operatorAppreciate everyone joining. I'm Jordan, and I'll be handling the operator duties for today's session. Right now, I want to extend a welcome to all of you on this webcast and conference call covering Orezone's Third Quarter 2025 results. <<operator_script>> At this point, I'll hand things over to Patrick Downey, our President and CEO. The floor is yours.
Patrick Downey
executiveThanks for joining us on Orezone's Q3 2025 Conference Call and Webcast. Peter Tam, our Executive Vice President and Chief Financial Officer, is with me today. I'll quickly point you to the forward-looking statements, and then we'll get right into the conference details. Gold production for the quarter came in at 23,371 ounces. Q3 is always noted as a period of lower output, and we'll go through that in more detail later, and on track — but we remain on track to achieve our 2025 guidance of 115,000 to 130,000 ounces. Gold sales totaled 20,350 ounces for the quarter at an average realized price of $3,375 an ounce, generating $68.9 million in revenue. This was partly affected by the late sale of roughly 4,000 ounces of gold — 4,942 ounces of gold — into Q3 because of a weather event, which led to that gold being shipped late. All-in sustaining costs came to $1,958 per ounce sold. And those were really impacted by external factors like the royalties and FX and also, obviously, the late sale of the ounces into Q4 and somewhat by the weather, which we always see in Q2 and Q3. On our balance sheet, a very, very strong financial position, cash and bullion at quarter end of $104.2 million, undrawn senior debt of $11.1 million, senior debt of $80.1 million, and we continue to build the balance sheet with our strong Q4 production to date into a rising gold price and our diminishing CapEx in the quarter.
Patrick Downey
executiveAlso, and this matters a great deal, the expansion into hard rock remains on schedule and is running a little under budget — a strong accomplishment that I'll cover afterward in this presentation — with the first gold anticipated in early December. That really speaks to the team once more delivering our project on time and on budget. So the outlook for Orezone is genuinely strong, and Stage 1 major CapEx is now basically finished. Once Phase 1 hard rock starts up into 2026, our gold production will rise by roughly 45%. Q1 2026 ought to be a significant inflection point for free cash flow, since from 2026 onward we will be mining the higher grade hard rock. So I'll now pass things to Peter Tam, who will walk through the production and cost data for Q3.
Peter Tam
executiveThank you, Patrick. Yes, turning to our summary of production and unit costs: in the third quarter of 2025, mining was impacted by a rainfall event that lasted longer than usual, and this slowed operations in the pit. Access to higher-grade zones was delayed, so 4.5 million tonnes were mined during the quarter, and that affected the grades fed to the mill. Mining rates have now picked back up in the fourth quarter, since the rainy season has finished. The mill processed 1.52 million tonnes in the quarter, as the plant keeps performing well and above nameplate. Operating hours were cut by 2.5 days for the annual ball mill reline in July, which should result in more tonnes processed in the fourth quarter. Looking at costs versus the prior year, cash cost per tonne came in higher because of the strengthening local currency, which affected costs across all departments. As was the pattern in 2024, grid utilization rose to 88% this quarter, a significant improvement from 50% in the second quarter, which helped lower processing costs. We are already seeing better gold production in Q4, with 13,296 ounces produced in the first 42 days, and we expect a further uptick before the end of the year from the start-up of the new hard rock plant and from processing higher-grade hard rock reserves.
Peter Tam
executiveMoving to the next slide, on financial and operating highlights: Q3 marked yet another profitable quarter, with earnings from mine operations of $26.5 million and net earnings attributable to Orezone shareholders of $5.4 million. Those earnings took a hit because gold production came in below plan and because a quarter-end gold shipment's export and sale slipped into early October. If that shipment had been sold in September, Q3 would have shown a higher average realized price and a lower all-in sustaining cost per ounce, thanks to more ounces being sold at a better gold price. Q4 metrics will gain from selling those additional ounces. On the whole, liquidity stayed healthy at quarter end, with cash of $85.3 million, and that figure is expected to rise above current levels by year-end as more ounces are sold at better gold prices. With that, I'll turn it back to Patrick.
Patrick Downey
executiveThanks, Peter. Now turning to what we expect for 2025. We've updated our all-in sustaining cost guidance essentially because of outside factors, while every other part of the guidance stays as it was. The new all-in sustaining cost range is $1,700 to $1,800, up from the prior $1,400 to $1,500. What's driving this is mainly the effect of increased government royalties stemming from the stronger gold price and higher royalty rates. When we set the original guidance, we assumed a gold price of $2,600 per ounce at the start of the year. A stronger XOF currency has also been pushing costs up by roughly $80 to $90 per ounce across the year. On top of that, a fire at a substation belonging to our grid supplier cut power availability for a period, and that had some impact on costs in Q2. So for the full year, our guidance stays unchanged at 115,000 to 130,000. As I mentioned, all-in sustaining costs came in at $1,709 for the first 9 months, and we expect them to land in the $1,700 to $1,800 range for the rest of the year. Sustaining CapEx, growth CapEx and the like are all unchanged as well, which speaks to the team and the way we keep costs under control. And truly, across the last 3 years, even with inflationary pressure and exchange rate challenges and so on, I really want to stress that our cost per tonne has hardly moved year-on-year.
Patrick Downey
executiveWe’re still very focused on our costs — specifically the input costs that go into producing each ounce. So for us, 2025 has genuinely turned into a major transition year; stage 1 hard rock is basically finished. I’ll show you a few photos of that. Commissioning is underway, and we anticipate feeding ore into the crusher this week. Output in 2026 will come in at roughly 170,000 to 185,000 ounces. I’d also like to stress that once you move into hard rock mining, we’ll largely get rid of the production lumpiness we experience in Q2 and Q3 because of the wet season, since we were shifting from a pure oxide mine to an oxide hard rock operation where you’re able to work in the pit bottoms, and so on. That will therefore cut down on the lumpiness we see year after year. Stage 2 hard rock, which takes us to 5.5 million tonnes per annum and a production rate of around 220,000 to 250,000 ounces — detailed engineering is now underway. Key long lead items have been ordered. We’re taking a measured approach to capital investment while we await the result of the WAF government negotiations regarding the Kiaka transaction. Once it’s done, though, it will rank among West Africa’s largest mines.
Patrick Downey
executiveAnd that's going to be a long, long life. So it's truly a very, very meaningful cash flow generator in the years to come. So Stage 1 — here's a bit of a graphic showing how it looks. The oxide is on the right in gray. Once more, on schedule and likely under budget. All of our CapEx is essentially finished. We're really just in the final phases of commissioning now. So again, a testament — we constructed the oxide on time, under budget. We constructed this one on time, under budget. So again, a testament to the team we've got on site and how we manage our cost and manage our schedule, et cetera, as we move forward. One of the few companies out there that can do that. Hard rock mining has begun, and we have a significant amount of stockpile ready to go. I expect the first ore into the crusher either today or tomorrow, which will be a big event for us. We'll then begin building our stockpiles for feed to the mill. First gold is expected in early December, and we expect to announce commercial production in early Q1 2026, which will put us at that run rate of 170,000 to 185,000 ounces per year.
Patrick Downey
executiveHere are a few photos. That's the dump pocket, and it has a large ROM pad. We'll have a big stockpile there. Ore will be arriving from several pits, which lets us blend and send the best feed to the plant. As I mentioned, I expect the first dump into that pocket today or tomorrow. After that we'll begin building our ore stockpile. Then from that point, we'll start feeding ore to the mill. At the mill, every liner is installed. We've energized the mill. The key step there is commissioning the variable frequency drive, which is what really delivers the operational optimization for mill throughput. That takes place this weekend, and then we'll begin feeding ore to the mill and directly into the leach circuit. The leach circuit runs 24 hours. So we do expect first gold very, very soon after ore goes into the leach and we start loading carbon onto the gold onto the carbon for stripping. We'll keep feeding tailings into TSF Cell 1 for the next year or 2. But at TSF Cell 2, earthworks are essentially complete. It is designed for the life of mine Phase 1 and Phase 2. So we align that over the coming months before next year's rainy season begins.
Patrick Downey
executiveSo we'll have a complete tailings platform covering the entire mine life. And as you can see, the hard rock mining fleet has arrived on site, and we'll begin hauling ore from P17. The drilling for drill and blast has been finished. Blasting should get underway next week, and once commissioning is done, that ore will serve as high-grade feed to the mill. So, the outlook. 2025 has truly been an excellent year for us — Stage 1 is complete, and all of our major growth projects are done. Once again, there's been considerable exploration this year, with plenty more ahead. We anticipate releasing a substantial set of exploration results toward the end of this year. We've just finished a geological structural interpretation covering the entire ore body, which will unlock additional exploration opportunities for us. I believe our team's record speaks for itself when it comes to delivering on cost, on schedule, and on budget. Excellent near-term growth and cash flow, and a very, very strong balance sheet. As I mentioned, $88 million at the end of Q3. And with Q4 — given the strong production we've had to date, plus a strong gold price and diminishing CapEx as Stage 1 winds down — we expect to close out 2025 with a very, very strong balance sheet.
Patrick Downey
executiveWe still look deeply undervalued compared with our peer group. On a consensus basis, our PNAV stands at 0.3, while peers sit at 0.7. Looking at EV to EBITDA, consensus for 2026 puts us at 1.5 against 4.4 for our peers. We're well positioned for index inclusion, and we keep pursuing growth opportunities, since we have significant cash flow coming out of Bomboré over the coming years. So it's a very exciting year for us, a strong year for us, and I expect a very strong finish. Thank you. I'll hand the mic to the operator.
Operator
operator<<operator_script>> The next question is from Jeremy Hoy at Canaccord Genuity.
Jeremy Hoy
analystStarting with my own question: I'm curious about the outlay for Stage 2 and this WAF — the continuing WAF agreement, or the continuing WAF talks. From where I sit, it sounds like spending on Stage 2 could be paused until they produce a resolution. Is that how it stands?
Patrick Downey
executiveNo, that isn’t what’s happening. We’re still spending, and we’re carrying out certain essential items. What we’ve actually done, Jeremy, is concentrate on areas we’re confident will bring value to Stage 1 before long. For example, an oxygen plant, a thickener, and so on. So we’re moving forward with those. The ball mill remains on order, and we have not canceled it as of now. So all of that is still in place. We’ve merely slowed the engineering somewhat. We are doing work. So we’ll keep the contractor on site for part of that work as we go forward. We anticipate a resolution quite soon, and that should give us the mandate to make that decision, I would expect, very soon.
Jeremy Hoy
analystAll right, understood. So for Stage 2, you don’t really expect any significant interruptions to that timeline, then?
Patrick Downey
executiveYeah, I think it's certainly going to have some impact on the schedule. But exactly how much, I can't say. Our team is pretty remarkable at getting things done. If you look closely at Stage 1, we began excavating the foundation for the concrete in November of last year. And now here we are in November of this year, putting ore through the ore body. So 12 months later, we're feeding the mill. We're quite skilled at how we pull that off. Still, my expectation is that if this continues for a longer period, there will be some effect on the schedule, yes.
Jeremy Hoy
analystYeah. All right, we’ll keep an eye out for a resolution on that. Can you say how optimistic you are about those discussions? Or does that fall outside what you can speak to?
Patrick Downey
executiveHonestly, that falls outside what I can speak to right now. So really — I'm pleased that talks are taking place. It appears they are ongoing. Which tells me conversations are happening, and that's a good thing, but we'll need to wait for the final resolution whenever that comes.
Jeremy Hoy
analystYes. All right. Really appreciate that, Patty. Okay. So, thinking ahead, we talked a few months back when we were on site about the structural work your team was doing and the hope it could generate some new targets, especially for higher-grade shoots inside the mineralized zone. Can you share any details on what you've seen from that, and whether there are any particularly promising targets you're looking to drill out that we might see results from soon?
Patrick Downey
executiveYes, and yes. So the answer is yes, we are. And yes, results will be visible to you in the near future.
Operator
operatorThat wraps up our Q&A portion. At this point I'll hand things back to President and CEO Patrick Downey, who has some closing remarks for us.
Patrick Downey
executiveWell, thanks. We’re glad to have Q3 finished, and now we’re in Q4, which is shaping up to be another strong quarter. We’re really looking ahead to 2026, when we get into a very, very strong year for free cash flow and growth after that. So the future should be very, very exciting for Orezone. Thank you.
Operator
operatorThat brings us to the end of today's meeting. You can go ahead and disconnect now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Orezone Gold Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Orezone Gold Corporation earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Orezone Gold Corporation or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.