Monadelphous Group Limited (MND) Earnings Call Transcript & Summary

August 22, 2023

Australian Securities Exchange AU Industrials Construction and Engineering earnings 43 min

Earnings Call Speaker Segments

Operator

operator
#1

I want to let everyone know that this conference is being recorded today. At this point, I'll turn things over to Kristy Glasgow, your speaker for today. Kristy, the floor is yours.

Kristy Glasgow

executive
#2

Thanks. Good morning, and welcome to the Monadelphous 2023 full year results investor and analyst briefing. Before we begin, I'd like to acknowledge and pay our respects to the traditional owners of the lands where this morning's meeting is being held, the Whadjuk people of the Noongar Nation, and to pay our respects to elders past, present, and emerging. Joining us from Perth are Monadelphous' Managing Director, Zoran Bebic, and Chief Financial Officer, Philip Trueman. As we go through this presentation, the speakers will let you know when to click through to the next slide. This morning's presentation will follow a structure similar to previous results presentations, with some additional detail provided as appendices. Copies of today's presentation and associated materials can be found on our website at monadelphous.com.au. I'll now hand over to our first presenter today, Zoran Bebic, who will start on slide 2. Please go ahead, Zoran.

Zoran Bebic

executive
#3

Thanks, Kristy. And welcome, everyone, to the briefing on our results for the full 2023 year. Phil and I will walk you through how we performed financially and operationally during the year that closed on June 30, 2023, and we'll also cover the outlook. After that, we'll take whatever questions you have. Before I begin, I'd like to pause and acknowledge that we recently lost our former chair, our mentor and our friend, Mr. John Rubino. On the next slide, we've put together a small tribute to John. John may no longer be with us, but his memory will remain forever in the corridors here at Monadelphous and in the hearts and stories of our people. We'll keep making you proud, John. Moving to Slide 4 for our group performance and highlights. Monadelphous posted sales revenue of AUD 1.83 billion for the year, which included a record AUD 1.3 billion from maintenance and industrial services, plus AUD 542 million from engineering construction. This result shows how strongly our maintenance services are in demand across every sector, especially oil and gas. As everyone knows, delays in when new major projects were awarded and started affected construction activity. Even so, we kept seeing high levels of construction tendering all through the year. Earnings before interest, tax, depreciation, and amortization came in at AUD 109.1 million, which gave us an improved EBITDA margin of almost 6%.

Zoran Bebic

executive
#4

Net profit after tax rose modestly to AUD 53.5 million, which produced earnings per share of AUD 0.558. A final dividend of AUD 0.25 per share was declared by the board, bringing the total full year dividend to AUD 0.49 per share, fully franked. We finished the year with a solid cash balance of AUD 178.3 million. Our discipline in keeping a strong balance sheet has continued to support our markets and growth strategy, and it enabled us to invest in opportunities such as our purchase of Victorian-based BMC. We kept strategically targeting new work opportunities while making sure risk was allocated appropriately. Since the start of the financial year, we have secured approximately AUD 2 billion of new contracts and contract extensions, including AUD 350 million of construction work post-year end, which ensures a strong pipeline of work for the coming year. Importantly, we continued to develop our approach to sustainability, and during the year we formalized our emissions and energy reduction roadmap, which I'll talk about later in the presentation. Moving now to slide five. As you can see, we've secured new contracts and extensions across Australia, as well as in Papua New Guinea and Mongolia, particularly in the resources and energy sectors. This includes a number of significant construction contracts in Western Australia, the first in a new wave of construction activity.

Zoran Bebic

executive
#5

On the iron ore side, we secured over AUD 750 million in new contracts with long-standing clients, among them BHP, Rio Tinto, and Fortescue Metals Group. In lithium, we landed a significant construction contract plus two strategic long-term maintenance agreements with Albemarle at its Kemerton facilities in WA's southwest. Those wins followed our successful completion of earlier construction packages at Kemerton. Over in energy, we picked up both of the available two-year extensions on our INPEX contract, worth roughly AUD 350 million, and our joint venture with Worley also secured an extension of our Santos contract in Papua New Guinea. Turning to slide 6. We ended the year with a workforce of approximately 5,700 people, subcontractors included. Consistent with our succession plan, we disclosed several board of directors changes that took effect when our AGM concluded in November of last year, among them Rob Velletri stepping into the chair and me assuming the managing director position. To help attract and retain staff, we ran an employee survey during the year. The feedback gathered from that survey helped inform our newest people and culture strategy.

Zoran Bebic

executive
#6

We introduced our Respect@Monadelphous initiative, designed to further ingrain respectful conduct throughout our operations. That initiative covers training on acceptable workplace behavior and the code of conduct, and it is delivered to every employee. Given the tight labor market, we keep reinforcing how we handle people data, using our talent acquisition and performance management system to gain deeper insights into recruitment activity. Our leadership programs remain a support for developing both current and future leaders, and we were named Australia's top construction and property services graduate employer for 2023. Turning to safety now. We remain focused on enhancing safety and wellbeing by identifying, eliminating and mitigating fatal risks, and by delivering sustained improvement in health and safety outcomes. This involved refining relevant in-field risk management tools and rolling out a series of fatal risk awareness campaigns. Happily, our serious incident frequency rate is still at historically low levels. Several technology-based safety improvement trials were finished during the year involving the use of mobile fleet. These included implementing software to help with pedestrian avoidance, distraction and fatigue monitoring, and running Franna crane awareness training to prevent rollovers. Via our health and wellbeing program, we kept supporting the mental and physical health of our people.

Zoran Bebic

executive
#7

That covered things like providing mental health awareness training, working together with The Resilience Project, and arranging various health checks. Our efforts and contribution to safety innovation also earned recognition, and we were named the winner of multiple state and national Work Health and Safety Excellence Awards. Moving on to slide 8. After launching our second Stretch RAP in July 2022, we keep celebrating and acknowledging the traditional owners of the lands on which our people live and work, which includes giving First Nations businesses opportunities and creating pathways for Indigenous peoples. Over the year, we sponsored the Yalamb STEM Camp in Gladstone once again. We renewed our long-standing partnership with the Polly Farmer Foundation, and ran a number of workshops for Indigenous high school students at our registered training facility in Coober Pedy. Our Indigenous Pathways program, delivered in partnership with Rio Tinto, additionally worked with Madalah to help Indigenous students from regional communities with their tertiary studies. On gender diversity and inclusion, we kept facilitating networking and mentoring opportunities for women through our membership with the National Association of Women in Operations, and took part in several panel discussions and in-school engagements. More broadly in the community, we took part in more than 120 events and initiatives spanning 20 locations.

Zoran Bebic

executive
#8

Like I said before, we put our roadmap for cutting emissions and energy use into a formal structure, which supports our objective of reaching net zero emissions by 2050. We set up working groups too, centered on shifting to renewable power, making our fleet greener, and getting operational activities running as efficiently as possible. We looked into ways to swap diesel vehicles for electric ones, moved forward with a thorough review of greenhouse gas data, and locked in our Scope 1 and Scope 2 greenhouse gas footprint for the base reporting year. Now moving to engineering construction, on slide 9. For the year, the division posted revenue of AUD 541.9 million. After a busy period of tendering and several early contractor engagement assignments, we landed AUD 640 million in new contracts, mostly in lithium and iron ore, and we hope to announce a few more shortly. During the first half of the financial year, BHP reappointed us to its WAIO Projects Framework Agreement for another 3 years. That agreement brought us the Car Dumper 3 Renewal project at Nelson Point in Port Hedland, and after year-end we were also awarded the electrical and instrumentation package of works. We wrapped up multidisciplinary construction services at Fortescue's Iron Bridge Magnetite project and Rio Tinto's Gudai-Darri Iron Ore project, along with a series of shutdowns at Rio Tinto's Western Turner Syncline Phase 2 project.

Zoran Bebic

executive
#9

Over in Mongolia, we won a contract to build surface infrastructure for the Oyu Tolgoi underground project. We carried out a strategic review of SinoStruct, our fabrication business based in China, to make sure it stays aligned with what customers expect and is structured appropriately to grow, diversify its supply chain geographically, and deliver in new and related sectors. That review led to the business being rebranded as Interforge. Following the review, Interforge landed fabrication contracts with Liontown Resources and HydrogenPro, plus one for the Oyu Tolgoi underground project. Our renewable energy business, Zenviron, reached substantial completion of work at the Rye Park Wind Farm — the largest wind farm in New South Wales — and was engaged on early work packages for several other wind farm and battery storage projects along the East Coast of Australia. Now moving to our maintenance division. The maintenance division had a stellar year, posting record annual revenue of AUD 1.3 billion, which was up 11.4% on last year. During the period we secured more than AUD 1.3 billion of new work and kept carrying out a significant amount of maintenance, shutdown, and project work across the oil and gas and iron ore sectors.

Zoran Bebic

executive
#10

Through our Sustaining Capital Projects panel agreement with Rio Tinto, we landed a number of contracts. We additionally gained a 2-year extension covering marine infrastructure maintenance services and minor projects at Rio Tinto's Cape Lambert and Dampier ports. BHP reappointed us to its WA Site Engineering Panel for another 3 years, and we obtained a 12-month extension of our general maintenance and shutdown services contract supporting BHP's iron ore operations in the Pilbara. Beyond that, we landed strategic long-term maintenance contracts with Fortescue Metals Group and, in the lithium sector, with Albemarle, which I mentioned earlier. Turning to the energy sector, we captured a 5-year contract for pipeline maintenance work in the Queensland coal seam gas market, along with the extensions with INPEX and Santos. Following a contract award from Petrofac on the Northern Endeavour FPSO, we began work on our first oil and gas decommissioning project. Late in the year, we bought BMC, a Victorian-based maintenance services provider. That strategic acquisition gives us a presence in the East Coast-based energy generation, transmission, and storage market and widens our geographical footprint in the expanding offshore oil and gas decommissioning sector. I'll now pass things to Phil, who will walk you through more detail on our financial performance on slide 11.

Philip Trueman

executive
#11

Thanks, Zoran, and good morning, everyone. As Zoran said, we posted revenue of AUD 1.83 billion for the year, a touch lower than last year. EBITDA came in at AUD 109 million, giving us an EBITDA margin of nearly 6%, up from 5.8% a year earlier. Our push to lift productivity, keep operational discipline tight, and drive greater efficiency right across the business played a big part in that margin gain, and it was central to softening the impact of a stretch of heightened inflation and escalating costs. Net profit after tax for the year stood at AUD 53.5 million, up 2.5%, and earnings per share were AUD 0.558. The board declared a final dividend of AUD 0.25 per share, which brings the full year's dividend to AUD 0.49 per share, fully franked. We finished the year with a strong cash balance of AUD 178 million, cash flow from operations of AUD 93 million, and a very pleasing cash flow conversion rate of 112%. Our ongoing emphasis on generating cash and keeping a strong balance sheet is key to supporting how we operate and our growth strategy, and it lets us seize suitable investment opportunities when they come along.

Philip Trueman

executive
#12

I’ll now hand things back to Zoran, who’ll discuss what lies ahead for the business and the industry outlook.

Zoran Bebic

executive
#13

Thanks, Phil. On slide 12, you can see the current and forecast conditions in the Australian market that matter for our business. It's encouraging that the sectors we operate in show a positive outlook for capital investment and operating expenditure over the next few years. Now let's turn to our outlook slide. Over the longer term, demand is forecast to stay strong across most commodity markets, even with some short to medium-term uncertainty around Chinese domestic consumption and a possible U.S. recession. The resources and energy sectors are expected to deliver a significant pipeline of prospects across a broad range of commodities, and expenditure tied to energy transition will make up an increasingly large proportion of investment activity over coming years. High levels of mining and mineral processing development are anticipated in the battery metal sector, and investment to sustain iron ore production levels will continue. In the energy sector, several new gas construction projects are currently in the development pipeline, and strong demand for maintenance and decommissioning services is expected over coming years. The development of the hydrogen market will also provide opportunities. Maintenance activity levels in the resources sector are forecast to grow, supported by a larger asset base from recently completed capital projects, as well as from new mining developments and expansions moving into the operating phase.

Zoran Bebic

executive
#14

Efforts to speed up decarbonization in Australia’s power sector are producing a growing pipeline of renewable energy projects and opportunities, among them a substantial number of new wind farms and battery storage projects. Zenviron is in a strong position to take advantage of the growth anticipated in this sector in the years ahead, having built an enviable track record since it was founded. After the Rye Park Wind Farm project reached substantial completion in this financial year, Zenviron has already been engaged on early work packages for a number of new wind and battery storage projects. The shortage of skilled labor in Australia remains a challenge, and we continue to focus on making our employee attraction, training, and development initiatives more effective. As well as ensuring Monadelphous remains a great place to work. An escalating cost environment and the potential for ongoing supply chain risks are also expected to persist. Given capacity constraints, we will draw on our strong position and take a strategic, targeted approach to new work, engaging and collaborating with customers early, maintaining an appropriate approach to the allocation of risk, and focusing on earnings quality. Having secured a number of new construction contracts after year-end, and with further awards expected in the months ahead, we anticipate construction revenue will progressively ramp up over the 2024 financial year, with overall group revenue weighted to the second half.

Zoran Bebic

executive
#15

We'll keep evaluating possible acquisitions that could help us expand services, diversify markets, and support sustainable growth over the long term. I'd like to use this moment to thank our incredible employees for another strong year. Here at Monadelphous, we have a highly loyal and talented team. I also want to express my gratitude to our shareholders, customers, and other stakeholders for their continued support. Thank you. I'll now pass things to the operator for questions.

Operator

operator
#16

Thanks. Just a quick reminder—if you'd like to ask a question right now, hit star 11 on your phone and hang tight until your name gets called. If you want to take your question back, just hit star 11 once more. Give us a moment while we put together the Q&A roster. Our first question is coming from William Park at Citi. Your line is open. Go ahead, please.

William Park

analyst
#17

Hello, Zoran, Phil, and Kristy. I appreciate you taking my question. May I ask about your workforce? I'm just curious whether, if you were to consider speeding up the momentum of project awards, and presumably there are additional work packages for Monadelphous to secure in FY 2024, you feel comfortable with the workforce as it currently stands to, I suppose, deliver the work that's out there, or whether you need to see additions to the workforce that you've disclosed today? Thank you.

Zoran Bebic

executive
#18

Well, I would say — especially in our engineering construction business — we've made a real effort to hold on to key white-collar staff so we can keep executing the work. If you look closely at the results, you'll notice some margin pressure in the second half. That lines up with making sure we have the capacity to deliver on work already won and work we expect to win. On the blue-collar side, the fact is we hire blue-collar resources to directly support the work. We've invested considerable time in understanding the work profile and what we expect to secure. We've put a lot of time and effort into understanding where the labor pools sit — whether local, interstate, labor forces, trade meets, trade classification. I think we're as well positioned as we possibly can be to support the level of activity we expect in FY 2024. Yeah, understanding-

William Park

analyst
#19

Much appreciated.

Zoran Bebic

executive
#20

The figures rise.

William Park

analyst
#21

Yeah. Yeah. And, yeah, just, just on labor still. If, if I were to sort of compare your comment, outlook commentary at the interim result on labor, versus, your commentary that you provided today, it, it appears that you're Am I reading into a bit too much, that you're suggesting that the labor pressures are progressively easing, or has it, has it still been quite difficult to source, skilled labor?

Zoran Bebic

executive
#22

Well, I suppose my take would be that labor pressures have not let up. I don't believe they've deteriorated at all compared with six months ago. And bearing in mind that the amount of major construction activity has been below what we saw in earlier years, which is why we mention this next wave of work. My expectation is that we'll keep encountering some difficulties. Everybody will keep encountering some difficulties when it comes to securing labor, but as I said, we've put in a great deal of effort to make sure we're in the best position to meet our need for that work.

William Park

analyst
#23

Thanks. Then just one final item, I suppose, concerns a few of the near-term engineering and construction opportunities in FY 2024. Where do you see — I mean, I know about a few opportunities, and I’m just wondering whether you’d like to identify some of the bigger opportunities that are coming up for an award decision in the near term.

Zoran Bebic

executive
#24

Sure, I suppose where we stand is this. Looking back at the half year results presentation, we offered some commentary on those opportunities, and given that the awarding of some of this work has kept slipping, our perspective would be much the same. My expectation is that the work will fall in the lithium market, the rare earths market, and a wide range of sustaining capital opportunities with the major iron ore producers.

William Park

analyst
#25

Much appreciated.

Operator

operator
#26

Thanks. Give us a second while we bring up the following question. That question will be coming from James Wilson at Jarden Australia, on the line now. You're open — please proceed.

James Wilson

analyst
#27

Hey, guys. Just three quick questions from me, if I may. First, regarding the E&C pipeline, the dollar value of contracts you won during this year's second half is roughly the same as what you won in the first half of FY 2021. Does the ramp-up you're talking about imply E&C returning to similar levels that we saw in FY 2022 for the division?

Zoran Bebic

executive
#28

To be honest, I don't have the FY 2022 figures right at my fingertips. I mean, certainly, we anticipate a ramp-up and an increase in activity. I suppose the caveat would relate to the first half versus the second half. The work we expect to be awarded has a varying ramp-up profile. Certain pieces of work will ramp up right away, but some of the bigger projects really won't start ramping up until the new calendar year. I just caught that number. I believe it was roughly 770 in FY 2024, in 2022, sorry. I would, I would, we would anticipate an uptick in activity, heading toward that kind of number.

James Wilson

analyst
#29

Thanks. Appreciate it, guys. My next question concerns CapEx. We noticed a bit of an increase during the second half of the year. Could you walk us through what caused that increase?

Philip Trueman

executive
#30

Sure, we’ve had — you know, obviously we’re, well, we’re constantly making plans for the business across the short and medium-term outlook when it comes to resourcing. Zoran has already talked about people. We already have an ongoing level of replacements in our CapEx each year regardless, but we’re right-sizing the fleet for the expected workload, plant equipment.

James Wilson

analyst
#31

Great. Last thing on that BMC acquisition from June — you said its yearly revenue contribution is roughly AUD 60 million. Could you give us some sense of how it does compared with the group when it comes to margin or earnings?

Zoran Bebic

executive
#32

I think our perspective would be this: in the maintenance business, our margin expectation would line up fairly well with what our regional operations deliver.

James Wilson

analyst
#33

Thanks, everyone.

Zoran Bebic

executive
#34

Because it really is—it definitely leans more toward being a services business.

Operator

operator
#35

Appreciate it, and just a moment while we go to the following question. That next question will come from John Hynd at Macquarie. Your line is open—please go ahead.

John Hynd

analyst
#36

Oh, good morning, Zoran and Phil. I hope you both are doing well. I have just a couple of questions, if I may. Yeah, coming back to that remark about construction revenue and the progressive ramp-up: does that mean you expect construction revenue to go up in 2024 compared with 2023, or is there something of a dip down in the — you know, the, the, the timing of the awards beforehand?

Zoran Bebic

executive
#37

Right, so the timing is really the key question here. What I'd say is this: for FY 2024, our expectation is that engineering construction revenue will come in higher than it did in FY 2023 — though it does depend on when the award lands.

John Hynd

analyst
#38

Hmm. On the margin side of things, do you anticipate some kind of margin improvement over the coming year, Zoran? And if there is any, should we be thinking of it as fairly modest?

Zoran Bebic

executive
#39

I think my perspective would be this: we might say something about cost, and our view on the cost pressure challenges that continue. That's something everybody is going to have to work their way through. If I look at the pipeline, or the committed work, or the prospects in engineering construction, we've clearly observed some shift from how compensation models were structured, let's say, 18 months ago, to how they look today — meaning perhaps more work on a rates reimbursable basis. That lowers the risk attached to those contracts, but it also puts a ceiling on the opportunity, or the margin, on the upside. More broadly, I'd say there's an opportunity for margin improvement. I don't think it's a significant step up over the next 12 months. And we also understand there are challenges and risks, and we need to execute well to capture that margin improvement opportunity.

John Hynd

analyst
#40

Thanks. On that final point—you brought up certain oil and gas construction projects that are in the pipeline. If you could, it would help to hear a bit more detail on what those involve.

Zoran Bebic

executive
#41

So, I mean, when you consider the wider pipeline — looking out over, let's say, the coming 2 to 3 years instead of 12 months — obviously Pluto 2 is in train. Past that, you've got Shell Crux, Santos' Dorado Field, and Santos' Barossa. The Project is Surat Gas Project works. There are several potential Gorgon Stage 2 projects. Over in PNG, Elk-Antelope is probably the closest one to execution, though it's still some time off. Broadly speaking, it's a pretty broad pipeline.

John Hynd

analyst
#42

Appreciate it.

Operator

operator
#43

Thanks. Just a second while we move to the following question. Our following question is from Julian McCarthy at E&P. Your line is open. Please proceed.

Julian McCarthy

analyst
#44

Hi there. I’ve got just a couple of questions. First, regarding the year-over-year changes in headcount, we’re seeing a fairly significant decline, quite a bit of it in maintenance. So have you simply become much more efficient, or was that maintenance revenue — sort of including some construction activity — and that’s why it ends up looking, you know, very inflated when it comes to revenue per head?

Zoran Bebic

executive
#45

Okay, so we did note that our Buildtek operations in Chile were shut down earlier in the year. That definitely affected the maintenance business. Another thing I'd point out is that the employee figures are a snapshot taken at one moment. What you're looking at there is the count as of 30 June, which is just a snapshot, and as we've said, construction activity was at quite low levels, at least at that particular time.

Julian McCarthy

analyst
#46

So, what was the headcount at Buildtek?

Zoran Bebic

executive
#47

More than 1,000.

Julian McCarthy

analyst
#48

Okay, so about cost pressures — you mentioned there's additional reinvestment-rate work happening. Earlier this year, and really across roughly the last 12 months, the pendulum swung heavily toward the contractors. Does that remain very much the situation?

Zoran Bebic

executive
#49

When you say the pendulum has swung very much, I would—

Philip Trueman

executive
#50

That would be nice. That would be nice.

Zoran Bebic

executive
#51

My sense is that the pendulum has swung somewhat toward us, coming from what was before an extreme point. It has shifted a bit. As I mentioned, the blend of work when it comes to compensation models does appear somewhat different from how it looked 18 months ago.

Julian McCarthy

analyst
#52

So with the tier one bench having pretty much emptied out over the last year — forges, costs, all of that — can you still be as picky about projects as you were last year? Or do you figure competition will return because builders are eager to get projects finished?

Zoran Bebic

executive
#53

I believe the overall pipeline is quite robust when it comes to opportunities. Yes, we've been lucky enough to prioritize the work that matters to us. Yes, we've been able to be somewhat more selective.

Julian McCarthy

analyst
#54

Alright.

Philip Trueman

executive
#55

I think it's also fair to say that many of our rivals, you know, are telling the market they're quite full right now.

Julian McCarthy

analyst
#56

Alright, thanks.

Operator

operator
#57

Thanks. Just a moment while we go to the following question. That next one will be from Nathan Reilly at UBS. Your line is open. Please go ahead.

Nathan Reilly

analyst
#58

Hey there, guys. Just a quick question about Buildtek — what did it contribute to FY 2023?

Zoran Bebic

executive
#59

Nathan, we’re losing you. The question didn’t come through.

Nathan Reilly

analyst
#60

Apologies—are you able to hear me at this point? I had just been inquiring regarding Buildtek.

Zoran Bebic

executive
#61

Yes.

Nathan Reilly

analyst
#62

I only wanted to find out what the contribution was.

Zoran Bebic

executive
#63

Right, so we discussed that it represented 4% of group revenue, which works out to around AUD 80 million.

Nathan Reilly

analyst
#64

Yeah, I was just wondering whether that was paid or actually lost?

Zoran Bebic

executive
#65

Nate, apologies — we didn't catch any of that.

Nathan Reilly

analyst
#66

Is this coming through now? What I was trying to find out is whether Buildtek's contribution to earnings in FY 23 was at break-even or whether it lost money.

Zoran Bebic

executive
#67

Well, yeah, it was.

Philip Trueman

executive
#68

And Nathan, even with what happened over at Buildtek operations, our results weren’t materially affected.

Nathan Reilly

analyst
#69

Alright, let's take the next question. It concerns the Unitywater matter. Picking up on what you announced recently about that project and the claim the customer has filed there — just remind me: I believe when a comparable case arose with Rio at Cape Lambert some years ago, you noted roughly AUD 150 million in public liability insurance coverage. Could you give us a sense of whether that insurance cover applies to this situation?

Philip Trueman

executive
#70

Oh, Nathan, I mean, I think we, we don't talk about our insurances and we never have, so I'm not quite sure where that's come from. We've got the usual insurances in place that you'd expect for a contracting business, and we are, we are comfortable with, with the position that we have taken in respect to the claim.

Nathan Reilly

analyst
#71

Understood. Fine. One last question — just on that point you're raising about how the compensation model mix is shifting. If we zoom in on that roughly AUD 640 million of E&C revenue you've booked this year, could you give us a sense of what the split would look like, I suppose, between this move toward cost reimbursable work and, I guess, your, you know, your more traditional, sort of, fixed price approach?

Zoran Bebic

executive
#72

I think, when we discuss this, it isn't necessarily a case of one model versus the other. So if you're saying it's — there are contracts that carry a fixed price, and there are contracts.

Nathan Reilly

analyst
#73

Yeah.

Zoran Bebic

executive
#74

Those are reimbursable rates. We have quite a few contracts that mix both. There are fixed components and variable compensation covering other portions of the contract. I'd say we're likely not at 50/50 yet, but we are heading that way between fixed price and reimbursable rates.

Nathan Reilly

analyst
#75

What would that look like versus 3 years back?

Zoran Bebic

executive
#76

My apologies — I let that one slip past me once more, my friend.

Nathan Reilly

analyst
#77

What would that look like next to where we were 3 years ago?

Zoran Bebic

executive
#78

I mean, I think it's probably fair to say that in engineering construction, 3 years ago, the majority of the work was fixed price.

Nathan Reilly

analyst
#79

Yeah.

Zoran Bebic

executive
#80

Probably the whole thing.

Nathan Reilly

analyst
#81

Got it. Thank you so much for taking my question. I apologize for the line.

Zoran Bebic

executive
#82

That's not a problem at all.

Operator

operator
#83

Thanks. Just a moment while we go to the next question. The next one is from Nicholas Rawlinson at Jefferies. Your line is open. Please go ahead.

Nicholas Rawlinson

analyst
#84

Hello, Zoran, Phil, and Kristy. I appreciate you taking my questions. First off, from my side, since 1H23 came in so strong on maintenance with a great deal of turnaround work, is it still reasonable for us to anticipate fairly solid year-over-year growth in maintenance for 1H24?

Zoran Bebic

executive
#85

Right, so the variability is going to come from major turnarounds and getting a handle on what that profile looks like. I'd hope to see some growth in maintenance in FY 24.

Nicholas Rawlinson

analyst
#86

And during 1H24, was there some growth as well?

Zoran Bebic

executive
#87

For the first half of 2024, actually, my expectation is that maintenance will perform better in that period than in the second, given the turnaround schedule, or the turnarounds you just mentioned.

Nicholas Rawlinson

analyst
#88

Alright.

Zoran Bebic

executive
#89

In the first half of FY 2024, a few of them are pretty significant.

Nicholas Rawlinson

analyst
#90

Yeah.

Philip Trueman

executive
#91

Nick, that first half of last year was a really huge one, wasn't it?

Nicholas Rawlinson

analyst
#92

Yeah. Yeah. Yeah.

Philip Trueman

executive
#93

So.

Nicholas Rawlinson

analyst
#94

Yeah. Okay, but you still expect strong performance there. Okay. E&C in 1H24, as we know, remains subdued. Should we simply anticipate it being roughly in line with what you delivered during the first half and the second half of FY23, or is it?

Philip Trueman

executive
#95

Nick, I think, as we said, the timing of the work is going to be key here, but you know, our way of doing things is to provide guidance around what we expect the first half to look like at the AGM. It's still quite early in the year at this point.

Nicholas Rawlinson

analyst
#96

Could you give us at least a rough idea?

Philip Trueman

executive
#97

If I had one, I would hand it over to you, but I don't have one.

Nicholas Rawlinson

analyst
#98

Right. OK, so on book-to-bill — in E&C it came in comfortably above 1, which hadn't happened for some time. You took in AUD 640 million, as I recall, and you spent roughly AUD 540 million. Is the bulk of that E&C revenue you booked largely forward-looking, and do you expect it to be recognised in FY 2024?

Zoran Bebic

executive
#99

I’m not certain I got the question.

Philip Trueman

executive
#100

Regarding your question, last year we recorded AUD 640 million in wins.

Nicholas Rawlinson

analyst
#101

Right.

Philip Trueman

executive
#102

Keep in mind, we do have a certain amount of recurring work in that business too, and we also pulled some work into the year as well.

Zoran Bebic

executive
#103

We saw an expansion in scope.

Philip Trueman

executive
#104

Yeah.

Zoran Bebic

executive
#105

We secured new contracts.

Philip Trueman

executive
#106

We have secured a portion of the work that we've won... You know, I mean, it, it, it, I don't know. It hinges on when the work is scheduled and when it actually arrives. I think, you know, I think we've already shared our perspective regarding where we believe E&C revenues might, might land this year. Higher than last year, approaching 2022, somewhere in between those two. It hinges on the timing, the commencement of the work.

Nicholas Rawlinson

analyst
#107

Okay.

Zoran Bebic

executive
#108

And just to add, we know the engineering construction business has locked in AUD 350 million in work after the close of FY 2023.

Nicholas Rawlinson

analyst
#109

Yes. Yes. Yes. All right, great. I'm finished. Thank you, everyone.

Operator

operator
#110

Thanks. We have no more questions at this point, so I’ll hand the conference back to Kristy Glasgow for any closing comments.

Kristy Glasgow

executive
#111

I appreciate everyone joining us today. With that, our presentation has now come to an end.

Operator

operator
#112

That wraps up our conference, ladies and gentlemen. You can go ahead and disconnect now. Have a great day, everyone.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Monadelphous Group Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Monadelphous Group Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Monadelphous Group Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.