NLC India Limited (513683) Earnings Call Transcript & Summary

August 1, 2023

BSE Limited IN Utilities Independent Power and Renewable Electricity Producers earnings 56 min

Earnings Call Speaker Segments

Operator

operator
#1

Ladies and gentlemen, good day and welcome to the NLC India Limited Q1 FY '24 Earnings Conference Call Hosted by ICICI Securities. [Operator Instructions] Please note that this conference is being recorded. I now hand the conference over to Mr. Mohit Kumar from ICICI Securities Limited. Thank you and over to you, sir.

Mohit Kumar

attendee
#2

Thank you, Yusuf. Good evening. On behalf of ICICI Securities, I would like to welcome you all to the Q1 FY '24 earnings call of NLC India. Today, we have with us, Shri M. Prasanna Kumar, Chairman and Managing Director of NLC India; Shri K. Mohan Reddy, Director, Planning and Projects; Dr. Suresh Chandra Suman, Director, Mines; Shri Samir Swarup, Director, Human Resources; Shri M. Venkatachalam, Director, Power; and Shri Mukesh Agrawal, Executive Director, Finance. The call will begin with brief remarks by the management, after which we'll open the lines for the Q&A session. I would now like to hand over the line to CMD sir, for his opening remarks. Thank you and over to you, sir.

Prasanna Motupalli

executive
#3

Okay, thank you. Good afternoon, everyone. Thank you very much, Mohit ji, for hosting this investor conference call, and greetings to all participants for showing interest in NLCIL and thanks to all investors for extending continuous support. I would like to take this as an opportunity to interact with the NLCIL shareholders and also reply to their queries in the financial results for the quarter ended 30 June, 2023 and company's capacity addition program. I am Prasanna Kumar Motupalli, Chairman and Managing Director of NLC India Limited, and joining with me today through conference call are Shri K. Mohan Reddy, Director, Planning and Projects; Shri Suresh Chandra Suman, Director, Mines and Director, Finance, Additional In Charge; Shri Samir Swarup, Director, Human Resources; Shri M. Venkatachalam, Director, Power; and Shri Mukesh Agrawal, Executive Director, Finance, along with senior management of the company. Before the interaction, I would like to brief on the highlights and performance of NLCIL during the quarter 2023-'24, major events. NLCIL secured the bid for solar 600 megawatt including 300 megawatt under Green Shoe option in the auction conducted by GUVNL. NLC India Renewables Limited, a wholly owned subsidiary, has been incorporated for pursuing asset monetization. On 13 June, 2023, power purchase agreement was signed between NUPPL and APDCL of Assam for power supply of 492.72 megawatt to the state of Assam. With this, the entire power capacity of NUPPL has been tied up. NLCIL has been awarded first place under Timely Payments in CPSUs for GeM purchase in the presence of Honorable Minister of State for Commerce and Industry. And Telangana has consented to take 200 megawatt of solar power under CPSU scheme of SECI. On standalone basis, the revenue from operations for the quarter ended 30/6/2023 is INR 2,601 crores as against INR 3,094 crores in the corresponding period of the previous year. Revenue from sale of coal during the quarter ended 30 June, 2023 is INR 461 crores as against INR 449 crores in the corresponding period of the previous year, registering an increase of 2.83 percentage. The total income of the company for the quarter ended 30/6/2023 is INR 2,690 crores as against INR 3,177 crores in the corresponding period of the previous year. Profit for the period for the quarter ended 30/6/2023 is INR 331 crores as against INR 506 crores in the corresponding period of the previous year. And on consolidated basis, the revenue from operations of the group for quarter ended 30/6/2023 is INR 3,316 crores as against INR 3,863 crores in the corresponding period of the previous year. The total income of the group for the quarter ended 30/6/2023 is INR 3,428 crores as against INR 3,966 crores in the corresponding period of the previous year. Profit before tax of the group for the quarter ended 30/6/2023 is INR 614 crores as against INR 854 crores in the corresponding period of the previous year. Profit after tax, PAT, for the quarter ended 30/6/2023 is INR 414 crores as against INR 569 crores in the corresponding period of the previous year. While wholeheartedly thanking the investors for the sustained support and encouragement all these years, I hope the same would continue in the future also. Thank you.

Operator

operator
#4

[Operator Instructions] First question is from the line of Abhineet Anand from Emkay Global Financial Service.

Abhineet Anand

analyst
#5

I was just trying to understand the dip in profitability on a Y-o-Y basis for the quarter. If you can just let us know what could have been adjusted for last quarter 1Q and this quarter 1Q?

Prasanna Motupalli

executive
#6

Okay. Actually, the dip in the profit for the quarter 1 is mainly attributed to the reduced production from lignite mines at Neyveli and the corresponding power generation from the lignite-based power stations at Neyveli. This was mainly on account of the non-availability of land for expanding the mining activities. This is the reason why the lignite production is less than the requirement for power generation. And because of that, there is a fall in revenue and the profit.

Abhineet Anand

analyst
#7

So what is the status now, sir? I mean, there have been some media articles with respect to this. So for the year, will we be able to match availability and decrease under-recovery?

Prasanna Motupalli

executive
#8

With the support from the central government, state government, and district administration, almost all the issues are sorted out and the process of taking over of the land already started. The first activity for taking over the land, the diversion of the river, has also already started. So we are hopeful that we will be able to take possession of all the land required in the next 1, 1.5 month, and we will reach to the lignite production level as per the requirement of our thermal power station.

Abhineet Anand

analyst
#9

Okay. Second thing is, sir, in state of -- what is the status of Ghatampur? I mean, is there some further delay from 4Q? We had talked about this year, I think H2, it will get commissioned, the whole plant. Is there some delay on that further?

Prasanna Motupalli

executive
#10

As committed earlier, all the 3 units of Ghatampur, we are committed to declare the COD in the current financial year. So the first unit, unit #1, the COD will be declared in the month of October. The second unit will be in the month of January and the third unit will be in the month of March. In the current financial year, all 3 units, COD will be declared and works are progressing in line with this target.

Abhineet Anand

analyst
#11

And last one sir, this Talabira, the ordering for this, when do we expect that to happen?

Prasanna Motupalli

executive
#12

At Talabira, the main issue was land, already we tendered for the power plant package and all the activities in that package are completed. Only we are waiting for some substantial part of land to be in our possession. There is a tremendous improvement in the land acquisition process. In last 2, 3 months period, things are moving very fast. With the support from the state government and the Ministry of Coal, the things are moving very fast and this project is under priority, so being monitored by highest authority in the country. That's why in all the areas, the land acquisition process is progressing with encouragement and already around 174 acres of land is acquired in the last 1.5 to 2 months. So we are hopeful that by October we will be able to take possession of substantial portion of land and complete the awarding process by around November, December.

Operator

operator
#13

Next question is from the line of [ Jitendra Jain ].

Unknown Analyst

analyst
#14

I'm little surprised by the rather a little dismal performance for this quarter. However, as I have understood that because of the lignite mining, the production was hampered. But what will be the position in the month of, say, in the quarter ending September or December, because this is a perennial problem which you are facing in lignite mining and unless you are able to get lignite, I think the production will suffer. And as I understood that you are still adhering to the schedule of October for the UP for this year. But are you sure that this will happen or it may also be get delayed? And the third question is about the regulatory issues which I had raised about 2, 3 times in con call. What is the present position about the regulatory issues, that appellate tribunal and the [Technical Difficulty]? Please elaborate.

Prasanna Motupalli

executive
#15

Okay. Sir, as I already communicated, there was some problem because of land in the quarter 1 of this financial year. But whatever actions we are taking and whatever actions are in process, with that, we are going to get a substantial portion of land with us that is sufficient for next 5 years. So I am confident that whatever actions we have taken now and the land possession activities are also already started and our lignite production also started increasing. So whatever measures we have taken now, they are not the short term measures. They will ensure the continuous production of lignite for next 4, 5 years without any interruption as per the requirement of our thermal power station. So we are confident about that. That is the first point.

Unknown Analyst

analyst
#16

And about the second question of UP, are you sure that in this year itself all the 3 will be initiated?

Prasanna Motupalli

executive
#17

Yes, yes. We are sure that all the 3 units will be commissioned in the current financial year and we are initially targeting for the COD of unit #1, which we are targeting by the end of October. All the activities that are required for COD of the unit are progressing as per plan and we are 100% sure that we will be completing that process by October and declare the commercial operation of unit #1 in October and subsequently the next 2 units also.

Unknown Analyst

analyst
#18

The third question is, as we understand, the Tamil Nadu government has withheld the payment because of that liability order of about INR 2,500 crores. So are you going to get payment -- have you received that payment or they have still withheld that payment because of the passing of local order? So the matter is pending at appellate tribunal but you have not received the payment. So that will hamper the cash flow position of the company. Kindly elaborate on this subject.

Prasanna Motupalli

executive
#19

Yes. I request our ED, Finance, Mukesh Agrawal ji to respond to this question.

Mukesh Agrawal

executive
#20

As we have already intimated that our 1 lignite transfer price regarding [ 2009-'14 ] is under appeal in the appellate, APTEL. The court has scheduled hearing on 25 July, 2023 and APTEL has directed the methodology for treatment of [ O&M ] cannot be changed in the [indiscernible] exercise and should be in line with the methodology adopted for the provisional tariff determination and has remanded back the case to the APTEL. Thus the case is in favor of the NLCIL. Now the second leg is regarding the [ '14-'19 ] for which TANGEDCO has withheld an amount of INR 1,200 crores, around. That will also be get resolved through this regulatory order. First they will redo the [ '09-'14 ] prices and after that they will revisit the [ '14-'19 ] prices because the [ '09-'14 ] -- [ '13-'14 ] will be the base for the [ '14-'19 ]. So in this process now the money will come back in a very short time, 2, 3 months it will take in the -- both the orders should be get set right from the CERC.

Unknown Analyst

analyst
#21

During this intervening period, I think the cash flow is getting affected, isn't it?

Mukesh Agrawal

executive
#22

Cash flow, as such, we are not facing any cash problem but definitely this will come and will be utilized -- when this will be released, it will be utilized for the CapEx addition program. It will support us in that way.

Operator

operator
#23

Next question is from the line of Rabindra Nath Nayak from Sunidhi Securities.

Rabindra Nath Nayak

analyst
#24

First of all, I'd like to thank the management for coming out with the Q1 results a little bit early this quarter and this year and there is no big negative line item. So good thing to know. So regarding this land issue, sir, you have already mentioned that what is the issue there. So how much land we are in possession right now to meet the FY '23 production of lignite? And how much is going to be acquired and how much is in possession right now for at least for this year FY '24? So if you can answer that.

Prasanna Motupalli

executive
#25

Actually, as on date, for maintaining the lignite production levels as per our requirement, the critical land requirement is 81.79 hectares of land. This is the critical land that is required to augment the production to the required level. But in the next 5 years, we require around 1,000 hectares of land with around 250 -- 200 to 220 hectares of land every year. So as on date, whatever possession orders are passed, around 379 hectares orders are already passed and around 675 hectares orders are in the process of issuing the notification. So immediately, the requirement is 80 hectares of land only and subsequently around 235 hectares of land to maintain the production levels in next 2 years.

Rabindra Nath Nayak

analyst
#26

Okay, so will we be able to beat the last year's production with the kind of -- if we -- whatever land we are in possession, from second quarter onwards, the run rate will increase and also beat the last year production or it is very difficult to beat the last year's production of lignite?

Prasanna Motupalli

executive
#27

No, no, no. Certainly, we will cross the last year's production. I think all the problems regarding land are going to be sorted out and already some positive effect we are seeing in the production of the lignite. So lignite production already started improving. So we are hopeful that we will cross all the production we achieved in the last financial year and ensure that the generation is maintained.

Rabindra Nath Nayak

analyst
#28

Okay. The coal realization, Talabira and EBIT number for coal for this quarter, if you can help me to -- these numbers, that will helpful, sir.

Prasanna Motupalli

executive
#29

Okay, in Talabira, we produced around 21.04 lakh metric ton and we supplied around 23.74 lakh metric ton. So the sale value is around INR 461 crores compared to INR 448 crores in the last financial year. And if you want further bifurcation in that, we -- the coal sale through e-auction is around 9.10 lakh metric ton. Coal sale to NTPC is 6.21. Coal sale to NTPC coal swapping is 3.40. And coal sale to NTPL is 5.03.

Rabindra Nath Nayak

analyst
#30

Okay, okay. And sir, from this INR 481 crores of mining profit, how much it is from Talabira?

Prasanna Motupalli

executive
#31

From Talabira, our mining profit is -- last financial year it was INR 677 crores. And in the current quarter, the profit is INR 198 crores against INR 94 crores in the previous financial year, quarter 1.

Rabindra Nath Nayak

analyst
#32

Okay. Okay. Sir, is it possible to give under-recovery because of the -- due to low generation and also the under-recovery due to the plant? Is it possible to give this number, the under-recovery?

Prasanna Motupalli

executive
#33

Certainly. Certainly. See, in the current financial year, the thermal under-recovery is INR 185.52 crores against previous year's of INR 81.25 crores. And if we add NTPL also, for the total NLC group, the under-recovery is INR 211.72 crores against previous year's of INR 125.30 crores.

Operator

operator
#34

[Operator Instructions] Next question is from the line of Somnath Saha from B&K Securities India Private Limited.

Somnath Saha

analyst
#35

Can you share me the PAF for the quarter and versus the last quarter, last year same quarter?

Prasanna Motupalli

executive
#36

Plant Availability Factor?

Somnath Saha

analyst
#37

Yes, sir. For this quarter and last year same quarter, sir.

Prasanna Motupalli

executive
#38

Okay. So, like if you go by the plant- wise, TPS I expansion against 100% PAF of last financial year, this year it is 77%; TPS II, against 86%, this year is 42%; and TPS II expansion, against 57%, it is 51%; and Barsingsar, it is -- against 62%, it is 80%; and NNTPS, against 90%, this year it is 92%; and NLCIL overall, against 83%, it is 63% this quarter.

Somnath Saha

analyst
#39

Okay. Sir, can you repeat the under-recovery figures for this quarter?

Prasanna Motupalli

executive
#40

Okay. The under-recovery in the current quarter, total NLC thermal is INR 185 crores against the previous year's INR 81.25 crores. And if you include NTPL also for a total NLC group, the under-recovery is INR 211 crores against the previous year's INR 125 crores.

Operator

operator
#41

[Operator Instructions] Next question is from the line of Nikhil Abhyankar from ICICI securities.

Nikhil Abhyankar

analyst
#42

I wanted to ask you about the coal to chemical project that you have taken up. So should we expect the award to happen in this year?

Prasanna Motupalli

executive
#43

Yes. Actually, I think you are talking about the lignite to methanol project.

Nikhil Abhyankar

analyst
#44

Yes, sir, lignite to methanol.

Prasanna Motupalli

executive
#45

See, the lignite to methanol project as on date is in the top of the list. [Technical Difficulty] It's already tendered. Both the packages of the -- this lignite to methanol project, one from lignite to syngas and another from syngas to methanol, both the projects are under tendering. We already tied up technology provider, Air Products of USA, and 4 parties are interested to participate in the bid. The vendors already signed NDA with the technology provider and also paid requisite fees to them. So the bid will be opened on 7 August, 2023. So we are hopeful that we will be awarding both the packages in next 2 months and start the work. Parallelly, the site preparation activities at the NLC Township already started. And the tree felling activities and preparation activities are in fast progress. So we are hopeful that once this is awarded, the work will start immediately. And the total -- the CapEx requirement for this project is INR 4,394 crores. And we are expecting some [indiscernible] from the government also.

Nikhil Abhyankar

analyst
#46

Understood. Sir, just to clarify again, NLCs overall PAF for Q1 was 63% as against 80% last year, you mentioned, right?

Prasanna Motupalli

executive
#47

Yes, yes, yes.

Nikhil Abhyankar

analyst
#48

Yes. So what can be the overall PAF in the month of July?

Prasanna Motupalli

executive
#49

In the month of July, we are expecting around 70% -- it will be around 70% to 75%.

Nikhil Abhyankar

analyst
#50

So under-recovery will definitely reduce in Q2.

Prasanna Motupalli

executive
#51

Yes, yes. Certainly it will reduce. And as we move on, I think that under-recovery gets reduced.

Nikhil Abhyankar

analyst
#52

Sir, what can be the target under-recovery for the entire year?

Prasanna Motupalli

executive
#53

So, our target, obviously, will be 0. But we are putting all efforts to reduce it to 0 level. But it will be certainly less than the whatever under-recovery was there in the last financial year.

Operator

operator
#54

Next question is from the line of Abhineet Anand from Emkay Global Financial Service.

Abhineet Anand

analyst
#55

Yes, from this Talabira coal mine, we supplied 23 lakhs this year. What was the number for last year, 1Q?

Prasanna Motupalli

executive
#56

Just 1 minute, last financial year, the supplies from Talabira -- 1 minute, last financial year, the supplies were 27.12 lakh metric ton that was supplied and 25.46 was the production.

Abhineet Anand

analyst
#57

So just trying to understand, the production was lower and revenues have been -- and average realization has been higher. But e-auction prices would have been lower, right? I'm assuming that e-auction prices have come down. So I'm just trying to fill the gap that our e-auction was 9 lakh. So whether the e-auction volume was far higher this year, which actually led to a higher overall revenue in coal mining or how is the case? So what is the average pricing for the quarter in e-auction?

Prasanna Motupalli

executive
#58

Exactly. Last quarter, the coal sale through e-auction was only 0.75 lakh metric ton. But at that point of time, the rate was INR 8,337. But this quarter, the e-auction quantum jumped to 9.10 lakh metric ton, with a base rate of around INR 2,370. So as the quantum of the e-auction increased, so the revenue increased to INR 273 crores through e-auction compared to INR 76.53 crores in the last financial year.

Abhineet Anand

analyst
#59

INR 273 crores versus what did you say, sir?

Prasanna Motupalli

executive
#60

INR 273 crores in this financial year and last financial year Q1, it is INR 76.53 crores.

Abhineet Anand

analyst
#61

Okay. So this year, is it fair to -- what could be your -- I mean, now that we have done 9 lakhs, for the full year, is there any estimate for what could be the e-auction, sir?

Prasanna Motupalli

executive
#62

See, actually, we are not targeting for any quantity in e-auction. After supplying to our NTPL plant and the country's requirement like NTPC and other, and whatever balance coal is there, that we will go for e-auction. So obviously, this will be certainly much more than whatever was achieved last financial year. But we are not targeting any quantity for e-auction.

Abhineet Anand

analyst
#63

Still, I mean, last year, I think we did around 1 million, right?

Prasanna Motupalli

executive
#64

Yes, yes, yes.

Abhineet Anand

analyst
#65

And we have already done around 1 million in 1 quarter -- around, I'm saying.

Prasanna Motupalli

executive
#66

Yes, yes, yes.

Abhineet Anand

analyst
#67

Is it fair to assume for this year that those numbers could be 2, 3 million at least?

Prasanna Motupalli

executive
#68

Yes, of course.

Abhineet Anand

analyst
#69

And sir, in terms of one of the units under-recovery was because of the CFBC boiler and you have -- last analyst meet and all, you had mentioned that you will be taking some structural changes which could lead to lower under-recovery. So can you just throw some light, where is that status in terms of...

Prasanna Motupalli

executive
#70

Last, I think, investor meet, we told some action plan about improving the availability and reliability of the CFBC boilers. In line with that, we already placed order on BHEL for doing the modifications in line with the suggestion given by the original technology provider, Doosan Lentjes. We engaged the original equipment manufacturer Doosan Lentjes for some recommendations. And we studied in the contemporary units also and finally, we formulated, we designed some modifications. And those modifications are already ordered on BHEL. They're in the process of manufacturing the required material. And we are expecting that by the end of this year, we will be able to take one of the units for the modification. And once this modification is done, then the availability of these units will be substantially improved.

Abhineet Anand

analyst
#71

So you're saying one of those units will be -- I mean, BHEL will be able to replace the required material by the end of this year, so availability improvement for one of the units will happen next year. And for the other units, probably subsequent year, right?

Prasanna Motupalli

executive
#72

For other unit, we will take immediately after this unit. So in continuation to that unit, we'll do the modification with the second unit also. So by the quarter 1 of next year, I think both the units, the modification will be completed.

Abhineet Anand

analyst
#73

And is there any gestation period when you order to BHEL, how much time it would take to manufacture and all? This is a large stuff or is it a small order, sir?

Prasanna Motupalli

executive
#74

It is a big order of INR 57.8 crores plus GST. The order is already placed on BHEL and we are planning to combine this activity along with the annual overhauling of the units also so that the availability reduction will be minimal.

Abhineet Anand

analyst
#75

And each unit will take how many months for this, sir?

Prasanna Motupalli

executive
#76

So this -- actually, the OEM is asking for more, but we are targeting for around 45 to 50 days for completion of this.

Operator

operator
#77

Next question is from the line of [ VK Sauthalia ] from [ VK Associates ].

Unknown Analyst

analyst
#78

So before I ask my question, there is some background I would like to share with all the esteemed members of the management committee here. So NLC, being a public sector organization, the ownership of the company belongs to the people of India represented by the President of [ India]. [Technical Difficulty]. And being a transitory [Technical Difficulty].

Operator

operator
#79

Sorry to interrupt, [ Mr. Sauthalia ], your voice is breaking, sir.

Unknown Analyst

analyst
#80

So, [ President of ] India being transitory administrator, and each government, every 5 years, [Technical Difficulty]. This background I'm giving with a view of clarifying the direction given to NLC to part with the Talabira coal to NTPC. By giving this major chunk of the Talabira coal to NTPC, which should have gone into e-auction, I am estimating that company is losing up to INR 500 crores per year. So is the management of the view that some of these NTPC coal can be retrenched back to the e-auction route? And what is the compulsion for the company to give coal to NTPC at the subsidized rates of INR 850 per tonne? Why does the NLC has to obey these orders?

Prasanna Motupalli

executive
#81

See, you must have already seen, compared to last year e-auction quantity of 0.75 lakh metric ton, this year, e-auction is already 9.10 lakh metric ton. And being a government of India public sector enterprise, the priority of nation is our first priority. There was a situation when the country was in the power crisis and the coal supplies were not meeting the requirement. And we also wanted a long-term type of coal supply agreement. That's why that was given to NTPC and that is the same thing is being continued. And as I already told you, after ensuring supplies to NTPL, our own plant, and NTPC as per the MOU, which we signed, after that, whatever is left, that will be going for e-auction. And as we are already targeting 12 million metric ton this financial year and the supplies we are committing to others is much less than that, that's why we are expecting that we will be increasing our e-auction almost 2 to 3 million metric tons in the current financial year and accordingly the revenue also will improve.

Unknown Analyst

analyst
#82

So is there any escape route like -- can you bypass the NTPC allocation entirely? Or are you bound by the Ministry of Coal direction to supply coal at INR 850 to NTPC?

Prasanna Motupalli

executive
#83

No, no.. There are no such directions for supplying at that rate or for this MOU. This MOU is signed with NTPC to ensure proper evacuation of our coal to different stations. And the -- above the base rate, we are getting 10% up to 3 MTPA. And beyond 3 MTPA, we will be getting 20% through the MOU route. So I think we are hopeful that we can maximize the revenue by supplying to NTPC also, more than 3 million metric tons in an [ annum ].

Unknown Analyst

analyst
#84

Is the swapping arrangement beneficial to the company? Is it substituting imported coal, the minimum requirement of 10% imported coal? Are you being compensated by supplying to NTPC?

Prasanna Motupalli

executive
#85

See, whatever compensation we are getting, that is in the form of the rate only, the base rate of Coal India, plus 10% and base rate of Coal India plus 20%.

Unknown Analyst

analyst
#86

No, no, no. What I'm saying is, is the company bound to use 10% imported coal? So by supplying to NTPC, is that quantity being compensated in some way or you're still bound to import -- use imported coal up to 10%?

Prasanna Motupalli

executive
#87

No. Actually, see, as on date, we are having the coal base station of only NTPL. That NTPL is a 70-30 plant, where 30% -- it is designed for 30% import and 70% indigenous coal. So that 10% requirement is not there for NLC because we are not importing any other coal other than for NTPL. So that application of 10% is not there for NLC India Limited. And second point is that -- one more point I want to highlight here, see, if you see by the e-auction trend, as on date, the demand for coal is reduced, that's why our prices for e-auction also got reduced substantially from almost INR 8,500 to now almost INR 2,600. So that also getting reduced day by day.

Unknown Analyst

analyst
#88

So are we using any imported coal now for NTPL?

Prasanna Motupalli

executive
#89

We are using imported coal for NTPL because that is designed for higher [indiscernible] coal.

Unknown Analyst

analyst
#90

30% are imported coal.

Prasanna Motupalli

executive
#91

We are not using 30% but we are using the coal at NTPL.

Operator

operator
#92

Next question is from the line of Rabindra Nath Nayak from Sunidhi Securities.

Rabindra Nath Nayak

analyst
#93

Sir, I have a question regarding this renewable power. We have a total capacity of around 1,421 megawatts currently. So where are we in sort of setting up a different subsidiary and also [ when you're unlocking ] from this renewable energy side, we have already got an order from [ GUVNL ] for setting up a renewable capacity there in Gujarat. So whether it will be in a separate subsidiary or it is in the standalone entity? That is my first question. And where are we in the green power -- the subsidiary monetization, if at all it is there? So where are we right now? And secondly, you have, in a recent media article -- you have -- media interview, you have commented that NLC is going to enter into exploration of different minerals or other minerals. What minerals you are looking at currently, beyond lignite and coal? What are the other minerals the company is looking at right now?

Prasanna Motupalli

executive
#94

Okay. Regarding the renewable capacity, as you already mentioned, we are having, as on date, 1,421 megawatt of renewable capacity and NLC India Limited was the first public sector to add 1 gigawatt of renewable capacity. And we are aggressively trying to add more renewable capacity. And as for our corporate plan, we want to be a 6-gigawatt plus company by 2030 regarding renewable power capacity addition. And already, efforts are on in this direction. Our 500 megawatt CPSE scheme, 300 megawatts were awarded at Rajasthan and work is in progress. We want to complete the project at the earliest in the current financial year itself. And 200 megawatt already we got consent from government of Telangana for signing PPA. We'll be going to signing the PPA at the earliest and the 10-megawatt solar project at Neyveli under Smart City, that is already commissioned. And in addition to that, we won 600 megawatt in the GUVNL tender at the Khavda Park in Gujarat, where we are trying to install and commission the projects at the earliest. So in this way, we want to add every year around 1,000 megawatt capacity to reach 6-gigawatt company by 2030. In addition to that, one more important aspect is for having -- from solar capacity added, the requirement is the land. So to ensure that the problem of land is addressed, we tendered for capacity addition of around 50 megawatt solar in our mine reclaimed land, and this is the first of its kind in the country where so much huge capacity is being added in a mine reclaimed land. And we are exploring the possibility of doing the same in more land area with more solar capacity addition. And second -- to your second question, exploration of minerals...

Rabindra Nath Nayak

analyst
#95

Sir, just -- sorry to interrupt. What about the subsidiarization of plant of the renewable energy capacity?

Prasanna Motupalli

executive
#96

We incorporated a 100% owned subsidiary, NLC India Renewables Limited. And whatever renewable assets we are having as on date, all those assets will be transferred to this subsidiary and for doing the asset monetization. And in all our future activities, we will be doing business of renewables under this subsidiary to ensure the -- to get the advantage of tax.

Rabindra Nath Nayak

analyst
#97

Okay. Okay. So this will -- there is no plan for any sort of listing or monetization of this subsidiary by the company in the near future?

Prasanna Motupalli

executive
#98

No, no. Certainly -- finally, the asset monetization that will result in the listing and sale of the asset -- sale of the stake.

Rabindra Nath Nayak

analyst
#99

Okay. Okay, sir, regarding the other minerals?

Prasanna Motupalli

executive
#100

Regarding other minerals, when there is some encouraging policy in the exploration of minor minerals, as we are having experience of mining for the last 65 years, what I told at that point of time was that we will look into the opportunities with the experience we are having in the mining sector, we will explore the possibility of exploring the minor minerals like lithium in the future. That is only a futuristic statement, because we are having experience in the mining sector.

Rabindra Nath Nayak

analyst
#101

Okay. So lithium mining [ near-term ] the opportunity in lithium mining you're expecting?

Prasanna Motupalli

executive
#102

Yes, yes. If the opportunity is there, then we will use our expertise in the mining and explore the feasibility at that point of time.

Operator

operator
#103

[Operator Instructions] Next question is from the line of Ashwani Sharma from ICICI Securities.

Ashwani Sharma

analyst
#104

So my first question is on the CapEx. What was the CapEx during the Q1? And what is the target for FY '24 and '25?

Prasanna Motupalli

executive
#105

Okay. Our CapEx target for the financial year '23-'24 is INR 2,880 crores. So if you consider the target in quarter 1, the quarter 1 target is INR 327 crores -- sorry, on the -- quarter 1 target is INR 878.34 crores. Against that, the actual expenditure is INR 744 crores, which is up around 85%. And you asked about the CapEx for '24-'25 also. CapEx for '24-'25 is INR 2,386 crores, and this is for '24-'25.

Ashwani Sharma

analyst
#106

Okay. Secondly, just a clarification on the Talabira. The awarding, you're still confident of doing in the month of October?

Prasanna Motupalli

executive
#107

Yes, in the month of October, we are expecting possession of substantial portion of the land. So immediately, we will take forward that award process. And we are hopeful that before the month of December, we will be awarding the contract at Talabira.

Ashwani Sharma

analyst
#108

And Neyveli?

Prasanna Motupalli

executive
#109

Neyveli also we are targeting for award before the month of December -- December 2023.

Operator

operator
#110

[Operator Instructions] We have our next follow-up question from the line of Abhineet Anand from Emkay Global Financial Service.

Abhineet Anand

analyst
#111

Just for Ghatampur our coal linkage was for Pachwara South Coal Block, right?

Prasanna Motupalli

executive
#112

Yes.

Abhineet Anand

analyst
#113

So I think that is going to probably start sometime later. So how are we thinking about the linkage there then?

Prasanna Motupalli

executive
#114

Actually, the Pachwara Coal Block, for that, the end use plant in Ghatampur. And we are expecting production of coal from this Pachwara Block from January, or February of this financial year. But before that, we already got the stack-up coal from [ Makum Coalfield Limited ] for stack-up activities and the commissioning activities. And also we got bridge linkage of 2.64 million metric tons for this plant for supplies from Coal India subsidiaries till the coal supplies from Pachwara Coal Block are established. So I think there is no problem for the coal supplies to Ghatampur. Usually, already, we are having the stack-up coal tie-up with NLC -- sorry, NCL and the contract is also awarded for the logistics. And subsequently, we will be getting the bridge linkage from Coal India subsidiaries till the time we get our coal supplies from Pachwara Coal Blocks are established.

Abhineet Anand

analyst
#115

So you said Pachwara will be ready from Feb '24.

Prasanna Motupalli

executive
#116

Actually full operations of coal extraction will start in '24, but we are expecting some coal extraction from the month of January, February.

Abhineet Anand

analyst
#117

Because why I'm saying is that, bridge linkage 2.5 million is not good enough for its PAF, right?

Prasanna Motupalli

executive
#118

Yes. [Technical Difficulty] 2.64 million metric ton. So taking our scheduled COD into consideration and already we are having stack-up coal for running the unit at least for 1 month or 1.5 month, so this 2.64 million tonnes, I think, is sufficient. If not, we are having a plan to move Talabira coal to Ghatampur, If any shortfall is there at that point of time.

Abhineet Anand

analyst
#119

Okay. So whatever extra we might have mined in F '25 in Talabira, we can move that.

Prasanna Motupalli

executive
#120

Yes, yes, yes.

Abhineet Anand

analyst
#121

And Talabira, what's your mining plan for F '25?

Prasanna Motupalli

executive
#122

Talabira, this financial year, we are targeting 12. Next it is going to be 15 and 18. And finally, it will be 20, the pit rated capacity.

Operator

operator
#123

The next question is from the line of Gaurav Lohiya from Bowhead India Fund.

Gaurav Lohiya

analyst
#124

I just wanted to check, sir, out of this INR 200 crores under-recovery in Q1, could you give the break-up, how much would be due to lignite-related issue and how much would be due to, let's say, CBFC (sic) [ CFBC ] boiler-related issue in TPS II?

Prasanna Motupalli

executive
#125

See, it is very difficult to exactly bifurcate these 2, but most of this under-recovery, other than TPS II expansion, is on account of lignite only. If a clear bifurcation is required, out of this INR 185 crores of under-recovery in NLC thermal -- if you remove the TPS II expansion INR 20 crores, INR 25 crores, around INR 150 crores is on account of lignite shortfall and the balance INR 35 crores is on account other reasons.

Gaurav Lohiya

analyst
#126

Okay. And last year, sir, in FY '23, your total under-recovery was close to INR 500 crores. And was that -- a similar proportion can be taken for that? Or again, that TPS II-related under-recovery was much higher over there out of that INR 500 crores?

Prasanna Motupalli

executive
#127

No, no. We are hopeful that this year, the under-recovery will be much less than the financial year '22-'23. Although there is some problem in the quarter 1, we are hopeful that this will be covered in the subsequent quarters as it is on annualized basis.

Gaurav Lohiya

analyst
#128

Yes. But our TPS II plant-related issue will get resolved only by Q4 end or Q1 of FY '25...

Prasanna Motupalli

executive
#129

That is TPS II expansion you are talking about. In TPS II expansion, already, we have taken short-term measures to improve the availability and those measures are working. Where we -- mainly, it is because of lignite shortfall, there is -- availability shortfall is there. So we are hopeful that once the lignite supplies are maintained, then we will be able to maintain substantial recovery in the under-recovery.

Gaurav Lohiya

analyst
#130

Okay. So you expect the overall under-recoveries to go down in FY '24 itself, not just FY '25.

Prasanna Motupalli

executive
#131

Yes, yes, yes.

Gaurav Lohiya

analyst
#132

And sir, you said that the possession of the land required for this lignite production, everything would be done in 1 month. But when do you expect the full production to come out? Because from possession of the land to extraction of coal can take time, right, or lignite coal can take time. So when do you expect the full production to start? Or are power plant to start production at full utilization?

Prasanna Motupalli

executive
#133

See, actually, our lignite production got affected because our -- due to fully mechanized mining and some pockets of land are not available for facilitating the mechanized production. So once we get to this 80 hectares of land, immediately, we will be able to increase the production, not to the full level, but gradually that will pick up and finally we'll reach the full level. So with the possession -- taking possession of some critical land, it will immediately increase and for other land, after taking possession, it will take 2 to 3 months again to start extraction and augmenting the production.

Gaurav Lohiya

analyst
#134

Okay. Understood. And sir, there were news report about some unrest due to we taking over those lands. So what's your view on that? Do you think that, again, the courts can then stay on we taking the possession and again, we may see some delays in ramping of the production?

Prasanna Motupalli

executive
#135

See, there were some problems, both at strike level as well as what you are highlighting the -- there were problems. But now all the issues have been sorted out. There was a court hearing also which was supporting the land acquisition at the earliest. So we are hopeful that this will be done at the earliest.

Operator

operator
#136

Ladies and gentlemen, this was the last question for the day. I would now like to hand the conference over to the management for the closing comments.

Prasanna Motupalli

executive
#137

Thank you. Thank you very much for your continued support, and I hope the same will continue, encouraging the NLC India for diversifying and maximizing the revenue as well as profit. Thank you, thank you very much.

Operator

operator
#138

Thank you. On behalf of ICICI Securities, that concludes this conference. Thank you for joining us, and you may now disconnect your lines.