operatorThank you for holding. I’m the conference operator, and I’d like to welcome everyone to the NexGen Energy Third Quarter 2025 Results Conference Call. Please note that all participants are in listen-only mode, and this conference is being recorded. Following the speaker’s remarks, we’ll hold a question-and-answer session. If you’d like to join the question queue, press star then one on your telephone keypad. If you need assistance at any point during the conference call, you can signal an operator by pressing star then zero. At this time, I’d like to turn the conference over to Mr. Leigh Curyer, Chief Executive Officer and Director with NexGen Energy Ltd. Please go ahead, sir.
Leigh Curyer
executiveThanks, Gillian. Morning, everyone, and thanks for being on NexGen's Q3 2025 Financial Results And Investor Conference Call. I'm Leigh Curyer, Chief Executive Officer of NexGen Energy Ltd. With me today are Travis McPherson, our Chief Commercial Officer, and Benjamin Salter, our Chief Financial Officer. In today's Q3 update, I'll walk you through the newest uranium market dynamics, which are simply unfolding faster than most industry observers anticipated — driven by unprecedented huge uptake of nuclear energy across the globe and the strategic execution of NexGen's offtake marketing strategy. I'll also cover our progress as we get ready for the first of two commission hearings on the federal approval of Rook I, now just 13 days away. On top of that, I'll go through all the Rook I site activities and preparations, and the updates we're executing on this generational project that will set a new benchmark in the economic, environmental, and social stewardship for the sector. When this presentation wraps up, we'll move to the Q&A portion of the call, where you're invited to ask Travis, Ben, and myself any questions. Throughout today's call, we'll be making forward-looking statements. Please visit our website for all the relevant disclaimers. In recent months, we've seen an unprecedented alignment of policy, capital, and geopolitical priorities in support of nuclear energy, along with a growing understanding of the constraints impacting uranium supply.
Leigh Curyer
executiveJust last week, the Nuclear Energy Institute, or NEI, hosted its yearly International Uranium Fuel Seminar in Charleston, South Carolina, bringing together industry executives from around the world. Utilities made one point unmistakably clear: sector developments are moving ahead so quickly that projections for electrical demand have risen more than tenfold compared with just 3 years ago. There is absolutely unmistakable, never-before-seen momentum for nuclear energy adoption supporting restart initiatives at several US nuclear facilities that are presently idle, and talks are proceeding regarding other idled sites as well, pushed by added layered tape demand from the leading technology companies. The entire nuclear energy chain is accelerating swiftly, as utilities pursue reactor uprates, longer operating life cycles, and subsequent license renewals. All of this is happening while they assess SMR deployment alongside major tech partners. Put quite simply, this means uranium demand is being forecast at a quickening pace. Only this past week, the US government unveiled an $80 billion investment alongside Westinghouse aimed at constructing new commercial reactors, and it has made further commitments to restart reactors that are currently idled. Note. Although recent mainstream headlines concentrate on the power generation piece of this generational opportunity, in the United States the government, via the 2024 Advance Act, has sped up modernization at the Nuclear Regulatory Commission and reduced key licensing timelines.
Leigh Curyer
executiveEnergy Secretary Chris Wright has urged expanding the strategic uranium reserve, and that reinforces how focused Washington is on fuel security and long-term nuclear capacity—including supply from allies like Canada. On top of that momentum, a landmark critical minerals framework was signed recently by the US and Australian governments to deepen cooperation in mining, processing, and supply chain security. What this agreement shows is a shared strategy among allied nations: making sure key raw materials stay stable and accessible is essential for geopolitical security. Cooperation is the only route to meeting the goals all allied nations share on this front, and we expect further announcements that demonstrate this approach. Among the syndicated banks in our recent North American $400 million financing—which I'll cover shortly—J.P. Morgan is the newest major institution to unveil a $1.5 trillion 10-year plan aimed at facilitating finance and investment in industries critical to economic security and resiliency, helping companies boost growth and innovation and accelerate strategic manufacturing; that move stands as a concrete signal of finance backing nuclear and uranium, the key fuel in the value chain. Morgan Stanley also released its national security index, and NexGen was included among the constituents—once more underscoring NexGen's unique role as a go-to solution provider for allied nations' uranium supply needs.
Leigh Curyer
executiveTurning to uranium in Q3: spot prices climbed 16%, reaching $83.25 per pound, with added market liquidity across August and September fueling that move. It shows just how quickly prices respond once demand shows up in the spot market. NexGen sees that when demand reaches the spot market, price discovery starts to take shape, sending an efficient signal of true incentive pricing—something that benefits both sellers and buyers. That extra liquidity in the spot market lined up with a greater number of supply disruptions during Q3. We saw production guidance cuts broadly across the world, including at existing producers Kazatomprom and Cameco, where output problems have lingered, plainly a reflection of late-life mine challenges being present. After prior years, healthy on-hand inventory levels are being drawn down quickly, and borrowed inventory levels are climbing steeply in order to satisfy post-offtake commitments at prices below today's spot. These forces are strengthening the case for a sustained higher price environment—a trend already taking hold as the term price climbs to $86 per pound, its highest since May 2008. The move to a higher-for-longer market has arrived, and it comes at a pivotal moment for advanced, field-ready projects such as NexGen's Rook I. What NexGen has accomplished across the last 12 years is lining up with all of these market dynamics.
Leigh Curyer
executiveKeep in mind, Rook I on its own can't fill this gap. Meeting the projected demand-supply shortfall through 2030 would take several Rook I mines up and running, and those simply aren't there. The result will be substantially higher prices down the road, and every one of our advanced development company cohorts across Canada, the US, and Australia is incredibly well-leveraged to forecasted high uranium prices of the future. In September, the scale and speed of this structural shift taking place in our industry was the key highlight from the World Nuclear Association's synopsis in London. Attendance reached a record 1,300 participants, up from 800 a year earlier, and the biannual fuel report upgraded all three global nuclear growth scenarios upward. Over the next 15 years, the upper-case projects' annual uranium demand reaching 530 million lbs per year, while the base case projects 391 million lbs. Today, demand is just under 180 million lbs. In 2024, primary supply was estimated to be 150 million lbs, with the deficit made up of continued inventory drawdowns, which only prolong and exacerbate the challenges facing primary uranium supply growth. With demand far outpacing supply and global mine supply at the same level as it was 10 years ago, one can see the need for both significantly higher uranium prices as well as policy support to address regulatory timelines and their impact on capital formation.
Leigh Curyer
executiveOne thing that stood out was the WNA synopsis — in their report, they noted that engagement from the technology sector is on the rise, and Microsoft has now officially joined the WNA. That shows the expanding link between power demand driven by AI and the essential part nuclear plays as clean baseload generation that can reliably supply this relentless demand. With the uranium market now entering the seasonally strong contracting window, we anticipate uranium prices will keep showing strength, and with that supportive backdrop, NexGen is positioned unlike anyone else, holding the most advanced, high-grade, build-ready uranium project in the world to bring a new secure supply that the world depends on. On the contracting side, talks with numerous utilities throughout North America, Europe, the Middle East, and Asia keep moving forward. Utility activity has picked up significantly, with counterparties actively looking to lock in long-term supply starting in 2030 and beyond — a clear sign of tightening market fundamentals and widening awareness that future supply will be difficult. Negotiations are progressing on offtake, where these forward-looking utilities want to finance NexGen into production. We anticipate that multiple agreements will be finalized over the coming quarters as utilities move to secure future delivery schedules. One theme that comes up consistently in these discussions is the strategic focus on supply diversification, and that is exactly where NexGen is genuinely unique.
Leigh Curyer
executiveNexGen stands out as the world's most significant supply source that genuinely delivers meaningful de-risking diversification on two fronts: technical, thanks to its competent ground conditions, and sovereign, since it sits in Canada. Utilities increasingly want to lessen dependence on producers backed by the state, while also confronting the fact that older mines are running down and hitting persistent production troubles late in their operating lives. The first commission hearing takes place just 13 days from today, on November 19th in Ottawa, and the second is set for one day somewhere between February 9th and February 13th in 2026; NexGen is eager to move from advanced development into constructing the greatest natural resources project in recent memory as soon as federal approval arrives. That milestone caps more than a decade of demanding technical effort, engagement with communities and indigenous groups, and the regulatory journey, and the carefully assembled team of experts we have built is ready for construction. The backing we have gotten has been considerable. Each of the four indigenous nations in the local priority area has legal support and has spoken publicly in favor of immediate project approval, along with the province of Saskatchewan, which keeps promoting it as a priority project. CNSC staff have advised approval through their technical assessments, and Ottawa has increasingly acknowledged how vital clean, dependable nuclear power is for achieving climate and energy security goals.
Leigh Curyer
executiveThat coordination among regulators, government, and communities strengthens our distinctive and authentic method of resource development. Canadians take great pride in this story, because it is redefining, in several ways, how resource projects can be—and are now being—developed technically, environmentally, and socially. We want to thank our investors for backing our highly successful global equity offering last month. With the closing of our AUD 1 billion raise, NexGen has bolstered its financial position even further so it can move forward with developing the Rook I project right away, once final federal approval comes. Notably, the bulk of the capital came from outside Canada, mainly Australia, where our registries showed a steadily rising Australasian presence—proof of NexGen's uncommon capacity to draw hundreds of millions of investment dollars into Canada, capital that will directly benefit local communities, the province of Saskatchewan, and the wider Canadian economy. The proceeds will fund the remainder of detailed engineering, pre-construction work, and general corporate purposes, putting the company in position to deliver on its next phase of execution and growth. The Australian raise has also put NexGen in position to satisfy the market capitalization and liquidity thresholds needed for eligibility in the ASX 200 index, the leading equity index in the Australian market.
Leigh Curyer
executiveRight now we're sitting on roughly CAD 1.2 billion in cash, and that gives us the funding to finish the 2025 site program and to get development started for the first 18 months after approval — that covers engineering, procurement, training, and construction. We've deliberately kept our strategic optionality fully intact, with a solid cash position and ongoing talks with strategic investors and utilities, among others, and those conversations have produced a range of highly accredited financing alternatives. As we've always done, we'll optimize those financing alternatives in. We're staying patient with the market, which continues to be recognized. Our production flexibility — and together these will maximize the value of every lbs of uranium we produce and sell, making us the most leveraged company in the world to rising higher uranium prices. Turning to our site activities. Since 2013, NexGen has delivered Rook I site activities safely and successfully, covering every aspect of exploration, engineering, development, and supporting infrastructure, totaling CAD 706 million. In Q3 2026, construction of the exploration, accommodation, and infrastructure — including the exploration airstrip, dual-way access road upgrades, and the expanded exploration camp facilities — has been a terrific opportunity for NexGen to once again validate its planning, management, and construction execution skills, incorporating NexGen's elite safety performance. This $98 million program is meeting precise design scope with an approved budgeted cost and schedule, with completion for early Q2 2026.
Leigh Curyer
executiveAnd at the same time, we're maximizing sustainable commerce and employment for local Indigenous communities. When it comes to preparing for construction after federal approval, nothing could be better, and the NexGen team stands ready to bring those same disciplines — safety, staying on budget, and schedule execution — to building Rook I. On procurement, critical path items coming up are being locked in and will be ready to deploy right after federal approval. We're also seeing tremendous interest in our training programs and in joining the NexGen team. Not long ago, we had more than 1,300 applicants for just 20 open positions — a clear sign that the highly experienced team we've built is drawing professionals who want to be part of NexGen's distinctive elite standards culture. Moving to our exciting exploration program, drilling keeps delivering at our basement-hosted Patterson Corridor East (PCE) discovery. The results reported validate continuity of our high-grade subdomains and confirm the system is still open for expansion in multiple directions. The profile taking shape at PCE is incredibly exciting and speaks to the exploration potential for further Arrow-type discoveries across our dominant land position. Assay and scintillometer results are scheduled in the months ahead as they come in. This exploration — the largest reported in the Athabasca Basin for 2025 — is strategic and forward-looking.
Leigh Curyer
executiveGiven that it usually takes 15 to 20 years from discovery to production, finding and developing high-quality, technically superior deposits now is crucial if we're to keep long-term production optionality going alongside Arrow. That's crucial for keeping the nuclear industry going and for the key role NexGen will play in stabilizing energy infrastructure around the world. We're setting out to meet global demand supply deficits for the next 50 years, not just the next five years, and that's what sets NexGen apart from the current uranium producers, and we're delivering it by developing Rook I into production post-approval and in parallel through the drill bit at PCE. As we head into the next phase, our priorities are clear: get final federal approvals and mobilize to build the most strategic and significant new mining project in the world. We're going about this the same way we always have, with accountability, honesty, a continuous improvement mentality, and a confidence to do things the right way. Our indigenous community and partners, the environment, regulators, Canada, and the world population, all our shareholders, in a most efficient, highly accredited manner. Through years of dedicated effort, the NexGen team has turned an underexplored ground into a national champion and a strategic asset of global significance.
Leigh Curyer
executiveThe macroeconomic environment is the strongest it has ever been. AI's emergence, the drive for energy security, and the necessity of economic expansion via natural resource development have made NexGen the very definition of the answer. The prize has never been larger in scale, and once final federal approval comes, we sit at roughly T minus four years from after-tax cash flows that will carry us among the top 10 global mining companies. Canada's government understands the urgency and is moving forward in meaningful ways by passing Bill C-5, the Building Canada Act. That legislation is meant to put projects of national interest first so as to boost Canada's economic resilience and independence and to capitalize on its distinctive standing as the critical minerals deposit of the world. Making this ethos succeed depends on turning verbal commitments into faster execution, and our focus is on doing our part. Canada has a chance to lead the world in critical minerals exports, and given the commitments made in Ottawa regarding accountability and timeliness, the economic and social growth that follows will benefit Canadians for generations to come. The outlook is unprecedented when it comes to actioning such a positive generational opportunity for NexGen and for all those advanced development companies in the sector that have been developing their projects to meet the unsatiable demand.
Leigh Curyer
executiveThe landscape for nuclear is shifting fast. Uranium market fundamentals are evolving in ways that should deliver upside unlike anything we've seen. The companies that come out ahead are the ones that saw the environment changing, found the nerve to take it on and lead it, focusing on tomorrow and the next 50 years rather than gazing backward and leaning on old, outmoded habits for reassurance. The surest route to delivering in the future is to build it yourself, and that is precisely what NexGen has done from 2011 onward, when a dedicated group of industry professionals traveled to the overlooked, never explored far side of the Athabasca Basin — contrary to the popular geological theory of that time — and found what is today broadly acknowledged as the premier uranium project on earth. Geologically speaking, NexGen has redrawn the boundaries of what's achievable and is still writing that story with PCE and beyond at Rook I. Environmentally and socially, the company has established fresh benchmarks for what genuine innovation and consultation can accomplish. On shareholder returns, it stands ready to produce returns for every dollar spent that set a new high-water mark for the sector. My thanks go out to each person on the team who is devoted to this company. We are full of good energy. With that, we'll open the line for questions.
Operator
operatorThank you. Ladies and gentlemen, we will now start the question-and-answer portion. To get into the question queue, you can press star and then one on your telephone keypad. A tone will sound to confirm your request. If you are on a speakerphone, please lift your handset before pressing any keys. If you would like to remove yourself from the polling process, please press star followed by the number two. Our first question comes from Ralph Profiti of Stifel Financial. Please go ahead.
Ralph Profiti
analystThanks, operator, and thanks, Leigh, for taking my questions. Leigh, first off, a competitor has made some remarks about how prudent certain contracting strategies are when it comes to the ability to deliver lbs, and about that being a risk the utility itself is bringing forward at a growing rate. I'm just wondering, what has your experience been in dealing with utilities and in building, sort of, a mutual confidence in delivery of targets?
Leigh Curyer
executiveYes. Well, thank you, Ralph, for asking that. On the contracting front, we're extremely active — we have a lot going on. There are numerous talks underway with utilities across the US, Europe, Asia, and the Middle East. What keeps emerging from those discussions is the importance of a diversified primary mine supply, and those utilities view NexGen as a genuine leader when it comes to delivering a more diversified supply chain fuel cycle that fits what they need. Well, we've already signed 4 contracts. We have another 600 negotiations in play. We've built up pricing terms that exceed what has been reported in the market. And on average, we're seeing GBP 2 million over the first 5 years. Now, at Arrow, our break-even sits at GBP 3.5 million. And I suppose the criticism that has been voiced or circulated out there simply shows that we are leveraged to this shifting environment and that we're taking action on it. Whatever that amounts to for them, I'll leave them to handle it. What we're doing is simply leveraging our project against the demand, in a way that benefits the stakeholders at NexGen while also addressing the key technical and sovereign risks for the utilities. Yes. We're continuing forward with that strategy. It's quite simple. It's very clear. And it's gaining a tremendous amount of traction with major utilities in the US and around the world.
Ralph Profiti
analystThanks, Leigh — that was a valuable answer. I also want to follow up regarding what you've seen when it comes to securing that kind of technically skilled labor, plus the seasoned upper-tier construction management that NexGen will be keeping in-house. Do any notable hiring gaps remain that worry you?
Leigh Curyer
executiveYeah. Our philosophy is that a NexGen team member owns each key aspect of our operations — whether that's mining, exploration, or the non-technical side, be it finance, legal, communications, any of it. Within NexGen, we have a person accountable for that. Basically, what you're seeing is an expansion of the teams reporting to those key executives we already have in place. We are experiencing huge demand in terms of people coming to NexGen and wanting to join the team. We put out for 20 open positions in September and had over 1,300 applicants. That, coupled with our training programs up in the local project area. It is a key aspect, but one that we are ahead of. I think the project itself, plus the company's culture, is attracting the right type of people to our organization. We have done an enormous amount of planning around that. We are currently ahead of it. I think labor availability sometimes gets unfairly used as an excuse for a number of mining projects around the world. We have been planning this for seven years since we submitted the project description. We have a very simple project, very simple mine, and in a great location.
Leigh Curyer
executiveWhen it comes to drawing people to this project — one that's generational in scale — we aren't running into some of the same labor difficulties that other companies in the sector are facing. As for the risk registry, I'm very, very comfortable with where we currently stand and with our forecasted position as we move forward into construction and production.
Ralph Profiti
analystThanks, Leigh, and nice work on the progress.
Leigh Curyer
executiveI appreciate that, Ralph.
Operator
operatorOur following question comes from Katie Lachapelle at Canaccord Genuity. You have the floor.
Katie Lachapelle
analystHi, everyone. Appreciate you fielding my question. Leigh, in your prepared remarks you mentioned having forward-looking utilities that want to provide financing to get NexGen into production. Could you say a bit more about what that involves? Would it come through the standard term contract talks you're currently having, or possibly through prepayments on offtakes? And on term contracts, clearly the base escalated price has risen over the past couple of months. How are the terms shifting in your negotiations? If you could speak to any floors or ceilings, that would help.
Leigh Curyer
executiveThank you. Of course. For that question, I’ll pass things over to Travis. Katie?
Travis McPherson
executiveYeah. Thanks, Leigh. And thanks, Katie, for asking. On the financing side, particularly where the utilities are concerned, yeah, I'd put it that way. We are in negotiations and looking at every avenue when it comes to financing. Prepayment is part of that. So are interests in the project itself. I think, importantly, going back to Leigh's earlier point, it shows a growing recognition of where the market is heading and the supply gap that exists today and that, come 2030, becomes very, very challenging for them. From where we sit, there's a clear understanding that you can't just sit there and wait around. You have to be proactive, and they are being proactive with us. As for offtake contract terms and discussions, obviously those are confidential in nature. What I can say is this. Again, all of our contracting is based on where the market is going to be in 2030 and beyond when it is relevant for us, not what the price is today or tomorrow. When we are having discussions with utilities, it is on that basis. The pricing and all the other terms reflect that world. Again, very much getting significant buy-in from around the world, from our counterparties that we are discussing this with.
Travis McPherson
executiveOnce again, we're incredibly busy on that front. What I'd say is that understanding keeps growing regarding where the market is actually headed, and these utilities are eager to get ahead of it — they want that diversification, and they want to lock in new supply.
Katie Lachapelle
analystGot it. Perhaps one brief additional question. During your prepared comments, you cited a break-even figure of GBP 3.5 million. Is there a specific number of contracts or a specific coverage percentage you aim to reach prior to a final construction decision? Or would you be at ease starting construction and then adding further contracts while the build proceeds?
Leigh Curyer
executiveAbsolutely, 100%. We feel very at ease beginning construction with only the contracts we currently have secured. As I mentioned, we're essentially at break-even. Beyond that, we hold an additional GBP 26.5 million that is fully exposed to future uranium prices. Some agreements we'll enter into—whether through offtake negotiations or signed contracts—will be tied very closely to the market price at delivery time. That's the core principle behind our contracting approach. There's no fixed element in that regard. We're simply capitalizing on our extremely low cost per lbs. The technical certainty surrounding our production volumes means we can increase output to GBP 30 million from GBP 3.5 million break-even quite easily, without any additional sunk CapEx. Our contracting approach simply mirrors the technical and sovereign characteristics of the mine, which is how every company's contracting strategy ought to reflect. It just so happens that our project possesses remarkably strong technical competence and highly favorable economics.
Katie Lachapelle
analystExcellent. Thanks so much, everyone, and congratulations on how far things have come.
Leigh Curyer
executiveAppreciate that, Katie.
Operator
operatorAndrew Wong of RBC Capital Markets has the next question. The line is yours.
Andrew Wong
analystHey, good morning, and thanks for taking my questions. Maybe just on the longer-term contracting implications again. The Rook I project is obviously large and has implications for that longer-term S&D outlook. Given that the approvals are getting there but aren't quite approved yet, are utilities waiting to see how Rook I timing plays out before they make decisions on contracting? And just in general, how does that potential timing of the project — how do you see that affecting utility behavior overall?
Travis McPherson
executiveRight, no, sorry Travis. Yes, thanks Andrew. No, no. On timing — permit approvals and that sort of thing — I wouldn’t call it relevant to the discussions we’re having with the utilities, because every one of our contracts is tied to commercial production starting. It’s premised on an understanding that, I’d say, there’s less and less uncertainty about exactly when uranium will be produced, given how far along the permitting process is — but on the understanding that, yes, this is a new mine we’re developing, so delivery depends on commercial production commencing. That simply reflects the fact that utilities understand where the market is heading and want to lock in uranium from this new mine.
Leigh Curyer
executiveThere's a decent chance we'll see an increase from certain utilities we aren't in talks with right now. That's definitely a possibility, Andrew. And as Travis mentioned, that factor hasn't been decisive for the offtakes we've already signed or for those currently under negotiation.
Andrew Wong
analystAll right, got it, and thanks. Turning to the PCE numbers, those still look quite encouraging. Once the resource figures come out, and if the stock perhaps doesn't fully capture that, might you look at something like a spin-out?
Leigh Curyer
executiveAbsolutely, it's quite possible. If we believe it isn't being valued fairly, that's certainly something we'd take into consideration. Time will tell, I think. Given how PCE is developing, there's still a great deal more drilling to be done before we fully grasp its nature. And once we do grasp its nature, I think that could be a possibility if we don't believe it's truly being valued the way it should be. So yes, that's something, yes. To answer your question, Andrew, that is something that's possible. But if that were the case, we would make sure that PCE has a right, subject to additional approval, to be extracted through the proposed production exhaust shafts at NexGen. And no corporate structure would stand in the way of optimizing the exploitation of that deposit.
Andrew Wong
analystAll right, thanks a lot — that's much appreciated.
Operator
operatorCraig Hutchison from TD COWEN has the next question — go right ahead.
Craig Hutchison
analystMorning, everyone — thanks for joining — and good morning to you, Leigh, along with your team. Leigh, during your opening comments you brought up Bill C-5 and the possible advantages it could bring to NexGen. So I was just sort of curious: when you factor in the timelines, since your permits are already quite clearly laid out at this point, in what way could Bill C-5 genuinely end up benefiting NexGen? And perhaps on a wider note, have there been any direct conversations with the federal government? How do you view them as being helpful to you folks and supporting you folks going forward?
Leigh Curyer
executiveJust to be clear, Craig, what I meant about Bill C-5 is that it shows the Canadian government is committed to nuclear energy and to speeding up important projects. I agree with you. Our project is already so far along in the existing regulatory process that Bill C-5 will barely affect Rook I itself. What's exciting for the group of advanced development uranium companies we belong to is that, in my view, the intent behind Bill C-5 is very encouraging for them. For anyone with an advanced development project in Canada, I think it's really exciting that the Canadian government genuinely recognizes the need to speed up approvals. In parallel, we are strong advocates of that. We believe congratulations are due to the federal Canadian government for recognizing it and acting right away. Prime Minister Carney has only been in office since May, but he's already on it. While it doesn't specifically affect NexGen, I think it's a very clear signal not only for uranium mining but also for the development of small modular reactors in Canada and for broader nuclear programs. As a general comment, it's great for nuclear, and NexGen is part of that value chain.
Craig Hutchison
analystAlright, thanks — a follow-up question. During your previous call, you mentioned that you were fairly far along regarding long-lead critical path items, procurement, and so forth. Could you give us some idea of where things stand at present, and whether there's anything further to do on that front before your permits come through next year?
Leigh Curyer
executiveYes. There’s a quite detailed execution timeline, and naturally it hinges on getting the final federal approval. It’s possible that we’ve already placed orders for the long lead time procurement items, like the freeze plant for the temporary shaft sinking for the first 100 meters. As we speak, that’s sitting in the warehouse, ready to be shipped to site once final approval comes. Other aspects concerning the Hoist house, et cetera. Look, we know exactly what we’ll be doing every single day of the construction period, and we’ve interrogated it multiple times. The benefit of a long permitting process is that it gives you an enormous amount of time to plan, revise, and prepare. That is what we have done. We have also got an additional $1 billion in our treasury. That process will continue and will exist right throughout the entire construction execution period. We are well ahead of it as we speak.
Craig Hutchison
analystAlright, thank you very much, everyone.
Leigh Curyer
executiveThanks, Craig.
Operator
operatorOur following question comes from Mohammed Sadubi at National Bank Capital Markets. You have the floor.
Mohammed Sadubi
analystHey Leigh and team, thanks for taking my question. Could you give us some detail on where detailed engineering stands right now for the project, and where you expect it to be by the time you RFID?
Leigh Curyer
executiveYes. Detailed engineering is moving forward well. To sum up, the detailed engineering for the initial items covering the first 18 months of construction has been finished. Detailed engineering will keep going through the following 18 months, and it is now shifting toward more of the surface infrastructure as well as the mill. It really hinges on which part of the construction you mean, but all of those items for the first 18 months are fully engineered. Let me be clear on this. Our final investment decision has already been taken. We took it back in 2017, when we were certain we had a world-class project in hand, and it was approved, conditional on financing and regulatory approval. There will be no pause or anything of that kind after the final federal approval while we make a final investment decision. That decision has already been made.
Mohammed Sadubi
analystMuch appreciated, Leigh. Regarding the shaft sinking process, if I understand correctly, that detailed engineering work has already been finished.
Leigh Curyer
executiveYou've got that right. Yes.
Mohammed Sadubi
analystExcellent. And taking that note into account.
Leigh Curyer
executiveBut let me make one thing clear. When we talk about shaft sinking, we mean starting from the point where the foundations are prepared, all hoists are installed, and so on, and then underground shaft sinking begins. A considerable amount of work comes before the shafts are actually bored. In practical terms, everything in the first 18 months of construction has already been fully engineered.
Mohammed Sadubi
analystAppreciate the clarification, Leigh. Turning now to your balance sheet — since it strengthened after the quarter, could you remind us what financing mix you anticipate for the rest of the funds needed to advance the project? I believe Travis said all options are on the table regarding possible interest at the project level, debt, or any combination. Any detail on that would be welcome. Thank you.
Leigh Curyer
executiveAbsolutely. Over to you, Travis?
Travis McPherson
executiveRight, thanks Leigh. Yeah, absolutely — nothing is off the table, and the interest we're seeing is enormous. That really shouldn't come as a surprise, given this is a world-class project and a world-class company. So there's huge interest coming from all over the globe, in several different formats. We've discussed these before, but it ranges from strategic interest at the project level, strategic equity, project finance, converts, prepayments, and so on. The encouraging part is that this interest keeps expanding. Those conversations are at fairly advanced negotiation stages right now, as we speak. What the billion dollars accomplished was letting us avoid any time pressure when it comes to figuring out the optimal mix among all these excellent options available to us. So we're in a really fortunate position, with so much interest from around the world across so many strong formats. And our task now, over the next six months to eight months, is to systematically assess and finalize that mix in line with what matters most to us — chiefly preserving our exposure to future uranium prices and our capacity to take advantage of our distinctive production flexibility and optionality. Yeah. We'd aim to have that finalized at some point next year, likely around the midpoint of the year.
Mohammed Sadubi
analystAppreciate it, and thanks for taking my questions.
Operator
operatorOur next question comes from Grace Symes at Energy Intelligence. Go right ahead.
Grace Symes
unknownHello there, and thanks for taking my question. Regarding that GBP 30 million per year production goal, you mentioned it's fairly flexible. I'm just wondering whether there are any plans to adjust that output up or down in response to uranium prices or contracting, or to hold back produced pounds depending on prices so the spot market doesn't get flooded?
Leigh Curyer
executiveRight. So first off, this mine is remarkably flexible — its break-even sits at GBP 3.5 million, and it can ramp smoothly up to GBP 30 million per annum of nameplate output. Whatever the market looks like at any given time, that's what we'll produce, and we'll squeeze the best return we can out of each and every pound we bring out of the ground. The reality is this: the most straightforward mining plan, one that takes the least amount of material out of the underground, given the nature of the deposit, delivers GBP 30 million per annum while moving only 1,300 tons per day. That said, I can't picture any scenario in which we aren't running at full production from 2030 onward, because demand today is plainly there. And that's just today's demand — never mind the growth that's coming, which it will. On top of that, mine supply among the producers operating now is extremely fragile. For 2025 we're forecasting roughly GBP 135 million for the year, while consumption sits at just above GBP 200 million. Inventories built up over the years have been run down fast. You've got producers out there borrowing lbss just to honor their existing contract commitments. Personally, I don't foresee any scenario where we aren't at maximum capacity from 2030 onward. And we retain the flexibility to drop all the way to GBP 3.5 million and still turn a profit.
Leigh Curyer
executiveWe're simply making use of the mine's technical and economic profile.
Grace Symes
unknownAll right, thank you. A quick follow-up question. The uranium market has seen a certain amount of speculation. There's hope on NexGen's part for a buyout prior to the point when it enters production. I'm just curious whether you're able to say anything about that. Thanks.
Leigh Curyer
executiveHonestly, what's being said in the market is ridiculous. A dedicated group of people has been guiding this project, and that team has now been together for more than 10 years. If you look back, permitting was always destined to be the biggest risk, even during production, given how many different stakeholder groups are at the table. Over the past 10 years, we've managed to bring every one of those groups together. Support for this project from all of them is extraordinarily strong — remarkably so, in absolute terms. We're eager to move into construction, because from that point everything is within our control. That's exactly what appeals to us about NexGen. This is a generational project — opportunities like this rarely appear. Our expertise sits in-house. Our financing capacity is there. What we're moving into construction and then production is, in mining terms, a very technically straightforward mine. In everything accomplished so far, we've established a new benchmark for the sector, and that will carry through construction and into production. I don't believe any other group has shown more efficient deployment of capital across the development path, or has avoided wasting a single day.
Leigh Curyer
executiveWith NexGen running things, this project reaches production as fast as possible, delivers the scope already planned, and does so in a way that truly brings in engagement from the various stakeholders. Yeah, the NexGen board, the executive, and the team have absolutely no intention of that. Honestly, we would be bored within roughly 2 days if we sold this company. For our shareholders, we really are the best option to maximize what they get from their investment. That means very clearly keeping it independent inside NexGen and having full leverage to uranium's future price rather than being locked into historical offtake practices.
Grace Symes
unknownOkay, thanks.
Operator
operatorOur following question comes from Graham Tanaka of Tanaka Capital Management. Your line is open.
Graham Tanaka
analystHello, and congratulations on the progress you've made so far. I'm curious about what you're planning when it comes to exploring much of the seven — I believe that's seven quarters — of additional acreage, and whether you might be — or rather, what you might need in order to speed up exploration and development of, basically, a second, third, or fourth Rook I. What are the dynamics that would make you accelerate, or else keep the current pace of exploration? If you could also just touch briefly on how things are going at Patterson Corridor East, thank you.
Leigh Curyer
executiveSure. Thank you, Graham, and thank you as well for the extremely lengthy backing you have given us from the very start. As I said, what we are trying to do is address this problem on a worldwide basis over the coming 50 years, rather than merely the coming five. As you know, we made the Arrow discovery with the very first hole — the 21st drill hole overall, but the very first one sunk inside a 4.5-kilometer radius of where it sits. PCE lies 3.5 kilometers away from Arrow. A highly substantial mineralizing event took place in this region. It is not only at our Arrow and PCE project — we hold numerous occurrences running along the Patterson corridor. As you noted, we have a further seven corridors that remain to be explored. We have not even completed our exploration of the Patterson corridor, where Arrow and PCE are located. PCE, despite sitting on a separate conductor, is still regarded as part of the Patterson corridor. We still have a tremendous quantity of drilling ahead of us. As a base case, however, we have Arrow, which will represent roughly 23% of worldwide mine supply. That is quite remarkable when you consider it. In context, nuclear fuel is turning into the preferred energy source among developed nations and emerging nations. You have Saudi Arabia, the most dominant oil producer in the world, at 9% of oil supply.
Leigh Curyer
executiveSome folks have drawn a comparison to Saudi Arabia when it comes to uranium at the Rook I project. In my view, the mineralization points to a huge amount still waiting to be found. I doubt we were skilled enough to hit the finest deposit on the very first hole drilled within a 4.5 km radius, or on the 21st hole on the property overall. We also hold two other land packages next to Rook I, SW1 and SW3. That's the reason we put up an expanded accommodation camp for exploration. You could run 20 drill rigs for 20 years and still not finish the complete geological evaluation. We know that once approved, four years after approval, we'll be producing roughly 23% of global mine supply from Arrow. A backup is already taking shape at PCE. In every respect it looks very analogous to Arrow. When you look at the mineralization beyond our location, also at Patterson Lake South, I believe there's enough evidence to suggest it's the same mineralizing event — something incredibly significant happened in the area with respect to uranium mineralization. Frankly, I feel we're just scratching the surface. Our results are evident of that. At PCE, we've got some assays coming imminently, followed by more scintillometer results as the program concludes for 2025.
Leigh Curyer
executiveBy 2026, it will be operating again with a program of comparable size. That genuinely reflects the fact that substantial work remains ahead of us before we even reach a fundamental grasp of PCE.
Graham Tanaka
analystI'm curious whether there's some way to pin down what would set off a faster push to build a second Arrow at PCE or somewhere else. What sort of pricing could speed up your work on developing another Arrow? Thank you.
Leigh Curyer
executiveHonestly, our focus is on doing what we're good at. As we move into construction, the exploration group is essentially its own division inside NexGen. To me, four rigs at PCE makes for a solid program. During 2025 it stood as the biggest program in the Athabasca Basin. Under the base case, you'll see that carry on in 2026. Graham, as things stand right now, 2026 will look like a similar program to 2025. Frankly, results can flip everything in an instant. All I can really say, I suppose, is keep watching that space. That's all I can say. We want to execute well.
Graham Tanaka
analystYeah, I'm just kind of wondering. If pricing and utility interest and so on pointed toward needing another Arrow, how quickly or how soon might you be able to bring on PCE or some other prospect? Are we talking 10 or 12 years?
Leigh Curyer
executiveYeah, on PCE — and I don't want to get ahead of anything here. From a conceptual standpoint, I believe the evidence is sufficient to indicate that if PCE were developed, it would be extracted via the very same production shaft as the one proposed at Arrow. That would require further permitting. Since our permit was granted on the basis of acknowledging an area of influence, we wouldn't be beginning from zero at all. My view is that the priority is getting Arrow into production first, running at the level it can achieve, and after that we'll figure things out. That will be step one. Decisions will then be made according to market conditions at that point in time. I agree with you, Graham. My own view is that demand at Arrow is going to be enormous, well past GBP 30 million annually. The gap that exists today on an annual basis is one we can't fill. Yeah, perhaps C5 will prove very advantageous to NexGen where PCE is concerned — to echo the earlier point from Craig Hutchison. Yeah. It's definitely on the radar. But the priority is to execute extremely well on Arrow and Rook I, moving that into construction and then on to production.
Graham Tanaka
analystMuch appreciated, and best of luck.
Leigh Curyer
executiveThanks, Graham.
Operator
operatorOur following question comes from Allen at Future Forten. You have the floor. Morning. Can you hear me?
Leigh Curyer
executiveYes, I can hear you. Last week, the Cree Nation challenged Saskatchewan's approval of the Denison Mine Wheeler River Uranium Project, citing inadequate consultation on Treaty 10, correct? I have two questions. Is your mine located on their territory? Second, do you think similar things could happen to you? Could it delay the opening of the mine? Out of respect for Denison, I cannot speak to that, and I will not comment on that particular situation because I have not been involved with the consultation and engagement with respect to that project. With respect to our project, it is very clear the four identified communities in the local project area identified by the federal government and also the government of Saskatchewan. It is very clear with respect to our four communities. We have undergone study agreements in 2019, which set the foundation for collecting all of the cultural studies and appreciations. We took that and incorporated it into the design of the project, respecting all of those cultural sensitivities. Further, we then executed legally binding impact benefit agreements with those four communities in the project area that covers the entire life of the project and closure with respect to environmental, commerce, employment, and community programs.
Leigh Curyer
executiveIn my view, we've satisfied and gone beyond what was required, and we enjoy complete backing from the communities located within our project area. Yes, I hold a great deal of confidence regarding where we stand and how the approval process will wrap up from that angle. Many thanks. Thank you.
Operator
operatorThat concludes our question-and-answer portion. Leigh Curyer, I’ll now hand the conference back to you for any closing comments.
Leigh Curyer
executiveThanks, Gillian. I want to express my appreciation to all of you for joining us today and for the great questions. This is a truly thrilling moment for the company — honestly, it always is, given everything that's happening at NexGen. And I definitely welcome any further questions you might have. Feel free to reach out to Monica, Paola, Stacey, or Travis, or to me directly, and we'll gladly get you answers. We genuinely value all of your support. Really looking forward to this fourth quarter and 2026 — it's going to be a remarkably exciting period, not just for the market but for the company too. Thank you, everybody.
Operator
operatorThat brings us to the end of today's conference call. You can now disconnect your lines. Thanks for joining us, and have a pleasant day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete NexGen Energy Ltd. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to NexGen Energy Ltd. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in NexGen Energy Ltd. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.