MYR Group Inc. (MYRG) Earnings Call Transcript & Summary
February 26, 2026
Earnings Call Speaker Segments
Jennifer Harper
executiveThanks, and welcome, everyone, to this MYR Group call. We're here to go over the company's results for the fourth quarter and the full year of 2025, which we released yesterday. On the line with us today are Rick Swartz, our President and Chief Executive Officer; Kelly Huntington, Senior Vice President and Chief Financial Officer; Brian Stern, Senior Vice President and Chief Operating Officer for MYR Group's Transmission and Distribution segment; and Don Egan, Senior Vice President and Chief Operating Officer for MYR Group's Commercial and Industrial segment. You can find a copy of the press release we issued yesterday covering our fourth quarter and full year 2025 results on the MYR Group website, myrgroup.com, under the Investors tab. A webcast replay of this call will be posted on that website and will remain available for 7 days after the call. I want to note that today's discussion may include forward-looking statements. Those statements rely on information available to MYR Group's management as of today, and MYR Group undertakes no obligation to update them; such forward-looking statements carry risks and uncertainties that might cause actual results to differ materially from what those statements suggest. As such, they are not a guarantee of future performance; for additional details, please see the risk factors covered in the company's most recently filed annual report on Form 10-K. We'll also be presenting certain non-GAAP financial measures. You can find a reconciliation of those non-GAAP measures to the most comparable GAAP measures in yesterday's press release. With that said, I'll hand the call over to Rick Swartz.
Rick Swartz
executiveThank you, Jennifer. Hello everyone, and good morning. I'd like to welcome all of you to the conference call for our fourth quarter of 2025, where we'll talk about both financial and operational results. To start, I'll give a summary of what we saw in the fourth quarter as well as the full year, and after that we'll hand things over to Kelly Huntington, who serves as our Chief Financial Officer, so she can walk through the financials in greater depth. Once Kelly finishes her overview, Brian Stern and Don Egan, the Chief Operating Officers for our T&D and C&I segments, will share a summary of how those segments performed and talk about a few of MYR Group's opportunities looking ahead. Then I'll wrap up today's call with some closing remarks before we open things up for your questions; we finished 2025 with strong financial performance, posting fourth quarter and full year revenues of $3.7 billion. A steady backlog of $2.8 billion as of the close of 2025 speaks to a healthy bidding environment and ongoing infrastructure investment aimed at meeting the rising electrification needs throughout the U.S; and Canada. The work we did this year highlights both the stability and the growth of our relationships with clients, along with our disciplined pursuit of new opportunities; we keep seeing robust bidding activity throughout our business segments, and we are watching these opportunities carefully and positioning ourselves to strategically go after and carry out projects with operational excellence. As it always has been, our success rests on an unwavering commitment to our customers through safe and reliable project execution. Our teams are devoted to assisting our customers in advancing their business objectives, and I appreciate all their continued hard work. Kelly will now share details about our financial results for the fourth quarter and full year 2025.
Kelly Huntington
executiveThanks, Rick, and good morning to all of you. During the year that concluded on December 31, 2025, annual revenues hit a record $3.7 billion. Net income for the full year came in at $118 million, along with EBITDA of $233 million. Revenues in the fourth quarter of 2025 totaled $974 million, up $144 million, or 17%, from the equivalent period a year earlier. T&D revenues in the fourth quarter reached $531 million, rising 18% versus the same period a year earlier. Within T&D, transmission accounted for $330 million and distribution for $201 million, with transmission projects contributing $64 million more in revenue and distribution projects adding $17 million compared with the prior year. Master service agreements continued to account for roughly 60% of T&D revenues. C&I revenues came to $443 million, a record for that segment, marking a 17% rise from the equivalent period a year earlier. The growth in C&I segment revenues was driven mainly by higher revenue on fixed price contracts. Gross margin for the fourth quarter of 2025 stood at 11.4%, versus 10.4% a year earlier. That gross margin improvement stemmed largely from the fourth quarter of 2024 having been hurt by certain T&D clean energy projects and a C&I project; during the fourth quarter of 2025, gross margin also benefited from productivity that beat expectations, favorable change orders and a favorable job close out. Partially offsetting these margin gains was a rise in costs tied to inefficiencies on certain projects. T&D operating income margin reached 7.4% in the fourth quarter of 2025, up from 6.7% a year earlier. The gain was mainly because the fourth quarter of 2024 had been hurt by certain clean energy projects. In the fourth quarter of 2025, T&D operating income margin also got a boost from a favorable change order and productivity that beat expectations; partially offsetting these operating income margin gains was a rise in costs tied to project inefficiencies on certain projects. C&I operating income margin was 6.6% in the fourth quarter of 2025, compared with 3.9% a year earlier. The improvement was mainly attributable to a greater share of our C&I projects moving ahead at higher contractual margins, some of which are approaching completion. In the fourth quarter of 2025, C&I operating income margin also benefited from productivity that beat expectations, a favorable change order and a favorable job close out. Partially offsetting these operating income margin gains was a rise in costs tied to inefficiencies on certain projects. SG&A expenses in the fourth quarter of 2025 were $65 million, which is $8 million more than a year earlier, driven mainly by higher employee incentive compensation costs and employee-related expenses supporting future growth. Interest expense in the fourth quarter of 2025 was $1 million, down $1 million from the equivalent period a year earlier. The drop came from reduced interest rates and smaller average debt balances outstanding in Q4 of 2025 versus the comparable period a year earlier. For that fourth quarter, our effective tax rate stood at 21.2%, versus 40.9% during the same stretch a year ago. This decline largely resulted from adjustments to state tax rates applied when measuring our state deferred income taxes, along with fewer permanent difference items. Net income for Q4 2025 hit a record $37 million, up against $16 million in the equivalent period last year. Diluted earnings per share came to $2.33, compared with $0.99 a year earlier. EBITDA for Q4 2025 reached a record $64 million, versus $45 million during the same period the prior year. As of December 31, 2025, total backlog stood at $2.8 billion, marking a 9.6% rise over the previous year. That total backlog as of December 31, 2025, broke down into $1.0 billion for our T&D segment and $1.8 billion for our C&I segment. Keep in mind that our backlog reflects projected revenue covering just a 3-month window for many of our unit price, time and equipment, time and materials and cost plus contracts, which typically get awarded under a master service agreement. That said, our master service agreements usually run for a far longer duration. Operating cash flow in Q4 2025 was $115 million, compared to $21 million of operating cash flow during the same period a year ago. This rise in cash generated by operating activities stemmed mainly from the timing of billings and payments tied to project starts and completions, greater net income and reduced contingent compensation payments linked to an earlier acquisition. Free cash flow for Q4 2025 totaled $85 million, versus $9 million in the same period last year, mirroring the gain in operating cash flow, partly offset by increased capital expenditures aimed at supporting future growth. Turning to liquidity. As of December 31, 2025, we held roughly $265 million in working capital, $59 million in funded debt, $408 million of borrowing availability through our credit facility and $150 million in cash and cash equivalents. As of December 31, 2025, we've kept up a solid funded debt-to-EBITDA leverage ratio of 0.25x. We're confident that our credit facility, robust balance sheet and upcoming cash flow from operations will let us cover our working capital requirements, back the organic growth of our business, chase acquisitions and seize chances to repurchase shares. I'll now hand the call over to Brian Stern, who will give an overview of our Transmission and Distribution segment.
Brian Stern
executiveThank you, Kelly, and hello everyone on this morning's call. Within the Transmission & Distribution segment, we posted stable results for both the fourth quarter and the entire year, aided by a solid blend of work ranging from smaller to midsized projects plus continuing master service agreements. What we achieved shows that we keep applying our foundational business tenets of safety, quality and dependable execution. Our bid pipeline stays robust, with backlog, revenue, margins and income all rising between 2024 and 2025. We keep broadening ties with clients who have been with us long term and go after chances involving new as well as current clients, leveraging the favorable industry outlook. During the quarter, Great Southwestern Construction put in place a fresh master service agreement spanning 7 years in Kentucky covering transmission line construction and maintenance work. L.E. Myers picked up a transmission project in Virginia and transmission work in Iowa; additionally, Sturgeon Electric secured two transmission projects in Oregon plus transmission work in Arizona. Station and line work in Washington, California and Arizona went to both Sturgeon Electric and High Country Line Construction. Harlan Electric was chosen to carry out numerous jobs across New Jersey and Pennsylvania. Based on electric — Edison Electric Institute industry data, investor-owned electric companies are expected to spend roughly $178 billion on transmission construction from 2025 through 2028. Such planned investment demonstrates a persistent requirement for grid modernization along with greater capacity to handle load growth. As utilities make these upgrades, we think our position is strong enough to gain from growing backlogs and long-duration project pipelines. Drawing on our experience, we keep placing ourselves to win future 765 kV projects together with 500 kV and 345 kV transmission and substation projects throughout the next 10 years. MYR Group subsidiaries stand ready to chase and complete these opportunities throughout the U.S. and Canada. To wrap up, our fourth quarter and full year 2025 achievements make us proud. We will keep bidding actively and carrying out projects of assorted capacity, size and complexity throughout the U.S. and Canada, all while holding to our steady emphasis on safety and on developing our committed workforce, who in the end make it possible for us to handle the significant work that lies ahead. At this point I'll hand the call to Don Egan, who will give an overview of our Commercial and Industrial segment.
Don Egan
executiveAppreciate that, Brian, and good morning to all of you. Solid results came through in the fourth quarter for our C&I segment, which we owe to the strength of our core markets. Steady bidding activity is still what we're seeing, along with growth in backlog, as we keep a strategic eye on new opportunities and go after them alongside our valued customers; we're confident that our capacity to carry out projects of varying sizes safely and with skill keeps generating plenty of long-term opportunities in our core markets. One of the most active investment areas across the country remains data centers, driven by the quickening demand for cloud, AI and digital infrastructure. Through 2026, industry researchers anticipate this demand will stay robust, with utilities and developers striving to grow power capacity in order to back this surge. Ongoing commitments in transportation, clean energy, wastewater and fresh water treatment facilities are likewise giving a boost to infrastructure-related construction. Clients in our ever-growing network keep bringing us in early on upcoming opportunities across these segments. An array of work is being executed and pursued by our teams throughout all subsidiaries. Multiple data center projects in Colorado, Arizona, California and New Jersey were awarded to us during this period. Beyond data centers, projects in clean energy, manufacturing and industrial work in California and Arizona were awarded to our subsidiaries. These accomplishments underscore the momentum we continue to build and our solid market presence across the U.S. and Canada. To wrap up, we're confident our core markets stay healthy, and the depth of our customer relationships keeps opening up new opportunities. Our dedicated employees drive this success, and their commitment to quality and safety sits at the heart of everything we do. Thank you, everyone, for your time today. I'll now hand the call back to Rick for his closing remarks.
Rick Swartz
executiveThanks for the updates, Kelly, Brian, and Don. Our results for the fourth quarter and for full year 2025 are something we take pride in — they showed how solid our business strategies are and how well we can hold onto and grow long-term customer relationships in both segments. With investment in electrical infrastructure picking up speed, we think our core markets are in a good spot to keep growing; we stay dedicated to building projects safely, pursuing opportunities with a strategic approach, and standing behind our customers as the energy landscape keeps shifting. Our established record of teamwork, doing things with integrity, and delivering projects people can count on, we believe, leaves us well placed for what lies ahead. It's exciting to have a meaningful part in making the electrical infrastructure that keeps our communities running stronger. I want to express my thanks to our employees for everything they contribute and to our shareholders for sticking with MYR Group. I'm looking forward to the coming year. Operator, we're ready now for your comments and questions on the call.
Sangita Jain
analystTo start, Rick, could I get your perspective regarding the sizable transmission sector? I recall you felt positive about possible bookings in late 2026 tied to revenue for 2027. I'm simply curious whether the same kind of pattern is showing up at present.
Rick Swartz
executiveYes, we are. On that front, nothing has shifted. Bringing these projects to market takes time, as you know, and that has always been clear to us. So our discussions with clients are going well, and we think we'll secure a portion of that work, which should begin to burn in '27.
Sangita Jain
analystUnderstood. Then, Kelly, perhaps this one's for you — our cash flow has been exceptionally robust during this year. What I'm attempting to determine is whether a portion of that stemmed from catching up on outstanding payments tied to solar projects from the prior year, or whether there are any significant advances on fresh projects that we ought to know about?
Kelly Huntington
executiveYes. Sangita, I appreciate that question. Indeed, it's been a remarkably strong year where cash flow is concerned, especially during the fourth quarter. Our lower DSOs are responsible for much of that. Currently — we've been sitting in the mid-50s, compared with the roughly 70 we've averaged historically. Several factors together are behind that. Looking at it year-over-year, we recorded a 16-day gain, and 11 days of that came during the third quarter. Getting past those troubled projects from 2024 accounts for part of it. Still, I'd argue a bigger contributor is simply our very robust net overbuild position, largely fueled by certain sizable fixed price assignments on the C&I side especially; thus, I believe that could amount to somewhat of a headwind going forward. And that will partly hinge on what mix of work we're awarded this year and what proportion consists of that mid- to large-sized fixed price work, which can carry a better billing profile, as opposed to something more MSA weighted — wonderful work to have, but its cash flow profile isn't quite as favorable.
Brian Russo
analystThis is Brian Russo, filling in for Julien. Could you expand a bit on how strong the T&D backlog is at $1 billion? It appears to have risen roughly 20% year-over-year, which is a fair amount of gain compared with the year-over-year trend we've witnessed over the prior few quarters. I'm just wondering whether any of the new projects — especially that Kentucky MSA agreement — are part of the December backlog? And separately, does that December backlog also contain the Xcel $500 million 5-year MSA?
Rick Swartz
executiveRegarding the backlog, I'd say where the Xcel work is concerned, very little of it sits in that backlog at present. What I mean is, we indicated it would be a slow beginning to the year, then gradually build through the year and rise. So once more, not a great deal of that is in our backlog at the moment, since we only include 90 days of that MSA work, as Kelly pointed out in her script, when calculating our backlog. Turning to the Kentucky side, that work truly won't get underway until later this year. So not a large amount of that is in there either. So again, we've observed strong activity in the markets out there, and we're choosing carefully what we take on and really concentrating on long-term relationships with clients. 90% of our business is return clientele. We're constantly seeking those one-off projects as additive. But again, how do we grow alongside our existing clients — that's where our focus lies.
Brian Russo
analystAll right, fantastic. And a quick follow-up on the transmission and distribution side. A Texas-based wires company just came out with a pretty strong updated 5-year capital plan, as we saw. So could you remind us where you stand in Texas right now? And then perhaps how active you've typically been during previous up-cycles in capital spending that we've witnessed?
Rick Swartz
executiveYeah. For the past ten years, Texas has served as a solid market for us. What I mean is, it's been a solid market. We keep watching it expand; we're enthusiastic about certain possibilities out there involving some of the 765 work, yet even some of the 500 and 345 work — that's something we handle daily; so my sense is the 765 is on the horizon. Our positioning on that has us excited. That said, once more, we're witnessing solid activity, not only in Texas, but throughout the country. Plenty of solid possibilities out there.
Brian Russo
analystAll right. And those robust C&I margins during Q4, up 6%, where does that leave us relative to the 5% to 7.5% operating margin improvement you're steering us toward for this year? Then, could you connect that with the backlog? Do projects remain that need finishing which would fall under that prior 4% to 6% goal? Or have those essentially all been used up? Meaning anything going forward truly sits within the fresh 5% to 7.5% band?
Rick Swartz
executiveWell, what I'd say is, based on our projection as we examine it across the year, operations will land in the middle portion of the margin profiles for both T&D and C&I. So within that central point, we're seeing solid chances out there; we keep observing healthy activity in the marketplace. Having said that, nothing has shifted from our prior quarter comments on either front — from a revenue perspective, we're looking at roughly 10-ish percent expansion across both segments and for the company as a whole. Then we expect to operate in that — that central portion of the range. So strong prospects exist there, and I believe we'll keep doing whatever we can to lift our margins from where we sit regarding what we accomplish on the prefab side, on the efficiency side, on making better use of our equipment, and we'll keep striving to optimize on that front.
Justin Hauke
analystThanks. I've got a few quick items. First, regarding your backlog, you break it into two pieces: what you anticipate booking within a year, and what you expect to book after that. It seems almost all of this quarter's backlog growth came from the longer-dated portion. I'd like to understand what's driving that. Does it involve some of the C&I data center projects you mentioned? Is project duration simply stretching out because the scale is increasing? Or could you just walk through how we should think about it?
Rick Swartz
executiveOf course. When it comes to our bigger projects, the timelines stretch out somewhat. A number of those data centers need roughly 18 months to build, or 18 to 24 months for the larger ones, and the same holds true for transportation work. Certain portions of that extend even further — those are 4- or 5-year projects. That said, we're seeing solid activity in the small and midsize segment, which is moving fast. With the bigger projects, though, construction simply takes more time.
Justin Hauke
analystAlright, and for my follow-up — apologies for focusing narrowly here — but clearly, winter conditions have hit many regions. The first quarter typically isn't your strongest one compared to summer; still, I'm wondering whether there's anything on your radar or anything you'd like to share regarding possible weather effects during Q1 that would be out of the ordinary and have already happened? Or perhaps that isn't the case — maybe it's simply consistent with typical seasonal patterns?
Rick Swartz
executiveFrom our standpoint, our planning has always assumed typical seasonal patterns. There will inevitably be certain storms occurring if it's — my sense is that < > doesn't necessarily hit us the same way that, say, extremely wet conditions do, when we're unable to get across the right-of-way. That tends to have a somewhat greater impact on us. That said, we're continuously watching conditions, and what truly matters is which — which projects end up impacted. You'll notice in any particular region, I mean, a location 50 miles distant can be heavily impacted while another might see nothing. So once more, conditions haven't hit our operations uniformly across, I suppose, the entire nation. Thus, I'd say we will — we keep examining that. The weather represents the largest potential disruption for us. Yet once more, it hasn't hit us nationwide as a whole, only within certain specific regions; and because of that, occasionally we get some balancing from a particular storm and other categories of work we perform for restoration. Still, once more, our core operations consist of routine MSA activity along with standard construction projects. We're happy to take storm assignments. That said, we don't rely on them.
Kelly Huntington
executiveAbsolutely. And let me just give a slightly wider frame here, Justin — when we look at Q1 revenues, our expectation is that during the first quarter we'll come in somewhat above that roughly 10% growth pace for the full year, and the real reason is that in the first quarter of last year, we got off to a somewhat slower start. So relative to the remaining quarters, it's a somewhat easier comparison. So as you work through your modeling, keep in mind that we'd anticipate somewhat stronger revenue growth in Q1.
Caitlin Donohue
analystIf we zero in on data centers alone, you mentioned several awards during the last quarter. As you talk with your customers, how do you expect that project pipeline to take shape for 2026 and 2027?
Rick Swartz
executiveOn that front, the discussions remain robust. It isn't only '27 and '28. What I mean is, we're talking with customers about periods that extend far past that. So once more, I believe our awards tend to be uneven simply because finalizing projects takes time. Yet again, promising talks lie ahead; so there's solid activity in that market. Still, we don't rely entirely on that market alone. We appreciate the diversification we get from transportation, health care, and some of the other work we perform. So there are strong possibilities there as well.
Caitlin Donohue
analystThat helps. Now, regarding how we'll deploy capital in 2026 — CapEx has ticked up somewhat, and you've repurchased shares before. What's your thinking on MYR Group's approach for this year?
Kelly Huntington
executiveRight, we see strong chances to keep expanding the business organically as well as via acquisitions. So, as we've mentioned previously, growth will remain the top priority in how we allocate capital. Share repurchases are something we do when the opportunity arises, and the past 2 years illustrate that well — we deployed more than $150 million at an average price of $117. That said, at this moment, our attention is really on the growth prospects in front of us, both organic and through acquisitions.
Brian Brophy
analystI'd like to pick up where we left off regarding that sizable transmission chance and the possible awards you might land there. If you do land something in the back half of '26, the way you hinted at, would those projects add to growth in 2027? Or would you need to take resources from other places to satisfy some of that demand?
Rick Swartz
executiveIt's not my expectation that we'd need to take resources from anywhere. We've been successful at keeping our people, bringing new ones in, and helping them grow. So from where we sit, that's additive. And it carries into '27 and beyond. So the work beginning in '27 isn't the whole story. Our view is that this cycle will run quite a bit longer. So I'd say there's a decade of growth ahead, and wherever we can, we'll take advantage of it, and we believe some excellent opportunities are headed our way.
Brian Brophy
analystGreat. Yeah, that's encouraging to hear. So, following up on that point, what's your view on how some of those big transmission project awards might shape the overall business — I mean the margin profile, not necessarily project by project, but in terms of how well you're using capacity. Should we see that as something that drives margins?
Rick Swartz
executiveYes. I'd say it can produce, I suppose, slight — improvements to margin on that front. Once again, it comes down to finding ways to get more out of our equipment, and how we can reduce field labor while handling more work through prefabrication or kitting. We constantly evaluate that area and aim to serve as a problem-solver for the people we work with. With that in mind, we're continuously trying to improve our margins. That said, our ties to customers stretch over the long haul. Because they operate in a regulated industry, we'll keep pressing for better margins wherever possible — though mainly by becoming more efficient, rather than by doing what I'd describe as squeezing clients unfairly. Our focus is genuinely on the long term. Once again, repeat customers account for more than 90% of what we do, and preserving those connections is always a priority.
Manish Somaiya
analystCan you hear me?
Rick Swartz
executiveYes.
Manish Somaiya
analystAll right, fantastic. Rick, you're up first with my question. The press release mentioned that the bidding landscape is holding firm. Could you perhaps help us understand what you're observing regarding pricing across different regions and end markets? Also, which business opportunities are you declining because the pricing isn't appealing? So maybe you could just paint a picture of what's happening out there in the market.
Rick Swartz
executiveFor our part, I'd describe it this way — we maintain a targeted roster of clients; our aim isn't to serve everybody, if that comes across clearly. Take C&I, for instance: when it's a client we've partnered with over many years, or someone with whom we have an ongoing relationship or the potential to develop one, that's where our attention goes, rather than one-time jobs. Bidding on a project with 20 competitors isn't something we pursue; what we prefer are clients who keep limited bid lists, or those with whom we've formed teaming agreements. On that front, there's solid activity and solid prospects. Speaking region by region, as you look at geographies throughout the U.S., certain areas remain somewhat tighter than others, yet we anticipate that places which might be slower right now will pick up later on. So that's something we keep watching at all times. We operate more than 65 offices throughout the U.S., plus a number in Canada; because of that, we constantly draw on regional know-how to determine which projects to pursue, which suit us well and which don't. Throughout that process, we're always assessing those prospects; and once again, we're witnessing strong activity everywhere we operate.
Manish Somaiya
analystI recall we touched on data centers a little while ago. Perhaps Don could give us additional detail. On the data center front, who are the customers — hyperscalers, GCs, developers? If you could just give us some idea, that would help. Then, when it comes to backlog, clearly everyone is taking on more data center work. Would you describe the C&I backlog as diversified? Or does it lean more toward concentration?
Don Egan
executiveLet me take that first question. Our backlog is highly diversified. You are entirely right. There's a great deal of activity out there in the market, and we're speaking with end users, the hyperscalers, general contractors, developers. Those conversations happen continuously and quite frequently, if that addresses what you were asking.
Manish Somaiya
analystWhen it comes to data center customers, who are they — hyperscalers, or general contractors and developers?
Don Egan
executiveLike I said before, every one of those groups; hyperscalers hear from us daily and weekly, and so do general contractors, end users, and owners.
Manish Somaiya
analystAll right, and for my final point, Rick — at a broad level, clearly you folks don't provide guidance, but when you consider your own internal benchmarks and targets for '26, what would the puts and takes be? How ought we to frame the risks and opportunities?
Rick Swartz
executiveLet me circle back to Don's question real quick — the one you posed on his behalf. What I'd add on the data center side is that new construction isn't the whole story. I think that's what grabs the headlines, but plenty of it involves retrofits in buildings that already exist. Take existing data centers that have been around — I mean, these are living buildings; the technology keeps changing all the time. So when that happens, that repeat work matters a great deal to us. And once we're inside a data center, we usually remain there quite a while. So it isn't only new builds; that retrofit work counts too. That's the sole thing I'd tack onto that. As for the puts and takes looking ahead, the largest impact we can ever have on the T&D side is weather. Beyond that, the activity in the market — unless something emerges that we don't currently see from any of our client conversations — would be some sort of market slowdown. But we don't see that, nor do we anticipate it. So really, weather on our T&D is the biggest impact; and then the timing of these projects, how fast they roll out, would be the other sort of risk out there, because it's not whether these projects are going to be built, it's when. So at times you can see a 2- to 4-month push on projects, but it's not as though they're going to be pushed out years; and that's kind of how we see it now. And then the other side on the T&D side that I'd probably highlight is permitting. Sometimes that can push a project out a little bit. But again, it's not if the projects are going to be built, it's when; so again, good activity on both sides, both T&D and C&I.
Tim Moore
analystNice work on the increase in your backlog and the book-to-bill. Somebody already covered my question about the equipment utilization tailwind for T&D. That leaves me with just 2 questions. Rick, could you perhaps take us through — or Kelly, you could add detail too — the way you weigh being selective about staffing for, say, an 18-month data center project against cross-selling into a mid-sized utility project? I realize those are different segments, but I'm curious whether you could say more about how regional staffing comes into it and about the cross-selling chance. And also whether it's a new customer, since no more than 90% are incumbents.
Rick Swartz
executiveSure, I'll begin with that. As you just noted, return clientele accounts for 90% of our business. That's our constant priority. Cross-selling is something we continually pursue. Plenty of chances exist there, particularly with data centers, where the substation on that side may sit within the owner's scope instead of the utility's scope; either way, we can build that part of the project. I'd say those chances are something we constantly evaluate. Our long-term clients come first, always. The one-off jobs, we'll pick those up afterward. If someone is only going to put up one project and then stop, that's likely not where our attention goes. But when someone is going to put up multiple projects, that's where our attention goes. And I believe we've performed very well on, for instance, certain data centers where facilities are — they put up one building, then they proceed to the next. As they complete their campus, that's an excellent situation for us. With some of them, we might be on — for instance, we're on building 3 out of perhaps a planned 12 buildings. So once more, this extends many years ahead, and that's genuinely where our attention goes. Kelly, would you like to add?
Kelly Huntington
executiveI think you covered that well, Rick. Thanks.
Rick Swartz
executiveAlright.
Tim Moore
analystThanks, that's quite useful. One more thing I wanted to ask — with the liquidity you have, the cash on hand, and the chance to do bolt-on acquisitions, could you give a big-picture view of how you think about it? On the T&D side, does the electrical contractors area come first for you? And when it comes to C&I, is the goal to gain geographic scale the way you're doing in the Southeast? I'm just curious whether you can share a bit more detail.
Kelly Huntington
executiveAbsolutely. I can take that one to begin with...
Rick Swartz
executivePlease, Kelly.
Kelly Huntington
executiveRegarding T&D, I'd simply note that electrical contractors are absolutely our main emphasis. Our geographic footprint is genuinely strong throughout the U.S., and extending into Canada and Ontario for T&D, so we're also evaluating chances in ancillary services such as right-of-way, foundation, or environmental work. Those could appeal to us too. When it comes to C&I, from a strategic standpoint I'd describe two main filters. The first is geographic alignment, since our coverage isn't nearly as steady as what we have for T&D, and the second involves examining carefully which end markets they cater to. So, does that possible acquisition share a comparable profile in terms of exposure to those faster-growing, typically less cyclical, more intricate core markets that define us? Those are the key factors we examine, with our attention still squarely on tuck-in acquisitions within familiar areas and risk profiles we grasp.
Jon Braatz
analystRick, your markets are performing really well, and I believe you've mentioned that on the top line, you might see revenue growth in the 7% to 10% range; but if opportunities come along as they could, do you possess the ability, the capacity, the workforce, and the infrastructure needed to perhaps speed that growth up as we move ahead?
Rick Swartz
executiveYes. I mean, that opportunity is there for us. If you look back at our history, I think during certain years we grew beyond that, and in other years, we reined it in somewhat. Again, it comes down to when awards land, how they land. I see solid opportunities out there, but our real focus is controlled growth as well. At this point, I think anyone could add revenue, but could they do it profitably; and for us, it's about keeping that right amount of growth, so we can be profitable. We are definitely capable of doing more than that; but for this year, we've said we anticipate growing in that 10%-ish range. So a bit more than the 7%; but again, ensuring we have controlled risk and then we pursue the right opportunities.
Jon Braatz
analystAbsolutely. With how strong the market is, plus all those projects out there and everything else, my feeling is you've got room to be pickier, and perhaps the risk profile attached to the work you're taking on has gotten better. Would it be fair to put it that way?
Rick Swartz
executiveAbsolutely. Whenever we choose our projects, our constant focus is on how we cap our exposure, how we work alongside our customers, and how we ensure those sorts of conversations happen. Still, taking risk out of our projects matters a great deal to us, and that's among the assessments we make when reviewing projects — I'd say the risk sitting in our backlog right now is lower than what was in our backlog 12 months back or 5 years back.
Rick Swartz
executiveWrapping up, Kelly, Brian, Don, and I want to express our genuine appreciation for your time on today's call. That covers everything from my side, and we're eager to collaborate with all of you going forward, as well as reconnect during our upcoming conference call. In the meantime, please take care.
Operator
operatorThanks. That brings us to the end of today's conference call. We appreciate everyone for joining in, and at this point you're free to disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete MYR Group Inc. transcript — plus 131,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to MYR Group Inc. earnings transcripts and 131,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in MYR Group Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.