, we’re in good shape. What I mean is, when I talked on the quarterly call three months back, that was a few weeks after Liberation Day. The world looked very different then. Global uncertainty was high, spreads had widened, and markets generally were pricing in considerable risk and uncertainty. Looking at where those bonds trade now, they’ve likely tightened by 400 bps or more. Support from our bond investors in the U.S. remains really strong. Right now we’re in a period where nothing can be done with it. A fresh set of financials is needed, and we’ll have those at the end of August. Barring any significant change, you could assume we’ll be targeting something like that this half.

Paul Young

analyst
#22

All right, that's helpful to hear. Thanks, Mark.

Mark Wilson

executive
#23

Apologies, Paul—one last point on that. Honestly, I don’t perceive any execution risk there at all. Like I’ve mentioned previously, it turns into a matter of price in order to clear it, yet I see no execution risk when it comes to extending that maturity.

Paul Young

analyst
#24

Okay, got it. Thanks, Mark. Perhaps turning to Onslow — a solid update today, and largely consistent with what we observed a couple of months back during the site visit. I'm curious about your remarks regarding some hedging, since we're hearing there's been a fair amount of producer hedging on this rise in the iron ore price as well. You're among the companies that have done so. I'm wondering whether you could walk through the volumes you've hedged, the pricing, and just how that works and how we should think about it. Also, just on your realized pricing for Onslow, which declined quite a bit, given that I know on the visit the team was talking up realized pricing. I'm wondering if there's anything connected to that regarding the unwind of the prepayments. Thanks.

Mark Wilson

executive
#25

Right, so prepayment isn’t affected. Those sales were made during a stretch in that quarter when the iron ore market was very soft. In past instances, we’ve generally seen discounts behave that way once the price begins heading back up toward $90. On hedging, yes, I examined that curve. It was nearly flat all the way to January, which was pretty remarkable. In any case, what we’ve done is put on a series of zero-cost collars that typically establish a floor near $99 to $100. We won’t exceed one-third of production for the half. We’re simply attempting to strike the right balance, but we’re taking the chance to secure some of that downside.

Chris Chong

executive
#26

Thanks. Our following question comes from Glyn Lawcock. Go right ahead.

Glyn Lawcock

analyst
#27

Hi, Mark. Good morning. I’ve just got a couple of quick questions. I’m trying to sort out what you meant when you said there’s CapEx to spend on the transshippers, but then you also mentioned $150 million of asset financing, which was also for the transshippers. What separates those two spends? Thanks.

Mark Wilson

executive
#28

Morning, Glyn. Good to speak with you. My aim was to highlight the significant spend items on the horizon for this year, simply to give you advance notice. What I'm saying is — and this is also the first time I'm saying it — when we consider FY 2026, we're thinking along the lines of roughly $150 million of asset finance generally across that period. That isn't solely transshippers. It takes in items such as the remainder of the haul truck fleet, the jumbo road trains, plus some yellow gear and mobile gear as older assets come off and we bring on new ones throughout the year.

Glyn Lawcock

analyst
#29

Yeah, sorry about that, Mark. I think I may have phrased that poorly. I was simply trying to reason that if we're putting CapEx toward the transshippers, then why are we doing asset financing too? Why? It feels to me like I'm counting the same thing twice. Is there something obvious that I'm overlooking?

Mark Wilson

executive
#30

Right, Glyn, in the past we discussed CapEx on a net basis and reported it net. What I'm aiming to do today is provide a view of both net and gross, and in some cases show how we plan to use the asset finance. We can walk you through the details offline if you'd like, but my goal is to give you both of those pieces of information so there's a bit more transparency.

Glyn Lawcock

analyst
#31

No, that's great. Just one last question. You made a comment that you — I couldn't keep up with you, but I believe you said 27 Bcf on the first expiration for energy, which came in under the contingent payment levels. You said Lockyer 6 certification should occur this quarter, but there's no contingent payment level for that one. What's the best-case scenario you think, out of the $300 million-odd that we could receive? Any thoughts on what we could get this half?

Mark Wilson

executive
#32

Sorry if I was speaking fast. I ought to have gone a bit slower. The target is out of Lockyer, and the maximum we could achieve is roughly 100.

Chris Chong

executive
#33

Lachlan Shaw has the next question. Go right ahead.

Lachlan Shaw

analyst
#34

Morning, Mark, Chris, and Mel — appreciate you making time and thanks for fielding my question. I've got two. To begin with Onslow: it's clearly encouraging to see the guidance for FY 2026. Could you give some sense of how you plan to build toward that quarterly figure — you know, above 35 million tons on an annualized run rate — so as to lock in the following $200 million from MSIP? I'll follow up with my second one.

Mark Wilson

executive
#35

Absolutely. Good morning. Regarding how we view this year, and to address your question directly, it's clear that during the quarter we're currently in, the road's completion is going to affect us. That creates inefficiencies when it comes to movements and similar matters. Some of our contractor vehicles are less efficient moving through the port on the load side and, you know, the load out of the mine. We've factored all of that in. This quarter is going to be softer than the others. Obviously, weather affects us in Q2 and Q3. That happens every year, as we've discussed on a number of occasions. We would expect a pretty clear Q4. As for your specific question about targeting the three months and the 200, I think the best way to frame it is this. We can't plan around the weather. We can't control the weather. It'll be what it'll be. What we can do is develop plans to sprint and to flex. We have a little bit of capacity within the system to do that despite the constraints we're dealing with this quarter. I should have mentioned in my comments that July production is going to be a little bit softer.

Mark Wilson

executive
#36

The reason is that during July, while the road upgrade was underway, we used that window to concentrate mainly on maintenance — both at the plant and with the transshippers. We've been completing all of the maintenance work and getting everything tidied up. That gives us a chance to begin pushing hard on production over roughly the coming month.

Lachlan Shaw

analyst
#37

Thanks. Just to build on that point about sprint capacity — we aren't referring to transshippers six and seven over the next 12 months. What we mean is simply pinpointing bottlenecks, or finding extra sprint capacity, within what already exists today.

Mark Wilson

executive
#38

Yes, I ought to have phrased that better — my apologies. We do have sprint capacity at various points along the chain, but especially given the haulage constraints, we've secured some temporary storage nearer the mine, close to the truck maintenance facility at Yarry, and that affords us somewhat greater flexibility in how we move tons through the system while the road upgrade is underway.

Lachlan Shaw

analyst
#39

Alright, great, thanks. For my second question, on the mining services margin — yes, it's near the upper end of guidance, but you noted that it's been affected, with some drag coming from the contractor trucks. Could you give us a sense of, as those trucks demobilize during the December half, what kind of uplift you might be able to capture in the mining services margins? Thanks, Mark.

Mark Wilson

executive
#40

I'd rather wait until we report our results in a month before talking about mining services margins. That figure has typically sat at roughly $2. A lot of things have hit it, as you've pointed out — many impacts and many factors over recent months, the contractor vehicles among them. Onslow is part of the mining services business, along with plenty of other elements, and plenty of other factors will shape where those margins land going forward. I realize I'm hedging here. This isn't the answer you're after, but I'd prefer to keep my comments on margin guidance under wraps until the end of August.

Chris Chong

executive
#41

Rahul Anand is next in the queue, and his line is now open.

Rahul Anand

analyst
#42

Morning, team — thanks for hosting the call. My first question concerns Wodgina, and quite a few people on the debt side have raised it. By my calculations, recovery this year sits at roughly 55%, though I realize you don't disclose that figure. You've mentioned the HICs arriving and possibly pushing it up to 65% in the following year. That's a substantial increase. How much time does it typically take for these things to ramp up correctly, be optimized, and reach that 65% mark? And when do you actually anticipate that the full effect would show up in the cost base? That's my first one — I'll return with the second.

Mark Wilson

executive
#43

Morning, Rahul. Good to speak with you. In my remarks I mentioned bringing flexibility into how we run things, and adding those HICS cyclones has already made a big difference. As the market is aware, we have three trains built at Wodgina. We've been operating two trains, and at times three, depending on the situation. We've managed to finish installing the HICS on one train, so we now have fairly solid evidence of how it has affected that train's performance and the recoveries. We expect to have the third and last cyclone in place by mid-August. For the vast majority of the year, we should see the benefit of those higher recoveries. As I said, the data and the numbers we're citing here aren't estimates. We've actually watched it running day to day.

Rahul Anand

analyst
#44

Alright, that makes sense. My second question builds a little on what Loki asked, and I had planned to ask about the mining services margin, so I’ll adjust it slightly. In June, you were close to the upper end of your guidance for next year at Onslow, correct? Of course, there will be maintenance and other factors, and you’re using contractors right now. What I want to know is when do you expect MinRes’s fleet to be able to operate fully, at 100%, on the private haul road, with no contractors and no reliance on the public highway? The real reason I’m asking is that I want to understand when that contingent payment from Morgan Stanley Infrastructure Partners might be expected. Thank you.

Mark Wilson

executive
#45

Good question. Let me get ahead of what you were likely going to ask about mining services, since I probably didn't cover it completely. At the time we issued guidance of 210 to 220, there were a great many shifting variables involving contractor trucks, volumes, and what those contractors cost. We were bringing on more vehicles and more people, and continuing to do so. We formed a view back then, and we wanted to be certain we had it right. As the rest of the quarter played out, we managed to actually find some savings. On Onslow, the $200 million, the full run rate, and Morgan Stanley Infrastructure Partners — I should mention that our relationship with the team at Morgan Stanley Infrastructure Partners is fantastic. They have backed the business tremendously, and they are very eager for us to reach that threshold. Let me try to respond in a somewhat different way. We'll have a window to operate at hard before cyclone season begins. Whether that lands in November or December, you can assume we'll be pushing for it ahead of then. If for some reason we aren't able to get there, we'll get another chance to do so in, sorry, calendar year 2026, after the season wraps up around the end of March.

Mark Wilson

executive
#46

We can identify obvious opportunities to pursue. Let me try to put what I said before more plainly: although the road is a hurdle when it comes to reaching that milestone, it does not stop us from getting there. We simply need a few factors to break our way, among them making use of this sprint capacity while the upgrade work is under way. By the close of the quarter, we anticipate the contractors will be off the road.

Chris Chong

executive
#47

Lyndon Fagan has the next question. Go ahead, please.

Lyndon Fagan

analyst
#48

Much appreciated. I just had a question about whether there was any Onslow OpEx that got capitalized during the quarter.

Mark Wilson

executive
#49

Okay, so Lyndon, hi — what we’ve done is essentially apply the standard cost method, which we disclosed all the way through June 30, 2023. A small amount was capitalized, though not a lot. The actual costs line up fairly closely with what we reported. We’re seeing FOB costs decline.

Lyndon Fagan

analyst
#50

Great. When you look at that $1 billion of CapEx for next year, how much of it would you describe as being above staying-business CapEx?

Mark Wilson

executive
#51

My apologies — I didn’t catch that. Was that figure above sustaining CapEx? Is that what you were asking?

Lyndon Fagan

analyst
#52

I'm basically just trying to understand how much of that $1 billion is the ongoing, repeatable piece.

Mark Wilson

executive
#53

The caveat is that I still need to walk the new board through all of this and have everything finalized for guidance. As we look at it today—and obviously I have a basis for saying this, since I've put those comments out there—roughly $500 million of it is sustaining. The large share of that is to first bring it down to about $285 million. That's based on current mine plans, but those plans will be reworked several times between now and the end of next month, and that gives us a chance to try to take some tons out. One of the areas where we're looking to pull tons out is lithium, again, with Mount Marion in particular, and just trying to make sure we do that in a way that leaves us with the flexibility to operate into the future, which we will do.

Chris Chong

executive
#54

Kate McCutcheon has the next question — go right ahead.

Kate McCutcheon

analyst
#55

Morning Mark, thanks for taking the question. Consensus has iron ore sitting under that $100 per tonne mark you mentioned, and I believe MinRes has secured a floor price through hedging. So when we model those revenues, could you give us some color on the volumes involved and how long that floor lasts on those hedges?

Mark Wilson

executive
#56

Yes, Kate — apologies, the volume is slightly low on my end, but I can hear your question clearly enough. On the hedging side, what we've done is essentially establish a floor beneath realized prices for this half. If you look at this half, we've layered positions across various maturities from now through the end of the calendar year, with differing volumes. The core idea is to set a floor somewhere between $99 and $100, depending on the zero-cost collar. As for the actual share of volume, our target is to reach a third, though we haven't gotten there yet — it will be below that. Should prices recover, we'll lock in additional volumes. Right now, that would amount to somewhere between 1 and 1.5 million tons at roughly that price level.

Kate McCutcheon

analyst
#57

Great, that clears that up for me. Regarding the May 2027 bonds, my assumption is that the refinancing window falls in September. Could you share anything about the rate we might anticipate for refinancing those, given what we know today, or any collar surrounding it?

Mark Wilson

executive
#58

That window is essentially open for 135 days from year-end, provided you have updated financials. It kicks off around the end of August and carries us through to mid-November. After that, it reopens at the end of February next year, when our next set of financials comes out. Going outside that window is possible, though it gets somewhat more involved. On rates and similar matters, my suggestion would be to look at how the bonds are currently priced. Every one of them is trading above par, and they're trading fairly tightly. Broadly speaking, when you head to the market, you're in effect issuing a new bond in this instance to retire the old one. It would be reasonable to anticipate paying a modest premium for new issuance. If we take a step back for a moment — and this is something we've discussed for some time — the credit markets have stood behind MinRes throughout a stretch of major capital investment and project development. They recognize that Onslow's purpose is to reshape the business for decades ahead, with higher-quality earnings. As the market begins to absorb today's news, along with our confidence about the path forward and the strength of performance through June, my hope is that — assuming the external market cooperates — rates will keep tightening.

Mark Wilson

executive
#59

If you asked me what that cost would be at present, it'd likely land around 8.5%, though it might come in tighter.

Chris Chong

executive
#60

Matthew Frydman has the next question, so please proceed.

Matthew Frydman

analyst
#61

Absolutely, thanks. Good morning, Mark, Chris, and Mel. Could I pose one more question regarding mining services? Clearly, there has been some discussion about the margins there. You highlighted robust external volume growth during the quarter. Would you be able to elaborate on that a little, Mark? Perhaps offer a bit more background on whether that stems from contracts already in place or from new ones, and I suppose whether those chances for volume growth carry over into FY 2026. Thanks.

Mark Wilson

executive
#62

Morning, Matt. This business is the crown jewel. It just keeps delivering very strongly. How I'd frame it — and I mentioned this in one of my earlier answers — is that there are now many moving parts here: various projects, various contracts, various clients. The simplest way to look at it is that our market positioning is still extremely strong. Inquiry levels are still extremely strong. Awareness of the services we offer keeps rising year after year. We hold a distinctive set of capabilities that the markets value. Client performance during this year has been very strong when it comes to delivery. Clients have been able to supply us the feed into the assets. We've been able to process it. It's been strong across every one of those contracts, which is the first time in my experience that all of them have performed that way. In the past, a few have fluctuated. What I meant there was consistency. Looking ahead, we haven't given guidance on tons for 2026. We're still working through that. Partly, that's because a portion of the tons that feed into the guidance are tied to deferred strip and similar items.

Mark Wilson

executive
#63

We're adjusting our mine plans as we go. From certain operations, we could take out a fair number of tons. Take the Pilbara — in 2026, deferred strip will be lower there. Marion will also have less deferred strip than we had in 2025, and so on. I realize I'm not yet handing you a firm figure, but what I'm attempting to do is convey how I look at this and what the business opportunities are for that mining services operation.

Matthew Frydman

analyst
#64

Yes, that's clear. Thank you, Mark. Your remarks seem to imply that, from an external contract standpoint at least, you remain positive about volume growth in that segment. Then, secondly, may I ask about how Wodgina performed during the quarter? You have already discussed the anticipated recovery gains ahead, and obviously production rose quite sharply in the quarter, which you tied to plant performance as well as feed quality. Regarding mine sequencing and the ore quality going into the plant, is that now a reasonably repeatable level of performance going forward? Is the mine better positioned when it comes to supplying higher-quality feed? And again, is that likely to be sustained over the coming quarters? Thanks.

Mark Wilson

executive
#65

Thanks for asking. Looking back 12 months, I found myself explaining to you and your peers that we had spotted a gap in how we understood the ore body. To try to firm up that understanding, we had needed to drill 90-odd additional holes. Earlier in my comments I believe I mentioned that we have now moved along nicely through stage two, and it is simply, you know, simply pure ore, and the plant is processing it extremely well. My point was that at Wodgina, we pass through various stages as development proceeds. In 2026, we will be drawing predominantly from stage three, which does not require us to open it up. It is there, but the upper levels will show some narrower veins, some risk of greater dilution, and so forth, simply during the early stages. What I am doing is moderating expectations that it will be one for one or simply drag right. Having said that, this plant and how it is recovering at present is configured extremely well, and it will perform extremely well in this new financial year.

Chris Chong

executive
#66

Rob Stein has the next question, so please go ahead.

Rob Stein

analyst
#67

Hey team, thanks for the update. Just a quick point on Wodgina, staying with the current theme: production came in higher than shipments. Was that a deliberate choice to hold back in order to pursue better pricing conditions, and should we expect that to lead to a working capital adjustment in the next quarter? I also need to follow up on CapEx and the balance sheet.

Mark Wilson

executive
#68

Sure — the way I’d put it is that when it comes to shipments and working capital at Wodgina, we essentially aim to schedule the vessels for when output is ready, when the stockpile is in place, and when the ore is on hand. At times things run late up there because of wharf access, and that can have a modest effect, though it isn’t significant. I don’t believe you should be building in any meaningful working capital swing at Wodgina across the coming quarter or six months.

Rob Stein

analyst
#69

Apologies, I just want to follow up on that. Looking at how the assets performed on cost, it came as a surprise on every front. How much of that was helped along by an increase in stripping and similar work? I also noticed that your CapEx figure came in ahead of expectations too. I'm simply trying to understand how much staying power some of those cost-reduction efforts have as we look toward the forecast ahead.

Mark Wilson

executive
#70

Yeah, that's a good question. The CapEx was really more about timing. Some strip factor came out of the forecast that we had expected to spend, but it was really a timing matter on a portion of the Onslow spend. Broadly speaking, when I think about cost performance, we've discussed that for roughly 12 months now, and as you know, we've removed plenty of heads from the business throughout. We've altered the rosters. We've cut back the dig fleets. We've resequenced. We've actually built even more sophistication into the mine planning through the technologies we're using, which give us improved insights and let us refine the planning faster. It's more iterative, and the results we're getting are excellent. That isn't to say we're kicking the can down the road and will have problems next year or the year after. I'm not saying that at all. What I'm saying is that we can pinpoint the best way to optimize ore extraction, and we're doing that alongside the focus on removing costs from the direct costs of the operations.

Mark Wilson

executive
#71

I've provided some guidance on how I'm viewing costs for Wodgina and Marion in the new year. I don't expect a return to the level of 12 months ago. I'm simply trying to encourage you not to just drag right — I'll use that phrase again, and I don't mean to be flippant about it, but hopefully I've given you a bit of a sense of how I'm thinking about it.

Chris Chong

executive
#72

Our following question comes from Ben Lyons. You have the floor.

Ben Lyons

analyst
#73

Thank you, and good morning to everyone. This is a similar topic to the one raised in the prior question, so if you would, Mark. Clearly you have offered a number of quite high-level remarks regarding the ways the business generally is reacting to weak lithium prices. I suppose, much like Rob's question, my sense is that once you alter the mine plans and push these assets to a higher grade by lowering the strip ratio, obviously at some later stage a period arrives when that stripping has to be made up. Could we attach some figures to the strip ratios you expect in fiscal 2026, say, or perhaps more broadly, when you anticipate the next significant cutbacks at each one of the assets? Thank you.

Mark Wilson

executive
#74

Morning, Ben. Good to speak with you. We'll be able to share that when we issue the complete guidance next month. Cost performance has several dimensions. Strip is only one of them, and recovery is another. I'd urge the market to consider how strongly those assets have done on recoveries, Wodgina in particular. We've now got that plant running really well, and that has made a significant difference to performance. On stripping more broadly, Marion is somewhat different, as you know, given the expectation that we'll move underground at some point down the road. We began that work. We paused it 12 months ago to preserve capital. We're very mindful that we need to be developing the mine so we can keep progressing underground at the right time, when the market permits. We've taken on board what you've asked, and we'll be sure to come back and address that via the year-end process with guidance.

Ben Lyons

analyst
#75

All right, thank you, Mark. I genuinely value that you disclosed the recoveries, and I hope that kind of disclosure keeps coming going forward. For my second question, perhaps this is just a housekeeping item regarding the accounts. Could you remind us what the outstanding balance is on the loan to RDG, and whether you anticipate recording some form of provision against that facility in the fiscal 2025 result? Then, secondly, I'd like some clarity on where the asset financing you mentioned will show up in the accounts — does it appear in investing cash flows or in financing cash flows? Thank you.

Mark Wilson

executive
#76

Ben, apologies — I did catch your first question, the one about the RDG loan balance and any potential accounting adjustments. Sorry, but you come through somewhat quietly on our side — likely an issue here rather than with you. Could you please say the second question again? I simply wasn't able to make it out. My apologies.

Ben Lyons

analyst
#77

Yeah, yeah, sure. About that asset financing you mentioned — I believe it came to roughly $400 million in fiscal 2025, plus another $150 million, if I heard you right, for fiscal 2026. Where should we expect that to appear in the accounts, please? Would it flow through investing cash flows or financing cash flows? I'd imagine there's an interest component tied to those facilities as well. Thanks.

Mark Wilson

executive
#78

Apologies, Ben. Regarding RDG, the answer lies with the RDG loan. You're able to review the accounts from December — those have been lodged. It might have risen slightly during the half, but that should give you a general idea. As for asset finance, that appears, as you know, on both sides — clearly on the asset side and also on the debt side. It is included in the gross debt figure.

Chris Chong

executive
#79

Mitch Ryan has the next question — go ahead, please.

Mitch Ryan

analyst
#80

Good morning, Mark and Tim. Mark, my apologies — I felt you didn't really address Ben's question. You discussed his balance sheet, but how does that show up in the cash flows?

Mark Wilson

executive
#81

My apologies — I didn't catch his question. It shows up in the cash flows within the financing component. You're able to see it in the financing line.

Mitch Ryan

analyst
#82

Alright, thank you. My question has to do with Kensborough and the strip ratio. At 0.5, it's clearly quite low. Are we beginning to see that? How should we think about it once Kaito Bore comes online? Will it go up? And does the strip ratio you're referring to count or leave out the clay ores that you're kind of stockpiling for the time when the Benny plant comes online?

Mark Wilson

executive
#83

Regarding the strip in general, that is among the characteristics of Kensborough which set it apart from the other iron ore operations in that region. It is low. We anticipate that will persist for a while. I don't expect the satellite deposits. Roughly one third of Kensborough's production will come from the satellite deposits. I don't expect activity at Upper Cane and Kaito Bore to have a material effect on that figure. As for the clay, I honestly don't have the answer to that. My assumption is that it has all been factored in, but we can take that offline and get back to you with confirmation.

Mitch Ryan

analyst
#84

Thanks for being with us this morning — we appreciate it.

Mark Wilson

executive
#85

Appreciate it.

Chris Chong

executive
#86

We’ll take the next question from Jon Sharp, and please make sure to speak loudly enough. Thank you.

Jonathan Sharp

analyst
#87

Morning, Mark and the team. I've just got one question. At Onslow, production appears to be moving along nicely, but the bigger risk constraint there has always been logistics — there's a chance of getting stockpile bound if haulage or portage is delayed. Based on my rough estimates, you're holding roughly 2 million tons in stockpile throughout the system, and please correct me if that's off. On capacities, my figures are about 1.5 million tons at the mine, 350,000 to 400,000 tons at the Yilgarn hub, and then 200,000 tons at the port. Again, correct me if I'm wrong there, but could you just tell us how this is being managed and whether it's managed fairly tightly, please?

Mark Wilson

executive
#88

That's a good question. You've basically captured the main idea, right? That shed at the port does contain the 200,000, and Yarry can handle as much as roughly 400,000. Right now it doesn't hold 400,000, but it could reach that kind of volume, and that's among the options available to us when it comes to sprint capacity and similar matters. As for how we handle it, in the end we simply reduce the crushing rate when necessary, and mining as well. Of course, there's an efficiency factor there that we have to keep in mind. That flexibility exists for us since we're integrated throughout the whole chain. Yes, that's how we manage it at the front end.

Jonathan Sharp

analyst
#89

All right, thanks — I'll stop here.

Chris Chong

executive
#90

Thanks. We’ll take the next question from Kaan Peker. Kaan, please go ahead.

Kaan Peker

analyst
#91

Hey Mark, Mel, and Chris. I’ve got one question about FY 2026 CapEx, and it picks up on what Glyn asked earlier. On that $1 billion, are we talking gross or net? Is the $150 million of asset financing included in it? How much do you expect will go toward the lithium business? And does that figure include a flight plant at Mount Marion? We’ll come back with a second one.

Mark Wilson

executive
#92

Hey Kan, so the figure I gave was a net figure. As far as lithium goes, we haven't included a flotation plant at Mount Marion in what we're spending for FY 2026. That said, it's something we keep watching.

Kaan Peker

analyst
#93

Sure. Thanks. As for the second question, could you perhaps indicate how many kilometers of the haul road have been upgraded? From what I remember at site, it was roughly 60 at the end of May. Do you happen to have that figure off the top of your head?

Mark Wilson

executive
#94

My recollection is that the document cites roughly 60%, which works out to around 90K. I can't give you the exact figure in kilometers offhand, KaaFn, but I'll track that down for you.

Kaan Peker

analyst
#95

Okay, that's great. Last thing—regarding the contractor haulage, could you give some indication, or an average cost per kilometer ton for that?

Mark Wilson

executive
#96

No, I can't. Sorry about that. I do know the pay levels in various areas of our business, but that specific figure isn't something I can give you. It's not a matter of refusing — I simply don't have it. My apologies. Once more, we can follow up with you on that outside this call.

Chris Chong

executive
#97

Thank you. That brings us to the end of today's call. We appreciate you spending your time with us, and have a wonderful day. If any follow-up questions come up, please get in touch with the MinRes team. You're welcome to disconnect now.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Mineral Resources Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Mineral Resources Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Mineral Resources Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.