Orezone Gold Corporation (ORE) Earnings Call Transcript & Summary
November 16, 2026
Earnings Call Speaker Segments
Patrick Downey
executiveThanks, and welcome everyone to the Orezone Q3 webinar and conference call. Joining me today is Peter Tam, Executive Vice President and Chief Financial Officer. I'll be making forward-looking statements, so please keep that in mind. Alright. Q3 was another significant stretch for Orezone, marked by record gold output, solid financial results, and ongoing advancement at both of our operating mines. During the quarter we produced a record 59,674 oz of gold, which lifts our year-to-date production to 157,029 oz. Consolidated all-in sustaining costs came in at $2,475 per ounce for the quarter, and year-to-date costs were $2,409 per ounce. On the financial side, we generated roughly $112 million in adjusted EBITDA and reported net income of $28 million. Those results reflect what both Bomboré and Casa Berardi contributed and show the growing scale of our business. Importantly, we closed the quarter with about $147 million in cash and bullion, which gives us a strong financial position as we keep investing in our operations and move our growth initiatives forward. One more significant milestone in the quarter was the September release of our updated life-of-mine plan for Casa Berardi, which we'll touch on later in this call. I'd now like to hand things over to Peter Tam.
Peter Tam
executiveThanks, Patrick. Turning to our financial results, Q3 marked yet another quarter in a row of strong earnings, free cash flow, and net income. Gold sales got a boost from record gold production of over 59,000 oz, along with a realized gold price just under $4,200 per ounce. Gold sales came in modestly below gold production because of the settlement timing of quarter-end gold shipments at both operations. Our balance sheet keeps deleveraging, with cash rising to $116 million and senior bank debt cut to $56 million at quarter end. Cash during the quarter was affected by the annual dividend of $16.8 million paid to the Burkina state on their 15% share of Bomboré 2025 net earnings. Next slide. At Bomboré, quarterly production keeps trending higher, with 40,562 oz produced in Q3 at an all-in sustaining cost of $2,246 an ounce sold. Q4 should continue this trend, with higher production forecasted to let Bomboré hit its production guidance for 2026. Next slide; at Casa Berardi, as expected, Q3 came in lower than the previous quarter. Production was lower than the prior quarter due to open-pit mine sequencing and the use of lower-grade stockpiles. The quarter was further affected by a seven-day voluntary shutdown of mining and processing operations because of local wildfire activities. Despite these factors, the operation exceeded planned throughput and recoveries, which allowed production to remain on target. Similar to Bomboré, gold production in Q4 is expected to be the highest in the year. I will hand that call back to you, Patrick.
Patrick Downey
executiveThanks, Peter. Moving on to what we're projecting for 2026: we still anticipate hitting both the production and cost goals we set for this year. Consolidated gold output is expected to remain in the 222,000 oz-247,000 oz range, with all-in sustaining costs coming in at $2,200 to $2,400 per ounce. For Bomboré, full-year production should land in the lower half of our guidance range, and all-in sustaining costs are expected to be in the upper half of that range. On an important note, the Stage 2A hard rock expansion's construction and commissioning are now complete, and it has once again been delivered under budget — so congratulations to the team, marking the third consecutive time. The fifth-stage raise at the tailings storage facility is now complete, and work has begun on the sixth-stage lift, which is progressing ahead of plan. At Casa Berardi, we anticipate output landing in the middle of our guidance range, while costs should come in near the bottom of their range. Our 2026 storage facility lift to level 5022 is finished, and underground mobile equipment deliveries have largely carried on through the period and should stay on schedule for 2027. Back to what we covered earlier—output in 2026 leans heavily toward the latter half, Q4 especially. Given the strides we made in Q3 and the better availability of high-grade material we anticipate at both operations, we're set up well to close the year strongly. On to the next slide. If we look at slide nine, I want to walk through the revised Casa Berardi life-of-mine plan that came out in September; our conviction is strong that this plan represents a significant milestone for Orezone and provides a solid basis for Casa Berardi's long-term future. The plan outlines a mine life spanning fourteen years, with overall gold output of roughly 1.63 million ounces. Average yearly production is projected at about 116,000 oz, and the all-in sustaining cost across the life of mine comes in at slightly below $1,900 per ounce. A central element of this plan involves bringing higher-grade underground mining back into operation, which ought to help deliver a stronger, more sustainable production profile as time goes on. Looking at the economics, the life-of-mine plan lays out an after-tax net present value of roughly $1.05 billion at a 5% discount rate, based on base case consensus gold price assumptions. In our view, this updated plan gives us a solid foundation, but it doesn't capture the asset's full potential, since several operational improvements and exploration opportunities could further strengthen the production profile and economics down the road. Next slide. Looking at Casa Berardi, there's meaningful upside to do better than what our current life-of-mine plan calls for; operationally speaking, the greater mill throughput we're already achieving, along with tighter grade control and better gold recoveries, could push output past that plan while bringing unit costs down; from an exploration standpoint, growing the resource and making new finds create chances to bring in higher-grade ounces, reinforce the production profile and lengthen mine life. We've also changed the development rate; at the point we acquired the mine, we started out at about 5 m per day, and today we're comfortably beyond 16 m per day, and over the last week our development rates hit more than 26 m per day. Looking ahead to 2027, we believe everything is tracking according to plan. Exploration continues to be a core element of our strategy. Given that we have two operating mines already established plus sizable prospective land holdings, we anticipate meaningful chances to expand our resource base, improve future mine plans, and uncover additional mineralization of higher grade. Let me quickly walk through what's happening at Bomboré and Casa Berardi. Turning first to Bomboré, three main goals have guided our 2026 exploration. First, we aim to extend mineralization at depth below the current life-of-mine pits. Second, we are working to find and better define subzones with higher grades. Third, we want to extend near-surface mineralization along strike. On every one of these fronts, the drilling program has kept producing encouraging results. In the third quarter, notable results included 2.97 grams across 34 m, with 4.5 g over 7 m. We also announced 4.28 g per ton across 11 m and 8.34 g across 6 m. Such findings reinforce our belief that significant exploration upside exists inside the presently outlined mining zones as well as outside them. Going forward, we anticipate publishing a revised Bomboré life-of-mine plan in Q1 2027, and that plan will factor in another 100,000 m of drilling on the property. Exploration during 2027 is slated to involve infill drilling of the higher-grade subzones, aiming to assess whether they may be suitable for underground mining. Exploration continues to be a top priority at Casa Berardi as we work toward realizing the full potential of this large mineralized system. In our 2026 drilling program, we've concentrated on extending near-surface mineralization down plunge in areas near existing underground infrastructure, especially the F134 and F160 zones. We've also been pursuing new zone discovery and delineation, including the 118 North area, while carrying on resource conversion drilling ahead of mining. The results so far have been highly encouraging. Notable highlights include 6.47 g over 21.5 m, which takes in 8.94 g over 12.7 m. These results strengthen our confidence in the property's exploration potential and in the chance to find additional higher-grade mineralization. Turning to what's ahead, our plan includes roughly 100,000 meters of exploration drilling at Casa Berardi during 2027, and we'll keep pursuing down-plunge extensions, infill work aimed at conversion, and new zone targeting. Ahead of taking your questions, I want to point to a few key catalysts we see arriving in the months to come. To begin, we're expecting Q4 to deliver yet another solid quarter of output, helped by better access to higher-grade material at both Bomboré and Casa Berardi. Next, the Heva-Hosco preliminary economic assessment is slated for release in the fourth quarter. The release is taking a little longer than we anticipated, since one consultant's work fell behind schedule. When it's finished, though, we expect to issue a report that is thorough and technically solid, and we're eager for that release. Third, we keep advancing an active exploration program at both operations, with 12 rigs currently running; we expect results from ongoing exploration at both properties to give us greater insight into the potential for resource growth and for extending mine life. Finally, as noted earlier, we intend to publish an updated life-of-mine plan for Bomboré in the first quarter of 2027, and it will include an additional 100,000 m of drilling. With that, I'll open the floor for questions.
Cosmos Chiu
analystHello, and thank you, Paddy and team. My first question probably concerns Casa Berardi, and it's good to see operations there continuing to get better. I don't believe I noticed this in the press release, but would you happen to have a breakdown of the grades for underground mining compared with the open-pit grades? Could you share that with us? Should we be tracking it? Does it matter?
Patrick Downey
executivePeter, do you have that at hand?
Peter Tam
executiveYeah, I mean, we do have that obviously internally here.
Patrick Downey
executiveYeah.
Peter Tam
executiveThat's a thing we could probably share moving ahead. During Q3, the grade from the open pit going to the mill was clearly somewhat lower. That clearly showed up in what we produced at Casa in Q3. So I'd say, I think that sat somewhere in the 1.8-ish range, and then as for the underground grade, it was nearer to 3.5.
Cosmos Chiu
analystHmm. Good; that's a metric we ought to keep an eye on going forward, isn't it? Since that way we'll be able to tell how much better things have gotten, would you agree?
Peter Tam
executiveYes.
Cosmos Chiu
analystIs it Peter, or Paddy? All right.
Patrick Downey
executiveYeah, we'd be on the same page there. Yeah.
Peter Tam
executiveThat's right. Yes.
Cosmos Chiu
analystAll right. Another item I've been keeping an eye on, of course, Paddy, is how fast you're advancing underground. It's great to see 11 m per day across the prior two quarters, an average of 15 m per day in October, and then the fresh detail was, I believe, 26 m per day as the peak you've hit. First, is that 26 m per day sustainable, Paddy? And can you remind us, on the way to your new life-of-mine plan, what the intermediate target looks like in meters per day, plus the longer-term goal?
Patrick Downey
executiveWell, we were anticipating averaging roughly 18 by year-end, then moving to 22, 23 next year. Obviously, we're very excited to see 28.5. I always pose the question, well, if it's possible one day, why not the next day? That said, what we've really observed is an improvement in contractor performance, but with the life-of-mine now released, we've drawn some very substantial underground development miners back to the company, and they've arrived with plenty of experience; they don't need to learn the mine, they already know it. So, I'm hopeful we'll keep seeing that improvement. Would I expect 28 m a day every single day? Well, I'd love that, but I doubt we'll see it daily. But what I'm seeing is a very, very encouraging trend running ahead of where we plan to be. We've also brought in new equipment, which matters a great deal, especially for bolters. Bolters were among the key items; we've already ordered ahead for 2027 equipment in 2026. We want to stay ahead of the curve. Overall, very positive. But next year, an average of 22 to 2 3 to meet the plan, and we're well on track to reach it.
Cosmos Chiu
analystHmm. That sounds great. Perhaps we could shift gears a bit and turn to Burkina. As we have observed in the country at present, refineries exist, and I believe the government is encouraging gold production refining inside the country. Does that have any effect on Bomboré? Could you perhaps discuss the current sort of flow of metal production out of Bomboré, and more importantly, at this point in time, the flow of cash flow right now, and could that change?
Patrick Downey
executiveYeah, I'll pass that over to Peter. He generally handles that and will answer that question, but I'm happy to do so.
Peter Tam
executiveYeah.
Cosmos Chiu
analystGreat.
Peter Tam
executiveThanks, Cosmo, for that question. Burkina has opened its new refinery within the country, and we do congratulate them on getting the construction completed successfully. We've been to see the refinery, and right now we're working alongside them to finalize the refining contract and to sort out the logistics along with the other arrangements. While that's in progress, we're still shipping our gold as scheduled and are able to sell our gold just as we normally have. All of that is more or less carrying on without interruption. There's no problem with selling the gold and repatriating those proceeds back into the country. I suspect that once we have the new refining agreement arrangement in place, we'll keep being able to do that.
Cosmos Chiu
analystGreat. Perhaps just one final question, and probably one for Peter too, but Paddy, feel free to handle depreciation if you like. In Q3, depreciation came in a little above my expectation, I believe, and it rose versus Q2, and that hit your earnings figure, EPS — non-cash, yes, but it still had an impact. Could you perhaps remind us whether this stems from the Casa acquisition, adding some kind of PP&E and therefore more depreciation, or was it something different I ought to know about, and what should I be roughly modeling for Q4?
Peter Tam
executiveYeah, look, Cosmos, I think you've touched on it. I think you've nailed it exactly. Obviously, it relates to the new operations we brought in, which we acquired earlier in the year. Part of that is the PP&E adjustment and having to obviously amortize it now across the updated life-of-mine plan that we have. So, I'd say that's something you'd expect to see on a go-forward basis.
Cosmos Chiu
analystGreat. Thanks, Paddy and Peter. That covers everything I wanted to ask. Thanks once more.
Mohamed Sidibé
analystHi, Paddy and team, and thanks for taking my questions. For my first question, maybe I could begin with Bomboré Stage 2, where I believe the investment decision is still pending and I think you're leaving that under review. If Stage 2 does not proceed, what would be the realistic throughput and recovery ceiling the mine can reach after Stage 2A? Since throughput at the mine is already doing quite well just in Q3 and likely running past the 2.5 million ton per annum from Stage 2A, what colour can you give on the realistic upside or potential throughput at Bomboré without Stage 2B?
Patrick Downey
executiveYeah. We've only just commissioned Stage 2A — that's the thickener, the oxygen plant and the rock breaker — so once we get that settled in, we'll then take a look at the blend, though that will form part of next year's budget. Like every other operation we've built, I'm hopeful we'll be able to push it harder. Right now we're observing roughly 2.8 to 3, and going ahead we'll find out if we can push past that. As I mentioned, Bomboré has multiple distinct rock types, and grind and hardness vary by type; even so, my expectation is that we'll run above nameplate, which as I recall stood at 2.5.
Mohamed Sidibé
analystGreat. And regarding Stage 2B, how far have talks with the government progressed on that subject, or are you still taking a wait-and-see approach there?
Patrick Downey
executiveYeah, I think we're waiting to see. Nothing has been finalized on the Kiaka front. We haven't seen a final announcement on that. We'd prefer to have that settled first before any decisions are made, and we've told the government as much; it's not as if we haven't discussed it.
Mohamed Sidibé
analystGreat. For my second question, then, if I may, regarding Heva-Hosco, since the PEA is expected before the year is out, could you give us a sense of Heva-Hosco's scale, how you're viewing that asset, and potential CapEx or capital intensity, and how we ought to think about it? Any extra detail you can share ahead of the PEA would be appreciated, if that's possible. Thank you.
Patrick Downey
executiveWell, naturally I don't want to release anything ahead of time, but what I can say is that it was a feasibility study of 3 million tons per annum back in 2012. That is precisely how we are approaching it. So all of those quantities, and so on, are quite clearly set out in that feasibility study; we have been through it in fairly close detail; so we're using broadly the same quantities as were in it, the same kinds of layouts, and so forth. We're simply bringing them up to date for present costs, and we will probably make a slight change to the schedule for how we build the plants. So that's how I would suggest you look at it. Beyond that, I really can't go into further detail. So it's a plant of 3 million tons per annum. Open pit.
Mohamed Sidibé
analystThat's wonderful, and it really helps. Thank you very much, Paddy. I have nothing further.
Patrick Downey
executiveAll right.
Jeremy Hoy
analystHi Paddy and everyone. Thanks for taking my questions. I want to zero in on your goal of hitting 300,000 oz a year. You're already quite a way along toward that. What other major pieces get you there? Heva-Hosco is pretty easy to see, I think, but do you anticipate a meaningful bump in output, perhaps from underground at Bomboré, or had you already talked about Stage 2B, so let's concentrate on what underground at Bomboré might deliver, which you also put in your presentation.
Patrick Downey
executiveYeah. So right off the bat, if we look at the Casa Berardi Mine, we've been pushing toward 150,000 oz yearly, and that's the target. We're drilling a lot, and hopefully in the next week to 10 days we'll have drill results out that keep showing this is indeed the case we'll be pursuing. Bomboré would go over 200,000 ounces, 230,000 to 250,000 if and when we do Stage 2B. It's really an easy call when you look at it through return on invested capital. We've reviewed it; it stays around $80 million. As you can see now, we've finished three builds there on time, on budget. So we'd expect that to hold true. If you compared that with a North American asset for this, it would be $400 million, not $80 million. So we'd be eager to get that started, but we want to make sure we're on the right track. Heva-Hosco, I'd say, would add roughly 110,000 oz per year. We will go straight into a feasibility study right after the PEA comes out toward the end of the year. But our plan would involve infill drilling and getting current on permitting. A lot of the work was already done for Schedule 19, so it really is a gap analysis and then moving straight into that. It will carry a capital cost that we, as Orezone, can handle ourselves. So if you put all of those together, there's a clear path to 500,000 oz, really not 300,000 oz. So 300,000 oz is the near-term goal here.
Jeremy Hoy
analystYeah, I agree. That's a pretty big jump. Regarding Heva-Hosco, the study is coming to us soon and we're eager to see what it shows. Broadly speaking, could you take us through how the timeline runs up to first production?
Patrick Downey
executiveWell, I'd say if you could get a There was plenty of feasibility work already completed, and typically I'd tell you a feasibility study takes 18-plus months. But we'll take a look and see whether our team can move it faster, since we've got a fairly strong internal team here. I've been through two feasibility studies and two builds over the past couple of years. But anyway, those were in Africa, and they're still builds, still studies. My expectation is that we could aim to have that finished in early 2028, and then reach an investment decision with the board by mid-2028. Moving into permitting would likely take another 18 months. So at a minimum, I'd say it's two and a half to three years.
Jeremy Hoy
analystGreat. All right, thank you. I'm grateful that you took my questions. I'll go back in the queue.
Patrick Downey
executiveWell, thanks to all of you for joining the call and the webinar. We're looking forward to a really strong Q4 to close out the year, drill results, and our Heva-Hosco PEA. Looking ahead to 2027 as we keep advancing at both Casa and Bomboré. So let's just hope the gold tape holds up.
Operator
operatorThat brings us to the end of today's call, everyone. Thanks for joining us. You can go ahead and disconnect now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Orezone Gold Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Orezone Gold Corporation earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Orezone Gold Corporation or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.