Oklo Inc. (OKLO) Earnings Call Transcript & Summary
November 6, 2026
Earnings Call Speaker Segments
Sam Doane
executiveThanks, operator, and good morning to all of you. It's a pleasure to welcome you to Oakley's Third Quarter 2026 Earnings and Company Update Call. I'm Sam Doane, Senior Director of Investor Relations at Oklo. With me on the call today are Jake Dewitte, Oklo's Co-Founder and Chief Executive Officer, and Craig Bealmear, our Chief Financial Officer. We released the financial results for the third quarter of 2026 earlier today. The slide presentation that goes with today's call can be found in the Investor Relations section of our website. Before we get started, I want to remind everybody that today's discussion — including our prepared remarks and the question-and-answer session that comes after them — will contain forward-looking statements. Such statements represent our present views on trends, assumptions, risks, uncertainties and other factors that might cause actual results to differ materially from those we discuss today. We urge you to look over the forward-looking statements disclaimer that is part of our accompanying presentation. To get a fuller picture of these risks, please see our Form 10-Q for this quarter, our most recent Form 10-K, and the other documents we have filed with the Securities and Exchange Commission, all of which are accessible through our Investor Relations website. Oklo assumes no obligation to update any forward-looking statements in light of new information, future events or otherwise, unless the law requires it. With that said, I'll hand things over to Jake. Jake?
Jacob Dewitte
executiveThanks, Sam. Our goal is to rank among the biggest energy producers on the planet and past it, and to make clean power, heat and critical ecotopes plentiful and affordable. We feel our position to deliver on that vision has never been stronger. At Aurora, Idaho, we're standing up the site's first core fuel fabrication capability. Groves-1 is now in operation. We're locking in fuel, pulling critical manufacturing know-how in-house and lining up capacity for deployments ahead. Our balance sheet lets us put capital behind that work. Our focus is on fleets rather than a single unit, and the ability to run multiple smaller projects in parallel as we pursue our bigger objectives provides valuable opportunities to iterate often and gain lessons from doing. Each project builds up people, processes, supplier ties and operational know-how that we retain and carry across Oklo. That positions us to succeed. Fuel is the foundation. Through our strategy, we leverage our balance sheet to connect sourcing, fabrication and recycling in order to back our own deployments and serve other prospective customers; we are building reactors. We have constructed a reactor, we have fuel in hand, we have run a reactor and we have the capital to continue. That is the source of our confidence. Also, government policy is creating more ways for us to deploy it. Three specific developments are especially relevant to the business we are building. To begin with, the NRC has completed a final rule that permits applicants to draw on pertinent technical evidence from reactor projects authorized by the DOE in order to bolster commercial licensing. In Oklo's case, this strengthens the strategic importance of moving Aurora IDO forward while under DOE supervision. Whatever safety analysis, testing and operating experience we generate can, where applicable, back up subsequent NRC applications while still satisfying the NRC's requirements; that makes today's work more valuable for future deployments; we are establishing an operating reference along with the technical basis capable of supporting a wider Aurora fleet. Next, Groves-2 was selected for the National Reactor Innovation Center's Nuclear Energy launch pad. That gives us entry into DOE authorization routes and specialized nuclear know-how as we move our combined isotope production and processing pilot forward. Groves-1 has already been taken through DOE authorization by us. With Groves-2, we get the opportunity to put that experience to use while adding the processing and finishing capabilities required to deliver isotope products. Third, key difficulties in nuclear fuel infrastructure that could meaningfully affect our overall business plan are what DOE's nuclear life cycle innovation campus initiative is solving for; these campuses could connect fuel fabrication enrichment, recycling and waste disposition potentially alongside reactors and power generation. That fits closely with our strategy, scaling nuclear power requires investment across the fuel cycle, and we're developing capabilities to participate across several of those activities. All of this together reinforces the path we chose on purpose — constructing reactors, standing up fuel infrastructure, and keeping the expertise we need so we can deploy again and again. That's a big reason we feel our position to carry out our vision has never been stronger. When it comes to the recycling business, the campus initiative may be a particularly meaningful opening. What Oklo already has planned matches up well with the priorities of the nuclear life cycle innovation campus: recycling, fuel fabrication, power plants, and isotope production factories — and federal policy is now clearing the way for them. There's also a sizable possible source of funding. As of fiscal year-end 2025, the DOE reported more than $50 billion in the nuclear waste fund. At these campuses, Congress could unlock money for eligible infrastructure to manage nuclear waste—recycling included—alongside private capital and commercial facilities. That widens the chances to provide recycling services, make fuel, obtain recycling feedstock and cell recovered materials, and support utilities and other reactor operators, all while strengthening supply for our own fleet. Our Tennessee project is already part of the Oklo development plan, and additional campus prospects depend on agreements, funding, and approvals. We are developing the capabilities those campuses would need, which gives us a concrete foundation for pursuing a broader commercial market. We are building Oklo to generate revenue across the nuclear life cycle. Our reactors are designed to sell electricity and heat, with further opportunities in irradiation services. Geofabrication applies to our own fleet as well as to outside customers. Through recycling, we can reclaim usable fuel along with valuable isotopes, and at the same time we provide services to those who own used nuclear fuel. Our isotype business caters to niche markets such as health care and space. These activities strengthen one another. Fuel demand comes from our powerhouses; supply is supported by fabrication and recycling; and expertise in engineering, procurement, asset delivery, and operations carries over across the whole platform. In our view, this integrated approach allows us to chart our own course, since it gives us greater security over critical deployment requirements and additional avenues for revenue as the nuclear energy industry grows. We are deploying capital into assets on the ground. At Aurora, Idaho, construction is moving forward into structural work. Next to that, A3F is being built by us to produce the first core. Power projects are moving forward, our recycling facility in Tennessee is being developed, and Groves-2 is being readied for forging. At Groves-1, the full path from an empty greenfield site to a reactor in operation has already been completed by us; that know-how now resides in side or cloud. These efforts sit at varying stages, yet they show how wide our execution spans—reactors, fuel infrastructure, and isotope capabilities all developed together and shaped by one another. Our investments are made with repeated deployment in mind. The teams, suppliers, manufacturing capabilities, asset delivery experience, and operating systems put in place today are meant to support many additional assets. That is how a business able to deliver fleets is being built by us. Moving on to power, and beginning with how construction is coming along at Aurora, Idaho. What these photos capture is a little more than seven weeks of work there. September shows us site and foundation prep. Come early October, foundation work on the administration building was moving forward; by November 4, structural steel was being erected; here you see our capital becoming physical infrastructure, with progress obvious from one visit to the next. On a recent trip with a partner, they were struck by the sheer amount of activity on the ground and by how quickly the site was changing; these images give a sense of what they saw. In this one, the reactor building is rising vertically, along with excavation work, the access tower and rebar installation. Excavation work in the reactor area has wrapped up, safety-related rebar installation is underway, and vertical steel placement is happening. Alongside construction, our teams continue to make headway on procurement, engineering, and the fuel fabrication capability needed to start up. The speed is clear to see. The coordination that supports it is equally important, since design, suppliers, equipment, and field execution are all moving forward together. We're building our first Aurora powerhouse and gaining the construction know-how, supplier ties, and project controls that will inform future deployments. What's happening in Idaho is foundational for the fleet we plan to build. Getting Aurora, Idaho operational requires construction, equipment, authorization, and fuel to converge. All 4 are being advanced at the same time. On the construction side, digging at the site has wrapped up, and crews are now working on structural and safety-related rebar. What comes next is further building in the reactor area plus installing equipment. As for procurement, RFPs for components went out and suppliers have been picked. The focus is now moving toward fabrication, delivery, and integration.
Jacob Dewitte
executiveRegarding authorization, the Department of Energy has given the green light to our preliminary documented safety analysis, or PDSA. Getting the PDSA approved for Aurora Idaho represents a significant milestone. That approval is similar to a construction permit from the NRC, and it functions as a crucial regulatory checkpoint for the project's preliminary design and safety analysis, which supports moving forward with safety-related construction and procurement while helping lower the risk of major safety-driven design changes later in development. Additional authorization steps still ahead involve finishing our first core and securing approval for it, using the secured EVR 2 material that has already been set aside for us; these work streams are being run jointly, with defined execution milestones mapped out along the route to startup. We deliberately submitted interconnection applications at several prospective sites within PJM. Developing a fleet requires pursuing multiple opportunities simultaneously while managing the risks associated with each. At present, 900 megawatts are under active consideration in PJM's 2026 cluster study. PJM took back one of the applications we had filed for a possible site in Virginia, and in the end FERC threw out the complaint we brought to challenge that withdrawal. That decision doesn't affect our Ohio project or the larger pipeline we've announced, and we're still working cooperatively with PJM on the interconnection applications that remain. The Ohio site continues to advance through the interconnection process, which supports development of the campus we have planned of as much as 1.2 gigawatts under our agreement with Meda. We're driving that effort forward together with fuel procurement, site development and execution planning. This demonstrates the practical value of Oklo pursuing multiple applications. Even with a setback at one location, these other development opportunities continue to move ahead. We're concentrating on moving these opportunities forward through the studies and agreements required to deliver power; that's typical for power development work. You choose sites, you assess them, you chase them, and frequently only if you succeed. We bought ARMEC and CEI to meet particular execution requirements, cut development timelines, bolster procurement, and enhance our capacity to control costs. ARMEC is already moving component specifications ahead, assessing supplier proposals, and backing reactor module development at Aurora, Idaho. Its manufacturing know-how assists us in determining, alongside other vendors, how components ought to be constructed and what their price should be. CEI has spent decades working with sodium systems, and it has produced sodium test equipment and pumps for Oklo. By bringing that expertise into the company, our engineering team gains direct access to the people who design, manufacture and test these systems. These are world-class capabilities that Oklo now has in-house, and moving them in-house also helps our deployment schedules and enables us to set priorities and coordinate iterations directly; it further creates a chance to keep manufacturing margin within Oklo and to reduce project costs as we apply these capabilities. It is early days, but we are already identifying opportunities for their value to reach across powerhouses, fuel fabrication and recycling. We’ve acquired capabilities that help us execute now and can support a larger fleet as it grows over time. In addition to what we can do internally, we’re lining up outside manufacturing capacity for repeated Aurora deployments. Oklo has entered into an agreement with U.S. With USFR or Forge Rings providing capacity equivalent to 27 Aurora modules from 2030 through 2035, we would also cover major components such as vessels, lids, and support structures. Those parts require specialized manufacturing and sophisticated planning. Securing capacity now gives us a stronger foundation for coordinating orders and deployment schedules later on. The agreement also allows us to expand it with options for additional eligible new capacity. Deliveries from USFR’s planned U.S. manufacturing campus, which would back domestic production, hinge on that facility being finished and qualified. Later orders will document each individual purchase. This partnership rounds out our wider supplier network. Through our capital and purchasing commitments, we're tackling possible bottlenecks early and giving suppliers visibility into what we need. That's how you plan for a fleet — lining up today the production capacity that multiple deployments will demand. AI is likewise speeding things up and changing how our businesses can execute with greater speed and efficiency. We already apply AI to accelerate technical work and extend the reach of our engineering expertise. Take Groves: in under a week, one engineer leveraged AI to adapt existing Aurora POWERHOUSE multiphysics models into a modeling prototype for growth. Our team figures this squeezed months of modeling effort in today's engineering work — work first built for our powerhouses — and it directly sped up progress in our isotope business, a prime illustration of our integrated platform in action; we're automating repetitive technical documentation as well. Legacy document conversion that once consumed days now takes minutes, with document control rules coded into software to automate checks. The bigger opportunity lies in connecting engineering knowledge throughout Oklo. That covers our models, technical data, documents, and the people accountable for them. We're trying to make those connections clearer within our software. That lets teams see where data came from, how it changed, and who's responsible for it. This can reduce hours lost searching for information, checking consistency, and repeating work, while also providing a solid audit trail. With reusable AI agents and workflows, teams can extend those benefits into engineering, coding, documentation, and analysis. What we're after is lowering the time and expense of technical delivery and freeing our people to tackle more engineering challenges. As Oklo expands, these capabilities can support additional projects across the company. Turning to fuel now — the basis for getting our first powerhouse running and growing the fleet. We're constructing the Aurora, Idaho powerhouse and simultaneously developing the capability to fuel it. For our first powerhouse, we've locked in access to recovered EBR-II fuel. And at the Aurora Fuel Fabrication facility, or A3F, we're preparing to turn that material into completed fuel assemblies for its initial core. Facility equipment installation is currently in progress. Our goal is a first full fuel assembly in 2027, and we're coordinating fabrication activities so they support Aurora, Idaho's targeted startup—that alignment matters. Our teams are able to match fuel specifications, manufacturing processes, qualification, and delivery straight to what the reactor needs. We're also exploring how A3F could serve customers outside the company, which would bring in additional revenue from its fabrication capabilities. Getting the first core delivered is the top near-term priority. The production experience and quality systems we've built up can also help shape fuel facilities down the road. We're installing the material equipment and manufacturing capability together with the powerhouse that will consume the fuel. DOE has chosen Oklo for roughly $6.8 million to move recycled metal fuel forward with Idaho National Laboratory. That backs a particular piece of our strategy: converting material reclaimed via recycling into fuel for Aurora and other reactors. Fabrication and qualification are tackled jointly in this project. Its scope covers creating manufacturing methods, producing and testing fuel specimens, and applying performance modeling to help qualify recycled fuel. The goals are to keep fabrication yield and throughput higher while generating less process waste, which might affect the economics of supplying recycled fuel across our whole fleet. The effort also involves readying specimens for upcoming radiation testing at Auror, Idaho. That link matters. We're constructing Aurora, Idaho, while also developing the fuel capabilities that can support later work and shape future fuel development.
Jacob Dewitte
executiveWe’re building out recycling and fabrication capabilities sized to what our planned fleet will need, as well as to extra chances to serve other reactor customers. This project moves forward the engineering work required for recycled fuel to become a scalable supply source for our reactors and for other reactors, generating third-party revenue; it’s worth stressing that with our recycling and fuel fabrication capabilities, the aim is to turn into leading fuel suppliers—not solely for our own reactors, but for other reactors too, which opens a possible fuel revenue stream from third parties. Moving to isotopes, beginning with what we delivered at Groves-1 and what that experience enables. We discussed Groves-1 during the prior quarter, yet I want to put the magnitude of that achievement back into perspective. This photograph provides a direct downward view into the reactor core structure. Substantial construction was completed by us in 229 days, and first criticality was reached less than a year after groundbreaking. For a complex industrial facility, that pace is remarkable. Groves-1 was built on private land with private capital; Oklo commercially sourced or manufactured its major systems, components, fuel, and construction services. DOE provided rigorous safety oversight via the authorization pathway, while Oklo supplied the capital and led execution. The build cost totaled approximately $65 million, plus about $10 million for commercially sourced fuel from <<inaudible>>. Groves-1 is a test reactor running at low power, and its purpose is to build up experience that will serve upcoming isotope production facilities. That project went from an empty field to construction authorization, then commissioning and startup of a nuclear facility, all inside under a year. What Groves-1 means goes beyond reactor physics. We constructed an entire nuclear facility and, through that work, formed the organization needed to deliver and run nuclear assets. Creating that capability was a major undertaking; we developed a site and finished civil construction. We put together the safety basis and the engineering documentation that DOE review requires, plus the quality assurance and configuration controls necessary to manage the project. We put in place programs for security, radiation protection, emergency preparedness and maintenance. We also built the operating organization — that meant hiring, training and qualifying the people responsible for the facility, writing and testing their procedures, and showing DOE that both the facility and the organization were ready to run safely. On procurement, we qualified suppliers, negotiated commercial terms, completed factory acceptance testing, and took specialized equipment through installation and commissioning. The project controls behind that work were also in order: cost, schedule, supplier performance, construction sequencing and readiness planning. Oklo built these capabilities. We used them and demonstrated them through Groves-1. Inside Oklo today, we now have real construction data, trained operators, operating experience and DOE authorization experience. Delivering a nuclear asset takes an organization that has now been proven through completed work. Because we build, own and operate, that experience stays with us and gets applied throughout the company. For the isotope facilities coming up, the most straightforward route is the transfer—we can take the operating programs, supplier relationships, authorization experience, and workforce capabilities developed at Groves-1 and reuse and strengthen them. On the Aurora powerhouses, we can adapt the project controls, procurement processes, construction sequencing, and commissioning and readiness practices to a facility that is bigger and more complex. That experience is already shaping how we're approaching Aurora, Idaho; for fuel fabrication and recycling, we can draw on experience with nuclear quality systems, material handling, radiological controls, and security programs. Every project still needs its own engineering, safety analysis, authorizations, and execution plan, and our teams now tackle these requirements backed by experience from a completed nuclear deployment. We keep the people and procedures; we keep the cost and schedule data, operating experience, and lessons learned. Every project offers us a chance to improve how we deliver the next one—that meaningfully shifts the starting point for future assets. And that's how we're building the capability to deploy repeatedly across the business. Groves-2 extends that base by offering a wider, integrated isotope production site. Our intention at Groves-2 is to combine radiation processing with product finishing under one roof. Reactor capability was proven at the Groves-1 test facility. On top of its reactor and irradiation capability, Groves-2 introduces processing and product finishing facilities. With this integrated scope, we would be able to make isotopes, separate and purify them, and get finished products ready for delivery. Combining those steps is intended to cut turnaround times, lower costs, and provide products that satisfy more customer requirements. Our team can draw on what we learned with Groves-1 — in construction, procurement, operations, and getting through the DOE authorization process — which gives us a practical foundation for carrying out this larger scope. Fuel for Groves-2 has already been bought and secured from Framatome. In addition, the project was chosen for DOE's Nuclear Energy launch pad, enabling us to start construction under DOE authorization. Site location is still being finalized, and we are developing the integrated facility scope. Our position for execution has never been stronger; we have the capital and the experience required to move our work forward across all businesses. The milestones shown on this slide represent what we plan to achieve next. At Aurora in Idaho, our goal is to install the major reactor components, and at A3F we plan to finish equipment installation and build our first fuel assemblies. On recycling, we're aiming for pilot facility commissioning in 2027; on isotopes, the goals are to start construction of Groves-2 and complete our first contracted isotope delivery. Those targets are ambitious. They give our teams clear priorities and give investors concrete measures of our progress. Timing will hinge on execution and the approvals required. Our balance sheet lets us lock in equipment and fuel early, build critical capabilities, and move several projects forward in parallel; we're putting that capital to work against specific deployment requirements. Groves-1 proved we can pull all those elements into one workable whole and hand over an operating nuclear plant. Know-how of that kind now benefits every part of the business, and we're building out what's required so we can repeat the feat again and again. On that note, I'll pass it to Craig, who'll walk you through the numbers and where we stand on capital.
Richard Bealmear
executiveThanks, Jake. Through the first 9 months of 2026, we continued advancing projects across our business units and maintained a strong balance sheet. For the year to date, our net loss through the third quarter was $123.3 million. That included an operating loss of $195.2 million, partially offset by $72.4 million in net interest and dividend income. Cash used in operating activities year-to-date was $110.9 million; that figure includes the $123.3 million net loss, adjusted primarily for $49.1 million of noncash stock-based compensation and $36.7 million of net working capital changes and other adjustments; we continue to expect cash used in operations to fall within our guided range of $120 million to $150 million. Investing activities used $1.3 billion in cash, and that included $965.1 million in net cash spent on marketable securities purchases tied to cash generated by our ATM program. Capital spending for the year to date was $280.9 million, reflecting ongoing planned investment in deploying assets across our 3 businesses; for property, plant and equipment, we expect cash usage to land within our guided range of $400 million to $500 million. As of September 30, our cash, cash equivalents and marketable securities totaled $3.1 billion. Breaking that down, $1.5 billion was cash and cash equivalents, with the remaining $1.6 billion in marketable securities. The balance also reflects $2.3 billion raised through our ATM offerings during the first 3 quarters of the year. We deliberately raised capital ahead of need so we'd have the financial wherewithal to advance projects throughout our platform. With this balance sheet, we gain flexibility to finance scheduled work across all 3 business lines as projects move forward—covering development and construction, purchases of long lead equipment, and fuel procurement for powerhouses and isotopes. It also lets us put money into projects when needs arise and gives us commercial room to support delivery on the milestones we've planned. Before taking questions, I'd like to tie our financial standing to the progress Jake outlined and to what we aim to achieve next. We've gotten the company into execution mode, and we're taking steps to build revenue-generating assets across every business line. Having our balance sheet behind us lets us lock in fuel and equipment early, develop essential capabilities, and move projects forward simultaneously. That capital is actively being deployed, including $55 million directed to priority work, and our momentum is reflected in a 44.3% improvement in our position and 64 cents of value per unit. Groves-1 has been completed. Aurora I&L is progressing through construction, with its preliminary documented safety analysis now approved, and equipment installation at A3F is underway. We're also preparing for the projects that come next. Our in-house manufacturing, supplier agreements, and fuel strategy are designed to enable repeated deployment. Customer commitments strengthen that effort. The prepayment from Meta supports development in Ohio and fuel procurement, and customer agreements now in development are moving our isotope business into space applications. Our model's design—and how we handle M&A—is intended to retain the operating expertise from our power, fuel, and isotope businesses and get the most out of it. We're also discovering that fuel fabrication and recycling can go beyond keeping our own fleet running; they can create opportunities to serve more customers and generate revenue. Our job is to put capital to work with discipline and turn those capabilities into operating assets and customer deliveries. The milestones Jake described provide us with concrete measures for tracking that progress. Thanks for being with us today. Operator, we're ready for questions.
Joseph Osha
analystI'd like to dig a bit deeper into the fuel business — specifically, what the potential is for third-party revenue. What's the timing on that, and what would it look like? Are we thinking it will all be highly enriched fuel, LEU fuel? And would that be supplied entirely through recycling, or through procurement from elsewhere? More detail there would be great, because that's an interesting area.
Richard Bealmear
executiveJake, do you want to handle that one, or should I? You're on mute. I'll take it, since it seems Jake is having some technical difficulties. That's a really good question, and thanks for asking it. It could take a couple of forms; we're strategically building out a recycling business. And we've always said that business isn't only being developed to produce fuel for Oklo powerhouses — we're also starting to explore other, non-Oklo customers for it. But maybe closer to the here and now: Ryan Webster, who leads our fabrication division and is leading the charge on A3F. There's fabrication work that we think we could do for others; some of the investments we're looking into and some of the partnerships around conversion and deconversion could also be sources of revenue. And maybe the other thing I keep pushing on is whether there's a world, even before we're ready to fabricate and produce fuel for others, where we could offer technical services. So right now we're really trying to explore all those options in parallel.
Jacob Dewitte
executiveLet me jump in and add a bit more here. There are a few things, I think, that sort of build out those capabilities. When you consider what we've got in fuel fabrication, to get at your question from several angles, it's genuinely a capability where, honestly, our aim is to be the top fuel fabricator for advanced fuel forms. We're not doing work on <<inaudible>> obviously, but regarding what we're pursuing with metallic fuel, with high-calorie plus oxide fuels for advanced reactors, and also to support next-generation fuel forms such as nitrides and hydrides, things of that nature, we'll possess the capabilities, the expertise, and the capacity to provide support; that's worked for others, correct? And the reason we called attention to those is that we've observed interest, we know demand exists, and we know there's a shortage of capacity for producing fuel to serve those markets. And mainly, the emphasis there has been on things above LEU, but there will be capacity to handle LEU, given that some unique things are possible with certain of those fuels using normal low and retraining. And when I say above <<inaudible>>, I mean things that sit between 5% and all the way up to just under 20%, right? So that spectrum will be a fairly strong area of focus; and the way we view it is that's not all of the capabilities we necessarily must perform ourselves. We have the infrastructure inside the building and the facility. Others are able to come in and lease that space from us, bring their own — basically, frankly, machinery and equipment — to fabricate, where we can partner with them and do it on their behalf given our expertise. But it creates a diverse set of — frankly, it's really a field fabrication platform that lets folks plug and play, or lets us make it for others. I think this is where we see a great deal of excitement, because as we sort of extend this outward, there's an enormous amount of opportunity in fuels — not only supporting what we're doing, what other fast reactor companies are doing, what other microreactor company concepts are exploring and doing, and what's enabled by advanced fuel forms, what space reactors require — but also even as we look at advanced fuel forms heading to next-generation it want to reactors or simply upgrades at light water reactors. That connects to a key point: there's a real scarcity of fuel fabrication capacity right now for the light water fleet, looking ahead. It isn't central to who we are to step into producing the standard, everyday fuel for light water reactors at present. Still, playing a supporting role, offering a site, or even manufacturing advanced fuel types directly to serve those needs matters a great deal. Then we're able to work with the incoming fresh uranium infrastructure supply, and equally with what the recycling facility produces. That gives us considerable flexibility when it comes to producing what we require to support fabrication. And once more, we can either manufacture it and sell those services, sell the fuel to them, or give them the space to come in and do it themselves. So there are multiple ways for us to participate along the value chain and capture some of that as revenues.
Joseph Osha
analystAnd just to get a quick, rough idea of when the first revenue might arrive? I realize that's tough to pin down, but I have to ask.
Jacob Dewitte
executiveHonestly, a few variables will shape how this plays out. I mean, there's a chance for some early services revenue of a sort that could land across roughly the coming 2 years, yet the actual ramp rate will come once the facilities are scaled into operation and past that point, and as other companies' reactor deployment pushes ahead into those areas. But you were asking about the ways that's evolving; and frankly, as we build out this capability and people pay closer attention to it, we keep seeing new folks turn up with different ideas and concepts. So that opens up a few different paths for bringing it to the table.
Dimple Gosei
analystAnd big credit — I thought the deck was great, really well done. Jake, could you remind us when the DSA submission is expected? And also, once Aurora is up and running, does it sell power commercially purely under DOE authorization, or does it shift to an NRC license under this new DOE-to-NRC rule, right? And on that same point, what's the anticipated timing if that transition occurs? Can you remind us of that and the offtake?
Jacob Dewitte
executiveYes; so a couple of variables are involved there. The PDSA is a really key milestone — it lets us build, which is why we're in construction and at the depth we are. The DSA is going to get very near the point of finishing construction. So our expectation is that we won't proceed with it before 2028, since that's the sensible course; after that, when the shift happens at the NRC will hinge on our operational milestones and other steps available to us. One key point regarding Aurora, Idaho: sure, it's able to sell power, yet it can sell radiation services too. In the Western world today, there really isn't any fast radiation — fast new trends, pardon me — radiation capability that's operational, correct? And the U.S. The government had planned to invest billions of dollars in creating a new capability, though in the end that effort never really went anywhere in terms of what it lifted. But that is precisely what Aurora, Idaho will be capable of producing and providing. So it will be able to monetize that in support of next-generation materials and fuel research, spanning everything from federally funded research programs through to private investment. I mean, we've observed companies across the United States, in Europe, and really throughout the world, having to put up money and ship things to Russia for testing. That is behind us now. Obviously, those avenues are no longer open or available. That gives us both the ability and the room to handle those items, along with very strong prospects for producing isotopes. So those are all kinds of improvements tied to that facility as planned — income improvements from selling power, which clearly serves as a core element, plus radiation services in which customers pay to insert materials and gain entry to emerging opportunities in that space. And on top of that, isotope production. So it amounts to a rather interesting three-part model for what that could become. A good number of those activities — for instance, isotopes and radiation services — can mostly be carried out to differing extents under DOE authorization, and power sales can be too in certain use cases. But in the end, once we shift that over to the NRC, it lets us operate from a far less restricted position and gives us considerably more flexibility. That's the reasoning and the timeline behind it. One piece, though, that got folded in fairly heavily across the May 2025 executive orders was the ability to sell power to data centers with DOE authorization. Put another way, sell power directly to a data center offtaker under DOE authorization. That gives us yet another route that might make sense to pursue along a trajectory of that kind. Still, with the flexibility offered by the NRC conversion, and considering how confident we feel based on the time spent with the NRC so far—bear in mind that roughly 1.5 years back, we finished a readiness review in preparation for filing the application before the accelerated pathways from DOE became available. So it's exciting to be in a position to actually carry out that work, and we see the NRC's readiness to accept an application and advance it so it can be converted into NRC space. That's where things ultimately land. Yet plenty of steps are available prior to that point. Our flexibility is quite broad.
Richard Bealmear
executiveThen Dimple, regarding power cells, the DOE permit lets us sell power to the labs, and we've always viewed them as the first initial customer for power generated by the powerhouse, after which we'll move to an NRC permit. The good news, I think, is that it doesn't really feel like DOE and NRC are collaborating to find streamlining options, because I think they're rebuilding that streamlined process at the moment. Putting a definitive timeline on it is hard, but it definitely feels like an accelerator. And I'll make sure Sam and the team get thanked on the deck, because they did all the hard work.
George Gianarikas
analystI'd like to ask about plutonium. What timeline do you have at present, and what cost structure do you expect, for getting hold of some of that government health surplus?
Jacob Dewitte
executiveYeah, I believe we're seeing — there are a few variables in play on that front; we keep making headway through the DOE's programs, as it were, and through engagement aimed at laying the groundwork for it. What we anticipate, I think, is material being tranched in from various sources, with availability and, more directly, "manufacturability" being the issue. So a portion of it may require work done on it before it can be manufactured. The idea, then, is to work with material that's available more readily. And that keeps moving forward. We're keen and enthusiastic to watch that carry on. And clearly we're very enthusiastic about the traction at this stage. Regrettably, as for how the timeline will shape up, we expect it to get much clearer over the next few months regarding when that material can come out and become available, or be moved forward. But we're hopeful and optimistic that various interim milestones will come along the steps there during the next few months, for that material to be released so it can be fabricated. Then the question concerns cost structure, as it were. Broadly, again, this is one of those matters that depends somewhat on programmatic structures and contours, yet generally it tends to be supplied to you as is, with no particular fee or cost, though the fabrication cost is clearly borne by the recipient. So that's roughly how it works. It gives you a fairly appealing feedstock cost. That's essentially 0; but then, obviously, it must be fabricated and turned into fuel from that point.
Marc Bianchi
analystI've got a question about the Ohio project and Meta's involvement there. Under the agreement with Meta, are they obligated to construct the reactor? If not, at what stage would that commitment come about? And could you perhaps walk us through the milestones that need to be achieved to reach that point?
Jacob Dewitte
executiveYes. Right now, there's no binding commitment to actually construct the reactor. That's fairly typical for a project of this kind, particularly one where <<inaudible>> is helping push forward a new approach that supports nuclear development here. Keep in mind, there really isn't any precedent for this — not from a nuclear developer-operator standpoint — to carry it through. Still, it clearly appeals to them to make that selection, and that's the reason they've gone ahead with it. It advances through several phases: site development, long-lead procurement such as fuel, then interconnection, and finally full execution. Still, it represents a relationship that grows over time. What matters for us is that this arrangement led them to contribute capital upfront, which helped demonstrate a viable route forward and then supported continued scaling and execution, while also clarifying the timeline for when delivery will occur. Beyond that, there's the question of costs—and by costs I mean not only Oklo's own expenses but also the actual going rate for power, and how those factors come together in a positive way. So everyone benefits. Still, it's worth acknowledging that — broadly speaking, if you consider how the strategies fed into the steps they took in assembling these elements and building out this program, the aim was locating partners who could help push this forward, since those partners view the technologies as bringing them substantial enablement. They aren’t looking to be only a transactional partner—they also want to serve as a development partner, in ways that work for us too. So figuring out how to make that happen was something we were quite glad to secure through this deal, and it has a very clear path—a direct line of sight to execution—that will actually get us to switching power plants on. And if you consider the power situation — in a market where supply is tight, and you factor in the schedules for delivering power and the fact that we're mostly leading, or near the front of the group, when it comes to electrons produced by nuclear, particularly the advanced features that really capture their interest and enthusiasm. That's probably one reason they picked us in that process to move forward into this; so it's a sort of buildup through a typical development project before it moves into that phase. And we're happy about that because, once again, it brings them in alongside us as a partner rather than simply a transactional customer.
Richard Bealmear
executiveMark, there are certain binding aspects involved — for instance, they've put up some capital that secures them reservation capacity, and we have milestones tied to what we do with that capital, with probably the first major milestone being the securing of fuel, and we're working on that process right now, and then additional milestones will come further along as the project moves forward.
Brian Lee
analystMaybe let's start with the big picture. I realize it's still early, but clearly there was a bit of a shift in the political landscape this week, and then you've seen a lot of these state-level moratoriums beginning to appear and turn into a fairly significant point of debate for data center development down the road. Given all that, I figure plenty of folks sort of presume you guys will mainly focus on data center PTM-style applications with the Aurora Powerhouse; even so, at 75 megawatts, you'd seemingly be set up better than certain SMR competitors of bigger scale — bigger scale referring to their capacity — to go after different kinds of data center–linked applications. Have you thought at all about maybe shifting your go-to-market approach, or at least aiming more effort at nondata center chances going forward, with everything that's going on?
Jacob Dewitte
executiveYeah. I believe to dive into that as well. Well, the short answer is yes, and that's basically the position we've maintained all along. Data centers, clearly, are high-yield and fast-moving, and they require substantial power, drawing it in large blocks. At this point we're seeing some different dynamics take shape. My sense is that data centers will keep clustering in states that welcome them, since certain states are inclined to support and eager to host these facilities — which will only draw more demand toward particular locations. And frankly, our <<inaudible>> lets us adapt to that. Still, taking a broad view of the situation, I tend to think in terms of three main forces behind the growth in electric demand and the considerable upward pressure on prices, which is driven largely by demand. Data centers are clearly a flagship part of that, but we shouldn't overlook the substantial move toward electrification that has occurred over the past 10, 15 years in a great many respects; that shift is placing load on the grid — perhaps in chunks that are less gigantic and less noticeable than data centers, but it is happening nonetheless. Let me build on that point. We're putting substantial effort into reindustrialization, which clearly helps support American jobs and enjoys broad bipartisan backing. If you look at what the last several administrations have done, from an energy policy standpoint, our country in many respects witnessed a shift in which those baseload-consuming industries, assets, and factories got shut down and relocated abroad. Now that they're returning, they require that same kind of power once more. We're seeing this play out even in the work we've done at the state level, when we've been evaluating states and choosing sites there. They’re noticing that in the past they could go out and try to bring in new factories or new manufacturing operations to their states. But it was assumed that this was there, and now they’re coming to understand they have — that is either a major weakness or vulnerability, or perhaps they have a bit of strength, but most of them don’t have nearly enough at all; so we’re finding that this is going to be, I think, a fairly sizable driver. So I think overall we’re quite confident. As you noted, the scale and stance we’ve established let us pursue that course. Yet another key point, in my view, is that nuclear power has robust backing from both parties. One likely development, I believe, is heightened attention on shifting clean generation into place and offering powerful incentives, through every available means, so it can step up—whether serving data centers or simply adding new capacity overall given the election outcome. Nuclear stands in an especially favorable spot for that. I'm reasonably hopeful, whether it's through policy changes heading in the direction of — perhaps simply the ongoing push to tell companies, if you're going to build here, bring your own power — or through policies aimed at drawing, and continuing to draw, manufacturing jobs into the states. Those jobs will require electricity generation, and nuclear fits that need remarkably well, plus where we sit in terms of size range is a great match for it as well. At megawatt scale it’s big enough that some of that counts, yet small enough to handle either a single industrial facility or an industrial park—so it fits that sweet spot quite well, I believe.
Richard Bealmear
executiveAnd Brian, one more thing I’d mention is the Advanced stack, which worked really well for our sector and for our business during the prior — during the Biden administration. I went to the U.S. governors conference, and there were just as many Democratic governors as Republican ones who wanted to speak with Oklo. So I believe that need for clean, affordable, reliable power is — I don’t see that demand profile disappearing, and that’s definitely not what we’ve seen — the elections took place, but I didn’t hear our corporate development team saying all of a sudden customers were calling to say they’d lost interest. So I think that’s — and that’s why we’re putting so much emphasis on getting assets on the ground.
Nathaniel Pendleton
analystAnd congratulations on the ongoing progress. I'd like to ask about the ARPE funding for recycled fuel mentioned on Slide 18. Given the residual lanthanides and how they behaved in the recycled fuel, how much of the EBR-II fuel data transfers over to recycled fuel? And what remains to be demonstrated through testing, I suppose? Or is this mainly a matter of process optimization?
Jacob Dewitte
executiveYes. What I'd say is this program is mostly about process optimization, along with supporting field qualification in various ways. But part of our — the way we're approaching it is that there is data from irradiated — we, as a country, have irradiated transgenic <<inaudible>> fuels in a number of different reactors and platforms, which generates data that applies directly and can be extended toward qualifying transgenic fuels for full commercial usage. That being said, we do intend to supplement and strengthen that with the fact that we'll have the Aurora plant operating, and we'll be able to use it to actually irradiate test pins and lead test assemblies of transgene fuel in order to, I think, fully characterize and essentially "qualify" it for our use. Formally, fuel qualification isn't really a thing — people like to use that as a colloquial term to describe it — but generate sufficient data that we have enough confidence for our own use, as well as enough data and confidence to support its behavior and to understand its kind of <<inaudible>> emergent effects, so as to justify its use to the regulators too. So I think at the end of the day, that's what we see the intent and mission as being, broadly speaking, and this is a really important step in that. I think what's also invested there that's quite exciting is support for other programs, not just ours, in using transgenic material, which is great for us because the recycling facility will produce transgenic material. So it clearly shows there's interest in a market emerging, with customers wanting that material, given that it has some huge benefits, right, and advantages. So it's pretty exciting to see how that's looking across the board.
Derek Soderberg
analystTurning to U.S. Forge Rings, I wanted to ask about the capital commitment you expect to make there, if there is any. Also, what component volumes does the agreement envision? And last, any further detail on why you're proceeding with USFR rather than some other, more established steel players?
Jacob Dewitte
executiveYeah. I'd say we partner with quite a few companies in this space. So we feel excited, and confident, about the way we go about securing offtake. I think we're — sorry, it isn't sufficient to secure the supply needed for what we must deliver. Still, at the end of the day, what we found here was an organization capable of standing up and backing a substantial amount of capacity that we anticipate being able to grow into, and we'd like that to relieve some of the congestion in other areas. Again, given our pace and our position, particularly on the work projects, we feel quite good about what we require in the near term. The real question, though, is whether that scale holds up over the longer term. That's precisely where we believe new entrants are necessary, since the capacity simply won't be available otherwise. So that's the reason we'll be able to support it and push it forward.
Richard Bealmear
executiveRight now, I'd describe it as a modest initial outlay, and in return we secure reservation plus capacity such that, when they expand, we're able to tap into that capacity. That said, it would represent a procurement commitment on our part that we'd take on as the fleet grows.
Ryan Pfingst
analystWhat remaining items should we be considering as we look ahead on the supply chain, procurement, and manufacturing side for Aurora I&L, and then for the longer-term fleet deployment strategy?
Jacob Dewitte
executiveYeah, so I think broadly, in terms of what we examine across everything there, and <<inaudible>> feel free to jump in on this. But I think when we look at the set of things we need to accomplish to support this, we're trying to solve and build, obviously, what's required for one, and sometimes you find solutions for that which matter for time, right? And we've been pushing really hard on time optimization to get that built fast. At times, some suppliers or providers simply lack the scale needed to supply the Beyond 1 at the pricing we aim to achieve. So you have to find a balance and approach it in different ways, while also weighing that against the danger of relying on one source and instead spreading work across several suppliers. Beyond that, there's the question of deciding what we should take in-house and make ourselves; and I think the perspective we've long held is that it's easy to talk in theory about doing it all internally — as if we had vertically integrated every last thing. It makes sense to tackle that after you've got fresh information and a clear grasp of your actual requirements and objectives, informed by having already constructed several of these systems — as opposed to trying to handle everything at the outset, since you'll inevitably need to circle back and rework things, which demands substantial capital and the like. So striking the proper balance is something we deliberately prioritize. That's the reason you start with a single unit and then scale to many, keeping that kind of trajectory aligned. When we consider how this operates, we’ve been lucky to add an excellent group in procurement and supply chain, plus internal people for manufacturing capabilities. That largely explains why we’ve chosen to develop capabilities internally. We’ve bought capabilities such as ARMEC to broaden what we must produce ourselves, while also identifying suppliers that can genuinely provide what we need for what we’re attempting here. Craig, would you like to add anything on that?
Richard Bealmear
executiveWell, on the I&L side, I’d say I sit down with Rob <<inaudible>> from our procurement group every two weeks. A procurement plan for I&L exists, we’re carrying it out, and we understood which critical-path items mattered, so we bought those accordingly. As for what comes after, we’ve already begun asking <<inaudible>> what could be done in a different way and what we will change for later powerhouse deployments, and how we might apply what Jake mentioned, ARMEC and the other capabilities we’ve brought in-house — after that we’ll turn to building that procurement strategy. I won’t name the vendor, but one of our major suppliers was with us this week at Groves, and those discussions focused largely on what more we can accomplish together. So I think it’s excellent that we have partnerships with our major suppliers. And that conversation has two parts. The first is executing — moving forward on deploying the assets going into the ground now. The second part, though, concerns what comes next.
Jeffrey Campbell
analystJust to change direction a bit and talk about Groves-2, I was wondering whether you're working right now with any participants from the drug industry to sharpen your sense of which isotopes will be most in demand once the facility can actually produce product?
Richard Bealmear
executiveSo Jeff, I'd say the short answer is yes, and that includes Ray Wang and the team. Groves-2 strikes me as somewhat interesting since it has 2 access points as we prepare to get that project underway. One is obviously where will it be located? How do we take the lessons from Groves-1 and apply them; it's going to be a bigger asset. It's going to be a commercial asset, but the other piece is the discussions we're having with pharma and other customers to ensure the isotopes we plan to make can satisfy their needs, and that's a very — I'd say that's likely where Ryan and his team have devoted a good portion of their time at the moment.
Jacob Dewitte
executiveAbsolutely, I agree completely—that's the beauty of it: this is a flexible platform. We've paired that with showing that Groves-1 can execute, and it lets us engage with quite a few different parties. What I find exciting on the radioisotope side is that a sort of strategy is emerging, correct? First, there's the capacity to produce what markets demand and require in the very—in what you might call the near term that's already known, right? And there are a few obvious isotope cases for that. Yet beyond those sits a range of others, and that was always essentially the aim of this reactor platform—being virtual in production—that are far more at the exploratory stage. Something I think we've been noticing is that the capabilities—using computational biology to investigate the ligands, to investigate the various molecular carriers for these isotopes—have been quite substantially underexplored, honestly, radically underexplored. And today, with AI, it simply isn't really happening, because there wasn't much incentive to say, well, let's devote a lot of—like I devote those resources—to examining things that carry isotopes. So we just can't buy them; so why wouldn't we do that? So they don't. Our view is that now you can begin to alter that substantially, and then you unlock a genuinely awesome kind of co-development opportunity where, when you consider it—okay, on the pharmaceutical side, as they begin applying computational biology, massively unlocking new, well, expanded capabilities for different ligands and carriers of various radioisotopes—we can collaborate with them closely and say, at the developmental stages, the exploratory stages, the fundamental research stages, right? We can work alongside them and say, "Hey, what do you need? Okay, in these cases, we can make these—here they are; and from that point, you've been able to begin producing the quantities required to support that early-stage R&D, which can then perhaps translate into and propagate all the way out to something in full production, but then we'll have the capability to truly have that flexibility to supply across the number of use cases. And then that opens the door for any more, right? So it's that kind of two-pronged approach: we've got what's clearly new, but we've got additional new translating around that we're not always going to—we're not going to need to use for producing things like the <<inaudible>> other similar isotopes that are sort of flagship isotopes at the moment; but that can be used to start making these exploratory quantities of others. So ideally, that becomes a massive advantage, since it sort of helps underpin and propel additional investments—using AI and computational biology to investigate and create those carrier molecules, and then employing other isotopes, correct, that simply aren't manufactured at all right now, which could be transformative for that capability at the therapeutic level; suddenly, we're able to start advancing those, right? I mean, it's just incredibly thrilling to consider how all of this shapes up, but you require that capability within the platform, and it isn't out there, and we're eager to be constructing it.
Chris Souther
analystI just wanted to ask a quick follow-up about the supply chain in the U.S. <<inaudible>>.
Richard Bealmear
executiveChris, your audio is cutting out. I don't believe we're getting the question; we really can't hear it. Operator, I think we ought to go to the next one and then perhaps we can come back.
Seth Basham
analystI have a question about the Virginia application that PGM turned down. If you don't mind giving a quick recap — I was rejected — and does that same reasoning carry over to energy or other interconnection requests, Ohio included?
Jacob Dewitte
executiveSure. I think I'll add a bit of color there. What I mean is, we're actively engaged on, I believe, 900 megawatts of development capacity. It does — in Ohio it doesn't impact our plans. My focus was really on some other opportunities we're developing that we're still exploring and examining ways to move forward through different alternative pathways. It's a really interesting moment, correct? Because I think one thing people have noticed broadly is a general recognition that the interconnection process needs continued improvement. It's clearly been a priority and policy focus for the current administration and for various state leaders, and it's something nonpartisan interests are focused on to make sure power plants can get online; and one struggle some of these interconnection processes have is that novelty is essential to moving into the future, and that's one thing that stood out here — we were bringing a mix of fuel sources and their processes simply didn't know how to handle it, and the kind of default is, well, we don't know what to do right now, but we're going to try to figure it out and get somewhere maybe later in a different way; and I think as you look across the spectrum, as an example set of those, where people are applying innovation to that. Obviously, things — there are things that went through and proceeded as anticipated, which is great. We keep developing those in Ohio. We're also still excited about some of these future other opportunities, given how close they are to where we see very attractive and exciting markets developing.
Richard Bealmear
executiveRight, and that was a single application. It got turned down on technical grounds. Honestly, we don't accept those technical grounds for the rejection, but we have to deal with the situation as it stands. Still, I think it only confirms why our strategy had to involve more than 1 application. So we're pressing ahead from here, but there's no read across to Ohio.
Chris Souther
analystUnderstood. And to follow up specifically regarding Ohio, what timeline do you expect for that application?
Richard Bealmear
executiveWe are moving through the PJM process, and my sense is that it will unfold across the coming 24 months. Still, I tend to think in terms of things you manage, things you influence, and things that belong to the environment. And certainly, I would say the PJM process is one more that falls under what we influence and manage.
Jacob Dewitte
executiveI'll just say that this was part of that previous wave, and it keeps moving along, right? So it isn't for a new set. It's 1 that came through for the last wave and even now is still going forward.
Sameer Joshi
analystGreat. Congrats on the headway. Just one brief thing regarding the connection with <<inaudible>> — did anything move forward? Or what's the game plan there across the coming 9 to 12 months?
Jacob Dewitte
executiveYeah, I'd say what we're noticing is that we're still pretty closely involved with them, along with a range of intent partners, so as to keep growing that market. Our position is solid thanks to the projects we've got — thanks to, say, as Craig mentioned, Meta being prepayment — and we're pressing ahead with those and building out those opportunities. Two years back, the thing that troubled my sleep most was fuel and how responsive the enrichment markets would be—that ranked among the largest worries. It wasn't because of any concern about our first plant; that one's fine. My real worry was what getting past that stage would look like. These days I feel more confident than at any prior point regarding developments in the entrustment markets, an industry that sat stagnant for so long and is now being jolted awake by numerous forces: incumbents and legacy players are stepping up and executing in exciting ways, and new entrants are coming forward. I'm really enthusiastic about the developments in that area. That said, our strong ties with <<inaudible>> stretch back many years, and we keep moving that partnership ahead while also supporting other participants in the ecosystem, since we believe this is a crucial field with substantial room to grow. Demand is rising sharply there—not only for next-generation advanced reactors but also for keeping today's plants running—given that an import ban and a cliff are set to hit hard next year, along with ordinary growth and upgrades. This is a thrilling moment for the sector, and our role is to back it and help get it moving—while, as you might say, standing right at the front of the queue.
Richard Bealmear
executiveAnd Sameer, honestly it blows my mind that after 3 years—since I joined Oklo—back then, 3 years ago around now, most of what we discussed was risk on the regulatory side and risk around fuel supply. And I believe we're taking steps daily to reduce those risks, and it feels like momentum is building on every front. And, at the risk of getting myself in trouble—Jake these days has a 2-year-old and a newborn. So there are other things keeping him awake at night.
Eric Stine
analystI'm just curious — you mentioned the optionality you have in PJM, in light of that one situation. It makes me wonder whether you have other agreements, and clearly you're chasing others such as the meta agreement: do you expect those deals to be tied to specific sites, or would there be some wiggle room if you hit problems like you did in one region — so that someone could sign for just a certain amount of power instead of power at that particular location?
Jacob Dewitte
executiveYeah. What we're discovering, I'd say, is that the strongest interest is in power generally. What we've noticed is a genuinely fascinating mix of forces showing consistent growth. And plainly — really, a continuous broadening of curiosity about where data centers will be sited — anyplace they can find power. That's the pattern we're tracking pretty carefully: they went from being, needless to say, in the core corridor states to now weighing, frankly, whatever location has power available, that's where we'll go. And I believe that carries over into the following phase, which is new power development — not just from assets we already have but from new car development — going wherever that ends up; and that's kind of coiterative, since obviously you've got some flexibility in determining where that power is located, unlike attempting to buy it from an existing plant that obviously is already built and running; but now there's this dynamic where it's like, hey, do you — if all right, Oklo, where are you able to put power, or is that more a situation where we respond to, hey, these are the locations we're going. And that's the capacity we either have or lack in those regions; then they responded, like, okay, yes, great, some of these make sense and some don't; and from that we can ensure we remain focused on the areas we want to pursue, which gives us considerable power and flexibility. Again, I believe what we're seeing is <<inaudible>> traction, clearly, with the sites we have. It isn't unusual for power development to proceed through — you select a number of sites because that's where we see the market pushing us — saying we'll develop these forward. A few factors narrowed the options for us, and you simply keep repeating that process, strengthening the habit, and continuing the cycle until you locate the right spots where you can build, scale, and also attract customers. Still, at this stage I sense we are moving increasingly into something like a field of dreams situation — if you build it, they will come. That isn't true in every market without exception, but it is quite — it is considerably more conducive to that approach, generally speaking, throughout the United States. One area I find particularly exciting is the idea of nuclear life cycle innovation campuses. Picture how they take shape: first you establish fuel production infrastructure in a region, along with government policy support, and then power plants naturally follow nearby, gradually creating campuses with real power capacity. Some data center companies are already expressing interest, saying this looks very promising. With 6 states now in what you could describe as the last phases, I believe it will prove the "build it and they will come" approach, which should draw in additional participants along those lines. Add to that a wider pricing backdrop that's generally favorable, and we end up with far greater room to maneuver, which is a good thing. Let me be clear: one factor that aided us in building the Meta partnership was spotting the chance in Ohio and pursuing it; we didn't show up there asking customers who wants this. What we'd learned from talking with customers was enough to convince us it was a solid place to go, yet having that ready and waiting, if you will, genuinely sped up Meta's interest. We’re beginning to observe comparable patterns taking shape elsewhere as well—driven partly by what customers tell us they want, while we’ve grown more adaptable about pursuing opportunities wherever they make strategic sense, and in some instances we see others approaching us instead. Given the recent patterns, this connects to another shift as well. In my view, it will begin drawing in additional industrial projects and infrastructure, which should help broaden the customer mix and also shift activity toward regions that tend to be more welcoming of growth and of newcomers looking to establish a foothold there. That works because securing your own new power supply gets handled within the development side of things. So those areas will be worth watching, and our approach fits them nicely thanks to the adaptability we bring.
Richard Bealmear
executiveThat capability — and I believe we'll witness more of it as we develop additional power campuses in locations such as Ohio, which will be contracting via virtual PPAs. So it's excellent that such a construct already exists for us to leverage.
Chris Souther
analystMy apologies for that earlier. Can you hear me more clearly now?
Richard Bealmear
executiveYes, far clearer. Sorry that we had to kick you out.
Chris Souther
analystPerhaps focusing just on the supply chain aspect for I&L compared with the fleet, Jake, since you mentioned that briefly. You all have talked about collaborating with Keith in order to somewhat formalize portfolio deployment. Could you explain why the USFR capacity reservation appears to suggest approximately 2 gigawatts by 2035? What additional long lead items must you reserve during the next year or 2 for that 2030 to 2035 window? And then could you give us a sense of what percentage of the supply chain for Idaho is finalized versus the percentage of the planned fleet supply chain that you all already assembled last year?
Jacob Dewitte
executiveYes. For the Idaho plant, at this point we're essentially finished, I'd say. We feel good about where that stands. Clearly we're still constructing and bringing things together, and much of that work will carry over into whatever comes next for us beyond that facility. I think in a few instances we're evaluating added capacity that goes beyond what existed before or presents stronger opportunities, though it wasn't fully available yet — USFR is one such case. But take, for example, the partnerships we've established with Siemens, which are long-term and grounded in mini plants at scale, and that's excellent fuel; we discussed <<inaudible>> additional componentry from our partnerships that we've managed to develop so as to not merely support what we have here but extend past it; and then I think it's among those areas where we're examining some of the bigger lifts, which are clearly fuel, vessel pumps, particular elements within the instrumentation and control stack, and steam turbine generators. Plus the steam generators and heat exchangers. So when we consider the work completed on Aurora I, much of it carries over directly and further still. After that, we keep working on providing — not optionality, rather Flex, pardon me — essentially a plan for added capacity past that point, based on what we anticipate unfolding, how we see the markets shifting, and the customer demand that keeps arriving. That, I think, is where we aim to address things at scale using those.
Drew Scott
analystIn the 10-Q, I saw that this Aurora I&L is scheduled to come online in 2028 to 2029. Should we interpret that as a modest slip into 2029, and if so, why, I suppose?
Jacob Dewitte
executiveYeah, I think so. I mean, Aurora — when you consider the timeline for Aurora house in terms of full commissioning and start-up. One thing the grows have taught us is which variables tend to surface when you're handling the kinds of issues that come up and that you have to work through and mitigate, along with the chance that equipment will need recalibration and testing and reinstallation; and when we examine the timelines and the pile-up of arrival dates for everything and how that all lines up, those variables matter quite a bit for making sure the proper buffer and bandwidth are there to back it up. That's a direct use of what we learned from the Groves. Some of that is already going in — managing electrical noise is a huge factor in nuclear plans. It's something that basically everybody's aware of, and then you kind of — it doesn't slip your mind, but each site varies enormously for a lot of reasons, depending on the type of building, where the steel sits, the structures you're using, the timing of when you do the grounding, the soil, the atmosphere, and the season during which you're working — there are so many variables; therefore having that extra capacity and that extra flexibility is critically important. And if you think about why, when you're detecting one single new tranche, which is more or less what you're able to do, right? What you're observing is the identification of individual nuclear reactions within certain newer term monitoring systems. The way this operates: a charge is placed in a detector, and it picks up the energy that a nuclear reaction essentially delivers. Depending on the detector technology and the particular thing involved, sometimes it's an efficient event; however, a number of them employ nearly the target that the Vision attempts to reach, and that delivers energy, which deflects the field, and you measure that perturbation — which is a very small figure. Consequently, you need extremely robust noise insulation and isolation; therefore, when issues come up, you must be capable of tracing them out. You have to be able to calibrate effectively. This process is fairly time-consuming, and when you scale up with Aurora, there are limits to how much of it you can complete prior to assembling the whole plant, since the entire system is inherently interconnected. What it comes down to is having the adaptability to handle that while still accommodating the firm finals for the items we're clearly procuring and what we're accumulating so that installation of everything is finished by the deadline. That said, I believe one of the longest lead times really ties back to the instrumentation-side variables, together with full plant integration, commissioning, and start-up, drawing on what we saw and learned at Groves. We're therefore implementing measures that could trim a portion of that timeline; we're starting to see some gains over on the left side. Still, given our current knowledge and everything we've picked up along the way — which is precisely the reason we go through these exercises — that's approximately how we expect the buffer to look once you add up the duration for every component showing up, being put in place, and then completing all the work needed to confirm everything is commissioned and run up. If things go well, we'd hopefully manage to get in front of a few of those items and perhaps shift you even further to the left. Ultimately, though, I want that cushion built in, since completing all of this will require time. I realize that sounds odd to say, but that's exactly why Groves-1 exists — to help us grasp these issues; now we're attempting to anticipate them. At this point we're trying to control whatever we're able to there, yet certain items truly can't be handled until everything is fully assembled and constructed. There are steps you can take to reduce it somewhat beforehand, but those are tasks that must be done. That's one illustration. Other cases exist as well, though that one tends to be the clearest illustration. Apologies — let me expand on that slightly. One point worth stressing: because of how this system works and what it can do in terms of radiation services — which matter a great deal for describing and creating the fuels and materials of the next generation, both for our company and for others — and because of what it offers for isotopes, along with certain calibrations we wish to carry out and must carry out so those advantages become possible. Those revenues can be quite appealing in certain respects, and beyond that there's the lasting value of what amounts to a national asset. Getting those matters fully secured is important, over and above the basics, so that we're strongly placed to capitalize on the remarkable performance the system is going to deliver. That's another area where this comes into play—making certain we handle it along those lines, and not solely through the angle of moving toward power generation, but also by backing the other elements and putting ourselves in a solid position on that front. Beyond that, it functions as a learning environment that shapes all our future efforts—since the work we carry out at this facility is designed to show us ways to build the coming plants better or with greater efficiency. So possessing that capability matters quite a lot.
Jacob Dewitte
executiveOkay, thanks everyone for being here today. So, in August, we brought online what we believe—based on all the research we've done and prior examples we've studied—is the quickest reactor in history that was privately funded and fully privately constructed. Being the very first to do that is a genuinely thrilling accomplishment. In the same way, at Aurora, Idaho, we're advancing at an extraordinary rate, and I believe we're on a path to likewise—as shown on Page 2—set a global record for the quickest privately constructed fast reactor, which is really neat. We're gaining a great deal of knowledge and obviously feeding that back into the work. We're delivering in a substantial way at scale. There's a real energy around that site. Some partners and other folks joined us for a tour not long ago, and as we walked them through it, they were stunned—and these are people accustomed to witnessing big infrastructure builds, everything from power to semiconductors to manufacturing equipment, really all kinds of sectors—and they were quite fired up to witness the level of activity, how quickly things are moving, and simply the dedication the team brings to making this happen. It also places us in a distinctive spot, because we hold this singular lever of control to genuinely finish the project, move ahead, and accomplish more using the resources, skills, and capital at our disposal—rather than ending up in the kind of situation nuclear has frequently been in, where you launch something but depend on a multitude of other factors for it to truly be completed and constructed. That isn't our reality; we possess everything required, which is a remarkable place to be and something that has been largely absent in the United States for many decades. Yet here we are. And I believe the team is tremendously enthusiastic. I'm tremendously enthusiastic about how this positions us for that segment of the business. But we're also continuing to push forward other highly important efforts. You can't switch on reactors without fuel. That's something we figured out and learned quite early—well, maybe not that early—but we had to handle it in-house to resolve that problem and steer our own future on it, and so we established a top-tier fuel fabrication operation to produce QR reactor fuel, while also building the know-how and capacity to manufacture fuel for other parties. Other reactors run on fuel that's the same or quite similar to ours, so we're able to produce fuel for them, and we also have the infrastructure, the overhead, and simply the floor space within the fuel fabrication facility that can either be rented out — at minimum at cost — or used to support additional fuel forms and types where we're seeing considerable growth in interest and demand, forms that are already in use today but aren't being produced or supplied in sufficient quantities. So we're quite excited about how that opens things up, not only to deliver the critical capabilities we require but also capabilities that others require, and that creates room for extra revenues and further partnerships. Beyond that, we have recycling capability — the ability to make not only transgene paying fuel forms for our own use but also feedstock for others. Given today's fuel markets and the dynamics in play, just last week we saw a clear endorsement from a range of companies pursuing this, along with government investment in and support for capabilities to explore various uses of transgenic material, which we can produce not only for our own reactors but as feedstock for others. So it's very exciting material advancing on all fronts there, and it places us in a strong position in the fuel business where we stand. Then, of course, on the isotope side, we keep learning from the Groves-1 experience and applying those lessons going forward, continuing to deepen the buildup of the muscles required to actually move from isotope production to isotope shipping, and we're very excited about how we see ourselves positioned there, with an enormous opportunity set opening up ahead of us. We haven't lived in a world of isotopic abundance for probably 50 to 60 years or longer, and we hope to change that. What that can change is a fundamental rethink of how we use these things, how we develop drugs and treatments. If you combine computational biology and AI capabilities with the capability of having diverse, flexibly produced isotopes, you can open entirely new frontiers for drug discovery and development, and we can be anchored into those — an incredibly exciting thing for the business, both on the human impact side and from an economic standpoint and perspective. And I think at the broadest and highest level, what we see happening is a generalized shift toward recognizing the key things that need to happen across the entire nuclear value chain for nuclear to succeed, in the places where you're uniquely positioned and uniquely executing to enable and support those things — whether through offtake, through partnering, through investing and doing so with offtake, or by doing it ourselves. Or some combination of those, so we're making sure those pieces work to our advantage while also capturing economic upside from certain of those activities for the good of nuclear broadly — and obviously that's a massive plus for Oklo in particular. Because we're linking our own success to elements of nuclear's success everywhere. We do that so we can guarantee we're able to build what we need to build and then reap the related rewards of opening up that ecosystem. So it's a thrilling moment given where things stand. And I appreciate everyone joining us. Craig mentioned it earlier, so I figured I'd hold mine until now — I did welcome our second child, who's coming up on 4 weeks old, so I'm not getting as much sleep as I used to; not losing sleep over fuel, though, losing more sleep to the baby. On the other hand, I've got more time to think about how we keep solving these problems and sort of scale into these opportunities as we spot them, with the ability to look around corners and get ahead of them as much as we can. But again, I couldn't be more excited to see nuclear rising to meet the opportunities in <<inaudible>> — or rather, to see a whole ecosystem and broad capital mobilized, and real innovation arriving and challenging the cost paradigm and moving these things forward. We discussed what Groves-1 cost. When I was growing up in the nuclear industry, when I was younger, when I was looking at investor presentations, the lowest figures I saw and heard people mention were $300 million, $400 million, $500 million. And that was 15 years ago, before inflation, and we managed to do what we did for around 75 all in; that's a fairly impressive accomplishment and a signal for how we see nuclear being significantly disrupted. And I just think that's among the most exciting things ahead of Oklo today. So thanks for your time, and I look forward to speaking with you next time.
Operator
operatorThis concludes today's call. Thank you for attending. You may now disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Oklo Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Oklo Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Oklo Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.