Tom Palmer

executive
#1

Hello, everyone, and thanks for being with us on Newmont's call covering results from the third quarter of 2021. Joining me today are Rob Atkinson and Nancy Buese, plus additional colleagues from our executive leadership, and once my remarks conclude we'll take your questions. Ahead of getting started, I'd ask you to review the cautionary statement and look at the SEC filings we've made, all of which are accessible through our website. Newmont performed well against a difficult third quarter, producing robust free cash flow, keeping up industry-leading returns for shareholders, and putting money into profitable projects, among them our newest, Ahafo North, which received board approval during July. We achieved these quarterly results while still navigating the shifting and increasingly complex conditions of the worldwide pandemic, and our commitment to safeguarding the health and well-being of our employees and the communities near our operations has not wavered. Across the mining industry, we keep encountering pandemic-driven difficulties unrelated to health, such as shortages of labor, escalating costs for inputs, and interruptions to supply chains. As a leader in this industry, Newmont stands in a strong position to meet these difficulties, drawing on our established operating model and diversified worldwide portfolio to create long-term value from assets we manage responsibly. Now, moving to our results for the quarter, let's review the highlights. During Q3, Newmont produced 1.4 million ounces of gold. On top of that, we had 315,000 gold equivalent ounces coming from copper, silver, lead, and zinc. Our operating cash flow reached $1.1 billion, and we also generated strong free cash flow of $735 million — $715 million of which was attributable to Newmont. With a clear strategic direction guiding us, we continue to take a disciplined and balanced approach to prioritizing capital allocation. We're holding $7.6 billion in total liquidity, and we've maintained a net debt-to-EBITDA ratio of 0.2 times. That keeps our financial flexibility intact as we continue reinvesting in the business and returning cash to shareholders. At the start of this month, we shared news about switching Boddington over to a completely self-driving haulage operation — a significant step forward for Newmont and for gold mining overall. Safety and output at this key asset get a boost from our 36-truck fleet. Beyond that, we keep putting money into and building out our highest-returning projects slated for the near future, such as Tanami Expansion 2, Ahafo North, the shift toward a more efficient underground extraction approach at Ahafo South, and Yanacocha Sulfides. Over the past quarter, we executed roughly $100 million worth of share repurchases when opportunities arose, at an average price under $56 each, and we issued a third-quarter dividend amounting to $0.55 per share, equal to a yield exceeding 4%. A year ago, we introduced a dividend framework that leads the industry and sets a straightforward route to consistent, dependable payouts. Over the last four quarters, Newmont has returned more than $2 billion to shareholders through dividends and buybacks, which reflects our belief in the enduring worth of our business and our capacity to stay financially flexible as we keep investing steadily in our operations. Here at Newmont, we've assembled a robust and diverse portfolio of mines and projects around the globe, and from our perspective, what matters is where those operations are located. Out of the 12 mines we run plus our 2 joint ventures, over 90% of attributable gold production originates in top tier jurisdictions — that's our label for countries that all three of Moody's, S&P, and Fitch rate somewhere in the A&B bands. Underneath that portfolio lies the strongest organic project pipeline anywhere in the gold industry, covering both greenfield and brownfield chances, managed through an integrated operating model whose track record shows value delivered to every stakeholder. Newmont has maintained a project pipeline with no equal and a leading industry position, opening the way to steady output and cash flow well beyond the 2040s. Every one of our operations carries near mine exploration upside capable of tapping existing infrastructure and extending mine life. Because our brownfield holdings are both steady and substantial, we're able to conduct careful, measured exploration in several of the globe's most promising greenfield areas. This quarter, we continued moving forward with projects close to completion, including the second expansion at Tanami, located in Australia's Northern Territory. That effort—building a production shaft reaching 1.6 kilometers deep along with the necessary infrastructure—locks in the operation's long-term role as a durable, inexpensive source of output, and it creates a base for additional prospecting within the richly mineralized Tanami region. Turning to Ahafo North, which we greenlit in July: that development expands the footprint we already have in Ghana, adding over 3 million ounces of gold output over a 13-year initial mine life. Then there's Yanacocha Sulfides, a project set to keep this cornerstone asset producing for many decades ahead. Newmont remains committed to Yanacocha Sulfides and plans to put in no less than $0.5 billion between now and the end of 2022 to advance critical path work — detailed engineering, long lead procurement, earthworks, and building accommodations for the construction crew. Like we said before, given how things stand with the pandemic in Peru right now and the possibility that more contagious variants could emerge, our decision on full funding for the sulfides project has been moved to the second half of 2022, and we'll keep advancing the project whenever pandemic conditions allow. A couple of weeks back, I was able to travel to Peru, where I sat down with government officials and other important stakeholders to talk about a path forward that's safe and works for everyone. I came away from those conversations feeling encouraged, and I'm eager for this next chapter and for Yanacocha's long and profitable history to continue. This global pandemic has tested all of us, and it will go on testing all of us for a while longer. Before we go further, I'd like to recognize how hard everyone across our sites has been working to protect both employees and the people living near our operations. Rob managed to get to Ghana during the previous quarter, and as this photo shows, he saw firsthand the crucial work our people are doing — adapting and pushing forward through the COVID pandemic. Across 2020 and 2021, Newmont directed over $2.7 million in Ghana to COVID relief and community support, plus $1.4 million for health screenings and security measures aimed at protecting our employees and their families. Teaming up with Ghana Health and Education Services, that money helped pay for several things: building out detailed rules and safeguards across Ahafo and Akyem; distributing PPE and medical items at our operations, area health centers, and other local organizations; acquiring PCR equipment to enable reliable testing and research; providing refrigeration units to track temperatures and store vaccines; using local radio shows to spread awareness and key health and safety messages; and fundraising efforts that deliver needed lesson plans to pupils during school closures. Another priority for us is supporting Ghana’s immunization effort. Alongside the American Chamber of Commerce in Ghana and Ghana Health Services, we’re working to secure and deliver roughly 100,000 vaccines across that area. At Newmont, we firmly believe COVID-19 vaccines are essential in curbing transmission of the virus, and if immunization coverage doesn’t increase substantially worldwide, the effects on our workforce and our operations will persist.

Tom Palmer

executive
#2

We've now reached a purposeful choice to move toward a future where ultimately all of our team members across the globe will be fully vaccinated, and we are closely monitoring the federal vaccine mandates that are already on the books and complying with them. We're taking this major step because we genuinely believe that vaccination is a vital part of helping the world get past a pandemic. Since March of last year, we've focused on operating responsibly and efficiently while protecting the health and safety of our workforce and the surrounding communities from this virus. With the government's mobility limits still in place, COVID-related protocols continuing to be used, and intense competition for labor in Canada and Australia, we continue to experience productivity impacts at a number of our sites. Due to those impacts, along with some cases of unexpected equipment reliability issues and weather-related challenges, we've decided to update the guidance we issued for the full year 2021. We now expect production of about 6 million ounces of gold, which is slightly below the range we originally guided, and for copper, silver, lead, and zinc we are reaffirming our original guidance of 1.3 million gold equivalent ounces. Combined, that totals 7.3 million gold equivalent ounces. That's the largest figure of any company in our industry and marks an increase of almost 400,000 ounces compared with the previous year. The changes from the gold production outlook we initially gave are mostly due to problems at Boddington, including unusually severe weather with heavy rain, shovel reliability issues, and operational delays related to managing bench hygiene as the mine goes deeper into the pit. On top of that came the ongoing ramp-up of the autonomous haulage fleet while the site fine-tunes this technology for use in a deep open pit mine, something never attempted before in mining. As a result, Boddington moved fewer tonnes than expected, which hurt our ability to access high grades and reduced Boddington's forecast gold production for the full year by about 140,000 ounces. As Rob will explain later, we are highly confident that the overall efficiencies autonomous haulage delivers will far outweigh any near-term production impacts at Boddington in 2021; additionally, at Nevada Gold Mines we are coping with the aftermath of the issues our operating partners flagged in their release the prior week. Carlin and Cortez are expected to finish at the low end of their annual guidance ranges, largely due to the impact from the failure and subsequent repairs of the mill at Carlin's Goldstrike roaster, and Turquoise Ridge is now expected to come in below its annual guidance range. As a result, annual gold production from Nevada Gold Mines is expected to land at the bottom of our annual guidance range. Beyond that, as I noted earlier, the global pandemic continues to shift and affect every one of our operations. Tanami moved to care and maintenance during late June and early July, and we continue to experience lower productivity caused by COVID-related absenteeism along with a tighter labor market up in Canada. With mill prices higher, output has come down, which has pushed our expenses upward throughout this year. Looking at 2021, we expect gold costs associated with sales to reach $790 per ounce, and all-in sustaining costs ought to come in at $1050 per ounce. Worth noting is that a $1200 gold price assumption formed the foundation for our regional guidance, and that identical figure still applies for long-term mine planning and reserve modeling, keeping us disciplined across every operation. Even so, since gold prices remained high for the entire year and investors shared their views with us, we're now providing an updated full-year cost outlook based on an $1800 gold price assumption. We expect those gold prices to carry into Q4, which would tack on approximately $50 per ounce to all-in sustaining costs via inflation, larger royalty payments, and production taxes. Finally, our development capital estimate is declining, moving from $850 million down to $700 million, because certain spending related to the second Tanami expansion is shifting into 2022 with no impact on the project schedule. At present we're putting the finishing touches on the 2022 business plan, and relative to this time last year, our understanding of how the global pandemic affects us is much stronger. Looking ahead to 2022, we expect production costs under an $1800 gold price assumption to be similar to those of this year. Gold output ought to increase about 5% compared with 2021 as we continue managing pandemic-driven labor shortages that reduce productivity across our operations. CAS and AISC per ounce should remain broadly in line with 2021, since we're building greater inflation-driven costs, higher metal prices, and ongoing COVID-related safety protocols into our forward assumptions. Capital for 2022 is the same as what we initially laid out, as we enter a period of major reinvestment — a crucial element of raising production, improving margins, and extending mine life. Returning this money into the business will enable Newmont to steadily increase output and improve its costs over time through our portfolio of world-class, long-life operations. We look forward to sharing further details on our long-term outlook during the annual guidance webcast in early December. With that, I'll pass it to Rob for a closer look at our global projects and operations. Over to you, Rob.

Rob Atkinson

executive
#3

Thanks, Tom, and hello everyone. As Tom said, COVID-19 is still causing difficulties throughout our operations and joint ventures, and I feel great pride in our team members who keep delivering safely each and every day. Although infection numbers are falling and more people are getting vaccinated close to where we operate, the ripple effects of supply chain interruptions and tighter labor markets are bringing fresh complications to handle. Input commodity prices, including steel and diesel, face growing pressure, along with freight costs and delivery schedules that are hard to predict. For instance, digital expenses have risen sharply lately, which has added $7 per ounce to our all-in sustaining costs versus the prior quarter and more than $15 per ounce versus a year ago. We are also monitoring closely and striving to lower voluntary attrition rates throughout our worldwide operations and tight labor markets, especially in Canada and Australia, by building an extraordinary shortage of workers that hurts productivity. Such inflationary patterns could emerge in upcoming contract negotiations, and we anticipate possibly noticing further effects as soon as the fourth quarter, and even though it is tough to forecast if these patterns will last over time, I have faith that our size, solid alliances, and demonstrated operating approach put Newmont in position to obtain the most competitive supply agreements and minimize the consequences for productivity and expenses. Moving to our regional reports, beginning with South America. Merian is still a robust performer in that region and is marking 5 years since it declared commercial production in October 2016. The operation keeps using a strategy of blending ore to maximize mill results, which helps counterbalance unscheduled mill repairs and small setbacks caused by heavy rainfall early in the quarter. In addition, Merian achieved greater tonnes mined and grade processed, and we anticipate this pattern will hold for the rest of the year and into 2022. Cerro Negro keeps enhancing productivity and results, with substantial gains in tonnes mined and processed every quarter. The on-site crew is handling pandemic effects as well as it can, and I take pride in the mitigation measures, shift change improvements, and general efficiency gains that helped counterbalance interruptions from earlier in the year. Because of the pandemic's impact, the site has achieved slower development rates in 2021, which restricts access to higher grade ore and lowers output in the fourth quarter and into 2022. Still, in spite of virus-related hurdles, the site keeps advancing upcoming organic growth initiatives, such as building San Marcos and the expansion in the Eastern District, which could potentially prolong mine life past 2030. Yanacocha has likewise faced ongoing pandemic-related difficulties affecting productivity, largely because of less available labor. To counter these issues, the sites made changes to mine sequencing, concentrating on higher grades, effective haul truck paths, and ideal ore placement on the leach pads. Consequently, Yanacocha produced ore of a high grade and achieved better recovery from the leach pads. As we covered in our 10-Q for the third quarter, work on a detailed study continues to advance so that water management requirements can be defined more precisely, together with other closure activities, and an update on this will come with the fourth quarter result. As Tom said, we are advancing the Yanacocha Sulfides. This is a project that could extend the mine life of this cornerstone asset far past 2040. Now to our North American region. Across our Canadian operations — Musselwhite, Eleonore, and Porcupine — COVID absenteeism and a tighter Canadian labor market keep weighing on us, and we anticipate these sites will land at the low end of our annual production guidance ranges, or below them. We anticipate these labor trends carrying on into 2022, with the impacts having been especially significant at Musselwhite and Eleonore, since shortages of labor and limited access to specialized services have led to fewer tonnes mined and processed than planned. Porcupine produced greater tonnes mined from the Hollinger open pit, which helped offset the effect of graphite levels in the oil plant underground coming in higher than anticipated, causing drilling delays and, in turn, meaning less high grade ore was mined from underground. Last month I went to our Canadian operations, and I am happy to say we are achieving considerable positive inroads at Musselwhite, Eleonore, and Porcupine toward raising development rates by using jumbos and tele-remote loaders, pushing productivity aggressively through carrying out the suite of our full potential initiatives. Backed fully by our subject matter experts assigned to these sites, these initiatives are going to boost efficiency and production. On to CC&V, where the mine saw lower grades and recovery during the third quarter. Even so, greater tonnes mined and adjustments to mine sequencing in the third quarter should lift leach pad production in the fourth quarter and through 2022. Last, Penasquito turned in another strong third quarter, driven by greater tonnes mined and processed, along with robust recovery rates from several full potential improvements. Since being acquired, Penasquito has generated more than $375 million in free cash flow improvements, and over 80% of that value has come from mining and processing improvements, which keep creating value now and will continue to do so far into the future. Turning to Australia. Tanami posted solid performance in the third quarter, since higher grades helped counterbalance fewer tonnes mined and processed, which followed from the COVID-related care maintenance period in late June and early July. Even though this stretch cut the site's output for the whole year by roughly 40,000 ounces, Tanami remains up and running, is doing quite well, and should absolutely post a robust close to the year. On top of that, the crew pushed Tanami Expansion II further along, and in Q3 we moved ahead with building the head frame, and by now we've finished close to 70% of the reaming work on the shaft that goes down almost 1 mile, still on schedule to bring meaningful gains in ounces, costs, and efficiency during the first half of 2024. As Tom noted, heavy rain hit Boddington in the third quarter, which held back the autonomous haulage ramp-up and cut the tonnes mined. I'm happy to report that Boddington keeps delivering outstanding mill results, with close to 11 million tonnes processed in the third quarter; we're also proud to have rolled out the gold industry's first autonomous haul truck fleet, a first for our sector. I want to thank our people and our partners at Caterpillar for their continued partnership, commitment, and energy as Boddington keeps ramping the truck fleet toward full productivity and keeps refining the technology for a highly productive operation in a deep open pit mine. Getting this project done on time and on budget through a global pandemic is a massive achievement, drawing on Newmont's scale, technical know-how, and partnerships to manufacture, deliver, assemble, commission, and operate a fleet of 36 autonomous trucks in under 18 months. Looking forward, we anticipate better grades and more tonnes mined, thanks partly to the efficiencies that come with autonomous haulage, lifting production in the fourth quarter and into 2022. Lastly, on to Africa. The team turned in another steady performance despite extremely heavy rain in the third quarter, since greater throughput and robust recoveries helped counter unplanned mill and equipment maintenance. The site is in a good spot to hit better grades and produce its highest output of the year in the fourth quarter. Ahafo posted a very strong third quarter. Greater tonnage from the Subika open pit and better mill performance helped counter haul truck availability issues at our underground operation. At Subika, we keep moving forward on developing our new underground mining method, sublevel shrinkage, and we expect to hit full production by year-end as planned, boosting grade and underground tonnes mined. Beyond that, the team keeps advancing Ahafo North. We've started mobilizing key personnel, and I'm glad to say engineering is about 80% complete. We remain engaged with local communities and regulators to secure a mutually beneficial path forward as we develop this prolific orebody and build the next generation of mining in Ghana. With that, I'll hand it over to Nancy on the next slide.

Nancy Buese

executive
#4

Appreciate that, Rob. Because of the power of our asset base and the way our operations work together as one integrated system, Newmont is now in the best financial position it has seen in a century, driving durable value via a capital allocation strategy more disciplined and balanced than any other in the sector. Now let's walk through the numbers. In Q3, we brought in $2.9 billion of revenue, and gold sold at an average realized price of $1,778 an ounce. Adjusted Net Income was $483 million, which works out to $0.60 per diluted share. On the adjusted EBITDA side, we came in above $1.3 billion. That's lower than what we posted in the same quarter last year, and the reasons are softer gold prices, lower sales volumes, and cost pressure tied to the global pandemic. Free cash flow was strong at $735 million, and 97% of that belongs to Newmont. Quarterly free cash flow doesn't match the record we set last year, but it did improve 27% versus the second quarter. Because our cash flow generation is unmatched, Newmont can return superior value to shareholders, primarily via our industry-leading dividend framework. This week we declared a regular quarterly dividend of $0.55 per share. That represents a 38% increase over the prior year and is consistent with our last three quarters. Our regular dividend provides a yield of roughly 4%, which is the highest return of this kind anywhere in the gold sector and places Newmont within the top 10% of large-cap dividend payers on the S&P. For the third quarter, GAAP net loss from continuing operations came to $8 million, equal to $0.01 per share. Among the adjustments was $0.46 related to a loss we recognized on the pending divestiture of the Conga mill assets, which sit in care and maintenance in Peru. By selling these assets, we reduce storage expenses while keeping long-term optionality intact for how the project might be developed down the road. Further adjustments consisted of $0.12 for unrealized mark-to-market losses on equity investments, $0.10 for reclamation and remediation adjustments at historical mining sites, $0.08 for tax adjustments and valuation allowance, and $0.01 in other charges. After you factor in those changes, our adjusted net income for Q3 came to $0.60 for each diluted share. One thing to keep in mind: since we file under U.S. GAAP, the adjustments we make to net income leave out $23 million in extra expenses we took on during the quarter because of COVID. Had we accounted for those costs, net income per share would have been roughly $0.03 higher, and we anticipate carrying these expenses for the rest of the year, since keeping our employees and the surrounding community healthy and safe remains our top priority. Newmont's approach to dividends depends on our peerless capacity to produce attributable free cash flow. If gold climbs past the $1200 baseline we've assumed, each additional $100 in the price translates into $400 million more in attributable free cash flow annually for Newmont. No other gold mining firm can match Newmont's capacity to produce attributable free cash flow on that scale. As Tom mentioned, it's now been a full year since our dividend framework was rolled out. That framework guarantees investors a consistent yearly base dividend of $1 per share, along with an opportunity to capture between 40% and 60% of any extra attributable free cash flow generated once gold exceeds $1200. This approach gives shareholders dependable, industry-best returns that are steady and predictable, and it reflects both our belief in where we're headed over the long haul and our ability to maintain discipline with capital. For the third quarter, the dividend we declared came in at the same level as the second quarter, based on a gold price assumption of $1,800, a 40% distribution, and incremental free cash flow. Alongside our Board, we continue to evaluate the dividend on a quarterly basis, looking at how the business is performing operationally and financially as well as what we expect over an extended horizon. Our priorities for allocating capital remain unchanged: put money back into the business through exploration and organic growth projects, preserve balance sheet strength and optionality, and deliver industry-leading returns to shareholders. Throughout the year, we met all of those objectives by pushing forward with reinvestment in the company that supports profitability, particularly via the strides made on the Tanami expansion, Ahafo North, and Yanacocha Sulfides. We rolled out the gold mining sector's first autonomous haulage fleet, which made Boddington safer and more productive. In May of this year, we completed the GT Gold acquisition. We gave back over $1.3 billion to shareholders in dividends, plus close to $250 million via opportunistic buybacks. Our balance sheet stayed solid, with $7.6 billion of liquidity and net debt-to-EBITDA at 0.2 times. That keeps Newmont financially strong and flexible enough to ride out price swings, helped by a weighted average cost of debt of 4.3%, among the lowest in the industry. As we look to the future, we have strong conviction in our capacity to meet our rigorous capital deployment objectives, generate lasting worth for the enterprise, and keep our standing as the top gold firm globally. With that said, I'll return the floor to Tom for closing remarks.

Tom Palmer

executive
#5

Appreciate that, Nancy. When it comes to tier-one assets with lengthy mine lives, Newmont holds a collection that nobody else can match, along with an organic development pipeline that stands above anything else in this sector. Even though our company, and the mining sector more widely, keeps confronting a variety of obstacles created by this worldwide pandemic, I have every confidence that our central strategic priorities, our demonstrated method of running the business, our exceptional ability to execute, and our industry-leading ESG approaches mean Newmont is set up to stay the top gold producer globally and keep generating lasting worth for each of our stakeholders; having said that, I will hand things to the operator so the phone lines can be opened for questions.

Fahad Tariq

analyst
#6

Hello, and good morning. I appreciate you taking my question. To start, regarding Slide 11 and the North American operations — could you discuss what measures are being implemented to tackle absenteeism at Musselwhite and Eleonore? From what I understand, a number of your Canadian peers aren't dealing with the same problems. I'm simply wondering what precisely is going on there and what actions are being taken. Thank you.

Tom Palmer

executive
#7

Thank you, Fahad, and good morning. I'll hand this over to Rob. What we're observing is two factors combined, which I believe Rob can elaborate on regarding the steps being taken. The first is voluntary attrition, especially at the Company, at the fly in, fly out operation. So it remains at the levels you'd normally anticipate at a FIFO site — the low teens, 12%, 13%. Beyond that, we're seeing the added absenteeism tied to COVID; so absenteeism can reach 10% to 15%. That's on top of situations where individuals cannot come to work owing to COVID-related absences; however, underlying that figure, two of our three sites are FIFO sites, and I'll let Rob address some of the measures we're taking to reduce and manage that pattern.

Rob Atkinson

executive
#8

Appreciate that, Tom. And Fahad, one more point I want to add onto what Tom covered — definitely, at certain moments during Q3, Canada saw some of its highest COVID infection numbers. At Musselwhite specifically, absenteeism reached 15% for the reason Tom described. We've put the fundamental measures in place: anyone who's away gets individual case management, with strong visibility into who's on site, who isn't, what's behind it, plus the follow-up and required oversight. On the hiring side too, we have a highly focused, dedicated group working solely on the Canadian labor market, so we can get to employment as fast as possible, aiming to recruit new people and get them onboarded extremely quickly. Still, it comes down to fundamentals — as vaccination numbers climb, as controls take hold, and really by executing the basics of good management. Whenever someone is repeatedly absent, they get managed extremely closely. There's no secret formula here; it's simply about executing the fundamentals extremely well.

Fahad Tariq

analyst
#9

All right, that’s great, and now perhaps shifting topics over to Ahafo. My understanding is the full-year guidance didn’t change, which suggests a very high output level during Q4. Rob, perhaps you could address that. Is that what we should expect?

Tom Palmer

executive
#10

Fahad, I’ll take that question and once more pass it over to Rob. However, what’s certain is that we will witness a robust fourth quarter from Ahafo relative to the first three quarters, which came in quite steady. Rob will go on to discuss what’s driving that robust fourth quarter.

Rob Atkinson

executive
#11

Sure, that underground is progressing really nicely, and earlier in the year we completed our first firing for the sublevel shrinkage, so we're seeing better grade coming from that area, and Ahafo's performance overall in the open pit and in the middle has been quite strong. I think, once again, it's just those elements of the call we made regarding the underground really beginning to pay off, along with solid productivity in other parts of the operation.

Fahad Tariq

analyst
#12

All right, that's everything on my end. Appreciate it.

Tom Palmer

executive
#13

Thank you, Fahad.

Michael Glick

analyst
#14

Hi. Regarding costs, can you take us through what you're seeing right now at the level of particular line items, things like consumables and other raw materials? How are you going about offsetting inflation from both the CapEx and the OpEx side moving forward? And then, sort of building off what you're observing in 4Q, what should the path of costs look like as we go into 2022?

Tom Palmer

executive
#15

Thanks, Michael. I'll start us off, and get Rob to add some color. I'll also ask Dean Gehring, our Chief Technology Officer, who has accountability for our global supply chain, to weigh in on trends as well. During our previous quarter's close, we started pointing out that inflationary cost patterns were emerging, and a portion of those are now coming through—this is part of what shaped our fourth quarter narrative—and we are certainly observing them extend into at least 2022, which informed what we said regarding how the coming year is beginning to look; so for the mining sector, my view is that 2022 will be defined by rising costs; production is improving at a pretty consistent but modest pace. So a cost escalation narrative is clearly present. When you combine materials, energy, and labor, we continue to observe increases in the neighborhood of roughly 5%. Yet underneath that total figure, there are fairly notable shifts taking place. In certain cases, actually, expenses have gotten better — in Australia, for example, CAT parts, meaning Caterpillar components, cost less because of currency movements and similar factors. Still, as I mentioned, we're observing meaningful patterns right now, and when combined they land near 5%. Rob, would you like to offer anything further? And then, Dean, please continue from there.

Rob Atkinson

executive
#16

Appreciate that, Tom. I'll address what Michael raised regarding our efforts to counterbalance it, and then I'll pass things to Dean on pricing and inflation. Michael, the complete potential is really where our attention sits across every operation. Each site has a set of projects that don't just help productivity — they also target bringing costs down. The major drivers we're watching are at Penasquito, recovery among them, and we're already seeing meaningful gains from that. Over at the Canadian sites, we've switched from McClean bolters and tele-remote loaders to jumbo rigs, which is lifting our productivity considerably. We're also getting back to fundamentals at Cerro Negro, where we've cut more equipment — we removed another 15 pieces of HME dealers during the third quarter — so we can run those fleets as efficiently as we can while keeping tight control over the consumables we actually require. Managing things this way is what the complete potential comes down to. Dean, would you like to cover inflation?

Dean Gehring

executive
#17

Absolutely, Rob, and thanks. When it comes to where we tend to see the widest swings, freight is honestly right up there at the top. That said, let me break it down a little. For our major consumables, freight represents somewhere between 2.5% and 5% of total landed costs. Keeping that in mind matters. To reduce the pressure, we're hunting for chances to leverage our worldwide supply chain capabilities, examining operations from a global viewpoint, and figuring out how to fit as much freight as possible onto ships or into containers, which lets us secure the most favorable rates we can get. Another mitigation step involves establishing pricing structures that are clear and largely tied to what we pay for many of the commodities we purchase, and that in turn helps ease the blow from inflation that shows up.

Michael Glick

analyst
#18

So, what's your take on consolidation within the industry? Everything you just brought up would suggest that having more scale is the more effective approach to running things in this climate.

Tom Palmer

executive
#19

Thank you, Michael. In our sector, the count of publicly traded gold companies is an order of magnitude greater than what you see in any other commodity — that fact alone indicates there's room for consolidation, given the extra <<inaudible>> it brings. With gold prices where they are, I suspect a great deal of that consolidation is being held back. My view isn't that consolidation will necessarily be pushed along by some of this near- to medium-term cost escalation. What I do believe is that the work every mining company must undertake to hit its 2030 carbon reduction goals, its greenhouse gas reduction targets, and its ambitions of reaching net zero by 2050 — commitments we're plainly witnessing governments worldwide make in order to meet those targets — means scale will be necessary, as will life, and throughout this decade, that imperative is what will bring about consolidation. So my prediction is that climate change, not some short-term COVID-related escalation, will be the force behind it.

Michael Glick

analyst
#20

Understood. Thank you very much.

Rob Atkinson

executive
#21

Thanks, Michael.

Greg Barnes

analyst
#22

Thank you. Tom, I'd like to get a clearer picture of how the autonomous truck fleet has been rolled out at Boddington. I realize it was delivered within the schedule and without exceeding the budget, but it sounds like getting it to function the way you intended has run into some difficulties. Could you describe those difficulties and what steps you're taking to resolve them?

Tom Palmer

executive
#23

Thanks, Greg, and good morning. The main difficulty when it came to commissioning that autonomous fleet — and I'll ask Rob to add some further detail — related to the severe weather conditions at that mine during the period when you're attempting to commission the trucks. We've moved past that and have now completed commissioning of the trucks and resolved a number of those tuning problems. As I mentioned, I'll hand over to Rob so he can give you additional detail on how that fleet is doing now that roughly a month has passed with the mine running in fully autonomous mode, which is one of the elements that comes into play when you're actually able to shift to full autonomy and are no longer dealing with interactions involving vehicles that contain people. While Rob walks you through the specifics, keep in mind the backdrop of how the weather has persisted in Southwestern Australia. In fact, October — and we're not even at the close of the month — is already the rainiest month since record-keeping started in that region. So with that backdrop, I'll have Rob give you additional detail on how autonomous haulage is going.

Rob Atkinson

executive
#24

Appreciate it, Tom, and thank you for raising that, Greg. For sure, week after week, our autonomous haulage keeps delivering more output, and to give you a bit of the background: ever since we started with zero injuries, we've covered more than 600,000 kilometers by now. We're sitting at roughly 21 million tonnes, and every machine has been linked up, so a great deal of solid effort is underway. Back at the beginning of September, we stood at approximately 53% EU, which counts among the key measures confirming the trucks get used to the fullest extent possible; as of the past week we've climbed past 61%, and on a shift-by-shift basis we've even reached roughly 68%, 69% a year. Of course, we need to sustain that level consistently. But a crucial point, especially significant for next year, is that next year's tonnage averages somewhere near a 135,000 tonnes coming out of the pit. We've already reached 160,000 <<inaudible>> ; so although we still have items to polish, just a final touch and to fine-tune, as Tom mentioned, be it certain road widths, be it the road conditions caused by wet weather, and so on; we feel very good about the way things are moving forward. Caterpillar gives us outstanding backing. We have quite a few Caterpillar personnel assigned to the site. So certainly, we believe progress is going well, though the rain causes chaos. Honestly speaking. But regarding commissioning, we should keep in mind, it's the fastest commissioning of any EHS system accomplished up to now, and so far, each week that passes, like I said, things improve.

Tom Palmer

executive
#25

Greg, those expected tonnes are showing up at the mill, and the mill is performing extremely well, operating at record rates. As a result, we feel confident about the fourth quarter, especially as we move into the next year, that the truck fleet will deliver the expected tonnes, and our mills are doing well.

Greg Barnes

analyst
#26

Rob, I don't know what that 68% EU figure refers to.

Rob Atkinson

executive
#27

My apologies, Greg. What it really comes down to is measuring how frequently your truck is operating and performing useful work. And usually, a major factor in our decision to move toward autonomous systems is that when people are running them, you tend to have delays for lunch, bathroom stops, and similar interruptions. The EU is among the most important measurements.

Tom Palmer

executive
#28

When it comes to the EU, what matters is how well it's utilized, Greg.

Greg Barnes

analyst
#29

Got it. So for the autonomous fleet compared with a human-driven one, what EU are you aiming at, I suppose?

Rob Atkinson

executive
#30

The figure we use to make the case is 68%, and of course, in our planning we're definitely going for something well above that.

Greg Barnes

analyst
#31

So you've already hit the rate you were aiming for, is that right?

Rob Atkinson

executive
#32

Not exactly. What we've reached is more of an intra-shift level — on average, we've been running at roughly 60% to 61%. So, like I mentioned, with every shift that goes by, we pick up more insights and make more improvements. I have a lot of confidence that next year we'll be right up there, consistently meeting those targets every single day.

Greg Barnes

analyst
#33

Okay, great. Thank you.

Tom Palmer

executive
#34

Thanks, Greg.

Josh Wolfson

analyst
#35

Thanks a lot for fielding my questions. I do appreciate the 2022 preview disclosure regarding expectations. If I look at the 5 year guidance that's already out there, there was an expectation of some cost reduction as we move into 2022. A sizable step down existed before, and afterward, during future years 2023 and '24, additional reduction was anticipated too. Given the trends we are observing across the sector, ought we still to anticipate that sort of trajectory over the longer term? Or could it be that certain operating improvements end up being canceled out by these trends, meaning they simply persist?

Tom Palmer

executive
#36

Good morning, Josh, and thank you. At Newmont and across the industry, you are definitely going to witness costs, owing to those escalation pressures we have discussed, the inflation pressures; nonetheless, cost improvement continues to arrive at Newmont. That's because it ties to the reinvestment we are directing back into our business. So improvements will keep emerging from Boddington via autonomous haulage, which is currently being commissioned, as Rob just described regarding how one can tune an extremely predictable autonomous system now that the fleet is automated; improvements will also emerge from commissioning the shaft at Tanami. We're able to bring ore to surface far more efficiently. The underground mining method at Subika, the near-mine Ahafo North, plus Yanacocha Sulfides are each investments we are undertaking that will yield better costs relative to guidance across the five-plus year period; thus, with those investments being undertaken, cost improvement will result from them since we will be delivering and producing ounces at considerably better margins. What COVID has caused us to see is that those three key development projects, Tanami 2, Ahafo North, and Yanacocha Sulfides, got delayed and are now overlapping one another to a greater degree. Consequently, through '22 and '23, we will see substantial development capital spend. As a matter of fact, it will be development capital spend of a scale Newmont has not executed in a generation, so it represents a major reinvestment in our business, and the benefit from that investment truly begins to appear in the later portion of '23, into '24, '25, '26, and '27 for a number of those projects. There's a modest delay regarding when those better margin ounces arrive, along with some piling up of that development capital, which stems from managing around COVID.

Josh Wolfson

analyst
#37

All right, thanks. Now turning to the capital figures — in a similar vein, several adjustments have occurred involving certain projects already underway, along with their sequencing, clearly including Yanacocha Sulfides. What's the right way to frame that? From what it sounds like, perhaps the baseline sustaining capital figures ought to sit higher over a longer horizon? Would it be fair to assume that?

Tom Palmer

executive
#38

Josh, when it comes to a portfolio the size of ours, sustaining capital essentially amounts to roughly $1 billion. One year it could be $951 million, and another year $1.50 billion. When I review our business plan, the spending stays fairly consistent for a portfolio like ours, hovering right around the even $1 billion. On the development capital side, Mike and Rob can offer a bit more detail. Regarding both Tanami Expansion 2 and Ahafo North, certain cost factors have already been locked in. I'll have Rob walk through those two. As for Yanacocha Sulfides, clearly we pushed back the full schedule because of COVID, moving it through the second half of next year. We keep carrying out all the detailed engineering work. We keep working the critical path on procurement, which means securing factory slots for oxygen plants as well as specialized steel, for the clothes and similar items. So we're de-risking Yanacocha Sulfides under these conditions. Then Rob offered some detail regarding costs for Tanami 2 and Ahafo North.

Rob Atkinson

executive
#39

Thank you very much, Tom. Regarding Tanami 2, our engineering work is moving along quite nicely, and we've reached the stage where confidence about the required scope is really high. At Tanami, the bulk of spending relates to reaming plus shaft outfitting. As a result, we feel quite sure right now that this portion of the work stays within budget. Our main difficulty comes from labor rates—once more, how orders are being handled in Australia's post-COVID environment. Still, that's where most of the expense sits, we have a solid partner in <<inaudible>> , and like I mentioned, having engineering this far along matters enormously. Over at Ahafo North, every piece of equipment was ordered ahead of time, so that gear is either in transit or currently being built. Engineering there was likewise very advanced, and we hold a modest amount of contingency, yet nothing is causing us serious concern at present—except, as Dean noted, possible hold-ups and the offsetting character of the three business. Taking everything together, since engineering has come so far, I'd say our confidence is quite high.

Josh Wolfson

analyst
#40

Thank you very much.

Tom Palmer

executive
#41

Thanks, Josh.

Tanya Jakusconek

analyst
#42

Morning, everybody. I really appreciate you answering my questions. Rob, could I ask you to stay on the line a moment longer, just so we can get some clarity regarding Boddington? Greg raised this, and I also had no idea what that EU referred to, but I wanted to confirm my understanding: assuming the rain is now behind us and the roads remain clear and clean, are these automated trucks doing what you'd anticipate, since they keep halting? So I'm simply asking whether we've eliminated those problems, rather than having them just stop, meaning have we sorted it out together with Caterpillar?

Rob Atkinson

executive
#43

Correct, Tanya, when it comes to the communication side, those are issues we've identified — from time to time, a communication problem will arise for quite ordinary reasons, and although the system is designed for it, whenever a communication problem occurs, operations halt. We've definitely handled that quite effectively, particularly in the deep mine, where some new techniques are being applied relative to the program. As for the roads, based on what the Boddington team has told me, they're in the best condition they've ever been in, and these trucks can certainly capture a tremendous amount of detail, whether that's rusting, rocks ending up on the road, or wash-outs from burns, and so on. So a great deal of attention goes into that, and when I mention road widths, the team has put in an enormous amount of effort. Overall, though, Tanya, we're certainly in good shape, the roads are in good shape, and the technology is in good shape. The one remaining factor is that it's still raining, and we'll keep managing that. On the positive side, though, the experience we're gaining here positions us very well for wet seasons down the road.

Tom Palmer

executive
#44

To add to what you said, Tanya, the fleet is delivering at record or needed rates, even with a soggy October at Boddington. Summer is nearly here in Western Australia, and from roughly November all the way to March or April you won't spot a cloud overhead, so the system is dialed in and properly configured for a really strong stretch across the coming 6 months and past that.

Tanya Jakusconek

analyst
#45

And on top of that, the grades we're seeing are improving, correct?

Tom Palmer

executive
#46

That's right — at Boddington, in the South <<inaudible>>, we're positioned directly on those better grades.

Tanya Jakusconek

analyst
#47

Perhaps we're still on Australia. Rob, regarding the Tanami expansion, as you brought up, that $150 million capital deferral, and the timeline hasn't been affected. Could you tell us, or give more specifics about what precisely is being pushed out? Should I be taking that $150 million and putting it toward 2020 capital? Which I believe Tom said would be comparable, meaning no change to CapEx for 2022. So perhaps a bit of clarity on that.

Rob Atkinson

executive
#48

When it comes to the CapEx, Tanya, it will be distributed across '22 and '23. Not all of it is arriving in '22, and as for the key work, it's really about finishing the reaming and beginning to outfit the shafts. So regarding that work's schedule, it remains very much on track. That capital is going to be distributed across the coming couple of years instead of only next year.

Tom Palmer

executive
#49

Tanya, regarding that wider question, what we'll put into development capital should stay around the same as the guidance we're giving right now for '22 and '23. Then when you look at '24, you'll see somewhat of that, somewhat more capital in '24, which comes from those 3 key projects overlapping one another, plus Yanacocha Sulfides has slipped; so spending stays comparable, with somewhat more in 24.

Tanya Jakusconek

analyst
#50

All right, that's useful. Then, Tom, I've got you next, and I only want to ask two things. You brought up disruptions in the supply chain. I'm hoping you can give me a clearer picture of what exactly you're observing — that's my first item. My second item: since these inflationary pressures are showing up in our cost structures, do you plan to revise the gold price assumptions behind your reserves and resources for the coming year? And also, with gold trading higher, might we see you use a higher gold price assumption when you give cost guidance for next year?

Tom Palmer

executive
#51

Thank you, Tanya. Our approach will stay the same — we'll keep doing long-term mine planning for reserves and resources at $1200. That keeps discipline in how we plan our mines strategically and makes sure we're being very deliberate whenever we consider adjusting cut-off grades to bring in particular <<inaudible>> . Strategic mine planning and the acquisition of reserves or resources are now done at $1200, and yes, we will give you cost guidance next year using the $1800 gold price assumption. As stated in the script, our all-in sustaining costs for next year, assuming gold sits at $1,800, should come in at essentially the same figure you're seeing this year as we begin assembling our plan. A few pieces are still in motion. Nevada Gold Mines is set to come in, but the direction of everything is toward levels comparable to this year with gold at $1,800. Cost drivers, rather than production drivers, are becoming more significant, just as they were this year. Our gold production is roughly 5% above this year's level, so if you want a specific figure, it will likely be about 6.2 million ounces next year. We will keep giving a view of all-in sustaining cost using a $1,200 gold revenue price. So that will remain a reference point in our guidance, but we will also give you the $1,800 — we'll assume $1,800 flat across the five years we guide to and show you that cost profile. Dean or Mike, could you address the first part of Tanya's question regarding supply chain disruption and what we're seeing there?

Dean Gehring

executive
#52

Absolutely, Tom, I appreciate it. Tanya, the biggest area where this supply chain trouble shows up for us is really around logistics—specifically freight and shipping. What’s behind that is the limited capacity for inland transport and freight; it comes down to how many truck drivers are available. We’re noticing that manufacturers and factories are gradually getting past COVID. They’re ramping production back up. However, the general expectation in the market is that this ongoing strain will last until the close of the year, mostly because of whether enough workers are available to transport goods from place to place.

Tanya Jakusconek

analyst
#53

All right, I appreciate that. Tom, thank you — I simply needed confirmation that the figure was $1,800 rather than $1,200, since I'd have to revise my numbers upward; I'm grateful for the clarification.

Tom Palmer

executive
#54

Thank you, Tanya. Operator, for those listening in, we'll continue and field everyone's questions. Should time permit, we'll remain on the line for as long as required to respond to questions. So operator, let's take the next caller.

Anita Soni

analyst
#55

Hello. There are still two things I'd like to ask about. You mentioned cash costs of roughly $790 million, while the earlier outlook had been $650 million to $750 million, correct? And now you're citing 6.2% for the production figure. That means you're near the bottom of the range you originally gave for production. So I'd like to reconstruct that 5% escalation, plus whatever extra comes from the price movement, and then see how that lands you at $790 million. Could you explain how much royalties would affect the terms in the gold price first?

Tom Palmer

executive
#56

Anita, let me just check that I've got your question right; are you referring to 2022?

Anita Soni

analyst
#57

Right, my question concerns 2022. What I'm getting at is this: you keep mentioning a 5% escalation on the cost side. If we took the midpoint of the earlier range, that would work out to roughly $35 an ounce. Since production isn't landing at the midpoint, I assume we aren't there either. That would put me at the upper end, and then I'm trying to figure out what closes the remaining distance to reach $790 million — are there pieces I'm missing that keep me from arriving at that $790 million?

Tom Palmer

executive
#58

There's the effect from production, roughly 5% from inflation, and then taxes — production taxes along with royalties. Taken together, those three items account for the difference from our $1,200 figure up to our $1,800 figure for 2022.

Anita Soni

analyst
#59

Does the royalty hit come to somewhere around 15 to 20 dollars for each ounce?

Tom Palmer

executive
#60

Not at all — it's higher than that. 30 at minimum.

Anita Soni

analyst
#61

All right. So $30 an ounce, plus that $115 million Tanami deferral — you're keeping the $2 to $2.2 million figure for 2022. My assumption would have been that number rises when you're pushing Tanami CapEx back? Or does it simply come down to the net being delayed in a steady way, meaning what gets spent on Tanami in 2022 shifts to 2023, and maybe a portion lands in 2024. Is that how it goes, or does something offset it?

Tom Palmer

executive
#62

No, basically that's a wave shifting for Tanami out of '21 and into '22, while what sits in '22 goes to '23, and after that, if you take a look at our total development capital figure, there are certain Ahafo North amounts we'd assumed in '21 that shift to '22 and then get pushed to '23 and '24. Yanacocha Sulfides then has a comparable <<inaudible>> , so it's those three together, with that spending shifting about, which leaves a few more matters when we gave guidance; you'll notice additional development capital in '24, though comparable rates for the Newmont portfolio across '22 and '23.

Anita Soni

analyst
#63

Regarding that fresh December guidance — will it still leave out the Yanacocha Sulfides outlay, given that a full funds decision hasn't actually come through?

Tom Palmer

executive
#64

Our present guidance does factor in the Yanacocha Sulfides outlay. Once full funds approval slips to the back half of the year, that Yanacocha Sulfides outlay will show up in the updated guidance we issue in early December. That project's timing works like this: across a five-year production outlook, only a tiny amount of the gold and copper will appear in our profile. The real payoff from that gold and copper, at attractive prices, arrives in '27, '28, and later on; so the outlay shows up, yet the payoff won't appear within our five-year guidance.

Anita Soni

analyst
#65

To put it another way, that heavy capex you're carrying over the coming 2 years takes in the Yanacocha Sulfides outlay, that figure of $2 billion across the next several years, correct?

Tom Palmer

executive
#66

That's right. It certainly does.

Anita Soni

analyst
#67

Okay, that's fine. Thanks. Apologies, and really, likely relevant here, does the 2024 decline also take in the Yanacocha Sulfides outlay?

Tom Palmer

executive
#68

Yeah, correct; so the development capital expenditure you're observing across the five years under our present guidance takes in the major items, namely Tanami 2, Ahafo North, and Yanacocha Sulfides.

Anita Soni

analyst
#69

Okay. Thank you.

Tom Palmer

executive
#70

Thanks, Anita.

Brian MacArthur

analyst
#71

Morning, hello. I think the topic I had in mind has already been addressed, but there's one more thing I want to explore in more depth, and that's Conga. Actually, I have three questions. First, why did this occur now — is it tied in any manner to a shift in government or anything of that sort? Second, given a total book value of $570 million versus $68 million, and since you brought up equipment and assets, my guess is that the $68 million is for equipment while the assets sit separately. Could you clarify that? I'm just trying to figure out what's in there; and third, $900 million is still on the books. Is any portion of that usable for Yanacocha Sulfides, other equipment, or things like that? I'm just trying to pin down exactly what that transaction covers.

Tom Palmer

executive
#72

Thanks, Brian. I'll take your first and third questions, and Nancy can speak to the book value. The $900 million that's there reflects the deposit, the reserves, what that's worth, and we also constructed a fairly sizable dam; that infrastructure is still standing and holds value. Of course, a mine once operated there, so we know the orebody. We plan to build a mine there eventually, so our knowledge of that orebody is very strong. <<inaudible>> for care and maintenance to keep the mill and each of its parts in good condition. That mill is extremely large. In fact, at that time it was known as the largest mill anywhere in the world, so it's quite unusual when you consider which buyer would take that equipment and actually use it; so when a party came to us interested in purchasing that equipment because they had a place to sell it, you take the opportunity to sell that mill. So the timing really came down to someone approaching us with interest in taking that mill off our hands. We sidestepped the care and maintenance costs, and in any future development of Conga, which is still some time off, the flow sheet will look very different. It wouldn't have a flow sheet with a huge mill in it; so what set this off was a party coming forward ready to take a rather unique piece of equipment and for us to get $2.5 million for it. Nancy, would you like to take the book value question?

Nancy Buese

executive
#73

Right. That carrying amount basically reflects whatever figure sat on the books, less depreciation across the stretch we owned it, so the loss comes purely from the sale itself — nothing beyond that. It had been sitting there for a good while.

Brian MacArthur

analyst
#74

Great. Thank you very much.

Tom Palmer

executive
#75

Thanks, Brian.

Danielle Chigumira

analyst
#76

Morning, and thanks for taking the question. I have one more follow-up regarding the Tanami expansion. I was hoping you could clarify something: we've pushed back $150 million in CapEx, yet the total CapEx budget is unchanged from what you previously guided. So, with labor markets as tight as they are and so on, what makes you confident the overall budget won't end up growing? That's my first question.

Tom Palmer

executive
#77

Thanks, Danielle. I'll start us off, and then hand it over to Rob. Regarding the current status of the Tanami expansion initiative, with roughly 70% of the shaft excavation complete, we are now in what is essentially a sequential phase. A specialized contractor handles the lining work, so this becomes a lengthy undertaking—concreting the shaft walls and installing the associated support infrastructure consumes a considerable stretch of months. To be clear, because of how much headway we've achieved on the path ahead, and since we've brought the top contractor in the industry onto the site to handle that job, and because we now have certainty regarding what's contracted and how much scheduling work we've completed, we feel confident about our timeline and our costs; Rob, would you like to add some detail there?

Rob Atkinson

executive
#78

Adding a bit more detail on that point here, Danielle: with Tanami 2, there's a head frame picture in the presentation, and it's progressing nicely. Refrigeration work is moving along well too. We wrapped up the crusher chamber at surface level. Work has kept going on the power station extension, and the box cuts are complete. So, like Tom mentioned, we don't have anything ready to kick off, and honestly, the main focus is holding on to and preserving the expertise required for the reaming and for the shaft lining — those are what really matter.

Tom Palmer

executive
#79

Danielle, with that kind of work ahead of us, the danger is whether we can actually get personnel out to the mine site to carry it out. At this point, vaccination coverage in Australia has reached the mid-70% mark, and it's clearly trending toward exceeding 90% nationwide before the new year arrives. A number of the hurdles around relocating workers across the country and through state borders should ease during the first quarter, and that gives us an unobstructed path to essentially have the <<inaudible>> on-site to complete the job.

Danielle Chigumira

analyst
#80

Thanks. That helps a lot, and switching to something entirely separate. Regarding Penasquito, has the new labor law that came in during September affected you in any way, specifically its restrictions on contractor usage — does that create any issues for you?

Tom Palmer

executive
#81

Not in the slightest, Danielle, and we are in complete compliance with those legal stipulations, yet no effect at all; as a matter of fact, Penasquito is performing exceptionally well. It is truly operating at its best.

Danielle Chigumira

analyst
#82

Thank you. That's useful.

Tom Palmer

executive
#83

Thanks, Danielle.

Adam Josephson

analyst
#84

Morning, everybody. I really appreciate you taking the time to answer my questions. Tom, regarding your production remarks for next year, based on what you've gone through this year, why are you confident about that forecast of 5% growth for next year, and similarly, how do you view the 2023 outlook you provided last December given everything you've seen so far this year?

Tom Palmer

executive
#85

Thanks, Adam. We're very confident in the figure we're looking at for next year. When I look at that figure, we've got a number of world-class assets that comprise that production figure. So in Australia, Boddington and Tanami are key contributors. Australia is basically through the toughest part of the COVID-related restrictions it had to deal with, plus a tight labor market—so the bigger problem there is really cost. Autonomous hauling has only been operating at Boddington, which is where labor is needed most at that site. Without driverless trucks across the whole fleet, we would have a gap—and we've now solved that by deploying this fleet. Those two major Australian operations are what support that output number, and I have a lot of confidence in them. At Ahafo South in Ghana, the underground mining approach is coming into service right now. We're set up for a really strong year, and right now we're in the middle of rolling out vaccines in Ghana—as I said earlier, 100,000 doses that we plan to get out to our employees, plus their families and the communities where we live and work. When it comes to Penasquito, like I said in answering Danielle's question, it's truly finding its rhythm and performing well. Penasquito is Newmont's engine room. And as for Nevada Gold Mines, Carlin, Cortez, and Turquoise Ridge, I fully expect that those three major world-class operations, together with Pueblo Viejo, will keep delivering on what they've committed to. Just a bit more detail on Pueblo Viejo. Several members of our staff traveled there during the past two weeks or so. Essentially everyone among them has been vaccinated — practically a full 100%. That means the operation in the Dominican Republic can keep operating, and operating effectively. As a result, Newmont is going to meet its production guidance. Provided the assets I referenced fulfill what they've promised — and I have every confidence they will — then when it comes to 2023, there will be an effect. The pandemic isn't going away anytime soon. Over the past couple of years, you couldn't achieve the development rates you'd have wanted, because you were dealing with health and safety and all the other controls. That's going to carry through into 2022 and 2023, along with certain hold-ups in our development capital spend, and we need to get some ounces moving through from those projects. So my view is that you'll see a COVID-related effect in '22 and '23. As a result, it stays relatively unchanged, and after that, benefits will start to show up more across 2024 and 2025. Consequently, there is a slight postponement caused by both COVID. COVID affects operations as well as the work being done to advance your mines, along with your progress on essential growth capital expenditure.

Adam Josephson

analyst
#86

Thanks for that; regarding the topic of inflation, I believe on the prior call you mentioned that you anticipated the roughly 5% inflation rate to persist at minimum until the close of next year. I'm simply curious, drawing on what you've seen in earlier cycles, what is the usual duration of these inflationary periods? What's your expectation? In other words, when do you think this inflation would begin to ease? Is it simply a case where elevated prices are the remedy for elevated prices, and ultimately, those elevated prices will stifle some economic growth? Or what's your perspective on that?

Tom Palmer

executive
#87

Thank you, Adam. In my view, the world is in uncharted territory when it comes to this inflation; therefore I don't think it's structural. My belief is it will be cyclical, though I think the cycle will be longer than usual, and COVID will determine that cycle. So definitely observing all the indicators, we're going to have elevated pricing, and that will remain with us throughout 2022. I'd say it's too early to forecast whether that cycle then declines again in '23 or remains at that level. We'll focus heavily on our 2022 cost guidance to incorporate inflation, and after that, we generally don't attempt to forecast that far ahead with our cost figures. So we would address our '23 and beyond numbers without fully having accommodated inflation, we'll simply handle it the following year; predicting that is extremely difficult.

Adam Josephson

analyst
#88

I’m genuinely grateful for that, Tom. Many thanks.

Tom Palmer

executive
#89

I appreciate it, Adam.

Tom Palmer

executive
#90

Appreciate it, operator, and thanks to all of you for being here. As things around the globe begin to reopen, I ask that you look after your own well-being and stay safe, along with the people you care about — especially with the colder season arriving across the Northern Hemisphere. Thanks again for spending your time with us, everybody.

Operator

operator
#91

This call is now over. We appreciate your participation in today's presentation. You are free to disconnect at this time.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Newmont Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Newmont Corporation earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Newmont Corporation or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.