Ladies and gentlemen, thank you for remaining on the line. Welcome to the Monadelphous 2020 Full Year Results Presentation. <<operator_script>> At this point, I will turn the conference over to today's first speaker, Ms. Kristy Glasgow. Thank you. You may proceed.

Kristy Glasgow

executive
#2

Good morning, all, and thanks for joining us for the investor and analyst briefing on the 2020 full year results. Here in Perth this morning, we have Monadelphous' Managing Director, Rob Velletri, along with Chief Financial Officer, Phil Trueman, presenting. You can find copies of today's presentation and the related materials on our website, monadelphous.com.au. During this presentation, the speakers will let you know when it's time to click through to the next slide. I'll now pass things over to our first presenter this morning, Mr. Rob Velletri, who will begin on Slide 2. Over to you, Rob.

Robert Velletri

executive
#3

Thank you, Kristy. Welcome, everybody, to the briefing on our full year results for 2020. Phil and I are going to take you through how we performed financially and operationally during the financial year that closed on 30 June 2020, and we'll give you some thoughts on what we see ahead. After that, we'll take whatever questions you may have. Turning to Slide 3, our performance summary: Monadelphous posted revenue of $1.65 billion for the year, an increase of 2.6% over the previous year. For the third year in a row, the Maintenance and Industrial Services division delivered record revenue, and it went past $1 billion for the first time in the company's history. That result shows how strong demand has been for shutdown and maintenance services right across the resources sector, especially during the first half of the financial year. Revenue in our Engineering Construction division came in at $615 million, with several large resource construction projects getting underway over the course of the year. Net profit after tax for the period reached $36.5 million, and earnings per share were $0.387. Profitability in the second half took a significant hit from the disruption that COVID-19 caused, and also from the disappointing levels of profitability we saw in the Water Infrastructure business. In early May, the company booked a provision of $14 million before tax to cover water project underperformance and the costs associated with restructuring the company's Water Infrastructure business.

Robert Velletri

executive
#4

The Board announced a final dividend of $0.13 per share, fully franked, which brings the total dividend for the year to $0.35 per share. Monadelphous, therefore, remains recognized as a leader in its market, having secured roughly $1.2 billion in new contracts and contract extensions since the start of the financial year, giving us a solid pipeline of work for 2021 and beyond. Several strategic acquisitions were completed over the year, broadening the range of services in the coal seam gas and rail sectors, as well as overseas in South America. Robust cash flow from operations during the second half of the year bolstered the company's balance sheet, and Phil will discuss this a little more later. After the year-end, Monadelphous was notified that Rio Tinto had lodged a Writ of Summons in the Supreme Court of WA against one of Monadelphous' wholly owned subsidiaries. That claim relates to a fire incident that took place at Rio Tinto's iron ore processing facility at Cape Lambert about 18 months ago, in January 2019. The writ has not been served. The company had been carrying out maintenance shutdown services before the fire began, and Rio Tinto has alleged that the company breached the maintenance contract, thereby causing the fire.

Robert Velletri

executive
#5

While the writ doesn't state a damages figure, Rio Tinto has told the company separately that it is claiming $493 million in loss and damage. That figure breaks down as $35 million in material damage costs tied to rebuilding the Sinter Fines processing facility, plus $458 million for a temporary operating solution and business interruption losses stemming from the alleged inability to process iron ore while reconstruction was underway. The company rejects Rio Tinto's allegations and claimed losses, which in its view have not been substantiated. In addition, the contract governing the work between Rio Tinto and the company includes exclusions and limitations of liability, and these will be relied upon in defending any claim. The company holds public liability insurance with a total limit of $150 million, providing cover for property damage, claims and associated losses. Monadelphous knows of no reason why the insurance policies would fail to respond and indemnify the company for any liability it may have to Rio Tinto. Together with its insurers and their legal representatives, the company plans to fully defend Rio Tinto's legal action. Monadelphous and its insurers continue working with Rio Tinto in pursuit of a satisfactory outcome in this matter.

Robert Velletri

executive
#6

Let's move to Slide 4. As we already communicated to the market, COVID-19 had a major impact on Monadelphous' operations and performance during the second half of the financial year. Steps taken to stop the virus from spreading led to delays, suspensions, deferrals and cutbacks in services across a wide range of the company's projects and work sites, along with a temporary postponement of potential new contract awards. Customers scaled back nonessential work and put off discretionary spending, while supply chain problems caused delays on several large construction projects. All up, we estimate that roughly 10% of Monadelphous' annual revenue has been pushed into later financial periods. With a smaller workload stemming from COVID-19, the company's workforce numbers at year-end were down about 20% compared with February 2020. Now to a slide covering how we responded to COVID-19. We have put in place a substantial number of proactive measures to secure our long-term sustainability and to safeguard the safety and well-being of our people and the communities where we operate. To date, that has included setting up a dedicated team to monitor and assess the situation and give guidance to the business. It has also included creating detailed health risk management protocols and putting alternate working arrangements in place.

Robert Velletri

executive
#7

Beyond that, we put in place a focused initiative to cut costs and safeguard cash, backed by the Board and the executive team, who agreed to pay reductions of as much as 30% over a 6-month span. As governments in certain areas of Australia have been gradually removing precautionary measures and demand from our customers has kept steadily improving, the business has experienced stabilization and a slow recovery across recent months. Naturally, we will keep watching the situation and adjust how we respond as needed. Turning to Slide 6 now. As I said earlier, revenue of $616 million was reported by our Engineering Construction division, consistent with the prior period, with certain projects facing delays in the second half because of COVID-19. New contracts and contract extensions totaling $640 million were secured by the division, including roughly $80 million after year-end. Throughout the year, work carried on across 2 major construction contracts at BHP's South Flank project tied to inflow and outflow infrastructure. Monadelphous also landed an additional multidisciplinary contract at South Flank with thyssenkrupp for on-site assembly of the largest ore handling stockyard machines in the world. Furthermore, Monadelphous was granted a major contract with Rio Tinto connected to the West Angelas Deposits C and D Project, with work starting during the period and anticipated to finish in 2021.

Robert Velletri

executive
#8

Construction also began on a significant contract at Albemarle's lithium hydroxide facility in Kemerton, Western Australia. Within the division's BHP iron ore panel agreement, 3 projects reached completion while another 4 were launched. As was announced yesterday, the company additionally landed a contract with BHP for the Port Availability Improvement Project, which involves brownfield modification work on ore handling plant and equipment at both the Nelson Point and Finucane Island facilities. Following 2 years on-site and a strong safety record, Monadelphous' work on Rio Tinto's Oyu Tolgoi project in Mongolia wrapped up in early 2020. That project remains strategically important to Monadelphous, and additional opportunities are anticipated to reach the market before long. Mondium, our EPC joint venture with Lycopodium, won a strategically significant $400 million contract from Rio Tinto for the Western Turner Syncline Phase 2 project — the biggest contract it has secured so far. The Mondium EPC delivery model covers full project development and direct execution, greatly lowering interface risks across the engineering, procurement and construction disciplines, and gives customers a more cost-effective solution. SinoStruct, our China-based fabrication business, delivered multiple fabrication packages for repeat clients as well as for several key Monadelphous and Mondium construction projects.

Robert Velletri

executive
#9

Then last but not least, our renewable energy joint venture, Zenviron, kept making its position in the renewable energy market stronger — it finished work on 4 large utility-scale wind farms and made substantial progress on another 2. On top of that, after year-end, Zenviron won another contract to deliver the Murra Warra Stage II Wind Farm in regional Victoria. Now let's turn to Maintenance and Industrial services. As you can see, robust demand for maintenance shutdown and sustaining capital services in the resources sector — again, especially during the first half of the financial year — helped the maintenance division deliver a record revenue result, rising 5.1% versus the prior year to $1.05 billion. The division brought in over $500 million in new contracts and contract extensions, including roughly $60 million after year-end. Among these was a major 5-year contract awarded at Rio Tinto's coastal iron ore operations in November 2019, covering mechanical and electrical fixed plant maintenance and shutdown services, plus a 3-year contract with Rio Tinto for maintenance services and minor projects on its Pilbara marine infrastructure in June 2020. The division was also reappointed for another 2 years to BHP's Iron Ore Site Engineering Panel, delivering multidisciplinary services at BHP's mine site and port operations in the Pilbara.

Robert Velletri

executive
#10

During the period, we kept growing what our maintenance services business offers, and in July 2019 we acquired iPipe Services. iPipe specializes in coal seam gas as well as pipeline maintenance and construction solutions, and we also set up a stand-alone industrial services team to deliver specialist services to our oil and gas customers. Through buying Harbinger Infrastructure's business and assets, we broadened our rail maintenance offering to the East Coast; that deal brought a 5-year contract with ARTC for rail maintenance services across its Hunter Valley rail network in New South Wales. Early in the period, the division also won a 3-year contract with Rio Tinto covering its rail network in the Pilbara. That contract additionally carries 2 further 3-year extension options. Lastly, the division took its geographical footprint overseas by acquiring Buildtek, a Chile-based contractor for maintenance and construction services. So we have entered the Chilean market via an established, well-recognized operator that holds strong relationships with major mining and energy customers and gives us a solid foundation for growth in Latin America. Turning now to Slide 8, which highlights all the work secured period to date.

Robert Velletri

executive
#11

Like I said before, we've secured roughly $1.2 billion since the start of the financial year. This slide lays out the locations and values of all those contracts — approximately $640 million in engineering construction contracts and more than $500 million in maintenance contracts. As you can see, the overwhelming majority of these sit within our core resources and energy markets, along with a few strategically significant contract wins in Chile. Moving to Slide 9, our safety performance. On the 7th of March, we shared, with deep sadness, that our teammate Haydyn Grubb had been fatally injured after a serious incident at our Kalgoorlie services facility. Since that incident, we've put in place a range of measures to understand what took place and have implemented actions aimed at preventing anything similar from happening again. Monadelphous continues to offer support to Haydyn's family, friends and colleagues, and Haydyn will remain long in our memory. Overall, our 12-month total recordable injury frequency rate improved by 7.5% to 3.72 incidents per million man-hours worked. Pleasingly, the Engineering Construction division delivered the strongest safety performance in its history, achieving 0 recordable injuries in its resources business across 12 consecutive months, spanning more than 3 million hours worked. Monadelphous remains committed to the principle of zero harm.

Robert Velletri

executive
#12

And in support of that commitment, during the period the company carried out a detailed assessment of how it governs safety, which included reviewing its minimum standards for controlling fatal risks and further strengthening our health and safety management standards. Now moving to Slide 10, people. We saw strong demand for personnel in the resources sector early — certainly early in the period — and we continue to roll out a number of strategic sourcing initiatives. We reviewed succession planning right across our business to make sure we have the critical skills and capabilities needed into the future. As I said earlier, our people numbers took a hit from COVID-19. By year-end, total workforce numbers stood at 5,689, roughly 6% lower than June 30, 2019. Looking ahead, we see our retention and attraction initiatives growing more important as the labor market tightens across the resources sector, particularly with border restrictions still in play. Slide 11 highlights what we contribute to society and to the communities where we operate. Our social value activities center on 4 strategically important areas: diversity, community, education and environment. To support gender diversity and inclusion, we concentrated on boosting female participation, including identifying job and development opportunities.

Robert Velletri

executive
#13

I'm pleased to share that women accounted for nearly 40% of all appointments in our 2020 Apprenticeship Program, and close to 25% of those brought into our 2020 Graduate Program intake. On top of that, more than 20% of the participants in our main leadership development program across the period were female employees. Thanks to our dedication to diversity, we reached and have kept up our stretch target of 3% for Aboriginal and Torres Strait Islander employment. That was helped along by roughly 70 indigenous job seekers finding work through Monadelphous' involvement in the Australian government's Employment Parity Initiative. We've begun planning for our next stretch — our fourth stretch reconciliation action plan, along with a gender diversity and inclusion plan, both of which are set to launch in 2021. Over the course of the year, key stakeholders are being engaged to help shape these important plans. Lastly, we keep actively looking for ways to connect with and take part in the local communities where we operate. During the year, we put together dedicated engagement plans for strategic regional locations, and that resulted in Monadelphous backing over 50 community initiatives, among them support for the victims of the Australian bushfires earlier in the year. I'll now pass things to Phil, who'll walk you through our financial performance in a bit more detail.

Philip Trueman

executive
#14

Thanks, Rob, and hello everyone. On slide 12 you can see how our financial results stack up against last year's. As Rob said, revenue came in at $1.65 billion for the year. EBITDA was $92 million, and earnings in the second half took a significant hit from both the disruption COVID-19 caused and the disappointing profitability levels in the Water Infrastructure business that Rob referred to earlier. Net profit after tax for the period was $36.5 million, with earnings per share of $0.387. The Board declared a final dividend of $0.13 per share, fully franked, bringing the full year dividend to $0.35 a share and producing a dividend payout ratio above 90%. The Monadelphous Group Limited Dividend Reinvestment Plan will apply to that final dividend. Despite the challenging economic and operating conditions we've seen recently, the group's balance sheet got stronger over the year, and we finished with a solid cash balance of $208 million. Disciplined and prudent financial management gave us strong cash flow from operations of $119 million, a cash flow conversion rate of 151%. Our balance sheet is still very healthy and gives us substantial capacity to invest in suitable new business opportunities as they come along.

Philip Trueman

executive
#15

And now I’ll turn things back over to Rob, who will give you a rundown of what the outlook looks like for the business.

Robert Velletri

executive
#16

Thanks, Phil. On Slide 13, you can see the current and forecast conditions in the Australian market that matter to our business. As is clear, essentially every sector — resources, energy and infrastructure, or our infrastructure sectors and maintenance — is anticipated to get better or hold steady in the years ahead. Turning to our outlook slide, Slide 14: although the worldwide economic picture in the aftermath of COVID-19 is still uncertain, over the years to come the resources sector should deliver a consistent stream of opportunities for Monadelphous. Demand from China and the robust iron ore price are ramping back up strongly. Australian iron ore investment continues to look solid. A number of Chilean copper projects that had been suspended or deferred because of the COVID-19 outbreak are resuming, and they should give the company opportunities to expand its position in the South American market. Because global demand for oil and gas has declined, new LNG project development has been delayed, and in the short term customers are cutting operating costs and putting off nonessential work. Renewable projects look positive over the long term. For now, though, investment in that sector has eased while the industry concentrates on developing better grid access and transmission capacity.

Robert Velletri

executive
#17

We anticipate that maintenance work will bounce back gradually from the impact of COVID-19, especially within oil and gas. Over the longer run, we expect demand for maintenance services to rise, driven by aging assets and by customers having put off nonessential work in earlier periods. Monadelphous has now begun the new financial year with a strong forward workload. Even so, how well our business performs financially over the short to medium term will hinge on how far and how long COVID-19's effects last. Our standing as a leader in our markets, our enduring dedication to providing safe, reliable and cost competitive service solutions, and our fast, decisive reaction to the COVID-19 outbreak all mean we are well placed to seize the opportunities and to handle whatever challenges may lie ahead. To close, I want to thank our stakeholders for their continued support, among them our shareholders and customers. I would also like to praise our team, which has demonstrated tremendous understanding, resilience and loyalty through the COVID-19 pandemic. Even amid these uncertain times, our team has shown collectively that we deliver what we promise. That's everything from me. Thank you. I'll pass it to the operator for any questions.

Operator

operator
#18

<<operator_script>> The initial question will be asked by Alex Karpos of Goldman Sachs.

Alex Karpos

analyst
#19

I have just a couple of questions myself. First, regarding the maintenance outlook commentary: if you are sort of charting a recovery here, would you describe it as relying more on COVID restrictions being eased? Or you mentioned oil and gas and the improving oil price backdrop—is that really the main force behind this work picking up? Or what swing factors, I suppose, ought we to keep an eye on for that recovery to accelerate?

Robert Velletri

executive
#20

Well, I think — yes, I believe the oil and gas situation ties into both of those. Obviously, the outlook for oil prices is placing strain on costs and so forth. So that is one driving factor. But certainly as well, a great deal of our work happens offshore, and the distancing requirements plus the challenges of rostering and keeping people safe from COVID-19 also play a part. So hopefully, in time, both of those things get better. More broadly, I suppose, yes, on the maintenance side, we took a big hit when COVID struck in March and April, and conditions are gradually improving. Beyond that, as these restrictions ease, what we're seeing is that probably the key restrictions around — or rather, travel restrictions and border closures are having more of an impact than anything else.

Alex Karpos

analyst
#21

Understood. And regarding water, could you perhaps provide a bit more detail about what exactly went wrong with those projects? And when it comes to closing the offices and consolidating, is that mostly finished by now?

Robert Velletri

executive
#22

Yeah. No, it's mostly finished. Look, I think that within the sector — we had a handful of projects once we'd sort of examined how profitable the business was. Back then, we were carrying out — we were taking a look at how long we'd been involved in this business. We found — we definitely did uncover some underperformance that, I suppose, forms part of a sort of wider strategy to try and raise the quality of our business. We've — well I suppose, we're scaling back on jobs we believe carry greater risk and trying to get better at picking work in that sector. But the restructure itself is pretty much complete.

Alex Karpos

analyst
#23

Great. One quick thing, circling back to oil and gas. Regarding the LNG project outlook, you brought up delays. Do you have any sense of how long those might last? We've heard about a year from other industry participants. What's your view on just how far out those delays might stretch?

Robert Velletri

executive
#24

No, I'm picking up the same thing you are. And no, I don't have anything further to add.

Operator

operator
#25

Michael Aspinall of Jefferies has our next question.

Michael Aspinall

analyst
#26

Rob and Phil, I have a couple of things from my side. First, just a couple of questions about the long-term oil and gas contracts in the maintenance business. The initial terms on those 3 — the INPEX, Shell and Woodside ones — begin to expire over the next few years. Are the options for the extra contract tenure exercisable and at the customer's sole discretion? I just want to get a handle on how that works.

Robert Velletri

executive
#27

Yeah. I mean, yeah, I'm fairly confident that's how it is, yeah.

Michael Aspinall

analyst
#28

All right. And have you spoken with customers about what that could look like? And what's your view of the offshore and onshore oil and gas maintenance market?

Robert Velletri

executive
#29

No. What I mean is, we have contracts that run for the long term. There isn't really anything — sure, there's clearly cost pressure and so on, but when it comes to the need for the work itself, that need remains, and it will remain going forward. And when those contracts reach the point of renewal or their option periods, I think we simply follow the usual cost process as we renew or rebid that work.

Michael Aspinall

analyst
#30

Right. And over the past 3 or 4 years, have those contracts performed the way you'd have expected?

Robert Velletri

executive
#31

Yeah, that's about right. Yep. Yep.

Michael Aspinall

analyst
#32

Okay, and then a technical question about those. My assumption is that the unsatisfied performance obligations you disclosed don't include the extension options. Is that correct?

Philip Trueman

executive
#33

No, they do not.

Michael Aspinall

analyst
#34

Alright. Great. And then just one more on that same point. I was hoping to get some clarity on how the work that falls under the panel agreements — things like the BHP West Australian Iron Ore panels and the Hunter Valley water panels — interacts with the unsatisfied performance obligations.

Philip Trueman

executive
#35

Regarding the construction portion of our operations, and those examples you mentioned, we count only the contracts that have been formally awarded to us.

Michael Aspinall

analyst
#36

So, okay — nothing about what might be coming up in the — under the panels?

Philip Trueman

executive
#37

No. We don't estimate what we think we'll receive or anything like that. It's simply the contracts we actually have in hand.

Michael Aspinall

analyst
#38

Alright, great. Then I've got 2 more. SinoStruct's Houston workshop shut down at the close of the financial year. How material is that revenue stream?

Robert Velletri

executive
#39

Nope, it's not material. No, not in the slightest.

Michael Aspinall

analyst
#40

And then the final question. Previously you told us that if work carried on at the same pace, revenue for this year would be flat. The actual result came in up around 50, and the employee count chart shows what looks like a gradual but steady rebound starting in April. How would you describe the pickup in activity we've seen since April? And do you have any remarks about July or August?

Robert Velletri

executive
#41

No. I'd say this is likely -- I mean, the ramp-up has been steady. Yes. Things are definitely continuing to get better.

Michael Aspinall

analyst
#42

And if that's the case, would that chart have a similar trajectory in July and August to what you put in the presentation?

Robert Velletri

executive
#43

Yes. Which chart are you referring to?

Michael Aspinall

analyst
#44

On Page 4, that chart of employee numbers by month, it looks like.

Robert Velletri

executive
#45

Page 4? Ah, that one. Yeah. Definitely, yes — possibly even better than that, in fact better than that.

Operator

operator
#46

The next question we have is from James Byrne at Citi.

James Byrne

analyst
#47

Let me just spend a moment on the maintenance segment. My sense is that some of your competitors are making a more deliberate push to gain share in maintenance. What I'd like to hear is how you see the competitive picture right now, and specifically whether new work margins are feeling any pressure at all. Maybe the segment's overall growth is big enough to absorb that without any effect on margin. Even so, a bit of color would be quite useful.

Robert Velletri

executive
#48

Yeah. Look, when it comes to the big Tier 1-type work, I'd say the competitive landscape is pretty — it really hasn't shifted all that much lately. I mean, everyone — it's an appealing sector for anyone who wants a piece of it. But as far as Tier 1s go, I wouldn't figure there are any additional ones beyond what there were or had been. Not really noticing a difference.

James Byrne

analyst
#49

All right, yes, right. I'll leave that one there, then. Regarding the Rio case — look, I'm not going to argue with you over whether you should deserve to win or lose it. But I suppose, thinking about the downside risk here, how do you believe the balance sheet is positioned to handle paying out those damages? And if you did have to do that and draw down your liquidity, how would that affect the capital allocation opportunities you would otherwise have pursued?

Philip Trueman

executive
#50

Everyone is familiar with the specifics of the claim, and Rob provided a solid recap of the situation and our current standing earlier. In response to your question, frankly, there's a process we need to work through here. And honestly, we haven't really looked that far ahead when it comes to answering your question. Yes, we — just as a reminder to everyone, we have — Rio asked us to keep talking with them, and over the past fortnight we've held quite a few discussions with them, and we're still meeting with them regularly to work through this matter together.

James Byrne

analyst
#51

So, from what I'm hearing, it sounds like that will likely get resolved. Would you say that's a fair way to put it?

Philip Trueman

executive
#52

Yeah, I believe the announcement speaks for itself — it lays out where we stand on this.

James Byrne

analyst
#53

All right, that's fine. I won't push you further on that one, then. So my final question is this: I'd like to understand how a higher iron ore price might or might not be helping you as a contractor. I suppose some of the pushback I hear from you and your peers is, why wouldn't I simply put money into the underlying commodity grid producer rather than take on the contractor's risk? So I'm keen to understand whether, in iron ore specifically, you're seeing additional add-ons to existing contracts that are contributing to your revenue at all. And whether you believe that the higher commodity price could actually result in any material increase in CapEx and, as a result, contract opportunities for you?

Robert Velletri

executive
#54

Yeah. I'm not really sure that the absolute iron ore price matters all that much, honestly — I mean, even at whatever the lower levels are, the Australian sector is extremely competitive. And I think the strength we're seeing in iron ore when it comes to work volumes is tied very closely to the enormous production rate that has to be maintained. That just takes an awful lot of work. Setting aside expansions entirely, simply to hold whatever it is — 1 billion tons a year of production — you need a significant number of new mines, of mining-type developments, and mines that have to get built every year. There's just a great deal of work happening continuously. Most of it is sustaining capital.

James Byrne

analyst
#55

Right, but when commodity prices are elevated, I suppose the real question is this: a producer might feel a stronger incentive to add bells and whistles, and that effectively opens up greater revenue opportunities for you, whether through add-ons or new contracts.

Robert Velletri

executive
#56

Sure, possibly. That's not how I see it, though it could be.

Operator

operator
#57

Moving on, we have Matthew Nicholas of Crédit Suisse with the next question.

Matthew Nicholas

analyst
#58

I've only got a couple of questions. Many of mine have already been covered, but on the social distancing issues — especially in construction — could we get a sense of how that's affecting your construction business right now? And what does it mean for, say, delivery of Western Turner Syncline? And how should we expect that to be sequenced over the next 18 to 24 months?

Robert Velletri

executive
#59

Right. I believe over the past few months, the restrictions in WA have eased. There hasn't been any community transmission there for quite a while. So at first, rosters were adjusted to fit the COVID-related restrictions, but everything has returned to normal at this point. Therefore, at present there's no meaningful effect on productivity — at least in WA.

Matthew Nicholas

analyst
#60

Okay, and one more general follow-up. You clearly mentioned that the iron ore market is strong right now. And as you said, much of what's out there is quite independent of the iron ore price. It has to happen. But I think what's taken place over the last 4 or 5 months has pushed a few things out to the right. Can we get a sense of your upcoming key opportunities, both here and also you mentioned Chile there. Is that more of a new type of thing? Or is that something we should be looking for in '21?

Robert Velletri

executive
#61

My apologies — I’m not sure I caught what you were asking.

Matthew Nicholas

analyst
#62

I’d say it’s really about the pipeline and which opportunities exist, first in Australia and then in Chile. As for the Chilean side of things, would you view that as more of a 2021 item?

Robert Velletri

executive
#63

No. Yeah, the Chile situation is still at an early stage. It's very early. I think — but yeah, there's clearly opportunity in that country as time goes on, especially — I mean, every mine in Chile is a copper mine, and copper prices are strong and the outlook is strong too. And I think over the long term that gives us some confidence about the chance to expand there. And as for iron ore opportunities, without laying them out in detail, I don't know what the figure is, but there are a number of new mines that Rio has to develop and a long pipeline of sustaining capital optimization projects for BHP in the pipeline. Without getting specific, there's plenty there.

Matthew Nicholas

analyst
#64

Alright, and this will be my final question. One topic that hasn’t come up yet is margin, which I know is pretty much an endless topic for you folks. But if you look at the second half and set aside the fact that there’s a large impairment sitting in that figure, I mean, your first-half margin came in at just above 6.5% at the EBITDA level when AASB is excluded. Yes — as we move into a recovery over the near term, which you’ve already had, do you think margins might normalize at that level starting in the second half of this year? Or are you seeing competition and that sort of thing, such that the level you reached in the first half is probably somewhat further out in time?

Robert Velletri

executive
#65

Sure — we'd be glad to keep going at roughly that kind of level. And honestly, that's a tricky one to answer, since it really comes down to how effectively we execute on the construction contracts we already hold — that's the crucial piece, probably the single biggest driver. That said, I think the point about margin has more to do with the pipeline and the volume of work out there, which looks quite solid. And our competitive standing with clients in the market is very strong. I'd be let down if we weren't able to carry that forward going ahead.

Operator

operator
#66

Ben Brownette of CLSA has our next question.

Ben Brownette

analyst
#67

Phil, I just had a question about gross margin. If you wanted to strip out that loss you recorded — the $14 million loss — would you simply add $14 million to the gross profit figure for the second half in order to think through gross margin?

Philip Trueman

executive
#68

Yes.

Ben Brownette

analyst
#69

All right, so if I go that route, it was, let's say, 9.2% during the second half, compared with 10.4% before. I mean, that's clearly not awful. But what's really behind it? Is it simply revenue declining? Or is something else involved?

Philip Trueman

executive
#70

There are likely 2 factors here: I'd point to reduced activity during the final quarter of the fiscal year; and clearly, as Rob said before, our productivity took some hits because of social distancing measures and a whole range of other factors that hit specifically around March, April, May and probably stretched into June somewhat too.

Ben Brownette

analyst
#71

Right. And in our earlier discussion, you mentioned certain site delays and the need to absorb some overheads and that sort of thing. So those shouldn't happen again as we move forward. Then, regarding that roughly 10% gross margin you posted recently, is there any reason to think it ought to come in lower if you're cycling out of that weaker productivity in the fourth quarter?

Philip Trueman

executive
#72

It probably hinges somewhat on how fast things ramp up as we enter the new financial year, how soon we return to typical operating levels, and what those levels turn out to be. That said, as Rob said, project execution is the main driver of our gross margins.

Ben Brownette

analyst
#73

Right. And on that point — Rob, regarding how the project is being executed, I mean, looking at your WIP, it seems fairly solid. So I suppose there was always a concern that when things slow down, certain companies could start throwing in claims and scope changes. You haven't done that. In your view, is there really no chance to pursue some kind of scope adjustment because of the disruption?

Robert Velletri

executive
#74

Hard to say. I mean, when our contract terms permit us to submit whatever claims regarding changes, that's exactly what we do. So, I mean, nothing here is new, even though a portion of the claims will tie to shifts in legislation and restrictions put in place over that COVID stretch. So that element does exist when it comes to recovering — potentially recovering certain costs. But all of that is already reflected in our figures.

Operator

operator
#75

The next question we have is from John Purtell, who is with Macquarie Group.

John Purtell

analyst
#76

Okay, just a few questions, please. So, Rob, you brought up some of the opportunities with BHP and Rio going forward. Obviously, we've discussed Fortescue in the past too, regarding North Star and Robe Valley. Do you still see potential project opportunities there?

Robert Velletri

executive
#77

Yes. That's correct.

John Purtell

analyst
#78

And I guess the timing — notoriously, it does tend to kind of drift when it comes to these project awards. But do you have any indication on the timing for those kinds of awards? Is it sort of moving into the next calendar now?

Robert Velletri

executive
#79

No. Well, there isn’t — I think the Robe Valley work, I think someone issued an announcement regarding that. So that has been awarded. There’s still FMG work that hasn’t been awarded yet. I’m not sure — do we expect that within the next 6 months or so, something along those lines. And there are additional projects in the Rio Tinto area too. I was — perhaps I can speak about them or perhaps I can’t, but I can — there are some other mine developments coming up in the next year or 2.

John Purtell

analyst
#80

Just to get some clarity on your outlook remarks there. First, especially regarding maintenance. So basically, from what it sounds like, you expect the productivity effect to carry on through the first half of '21, and that's mainly tied to maintenance rather than construction?

Robert Velletri

executive
#81

Yeah, well, it comes down to volume — sort of a ramp-up, especially on the work — on our shutdown work, since that's where the impact has been greatest. So the ramp-up of that work really depends on how fast it comes back up again. And it is coming back up, by the way. It's just a matter of how long it takes to reach what, I suppose, what we set out to do. So — and at present, we're confident it will.

John Purtell

analyst
#82

Yes. Assuming that type of work is necessary, then it should be done.

Robert Velletri

executive
#83

Right, so yes — everyone is making plans for a great deal of work that they weren't doing previously. All of them are going to tackle it simultaneously, and we intend to have the staffing in place for that. Those are my anecdotes.

John Purtell

analyst
#84

Phil, a cash flow question for you: it really looks like a large receivables decrease in the second half was the main driver. What exactly caused that, Phil? And do you view that as a sustainable level, or does it go higher from here?

Philip Trueman

executive
#85

The softer activity we saw in the last quarter, I think, clearly resulted in some of our working capital coming back down. Believe me, holding it at that level would be great. That said, my expectation is that as activity picks up, you'll see working capital drawn on once more over the next half — that's what I'd suspect.

John Purtell

analyst
#86

Yes. And on just that last point — you might not be in a position to comment, but it ties back to the Rio claim as well. Can you give any kind of indication on the timing for a potential resolution?

Robert Velletri

executive
#87

Nope.

Philip Trueman

executive
#88

Nope.

Operator

operator
#89

Wei-Weng Chen from JPMorgan has our next question.

Wei-Weng Chen

analyst
#90

I have a couple of questions. First, I just wanted to reconcile what you said about a solid order book with the 20% reduction in staffing levels. Should we expect that you'll need to ramp up hiring quite aggressively in the near term? Or does the solid outlook refer to, I guess, your new staffing levels?

Robert Velletri

executive
#91

No — what we expect is that our work is going to ramp up. That is what we expect. So the numbers ought to rise. We've had quite a lot of — as we've said, 10% of our revenue from last year is being pushed into next year. And right now, most of the restrictions certainly apply to our work in WA; Queensland's have been lifted. So unless those come back again, which would be another matter, we expect — we hold a strong expectation that work levels and people requirements will go up — are increasing. We know that they are.

Wei-Weng Chen

analyst
#92

Alright, so a quick question about that 10% of revenue that's being deferred. Should we expect all of it to be deferred into the first half, or does it spread across the full year next year and then build up over a multiyear period?

Robert Velletri

executive
#93

Yeah. It's difficult to pin down, honestly, but I'd guess around 12 months, something along those lines.

Wei-Weng Chen

analyst
#94

All right, so turning to profitability and EBITDA margins — I realize someone already raised a question about the second half and what to expect for FY '21. If you adjust for those water losses, my assumption is they disappear in '21. And you're telling us COVID effects aren't hitting the business right now. So how should we frame margins going into '21 relative to, say, the first half? Do you still expect them to run directionally lower while you recover, or do you anticipate getting back to that margin level?

Robert Velletri

executive
#95

No idea. No idea. It ought to beat how things went in the latter six months of last year — that much is certain, and with luck it could match the opening six months. Right, nothing ought to be holding us back, that's the way I'd phrase it.

Wei-Weng Chen

analyst
#96

All right, but the water problems are finished, correct?

Robert Velletri

executive
#97

Yes. Yes. And any drag — sorry, I tend to always qualify that, like I always qualify those margin questions. Any drag is going to be a matter of roughly competitiveness in oil. Oil and gas customers will want to cut costs or find ways of reducing costs, et cetera, which may or may not impact margin. But they're probably the only drags. Otherwise, more broadly, activity should increase, which should be positive, but then it's a case of how well we perform.

Wei-Weng Chen

analyst
#98

Right, thanks. Turning to cash — clearly, the second half was an excellent result. You mentioned, I believe, the softer activity levels and that natural working capital release. Was there anything further worth highlighting? Did any cash perhaps get pulled forward that would otherwise have come in during the first half of '21?

Philip Trueman

executive
#99

No. The only other big item, really, would be that we made use of the concessions regarding when payments are due for some of our GST and a bit of payroll tax — probably in the range of about $10 million to $15 million. That's likely the sole thing deferred until September that normally would have been paid during the second half of this past financial year.

Operator

operator
#100

Nathan Reilly with UBS has our next question.

Nathan Reilly

analyst
#101

Just a quick question about the staff numbers. You shared in a chart that there were roughly 5,500 at the end of June. What's the figure now? Or what was it at the end of July?

Robert Velletri

executive
#102

Perhaps slightly improved, maybe. A touch better. I don't have the figure, though it is certainly rising.

Nathan Reilly

analyst
#103

Alright. And Rob, I suppose just returning to this claims matter — I'm not asking about that particular claim. I'm simply curious whether the character of this situation has in some way shifted how you view pricing your maintenance contracts from here on?

Robert Velletri

executive
#104

Nope, not really. No, it hasn’t.

Nathan Reilly

analyst
#105

And then, just following up on that point. I'm curious — are your maintenance customers, or customers across the industry more broadly, asking contractors to hold higher levels of insurance?

Robert Velletri

executive
#106

Nope, not truly. No. That isn’t something that plays a role.

Operator

operator
#107

Steven Anastasiou from Bell Potter has our last question.

Steven Anastasiou

analyst
#108

A lot of what I had has clearly already been covered since I'm the last one, but there are just a couple of items. On the oil and gas maintenance revenue, clearly, the second half took a hit. Even so, activity levels still appear to have been fairly healthy during that second half. So our view is that they will at minimum reach that same level once more in the first half of '20, and possibly go beyond what the second half showed?

Robert Velletri

executive
#109

I believe you're going to see a steady improvement, yes.

Steven Anastasiou

analyst
#110

Yeah. About the Buildtek staff shown on Page 10 of the slide — it appears the headcount was much lower by the close of FY '20. My guess is that operation may have been hit especially hard by COVID down in South America. Or...

Robert Velletri

executive
#111

Yeah, the effect there is significantly bigger than what we've seen in Australia.

Steven Anastasiou

analyst
#112

So does that shift any of your initial thinking, or the rationale for buying that business? Is the long-term and medium-term outlook still positive?

Robert Velletri

executive
#113

No, no, no. Yeah, it's still positive. Yes. Yes. Sorry — over the last few weeks, things have been getting better.

Steven Anastasiou

analyst
#114

Okay, this is the last one, and you may prefer not to address it, but regarding that legal claim, you said the contract contains certain exclusions and caps on liability. My assumption is that this could encompass items such as the consequential losses being sought?

Robert Velletri

executive
#115

Look, there’s no way for me to respond to that. That’s not something I can respond to. All right. Thanks.

Kristy Glasgow

executive
#116

Thanks for being with us today. That brings our briefing to a close.

Philip Trueman

executive
#117

Thanks.

Robert Velletri

executive
#118

Appreciate it, everyone. Cheers.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Monadelphous Group Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Monadelphous Group Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Monadelphous Group Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.