Northern Star Resources Limited (NST) Earnings Call Transcript & Summary
January 23, 2024
Earnings Call Speaker Segments
Operator
operatorWe appreciate everyone being on the line, and we’re glad to have you join us for Northern Star Resources’ December 2023 Quarterly Results. Everyone attending is in listen-only mode for now. After a presentation, we’ll hold a question-and-answer session. <<operator_script>> At this point, I’ll turn the conference over to Mr. Stuart Tonkin, Managing Director and CEO. Over to you.
Stuart Tonkin
executiveThanks, and good morning, everyone. Joining me is our Chief Operating Officer, Simon Jessop, and Ryan Gurner, our Chief Financial Officer. I'm happy to report that the December quarter came in strong, putting Northern Star where we planned to be for growth in both production and cash flows during the second half of FY 2024. During the quarter, every one of our production centers delivered great progress toward our profitable growth strategy, and Simon and Ryan will walk you through several highlights shortly. Gold sales totaled 412,000 ounces at an all-in-sustaining cost of A$1,824 per ounce, which produced underlying free cash flow above A$100 million. Our full-year guidance stays unchanged for costs as well: 1.6 to 1.75 million ounces at an all-in-sustaining cost of A$1,730 to A$1,790 an ounce, and we see a strong H2 ahead as we sell gold into a very healthy price environment, currently above A$3,000 an ounce. Financially, we remain resilient with a net cash position of A$238 million, strong liquidity of A$2.5 billion, and robust cash flows that fund all of our growth investments, exploration activities, and dividends. On the KCGM mill expansion, enabling works have moved forward and the early stages of construction began ahead of schedule. Seeing this activity underway at Fimiston is exciting, and it leads the 3-year build that will double plant throughput to 27 million tonnes per annum and lift production to 900,000 ounces per annum by FY 2029, establishing KCGM as a top five global gold mine.
Stuart Tonkin
executiveLast week the Kalgoorlie team dealt with days above 40 degrees, made worse by state-grid power outages affecting homes and businesses in the city, and Northern Star is lucky to own and run the Parkeston Power Station together with TransAlta, which has been essential for keeping operational disruption to a minimum and helping meet the city's power needs while repairs are carried out. By contrast, the Pogo team is facing minus 40-degree days in Alaska, yet has kept up strong momentum on operational improvements, with quarterly gold sales of 66,000 ounces and all-in sustaining costs of US$1,367 an ounce. At Pogo, stoping dilution continues to affect mine grade slightly, partly offset by higher mill throughput, which ran at an annualized rate of 1.4 million tonnes per annum during the quarter. Mine operating cash flow from Pogo keeps getting stronger, with US$40 million produced in the quarter, which is very pleasing to see. Simon will now talk about the Australian operations.
Simon Jessop
executiveThanks, Stuart. Turning to the Kalgoorlie production center — that includes KCGM, Carosue Dam, Kanowna Belle and South Kalgoorlie — we sold 220,000 ounces of gold, which was up 20%, at an Australian all-in-sustaining cost of A$1,683 an ounce, down 9%. From that production we generated mine operating cash flow of A$288 million, up 65% quarter-on-quarter. The region also invested $200 million in significant growth capital projects, among them A$72 million for the KCGM mill expansion and $65 million for KCGM open pit mine development and new tailings storage facilities. At the KCGM open pit, material movement matched plan at 18.3 million tonnes for the quarter, and total movement for H1 reached 40 million tonnes, in line with the total material movement goals we stated. The open pit carried on successfully mining the East Wall remediation area to regain partial access to Golden Pike North, with 25,000 ounces mined in quarter 2 and slightly ahead of schedule. That partial access to Golden Pike North is a genuine highlight as we keep accelerating toward unlocking the 1.2 million ounces. Underground mining volumes across the Kalgoorlie region held steady at 1.54 million tonnes, while grade rose 13% to deliver 128,000 ounces. The stronger grade came from Mt Charlotte and Carosue Dam, as we regained access to higher grade areas of the mine.
Simon Jessop
executiveFor the quarter, development at KCGM's underground Mt Charlotte operations was held steady at 3.3 kilometers, following a 52% increase in quarter 1. That figure is an important leading indicator for unlocking new mining fronts, since rising production will come from additional stope areas being brought online. All of the underground mines at Carosue Dam turned in solid results, which allowed the underground ore mine to provide more than 60% of mill feed for the half. Open pit movements rose to 1 million BCMs as we kicked off the new Wallbrook open pit. At the Kalgoorlie operations, mined volumes were lower at Kanowna Belle, where a major production blast was finished late in December, while the South Kalgoorlie ore mine held steady, though average grade climbed to 5.4 grams across a total of 24,000 ounces. Processing volumes at the Kalgoorlie production center were up 11% after the quarter 1 major shutdowns, reaching 4.85 million tonnes. Recovered gold at KCGM rose 36% quarter-on-quarter to 124,000 ounces, driven by processing volumes, grade and first access to high grade ore from Golden Pike North. Carosue Dam milled 1 million tonnes for the quarter, alongside higher head grade and gold sold. The KCGM mill expansion saw A$72 million spent during the quarter, and on-ground enabling works carried on successfully. Substantial earthworks are now underway in the crusher <<inaudible>> stockpile area, along with clearing of the new mill footprint.
Simon Jessop
executiveWe also completed substantial work on the 33kV power line serving the northern switcher. Engineering design work is moving along nicely, sitting at 20% complete, and it remains on schedule. Our attention stays fixed on the enabling works so the mine construction team can get started late in the March quarter. At our Yandal production center, which takes in Jundee, Thunderbox and Bronzewing, we sold 125,000 ounces of gold at an Australian all-in-sustaining cost of $1,923 an ounce. That production generated mine operating cash flow of A$125 million, and we invested A$61 million in growth capital projects, with A$22 million of that going mainly to the Orelia open pit. At our Jundee operation, development advance held steady at 7.5 kilometers, with 760,000 tonnes of ore mined and 80,000 ounces for the quarter. Processing suffered an unplanned SAG mill trunnion bearing failure, which cost us 10 days of lost mill availability. We finished December with that fixed and with an annualized 3.2 million tonne per annum mill throughput, as the issues were resolved midway through the quarter. The Jundee renewable project moved forward, with all panels laid out for the 16 megawatt solar farm and wiring work now underway. Foundation works for the 24 megawatt wind farm have begun, steel is complete in two of the four foundations, and it remains on track for FY 2025.
Simon Jessop
executiveOver at Thunderbox, our underground operation produced 498,000 tonnes of ore mined, with head grade coming in a bit higher at 1.7 grams per tonne. During the quarter we also kicked off mining at our newest underground mine at Wonder, where the portals are in place and a substantial amount of infrastructure is already set up. Northern Star Mining Services put in those portals, reaching 74 meters of development before Christmas, and we're eager for the higher-grade ore this mine will deliver down the road. For the quarter, combined underground and open pit operations mined 1.35 million tonnes of ore, which lined up with the tonnes milled at the Thunderbox process plant. The Thunderbox process plant milled 1.29 million tonnes for the quarter and sold 51,000 ounces of gold. Throughput per hour stayed above nameplate, averaging 759 tonnes per hour. Availability came in at 77% for the quarter, with the biggest impacts being damage to the main feed mill conveyor and low crushing circuit availability, which in the end affected the feed rate on the mills. Our focus is on availability while repairing wear points and making engineering improvements for operability. The ongoing opportunity is to lift availability above 90% and mill more than 6 million tonnes per hour. At this point I'd like to hand things over to Ryan, our Chief Financial Officer, to go through the financials.
Ryan Gurner
executiveThank you, Simon, and good morning, everyone. The quarterly results we released today show that Northern Star continues to be in an excellent financial position. Our balance sheet is still solid, as shown in table 4 on Page 9, with cash and bullion of A$1.1 billion, and at December 31 we remain in a net cash position of A$238 million. For the first half of FY 2024, the company has posted strong cash earnings, estimated at between A$685 million and A$715 million, and as a reminder, our dividend policy is set at 20% to 30% of cash earnings. On a pleasing note, all three production centers delivered positive free cash flow, with capital expenditure fully funded. Figure 9 on Page 10 shows how the company's cash and bullion investments moved during the quarter; the key elements are that the company recorded A$486 million of operating cash flow, a 22% increase on the prior quarter, and this figure includes a A$28 million coupon payment on the notes as well as A$25 million of our annual insurance premiums. Then, after deducting CapEx of A$315 million related to plant and equipment and mine development, A$28 million of exploration and A$41 million of lease payments, free cash flow generation for the quarter came in at a healthy A$102 million.
Ryan Gurner
executiveSpending on sustaining capital, growth capital, and exploration during the quarter is tracking to plan. Within growth capital, we have waste removal at KCGM at Fim South and the East Wall, development at Fim Underground, the KCGM plant expansion, development at Porphyry Underground and the Wallbrook open pit at CDO, plus development at the Orelia open pit and Wonder underground at Thunderbox. Also in the quarter, the company paid its final FY 2023 dividend of A$0.155 per share, which totaled A$165 million. As for the company's on-market share buyback, that program remains open and stands at 56% complete. A blackout period is in effect through and including the release of our first half FY 2024 results on the 22nd of February. Turning to other financial matters, depreciation and amortization align with the company guidance we provided of 650 to 750 an ounce. First half FY 2024 depreciation sits at the midpoint of that guidance range, at roughly $691 per ounce sold, and for the quarter non-cash inventory charges for the group came to $33 million. Most of these non-cash charges relate to the milling of acquired stockpiles at KCGM and form a component of EBITDA. During the quarter, the company refinanced its revolving credit facilities, pushing maturity dates out to December 27 and December 28 across two equal tranches totaling A$1.5 billion.
Ryan Gurner
executiveSince those facilities stayed undrawn and were available as of quarter-end, the company still holds $2.6 billion in liquidity. On hedging, Table 5 on Page 10 lays out the committed hedge position as of December 31. Over the quarter, 100,000 ounces were delivered by the company into contracts, and 285,000 ounces were placed at an average price of A$3,450 an ounce. The hedge book overall stands at 1.8 million ounces at an average price of A$3,028 per ounce. I'll now return things to Lexie for the Q&A session. Thanks.
Operator
operatorThanks. <<operator_script>> Hugo Nicolaci of Goldman Sachs has the first question. Go right ahead.
Hugo Nicolaci
analystMorning, everyone. Appreciate the update today. Perhaps one further point regarding the medium- and longer-term outlook — it keeps tying back to what was said at the November exploration update. Broadly speaking, I believe the KCGM picture is fairly well grasped, yet the way some of the other assets are perceived over the medium term is likely still somewhat short of where it should be. So I'm curious whether you could kindly walk us through in somewhat greater detail what you presently anticipate the capital commitments will be for items such as the continuing development at Pogo, the satellite pits at Jundee and Thunderbox, and the wider sustaining CapEx profile over the medium to long term. Thank you.
Stuart Tonkin
executiveThanks, Hugo. So, yes—regarding the outlook you mentioned, whether it relates to capital compliance versus the capital guidance figure, or to greater production certainty or exploration, what does it come to around the CapEx conference?
Hugo Nicolaci
analystYes, I’d like to hear more about CapEx, but beyond that, whatever you can share on the physical side — something covering the medium term rather than just reserve grade and that kind of thing — would be great too.
Stuart Tonkin
executiveOkay, absolutely. So look, the main thing that's changing at Pogo is essentially about the grade — and boosting the stoping grade while reducing mining dilution. The ratio of stoping to development came down a bit this quarter, but ultimately it comes down to getting higher-quality tonnes through that plant so we can hit 300,000 ounces. So raising that average grade is how we're going to achieve that revenue uplift. You can see costs are improving, but Pogo still carries a lot of fixed cost. So the improvement there comes mainly from a combination of better grade driven by mining dilution improvements plus some added throughput — we milled 1.4 million tonnes. There are a few other small plant capital items that will be in place to stabilize and maintain an increased milling throughput. So that's Pogo settled. The other growth basically comes from stabilizing the availability of the Thunderbox plant. So we've managed to meet that milling rate fairly consistently, but not for the whole quarter. So it's about getting that available time up, keeping that average grade through there and basically holding that 6 million tonne per annum rate consistently across the quarter. We think we'll be at the exit rate in quarter 4 at that 6 million tonne.
Stuart Tonkin
executiveIt's coming a little later in the year than we'd have liked. But really it comes down to achieving that mechanical uptime. So a handful of those modest capital items are being upgraded at that plant. The remainder is genuinely driven by the volumes of grade coming out of KCGM, as you noted, since we're now in Golden Pike North at the pit floor. We will still have 6 months of waste material movement at East Wall, yet we are into the grade up north at the pit floor, which took 3 years to reach, and that is a fantastic result, ahead of where we thought we'd be. So those are the three main drivers of inflex. We'll be releasing a resource reserves statement. We finalise them at the end of March, so there will be plenty of detailed content underlying the life-of-asset plan and the guidance on grade. But apart from those three key moving parts, everything else stays pretty static for the rest of this year and next year.
Hugo Nicolaci
analystThanks for that background. Picking up perhaps past the latter portion of 2024, how much do you expect to need to invest, for instance, during FY 2025 and 2026, on fresh satellite pits at Thunderbox and Jundee? And what ongoing development CapEx each year are you roughly forecasting on the order of A$50 million annually on top of sustaining CapEx for plants and similar items, or how do you see that medium-term CapEx profile taking shape?
Stuart Tonkin
executiveRight. So in that respect, we haven't provided multiyear growth capital expenditure, and we'll look at whether to do so around midyear. What it really amounts to is delivering this year's capital, and most of it is going into KCGM — obviously into the waste stripping movement, but also into the mill expansion. So a proportionate share of the capital is directed there. Across the Yandal, we have a fairly steady pattern of starting one new mine each year, whether that's an underground or an open pit, and we're managing that with our own fleets. So in the end you're spending the same amount each year, because you're reallocating your people and your fleet to those jobs. So it isn't a matter of stacking them one on top of another; it's simply a sequence through those underground mines and open pit mines. So there's fairly consistent spending around opening up those growth ideas, and that pipeline of targets, or pipeline of ore sources, will come through in the resource reserve statement in a few months.
Hugo Nicolaci
analystThank you. Okay, one final item, apologies — let’s return to the CapEx topic. When you consider sustaining CapEx over the longer term, do you view it as A$1 per ounce, and once your growth projects have settled down, what figure do you expect sustaining CapEx to reach? In other words, will sustaining CapEx exceed A$200 an ounce?
Ryan Gurner
executiveYeah, Hugo, it's Ryan here. Yeah, I think that if you take a look back through the history, the trend for this business has sat at roughly A$200 to A$250 per ounce, and I think we've moved along those lines for a great many years, and even in this year, if you look at the half-year results, I think we're a touch above A$200, at about A$210. So, yeah, that's the figure I'd guide to.
Hugo Nicolaci
analystI appreciate that, and I'll make sure the team hears about it.
Operator
operatorMuch appreciated. Our following question is from Daniel Morgan at Barrenjoey. You have the floor.
Dan Morgan
analystHello, Stuart and the team. My first question concerns the super pit, and I'm simply asking what led to getting into Golden Pike sooner, and whether that means you might be a bit ahead of schedule and we could see improved grade during this year's second half? Or is it only that you managed a few days at the close of the quarter, so it landed in this quarter rather than the next one? Thank you.
Simon Jessop
executiveYes. Thank you, Daniel. This is Simon. I guess following 3.5 years of effort, it’s genuinely strong execution from the team to remain on track and on the path, and basically through solid mining plus thoughtful and technical work, we’ve regained partial access to a portion of the southern side of Golden Pike North and also recovered a small amount of access at the northern end. So I think really the bulk of it is simply good mining, good focus, and the teams truly delivered there. So we accessed that a bit early. The grade in the second half, absolutely, KCGM will climb. And you can kind of see that timing gap between the gold recovered and the gold sold of 112,000 ounces. We had a significant buildup in gold in circuit there. And that was really about getting access to some of that Golden Pike North late in the quarter. And KCGM, it really takes roughly 3 weeks for the gold to move through the entire circuit. So a bit of a timing element there. So a large buildup in GIC at the end of the quarter. But we’ll keep gaining access into Golden Pike North going forward. So some truly excellent work from the team.
Dan Morgan
analystYeah, a lot got done there—sorry, that part was inaudible. Just to clarify, you've got partial access back now. And obviously, my understanding is that you're planning for full access to be restored around the middle of this year, by the end of June. Can I just confirm that at the bottom of the pit you'll have complete access and, for all practical purposes, won't face any restrictions—or is there still work remaining that will carry into FY 2025?
Simon Jessop
executiveYes, that’s spot on. All of the East Wall work should be wrapped up by the close of FY 2024 — that is, June of this year. So we’ll then have unrestricted access to Golden Pike North throughout FY 2025 and FY 2026. And clearly, that matters a great deal for our strategic plan to lift KCGM to 650,000 ounces.
Dan Morgan
analystThanks. This is more of a sector-level question — unfortunately, your nickel peers are going through a tough stretch with weak prices. There have been a handful of shutdowns, and possibly more in WA. I'm just curious what that might mean, if anything, for your operations when it comes to securing people, contractors, and equipment. Are there any indications of that yet? And could we perhaps see some easing of the cost inflation that's been affecting your business? Thank you.
Stuart Tonkin
executiveYes. Thank you, Dan. So an initial step we took was making contact throughout those operations. We recognized that as we move toward care and maintenance or cut back on personnel, there are open positions group-wide that we can fill. We've therefore extended that invitation to bring those people aboard. Fundamentally, I don't view this as a cost reduction. It's about retaining those roles within the regions, keeping those individuals working, and filling gaps, and as we expand, it will definitely support execution of our business and, once more, the caliber of skilled staff brought back into work.
Dan Morgan
analystAlright, thanks so much.
Operator
operatorThanks. We’ll take our next question from Hayden Bairstow at Argonaut. Hayden, please go ahead.
Hayden Bairstow
analystMorning, everyone. I have a couple of questions. First, some remarks about the reserve and resource update. I’d find it useful to know whether there will be any kind of change in the way you’re approaching things, especially Kalgoorlie, given how much has already been committed as the mill expansion is sort of under way, as opposed to Carosue Dam as a separate operating centre, and likewise with KB, and steering more of those resources toward the mill over the longer term. Are you considering that, or is it still a couple of years off?
Stuart Tonkin
executiveOkay, so we have clearly updated everything concerning our cost-based cutoff grades and, of course, the revenue figures and gold price assumptions. We might adjust the gold price a bit, since there is considerable progress from the sub-$2,000 level previously used compared with spot prices above $3,000, but it more likely comes down to drill density at a site such as KCGM—things like the confidence level of measured, indicated, inferred, and so on, from resource through to conversion into reserve. So it is not especially sensitive to cutoff grades or gold price assumptions. What really matters is achieving the definition density, correct. So right now we simply see enormous opportunities to come in later. We know there is material within the pit-shell that is economic and highly profitable through that expanded mill and the reduced milling cost. That will not be included in this resource reserve statement. We obviously still have 2.5 years of construction on that part before it would be incorporated into the statement.
Hayden Bairstow
analystAlright. Then regarding the hedge profile — a decision was made to add A$195,000 ounces to the book. I mean, should we be thinking about that, and could it grow larger over time, opportunistically? Just to understand what that was about?
Stuart Tonkin
executiveNo, it really does align with that policy, keeping us at roughly that 20%-odd average, and as you know, we’re growing our ounce profile. So it comes down to that 4-year outlook and holding at that level. Opportunistic when the price is up, so those were added over A$3,400 an ounce, and it basically keeps that percentage flat across that period. So just as we deliver into those hedges, opportunistically adding to that book, using that contango to get the price up. Average book price is above A$3,000 an ounce. And if you took a spot out of the money, it’s under A$100 million, which is what we’re generating cash flow on the quarter, it’s pretty cheap insurance.
Hayden Bairstow
analystYes. All right. Excellent outcome. Appreciate it, everyone.
Stuart Tonkin
executiveAppreciate that, Hayden.
Operator
operatorThanks. Our following question is from Ben Lyons at Jarden Securities Limited. You have the floor.
Ben Lyons
analystMorning, everyone. Nice work, Stuart — clearly a strong quarter. Perhaps, given such a solid result, I'll focus on one of the softer figures, but I wanted to spend a moment on the physicals at Jundee. The grade reported there came in at the lowest level in more than 5 years, and of course I understand there will always be some natural tension between pursuing tonnage and holding the grade profile. I'm just wondering whether you could offer any comments on what you expect for that grade profile going forward. Thanks, Stuart.
Stuart Tonkin
executiveYes, thanks, Ben. I'll hand it over to Simon and congratulate him on a great quarter as well, since he did all the work. But it concerns the sequencing of open pit and underground contribution, along with some mill outages while just utilizing some low grade stockpiles. So, yes, Jundee is particularly lumpy when it comes to sources and feeds. So it concerns maintaining and getting back to those reserve grades. Simon, just let me give you the color of the forward look.
Simon Jessop
executiveYeah, Ben, thanks. Jundee’s grade came in lower, but part of that is a mix of Ramone material at a reduced grade as a share of the total blend at Jundee, plus we saw some stronger grade arrive late in the quarter. So it’s really about the timing of the mine sequence at Jundee. Grade does swing around quite a lot, but on average we’re getting a bigger contribution from Ramone at a somewhat lower grade — though it isn’t far off the reserve grade of 3.6 per ounce per tonne for Jundee.
Ben Lyons
analystYeah, cool. Thanks for that, Simon. Then on the second one, shifting over to Thunderbox, it's good to hear you're opening up the Wonder underground. I was just wondering if you could possibly remind me what kind of rough throughput and grades you're aiming to achieve from that new underground operation. Thank you.
Simon Jessop
executiveAbsolutely — we’re very, very enthusiastic about finishing the portals and getting that set up right at the end of the quarter, and starting with this quarter we’ll be increasing activity at Wonder underground. The first reserve estimate for Wonder came in at roughly 455,000 ounces, with a grade of about 3.2 grams per tonne. If you set that beside Thunderbox underground, which is at approximately 1.7 to 1.8 grams per tonne, it’s a notably high-grade source for us, and we also see substantial room to drill and keep expanding it. So we’re quite excited to complete that project in the right way. Naturally, there is some lead time involved in development, as there is for a typical underground operation that begins to ramp up, but those are the initial figures based on last year’s iron ore <<inaudible>>.
Ben Lyons
analystYeah, cool. Thanks, Simon. Just off the top of your head, were you thinking about that 1 million tonne per annum dedicated underground, or more like 500,000 or 600,000 tonnes per annum at this point?
Simon Jessop
executiveI guess it partly hinges on when we actually open up those various zones, but I'd say pushing toward roughly 1 million tonnes per annum is quite a sensible expectation for that operation. So definitely comfortably above 500, no question about that.
Stuart Tonkin
executiveYes, when the iron ore output or the stoping ore are combined, that figure would be close to that million — it really just comes down to how they’re blended together.
Ben Lyons
analystAlright, I'm finished. Nice work, everyone. Thanks.
Stuart Tonkin
executiveAppreciate it, Ben.
Operator
operatorThanks. We'll take the next question from Alex Barkley at RBC. Go right ahead.
Alex Barkley
analystThank you. Morning, Stuart and everyone. I'd like to focus a little more closely on Pogo and those grades. This quarter did appear somewhat weak, and you indicated that for the second half you anticipate only a slight improvement. I'm not sure whether you could offer further detail regarding that increasing share of stope ore, and you noted that dilution could be a problem. So at what point should we expect this mine to move up toward reserve grade, and is that genuinely attainable? Thanks.
Stuart Tonkin
executiveOkay, so when you look at the physicals on a quarterly basis, we're holding roughly above 1,600 meters per month in development, and when that's breaking out a wall, essentially that material heads to the plant ahead of stoping. That then translates into greater stope tonnes down the road, but it comes down to balancing the total number of people against the total fleet hauling material. So whenever we exceed targets on development, it does eat somewhat into stoping, yet it gives us additional working faces and the capacity to ramp up later. That's the reason we have that visibility and confidence — when we were roughly at 1,200, 1,300 meters per month, we were not only drawing down stockpiles, we weren't moving ahead. So it's encouraging to see those leading indicators sitting there. And the grade reflects that elevated share of development, or development going into the feed, as well. Mining dilution differs across the various zones and areas and ground conditions in the mine. So it's about us grasping that, rather than applying a single pattern to each of those areas, and the technical teams fine-tuning those things. So, yes, we've witnessed gains across the year, though a particular area will still cause us some trouble.
Stuart Tonkin
executiveThe focus is really on separating that out, adjusting it, and then carrying forward. So all of those items are things we're actively addressing. On reserve grade, at 8.5 grams, we'll once more evaluate it through all the drilling and the level of confidence in what we're seeing across each of those zones, along with what the mining factors turn out to be, and come March we'll revisit what the reserves come back with — whether it holds at 8.5 grams or returns with mining factors applied. That work is still underway at present.
Alex Barkley
analystOkay. Got it. That's quite clear. Thank you. And just a quick question. Have the recent power problems in Kalgoorlie caused any trouble for you folks?
Stuart Tonkin
executiveWell, the past couple of weeks have been absolutely terrible for Kalgoorlie and Boulder. We think it'll be permanently sorted out very soon, within the next few days or so. But yes, there was plenty of drama up there, with power obviously out for 30,000 residents and businesses. We're lucky to have the Parkeston Power Station, which can serve the city and, of course, serve our mines. So we've gotten through those events over the last couple of weeks. We're kind of the state enterprises in that regard. So yes, there have certainly been disruptions throughout the goldfields. It hasn't materially affected us, but we've also worked hard to support the community, even providing backup gensets and power and redistribution of our power. So we act under the instruction of those energy companies when it comes to using Parkeston to feed and supplement power into the city.
Alex Barkley
analystAlright. That works for me. Many thanks, everyone.
Stuart Tonkin
executiveAppreciate that, Alex.
Operator
operatorThanks. We’ll take our next question from Alex Papaioanou at Citi. Go ahead, please.
Alex Papaioanou
analystHello, Stuart and Simon. I’ve just got a single question. At KCGM, when should we expect recoveries to return toward 84%?
Stuart Tonkin
executiveAppreciate that, Alex.
Simon Jessop
executiveYeah, thanks, Alex. It's Simon here. Yes, we ran into quite a few problems in the flotation area, and that's been dragging our recovery down a bit below what we'd normally see. So we just had a shutdown not long ago and did quite a bit of work on the rough <<inaudible>> columns, and really it comes down to how the material is distributed going in there versus skipping some of it and sending that to the CIL train. So that's really where the main impact sits. We've got a handle on it. We're putting in a lot of effort on the float to try to improve the optimization there. And honestly, that's the biggest challenge we're facing on recovery in this case as well.
Stuart Tonkin
executiveTo reach those kinds of figures, our mindset centers on the fully expanded mill scenario, which clearly involves a different circuit and is really what we're aiming at. So with the significantly larger ounce profile and the residence time, it comes down to having all the ultrafine grinding located at the same site rather than sending material out to Figi <<inaudible>>, plus plenty of residence time across multiple tanks added to that higher-throughput circuit, and stabilizing every one of those float banks feeding into it. So as Simon mentioned, we're concentrating on what we have over the coming couple of years, but the truly major shifts really lie in the new circuit and in ensuring that it delivers the best recovery we can achieve.
Simon Jessop
executiveYeah, the residence time is kind of moving from our usual 8 to 10 hours out to not just 16 hours on the new circuit. So that's a pretty big difference in the new design of the expanded process plan. So we get the volume increase. We also double the residence time.
Alex Papaioanou
analystAlright, that's all I had. Appreciate it.
Stuart Tonkin
executiveAppreciate that, Alex.
Operator
operatorThanks. The following question is from Matthew Frydman at MST Financial. Go ahead, please.
Matthew Frydman
analystAbsolutely. Thank you, and good morning to Stuart and the team. I’m sorry if this was covered before the Q&A began, but I’d like you to elaborate a bit, please, on the difficulties you’re encountering at Thunderbox. Clearly, there are some continuing pressure points and challenges that your team is dealing with and addressing at the mill there. How do you — I suppose, what is the route to correcting that during the second half? In your view, will that bring you back to the 6 million tonne per annum nameplate capacity? Or do you need to begin reassessing that? And then, perhaps also building on a few of the remarks made in the previous question, are there any lessons from that expansion and how it was implemented that you can apply to what you’re carrying out at KCGM? Thanks.
Simon Jessop
executiveOkay, thanks Matt. This is Simon. I guess, on either the first or last part of what you asked, regarding what we’ve learned for KCGM — those two are hugely different when it comes to the thinking methodology and every element of the KCGM plant. So we’ve genuinely put in a tremendous amount of effort alongside Steve and the team on how operable the new KCGM plant will be, and we’ve done a great deal on design reviews to ensure it emerges from construction in a very, very robust state. So yes, we have definitely examined some lessons internally from the Thunderbox process plant, but the two really are like chalk and cheese. As for Thunderbox itself, there was actually a significant conveyor failure with the belt, which was a reasonably large task to repair over the quarter. But there are plenty of small items here and there — wear points in the SAG feed chute design and that kind of thing — which need a few iterations before they’re developed and in place. And so we’ve kind of had to live with this reduced availability while we work through them. So we’re addressing the near-term issues right now, along with medium-term improvements, and then longer-term as we get a handle on where it sits regarding the process plant.
Simon Jessop
executiveSo if you annualize the H1 results, we're at about 5.3 million tonnes, and that's with availability running between 77% and 80%. Every one of our other process plants operates well above 90%. Getting there doesn't look like a problem at all to us. It's simply a matter of raising that availability by 10% to 13%, and then we're past A$6 million. So we're close. It is a bit frustrating. It's taking somewhat longer than we thought, but we have the right people fully on it now.
Matthew Frydman
analystRight, that's logical. Thanks, Simon — I appreciate it. Of course, KCGM and Thunderbox are quite different plants. I suppose the confidence about getting back above 6 million tons per annum clearly also takes into account, I guess, the growing share of fresh ore entering that mill. Obviously, you mentioned the development of Wonder underground and others that are kind of boosting that fresh feed. So 6 million with a larger proportion of fresh is still very achievable.
Stuart Tonkin
executiveYeah, it’s really all just excellent streaming. So whatever material doesn’t meet that standard is currently the lowest grade. That’s why we’re putting the better grade in first right now, but we’ll maintain a fairly steady blend of that in FY 2025 and beyond. And there’s room for that to return above 90% of our capability to exceed 6 million tonnes per annum. So we’re not counting those chickens yet, but we’re definitely working toward what we’ve achieved at every other part — once we’ve brought it to nameplate, it’s about optimizing from there.
Matthew Frydman
analystUnderstood, and thank you, Stuart — and thank you as well, Simon.
Operator
operatorThanks. The following question is from Levi Spry at UBS. Go ahead.
Levi Spry
analystHello, everyone. Appreciate the added detail. Perhaps focusing on the main value driver behind the KCGM Super Pit plant expansion — Figure 5, I believe — could you walk us through the trajectory over the coming 18 months? What activities come next? And, I suppose, how does the remaining CapEx profile look for the second half and on into next year? Thank you.
Stuart Tonkin
executiveYes, that figure stands at A$1.5 billion. Appreciate it, Levi. The count is essentially 3,033, though roughly 500 <<inaudible>> remain outstanding in year four. On that point, Figure 5 really illustrates that the bulk of activity so far has consisted of pre-works plus clearing the site and preparing it for construction crews. We've also begun a modest amount of that construction activity, as seen this quarter. So yes, we're happy with where things stand. Regarding timing and how we're tracking against it, we'll keep this graphic and the accompanying commentary refreshed every quarter. We'll walk through the milestones taking place there, and clearly we've kept production separate from this expansion work so the mine stays uninterrupted — milling, mining and operations carry on right through the build period. And clearly, operational cash flows fully cover the funding for this. Then this sits under distinct leadership and distinct supervision, with a contractor handling all of this activity in and around the plant that's currently running. So yes, it's a tightly managed operation with plenty happening — clearly all the accommodation, and crews beginning to arrive in greater numbers during this March quarter. And then really you'll have 500, 600 people on site for a couple of years carrying out fairly substantial construction works.
Stuart Tonkin
executiveWe’ll keep that updated in CapEx, and it stays pretty steady across those years. Checks written versus commitments made could be a little lumpy, but overall it’s fairly consistent. It’s going to get built.
Levi Spry
analystYes, excellent. Nice work. I appreciate it. Much appreciated.
Stuart Tonkin
executiveAppreciate that, Levi.
Operator
operatorThank you. <<operator_script>> Our following question is from Jared Brian Lucas with ABC News <<inaudible>>. You may proceed.
Analyst
analystMorning, and thanks for using my full name there at the start. Stuart, early in the call you brought up Parkeston Power Station and the part it's currently playing in keeping Kalgoorlie's lights on. I was just wondering whether western powers have told you how much longer it will be counted on to feed the grid more heavily than usual.
Stuart Tonkin
executiveYeah, thanks, Jared. Oh, look, we have guidance saying it's just days away, and that's the permanent fix. So we expect that work has obviously carried on since the first outage, and those poles got damaged during that storm. So, like you, you hear plenty of different accounts of what was done at the start of this period. I believe they've worked through a lot of those and I understand they have several efforts in progress. So, most of that disruption people went through will be fixed very soon.
Analyst
analystAll right, it's clear the state government utilities have had to depend on you folks, and they're fortunate that you were available. I suppose you'd prefer to see somewhat more strategic investment perhaps coming from the state toward the power infrastructure, so that they aren't forced to count on you?
Stuart Tonkin
executivePutting that aside, it's fairly widely recognized that the Parkeston facility has long been the backbone of power supply in Kalgoorlie. That much is obvious. What matters more, I think, is how quickly you can respond and whether you have several backup plans in place. Nobody is able to forecast which portion of that network might go down. Sure, you could pour substantial funds into contingencies and that kind of thing, but I think the real issue is that when a storm or some other event happens, what counts is the pace and the readiness to move fast so that residents aren't left without service — and we recognize the disruption that has taken place throughout that community. Those have been some very hot weeks there.
Analyst
analystThe final question concerns the renewable power plan involving solar arrays and wind turbines, which has been discussed for some time. Do you have any update on where that planning currently stands?
Stuart Tonkin
executiveThis remains a multi-year effort, and the expectation is that it comes online once the mill expansion is complete. Had it been available now, it very likely would have addressed the problems we faced over the past fortnight, but it will serve as an additional asset. It is something that supports continuity and power security across the region. So there are considerable advantages to having it either behind the meter or tied to the grid — renewable, cutting our carbon footprint at that site, while delivering absolute power security for many businesses' homes and, clearly, for the operation we run in Kalgoorlie.
Analyst
analystThanks, guys. I just want to make something clear before I move on: that figure comes after the 3-year mill projects, which remain at the feasibility stage.
Stuart Tonkin
executiveYes, we’re still looking at several possibilities when it comes to wind-solar battery with respect to that.
Analyst
analystAppreciate it, everyone. Thanks a lot.
Stuart Tonkin
executiveAppreciate it, Jared.
Operator
operatorThank you. That brings us to the end of the question-and-answer session, and I now return the floor to Mr. Tonkin for his closing comments.
Stuart Tonkin
executiveAlright. And thank you all for being with us on today's call. We're very happy with the quarterly results at mid-year, and we look forward to bringing you updates as we keep moving forward with our strategy of profitable organic growth. So have a great day. Many thanks.
Operator
operatorThanks. That brings today's conference to a close. We appreciate everyone joining us. You're free to disconnect at this time.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Northern Star Resources Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Northern Star Resources Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Northern Star Resources Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.