Oklo Inc. (OKLO) Earnings Call Transcript & Summary
March 17, 2026
Earnings Call Speaker Segments
Sam Doane
executiveGood afternoon, everyone, and thanks for being here for Oklo's update covering Q4 and the entire 2025 fiscal year. This is Sam Doane speaking, and I serve as Senior Director of Investor Relations at Oklo. With me on the call today are Jake DeWitte, who is our Co-founder and Chief Executive Officer, along with Craig Bealmear, our Chief Financial Officer. Once I finish these opening comments and we get through the forward-looking statement disclosure, Jake is going to take everyone through the business update and strategic progress, and then Craig will present our financial results. Today's remarks contain forward-looking statements, and those come with risks and uncertainties that might lead actual results to differ materially from what we discuss on this call. We'd encourage everyone to look over the forward-looking statements disclosure that's included in our supplemental slides. You can also find additional details about relevant risk factors described in our filings with the SEC. We're not undertaking any obligation to update forward-looking statements unless the law requires us to do so; with that said, I'll hand things over to Jake. Jake?
Jacob DeWitte
executiveAppreciate that, Sam. For Oklo, 2025 represented a year of step-change. Across every one of our business units, we moved out of product development and into active project deployment. Over the course of that year, we broke ground at Idaho National Laboratory on our inaugural Aurora powerhouse, working under the DOE's Reactor Pilot Program. We also pushed forward key commercial partnerships throughout the value chain — among them our early 2026 prepayment agreement with Meta, which backs plans for a 1.2-gigawatt power campus — and kicked off initial construction activities on A3F at INL. Beyond that, we closed our acquisition of Atomic Alchemy and achieved substantial construction progress at Groves in Texas, which is our first radioisotope test reactor. When it comes to fuel, we wrapped up fast-spectrum plutonium criticality tests that back plutonium's role as a bridge fuel. In Tennessee, we introduced the first phase of our advanced fuel center, and we pushed licensing efforts ahead on several assets. Taken together, this shows that 2025 was the year Oklo turned its platform strategy into projects on the ground, while also strengthening the balance sheet to support that delivery and our longer-term expansion. Before I go deeper into execution, it's equally important to recognize just how much the outside landscape has shifted over the last 2 years. During 2024 and 2025, U.S. nuclear policy became more focused on execution, covering licensing, asset deployment, fuel supply, and capital formation. These are the four core pillars, as you can see here. First off, government mandates and agency rulemaking that focus on accelerating approvals and enabling maiden deployments. Second, programs backed by the federal government — including credits against taxes owed, promises to guarantee loans, and vehicles for direct funding — are smoothing the route to securing capital for projects. Third, efforts aimed at fuel independence are spurring homegrown capacity across conversion, enrichment, HALEU, and materials deemed strategic for fuel. Fourth, operationalizing the ADVANCE Act seeks to reduce licensing obstacles and unlock deployment channels that are more efficient. Within the nuclear industry, the policy climate has shifted from a mild boost to an exceptionally powerful one, and Oklo stands ready to operate amid those conditions. Going forward, we'll be talking about Oklo in terms of three business units that work together: power, fuel, and isotopes. Together, these make up a nuclear platform that's unique and vertically integrated. When we say power, we mean the clean baseload electricity and heat produced by our sodium fast reactors, which can run on a wide range of fuels. With fuel, Oklo gains an integrated route to make the fuel our powerhouses need, along with what our peers and competitors need. That lowers deployment risk, bolsters supply over the long term, and opens the door to nuclear energy abundance at scale by recycling fuel. Isotopes take the platform into high-value goods and services that matter strategically for the domestic market, and these arise naturally as co-products of our other business units. Here's the main takeaway: by bringing the whole value chain together, we expect to open up several complementary sources of value down the road. Power comes first. The reason we're standing up the power business unit is that demand keeps climbing fast nationwide for firm, reliable electricity. Whether it's data centers, industrial customers, or government applications, the people we serve require clean, dependable baseload power rather than something intermittent. Our Aurora powerhouses are meant to supply that steady baseload electricity, and the foundation of our commercialization approach rests on long-term offtake agreements. On top of that, power serves as the base that supports every other part of our platform. As we deploy power, it generates demand that lets us scale fuel production and fabrication down the road, and those first deployments give us reference assets that make future campuses more repeatable. Through developing our power delivery capability, we've spotted key chances in other ecosystem areas that we're now focused on building out and scaling up. So power serves as a near-term answer for customers as well as the groundwork for wider platform scalability. Turning to our second business unit, fuel, which ranks among the most strategically vital pieces of what we're constructing. One of the biggest things holding back new nuclear deployment continues to be whether fuel is available. Since the very beginning, we've been developing fuel capabilities to back our own deployment plus the broader deployment of advanced nuclear. For us, that begins with fabrication. Through fuel fabrication, raw material gets turned into forms ready for reactors; that's how we serve Oklo reactors and also open up the possibility of serving third-party reactors later on, whether by fabricating their fuel directly or by hosting their fabrication lines inside our factories. Oklo is additionally looking into developing modern deconversion processes to gain efficiencies, such as the Centrus announcement we made recently; historically this step happened at the fuel fabrication facilities themselves. When we consider where nuclear fuel manufacturing is headed, putting it alongside the enrichment facility makes far more sense. Recycling makes up the other major piece of our fuel approach. Through recycling, uranium can be recovered for reuse, transuranic-bearing material can be recovered and produced for use as fuel in advanced reactors, high-value isotope production can be enabled, and used fuel management solutions can be delivered via recycling pathways. So fuel acts as a near-term enabler of deployment and, over the long haul, a scalable fuel cycle business. Our third business unit is Isotopes. We're building it out for two reasons: there are attractive, high-value end markets in healthcare, industrial, space, and defense, and domestic supply of many isotopes remains strategically limited. Isotopes are essential material for humanity's future — from therapies that save lives, to the long-duration power supplies that have fueled human space exploration, to the future of remote monitoring and sensing for security. We see these isotope opportunities as fitting well alongside our power and fuel business units, since those units can produce isotope co-products that the isotope unit would then package and sell. At the same time, we're working on purpose-built production, using reactors and facilities that are optimized for making isotopes. There's a services revenue opportunity we're looking at in irradiation — it covers advanced nuclear technology research and development, defense research and development, semiconductor doping and hardening, plus other applications. Taken as a whole, isotopes carries the platform into high-value domestic supply for critical uses, and at the same time it improves the economics of the broader business. This slide shows how the three business units connect with one another. If you look at the traditional side of the nuclear business, mining, enrichment, electricity generation, and long-term waste storage are each handled by different players. Our aim is to build a platform that's far more interconnected — one that brings together power production, fuel manufacturing, fuel recycling, and isotope production. Once you're able to turn fuel into forms ready for a reactor and keep recycling material as time goes on, you shift away from a linear fuel cycle and into a loop you can repeat. That gives you better fuel optionality down the road, helps keep supply resilient, and opens the door to extra products throughout the value chain. It also generates fresh revenue streams. Materials you recover can feed radioisotope production, which ties straight into the isotope business we run. What we're after isn't simply putting powerhouses in place. It's creating an integrated platform in which power serves as the anchor product, fuel acts as the enabling system, and isotopes carry the platform into high-value products and services. A strategy like the one we have fits the U.S. in a way no other country can match. For over 30 years, nuclear has supplied approximately 20% of America's electricity, yet the physical volume of used nuclear fuel produced has been quite small. Over 90,000 metric tons of used nuclear fuel from the U.S. would fit on a football field roughly 10 meters tall. People usually talk about that material purely as waste, but the truth is it holds tremendous energy potential. The energy potential in U.S.
Jacob DeWitte
executiveThe amount of used nuclear fuel out there is roughly on par with all the world's major oil reserves combined. That's the reason recycling and reuse carry such strategic weight. Spent nuclear fuel isn't merely a burden we have to handle — it's also a huge possible domestic energy source, provided the infrastructure is in place to return it to service. That brings us to the next slide, covering one of the mechanisms that is now appearing to assist in constructing that wider life cycle infrastructure. The U.S. already possesses a significant strategic energy reserve in used nuclear fuel, yet capturing more of that value as time goes on hinges on creating the infrastructure, capabilities, and coordination required to activate it. That's exactly why the DOE's Nuclear Lifecycle Innovation Campuses matter so much. DOE has described this as an initial move toward possible federal-state partnerships aimed at modernizing the entire nuclear fuel cycle through regional campus models capable of co-locating critical portions of the life cycle. If this model moves forward, it might lower development friction, speed up execution timelines, and enable more efficient investment spanning fuel, recycling power, and isotope-related infrastructure. Just as crucially, treating used nuclear fuel as a resource rather than a liability might shift the power outlook for the U.S. over time, sustaining advanced reactor fuel supply for generations, bolstering domestic radioisotope production, and enhancing long-term used fuel management outcomes. From where we sit, this is significant because it mirrors a more integrated approach to building nuclear infrastructure in the United States, which aligns closely with the strategy we're carrying out across our business units; we remain highly supportive of state responses to the RFI and have begun engaging with multiple states as they assess potential campus proposals. Such efforts lay the groundwork for guaranteeing energy affordability and re-industrializing the nation. Here's where the strategy turns tangible. Across power, fuel, and isotopes, we're already constructing assets that back a more integrated nuclear development model to unlock nuclear energy abundance. On the power side, there's Aurora INL, our inaugural Aurora powerhouse at Idaho National Laboratory, plus Aurora, Ohio, our planned clean energy campus in Pike County linked to our partnership with Meta; on the fuel side, we have A3F at INL, our first fuel fabrication facility, along with our advanced fuel center in Tennessee, representing our first phase of used nuclear fuel recycling infrastructure. In isotopes, we're building Groves, our radioisotope test reactor at the Idaho Radiochemistry Laboratory, which enables isotope processing and scale-up. When we describe ourselves as vertically integrated, this is the meaning behind it. Several real assets are now advancing across all three business units. Since our previous company update, we've achieved meaningful progress in every aspect of the company. When it comes to power, Aurora INL carried out its DOE Other Transaction Agreement through the Reactor Pilot Program, got DOE's approval for the Nuclear Safety Design Agreement, kept construction going, blasting included, and signed a deal with Siemens Energy covering the power conversion system; beyond that, we signed the Meta prepayment agreement backing as much as 1.2 gigawatts at Aurora, Ohio. Turning to fuel, A3F secured DOE approval for both the NSDA and the Preliminary Documented Safety Analysis, and it got picked under the DOE Advanced Nuclear Fuel Line Pilot Program. On recycling, an agreement was signed with TVA to look into fuel recycling, we kicked off site pre-work at our flagship recycling facility, wrapped up NRC pre-application engagement, started a rolling NRC readiness review, and were chosen to receive DOE recycling R&D funding. We additionally finished a fast-spectrum plutonium criticality experiment and unveiled a joint venture initiative with Centrus focused on deconversion; over in isotopes, Groves carried out its DOE OTA, obtained NSDA approval, turned in its PDSA, and pushed construction ahead toward a July 4th criticality target. On a separate note, the Idaho Radiochemistry Laboratory secured its NRC materials license; what you're seeing is execution spanning numerous assets, numerous licensing pathways, and numerous business units, all progressing simultaneously. Aurora INL is moving ahead along a DOE first authorization pathway. The OTA under DOE's Reactor Pilot Program has already been executed by us, and we've obtained approval of the Nuclear Safety Design Agreement; these matter because the OTA formally pulls the project into the DOE authorization pathway, while the NSDA cements the safety and regulatory framework for the project. Coming up on the DOE side are the Preliminary Documented Safety Analysis, the documented safety analysis, and after that the readiness review and startup approval. Every one of those steps gradually brings DOE and Oklo into alignment on the safety basis, from final design and construction all the way through startup and operations. What matters here is that the DOE pathway lets us continue advancing construction, procurement, and system integration activities concurrently as the project proceeds. In parallel with the authorization work, Aurora INL is also making headway on execution and build readiness. On-site development, we wrapped up site characterization at INL. Site preparation is in progress, blasting included, and construction activities are moving forward consistent with the project plan. On procurement and supply chain, responses have come in for most of the identified long-lead component requests for proposal. Supplier down selection is in progress and vendors are now under contract for all major equipment; that covers the Siemens Energy contract for the power conversion system, active supply chain agreements for reactor module components, and active vendor contracts for all major refueling equipment. Aurora INL is advancing on the physical site side as well as the supply chain side, which is exactly what we hope to see at this point in a first deployment; we're picking up plenty of lessons along the way. Up next is Aurora, Ohio, where the headline update is our agreement with Meta supporting a 1.2 gigawatt Aurora campus. The agreement moves phased deployment plans forward, with an initial phase of 150 megawatts targeted around 2030. This is backed by a prepayment arrangement for the power structure, meant to boost project certainty and assist phase one development. A key point: Oklo anticipates deploying money from that prepayment deal to help with fuel procurement. We also hold roughly 206 acres located in Pike County, Ohio, which provides a location for us to push campus development forward alongside commercialization and permitting efforts. That illustrates how customer demand, commercial structure, site control, and fuel planning are beginning to converge around an actual deployment opportunity. One of the main gating items for advanced nuclear deployment is fuel availability. Flexibility, supply optionality, and execution readiness are the deliberate foundations of our fuel strategy. As shown on this slide, we tackle that via strategic enablers, fuel supply pathways, and strategic fuel partnerships. Regarding enablers, our fast reactor technology is engineered to work across a broad variety of fuel sources. And our fabrication capabilities are meant to transform differing feed supplies into reactor-ready fuel. In time, recycling can convert used fuel into a strategic fuel supply that is more repeatable. Oklo is pursuing a differentiated strategy in this area to help speed deployment even when conventional supply chain bottlenecks arise. On supply pathways, we are collaborating with DOE-managed materials. HALEU from conventional and advanced enrichment providers, plus recycled fuel supported through our own recycling and fabrication capabilities. On partnerships, we are working with DOE, cultivating relationships around enrichment and deconversion, and developing opportunities around recycled fuel.
Jacob DeWitte
executiveOur aim is to address scale across near-, mid-, and long-term horizons, all while keeping adaptability as market conditions shift. Within our deployment approach, A3F occupies a distinctly defined position; this facility was purpose-built to produce fuel for Aurora INL, leveraging an existing building at INL where Oklo is setting up and running the fabrication equipment. Regarding authorization, A3F came through a selection process under DOE's Advanced Nuclear Fuel Line Pilot Program, a program designed to facilitate faster licensing and construction of advanced fuel fabrication capabilities. Work is already in motion. Early construction work has kicked off, and A3F is moving ahead concurrently with Aurora INL, ensuring fuel fabrication won't turn into a bottleneck that gates deployment. We've additionally secured DOE's sign-off on both the NSDA and the PDSA for A3F, allowing us to proceed toward final design and construction. Of particular note, Oklo's PDSA stood as the first facility to gain approval through DOE's Fuel Line Pilot Program, a meaningful confirmation of the approach we're pursuing. Up next is the Tennessee Advanced Fuel Center, representing our initial significant move toward establishing long-term recycling capability. On the site and development side, we finished preliminary geotechnical surveys along with soil borings at the Tennessee location and kicked off site development work. On the regulatory and licensing front, we wrapped up our scheduled NRC pre-application engagement and began a rolling NRC readiness review ahead of a forthcoming license application; regarding fuel supply and partnerships, we were chosen to receive DOE recycling research and development funding. The larger takeaway is that this project is moving forward simultaneously on site, regulatory, and funding dimensions, which is precisely how we plan to shift recycling from a concept into genuine long-term fuel supply infrastructure. Still on the fuel topic, this slide addresses upstream fuel infrastructure, specifically uranium deconversion; we disclosed a potential joint venture with Centrus centered on deconversion, which builds on our existing relationship. What makes this strategically attractive is where it's intended to be located. Centrus' site in Pike County, Ohio, sits co-located with Centrus' enrichment operations and borders our planned 1.2 GW power campus. Deconversion represents an essential upstream link in the domestic fuel supply chain, and co-location could enhance logistics, cut down on friction, and bolster both cost and supply resilience over time. It's worth highlighting that these deconversion capabilities are able to serve Oklo's fuel requirements as well as the fuel requirements of other reactors and reactor types, light water reactors included. This marks yet another instance of how we intend to grow fuel infrastructure alongside fabrication and recycling, even as our present emphasis stays on initial venture structuring and project planning. Shifting to isotopes, the Idaho Radiochemistry Laboratory stands as a valuable near-term asset and a demonstration of prompt execution. We secured the NRC materials license for this facility, marking a crucial operational milestone. This facility should generate its first revenue within this year, which positions it among the more near-term revenue-focused components of our wider business. On the strategic side, this lab could serve as the groundwork for building out our isotope processing techniques and afterward expanding them to back upcoming VIPER facilities. The lab is already far along toward becoming both a working operational asset and a core capability for growing the isotopes business as time goes on. Turning now to Groves, which is our inaugural radioisotope test reactor deployment. Groves is advancing along a DOE first authorization route, and two significant steps are already behind us: carrying out the OTA under the Reactor Pilot program and securing approval of the NSDA. Those count because the OTA officially places the project within the DOE pathway, whereas the NSDA secures the safety and regulatory framework for it. What comes next are approval of the PDSA, which has now been submitted, approval of the DSA, and afterward the readiness review plus startup approval. Groves is making its way through an organized DOE-first pathway intended to allow full project build-out and put the facility in position for startup and operations. Instead of merely describing it, I'd like to show you what we've carried out. We'll take a brief pause here for a short video from the Groves site, and after that I'll return and talk you through the key build milestones. Having now seen the progress on the Groves project, here's where things stand on the rest of the path toward criticality. Site development along with the structure was finished within five months. The reactor tank has been installed, fuel has been procured, and interior, mechanical, electrical, and plumbing installation is underway. Auxiliary equipment is likewise at various points in the procurement process. From this point, attention goes to completing the remaining construction work, final installation of reactor equipment, integrated system testing, and fuel delivery. The present execution target is criticality by July 4th; we, along with others, are proving nuclear assets can be constructed and brought online in under 10 months. These are genuine examples that break the widely held assumption that nuclear is slow. Instead, we're showing that new nuclear can be deployed at pace. Groves is advancing quickly. The structure is up, major components are in place, and what's left is the execution closeout and commissioning path toward criticality. Something exciting about this project is that it fully pursues a commercially viable sourcing strategy across every component and doesn't depend on pre-existing or non-scalable or non-viable components and capabilities. The lessons we're picking up are teaching us a great deal en route to full commercial operations. Before moving ahead, it's worth stepping back and spelling out what Groves actually is. Groves is our first radioisotope test reactor, and strategically it acts as a test platform for Atomic Alchemy's production-scale VIPER Reactor platform. It bears the name of General Leslie Groves, who led the Manhattan Project. From a design perspective, it's a pool-type, water-cooled, non-pressurized reactor engineered for thermal neutron irradiation, using pressurized water reactor fuel bundles with low-enriched uranium fuel. The reason this is significant is that Groves isn't merely one project. Its purpose is to provide hands-on learning spanning engineering, production, sourcing, building, setup, and eventually running the facility. The benefit is twofold: short-term and long-term — short-term by getting this inaugural asset constructed and operational, and long-term by shaping how upcoming isotope production facilities might be rolled out and run. Something crucial throughout the entire company is that these assets don't all take the same route for licensing. Our approach is customized based on the asset itself, the location, and what we're aiming to achieve in development. For some first-of-a-kind assets and DOE site projects, we're going after DOE authorization. That covers Aurora INL, A3F, and Groves. When it comes to wider commercial rollout and other non-DOE assets, we're following the NRC pathway. That covers Aurora, Ohio, the Advanced Fuel Center in Tennessee, and the Idaho Radiochemistry Laboratory, which got its NRC license earlier this year. The main point is we aren't attempting to push every asset through one single framework. We're choosing whichever pathway suits the particular asset and development stage best, while also letting insights from early DOE-authorized assets guide later NRC-licensed deployments. With that said, I'll hand things over to Craig for the financial update. Craig?
Richard Craig Bealmear
executiveThanks, Jake. The company had a solid 2025, and during that year we made major improvements to our balance sheet, which means capital is now able to serve as a driver for the strategic plan Jake just laid out. Looking at the full year, Oklo recorded an operating loss of $139.3 million, mostly attributable to payroll, ordinary business costs, and professional fees tied to capital market and asset deployment work. That operating loss also reflected $41.8 million in non-cash stock-based compensation expense, which was affected by the rise in the firm's share price over the year. Our loss before income taxes came to $110.2 million, and that figure benefited from $29.1 million of interest and dividend income generated by our marketable securities investment. Beyond that, for the full year, cash used in operating activities totaled $82.2 million; included in that amount is roughly $13 million of prepaid capital project expense, which will eventually be reclassified as property, plant, and equipment and will flow through cash flows for investing activities. Once you adjust for that amount, we arrived at $69.2 million in adjusted cash used in operating activities, and that landed inside the guidance we gave for 2025 cash used in operating activities of $65 million to $80 million, which shows disciplined stewardship of the company's cash reserves while also taking advantage of the tailwinds to speed up growth opportunities. In 2026, the company plans to keep a disciplined approach toward cash management and capital allocation. We are raising our guidance for cash used in operating activities from $65 million to $80 million in 2025 to $80 million to $100 million in 2026. This measured increase will let the company grow headcount across its business units and carry out its business plans. As asset deployments move forward, we anticipate investing more into projects spanning all three of our business units. We expect cash used in investing activities to fall between $350 million and $450 million in 2026; spending at that level should advance our strategy across all three business units, covering powerhouse deployments at Idaho National Laboratory as well as future power projects in places like Pike County, Ohio. Fuel development for our first powerhouse in Idaho, plus making progress on potential fuel projects that might rely on HALEU, plutonium, or recycled transuranic fuel pathways. An isotope project for both Groves in Texas and possible projects elsewhere, along with other uses in support of the overall corporation. Oklo finished 2025 with cash and marketable securities of $1.4 billion. In the first month of 2026, we additionally raised $1.182 billion net of fees, which completed our $1.5 billion ATM program. This financing gives Oklo a strong balance sheet, leaving the company well-positioned to gain from ongoing policy and regulatory tailwinds and to carry out our business plans in 2026 and beyond. Operator, we are now ready for questions.
Brian Lee
analystHi, everybody. Good afternoon. I appreciate you taking my questions. Thanks for all the updates — there's a lot happening. Perhaps for the first one: you brought up significant movement on the path to commercialization. I realize there's considerable attention on the pipeline and where customers stand. Jake, could you talk about the current situation, whether there are any new additions or conversions into binding agreements, and any added visibility into more of that occurring in 2026?
Richard Craig Bealmear
executiveHi, Brian; this is Craig. I'm not certain exactly why, but Jake just fell off our line. My guess is that the question wasn't the reason. Meta was definitely a key anchor point for the commercialization progress you brought up. Building on that, we're still holding discussions with Meta as well as other prospective customers — some already announced, others that we keep moving forward. The way we see it, Meta matters greatly to us as an anchor customer, and we're able to accomplish more both at the Ohio site and with certain behind-the-meter on-campus customers. That applies not just to data centers either — there's plenty of activity happening with U.S. armed forces, mostly based in Alaska though not exclusively there, plus additional industrial clients. It seems Jake has rejoined the call. Jake, I went ahead and took that question because I believe your line dropped.
Jacob DeWitte
executiveYes, that's exactly right. What I'd say is that ultimately there's a solid pipeline that keeps expanding across various regions. One key factor is that having Meta as essentially a top lead customer encourages others to want to join in and do the same, since often securing that initial customer represents the toughest barrier to entry. That generates a really strong momentum. Beyond that, the positioning and the way we've structured our approach around, you know, the areas where we see substantial opportunity in Ohio will keep growing and scaling alongside us.
Brian Lee
analystAll right. That makes sense. Now I have another question about the CapEx guidance. Going from $350 million to $450 million in 2026 is a fairly significant increase. There's a lot happening, obviously, and certain areas appear to be speeding up. Could you give us some detail on how that CapEx is being divided up? You brought up a few different sites. What should we expect in terms of the pace as we move into 2027 and beyond, starting from this level? I'm also wondering what portion of the CapEx is going toward the Meta Piketon site in Ohio. Thanks, everyone.
Richard Craig Bealmear
executiveYes. Brian, at this stage I won't give you a breakdown by business unit or by individual project. Part of the reason is that we're still doing considerable work refining cost estimates on some projects, and we're also continuing to move procurement efforts forward on those projects. Given where we stand commercially, it seems sensible to let those things develop further before we put out project targets while our procurement strategies are still taking shape. That said, activity is moving ahead across all three business units. The Idaho project is obviously a significant portion of that spending, simply because it's so critical to get that first power project launched and running. We've also begun some early work in locations such as Ohio for the Meta powerhouses. In addition, there's a substantial amount of work happening in recycling for the possible project in Tennessee, along with efforts to launch isotope projects. There's also some scoping CapEx available, though not for certain fuel projects that Jake referenced across HALEU, plutonium and transuranic fuels.
Richard Craig Bealmear
executiveWhen we look at 2026 through 2027, considering how quickly projects are being delivered, my belief is that we will keep seeing CapEx at those same levels. That simply mirrors the fact that many projects are underway, spanning several dimensions, throughout all three business units.
Jacob DeWitte
executiveRight. I'll simply add to that — I believe it matters a great deal when it comes to where we've placed ourselves, plus, honestly, our capacity to act faster and expand into the opportunity space in its current state, and in a way to establish the course and position ourselves for success over the very long term by flexing into every bit of that. That, I think, is a really significant thing to be doing, and it's great that we're able to do it.
Dimple Gosai
analystEvening, everyone, and thanks for taking my question. I wanted to ask about your approach to regulation. Could you update us on where things stand with COLA's schedule and the review of the PDC topical report? For instance, how are you lining up DOE's authorization at INL alongside the NRC licensing you'll need later at additional sites? Related to that, did the government shutdown late last year, plus the staffing shortages we've heard about at DOE and NRC, shift any of your internal licensing timelines, and does that alter your schedule at all when it comes to deployment or filings? That's my first question. Thank you.
Jacob DeWitte
executiveYes, and thank you for bringing those up. A few regulatory items matter here. There's still some muddiness out there, I believe, around how DOE authorization and NRC licensing relate to one another and how the pieces come together. What really counts is that DOE authorization lets us accomplish the single most crucial objective, and that's to build — to gain knowledge through construction right now along a quicker route, which is exactly what we just discussed and gave you plenty of detail on. Without that path forward, the strides we've made with the Aurora plant simply wouldn't have occurred. In a lot of respects, you could argue this is how policy was designed quite a while back; it goes back even, well, a bit more recently than that, but still a fair amount of time ago. In 2018, legislation was enacted and signed into law named the Nuclear Energy Innovation Capabilities Act, and that laid the groundwork for tapping Department of Energy capabilities and resources, including on the regulatory authorization front, to back essentially first-of-a-kind builds, since DOE simply possesses a broader scope of regulatory experience and flexibility. Now, with the executive orders, they laid out a fairly clear direction and priority for DOE to take advantage of that and develop the capacity to do so, which honestly, they mostly already possessed. It merely said, deploy them to support these efforts, which is wonderful because it has totally broken the paradigms, or the path; it has truly brought to light the considerable regulatory inefficiencies that have been there. Beyond that, it establishes a solid route for us to then construct that first plant. And what we anticipate seeing from the NRC under the executive orders there, which build upon all the efforts from the ADVANCE Act beforehand, is generating a great deal of fresh regulatory, honestly, pathways and progress in that area that connect from the DOE, essentially authorization itself. We expect the NRC to issue fairly soon, in essence, their approach, so to speak, for turning a DOE-authorized, built, and operating facility into one that's NRC licensed. We're positioned well to be able to, you know, work through that and find out what it entails. That by nature isn't like a COLA, since you aren't receiving a license to construct and run the plant. The plant is already constructed. It's truly a conversion effort, which is neat; they must conduct the safety review, and they must cite and draw on everything prior. On top of that, we've also been working to bring in and involve the NRC in our essentially regulatory review alongside DOE; they're observing how it's carried out, and they're gaining experience by watching and shadowing those elements, which is quite impactful. This strikes me as a major chance to move more quickly, I'd say; it's tough to exaggerate how valuable it is to concentrate on genuinely getting out of the way of — well, if you consider what a nuclear firm would traditionally have needed to do, what we offered as a product, if you examined it honestly prior to these possibilities coming along, our initial offering was really geared more toward submitting licensing paperwork, correct? Documents. These days, thanks to the DOE authorization route, we're constructing while simultaneously handling that, and that lets us learn and iterate far faster since things inevitably arise and shift, and that assists you in grasping the genuinely difficult matters that truly matter for, like, deployment and scaling up. Beyond that, all of this carries over really well into what we'll be doing, you know, with the NRC in Ohio. What seems fairly evident is that DOE, along with their methods and the milestones we've achieved alongside them, demonstrates they're capable of performing a safety evaluation for particular fast reactors, and they've completed plenty of those previously since they supervised the power plants that our legacy is founded upon. Furthermore, the NRC has likewise demonstrated through recent progress they've made, such as, for instance, the construction permit efforts with TerraPower, that they're able to handle that work too. Bringing them into this and drawing on the experience and know-how DOE possesses, given that DOE has handled this before, is really beneficial and really efficient, honestly. We're awaiting the new framework from the NRC so we can begin moving along the path of getting ready to convert a license. Meanwhile, we're holding steady and pressing on with essentially fleshing out the combined license at present for submission regarding Ohio. Having said that, it's crucial to point out another thing too. As part of the executive orders, there's considerable regulatory effort and rewriting underway that might greatly affect our strategy in a helpful and fruitful manner that we'd anticipate lowering expenses and, you know, schedules while also introducing extra regulatory, sort of, assurance and predictability; that's all an extremely active matter right now, and we're monitoring keenly as different items emerge from the NRC regarding that. It's, you know, reasonable to state that this will likely prove fairly beneficial yet also involve some adjustments, perhaps even bigger modifications to our real regulatory — I'll term it wording-related approach. To put it differently, we still need to obtain an NRC license, yet the mechanisms through which we could accomplish that might look somewhat different given what's going on at the NRC. With that said, you know, we've been getting ready and persisting along the pre-application path that tackles broad and rather general or cross-cutting concerns that matter for our licensing; those will prepare us to actually be able to, you know, cite them within whatever application format emerges subsequently from the NRC. So once again, at this stage, we're still anticipating a Part 52 combined license, though that's simply due to the fact that we haven't yet seen how the new set of choices will shape up, and we expect that to become clear across the coming few months, after which we'll adjust our approach accordingly. A couple of essential points that we're seeing are clearly just gaining the experience of working through the Aurora plant in Idaho under DOE authorization, moving through the DOE regulatory process, having the NRC portion of it, adopting an iterative method, learning through actually constructing and scaling it up, and then applying that knowledge outward. Beyond that, we're also building experience from NRC licensing already on the isotope side, having now secured an NRC license. That's a fantastic win. Regarding the second half of your question, Nicole, yes, we did encounter some holdups on that front with the license application last fall amid the shutdown. Now the license is in our hands and away we go. I don't perceive any of the other impacts that are, honestly, at this juncture, meaningfully impacting our advancement on the remaining activities that we have underway with the NRC and with DOE. That was certainly something that got flagged. The final point I'll make is one significant item as well that's quite beneficial: within the present frameworks, which once more might develop and shift somewhat, or honestly, quite a bit, the methods for what we're licensing and the work we've been doing on the isotope side — not merely the material handling license, but the actual production reactor, essentially the complete commercial edition of Groves that we've devoted some NRC pre-application time to — that follows a distinct pathway from the one the commercial Aurora power plant version follows. Possessing the experience we've picked up across both of those, plus what we're picking up on the recycling side and what we've accomplished on fuel fabrication, is extremely beneficial, since we engage with a whole range of different sections of the NRC and can interconnect best practices and help steer things from our preparation of an application as well as our interaction with them during the review. That assists in numerous ways, in terms of some scaling efficiencies, and carrying best practices over from different business units. That's fairly distinctive for us, because we're shouldering that wide-ranging, well, wide-ranging collection of projects. Yes, that's roughly how I'm watching that landscape develop and how everything here is progressing.
Dimple Gosai
analystThank you, Jake.
George Gianarikas
analystHello, Oklo team. We really appreciate you fielding our questions. In the past, you've said roughly 70% of Aurora powerhouse components come from supply chains that aren't nuclear-related, and I believe that's when Kiewit got involved. Do you have any fresh details on what CapEx for the 75-megawatt reactor might look like — not a full update, but perhaps an initial sense of the dollars per kilowatt? Thanks.
Jacob DeWitte
executiveYes. What I'd say is this is among the areas that keeps shifting as we progress through the build cycle, based on what we're finding is achievable, and likewise what we're finding can be done either to shift certain timelines earlier and construct more quickly while spending more to achieve that, or not, correct? Broadly, speed matters a great deal to us, so that's where our attention is directed. That also provides considerable insight into what we'll then pursue under a more, let's call it, refined approach with the Ohio facilities, which would let us expand those based on what makes the greatest sense given, sort of, the lessons taken from the Idaho facility. What all of that means is, we'll have additional details as we keep moving into the deeper work past certain civil and prep activities, and there will be pertinent updates arriving in turn as I get further along. What we've discovered regarding procurement is that we've managed to identify methods to advance schedules constructively in various respects. We've managed to identify methods to, you know, examine how certain items could be sped up. At, you know, one element of that is occasionally it assists that we have the Aurora facilities in Ohio arriving later, since it might speed up certain items here in Idaho to help us with, you know, additional components and additional parts and additional sourcing for expanding those to the other Ohio facilities and perhaps yielding certain advantages that arise that way. Our overall perspective is that it keeps shifting as we move through this, and as we cultivate and strengthen the connections we hold, and we examine various angles of attack across the different, you know, fronts of what creates cost and what doesn't. Certain items are frankly not worth driving the modernization for on the first facility that we'd want to see when it comes to the actual supply chain and its procurement. So we could spend somewhat more to go faster, while for other items doing so is worthwhile; it's somewhat of a fluid circumstance that we keep evolving and examining. In the end, my perspective is that, broadly, all these components can function—almost everything besides the fuel is able to exist outside of the nuclear, conventional supply chain. What matters most, I believe, is that this paradigm has really been flipped recently, since we're witnessing industry growth for the first time in quite a while. People are now putting forward more disruptive methods and are sort of removing some of the legacy models and approaches that were creating major costs and inefficiencies by getting locked into the status quo, across different suppliers in various segments of the whole value chain, so to speak. Something quite neat we're observing is that we can get, I don't know, far more thoughtful involvement from our partners regarding how to accomplish that, and more productive involvement in eliminating some of the artificial, nuclear cost multipliers that existed previously. I know I repeat this often, but it's difficult to overstate how valuable it is to essentially remove some of those nuclear cost multipliers, correct? The so-called "nuclear idiot index," if you will, is extremely, extremely high and ought to be altered by changing our design approach, by trying to minimize and cut down parts that arrive with some of the standard nuclear classifications attached, through leveraging passive and inherent safety features, and also by updating the way our suppliers and we ourselves actually deliver those plans; we're discovering that in certain areas, you know what, it's just simpler to handle with legacy for the Idaho plant to get it operational, because that's more crucial; that prepares the ground for how we can then resolve that issue in Ohio, since we gained the best practices for doing so; it's quite fascinating to watch that combination developing and coming together. Broadly, though, we're observing a very different style of engagement throughout most of the supply chain, without some of the traditional legacy requirements. What I truly mean by that is that not being a light water reactor is actually quite beneficial. Counterintuitively, the benefit of that is not having to participate in the legacy supply chains with the historical cost structures that are in place there. That is genuinely worth a great deal, because it provides us with far more flexibility, since we're not purchasing light water reactor parts for the most part. I mean, sure, there are some similarities, but we aren't a light water reactor, so much of it is different, and that grants us considerably more flexibility. It also assists us in concentrating on where we need to flex into building ourselves? Which components are best to purchase in order to accelerate, versus developing in-house — perhaps creating them ourselves so we can scale, or producing them internally to relieve pressure on supply chains, or making them ourselves purely to lower costs? This is a dynamic, let's say, expansion-oriented side of the company, and it's likewise the lens through which we consider, you know, not only the capital expense, you know, the modeling and data sets, but additionally the longer-horizon, you know, expense frameworks for the company and also, like, chances within the company.
Ryan Pfingst
analystHi everyone, and thanks for letting me ask. This is kind of building on a few things you mentioned earlier, Jake. When it came to the Meta deal, after their nuclear RFP process they wound up picking two developers of sodium-cooled reactors. Could you walk through some of the advantages your design brings and what may have led Meta to select it?
Jacob DeWitte
executiveSure. What I'd say at this point is that it comes down to what we have. They recognize, I believe, the value that a particular fast reactor approach offers for shutting down an entire power supply, correct? That's essentially restating your point. In essence, I think this shows up along a few different dimensions. The first is technical maturity, which is something even plenty of nuclear specialists seriously underestimate. The reality is that our society has constructed many of these plants. We've gained substantial knowledge about what fails and what succeeds. In the US, particularly the lessons from EBR-II and FFTF, the capability those facilities demonstrated in reaching fairly impressive operational performance — whether in operating capacity factor, in occupational dose rates, or in how to service and run those plants, right? Their operating capacity factors were competitive with and often better than light water plants back then, which demonstrates many of the built-in advantages of the technology itself, and it's the sole technology that has genuinely managed that. Beyond that, I believe there's an obvious path toward cost advantages from sodium being a comparatively, you know, materially benign fluid with readily obtainable seals. Put differently, it can be used and it's very, you know, compatible with stainless alloys; that's excellent for unlocking supply chains and cutting costs and steering clear of the big cost drivers tied to highly exotic alloys you'd otherwise need, absent those advantages. And then there's the fact that it isn't pressurized, plus the upside of running at comparatively greater temperatures. The properties that result from that for, you know, passive heat rejection via the extraordinary heat transfer properties sodium possesses, along with running hotter and what that lets you do to dump heat into air since you're at somewhat elevated temperatures. Taken together, this adds up to a lot of broadly speaking, cost, I'd call it cost advantages, plus the robust operational track record and elevated technology readiness. Those, in my view, are the major points.
Richard Craig Bealmear
executiveRyan, perhaps just a few extra points to throw in. As we keep stressing on calls such as this one, having several fuel routes matters, and so does possessing evidence that backs up those routes — that struck me as one more key differentiator. On Meta, another significant plus was that we already had a solid foothold and secured land in Ohio; and from there, we've gotten even more out of that land position through what we might be able to accomplish alongside Centrus.
Ryan Pfingst
analystThanks, guys.
Vikram Bagri
analystVikram Bagri here — hello and good evening to everybody. There are a couple of things I'd like to ask, and I'll put them both out there at once. The first one is probably for Craig. Could you discuss when Aurora INL is expected? The schedule seems to have moved a bit later, since the wording changed from late 2027 to early 2028. At this point it reads 2028. Is my understanding correct? What caused that timing to move? And I also notice this is a 75 MW reactor. Could you address what the CapEx needs will be for that reactor, or when we'll get better visibility on the CapEx requirement? Then the second one is for Jake. I noticed a fast spectrum plutonium criticality experiment was carried out. Could you explain what that involves, and what your expectations are regarding when plutonium allocations will come through — something we've been anticipating? Thank you.
Richard Craig Bealmear
executiveYeah. Regarding the final portion of what you asked, I'll address that first. As you're aware, plenty of work is still underway, and Jake touched on that tension between cost and schedule, because pulling schedules earlier can carry a cost implication. We're genuinely attempting to strike a balance between those two elements, and I believe we'll be able to share additional details about what that first asset costs, later this year, along with how we intend to reduce cost for deployments down the road. As for the schedule, I think my message has stayed fairly consistent across the different investor meetings I've attended — that 2028 is the target we're aiming at. We recognize it's an aggressive target, yet we sense that the industry and our customers are pressing us to be capable of meeting those schedules. There's another reason it matters that we're pursuing project-like growth: it lets us learn how to lower capital costs and also learn how to shorten project schedules.
Jacob DeWitte
executiveLet me jump in here, Vikram. One thing that stood out to me is what's happening with — well, the way things are shaping up, the schedule pieces basically fall into place as we bring all of this together, correct? In other words, we've got a route to reach key construction milestones during this year and to carry out certain plant commissioning activities, yet bringing the entire plant to the point of producing nuclear heat simply won't occur until 2028 — that's simply the reality of it. At this stage, I'd say what we're observing is consistent with that being how it plays out. We constantly examine various options that could shift portions of the schedule earlier, and certain items might somewhat assist with achieving that. Much of this comes down to how we're able to carry out the building of this facility, and to do so rapidly, and to move through iterative learning processes fairly quickly. I believe this matters since we're also striving to ensure we retain the lessons learned rather than designing as we go in order to apply all of those items, though that benefits us when it comes to Ohio. This matters because it means subsequent plants will, you know, clearly demonstrate those enhancements in a major way. That's a crucial aspect of smaller reactors, isn't it? The expense and the schedules associated with iterations are simply far smaller, and that's precisely how you genuinely propel learning and scaling, as we observe in every context. Now turning to the plutonium side. Yeah, that was quite something. We had the chance to work alongside Los Alamos National Laboratory and travel to the Nevada National Security Site. Essentially, what we had the opportunity to work with was a small plutonium — sort of a metal assembly — where we employed uranium as a reflector, while plutonium served as the primary fuel on board. We got to put it through a number of criticality benchmarks and tests, plus some reactivity measurements, which means you're essentially taking the system, feeding some power into it, warming it up somewhat, and examining the thermal expansion along with the other effects that lead it to shut itself down on its own. This matters because although much of that data was already available, carrying it out in this manner allowed us to achieve greater fidelity across certain ranges of specific interest to us that are relevant to our application, and also to improve our overall models, you know, for validation purposes. It was quite something, since it was genuinely doing that, correct? I believe we were inputting a couple kilowatts at most in thermal power terms, yet within an extremely small system — literally tiny. You know, it counts, and it managed to warm the system up, and we got to witness all of those, you know, unbelievably rapid dynamics and responses. I've had the chance to spend some time around a high-energy uranium fast reactor system earlier in my career. But this one behaved even more quickly. It was extremely, like, tightly responsive, which was fantastic. The manner in which they operated it really demonstrated how sturdy a compact, closely integrated, rapid reactor can be when it comes to inherent feedback mechanisms and all those advantages. That proved useful. We expect additional work in that area, which will simply bring greater accuracy, essentially enhancing reactor output and lowering certain uncertainties across the whole system, and those ultimately convert into money saved, more money made, correct? Or perhaps both. Then there's the second piece: regarding the plutonium awards, we anticipate those will move forward. The Department of Energy is conducting the active assessments of the request for applications that they issued, and we feel quite enthusiastic about our standing for it. As for timelines, I believe we will be watching closely during the upcoming quarter. I think it hinges on a few elements that continue to develop.
Jeffrey Campbell
analystHello, Jake, and hello, Craig. I appreciate you both fielding my questions. First off, will those deconversion talks you mentioned lead to Centrus boosting its enrichment capacity beyond the modest amounts it handles today? Or is your vision that deconversion stands on its own, separate from whichever uranium enrichment provider is involved?
Jacob DeWitte
executiveWell, on the deconversion tech front, what we've been engineering and refining is quite adaptable. It takes UF6 as its feed, and it incorporates certain methods we believe can enhance scaling while lowering expenses more efficiently at the plant level — it's really adaptable. One reason we looked into this alongside Centrus initially comes down to our positioning in Ohio. In fact, we're going to construct numerous plants right in that vicinity where their operation sits. There are meaningful economies of scale from situating deconversion there, plus possible fuel fabrication nearby, along with the reactors. You end up with a rather impressive campus spanning enrichment, deconversion, fabrication, and actual reactors, all within that broader region — and it's a very appealing market to operate in generally. That's our perspective on the chance there. Regarding the arena we're eyeing, I believe we hold some intriguing technology components. We're keen to investigate how that might look when integrated with what they have — their facility and their methods, that is. Naturally, the aim would be to back their considerable growth and expansion. Yes, we view this as broadly compatible with any uranium hexafluoride-based method. Any of the more standard centrifuge enrichment routes, I'd say. When we speak with other enrichers employing uranium hexafluoride across various processes, the advantage is comparable. Beyond that, certain other tech developers are pursuing genuine metal-to-metal enrichment, and clearly deconversion isn't required for that. For us, that's terrific too, since we can feed the metal straight into fabrication. Yeah, that's roughly how we're assessing the landscape.
Jeffrey Campbell
analystAll right. The second thing I wanted to ask about — I found your comment on going after separate licensing routes quite interesting. When it comes to fuel specifically, and fuel recycling, what was behind picking the NRC path for Tennessee, and in what ways does that differ from the DOE fuel facility licensing at INL?
Jacob DeWitte
executiveYeah. The way we look at it, the DOE INL arrangement was structured really well under the well. To start with, we knew we'd have to produce fuel for the Aurora plant. Quite a while back we asked ourselves, "Where are we able to do this, and what route gets us there quickest?" Back then — and this still tends to hold — the answer is to take one of their buildings that already exists and install the fabrication equipment inside it. Our intent is to expand that outward as soon as it's reasonably feasible, and since it's already located on a DOE site, it simply makes sense for that to sit under their sort of oversight. We think about how that could grow, given the reactor pilot program along with the Fuel Line Pilot Program. As for the commercial sort of application involving recycling, considering its location, and since it's meant to be a completely commercial facility, that's something we view as inevitably requiring an NRC licensing route. Incidentally, we've also been in pre-application talks with the NRC regarding fuel fabrication, since eventually we're going to need full commercial fuel fabrication, so that too will ultimately be NRC licensed. Getting that repetition of permitting, regulatory oversight, and execution by actually building and running these things under DOE authorization simply goes faster, and those programs existed on the fuel side. On the NRC side, we then expect those to convert over to the NRC, or at minimum help guide where we ultimately go fully with a commercial fuel fab facility holding a full NRC license. It's comparable to — you know, we're essentially at that point already on the recycling piece and needed to do considerably more pre-application work there because, I'd say, there are more fundamental licensing-type subjects to address on recycling, which is why we've been at it for several years now and why we were pretty thrilled to move into this sort of rolling readiness review once we'd finished the major items we intended to on the pre-application side. That's actually part of the story that perhaps gets somewhat underappreciated, but the progress achieved on NRC licensing for the recycling facility in Tennessee is really exciting; it's really staggering, in fact, to see how much work has gone into it and how much headway has been made through a pre-application getting set for a full application submission. With that said, now that the DOE lifecycle program is out, it wouldn't surprise me if a pathway exists that makes sense for pursuing recycling via a DOE authorization route for a sort of pilot facility. Whether we pursue that is a decision we'll make later, provided it seems logical. And if it does seem logical, well, we'll bring what we've learned into that effort, even as we keep collaborating with the NRC toward full commercial scale. What we observe is that each of these DOE routes lets us reach first of a kind sooner and puts us in a stronger spot for NRC licensing at scale.
Sameer Joshi
analystHi there, good afternoon and good evening. I appreciate you taking my questions. I've just got one regarding Atomic Alchemy and the Groves test reactor. About three and a half months remain before your July 4th criticality target. Some construction is still outstanding, along with procurement of auxiliary equipment. How sure are you that you'll be able to make that deadline?
Jacob DeWitte
executiveYeah, this has served as a fantastic rallying cry for the whole company — designing and building fast, plus learning fast and iterating fast. When you consider the progress made so far, we're fairly confident we can reach or achieve that date, or even beat it, and pull rods to bring the system critical. Fuel has already been ordered. Nearly all the big-ticket items have generally been ordered too. There's still effort going into figuring out how to create sufficient buffer time for receiving and managing everything. It's a logistical undertaking to align all the permitting steps with receiving the fuel, loading it, having equipment ready, and finding ways to perhaps speed up solutions that let us use what's on hand right now, rather than what we'd prefer at a more commercial scale with replaceability for certain instrumentation and detection items. That's partly what this feature and facility exist for — giving us room to operate, work with what's available, and retain flexibility to swap those things in later. Consider the journey: from a bare field, to excavation, to concrete and foundation work, to placing the vessel, loading it, constructing the structure, lining up other major items, and preparing everything for receipt and installation. It's genuinely exciting watching it all come together. We feel quite good about it; it's a challenge. It won't be simple, but we feel quite good about where we stand. I'm constantly asking, "How do we ensure we can move quicker and perform better?" Another interesting aspect: some other companies will likely reach criticality ahead of that date, which is very exciting, because as I mentioned, it demonstrates a range of solutions being delivered. What makes this one special is that it involves genuine civil works. Certain others are simply at a different scale, so they don't require comparable effort. They might rely on pre-existing prefabricated fuel from DOE facilities or inventories and similar things that let you reach that criticality milestone, which is awesome. I mean, this really matters. One thing we've taken away from this effort — and with Groves, that's what gets me so fired up — is that, you know, it's a complete design-build effort, and it didn't rely on hardware that already existed, correct? I mean, sure, a few items sit in stock and on shelves from our vendors, but this isn't a case where we're burning fuel somebody else already produced that's just sitting around in some DOE warehouse or whatever. Basically the entire project was done from square one. That makes for a heck of a compelling narrative, and for us, our capacity to genuinely construct and hand over that system and pull off building something that quickly that will actually generate real neutrons — that's going to be pretty damn cool.
Sameer Joshi
analystUnderstood. Thanks. Good luck.
Jacob DeWitte
executiveThank you.
Sherif Elmaghrabi
analystHello, and thanks. I've only got one thing to ask today. Craig brought up the land you hold in Ohio and how it helped secure the Meta deal. My understanding is that an economic development organization, assisted by an economic development council in that state, provided you with that land. Could you explain why they viewed Aurora's powerhouses as a compelling use for that property? Are you seeing comparable chances in other states?
Jacob DeWitte
executiveThat's a great question, and it traces back to a strategic vision that I believe Caroline, our co-founder, along with several others on our team, identified regarding the possibility of acquiring federal land resources that were being cleaned up, then made available and repurposed for economic development. That was an ideal spot for it, correct? In case you don't know the site, it hosts one of the biggest enrichment plants anywhere in the world. It's an amazing example of industrial scale and capability. When that plant shut down and they began considering how to repurpose much of that property, a chance emerged to say, "Hey, there's substantial infrastructure here that would support building on it. We ought to pursue this." You know, prior to ChatGPT, prior to this general realization that an inflection point in power demand was approaching, we recognized that, hey, there might be chances to place some power plants at that location. We're going to require fuel from Centrus. As you know, we announced a relationship with them several years back to potentially sell them power and construct some infrastructure at that site, including the power plants. We, you know, began collaborating with them to accomplish that and held that vision. Then suddenly, all these factors begin converging quite favorably, all within a fairly brief period. We had discovered that position to be a genuinely valuable asset to possess. While pursuing that, we also discovered precisely what you're asking about, which is, yeah, there are in fact solid opportunities if we approach it correctly, strategically at the appropriate moment, at other sites. Yes, that's something we're actively pursuing. Like, I think I mentioned to you earlier during this call, everything required to deliver power to customers is revealing things and opportunities for us to pursue, you know, in certain respects more, in numerous respects more, and to accomplish it with greater efficiency and cost effectiveness by handling it ourselves and sort of capitalizing on our sites. Rather than collaborating with others who own the land, developing the land on our own or joining with partners to develop the land jointly and delivering power as well is a fairly significant, you know, point of differentiation for us. We're quite enthusiastic about, like, the opportunities we're seeing in that area. Given our business model, those challenges have to be tackled by us. That matters, since it pushes us to handle the genuinely difficult pieces that make deployment tough — and that isn't merely constructing the reactor; it's everything surrounding it. The understanding we've gained from that is, in fact, letting us generate substantial value through those efforts. Indeed, that's what we observe, and we observe additional possibilities that are quite thrilling. What they recognized in us was a desire for nuclear power locally, since their region had a deep nuclear heritage. They sought economic development, as many positions existed there for that purpose, yet those were subsequently being eliminated or decommissioning was sort of advancing. We were in a strong position to assist with some of that. At present we're expanding further there, so plenty of opportunity will emerge as a result. I believe they likewise recognized that — and clearly I'm offering my own read on their thinking; they're the ideal people to inquire with directly — but they also recognized that we were, well, developing energy and infrastructure is excellent since it generates ripple benefits. Once more, this occurred before the entire data center surge. It generates ripple benefits for additional sectors and, clearly, data centers receive much of that focus today, yet I believe that's what they recognized. Should some power stations arrive here, you'll likely gain some other possibilities that accompany that. That's, I believe, what they recognized, and how we perceived it.
Eric Stine
analystHello, everyone. Clearly, the Meta deal matters a great deal, and it does establish that pre-payment mechanism, though I'd imagine it hinges on a solid PPA. Just wondering how things are going on that front. You noted that other prospective customers might want to adopt this same approach. Perhaps you could discuss or describe the PPA talks with those other prospective customers.
Jacob DeWitte
executiveYeah. I suppose the way I tend to view it is that this is among the great aspects of how we examine the landscape and what we've aimed to position ourselves within — power is an enormous requirement for many players. Our capacity to collaborate with Meta came about because we positioned and structured things so that, well, they want us to succeed; we want to succeed; we also must ensure, just as they do, that we can engage with various prospective partners across different regions and through different approaches. The manner in which we attempted to structure that agreement gives us the ability to, clearly, prioritize our location in Ohio with them, while also opening up chances for them to either partner with us or for others to partner with us, whether expanding in that area, nearby, or at additional sites. Broadly, I believe what we're witnessing is — we're seeing the inbound interest and the attention on concrete structure, now that we have a working example, genuinely shift in a positive direction. We're truly discussing meaningful binding offtakes that mirror comparable dynamics, featuring a structure resembling prepayment, which lets us drive project certainty, while also letting us ensure we're partnering with parties dedicated to success here for us, who possess the proper comprehension and the right sort of, I'd say, grace incorporated into how they'll collaborate with us, along with commitment; that matters quite a bit. We've observed that the tone, the tenor, the approach, and the discussions we've engaged in have zeroed in on the major players who will be the correct ones to consider there, and it has sped up the set of conversations since that deal was announced. Personally, I feel rather enthusiastic about how this paves the way for how we'll collaborate with both Meta and, possibly, others, as they step forward. We don't perceive any lack of demand or desire. There are far more possibilities. It's simply an enormous quantity of possibilities. Even so, what this gives us is a structure that lets us genuinely determine which parties matter most, how to rank them, and which ones will show up ready to bring the right elements — the sort of things that demonstrate real dedication as a collaborator, enabling us to carry things out effectively. Hopefully that addresses what you asked. Craig, I'm not sure whether you'd like to tack on anything there, but.
Richard Craig Bealmear
executiveNo, Jake, that matches my view.
Eric Stine
analystOn that point, then — the following stage would involve securing a firm PPA with Meta. Or is that how we ought to be framing it? Given that this mechanism exists now, taking it as an illustration, be it Meta or another party, a firm PPA would serve simply to push this region, this development potentially located in southern Ohio, ahead.
Jacob DeWitte
executiveYeah. Well, let me be somewhat direct. I think this constitutes a binding pledge to supply power, and from our side, for them to purchase power from us. What we observe is that this lays the groundwork to proceed into actual execution on pre-procurement for the long lead items concerning fuel and certain other things, plus carrying the project into those phases. Yeah, transition into a PPA. I realize we've repeated this for quite a while, yet our method with customers has been not to hurry toward a PPA, instead locate stronger binding offtake arrangements. This is essentially the concept we had in mind, since over-specifying the PPA at present isn't the correct solution compared with possessing the binding commitment enabling us to scale into the proper sort of PPA structure once this advances. That's a really crucial point of distinction, I suppose, or differentiation, owing to what this permits us to accomplish in defining that while we work through this alongside them. Yes, looking ahead across roughly the coming year, I'd guess that's when we'll see the PPA take shape. Partly, the timelines will shift somewhat depending on precisely which need sets apply and the best way to structure this. Ultimately, what matters here is that this is a binding offtake, and a binding agreement in support of that.
Richard Craig Bealmear
executiveJake, what I'd add is that, you know, we're just trying to move both the plans for deploying assets forward together with the commercial talks on the PPA, so we can be sure we achieve the proper returns at the asset level. Obviously, you know, the lock-in pieces Jake brought up that we have with Meta, you know, really turn into a significant enabler for the projects we plan to carry out in Ohio.
Derek Soderberg
analystYeah. Hey, everyone. I've just got one question. Jake, as you're aware, government policy and the regulatory landscape in general have been quite favorable. Based on the discussions you've been having with the DOE and the NRC, I'm curious whether you anticipate any fresh government initiatives or regulatory shifts in the coming year that might enable you to speed up your plans even more? Thanks.
Jacob DeWitte
executiveYeah. What we're seeing, I think, is that the government, well, I gave a fairly lengthy response to Dimple on this earlier, along similar lines. We do anticipate further federal measures that keep being supportive and look for various approaches to assist with accelerating this. The Nuclear Lifecycle Innovation Campuses stands out as a key one. I believe that one is also quite significantly undervalued, yet essentially it lays the groundwork for a major federal pledge toward states concentrating on tackling the back end of the nuclear fuel cycle. The typical economic development style of pursuing that is going to center on recycling. We're quite thrilled about the way that appears and the advantages that will flow from it. On top of that, from the executive orders, there remains considerable activity surrounding the NRC and, shall we say, reform, plus modernization efforts at the NRC, which involve a substantial amount of effort going toward modernizing and refreshing essentially the entire set of regulations there; we're beginning to see some of that emerge, though we're aware much more is on the way. From what we can gather, that's going to unfold across, well, everything, which generally strikes me as a pretty darn good thing. We anticipate greater clarity, improved schedule reliability, shorter timelines, lower costs right across the board for a whole range of things that matter to us. Since we have so many projects and since we're undertaking so many activities throughout the space, thanks to the chance to incorporate new elements, we find those align very favorably for us to gain from them. In certain respects, operating with the agility and nimbleness we possess provides us a stronger route to capitalize on those than if we'd already had a license application submitted. I realize it sounds a bit odd, but that's roughly how we view the landscape.
Craig Shere
analystHi, and thanks for squeezing me in. So regarding Brian's question about CapEx heading into 2027, Craig, your suggestion seems to be that the investment spend might keep going at 2026 levels. Depending on approvals and partner capital, could we potentially see another step up into next year? Considering what looks like $2.5 billion of pro forma cash and investments, counting the January ATM you hit, would it be fair to say that's enough to get you through at least next year? And lastly, do you have sufficient fuel for that 75 MW at INL?
Richard Craig Bealmear
executiveI'll have Jake take that final question. Well, we're very well capitalized for 2026 and beyond. As I think we've mentioned in previous discussions, the one thing we haven't managed to execute on yet, though it's certainly part of our broader long-term capitalization strategy, is what we could potentially accomplish through what I'd describe as an asset level financing approach. Things such as project financing; as far as the spend level goes, I think something Jake's taught over two and a half years at Oklo is to expect the unexpected, since I believe we're seeing more opportunities in front of us than we were at this point last year. I do believe what's going to unfold in the coming years is that the character of the spend will shift in terms of seeing more, as our projects advance, particularly in the fuel space. We've discussed recycling quite a bit. I could envision that the mix of the capital will evolve over time, which is another reason I think it matters that we've demonstrated an ability to raise capital in the capital markets. We have other levers available to us going forward, which would be project financing. We're in discussions with the LPO, formerly the Loan Programs Office. We certainly ensure that the treasury team under Graham Johnson's leadership is always on top of the next thing. I'm really proud of what the team achieved in 2025.
Jacob DeWitte
executiveAppreciate it, and thanks to everyone for being here today as we dive into the sorts of opportunities we have, or really just the updates and all the opportunities we're pursuing and putting into action. 2025 turned out to be quite a year; it finished strong and the quarter we're in now got off to a great beginning, thanks to some of the milestones we discussed reaching, such as the Meta announcement. As we keep growing into building and execution, I'd say we're sitting in a very strong spot to learn by doing — something the nuclear ecosystem has largely gone without in any meaningful way since around the 1960s, in my view. It's a very exciting moment for the space, a very exciting moment to watch all kinds of new things get learned in a modern setting, including the best ways to design, build, deploy, and scale throughout the ecosystem. Because of our positioning, our posture, and our business model, we're also uniquely set up to learn plenty about where the opportunities lie for us to pursue, both regarding where we can create value — whether we build things on our own, whether we acquire, merge with, or purchase companies, or simply partner with people to buy sourcing or supplies from them, or material from them. It gives us lots of good insights into how to actually execute here; that, though, is the crucial part. What we're solving for is broad, scaled nuclear execution, which really comes down to how we can build, how we can license, how we can operate, how we can source and supply in-house, and do everything necessary to actually accomplish what we're setting out to achieve; we're also genuinely excited about the strides we've made on the isotope science. We've demonstrated we can obtain an NRC license, we've demonstrated we can execute against DOE authorization across multiple lines, and we've demonstrated that we can also build a real physical asset, an actual reactor, in incredibly short timelines. Also absorb all those lessons learned, the things we've learned that are hard, the things we've learned are easier, the things that didn't work and the things that do work, and help apply those to where we go from here, and aim for turning that reactor on by July 4th, which will be a truly exciting milestone for us. With that, I'll go ahead and say thanks again to everyone who joined, and I look forward to the next quarterly update. Thank you all.
Operator
operatorEveryone, that brings us to the end of today's call. We appreciate you all being with us, and at this point you're free to hang up.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Oklo Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Oklo Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Oklo Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.