Monadelphous Group Limited (MND) Earnings Call Transcript & Summary

February 21, 2023

Australian Securities Exchange AU Industrials Construction and Engineering earnings 45 min

Earnings Call Speaker Segments

Operator

operator
#1

Hello, everyone. Thanks for being with us. You're listening to the Monadelphous 2023 half year results presentation. Right now, everyone is in listen-only mode. Once the presentation wraps up, we'll move into a question and answer session. If you'd like to ask something during that session, press star one one on your phone. Please note that this conference is being recorded today. I'll now turn things over to our first speaker, Kristy Glasgow. Thank you. Over to you.

Kristy Glasgow

executive
#2

Good day, and welcome to the Monadelphous 2023 half-year results briefing for investors and analysts. With us in Perth are Zoran Bebic, Monadelphous' Managing Director, and Philip Trueman, Chief Financial Officer. Our Chair, Rob Velletri, is also here in the room. Today's presentation follows the same format as earlier results briefings. First, Zoran and Phil will walk you through how the company performed during the half year that ended 31 December 2022, along with the outlook, and then they'll take whatever questions you have. Additional details appear in the appendices of the slide deck. You can find copies of today's presentation and the related materials on our website at monadelphous.com.au. During the presentation, the speakers will let you know when to click through to the next slide. I'll now hand things over to our first presenter, Mr. Zoran Bebic, who begins on Slide 2. Thanks, Zoran.

Zoran Bebic

executive
#3

Thank you, Kristy, and welcome everyone. Before we get into our 2023 half year results briefing, I wanted to take some time to acknowledge the passing of our former Chair, mentor, and great friend, John Rubino. Many of you would have had the pleasure of getting to know John at an investor briefing over the years or hearing from John at one of our annual general meetings. You will no doubt remember his thick Sicilian accent and his cracking sense of humor. I'm sure you will also remember him as an exceptional person with breathtaking business acumen and an ability to form long-term trusting and mutually beneficial relationships like no other. John was a born leader with enormous charisma. He had an ability to inspire people and was a mentor to many, including myself. We have included on this slide just a snippet of John's story. To have built one business into a powerhouse is a once in a lifetime achievement for many people. John Rubino was not just anyone. John succeeded in doing it twice with United Construction and Monadelphous. Under John's exceptional leadership, Monadelphous went from a company that was insolvent in the late eighties to an ASX 100 company, where people were proud to come to work, that suppliers had confidence in, and that customers knew and respected.

Zoran Bebic

executive
#4

While John was leading the company, Monadelphous was entrusted with building and maintaining some of Australia’s and the world’s biggest and most intricate projects and facilities. Although he has passed, his memory will remain forever in our hallways at Monadelphous and in the tales told by our staff. We will keep making you proud, John. Now on to the results for our half year. As Kristy said, Phil and I will walk you through the financial and operational performance for our 2023 half year, plus our outlook, and then we’ll take any questions. On Slide 4. Revenue for the first half came in at AUD 953 million, a decline of 10.5% versus the prior corresponding period. Our maintenance and industrial services division posted record half year revenue of AUD 677 million, an increase of 13.5%. That reflected robust demand for maintenance services throughout the resources and energy sectors, supported by favorable commodity prices, high production levels, and aging site infrastructure. As we had forecast, our engineering construction division saw lower activity because several significant construction projects wrapped up last financial year and because of when new projects were awarded and started.

Zoran Bebic

executive
#5

All told, revenue for the division came in at AUD 278 million, a decline of 42%. On a more recent note, our engineering construction division has been brought in for early contractor involvement across a range of projects, and tendering activity remains at high levels. For the half year, we achieved a better EBITDA margin of 6.1%, which felt especially good against today's environment of escalating costs. With shortages of skilled labor persisting, our attention stays on strategically choosing new work opportunities and lifting the quality of earnings. Net profit after tax reached AUD 29.1 million, producing earnings per share of AUD 0.305. An interim dividend of AUD 0.24 per share, fully franked, was declared by the board of directors. From 1 July 2022 onward, we have locked in roughly AUD 950 million of new contracts and contract extensions throughout our core markets. Our more recently developed relationship with Fortescue Metals Group keeps growing, with a number of new contracts awarded, among them a construction contract at the Iron Bridge Magnetite project and long-term services contracts covering their Pilbara operations. Several strategic contracts were also won, including one with Petrofac for decommissioning work on the Northern Endeavor floating production, storage, and offtake facility. That represents our first offshore decommissioning contract, and a rising number of similar opportunities should reach the market in the years ahead.

Zoran Bebic

executive
#6

Over the half, we carried out a strategic review of SinoStruct, the fabrication business we run in China, to make sure what it offers stays in line with what customers expect and that the business is structured appropriately to grow in its core markets, diversify its supply chain geographically and deliver in new sectors. After that review, we rebranded the business as Inteforge. Our heavy lifts business kept expanding its capability and customer base, and it was awarded its first contract in the infrastructure sector on the West Gate Tunnel Project in Melbourne, Victoria. I'll now discuss our new work on the contracts secured slide. Here you can see where our new work is located geographically and how much of it there is. This includes a significant amount of work in the Pilbara region of Western Australia, with approximately AUD 540 million of work secured in the iron ore sector with long-term customers such as BHP and Rio Tinto, as well as with Fortescue Metals. We have also been awarded a number of contracts in the expanding battery metal sector, including the lithium and copper markets. We keep seeing strong demand for our services overseas, including in Mongolia at the Oyu Tolgoi underground project and in Chile through Buildtek, our construction and maintenance services business.

Zoran Bebic

executive
#7

Turning to Slide 6 now — our safety results. Over the past 12 months, our total recordable injury frequency rate came in at 2.4 incidents per million hours worked, which is a 22% improvement. Thanks to our ongoing emphasis on spotting, removing and reducing fatal risk hazards, along with how we apply our fatal risk control standards, we saw a 45% drop in our serious incident frequency rate compared with this time last year. Our work in safety innovation earned recognition, and we were named the winner of two Industry Excellence awards. We also made headway on several safety technology trials — among them pedestrian monitoring and proximity sensors for mobile equipment, plus surveillance of vehicle driver fatigue and distraction. Beyond that, we remain focused on the physical and mental health of our people, launching our 2023 health and wellbeing program, which lets employees take part in tailored initiatives like mental health awareness training and physical health checks, among other things. Now on to Slide 7 — our people. We finished the half with a workforce of around 7,300 people, a slight decrease versus the prior corresponding period. Demand for maintenance services was strong, though lower construction activity offset that. The shortage of available talent, both now and as predicted going forward, is still a major challenge for our business and for the industry.

Zoran Bebic

executive
#8

Over that timeframe, we ran a survey across the whole company to help inform how we attract and retain people in 2023 and to soften the impact of the labor shortage. We introduced our Respect at Monadelphous program, aimed at embedding respectful conduct more deeply in our workplaces, following a significant body of work carried out in the prior financial year. To aid recruitment, we stepped up our international sourcing approach so that we are as well positioned as possible to satisfy our future resourcing needs, and we carried out a thorough review of our graduate program so we hold our standing as an employer of choice for people on early career pathways. Moving to Slide 8 now, sustainability. We stay dedicated to contributing positively to the communities where we work, concentrating on the core areas of diversity, community and environment. After Reconciliation Australia endorsed it, we launched our newest stretch reconciliation action plan. That makes it our fourth RAP and our second stretch RAP. It sets out our commitment to taking steps that advance reconciliation by giving Aboriginal and Torres Strait Islander peoples equal access to meaningful employment and development opportunities. Over the period, we brought in a new group of trainees to our Indigenous Pathways program, run in partnership with Rio Tinto, carried on our partnership with the Polly Farmer Foundation, and opened our Ngaangkrl Room, a new training facility located at our employee development center.

Zoran Bebic

executive
#9

In line with how we're dedicated to inclusion and gender diversity, we've moved forward on steps in our gender diversity and inclusion plan — that covers launching the Respect at Monadelphous framework, plus pushing for more women to join our sector via STEM events and through our partnership with the University of Western Australia's Girls in Engineering program. Consistent with our strategy aiming at net zero emissions by 2050, we advanced our roadmap for cutting emissions and energy, which sets out a set of interim targets on the way to that goal. Working groups, a number of them, were set up to back the strategy. Audits of energy use took place across every workshop facility, and several trials got underway, among them hybrid vehicles and solar powered equipment. Turning to operational highlights in engineering construction. As I noted, revenue of AUD 278 million was reported by our engineering construction division for the first half, and since the start of the period it has locked in roughly AUD 280 million in new work, among which are several early contractor involvement engagements. Multiple work packages for Rio Tinto were finished by us, among them construction services at the Gudai-Darri Iron Ore Project, along with a run of shutdowns at the Western Turner Syncline Phase 2 Project. Recently we landed a key contract with BHP for the Car Dumper three replacement project at Nelson Point in Port Hedland.

Zoran Bebic

executive
#10

That contract covers structural, mechanical, and piping work; it carries a value above AUD 115 million, and completion is anticipated during the first half of 2025. In the period, we finished our electrical and instrumentation scope at the Chemours lithium hydroxide plant, and we landed a contract to build site infrastructure at Talison Lithium Australia's Greenbushes mine. Demand stayed strong in our heavy lift business. Under our long-term services contracts, we kept supporting Fortescue Metals, and through existing construction and maintenance services agreements we supplied specialist heavy lift services to Woodside, BHP, and Rio Tinto. Alevro — our heavy lift joint venture with Fagioli — kept delivering heavy haul services for Fortescue's Iron Bridge project. Following a strategic review and rebrand, Inteforge, our fabrication business, won several contracts, among them Liontown Resources' Kathleen Valley lithium project and the Oyu Tolgoi Underground project. It also won a contract with HydrogenPro to fabricate hydrogen gas separator modules for a renewable energy project in the U.S. Zenviron, our renewable energy joint venture, kept strengthening its reputation as a market leader in delivering balance of plant work for wind farms, and it made good progress on the Rye Park project, the largest wind farm ever to be built in New South Wales.

Zoran Bebic

executive
#11

Turning now to the maintenance division. As I said before, our maintenance and industrial services division posted record half-year revenue of AUD 677 million, which is up 13.5%. That result shows continued strong conditions throughout the resources and energy sectors, and since the start of the financial year the division has been awarded roughly AUD 665 million in new contracts and extensions. We carried out a substantial amount of maintenance, shutdown and project work in iron ore for customers such as BHP, Rio Tinto, Fortescue Metals and Roy Hill. BHP reappointed us to its Iron Ore Site Engineering Panel, so we will keep delivering multidisciplinary services across its Pilbara mine and port operations for three years, and we also got a 12-month extension for general maintenance and shutdown services across BHP's iron ore operations. Under our Sustaining Capital Projects panel agreement, we additionally won a number of new contracts with Rio Tinto in the Pilbara. Importantly, Fortescue Metals awarded us two strategic long term contracts: a five-year services contract at its Pilbara operations and a panel appointment to provide non-processed infrastructure services over a three-year period. In oil and gas, besides securing our first offshore decommissioning contract, we completed several major turnarounds for customers such as Woodside, INPEX, Origin, Shell and Santos.

Zoran Bebic

executive
#12

In addition, we obtained a 12-month extension of the contract we already hold, through our joint venture with Worley, to supply engineering, procurement and construction services for Santos' oil and gas production facilities in Papua New Guinea. And Buildtek — our construction and maintenance services business based in Chile — won several new contracts with major copper producers Minera Escondida and Teck Resources. At this point I'll pass things over to Phil, who will walk you through more detail on our financial performance on Slide 11.

Philip Trueman

executive
#13

Thanks, Zoran, and good morning, everyone. On Slide 11, you can see how we performed financially versus the same period a year earlier. As Zoran said, strong demand for maintenance services drove revenue of AUD 953 million for the half year. EBITDA came in at AUD 58.2 million, and that gives us an improved EBITDA margin of 6.1% for the period, up from 5.7% at this time last year. That's especially pleasing when you consider the escalating cost environment we're dealing with right now. Net profit after tax was AUD 29.1 million, a bit lower than the prior corresponding period, with earnings per share of AUD 0.305. The board declared an interim dividend of AUD 0.24 per share, fully franked. We generated strong cash flow across the six months, with a cash flow conversion rate of 110%. We finished the period with a bank balance of AUD 190 million. Our strong balance sheet gives us sufficient financial capacity in the current economic environment and lets us take advantage of investment opportunities as they come up. I'll now hand you back to Zoran, who's gonna give you an overview of the outlook for the business.

Zoran Bebic

executive
#14

Thanks, Phil. On slide 12 you'll find the current and forecast conditions in the Australian market that matter to our business. As you can see, every sector we operate in is projected to have a strong outlook for capital and operating expenditure alike over the coming years. Now let's move to our outlook slide. Global economic growth is expected to stay steady, commodity prices remain strong, and the outlook for our core markets is still positive. In Australia and at our overseas locations, the resources sector keeps offering a significant number of prospects for our services across a broad range of commodity markets. The buoyant Australian iron ore industry should persist, with capital and operating expenditures needed to sustain and maximize production levels, which drives demand for our services. High global demand for battery metals is driving significant investment in lithium, copper, nickel and rare earths. Those markets, together with the gold sector, will present ongoing opportunities, not only in Australia but also in South America, Mongolia and Papua New Guinea. In oil and gas, a number of new LNG construction projects are currently in the pipeline, and heightened demand for maintenance services is expected to remain. Australia's transition towards clean energy is strengthening, and an increasing pipeline of new wind farms will provide opportunities for Zenviron, both in the electricity market as well as in the private sector as industrial operators move to meet their decarbonization objectives.

Zoran Bebic

executive
#15

Growth in the hydrogen industry is set to create opportunities over the next few years as well. On a wider front, supportive conditions plus ageing assets right across the resources and energy industries are generating robust demand for maintenance work. A lack of skilled workers remains the single biggest issue we face in running our operations. Supply chain risk, now elevated, together with a cost environment that keeps climbing, is creating further pressure. Given these capacity limits, our approach to new work is strategic and selective — we engage and collaborate with customers sooner, keep a sensible stance on how risk is allocated, and place more emphasis on the quality of earnings. Our attention stays on attracting, training and developing employees and on making Monadelphous a terrific place to work. Now that travel restrictions have been removed, our strategy of sourcing labor internationally keeps building momentum. After construction activity stepped down in the last financial year, a fresh wave of construction projects is coming through the pipeline. Because awards and starts on new projects have been delayed, engineering construction revenue this year is forecast to fall relative to the prior year, then ramp up in 2023 to 2024. Consequently, group revenue for the full 2022/2023 year is anticipated to land roughly 5%-10% below the previous year.

Zoran Bebic

executive
#16

With a solid balance sheet behind us, we'll keep evaluating acquisition opportunities so we can keep diversifying our services and customer markets and back sustainable growth over the long term. To wrap up, I want to thank our team for everything they've done. Our team is extremely loyal and talented, and they're the ones powering our strong results. I'd also like to express my gratitude to our shareholders, customers and other stakeholders for their continued support. Thank you. I'll now turn things over to the operator for questions.

Operator

operator
#17

Thanks. Just a reminder that to ask a question, you'll need to press star one one on your phone. If you want to cancel a request, press star one one once more. Please hold while we put the Q&A roster together. One moment while we get the first question. Our first question is from James Wilson at Jarden Group. Please go ahead.

James Wilson

analyst
#18

Hello, everyone. I only have a couple of questions for you today. First, regarding the E&C contract outlook, you've guided toward a ramp-up in FY 2024. Given the delays to new contract signings that you've mentioned, should we now expect that to come more during the second half of 2024?

Zoran Bebic

executive
#19

That expectation doesn't strike me as reasonable. We are definitely still seeing projects take longer to be awarded. I'd say that is a fair expectation.

James Wilson

analyst
#20

All right, thanks — one last question from my side. You mentioned that, given the labor shortages right now, you plan to be more selective about the work you take on going forward. I'd just like to understand whether you expect to hit a point where new construction work becoming available forces you to turn away from chasing additional maintenance growth, so that those resources can instead be directed toward winning construction contracts. Is that clear?

Zoran Bebic

executive
#21

Yeah, that’s not what I’d have expected either. The fact is, the people we draw on for maintenance work come from a separate pool than the one construction draws from — and that’s true not only for us but across the wider market. Sure, some individuals do move from maintenance roles into construction roles, broadly speaking, but those are two distinct labor pools.

James Wilson

analyst
#22

Appreciate it, everyone.

Operator

operator
#23

Appreciate the questions. Give us a second while we get to the next one. Coming up next, we have Ross Chapman from JPMorgan on the line. Please go ahead.

Ross Chapman

analyst
#24

Morning, and thanks for taking my question, gentlemen and Kristy. First off, my thoughts are with you and the team following John's passing. My first question relates to what you said about putting more emphasis on quality and sound risk management on new work. Are you noticing any paradigm shifts when it comes to how contracts are structured, especially around cost pass-through and risk sharing with your customers?

Zoran Bebic

executive
#25

That's definitely where we're putting our attention. In a tight labor market, clients clearly grasp the wider situation better than they did 12 to 18 months back. We're noticing some movement, along with discussions about contract structures and commercial arrangements.

Ross Chapman

analyst
#26

Okay, great. No, thank you. I just have one more question about what you said regarding potential acquisitions. When it comes to these acquisitions, are you zeroing in on a specific segment or one of the divisions — especially now, with respect to any additional diversification into infrastructure, or is the focus on a particular end market?

Zoran Bebic

executive
#27

I wouldn't frame it as though we're zeroed in on any one thing. The truth is that every segment of the business — the maintenance side and the construction side alike — has its own detailed growth plans, and we routinely review smaller acquisition opportunities. I suppose the way we've consistently viewed acquisition opportunities is less about big bolt-on businesses and more about targets that add a service capability we don't necessarily possess, yet sit close to and in line with the core. The thinking behind it is to bring the Monadelphous name, brand, and balance sheet to that opportunity so as to leverage it.

Ross Chapman

analyst
#28

Yeah, that's great.

Zoran Bebic

executive
#29

Nothing in particular, though we always keep a pipeline of smaller possible acquisition targets that we're sifting through.

Ross Chapman

analyst
#30

Alright, great. No, I appreciate that. I’ll just slip in one more if I may. It’s probably a follow-up on the labor question. You’ve been able to widen margins during the first half, even though wages make up a fairly significant portion of your cost base. Do you see any risk from wage inflation, especially as you work to bring in a larger workforce?

Zoran Bebic

executive
#31

Sure, absolutely. I suppose that’s really the craft of it—when it comes to pricing work, you have to put enough emphasis and effort into understanding what you believe it will actually look like. As you know, what we’ve experienced across the past 12 months has been difficult. What I mean is, we devote considerable time to our bid submissions and bring in a lot of data so we can form a view and make assumptions about what wages are going to look like over the next 12 to 18 months. My point is that we put substantial time into pricing that into our tenders, particularly in the construction business. In the maintenance business, it’s a bit different. We have some longer-term contracts that carry commitments and include mechanisms within the contracts to handle rise and fall.

Ross Chapman

analyst
#32

Great. No, thank you so much for that.

Operator

operator
#33

We'll now take questions. Our next caller is Nicholas Rawlinson with Jefferies. Your line is open.

Nicholas Rawlinson

analyst
#34

Hello, Zoran and Phil. I appreciate you taking the time for my questions. Could you walk us through whether that AUD 675 million in maintenance revenue for the half serves as a starting point for further growth in the second half and into FY 2024, or do you anticipate that part of it will reverse?

Zoran Bebic

executive
#35

I guess I'll address that from a broader perspective. At the macro level, as we've mentioned, the market is buoyant, and opportunities exist out there. In the maintenance business, I believe, growth opportunities keep on continuing. The challenge, I think, turns into the timing of some of this work. Even though it's a maintenance business and you could argue it's a recurring revenue stream, plenty of larger turnarounds or shutdown contracts affect the revenue flow when comparing one half year with another. That will be subject to that, which is normal. I suppose we can offer a bit more color — if I give you a little additional detail, we saw more turnaround activity in the maintenance business during the first half than I would anticipate seeing in the second half.

Nicholas Rawlinson

analyst
#36

All right, thank you. Broadly speaking, for the second half should we anticipate group margins staying roughly in line with the first half, since it sounds as though E&C work won't pick up until FY 2024?

Zoran Bebic

executive
#37

I think, again, it's going to depend on when the work comes in and how well we execute. I'd say the bigger theme here is that this emphasis — and the story we're telling about prioritizing the quality of learnings and being somewhat smaller and more selective when it comes to opportunities — should, hopefully, back up a view that we can hold margins steady and, in time, hopefully make them better.

Nicholas Rawlinson

analyst
#38

Appreciate it. One final question from my side. Could you give us any update on when the E&C awards currently out in the public market might come through?

Zoran Bebic

executive
#39

I mean, at the AGM, Rob mentioned a pipeline of more than AUD 2 billion in capital projects, just within E&C. As for that pipeline, we're tracking it, obviously tracking it, and the number is very similar. The reality is that nearly all of those projects have moved to the right, and we're seeing delays.

Nicholas Rawlinson

analyst
#40

Right, so could you update us on any particular projects — the ones that are publicly known to be out to tender over the next three to six months — and just give us any extra detail on that?

Zoran Bebic

executive
#41

There are a few things—maybe if I go into the lithium market a bit, there are several projects that people have been discussing more widely out there. Albemarle's Kemerton project, Talison's Greenbushes expansion, Kathleen Valley. Those are projects where we probably would have expected to see them, or been near awarding, at this point or perhaps even sooner. What we're seeing is them slipping to the right. Three to six months. I think that lines up pretty well with what we're observing throughout the wider pipeline. It isn't tied to one specific commodity market. We're seeing it everywhere. Those capacity constraints we're referring to when it comes to resource challenges—they show up more often at the front end of projects. Reaching the stage where engineering, procurement, and final approvals are granted—that is taking longer and making the pipeline drift to the right.

Nicholas Rawlinson

analyst
#42

All right, that's all I have. Appreciate it, everyone.

Operator

operator
#43

Thanks for the questions. Give us a moment for the next ones. Up next, we have Andrew Hodge from Credit Suisse on the line. Please go ahead, Andrew — your line is open. You can unmute locally. Since Andrew isn't giving us any response, I'll move on to the next question. Up next, we have John Purtell from Macquarie on the line. Please go ahead.

John Purtell

analyst
#44

Oh, hey, good morning there, Zoran Bebic. How's everything going with you?

Zoran Bebic

executive
#45

Hello there, John.

Philip Trueman

executive
#46

John.

John Purtell

analyst
#47

Zoran, to build on what you just said: regarding a few of the industries you're bidding into, you brought up lithium, so I want to confirm what you're anticipating. You've observed some movement to the right there, but you expect results on those projects within the coming 3 to 6 months — just confirming that, and perhaps also some of the other opportunities, plus the timing around them, in terms of rare earths and oil and gas and that sort of thing.

Zoran Bebic

executive
#48

On rare earths, our perspective is much the same. Another point worth making: apart from the big major projects, there's a sizable portfolio of sustaining capital activity among the major iron ore producers. Across BHP, FMG, Rio Tinto and Roy Hill, we're seeing projects valued at AUD 50 million to AUD 150 million. A growing plethora of projects is building in that space — the sustaining capital space — and those will come through. Similar to the large projects, we're also seeing a lag as that kind of work moves through approvals and award.

John Purtell

analyst
#49

Do you think that kind of lag stems more from — sorry — more from the approval process rather than any underlying cost or economic concern?

Zoran Bebic

executive
#50

Yeah, that's probably—actually, not probably. That's a fair question. No. At this point, cost isn't the issue. It's that constraint we mentioned earlier regarding client organizations and engineering firms. They're up against labor constraints, and they're seeing more of it because of the status or the phase that the project's at. That's definitely contributing to this delay that we're seeing.

John Purtell

analyst
#51

Thanks. I’d like to ask a couple more things if that’s OK. Just to clarify one point: you mentioned construction revenue ramping up in 2024.

Zoran Bebic

executive
#52

Mm-hmm.

John Purtell

analyst
#53

So does that mean you anticipate construction revenues will be higher in 2024 than they were in 2023?

Zoran Bebic

executive
#54

I'd say assuming that timing works out, that seems like a fair assumption or expectation.

John Purtell

analyst
#55

Understood, thanks. That kind of margin uplift is exactly what we've been seeing, and I appreciate the remarks on earnings quality, but we saw it even with construction revenue much lower. With the margin gain this period, presumably that took in stronger margins in maintenance as well as improved margins in construction, even with that reduced revenue.

Zoran Bebic

executive
#56

Yeah, I think that's a reasonable point. You have to keep in mind that Sustaining capital or smaller project work is part of the maintenance business too. When that work is carried out well, margins ought to be stronger in that segment of maintenance as well.

Operator

operator
#57

All right, thanks. Any questions? We have Andrew Hodge from Credit Suisse on the line once more. Go ahead, please.

Andrew Hodge

analyst
#58

Good morning, everyone. I hope you can hear me. Thank you for taking my questions. You brought up a very challenging operating environment for pricing things, and you spent considerable time examining the pricing. Since historically you've been much stronger than many of your peers at getting that right, do you think there's a risk over the next six months as contracts begin to drop that you've priced them appropriately but competitors have been a little too punchy in their pricing? They win them, but they can't execute them at those prices. That the effect is that you're right, but you miss out on work as those contracts get awarded.

Zoran Bebic

executive
#59

Yeah, I'd say that risk exists. To be honest, the market remains competitive, and that's true not only here but in any market when it comes to pricing assumptions. So yes, I see that as a risk. As for the pipeline — coming back to that point — it really is quite strong. This is a different market now. We don't depend on winning one particular opportunity, which wasn't the case a couple of years ago, when losing an opportunity mattered far more.

Andrew Hodge

analyst
#60

Thanks. Then, regarding staffing, you said that remains a major challenge both for your company and the sector. As time goes on, are you noticing any gains in the labor market, or is it still clearly unresolved but getting better in any way?

Zoran Bebic

executive
#61

I'd say no on that. It hasn't gotten better. If you look at the pipeline we're discussing, much of this work is beginning to line up fairly well now. Arguably, the bigger challenge comes 12 months from now, when it comes to resourcing and work overall.

Andrew Hodge

analyst
#62

Thanks a lot, that's great.

Operator

operator
#63

Thanks for those questions. Just a moment while we get to the next one. Our next caller is Richard Johnson from Jefferies. Go ahead, please.

Richard Johnson

analyst
#64

Thank you so much. I'm basically attempting to reason through the wider market situation you were just describing, in which there's a really robust pipeline but a system that is limited by capacity. And at the same time, pricing is highly competitive. I'm really just attempting to resolve that apparent contradiction. How all of that comes about is not something I truly grasp. Usually the situation would be the reverse.

Zoran Bebic

executive
#65

Look, I'd say it's just part of the cycle — obviously a great deal of this work hasn't been awarded yet, so firms are jockeying for position to lock in that first batch of projects. It really comes down to how well you grasp the risk and the project itself. Pricing isn't only about, you know, the assumptions you make regarding your rates. It also reflects your grasp of productivity and what's needed to deliver that work. You know, Hodge mentioned this. We all make different assumptions, and ours might turn out right, but if a competitor adopts a much more aggressive stance or fails to understand what delivering the work actually demands, then we lose out — they get the job. Sure, that has repercussions for them when it comes to execution down the line, but it does nothing for us. I think... Yeah. I'm not certain that addresses your question.

Richard Johnson

analyst
#66

Yes, it does. It definitely does. I was just kind of working through this — are we basically saying that the customer is now ready to take on more risk? What I mean by that is that.

Zoran Bebic

executive
#67

Oh.

Richard Johnson

analyst
#68

They're willing to work with a vendor they wouldn't typically turn to.

Zoran Bebic

executive
#69

Sure, that's part of it, but what I mentioned before is that customers, you know, they grasp what's going on in the market. There's also more conversation about various commercial structures. So it's not the case that every contract, every piece of construction work, will be handled on a lump sum basis. There are rates reimbursable arrangements with a risk reward model tied to them. Some of those discussions are taking place.

Richard Johnson

analyst
#70

Understood, thank you. And then last thing, that remark in your outlook regarding a different strategic approach to new work opportunities — the one you explained. I was hoping you might give a bit more detail on it. I just want to get a sense of what you're doing differently now that you weren't doing before. It all sounded fairly familiar.

Zoran Bebic

executive
#71

Yeah. Well, yeah. You know, we discussed how risk gets allocated. You know, there are discussions with certain customers about commercial structures that differ somewhat from how things stood 3 or 4 years back. I mean, that's part of the discussion. We're engaged in some ECIs — early contractor involvement — where clients compensate us to work through planning for some of these smaller projects that will come through. Yeah, even large ones.

Richard Johnson

analyst
#72

That is quite useful.

Zoran Bebic

executive
#73

I suppose so.

Richard Johnson

analyst
#74

Much appreciated.

Zoran Bebic

executive
#75

And I suppose, when it comes to grasping how much activity is out there and what the pipeline shape is, we're clearly able to be somewhat more picky regarding which opportunities we go after — looking at the customer, the market that customer sits in, when the work would happen, and how confident we are in our capacity to secure the resources. That has become more of a characteristic too.

Richard Johnson

analyst
#76

Right, understood. So, extending that logic—and I know you might say this every time—is it fair to assume that, because of how you're approaching things and being far more selective about which work you go after, your confidence in the win rate is very high?

Zoran Bebic

executive
#77

Apologies — I’m not certain I grasped what you were asking.

Richard Johnson

analyst
#78

It really comes down to how confident you are about winning that work, since you're going after quite specific pieces of business, given the strategic differences or the strategic approach you're taking now.

Zoran Bebic

executive
#79

Yeah, well, I suppose part of that strategic rationale — and the factors behind the opportunities we're going after — are ones we're confident we can secure and can deliver.

Richard Johnson

analyst
#80

Understood — that’s really useful. Thanks a lot.

Operator

operator
#81

Thanks for the questions. We now have a follow-up from John Purtell at Macquarie. Go ahead, please.

John Purtell

analyst
#82

Sure, I just wanted to ask a quick follow-up, guys, on the… There was a recent win in the U.S. when it comes to hydrogen fabrication. So the question is: does that signal, you know, what's coming, given how much renewables activity there is over there, and how do you handle the risk surrounding that kind of work, in terms of, you know, more broadly around that fabrication piece?

Zoran Bebic

executive
#83

Right, I believe that's the key takeaway. The issue isn't field execution within the U.S. What we're dealing with is a fabrication package covering several skids. Fair to describe it as strategic, though modest in size — yet this is definitely a market we're keeping a close eye on and would want to play a bigger part in down the road.

John Purtell

analyst
#84

I appreciate it.

Operator

operator
#85

Appreciate the question. So with that, I'd like to return the call to management now for their closing remarks.

Kristy Glasgow

executive
#86

Thanks a lot, everyone, for joining us today. That brings our briefing to an end.

Zoran Bebic

executive
#87

Thanks, everybody.

Philip Trueman

executive
#88

Appreciate it.

Operator

operator
#89

We appreciate you all joining us. That concludes the call, so you’re free to hang up at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Monadelphous Group Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Monadelphous Group Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Monadelphous Group Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.