Monadelphous Group Limited (MND) Earnings Call Transcript & Summary

February 20, 2024

Australian Securities Exchange AU Industrials Construction and Engineering earnings 55 min

Earnings Call Speaker Segments

Operator

operator
#1

Hello, and thanks for joining us today. You're listening to the presentation of Monadelphous' results for the 2024 half year. Everyone is currently in listen-only mode. Once the speaker has finished presenting, we'll move to a question and answer session. If you'd like to ask something during that session, press star one one on your phone. An automated message will then confirm that your hand has been raised. Should you wish to withdraw your question, just press star one one once more. Please note that this conference is being recorded today. I'll now hand things over to Ms. Kristy Glasgow, the company secretary. Over to you.

Kristy Glasgow

executive
#2

Good day, and thank you for joining the Monadelphous 2024 half year results investor and analyst briefing. Before we begin, I'd like to recognise the traditional owners of the lands from which we're joining you today in Boorloo, Perth. We acknowledge the Whadjuk people of the Noongar Nation and the traditional owners of country, and we pay our respects to elders, past, present, and emerging, and we extend that respect to all First Nations people. With us today are Monadelphous' Managing Director, Zoran Bebic, and Chief Financial Officer, Phil Truman, who are joined in the room by our chair, Rob Velletri. During this presentation, the speakers will let you know when to click through to the next slide. This morning's presentation will follow a structure similar to previous results presentations, with some additional detail provided where appropriate. Copies of today's presentation and associated materials can be found on our website at monadelphous.com.au. I'll now hand over to our first presenter today, Zoran Bebic, who will start on slide two.

Zoran Bebic

executive
#3

Thanks, Kristy, and welcome everyone to the briefing on our 2024 half year results. Phil and I will walk you through how we performed financially and operationally during the half year that closed on 31 December 2023, and we'll also cover the outlook. After that, we'll take any questions you might have. Moving to our group performance and highlights, which you'll find on Slide 3. Monadelphous brought in revenue of AUD 1.008 billion across the six months, which matches the guidance we gave to the market and works out to a 5.8% rise versus the prior corresponding period. We saw record levels of activity in maintenance services during this period, and we finished the half holding a record cash balance of AUD 263 million. All up, we locked in over AUD 1.8 billion in new contracts and extensions. Our Maintenance and Industrial Services division posted revenue of AUD 708 million for the six months, an increase of 4.6% against the prior corresponding period. We completed a number of major turnarounds for key customers in the energy sector, and we also landed a couple of truly material long-term contract extensions and variations. Demand for services and sustaining capital works remains high in this division, which helps customers keep their assets maintained and supports production. Over at Engineering Construction, we secured roughly AUD 750 million in significant new construction contracts, coming off high levels of tendering activity in recent periods.

Zoran Bebic

executive
#4

For the six months, the division posted revenue of AUD 303 million, which is a 9.2% increase over the prior period, as a number of recently awarded projects began site activities. Net profit after tax came in at AUD 30.1 million, up 3.2% compared with the same time last year, which delivered earnings per share of AUD 0.312. The board declared an interim dividend of AUD 0.25 per share, fully franked. Our renewable energy joint venture, Zenviron, kept building on its strong reputation for delivering balance of plant work for wind farms, and it successfully completed work at the Rye Park Wind Farm in New South Wales. It also moved into the energy storage market, winning its first EPC battery storage project. Zenviron is well placed to capitalize on the significant growth expected in the renewable energy sector over the coming years. During the half, we acquired Perth-based structural concrete business Melchor Contracting. Melchor, which employs around 300 people and generates revenue of approximately AUD 100 million per annum, offers full structural concrete capability in the resources, energy, and infrastructure sectors. This strategic acquisition further broadens our multidisciplinary construction offering to now include civil capability. Moving to Slide 4. As I mentioned, we have secured approximately AUD 1.8 billion of new contracts and contract extensions since 1 July 2023, with major contracts secured in the energy, lithium, and iron ore sectors.

Zoran Bebic

executive
#5

When it comes to energy, we picked up substantial long-term maintenance work with INPEX and Woodside, plus another three-year contract to keep delivering sustaining capital and maintenance services for Santos in Papua New Guinea. Over AUD 530 million in new construction work was won in lithium, covering major contracts with Albemarle, Talison Lithium, and Liontown Resources. Over in WA's iron ore sector, we broadened our ties with longstanding clients BHP, Rio Tinto, and Fortescue through new work awards and contract extensions. Now let's turn to Slide 5, everyone. Including subcontractors, our total workforce came to just over 7,400 people at half year end. That represented a rise of roughly 20% compared with 30 June 2023, driven by higher construction activity and the Melchor acquisition. Thanks to our unwavering focus on staying engaged with our employees, retention rates improved, which is especially pleasing given that skilled labor shortages across the industry continue to pose a challenge. We carried out a review of how effective our long-term leadership reward programs are and how they are designed, to make sure they keep supporting the retention of key leaders in a way that aligns with building long-term shareholder wealth. That review led us to implement a performance reward plan for the senior leadership team, which replaces the employee option plan as the main employee equity vehicle.

Zoran Bebic

executive
#6

Helping people build careers early on stayed a key focus for us — over the 6 months, more than 200 people took part in our graduate, vocation, apprenticeship, and traineeship programs. Those programs are all about creating learning and development opportunities across a variety of relevant career pathways, and right now our graduates are working in construction management, engineering, and accounting disciplines. At Bibra Lake, our registered training organization ran more than 700 training courses for over 2,600 tradespeople, covering high-risk training, accreditation, and verification of competency. Turning now to safety and wellbeing — that's slide 6. Thanks to our unwavering focus on health and safety, our serious incident frequency rate stayed at low levels. Through our Fatal Risks Control campaign, we also kept working on identifying, reducing, and eliminating fatal risks throughout the business. Our dedication to innovation and safety performance earned us recognition at the Queensland Work Well Awards and at the Queensland and Northern Territory Welding Excellence Awards. On top of that, Melchor was named a finalist in the WA Mental Health Awards, and in August I handed the Managing Director's Safety Innovation Trophy to our Gladstone workshop team for coming up with a safer way to remove and refurbish heat exchangers. As part of our continuing commitment to employee health and well-being, we provide general health checks, skin checks, and a series of health-related information sessions, and we've also partnered with the Resilience Project to offer a resilience and well-being program for our employees and their families.

Zoran Bebic

executive
#7

We also kicked off an independent review of psychosocial risk management systems, looking for ways to keep improving how we support the wellbeing of our people. Moving on to slide seven. We carried on with our work in the important areas of diversity, community, and environment. Through our Stretch Reconciliation Action Plan, or RAP, we help identify and create opportunities for First Nation peoples and businesses, and we nurture an internal culture of understanding and respect. Happily, we keep surpassing our RAP targets for Indigenous workforce participation. Our partnership with the Polly Farmer Foundation carried on, with school visits hosted at our Perth office and Bibra Lake Employee Development Center as a key founder of the Polly Farmer Follow the Dream program, and we also supported foundation alumni in pursuing trades-related career pathways. We launched our reinvigorated cultural learning strategy, a key RAP initiative, adding new cultural awareness and cultural activities, and we delivered learning opportunities from the Acknowledge This! program to help our employees learn about delivering a meaningful and genuine acknowledgment of country. We advanced the initiatives under our Gender, Diversity, and Inclusion Plan, which included taking part in events such as the Bright Futures STEM program and the Inspiring Girls Forum, aimed at encouraging girls and young women to choose STEM subjects.

Zoran Bebic

executive
#8

We were also recognized as a finalist in the Women in Resources Awards, which honors our Crane Operations Pathway Traineeship — a program running three years that gets female and Indigenous trainees ready to become qualified crane operators. In line with our dedication to giving back to the communities where we operate, we backed roughly 70 community initiatives, providing over AUD 170,000 in funding along with close to 400 hours of volunteer time. We kept moving forward on our roadmap for cutting emissions and reducing energy, consistent with our net zero commitment, pushing ahead with emission reduction trials and putting emissions data capture processes in place before base year reporting. In addition, we put together a proposal for a hybrid power solution aimed at lowering diesel emissions at operational compounds, adding to our fleet of hybrid and electrical vehicles. Now moving to slide 8 and our engineering construction division. For the half year, that division posted revenue of AUD 303.1 million, which is 9.2% higher than the prior corresponding period. After increased tendering activity, we landed a substantial number of major new construction contracts. On the lithium side, we won a major construction contract with Albemarle worth about AUD 200 million, covering the front-end pyromet works tied to two new lithium processing trains at the Kemerton expansion project.

Zoran Bebic

executive
#9

Towards the end of the period, we also locked in another package of work covering the utilities and reagents scope on that project. Those awards came after Monadelphous had earlier completed construction of two processing trains at the project successfully, and after the long-term maintenance and sustaining capital works for Albemarle's Kemerton operations were awarded last financial year. After a successful early contractor involvement phase, we landed a AUD 160 million multidisciplinary contract at Talison Lithium's Greenbushes site. Construction also got underway on the wet plant at Liontown Resources' Kathleen Valley Lithium Project. That contract, valued at approximately AUD 100 million, comes on the back of a fabrication and supply contract given to Inteforge in the prior year. In iron ore, we carried on with the structural, mechanical, and piping package for BHP's Car Dumper 3 Renewal Project at Nelson Point in Port Hedland, where we also picked up the electrical and instrumentation scope. We were awarded a contract in the rare earth sector with Lynas Rare Earths for stage one of the Mount Weld expansion project, tied to construction of the new concentrate processing facility, as well as a contract with Chevron Australia to support installation and modification of electrical power and control facilities at the Jansz-Io Compression Project at Barrow Island.

Zoran Bebic

executive
#10

Turning to the maintenance division now. For the half year, this division once again posted a record revenue figure — AUD 708 million — which represents a 4.6% increase over the previous period. We're pleased that since the start of the 2024 financial year, the division has won more than AUD 1 billion in new contracts and extensions, and that includes roughly AUD 800 million in long-term maintenance work with INPEX and Woodside, both of which I referred to earlier. Demand for maintenance services was strong across every sector, though activity was especially elevated in energy. The division carried out a major turnaround at Shell's Prelude FLNG facility, and it also completed a number of shutdowns at Woodside's onshore and offshore assets in Western Australia's northwest. In addition, decommissioning activity carried on for Petrofac on the Northern Endeavor. A substantial amount of work was delivered in Western Australia's iron ore sector through our long-term panel agreements with Fortescue. We obtained a one-year extension of our sustaining capital works agreement covering services at Rio Tinto's Pilbara operations, plus an extension for general maintenance services provided to BHP. Further contract extensions were secured at BHP's Nickel West, Mount Arthur Coal, and Olympic Dam operations, and also for our fixed plant shutdowns contract at Rio Tinto's Gove operations.

Zoran Bebic

executive
#11

BMC — the specialist business we acquired last June for electrical and maintenance services — has been brought in successfully, and over this period it landed an outage contract at Victoria's Loy Yang B Power Station in Traralgon. Phil will now take you through further detail on our financial performance, which is on slide 10.

Phillip Trueman

executive
#12

Thanks, Zoran, and good morning, everyone. The slide we have up right now sets out how we performed financially against the equivalent period a year earlier. As Zoran said, we booked revenue of just over AUD 1 billion across the half, an increase of 5.8% over the first half of FY 2023. EBITDA came in at AUD 61.3 million, giving us an EBITDA margin of roughly 6.1%, which is comparable with the prior corresponding period and a touch higher than the 2023 financial year. Net profit after tax reached AUD 30.1 million, up 3.2% versus this time last year, producing earnings per share of AUD 0.312, and the board has declared an interim dividend of AUD 0.25 per share, fully franked. The standout in this result was clearly the record cash balance of AUD 263.3 million, lifted materially by the significant advances we collected during the period tied to construction contracts awarded recently. Cash flow from operations over the six months came to an incredible 147.3 million dollars, which means an outstanding cash flow conversion rate of 260%. A strong balance sheet continues to be a key enabler of operational performance and underpins our markets and growth strategy.

Phillip Trueman

executive
#13

During this period, we put significant investment into our heavy lift crane fleet. That was to back the construction contracts we were awarded recently, and it grew both our fleet's capacity and its capability. We also carried out major maintenance work aimed at extending how long our current assets stay useful. Our heavy lift crane fleet gives our business a competitive edge, it supports our self-execution strategy, and it further reduces how much we depend on the outside supply market. I'll now pass things back to Zoran, who will give you an overview of the business outlook.

Zoran Bebic

executive
#14

Thanks, Phil. On slide 11, you can see the current and forecast conditions in the Australian market that matter to our business. It's encouraging that, as the slide shows, the sectors we operate in keep offering a positive outlook for both capital investment and operating expenditure across the next few years. Let me now turn to our outlook slide... Demand forecasts over the longer term are still strong in most commodity markets, and global economic uncertainty has moderated of late. The resources and energy sectors are delivering a substantial pipeline of prospects spanning a broad range of commodities, and expenditure tied to decarbonization makes up a growing share of investment activity. For most commodities, production is expected to stay near today's high levels, which supports ongoing sustaining capital and maintenance spend. Price volatility in certain commodities could cause production to fall or capital investments to be deferred, as clients concentrate on cutting costs. Even so, mining and mineral processing development in the energy transition metal sector is forecast to stay high over the longer term, and investment aimed at sustaining iron ore production levels will carry on in the years ahead. In energy, several new gas construction projects are presently in the development pipeline, demand for maintenance services remains strong, and decommissioning prospects are expected to increase over coming years.

Zoran Bebic

executive
#15

Hydrogen is still an evolving market, and we expect bigger opportunities to emerge during the latter half of this decade. In resources, maintenance work should stay steady, since output remains elevated and recent mining builds and expansions are entering operation. In Australia's power segment, faster decarbonization is producing a growing set of renewable projects, among them many new wind farms plus battery storage schemes. Over the last year, investment choices were affected by planning approvals and network constraints. Even so, Zenviron is positioned well to benefit from the substantial expansion anticipated in this sector in the years ahead. Skilled labor shortages in Australia persist, so our attention stays on attracting, training, and developing employees to help with retention. After a solid first half and the momentum from construction awards booked in that period, FY 2024 full year revenue should rise by roughly 10% versus the prior year. Given constrained labor and supply chain capacity, we'll keep drawing on our strong position and pursue new work in a strategic, targeted way—engaging and collaborating with customers early, emphasizing earnings quality, and keeping a suitable approach to risk allocation.

Zoran Bebic

executive
#16

With a solid balance sheet behind us, we'll keep evaluating possible acquisitions that could help expand our services, diversify our markets, and support sustainable growth over the long term. To wrap up, I want to thank the talented people at Monadelphous for their loyalty and their dedication to the company's continued growth and success. I'd also like to express my appreciation to our shareholders, our customers, and other stakeholders for their continued support. Thank you. I'll now pass things to the operator for questions. Just bear with us. We're waiting for the operator to join us. We're just having a few-

Operator

operator
#17

Thanks, Aisha. The first question we have comes from James Wilson at Jarden in Australia.

Zoran Bebic

executive
#18

James, can you hear us?

Operator

operator
#19

Aisha, the next question we have is from Nicholas Rawlinson, who's on the line from Jefferies. Nicholas Rawlinson, your line is now open.

Zoran Bebic

executive
#20

Nick, are you there?

Operator

operator
#21

Ladies and gentlemen, should you wish to ask something right now, kindly hit star one one on your telephone. To repeat that, if you'd like to pose a question at this moment, simply press star one one. All right, I see that the first question is from the line of—of course, your line is open, Mr. Wilson.

Phillip Trueman

executive
#22

Hey, everyone.

Zoran Bebic

executive
#23

Hello there, James.

Phillip Trueman

executive
#24

Phil, are you able to hear me at this point?

Zoran Bebic

executive
#25

Yeah, we’re able to do that.

Phillip Trueman

executive
#26

Hi. Okay. All right, we're live. Okay, folks, maybe to start things off, could you give us a bit more detail on how you see the split between construction and maintenance work shaping up as we head into the second half of the year?

Zoran Bebic

executive
#27

We've noted that, you know, we locked in quite a bit of construction work during the first half, and we've begun. Well, site mobilization is genuinely underway at this point. So my expectation is that construction activity will ramp up in the second half. That said, during the back end of the six-month period, we mobilized most of the contracts that had been awarded, but we will certainly see a modest ramp-up on the construction side of the business in the second half.

Phillip Trueman

executive
#28

I think it's worth noting too that the energy sector saw a couple of significant turnarounds on the maintenance side during the first half. As you know, James, we don't anticipate that same level of turnaround activity in the second half.

Zoran Bebic

executive
#29

Okay, thanks Phil and Zoran. About that contract ramp-up — it clearly gave a boost to the working capital figure you reported for the first half. Could you perhaps walk us through how you expect that to unwind as we move into the second half?

Phillip Trueman

executive
#30

Okay, on the advances. If we focus specifically on the construction contracts, since the maintenance working capital tends to stay pretty steady, you know, we received a decent amount of advances on those construction contracts. And my expectation is that they would roll off proportionately across the duration of those contracts. So yeah, we'll likely see roughly half of those advances unwind between now and June.

Zoran Bebic

executive
#31

Thanks, that's really useful. And then, guys, just one last question from my side. Could you maybe update us on how you're viewing labor availability for, say, the incremental E&C contract at this point compared with your August result from last year? I think what we're seeing is consistent with what others are seeing. There's been a modest degree of moderation. I wouldn't say it has improved materially, but it certainly hasn't gotten worse. But also bearing in mind that the number of large-scale construction projects actually underway right now is relatively low. So as we see this ramp up, I'd expect the tightening to continue. So that's how I'd put it — it's settled, arguably moderated slightly, but we haven't seen a material improvement.

Phillip Trueman

executive
#32

Alright, excellent. Thank you, everyone.

Operator

operator
#33

Thanks. The next person in the queue is Nicholas Rawlinson with Jefferies. Your line is open.

Nicholas Rawlinson

analyst
#34

Hello, Zoran and Phil. I appreciate you both fielding my questions. First off, could you bring us up to speed on where things stand with those large lithium contracts of yours?

Zoran Bebic

executive
#35

All right, where things stand—so, basically, everything we've got is still under contract. Certainly as far as Liontown and CG- CGP3 Talison go, I'd expect no shifts at this point. Albemarle's adjustments, I think, are fairly well covered out there. What we're seeing is an anticipated emphasis on Train 3, so we'd look for some softening in the revenue profile under that contract, though we still anticipate finishing every piece of contracted work, meaning the timeline could stretch a bit.

Nicholas Rawlinson

analyst
#36

Okay, thank you. The margin seemed a bit thin, especially since E&C activity increased on the PCP. Was that purely the ramp-up curve behind it? And ought we to anticipate a measure of margin growth half-on-half during the second half?

Zoran Bebic

executive
#37

I wouldn't put it quite that way. From a margin standpoint, the wider environment remains difficult. You know, certain commodities are showing some volatility, and there's still a problem — you know, the difficulties around the labor market, securing access to labor and productivity results, and supply chains are... While supply chain constraints have eased, everyone is still working through supply chain constraints, so-

Phillip Trueman

executive
#38

Nick, we're still in the early phases of these jobs, aren't we?

Nicholas Rawlinson

analyst
#39

All right, all right, that's useful regardless. Just one final question from my side. Could you give us some sense of whether any of those iron ore projects or gas construction projects in the pipeline have moved forward at all? For instance, are you beginning to see any contractor engaged on any of them?

Zoran Bebic

executive
#40

This is probably pretty similar to what we said back in December. If you look at the situation in August. If you look at those big greenfield projects, they're still — I mean, they remain further out. So when you mention Brockman Syncline, Rhodes Ridge, I mean, those are being pushed out. But what we're seeing is that there's definitely a greater degree of engagement when it comes to putting that category of, you know, material brownfield projects in place across all three of the major iron ore players. So I think it's still a sustaining capital portfolio profile for the next 12 to 18 months before some of these larger scale, or large-scale, greenfields projects come to fruition.

Phillip Trueman

executive
#41

All right. That's all from my side, everyone. Thanks.

Operator

operator
#42

Thanks. Our next question is from Nathan Reilly at UBS. Go ahead, please.

Nathan Reilly

analyst
#43

Hey, gentlemen. I was just curious — could you give us a bit of an update on tendering conditions overall? Maybe walk us through your main end-market exposures, I suppose across energy, iron ore, and through materials now. Just give us a sense of how those tendering conditions have changed over, say, the past 6 to 12 months.

Zoran Bebic

executive
#44

Tendering activity is running at high levels throughout the business, in line with where we were six months ago. Our attention — well, as you know, we have a robust order book, so our attention has shifted to looking a bit further ahead, and, you know, we have to build on the FY 2025 order book. But across cross-market, opportunities exist in energy, opportunities exist — you know, the pipeline is quite strong, as I mentioned, when it comes to the iron ore market, sustaining capital opportunities with all customers, plus other commodity markets. I think the pipeline, when I compare it with six months ago, is not dissimilar. It is quite — it is very strong.

Nathan Reilly

analyst
#45

Thanks. And how much nickel exposure is there in your maintenance order book?

Zoran Bebic

executive
#46

So yes, our exposure to nickel is extremely minimal. It's mostly or concentrated around, it would really be around our operations at Kalgoorlie. So, I mean, it's not just immaterial — it's extremely minimal.

Nathan Reilly

analyst
#47

Alright.

Zoran Bebic

executive
#48

If I had to attach a figure, I'd put it at under AUD 20 million annualized. Yeah, that's quite low.

Nathan Reilly

analyst
#49

Understood. All right, thank you for taking my questions. Very much appreciated.

Operator

operator
#50

Thanks. Our next question is from Jon Patel at Macquarie. Please go ahead.

John Purtell

analyst
#51

Hello there, Zoran and Phil. I trust you're doing well. Appreciate the commentary. Zoran, regarding that pipeline remark compared with six months back, it's fairly similar. I'm aware that you had sort of won one or two of those lithium jobs, though some remain. So basically, what occurred is that you've now been awarded that lithium work, but has it been refilled, so to speak, or backfilled by other end markets so the pipeline stays flat?

Zoran Bebic

executive
#52

Yeah, I'd say that's a fair point, and really it just comes down to timing — where that lithium work landed last year. That window held a lot of opportunities. That said, opportunities do remain in the lithium market, though they aren't as significant as what we saw 12 months ago. And you're right — the wider pipeline across other markets fills that gap.

John Purtell

analyst
#53

Zoran, when it comes to the timing on a few of these sustained business opportunities in iron ore, should we expect those to play out over the coming 6 to 12 months? BHP has given the green light to the Western Ridge Crusher Project, as we can see. That represents a $900 million US investment. So is that one illustration of it — an opportunity sitting there for you?

Zoran Bebic

executive
#54

Yeah, that’s one example, and it’s on the bigger end. There are other opportunities with other customers, and a materially larger number of cases with a smaller value. But that’s an example.

John Purtell

analyst
#55

Of course, we understand you have to get through 2024 first, but. And I guess it depends on how the pipeline shifts. But do you still see, you know, solid potential for engineering construction revenue to grow in fiscal 2025?

Zoran Bebic

executive
#56

I mean, I think the pipeline is in place. We have to lock in the right opportunities. I think there's growth potential. Yeah, and probably worth emphasizing that the Melchor acquisition is helpful within the EC business in terms of what we discussed, you know, extending our multidisciplinary capability. So having that concreting capability and detailed earthworks helps broaden our reach and opens up additional opportunities.

John Purtell

analyst
#57

Understood. Just a couple of final questions, if I may. Phil, the tax rate came in somewhat higher during the first half. It seemed to be roughly the equity accounted profit, easing in terms of full-year tax rate expectations, and just regarding that cash flow remark from earlier. So it sounds like you're still anticipating — I mean, it was a really strong cash flow. It sounds like you're still expecting some of that to moderate, but you're still expecting, you know, positive operating cash flow in the second half.

Phillip Trueman

executive
#58

Okay, so regarding your first question, Jon: the business's underlying tax rate is 30%. During this six-month period we did some work in Mongolia, and over there you're required to pay a dividend withholding tax. Strip that out, and you're back to roughly that 30% underlying rate. On cash — we're always looking to maximize and optimize the cash flows of the business. Regardless, it does. It depends heavily on how you collect, or on how your customers actually pay you at that year-end or half-year end. But the way I'm thinking about it is along the lines of a 100% cash flow conversion rate. And then, as I said a couple of questions back, some of those advances we've received — by the time the year is over, probably half of them will be gone, that's what I'm expecting. So put simply, I think about a 100% cash flow conversion rate plus a little bit extra from the advances that remain.

Julian Mulcahy

analyst
#59

Understood. Thanks.

Operator

operator
#60

Thanks, and up next we have a question from Rohan Harrison at Bank of America. Go right ahead.

Rohan Sundram

analyst
#61

Good afternoon, everyone. Regarding capital expenditure — I mean, we saw quite a notable increase during the first half. Should we expect that to continue as roughly the ongoing pace in the latter part of 2024 and possibly into 2025 as well?

Phillip Trueman

executive
#62

If we’re speaking very roughly, Rohan, our typical annual spend is around 2% of revenue. And as we’ve said across several consecutive quarters now, we saw this construction-related work approaching. That work is now secured, but we’ve had to—we took the chance to put money into, particularly, our heavy lift crane fleet, which gives us a genuinely important competitive edge. For our company, I’d expect this year’s CapEx to land perhaps around the 3%–4% range, based on what we think right now.

Roy Harrison

analyst
#63

Understood.

Zoran Bebic

executive
#64

My view is that the remark about the wider pipeline and the business outlook, which has been building over the past 18 months, also backs up the confidence behind the CapEx investment.

Rohan Sundram

analyst
#65

Yeah. Okay. And then, just on—there was a pretty meaningful increase in how much subbies made up of your total headcount. Is that going to weigh on margins as we head into the second half and FY 25 as well, maybe?

Zoran Bebic

executive
#66

No, I wouldn't say that. I wouldn't anticipate that margins are directly correlated with cost in that way. Yeah.

Rohan Sundram

analyst
#67

All right, that is—

Zoran Bebic

executive
#68

My apologies — I take it you mean the gap of a thousand between those directly employed and the overall figures.

Rohan Sundram

analyst
#69

Yeah.

Zoran Bebic

executive
#70

Take, for instance, a few cases—you know. Mongolia is likely where our operations have hit that the hardest. A fair share of those workers aren't on our direct payroll, so they fall under our oversight and direction, yet we don't employ them ourselves.

Rohan Sundram

analyst
#71

All right, thanks — that's very clear.

Operator

operator
#72

Thanks. Our following question is from Julian Mulcahy of E&P on the line. Please proceed.

Julian Mulcahy

analyst
#73

I have just a couple of questions. First, on the joint venture, revenue came down pretty sharply, and the wind farm was also completed. When do you expect that to ramp back up again?

Phillip Trueman

executive
#74

I think, for everyone's benefit, that's mainly Zenviron. During the six months, Zenviron did experience a bit of a lull. We saw some delays when it came to approvals on the projects they were hoping we'd be working on. But I think the outlook for — I mean, it's no surprise — the outlook for renewable energy projects in Australia especially is very strong, and they have a good pipeline of opportunities. It's going to depend on, you know, some easing of these issues that developers are facing regarding approvals. But I have no doubts that the future for renewable energy, and specifically for Zenviron, is very good.

Julian Mulcahy

analyst
#75

I think Zenviron—

Zoran Bebic

executive
#76

No, I just wanted to add a quick note. Zenviron was coming off a really high base last year, so with the Rye Park Wind Project, the bulk of that work was substantially finished inside that 12-month window.

Phillip Trueman

executive
#77

Julian, your question comes back to timing once more, and that really hinges on when new work gets awarded. Still, as I mentioned, plenty of opportunities are coming through.

Julian Mulcahy

analyst
#78

Maybe the second half won't produce a comparable outcome?

Phillip Trueman

executive
#79

It was... Yeah, something along those lines. Next, we think it's a 25.

Zoran Bebic

executive
#80

Yes, 25 stories.

Julian Mulcahy

analyst
#81

Right. And when it comes to the labor market, do you believe it will tighten up once more, and what do you figure that implies for margins — especially in construction, which, as you know, tends to perform quite strongly during an upcycle? Do you expect to see expansion in that area?

Zoran Bebic

executive
#82

It's difficult to give a clear answer there, since that isn't the sole element affecting margin. Of course, we would certainly welcome the margin moving higher. Yeah. We need to price projects properly and perform well, and perform well, in order to achieve better margin. And at a macro level, you know, a wider range of constraints exists that renders this fairly tough.

Julian Mulcahy

analyst
#83

Cool. Is there anything you can share about the competitive landscape, given that Tier One has emptied out over the last few years? How are the tiers below at risk of pushing up into your markets?

Zoran Bebic

executive
#84

I mean, that risk doesn’t go away, but one thing we’ve been discussing among ourselves is that over the past five years we’ve witnessed plenty of consolidation, problems, and shifts in the competitive landscape. A couple of weeks ago, though, we were actually remarking that during the last 12 months it seems to have calmed down, so within the most recent six-month stretch we haven’t really observed much change at all in that area.

Julian Mulcahy

analyst
#85

Cool. Thanks, guys.

Operator

operator
#86

Thanks. Our next question is from Richard Aplin at CLSA. Please go ahead.

Richard Aplin

analyst
#87

Hello, gentlemen, and good afternoon. I have a couple of questions. Could you confirm how much revenue Buildtek contributed to the first half 2023 result? I'm just trying to make sure I account for them, since they won't be contributing to the first half 2024.

Phillip Trueman

executive
#88

Right, Buildtek brought in no revenue at all. Its operations were shut down during the second half of the prior fiscal year.

Zoran Bebic

executive
#89

The prior year.

Phillip Trueman

executive
#90

I believe that for the prior year, the total revenue across the nine months came to roughly AUD 80 million.

Richard Aplin

analyst
#91

My apologies — I didn’t catch that. Would you mind repeating it?

Phillip Trueman

executive
#92

AUD 80 million for the nine or ten months that it generated revenue during FY 2023.

Richard Aplin

analyst
#93

Thanks. Could I get some clarity on how much revenue Melchor brought into the construction segment during the first half of 2024?

Phillip Trueman

executive
#94

Yes, Melchor, from November 1 we owned roughly AUD 25 million.

Richard Amland

analyst
#95

Right, and all of that went toward construction and not maintenance, correct?

Phillip Trueman

executive
#96

Every bit of it was allocated to construction.

Richard Amland

analyst
#97

Since I don't follow your company as closely as some of the other analysts do, this may sound like I'm going over some of the same territory. That said, in the construction segment, you reported that 44% of revenue was derived from energy transition materials. Yeah, that strikes me as a fairly heavy exposure to be carrying going forward, given that a number of those commodities are really confronting some challenges. I suppose, you know, what are — give me, and, you know, aside from, aside from the construction contracts you've already got that are currently underway, what's the, what's the kind of trend — what does the outlook look like, beyond the next six months, when it comes to activity levels in lithium and some of those related commodities?

Phillip Trueman

executive
#98

Well, you know, during the period we secured lithium contracts valued at AUD 500 million, and a lot of those are likely to wrap up somewhere in the next 12 to 18 months. I mean, really, Richard, to get to your question, I think we're very fortunate that our construction business, we can direct it toward the commodities and the sectors of the resources sector, or the segments of the resources sector, where the activity is. And as we've said, you know, apart from lithium, which certainly is, and nickel, which we, I can't remember the last time we did a job in nickel. But apart from lithium, you know, the pipeline of opportunities is very strong. So certainly iron ore has always been, and just purely by its size, is a very, very, very strong sector or segment of the market for us. That is where we see probably the next range of projects coming from. I think Zoran spoke about some of the opportunities that are available to us, in the energy sector as well. Renewables is strong. So really, it's all of the sectors that we have got experience and what we believe to be a good, strong competitive advantage in, offer a very good pipeline of opportunity.

Phillip Trueman

executive
#99

And after those lithium projects wrap up, well, then we’ll be turning our attention to opportunities in those other segments. If you look across many — well, across the whole span of my time at Monadelphous, the share of revenue in construction that a given commodity accounts for… Sorry, how much of the construction revenue pie a particular commodity represents can shift quite a bit from one period to the next.

Zoran Bebic

executive
#100

I mean, I'd say our overall exposure when it comes to energy transition metals sits at roughly 20% of total revenue, so I wouldn't characterize that as a concentration risk. And bear in mind that in the past, we've gone through stretches where you could make the case that concentration risk existed given how much iron ore activity we had.

Richard Aplin

analyst
#101

Thanks for that, Colin. So when I look at the FY 2024 guidance and how I've worked it out, it looks like the expectation is flat revenue on a half-on-half basis — first half versus second half — and it sounds as though construction revenue will rise half on half, which would mean maintenance simply eases back modestly. Is that right — is that consistent with what you're trying to project?

Zoran Bebic

executive
#102

Yes, exactly. That's how we see it.

Richard Aplin

analyst
#103

All right, I'm done on my end. Thanks a lot, everyone.

Operator

operator
#104

Thanks. Our next question is from William Park at Citi. William Park, please go ahead.

William Park

analyst
#105

Hi, Zoran and Phil — thanks a lot for taking my questions. I believe most of what I wanted to ask has already been covered, but just a couple more, if I can. First, on the EMC side, have there been any further, I suppose, discussions with your clients regarding the pricing arrangement? Any shifts or trends we ought to know about, especially when it comes to fixed price work?

Zoran Bebic

executive
#106

Apologies, Will — was your question about pricing, is that what you said?

William Park

analyst
#107

Yeah. So I mean, just to be clear, just around whether if you've seen any changes around the proportion of your work in hand in the EMC part of the business that is fixed price, under a fixed price around?

Zoran Bebic

executive
#108

Since the full year, we really haven’t observed any meaningful shift—or any meaningful shift in the conversation. At that time, we noted that, you know, we believed that in the EC business we likely had—I think the figure we gave was something like 60% fixed price and 40% other compensation arrangements with customers. But that remains the same. And beyond its staying the same, we probably also haven’t encountered many shifts in dialogue or conversations with customers, whether regarding existing work or, certainly, the pipeline.

William Park

analyst
#109

No, thank you. And just one final question. Could you comment on safety performance across the last six months? Thank you.

Zoran Bebic

executive
#110

Safety performance? Yep. Okay. So, look, we track a set of safety performance KPIs, measured against certain leading indicators and certain lagging indicators. Our two main lagging indicators are the Serious Incident Frequency Rate. And we made, you know, we made a remark that it's sitting below 0.7, which is near or around historically low levels. Those are certainly the incidents that can lead to serious injury or fatality, so we're fairly pleased with that. As for our other main lagging indicator, our Total Recordable Injury Frequency Rate, it has ticked up since June. We said it's sitting at 3.82. So there's some work for us to do in that area, and we've had and continue to see, I'll say, worse possible outcomes tied to simple line of fire injuries and plenty of hand and finger-related injuries in terms of... Yeah, well, hand and finger injuries.

William Park

analyst
#111

I really appreciate it.

Operator

operator
#112

Thanks. And our final question is from Nicholas Rawlinson at Jefferies. Go ahead, please.

Nicholas Rawlinson

analyst
#113

Hey, everyone. Just a quick follow-up question. Phil, you said there were no significant oil and gas turnarounds in the second half. I know you have pretty solid visibility on these things. So could you give us a sense of what the turnaround schedule looks like for the oil and gas projects in FY 2025?

Zoran Bebic

executive
#114

Sure, Nick — what I'm really pulling from here are the discussions I've had with the energy team.

Nicholas Rawlinson

analyst
#115

Absolutely.

Zoran Bebic

executive
#116

And I think on that point—I don't believe there are—well, there definitely aren't an unusual quantity of turnarounds coming up in the next period, though I'd say they're split evenly between the first half and the second half in FY 2025. But this—

Nicholas Rawlinson

analyst
#117

Alright.

Zoran Bebic

executive
#118

During the first half of FY 2024, the number of turnarounds we experienced was unusually high, and their scale was considerable as well. To be more specific, Shell Prelude FLNG represented a particularly large turnaround. It was the first major one.

Nicholas Rawlinson

analyst
#119

All right, that's useful. I'm finished with my questions. Thank you, everyone.

Operator

operator
#120

Thanks. That brings the Q&A portion to an end. Right now, I'd like to hand things back to Kristy Glasgow so she can offer some closing remarks. Kristy, please go ahead.

Kristy Glasgow

executive
#121

I appreciate it. That brings our briefing to a close. Many thanks to everyone for joining us today.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Monadelphous Group Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Monadelphous Group Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Monadelphous Group Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.