NexGen Energy Ltd. (NXE) Earnings Call Transcript & Summary

November 10, 2026

Toronto Stock Exchange CA Energy Oil, Gas and Consumable Fuels earnings 53 min

Earnings Call Speaker Segments

Leigh Curyer

executive
#1

Thanks, Jason. Good morning, everyone, and I'd like to express our appreciation to all our shareholders and stakeholders for joining NexGen Energy's Q3 2026 Financial Results and Investor Conference Call. Joining me on the line today are Travis McPherson, who serves as our Chief Commercial Officer, Ryan Podrasky, our Chief Financial Officer, and Chris Copley, our Project Director. During this call, we'll walk through the most recent developments in our commercial activities, which includes the uranium market conditions seen through the third quarter of 2026 and up to now, the continued exploration wins at Patterson Corridor East, or PCE, located a mere 3.5 km to the east of Arrow, and, significantly, a report on how construction is advancing successfully at our Rook I site, complete with a slideshow that illustrates the progress being made on site. Following that, we'll open the line for Q&A, giving you an opportunity to put questions to me, Travis, Ryan, and Chris. Forward-looking statements will be part of today's discussion, so the relevant disclaimers are available on our website. NexGen's history will mark August 13, 2026, as a defining day. A ceremonial groundbreaking for the Rook I project took place on that date, symbolizing the start of major construction activities following approval. That date fell 12 years and six months after the Arrow deposit's initial discovery. What has characterized this journey is the boldness to challenge conventional geological thinking, along with persistence, toughness, authentic teamwork, and partnerships with nearby communities—all supported by disciplined planning and achievement of our stated goals with top-tier safety and regard for the surroundings where we operate. Put plainly, this never-ending method has produced outcomes superior to what came before. NexGen's strong base, established through execution across the last 16 years, is now mirrored directly in the calibre of on-the-ground work seen in the accomplished construction at Rook I. Everyone who stood with us and offered their views on August 13 at the groundbreaking ceremony captured what this project represents. We had Saskatchewan Premier Scott Moe with us, along with former Prime Minister Stephen Harper, Secretary of State Buckley Belanger, Métis Nation-Saskatchewan President Glen McCallum, and Métis Local 39 President Keith Shewchuk. Leaders and members from each of our four local priority area communities attended as well, plus many of our international shareholders, board of directors, and team members, among many others—some of whom couldn't make it because of illness or family commitments. What their being there showed went well beyond any one mine. Rook I matters at the provincial level, stands as a national champion, and is being built together with the local communities to establish a fresh benchmark for the global resources sector. Rook I and the southwest portion of the Athabasca Basin form the bedrock of global nuclear fuel supply, and they will underpin Northern Saskatchewan's path and Canada's nuclear energy goals for many decades ahead. Today, that timing matters more than ever. Demand for uranium is at record levels while supply remains constrained. During the quarter, the long-term uranium price reached an all-time high of $99 per pound and has held at that level, and market observers expect a substantial additional rise. Production downgrades, rising sustaining capital, and higher production costs are the dominant features of the world's existing producing mines as those operations move into the later phases of mine life. Energy security and electrification are the two forces shaping this period, and both lead the same way. More electricity is required, and it must be domestically controlled. The idea that Canada possesses what the globe requires has taken on more significance, and Prime Minister Mark Carney recently gave voice to that view. When it comes to resources, uranium above all, that claim definitely holds. Having those resources is just a single element. Seizing Canada's chance rests on firms that see the opening — understanding where the uranium market will go next rather than where it sat before — and that act with responsibility. Saskatchewan now has a different kind of future uranium producer emerging, and this is happening when the market offers opportunities unlike anything seen before. Full credit goes to the group of uranium companies that have projects under construction right now; in these inflationary times, they are setting up contracts the same way NexGen does, linking them to future prices at delivery time, so they can reduce exposure to inflation and cost increases while also being financially shrewd, concentrating on getting the highest financial returns for shareholders and the highest royalties for the great province of Saskatchewan. It is true that uranium prices have increased fivefold over the last ten years, but the volume of uranium we mine is the same as it was a decade ago. Production costs are climbing and existing mines are being depleted, so prices are bound to go considerably higher. The nuclear industry keeps building momentum. Construction is underway on more than 88 GW of nuclear capacity, and roughly another 8 GW will come from restarts and uprates. That adds up to greater than 20% growth, and it leaves out the enormous pipeline of planned reactors plus SMR deployments, which are progressing quickly. Nations worldwide need dependable baseload power at scale to satisfy electricity demand that is rising fast, and that need is fueling this expansion — something the industry has not experienced since the 1970s and 1980s. Right now, enormous amounts of capital are being poured into energy infrastructure worldwide. In Canada in particular, demand for new nuclear plants has come roaring back—Saskatchewan is one example, where Premier Scott Moe laid out a plan to bring 2.6 GW of nuclear power to the northern part of the province by 2050. On top of that, Ottawa is breathing new life into CANDU, the Canadian nuclear mainstay, and recommitting to it—with a pledge to sell this proven, homegrown technology to markets across the globe. What's unfolding in Canada is truly remarkable. This quarter, Prime Minister Mark Carney made the case for a four-reactor nuclear facility at Darlington, Ontario, backed by a CAD 3 billion investment split between federal and provincial governments, framing it as a step toward Canada controlling its own future. Canada's nuclear narrative has turned a fresh page. In the words of Prime Minister Mark Carney, "We are an energy superpower, and we are only getting stronger." Across the country, atomic energy is enjoying a standout stretch. Out in Port Hope, Ontario, the province's utility has submitted plans for a brand-new 10,000 MW nuclear facility, while along the Lake Huron shoreline, the Bruce Power Nuclear Power Plant — among the biggest such stations anywhere on earth — is proceeding with an effort to double its output to 4,800 MW. Over in Alberta, a pitch to produce a comparable amount of electricity via four large-scale reactors close to the town of Peace River has now entered its impact assessment process. At the same time, in New Brunswick—the province home to the sole nuclear plant in operation beyond Ontario—authorities are exploring options to grow nuclear capacity. Such momentum was equally evident during the quarter at the sector's leading uranium gatherings, including the World Nuclear Symposium held in London and the Global Uranium Conference in Adelaide, where considerable appetite for NexGen's offtakes alongside encouraging sentiment bolstered an extremely favorable environment for NexGen and the broader uranium sector; this transformation is becoming more and more concrete, as large technology firms like Amazon, Microsoft, Meta, Google, and numerous others provide financial backing for nuclear power's expansion and the supply chains needed to sustain that growth.

Leigh Curyer

executive
#2

On top of that, governments are making clear they see a need for strategic reserves—Kazakhstan was the latest to do so during the quarter—and they are putting more money into nuclear fuel supply chains. Taken together, these developments keep reinforcing the expectation that uranium requirements will be materially higher. You can see these dynamics reflected in uranium pricing right now. As I noted earlier, term pricing as of October 31 sits at a historical high of $99 a pound. Three-year and five-year forward prices have hit 105 and 112 US dollars per pound, respectively. Uranium prices keep climbing, which underscores how strong the fundamentals are in our sector. Rook I stands as one of only a handful of uranium projects currently being built anywhere on the planet. Combined with Patterson Corridor East and the 190,000 hectares of prospective ground we hold, this provides NexGen with the base to supply the uranium required for the coming stage of worldwide nuclear expansion. Over at Patterson Corridor East, the 2026 drill campaign is nearly finished. We keep observing expansion and robustness within the mineralized system, and further news is on the way. The results we released in the quarter once again brought attention to a substantial basement-hosted uranium system that continues to expand. In the course of the quarter, the high-grade subdomain expanded 17%, reaching 644 meters at present, and in light of those results we committed an additional fifth rig to the program. Additional results are on the way and will be put out imminently. Although resource estimation, engineering, environmental studies, and permitting are still going to be required down the road, these results indicate that PCE is a highly advantageous avenue for NexGen and for Canada's nuclear energy objectives. Regarding contracting, we are in advanced discussions with numerous utilities around the world. Utilities globally recognize NexGen's unique value proposition when it comes to materially diversifying their supply chains toward reliable, technically sound, and geopolitically stable new sources of uranium. Negotiations will continue to move forward, and we anticipate signing further sales deals over the periods ahead. While we carry out construction at Rook I, our approach to contracting stays straightforward and unchanged: getting the greatest value for each pound we produce and sell by making contract terms shorter and linking them to market prices prevailing when delivery occurs. That method has shown itself to be sound, especially given developments at other large supply hubs. As of today, NexGen is the Western world's company with the most exposure to where uranium prices go in the future, and that will always remain the case. At the close of Q3 2026, we held CAD 822 million in cash and short-term investments, plus another CAD 341 million of inventory in U3O8 — a strong balance sheet that gives us considerable financial flexibility as we move Rook I forward. NexGen's strategic positioning and its unique exposure to future upside in the uranium price have opened the door to a wide range of attractive, accretive financing options, among them strategic financings, prepayments, and project financing. What matters greatly is that the liquidity we already have gives us the room to be very disciplined as we weigh those alternatives and pick the funding package that works best, so we keep our flexibility and go on maximizing long-term shareholder value by delivering the Rook I project build successfully. What matters greatly, too, is that we keep hitting the key construction milestones within scope, on schedule, on budget, and safely. During the third quarter, construction activity picked up substantially, with earthworks and critical surface infrastructure moving forward throughout the whole site. Work has begun on the critical path exhaust shaft pad, along with civil and concrete foundational work. The work to extend the runway to 5,840 feet has been completed, and that means we'll be able to accommodate big jet aircraft before the year is out. On the construction facilities pad, the civil foundations are mostly done, and they support both the temporary construction facilities and the main batch plant. The contractor for shaft sinking is now on site, along with the freeze plant, which we purchased strategically back in 2023; that equipment reaches the site in January 2027, and temporary freezing gets underway in March 2027 — an important milestone on the critical path. We'll go into more detail on this in the visual slideshow at the end. Detailed engineering keeps moving ahead in line with the overall project schedule, focused on civil packages, shaft infrastructure, and site-wide utilities. NexGen has also awarded key construction contracts spanning aggregate crushing, earthworks, concrete, shaft sinking, steel buildings, and power generation. Procurement keeps speeding up, with procurement underway right now for over 50 process plant long lead items, as well as procurement for underground equipment. The progress made through Q3 reflects the result of substantial detailed planning carried out over many years during permitting and our focus on safe execution. Let's go through the latest construction photos via the link included in today's news release. They provide a straightforward visual update on the substantial progress being achieved throughout the site, the scale, and the work currently underway as we continue moving Rook I toward production. Going through the slides here, this is the eastern end of the extended runway of 5,840 feet, which was completed on October 23, 2026. The permanent access road remains on schedule for November 26, and the runway electrical systems remain on schedule for February 15, 2027. This slide shows two pictures of the exhaust shaft and temporary power facility pads. Building on what we covered earlier on this call, the civil works for both of those activities are now mostly finished, getting us ready for the batch plant to arrive and for the foundations that will support the freezing for the freeze plant, followed by the freezing of the exhaust shaft in Q2 2027. The production shaft pad is finished already and set for civils that are on track to wrap up on December 16 of this year. On slide six you'll see the construction facility pad, which covers the primary batch plant area along with the temporary facilities area. And as you can tell, snow has begun falling at site too. Turning to the secondary batch plant, it has either reached the site already or is in the process of getting there, and the first concrete pour is set for December 16, 2026. Here you see the primary batch plant, which is going to serve project construction by producing and delivering concrete for the foundation, the structural works, and other essential site infrastructure. Right now it is being unloaded at the Port of Houston before it heads to site. Every component is expected on site by December 4, 2026, and installation will take place during the first quarter of 2027. As for the stockpile facility, all of the earthworks were finished on October 15, 2026. Moving on, the waste pad—also called the waste management facility pad—offers short-term holding capacity for materials from the site prior to treatment or disposal. Site clearing and grubbing for this work has been completed, cut and fill activity is underway, and completion is targeted for December 18, 2026. What you see here is the effluent diffuser installation, a 500-meter pipeline completed on August 30, 2026. This was an extremely intricate effort involving multiple contractors working together under project management by the NexGen team, and the installation was successful, calling for barges, cranes, and divers to carry it out. Finishing work on the pad and roads continues and remains on schedule for completion by December 18, 2026. Regarding the expansion of the exploration core yard and the mineralized cutting tents — that yard is getting bigger so it can handle, or be prepared for, PCE's complete 2027 drilling campaign.

Leigh Curyer

executive
#3

That really shows how confident we are in the PCE resource and in how much core will be needed, or how much core storage will be needed, because of the drilling program we're running at PCE in 2027. We also expanded the temporary accommodation at the camp expansion. Again, that was finished in June 2026, on time and on budget. We now have accommodation on site for 570 people, including an additional 200-person camp as well. We have capacity for more than, well, 770 people when it comes to construction activities at site. The septic tank absorption field as well, on schedule and set for completion in December. The Clearwater Bridge was installed by the Saskatchewan Highways Department, which NexGen greatly appreciates, and it reflects the government's commitment to the project in making sure the right transport infrastructure is in place to support the heavier haulage vehicles coming to and from site going forward. Thank you, and I'll hand it over to the operator to open the call for any questions anyone may have.

George Eadie

analyst
#4

Yeah. Hey, Tim. Thanks for today's update. I just want to ask about cash spend — the run rate went up in Q3 the way you expected. Could you help us think through what that run rate looks like from here over the coming couple of quarters? And on that same point, once some of the larger elixir capital arrives, and thinking about your current liquidity buffer, when do you need to finalize the next funding strategy at the latest? Thank you.

Leigh Curyer

executive
#5

Yeah. Thanks, George. Yeah, look, as things stand, our cash and short-term investments fund us through to the end of Q3 2027. Our spending has increased, particularly over the past quarter, and construction is progressing well. The larger reduction of our cash reserves begins once we start excavating the shafts. Those are planned to get underway at the start of Q3 2027; so, yes, we have ample runway. We have numerous alternatives available to us regarding financing, and we will address that matter in a way that preserves the optimization of project construction; we will provide an update on that in due course.

George Eadie

analyst
#6

Yes, great, thanks Leigh. On the strategic inventory — you still don't view that as a source of funds, is that right? Then, if I can squeeze in one more as well, some of the bigger CapEx spends with the shaft sinking, like, can you remind us of the contracts? Are they fixed at this point, or are they price-based, or are they still TBD?

Leigh Curyer

executive
#7

Yes. To start, we won't be selling the inventory at all, nor using it as a source of financing; regarding your second question about the shaft sinking contract, that contract is signed. The result matched exactly what we had projected for financial cost on the Rook I project back in August 2024. That served as clear confirmation that our financial cost estimate for sinking the shafts had been extremely conservative, since expenses have risen during that period. Labor makes up a big portion of shaft sinking, and as everyone knows — it's been widely reported — there are inflationary and wage pressures at play. Our contract is structured so that we have full transparency into and control over those costs. Should they rise, we will cover them. For those shafts, the shaft contractor has a big incentive tied to how fast it sinks them, and those rates have been heavily analyzed and validated against the rock conditions. As with everything we've done at NexGen throughout our 16-year history, we have been conservative and met market expectations in everything we've done, and the construction of this project will be no different. I would also just add-

George Eadie

analyst
#8

All right. Thank you, Leigh.

Leigh Curyer

executive
#9

And one more thing I want to mention. We've already secured the purchase of quite a few pieces of equipment, and where we've pinpointed items that even if they show up in year four of construction, we've gone ahead and ordered certain significant pieces so they arrive on schedule and at the price we anticipate. As I mentioned, we've spent more than seven years planning how this project will be built. We know precisely what we're doing on each day across that four-year construction window, and I really need to trace that back, since we're already well into it, along with who's carrying it out and which contractors will be backing NexGen in that effort. From the slides we reviewed, you can see the dates are extremely specific, down to the day, for when things begin and end, and that shows just how much planning we've put in.

Ralph Profiti

analyst
#10

Thanks, operator. Leigh, I've just got one question for you about the geotechnical side. You actually touched on this in your last answer, and that 60-hole program did a very good job of identifying things like rock quality and compressive strength. I'm just wondering what follow-up work is underway, what happens now on the geotechnical side, and what comes next between now and, say, when temporary freezing begins in March of 2027?

Leigh Curyer

executive
#11

I'll take the first part, and if I've missed anything, I'm sure Travis or Chris will gladly jump in. But taken as a whole, we've finished a full geotechnical assessment of the shaft conditions themselves. So we've drilled pilot holes right down the middle of the exhaust and the production shafts; we've drilled geotechnical holes right throughout the ore body, right throughout where the underground tailings management facility will be located, and more broadly around the project as well. I'd venture to say, or rather I will say, I'm not aware of another project that's had geotechnical testing to this extent before actual construction. We know every millimeter we're drilling through with respect to the exhaust and the production shafts. Now, those are the two most critical items in this entire construction process. As we highlighted in our webinar on September 1, we've been extremely transparent about the ground conditions we expect, the reasons for them, and those who've been fortunate enough to visit site have seen the core firsthand and can attest to its competency and consistency. To answer your question, Ralph, no further geotechnical work needs to be done before we commence excavating the exhaust shaft, starting at the beginning of Q3 2027.

Ralph Profiti

analyst
#12

Got it. Thanks so much.

Mohamed Sidibé

analyst
#13

Hi, Leigh. Thanks for taking my question — I appreciate it, and it's great to see the progress at site. Maybe on your procurement packages and contracts: the shaft sinking contract is signed, but could you remind us of any other procurement packages or contracts that haven't been awarded yet that might be driving, in your view, perhaps the biggest cost or schedule risk? Thank you.

Leigh Curyer

executive
#14

Well, I'll start. The major ones have been issued. Right now we have more than 50 that we're issuing, and there are quite a few more beyond that. Among the major construction items is the batch plant for the foundations. One item is the freeze plant that we purchased in 2023, over three years ago. For a good while now, it has been sitting in a shed, prepared to be moved up to the site. The second would be the power plant, which isn't required until year four, though we have already bought it. The order will be placed, and we have locked in the contract terms for it. As things stand, those are the main ones, I'd say. We have not observed any increase in delivery risk that matches our construction schedule whatsoever. My view is that this comes from how thoroughly we planned during the seven years prior to receiving approval to begin building the project. The speed with which the runway has been put in, and the growth of that camp to 770 people in a top-tier environmental way, show that we're extremely active at the site right now. The count is 376 people. There's a tremendous volume of work underway on site, and all of it is progressing. It's proceeding in this sequence. I want to state this very plainly. The scope is fixed, and we won't scale it back—doing so serves this project's long-term economic interests poorly, while we keep environmental and safety standards at the highest level and build in or maximize community contracting and hiring wherever possible, an area where we presently lead Canada. Management has it well in hand; the big items have received substantial effort and remain our focus, and as we speak it's tracking to our schedule, scope, and cost. We review it continually. It isn't a one-and-done situation where every day everything is wrapped up. Review and mitigation happen nonstop, and that will keep going. I can say right now that this project is going to be delivered within scope, and at the best time and cost we can possibly achieve. As I mentioned, that comes down to the team we have at NexGen, which we've built up over the last seven years, and to how much fine-grained detail we've invested in the planning and the risk mitigation surrounding it. I'd simply ask everyone to keep an eye on how we're progressing. If you go back to the September 1 webinar, you can look at the timeline of events and compare it against what we share on every quarterly call, and then hold us to it. That doesn't worry us in the slightest. There is a lot of excitement on site, and it is building right now as we speak.

Mohamed Sidibé

analyst
#15

Thanks a lot for that color, Leigh. For my second question, if I may, I'd like to direct it at Travis, just on the contracting side and offtakes. Given the recent policy shifts in — not policy, but the midterm election won by the Democrats — and questions around data centers and hyperscalers, I'm just wondering, from a utilities perspective, has anything changed in terms of your conversations and how they're approaching long-term contracting? Or is it the same kind of strength and bullishness that we've seen since the last few years? Thank you.

Travis McPherson

executive
#16

Yeah. Thanks, Mohamed. The short answer is no, we haven't seen any change with respect to that. We wouldn't forecast any, or any material anyways. Some SMR companies made announcements today about their progress. The midterms, of course, are a U.S.-specific matter. The U.S. is clearly a very important jurisdiction—one that has backed nuclear power on a bipartisan basis, and has done so for quite a while. Our conversations aren't limited to American utilities; we're engaging with utilities worldwide. As we mentioned earlier, there's enormous interest in our project and our product, and people want to move quickly. So the midterms haven't changed anything on that front.

Leigh Curyer

executive
#17

No, I'll just.

Mohamed Sidibé

analyst
#18

Thank you.

Leigh Curyer

executive
#19

Let me just add that at the Global Uranium Conference in Adelaide — normally that's a conference where you don't have, or historically there haven't been many utilities. Asian utilities had a strong presence, and they spoke quite openly about accessible uranium supply from 2030 onwards. That's a genuine worry for them, and the demand is insatiable. They're well aware that Kazakhstan is building its own strategic inventory to back its own nuclear initiatives. The takeaway was that essentially everything they're going to be permitted to procure is pretty well locked up; so it's materializing. While you won't see that directly reflected in the spot price, the spot price is climbing, the long-term price sits at a historic high and is moving further. The three and five year is well into the hundreds and heading higher. So it's happening. People ought to look at all of those components when they try to gauge these market fundamentals and how they're playing out. As NexGen and having been in the sector since 2002, but particularly as NexGen's history, this market opportunity is, I think, the most compelling across all commodities, without a doubt. As everyone knows, I bang on about it. I'm very technically and financially fact-driven, and that assessment rests on that, technical and financial fact. It's incredibly exciting for investors in NexGen and also the other uranium cohort.

Mohamed Sidibé

analyst
#20

Appreciate that, Leigh Curyer. Thanks.

Leigh Curyer

executive
#21

Thank you, Mohamed.

Bill Peterson

analyst
#22

Yes. Morning, and thanks for fielding the questions and for all those progress updates. You're hiring a great many people, you're putting them through training and so forth. How should we think about headcount additions over the coming 12 to 18 months? What kind of inflation are you seeing with such additions? I guess more broadly, how should we think about expenses, salaries, given the big step up in 2026?

Travis McPherson

executive
#23

Yes. Honestly, our training initiatives have remained a major priority for us since 2022. Before it became a common talking point that hiring is difficult, with labor shortages and so on, we had already long struggled to locate the right candidates, simply because we hold out for the right fit. We've consistently invested time in developing them, spotting them, and bringing them aboard properly, and we aren't encountering any difficulties on that front. Whenever we post an opening, we genuinely receive thousands of interested applicants for every single role. So no, we aren't running into problems there. We've got it handled. Our efforts go back quite a ways, and those early bets are paying off today. Take one recent case: we ran a training course for heavy equipment operators. Forty-seven people enrolled, all forty-seven completed it, and ten were hired right away at our site, while the remainder went to work for various contractors of ours to round out their employment. That's just one modest illustration of the training programs we keep running. On the subject of wages and similar matters, as you and Leigh both noted, our top two priorities are scope and schedule. We're prepared to compensate people well to get the work done and done to a high standard. It doesn't require a huge headcount if you've got the right individuals. You compensate those right individuals appropriately, and you don't bring on five staffers for a role one person can handle.

Leigh Curyer

executive
#24

Yeah, over the quarter and heading into 2027, we’ve actually brought down the level—or the overall G&A cost—as well. At a managerial level, when you look at the scale of activities or the spend during Q3 and going into full year 2027, the G&A component is actually going to decrease as a percentage; we’re extremely focused on every dollar we spend. I have to say, right now, when it comes to labor rates, the actual cost on a per-hour basis, we haven’t seen a significant increase in cost over the 2026 and 2025. I think that comes from a couple of aspects. Very strong management of them, but also people want to come and work at NexGen, given the project that we’re working on and the conditions at NexGen and the advancement. It’s another factor that you’ve got to really manage closely and be ahead of. With the training programs that we’ve put in place early, we’re starting to see the results and benefits of that planning.

Bill Peterson

analyst
#25

Yes, thank you for those remarks. Perhaps if we take a step back and consider the larger CapEx picture; during the investor day, you noted that 2027 appears to be the peak year for CapEx. First, I'd like to verify, at least two months later, that this remains true. I suppose if you run the numbers, it comes out to roughly CAD 600 million. Is that the correct way to view it right now, particularly considering the comments you just provided?

Leigh Curyer

executive
#26

Yes. That remains entirely accurate, and we anticipate it will occur during 2027. Yeah.

Bill Peterson

analyst
#27

Thanks.

Graham Tanaka

analyst
#28

Hi, guys. Congrats on the progress. It's good to see things moving along on schedule and on budget. Can you confirm, or repeat once more, what you expect the all-in cost per pound to be once you're at production? And maybe give us some sense of how that curve could shift as you move from year one to year two to year three on cost per pound; I also had questions about your reserves, and really the mine life plans in terms of scaling up and flexibility going forward. Thank you.

Leigh Curyer

executive
#29

Thanks, Graham. I'll begin and then pass it to Travis. The cost estimate, the production rate, and everything of that nature per the definitive feasibility study stays as it is in that study. On PCE, there is clearly a lot of interest, obviously, because of the clear upside it brings to the NexGen story. That remains subject to a future resource calculation, engineering studies, environmental studies too, and obviously subject to permitting. I'll simply say the probable development scenario would be, and as I mentioned, with that qualification, would be subject to permitting, and so on. We wouldn't anticipate any material challenges there, since we've already gotten the permit for the Arrow deposit. There is still substantial mineralization that we've hit with the drill bit outside the current grade shells and mine plan of Arrow. I think a logical development scenario is Arrow, as laid out in the definitive feasibility plan, with ongoing production at Arrow while we prove up additional material and increase the drill density of those intersections in and around Arrow, and also beneath the current Arrow grade shell. Also examining how PCE gets optimized once we have an initial resource statement for PCE, which we'll be aiming for around the beginning of Q3 2027, obviously subject to when assays come in. So, very exciting. NexGen is clearly much bigger than Arrow alone, even though Arrow is number one in the world. It's a great position to be in. I think the exploration team is doing a magnificent job with the five rigs on PCE. They'll take a short break over Christmas and then get right back into it at the start of 2027.

Graham Tanaka

analyst
#30

And yes, on that cost per pound—coming back to it—how does it look compared with your plans even seven years back? I'm just curious how much that works out to per pound.

Leigh Curyer

executive
#31

Well, the cost per pound, as validated in the August 2024 financial cost, came in at just under $10 a pound U.S., with an all-in cost of roughly $14 U.S.

Graham Tanaka

analyst
#32

All right. What would that estimate come to today?

Leigh Curyer

executive
#33

Well, it's kept in line with the August 2024 financial cost we published. It's unchanged.

Graham Tanaka

analyst
#34

Fabulous. Congratulations. Thank you.

Leigh Curyer

executive
#35

Thanks, Graham.

Craig Hutchison

analyst
#36

All right. Morning, everyone. On the financing side, you said you're funded through Q3 of next year, but could you speak to how the financing will roll out? Should we expect a set of financing measures announced together, or might some of these announcements come separately? I'm also curious about your latest thinking on prepays. Thanks.

Leigh Curyer

executive
#37

Yeah, well, it hinges on several factors, market conditions at the time, et cetera. Look, I think as things stand, it'll be a mix of those different alternatives, not just one. A rising uranium price certainly helps in securing a lower cost of finance, whatever form it takes. So, yeah, I'd like to be more specific, but that's as specific as we can be right now. As I said, as we sit here, we would expect a combination of one or more of those activities that we're looking at. We are negotiating a prepayment with entities both in and outside of the U.S. as we speak. There are a number of prepayment options that we're looking at. Very importantly, any decision around that is tied to maintaining leverage to the future price of uranium at the time of delivery. So, that is our approach and our guiding principle in those prepayment negotiations.

Craig Hutchison

analyst
#38

Okay. Thanks, Leigh.

Leigh Curyer

executive
#39

Thanks. Thanks to all of you for being here today and joining our call. We're in construction mode right now, working on what is the world's newest uranium project of major importance. The timing could not be better; we're seeing a market in which supply stays structurally constrained while demand for secure, reliable nuclear power keeps accelerating, exactly as Rook I moves forward in construction and will reach production just a few short years from now; to close, safe and successful execution along with community advancement stay at the heart of everything we do. We're delivering Rook I to the highest standards, importantly to scope, and within the most efficient time and cost achievable, while we keep growing the opportunity across our wider district and creating long-term value for our stakeholders. We invite and expect better, and we always will deliver better in everything we do; with that, it's an exciting time in the industry, an incredibly exciting time at NexGen Energy. I'd like to take the opportunity for the team on the call and the team out at site, they're doing a magnificent job delivering this hugely material project on a world scale. Thank you.

Operator

operator
#40

That concludes today's conference call. Your lines can now be disconnected. Thanks for joining us, and enjoy the rest of your day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete NexGen Energy Ltd. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to NexGen Energy Ltd. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in NexGen Energy Ltd. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.