Thanks, operator. Brian here. Hello, everyone, and welcome to the conference call for our second quarter. Joining me is Matt Farabaugh, who serves as our CFO. Naturally, and I'm sure most of you are aware, we put out our earnings this morning; inside that earnings release you'll find directions explaining how to get the presentation, and we're about to walk through it now on the webcast. That presentation can also be found posted on our website. I believe you genuinely want to have a copy of it sitting in front of you while we go through it, since that makes this call more meaningful. As we always do, we aim to offer some interesting perspective from the inside; covering everything isn't possible. We don't spend much time marching through boring data points; that's truly not our aim with these presentations. And I should warn you, this one might run long. I believe the last 3 or 4 were, and it could go something like 45 to 50 minutes, so stick with us if you're able. Matt and I will gladly take your questions, so let's move through the presentation. Let's begin. Slide 2, here's our forward-looking disclaimer. Reach out if anything about the disclaimer language is unclear. Slide 3 is our table of contents; attached to the presentation are 3 appendices. Right now we won't be walking through those; but once more, let us know if anything is unclear, either when the presentation ends or by calling us afterward. Slide 4; here's where we reach the portion where we dive right into the numbers; so we've just announced our fiscal year '22 Q2. Sales, as you're aware, came to $13.618 million. Take a look at the column on the right-hand side. Gross profit, $4.411 million. Gross margin 32.4%, lower than Q1, as you can see, roughly around the level of the past couple of years. And I believe we signaled that gross margins would decline in Q2 back when we held our Q1 call. Adjusted EBITDA of $3.232 million and adjusted EBITDA margin 27% — let me correct that, 23.7%. So what did we tell you about Q2 on our Q1 investor call on July 8, we told you our sales estimate ranged from $13.25 million to $14.25 million; so it appears we landed inside that range. And our adjusted EBITDA estimate ranged from $3 million to $3.7 million. Once again, we landed inside the range. Our forecast philosophy, we go over this each quarter. I just want to mention, I'm not certain how much of this material we ought to review, because I think many of you know us pretty well, but we still cover some of the fundamentals in case you've forgotten or in case some new people have dialed in, which we hope for. Our forecast philosophy differs somewhat; we don't give out numbers that we can beat. To us, that whole exercise seems rather foolish. Pretty much everyone engages in it, we realize, yet we don't participate. Whenever we hand you guidance, it comes as a range; what we're telling you is our best sense of what will occur. We might miss the mark, but the message is: here's what we believe will take place — not what will easily take place, but what will take place if we keep doing what we always do, meaning putting in serious effort with tremendous dedication and commitment. So our aim isn't to hand out a figure we can later exceed and then look like heroes. That strikes us as somewhat foolish and honestly — simply not a good use of your time; so I wanted to flag that. Moving along to Slide 5. There are numerous elements that shaped Q2, and we'd like to walk through them. And across this whole presentation, these will be the sorts of things — these are the recurring topics. Revenue from the vital part used in missile programs; we've talked about this across the past few quarters. During Q2, we sold roughly $1 million of one component. Keep in mind, the margin there is low. This is — we've got a relationship with a supplier. That supplier is located overseas. Certain customers and OEMs of ours involved in those missile programs within the U.S. request that we purchase this item on their behalf. We maintain that relationship with an overseas supplier. These programs matter greatly, and afterward we sell the product, we sell an item to those customers; so a markup gets applied, though the margin stays quite low. On the other hand, as we've covered repeatedly, once we truly utilize that product and manufacture the — what we refer to as ablative prepregs, the margins become quite high; now after we've sold the product to those customers, they're free to do as they please with it, but the anticipation is that eventually we'll use it to make the composite materials for those ablative programs on their behalf at some future point. So it reverses; when we make the materials, margins are good; when we sell the central component, it's essentially a low-margin markup. So in the second quarter, low margin — pardon me, $1 million in sales of that component. Trouble obtaining key raw materials. Yes, that's a major recurring topic. Over $200,000, in fact, tied to missed sales because of our — inability to obtain materials we required. And then challenges with international shipping, another $200,000 in missed sales during Q2; put differently, this concerns goods heading out, not arriving. We serve customers abroad; we couldn't get international shippers to move all of it. I mean, our team excels at this, truly excels at it, yet we still couldn't ship $200,000 worth of product that was undergoing testing overseas. Our approach is really straightforward: once a product goes out the door, we bill for it, and that's when it gets booked as revenue for the quarter. If shipping doesn't happen, though, there's no sale recorded in that period. That left us roughly $400,000 short; not a great look, admittedly, but consider this. During the final two weeks of the quarter, more than $1 million in extra dollars hung in the balance. Our team pulled off something truly impressive on the assembly side to push this through. Tons of brute force, tons of shifting things around, tons of juggling, tons of logistics. Still, it kept us on edge a bit, since so much more was riding on it. Everything hinged on those same end-of-quarter dynamics; so plenty of brute force, everyday struggles, and on top of that we're handling COVID quarantines. A fourth layer, yet we're managing. This time nobody has gotten seriously ill; however, it created chaos for production scheduling and planning, because here's what occurs: someone's spouse gets a positive test, they head home, the entire crew heads home too, and we've got to maneuver around all of it. None of this is grumbling. It's simply the reality we live with, and we want you to know about it. I believe our folks handled these sorts of challenges quite admirably.

Brian Shore

executive
#2

Yes, domestic freight problems, plus difficulties with international shipments — domestic freight problems too. Alright, um, sorry — our supplier has performed miserably. He cannot find anyone to deliver to us. We're discussing the possibility of driving over to the Kansas City train yard ourselves to collect some of the materials, and that wasn't something we could do. We told them, fine, when we're discussing this, let us. Extra expenses tied to expedited freight shipments. So yeah, it's a bit odd, honestly. Our suppliers aren't truly delivering the product to us, and they claim, "Oh, at the last minute we can get you something," yet then we're on the hook for the expedited freight, which, alright, you might call that an interesting way of looking at it, but those costs remain. Cost escalations — if you're paying attention to anything happening globally, reading journals, financial news, or hearing other companies speak, none of this should catch you off guard. This is basically everyday life for a company that manufactures in the U.S., and not only in aerospace, I suspect. Raw material cost increases, yes, they tie a lot of them. The majority are covered. When we sign an LTA with a customer, that's norm — it's based on the LTA we hold with the suppliers. No LTA, well, then we obtain new quotes for customers, and normally we'll make an adjustment tied to raw material cost increases, though it isn't always covered. General freight cost increases, mostly covered, not always covered. Regarding our P&L — sorry, manufacturing supplies, yes, not always covered. So risk exists when it comes to manufacturing supplies; costs for supplies can climb and climb and climb. Miscellaneous and other costs. Yes, every single one. You can name them for me — utilities, wages, benefits, insurance, whatever you've got. It's a very strange environment we find ourselves in, in my view. I mean just broadly, as a country. We've finally managed to raise our people count. Remember, we mention that each quarter, and we'll give you specifics later on. That's good news, but there's — to reassure you, because obviously, as the people count rises, the cost rises too; these aren't any sort of excuses whatsoever. We don't — we're not the type for that kind of excuse thing. We don't like that; but these are factors we figured you'd want to know about. So let's move along to Slide 6. I'll just discuss Slide 6. This is our annual P&L history reaching back to 2017. You can have a look on — when we look at Slide 34 and our forecast for the current fiscal year, fiscal '22, if you'd like to compare it against the prior years; but let's just move on. Let's keep going here on Slide 7. Therefore, for a few quarters, we weren't providing this data until a major investor told us, you know, we'd truly prefer to review these details each quarter. We replied, absolutely; so here it is. Park holds zero long-term debt; this represents our balance sheet, cash, cash dividend record, and capital allocation plan — apologies, I neglected to read the heading. Park holds zero long-term debt. At the close of our Q2, Park had $113 million in cash and marketable securities. We need spending to finish our big expansion, roughly $2.25 million, with spending so far around $17.25 million. During Q2, we spent approximately $800,000. So — and regarding the tax transition payments, we've discussed those previously. Matt can clarify that better than I can, but they relate to Trump tax law and earnings — apologies, overseas cash; so let's look. We owe $14.3 million, $6.7 million has been paid so far, and $1.7 million in fiscal was paid during the second quarter. Those payments, the $14.3 million, must be paid through calendar year 2025. Naturally, each quarter we always have slightly more than $2 million plus the standard dividend. So you should factor that in too regarding cash outflows. Park's cash dividend. At Park, we kept a standard $0.10 per share quarterly cash dividend going during the whole pandemic and economic crisis. I doubt everyone did that. Park has paid 36 consecutive years of interrupted — uninterrupted regular quarterly cash dividends without ever skipping a dividend or reducing dividend amount. I'm hurrying since it's a lengthy presentation, sorry. Since the start of fiscal year 2005, Park has paid $548 million, or $26.75 per share, in cash dividends. Let's move to Slide 8. On September 13, another $0.10 per share regular quarterly cash dividend was declared, payable November 4, to shareholders of record on October 1, 2021. So here we are. Once this cash dividend is paid on November 4, 2021, Park will have paid $550 million in cash dividends since the start of fiscal 2005, with 3 exclamation points. I'm not sure what you think, but for a small company like Park, that's an awful lot of money; yet we understand it, don't tell me what you did from yesterday, tell me what you'll do for me today and tomorrow. So now we move to Park's capital allocation strategy or a fancy way of saying, what will we do with all that money. For those of us not really living in the Wall Street financial world, I believe that's what it means. So acquisitions and potential collaborations, Park keeps watching and tracking certain potential acquisition opportunities but also strategic targeting of certain aerospace industry segments and product lines. During our prior discussion, we covered this, which is how we pinpointed the sectors we intend to pursue—ones we view as strategic, instead of merely responding to whatever gets pitched to us, say, by bankers. Park has approached multiple businesses and keeps approaching businesses within those chosen segments. So the effort continues. We keep making attempts. Moving on — let's turn to Slide 9. Possible strategic investments tied to significant aerospace and aircraft initiatives. Park has approached particular big OEMs about strategic investments in significant new aerospace initiatives; this is genuinely compelling. These are recognizable, well-known OEM names in aerospace. We know about new initiatives those companies are weighing, possibly not yet publicly revealed; thus we contacted them and proposed collaborating with them on those initiatives, in part through an investment. Naturally, we'd want the business included in that conversation too; so let's proceed. Every dollar of Park's cash was earned via enormous commitment and sacrifice by numerous Park personnel across many years. Park's money isn't simple or inexpensive money; with us it isn't easy come, easy go. Therefore we won't put our cash at reckless risk or complete a deal merely because we want to complete a deal. That money, when it's earned with difficulty, my sense is you lean toward being far more deliberate, far more cautious, far more earnest regarding the way you use it.

Brian Shore

executive
#3

This isn't about simply scattering funds at whichever project or concept someone dreams up. Whenever we move forward with a transaction or put our cash toward buying a company or making another kind of strategic investment, we'll be convinced it's the correct move for Park and for its owners — that means you. Admittedly, a few of you might not hold shares, though plenty of you do. Turning to Slide 10. All right, this ranks among the usual slides we include in our decks — our five biggest customers, which is somewhat entertaining. We'll begin with Aerojet Rocketdyne; they've appeared in headlines a fair amount lately. That ties into North Grumman's ground-based strategic deterrent, or GBST. Did you catch that? It's genuinely a massive opportunity. Being part of this program makes us quite pleased, and we're hoping to gain additional penetration into GBST. These are the upcoming generation of ICBMs, extremely critical to a nation's defense. Aeromatrix Composites. We lack an image for Aeromatrix in this spot, yet there are several programs involved. Kratos — they keep showing up among the top five rather often. We do have a photo of their UTAP-22 drone; Kratos tells us we're the primary provider of composite materials for their drone efforts. In any case, at this point we typically attempt to locate a fresh picture each quarter, since they appear among the top five so frequently. Next, Middle River Aerostructure Systems. This is something we all know well. You can find plenty of information about these elsewhere in the presentations available to everyone here, but in the bottom right we've got a nice image of 747 to 8 engine nacelles. Those nacelles, as you can see, are made completely from Park materials. Now, the NORDAM Group. If I'm remembering correctly, we featured the NORDAM Group last quarter under a different program. This time it appears in the upper right — the Passport 20 engine. What stands out here is that through MRAS, we supply the materials for the nacelles for this engine, and yet this isn't MRAS. This is actually a component of the engine itself. It's part of a primary structures — the primary structure of the engine. And the NORDAM produces this for the Passport 20 engine, which equips the Global 7500 long-range business jet. Moving along to Slide 11. All right. So here's yet another standard slide that appears in our presentations — our pie charts. We've got '20, we've got '21, and we've got '22 covering the first 2 quarters. And purely for the sake of comparison, notice how the slices of the pie have shifted around. Commercial is back to dominating — actually, I shouldn't call it dominant, that's inaccurate, but far more substantial than it was, say, back in '21. That's not — so I doubt it strikes anyone as a major shock. When it comes to the military, progress may be somewhat slower. The message we typically receive is that the issue isn't with us—it's tied to budgets—although I understand the Senator Arm Service Committee recently released its complete markup, and based on what I can share, it appears somewhat reduced. That's encouraging for several of our initiatives, including Valkyrie. Regarding the military, from our perspective, it all depends on the specific programs we're involved in and whether those programs are currently active. For our company, the military represents a completely different situation compared to commercial. In the commercial space, particularly with the emerge programs, they'll be operating continuously—every month, every week, really. When it comes to military work, we could be involved in a really solid initiative, and it might be busy for one quarter, busy again the following quarter, and still busy the quarter after. Naturally, we have no say over that at all, which is why military revenue tends to fluctuate somewhat, but from my perspective, at least, that doesn't mean the military market is getting better or worse. As we see it, things are perfectly fine; smaller specialized programs are also underway. We're fans of those; we believe they're less vulnerable to the significant budget fluctuations that these initiatives occasionally get caught up in. Business Aircraft. For us, that mainly means the Global 7500. Within business aircraft, that's our biggest player. Having said that, we also provide components for other platforms, including Gulfstream, Falcon, and Citation models. Business Aircraft performance has been strong. Over roughly the past six to nine months—maybe eight—likely for clear reasons, those with access to private jets have chosen that option over commercial airlines. On the commercial side, I'll share far more specifics later in this presentation. So let's continue onward. I don't want us to get stuck in the weeds. Turning to slide 12, here's one of the lighter slides we put together every quarter. Elaine and Donna handled this project. We really enjoy doing it. The programs shown here may not be the largest military efforts, but we believe they're the ones you'll find most intriguing, starting in the upper left. First, there's PAC-3. For us, this is genuinely an enjoyable—or at least fascinating—item: F-35 supplying tracking information on an inbound missile to a ground-based intercept using PAC-3. We've been involved with the PAC-3 effort for quite some time. I believe we've brought it up on numerous occasions. Moving to the right, the next item is the U.S. Navy MK-41 vertical launch system. We did manufacture materials and components for this effort, though we're not truly in a position to discuss it in much detail—other than to note that this is a very nice picture. Looking at those, you can see the missile actually taking off from the Navy vessel's deck. Moving on, there's the C-27J Spartan, a medium-range surveillance aircraft—this involves radome material intended for the Coast Guard. After that comes Avio Aster, with blader materials for hypersonic missiles, which probably doesn't come as a shock. Then SpaceX Falcon Heavy—it's genuinely great to be involved in that effort. We ought to be expanding our role in SpaceX's programs, even though we can't really talk about our specific contributions there. When it comes to radomes, rocket nozzles, and drones, we classify those as our niche military programs. That's the space we like to focus our attention on. Let's continue to Slide 13. Alright. Moving to a different subject, I want to give you an update on the significant expansion we're doing in Newton, Kansas. We've increased the overall budget to $19.5 million. As I recall, the figure we gave previously was $19 million, so it's creeping upward a bit. What we've spent to this point comes to approximately $17.25 million, and the amount still left to spend, which combined with what's already gone out gets us to that $19.5 million total, is $2.25 million. The expansion itself is complete, and the way this works is that certain suppliers have holdbacks until items are signed off and certified, at which point final payments get released. That explains why some money has yet to be paid. Manufacturing trial is underway, which is good. We anticipate that qualification runs will kick off near Thanksgiving — so we're pointing to December. While plenty of other companies were slashing their capex, maybe all the way down to zero, we went ahead and made a big capacity addition, and that turned out to be the right call. Had we not done it, we'd be suffering badly today. As you remember, we first intended this added capacity as backup, but given all the circumstances, we now genuinely require it for volume too.

Brian Shore

executive
#4

And we've now figured that out, we would have been in serious trouble, because you can't complete an expansion and construction — get a building constructed, place orders for equipment, engineer that equipment, get it certified and released, and have the factory qualified in 6 months. That's roughly a 3-year process. So had we not gotten started and kept pushing forward, we'd be facing — we'd have a genuine crisis on our hands at this moment. So thankfully we made the correct call. Something that's somewhat new here, the photo is the bottom photo, you can see the current facility in the center along with the new offices, the facility on the left side, this brand-new facility. And that small structure on the right, that's actually something that has existed all along. And I've never really discussed it, but I'd like you to see it; it's approximately 10,000 square feet. Tin City Aircraft Works, that's our R&D facility; and the name — we came up with a name that's sort of a little secret, but anyone can figure out how we arrived at that name. Well, perhaps we'll send you at least $1 or something along those lines. All right. And then the center photo, that's the new building featuring the new office — pardon me, the existing building with the office expansion, it now appears as 2 stories, the building at the top is the new building. Let's continue on Slide 14. So commercial aviation, updates and developments, shifting gears once again to commercial aviation. The first item we had in our earlier presentation, higher jet fuel prices and environmental concern provide additional motivation for airlines to more rapidly replace less fuel-efficient legacy single-aisle aircraft with more fuel-efficient modern single-aisle aircraft such as the Airbus A320neo. Next item — so this is fresh material, and we're going to attempt to give you some perspective here regarding what's happening with the commercial aerospace, commercial aviation market. The domestic commercial aviation activity was coming along nicely in all major markets, but the Delta variant negatively impacted recovery in August and September. The passenger traffic down in August and probably September as well. September, as we fully reported, but that's the expectation; so — and the China domestic aviation market is probably impacted the most of major markets based upon the Delta variant outbreak in China; but the U.S. domestic aviation market as well as other major markets have also been negatively impacted by the Delta variant. The full U.S. domestic aviation recovery, meaning back to pre-COVID, I suppose that's what we mean by that, which have been predicted to occur in the first quarter of next year or even earlier, maybe the fourth quarter this year, maybe pushed to the right to some extent by the Delta variant. My feeling is a very minor amount. That's my feel; and let's go on to Slide 15, maybe we can talk about this more, why will it be a minor amount, if at all. Could this short-term disruption hurt plane purchases from the big commercial aircraft builders? Honestly, I’m not sure whether you operate an airline, but a lot of it comes down to this: the airline industry requires planning far ahead. You don’t simply place an order for an aircraft and complete the purchase within 14 days. So if passenger traffic figures suffer a setback lasting 2 or 3 weeks — pardon me, 2 or 3 months — and you are in charge of an airline, are you truly going to alter your ordering habits, delay deliveries, and scrap orders? We aren’t discussing the early days of the pandemic, when there was enormous uncertainty about virtually everything. The current circumstances are quite different. My view is that if you run an airline and decide to defer or cancel orders in a situation like this, you’re likely in the wrong line of work and probably ought not to be leading an airline. Would a major commercial aircraft producer, Boeing or Airbus, alter or modify its production timetable because of this short-term disruption? That would shock me. If they actually did so, I’d be extremely surprised. In any case, we haven’t observed any sign of that within our own operations. Will the Delta variant be declining by the close of November, as some experts have forecast? I mean, people already say it’s declining. Many are saying that, and there’s apparently plenty of data backing it up. Additionally, other nations encountered the Delta variant earlier than we did, such as India and, I believe, the U.K.; we examine their trends. So there’s considerable anticipation that the Delta variant is gradually fading. And by the close of November, perhaps even by the close of October, we’ll see it fade even further. So my sense is that yes, it did impact passenger traffic, say during, let’s say, August and September. But my sense is also that it simply won’t affect our commercial aerospace business. Global commercial aviation has begun recovering somewhat, driven by some easing of travel restrictions and higher vaccination rates, yet it still trails domestic aviation recoveries considerably. Global commercial aviation is still anticipated to require a number of years to typically recover. Full recovery means reaching a pre-COVID level. I don’t know, perhaps 3 or 4 years, based on what people think. Let’s move to Slide 16. Because single-aisle commercial aircraft are built to serve domestic aviation markets along with shorter-range international aviation markets, Park holds the view that single-aisle is where to be in commercial aviation, at least right now. Yes, we believe we’re positioned correctly, since single-aisle means the A320 family. That’s essentially the — probably, I don’t know, aircraft of the decade, perhaps for several decades, COMAC919; all of those are single aisles. Three intriguing questions. How will GE Aviation’s RISE engine development shape the commercial aircraft industry going forward? Have you heard of this GE Aviation RISE engine? Actually, that's not right—it isn't GE Aviation at all. It's CFM, the joint venture involving GE Aviation and Safran. So that's simply incorrect. But people—will Boeing build a new single-aisle plane to go up against the A321XLR, which Airbus intends to bring in during 2023? Final one, will COMAC919 receive certification in China prior to the close of this year? We won't dive into those points since we simply lack the time. A proper discussion of those points could take 15, 20 minutes. I just want to mention them since they might matter regarding what occurs down the road in commercial aviation markets and the industry. Let's move to 17. Here's a slide you've probably seen nearly every quarter, with a few small tweaks; we won't go through it, just to save time, other than the initial couple of items. So just the fundamentals here; we have a firm pricing LTA. It's a requirements contract spanning 2019 through 2029, with Middle River Aerostructure Systems, MRAS, a subsidiary of ST Engineering Aerospace. So what's this all about?

Brian Shore

executive
#5

At the time this contract was signed, MRAS operated as a GE Aviation subsidiary, and roughly 3 years back, it got divested to ST Engineering Aerospace. That explains why every program we participate in via MRAS, GE Aviation, or CFM-type programs carries that GE Aviation connection dating to before GE Aviation divested MRAS to ST Engineering. As we've already mentioned, in fact, construction has wrapped up; our arrangement with GE Aviation and MRAS was that the moment they put their signature on this LTA, we would move forward and construct a factory. Naturally, we proceeded with only a handshake in place, yet we will honor what we committed to. So let's skip the remaining items here. If anything needs clarification, feel free to reach out. That iconic Boeing 747 with eight engine nacelles — this image is one I really like, mainly because of that person standing in the background, which really shows just how massive those nacelles are. All of this involves Park materials going into those nacelles, so there's a lot of substance here. Moving to slide 18. Here's where we stand on GE Aviation jet engine programs. Let's walk through the latest. This will take some time. We'll go through it as quickly as we can. Starting with the A320neo family of aircraft — this one is by far the largest. These aircraft use LEAP-1A engines. It's rising steeply. We covered this in the previous investor presentation, but let's go over it quickly. Airbus put out a news release dated May 27. In it, the company verifies that its A320 family will be built at an average of 45 units per month during Q4. That basically means the fourth quarter of this year, which is right around the corner. Worth pointing out: throughout the pandemic, that figure stayed flat at 40. Forty was the number they held to. Airbus is now reaching out to its suppliers, asking them to get ready for what's ahead by locking in a solid rate of 64 units by the second quarter of 2023 — 64, which represents a big step up. Because the market keeps bouncing back, Airbus additionally wants suppliers to make possible a scenario of 70 units by Q1 of 2024. Looking further out, the company is putting money into chances to reach rates as high as 75 by 2025. Here's an image of the A320neo — the figures involved are enormous. Moving on to Slide 19 now. By the close of August 2021, CFM — that means the LEAP-1A powerplant — held 60.25% of the firm orders placed for the A320neo aircraft family. That data comes from Aero Engine News, which serves as something like the definitive reference in the commercial aircraft engine world. Two engines are certified for the A320 aircraft family program: the CFM LEAP-1A on one side, and Pratt on the other. What we're discussing here is the portion belonging to the CFM LEAP-1A engine. The CFM LEAP-1A is our program — we have no involvement in the Pratt program. Okay, so that works in our favor with CFM. As for Pratt, we're not part of that supply chain. Let's pick up where we left off. The assumption here is a 60.25% share for CFM, and that's based on how things stand right now. We're not trying to forecast what might happen later on. We can't know what's coming, but this is where the share sits today. And this backlog is massive — we're talking thousands of planes and thousands of engines on order, not just a few. When you look at 75 A320neo family aircraft per month — the number we went over on the previous slide — that represents a big increase over what our long-term forecast projected in terms of units. Let's get into the details on that. What sets it apart? From the long-term projection MRAS gave us, if you take the A320 units — sorry, A320 — and do the math by working backward, you land at 57 planes each month, 57 A320 planes each month. Suppose we take that share — let's say it's 60.25% per share, just as an example — and then make some other computations, 57 against 75, that's — it's quite a bit larger. Like I said, my feeling is it exceeds a 30% bump relative to what we forecast. Our forecast tops out at that number, using the 57 figure for 2024. We still haven't gotten to that number; in the forecast we're not there yet. Our forecast tops out during 2024, and it bakes in a rate of 57. Airbus, though, has stated an ambition of getting to 75. That is an enormous figure. For Park, the space between those two numbers — 57 versus 75 — works out to millions upon millions of dollars every year. Whether it truly comes to pass, I cannot tell you, but I'd ask you to keep it in mind, because in my opinion it matters a great deal. There's also some strain right now involving Airbus suppliers, engine suppliers in particular. Friction has emerged around the ambitious planned ramp up of the A320neo aircraft family. Airframe and engine manufacturers have clashed before about production rates, since the economics that motivate aircraft makers and engine makers are not the same. How should we interpret this? Plane builders make their revenue from the sale of aircraft. Engine makers, by contrast, generate their revenue through engine servicing rather than through engine sales. That friction has been around for ages. It's nothing new. So the key takeaway is this: engine producers aren't particularly keen on seeing airframers introduce a next-generation aircraft, since they'd prefer to continue maintaining older powerplants on older jets. Through the CF56 engine, CFM likewise delivers into the older 737 and the older A320, and they're looking to squeeze additional service life out of those powerplants. So imagine everyone suddenly decides, hold on, we're about to significantly increase how many neos we build. What follows is that the older planes get taken out of service, and once that happens, you stop collecting the money and the profit tied to maintaining those engines, since the aircraft themselves are gone. See how that works? Anyone working in commercial aerospace really needs to grasp this point. Now, turning to Slide 20. Later, on July 29, 2021, the head of Airbus expressed frustration that some of its partners — meaning its suppliers — were resisting the production increase. He added that the orders still on their books total more than 6,000 planes within the A320neo family. If you assume a pace of 40 — and that's where things sat, as far as I know, up until this quarter — that works out to 15 years' worth of output. Bump it to 60, and you're looking at 10 years. That's a really long horizon. No customer is going to sit around for that long. We've got to move — and on that point, regarding the SIC, I think the quote got garbled. Even so, the math just doesn't work. My read is he was referring to something north of 60; it seems pretty evident he said above 60, because if not, the numbers wouldn't line up whatsoever. He added that we expect the supply chain to scale up much faster. And that's the situation. There's a bit of tension here, like I mentioned. This aggressive ramp up rests in part on how well the A321neo has done, and the CEO also remarked on July 29 that Airbus aims to be capable of a production share of A320neos substantially above 50%, reaching a share of 60%.

Brian Shore

executive
#6

So, you're asking for my take on what's going to happen. That's just my view, and I could be mistaken. My belief is that if Airbus is able to sell these planes, then GE or CFM will provide the engines. Why do I believe that? All right, since they share this program with Pratt, if CFM refuses to budge and says, well, we're not going to deliver that many engines to support the aircraft you want to build, Airbus, Airbus will respond, "Okay, fine. I'll turn to Pratt, maybe Pratt can assist us." In that scenario, what becomes of CFM? Servicing new engines brings in zero revenue for them, meaning none of those new engines get sold under these arrangements. As for the older aircraft, the legacy fleet, replacement will happen no matter what, yet it'll come through agreements constructed around Pratt powerplants. So either path leaves you worse off. That's how I see it — I could be mistaken — but my sense is that once everything wraps up, there will be a great deal of negotiation going back and forth. Should Airbus manage to move these planes, GE or Safran — GE, Safran, possibly CFM will get behind it. Airbus likewise announced not long ago that it is resuming construction on a fresh final assembly line over in Toulouse meant for the A321neo. So maybe they're actually backing up their words with cash — not just talking about raising rates, but putting money in. Now let's turn to Slide 21. The A321XLR — we've been talking about this one for several quarters; it should start flying commercially in 2023, and it's probably a big reason behind that bold forecast for the A320neo family. It's considered a version of the A321neo. They've already got over 450 orders. Does this plane change the game? That's possible, I'd say probably so, since given that capability of over 5,000 miles plus room for 225-plus passengers, it genuinely takes the place of certain widebody aircraft on some shorter long-haul international services, and does so far more cheaply. Picture flying from North America over to Europe — you could board a widebody, or you could board the XLR, and for the carrier operating the XLR the expense is considerably reduced, while the passenger count it offers remains pretty substantial. So we'll see how it plays out. One big thing to watch is whether the market for single-aisle jets with over 5,000 statute miles of range and 225 seats gets handed over to the Airbus A321XLR — meaning what kind of plane Boeing will build to go head-to-head with it. Then, on the A320neo family overall, August brought 95 orders, which is a decent showing. Turning to Slide 22, we're still on GE Aviation programs, and here it's another CFM effort — the COMAC919. We've discussed it a lot already. There's an interesting wrinkle: recent reports said U.S. export controls were holding back the 919's development. However, COMAC pushed back immediately, saying that wasn't accurate — the export restrictions hadn't made much of a difference — and they reaffirmed their commitment to completing certification by the end of this year. According to them, the aircraft will receive its certification during this year, and that certification would come from China, covering deliveries inside China. Even with that, they're holding their ground. So time will tell how this turns out. Maybe during our next conference call, we'll learn what really occurred. Anyway — this might end up being a major program for Park; so we'll keep an eye on how it develops, but that's where things stand. Slide 23. We'll go through this quickly. Production of the Global 7500, fitted with Passport 20 engines, is increasing. For this aircraft as well, we intend to obtain certification of our lightning strike material during the coming year, which is a favorable development; beyond that, these represent high-margin offerings for our company. Turning to the COMAC ARJ-21, a regional jet, its output is also rising. The final item is the 747; each quarter we bring this up, and we possess numerous photographs of the 747. For reasons we've likely covered before, it carries a certain nostalgia for us; however, as has been indicated, the 747 program will be discontinued next year. That's going to be genuinely unfortunate on our end. What I mean is, for that group we'd need to reach a double-digit figure. Still, I should point out that this represents under $2 million in revenue for us. So even though we've talked it up quite a bit, it comes in below $2 million. On a yearly basis, that program brings in under $2 million for us. Slide 25. All right. Let's take a brief look at this commercial aerospace sector that's in meltdown mode — pardon me, a review of the industry meltdown. How about we simply jump ahead to the conclusion. Every one of those items is available for you to look at, and we're familiar with all of them. In the commercial aviation sector—the commercial aircraft sector—what happened was genuinely catastrophic. Nearly every piece of coverage concerning that industry at the start of the pandemic carried a strongly negative tone. Forecasts and commentary from aviation analysts said a rebound wouldn't arrive for a long stretch of years, or perhaps would never arrive at all—the end-of-days scenario, extremely grim material, extremely grim material, that people were both discussing and accepting as true. Turning to Slide 26. Because of those end-of-days mindsets, businesses throughout the commercial aircraft supply chain let thousands of employees go. They shifted into a bunker-survival posture, with output cut back sharply or stopped altogether. Planning for an upturn, figuring out what to do when it arrived — that simply wasn't on the radar for a lot of businesses in the supply chain, likely the majority. Staying alive consumed all their attention, because everyone assumed any rebound was so distant that contemplating it made no sense. Then, to everyone's astonishment, people grew weary of restrictions. As soon as the vaccines arrived, exactly as promised, individuals were eager to head back up into the sky — to travel by air once more — and they gravitated toward domestic routes, showing up in huge numbers. Don't forget, those aircraft had been operating empty. All at once, a fresh appetite emerged among the public to get on planes. That marks quite a significant shift. Consequently, carriers were ready to purchase aircraft once more. When the pandemic first hit, carriers simply had no interest in planes. The level of uncertainty regarding what lay ahead was enormous; yet today they are looking to acquire planes, and not just a few. And someone has to manufacture the thousands upon thousands of parts that go into those planes — the very planes the carriers now wish to purchase. Let's move along to Slide 27. However, the commercial aircraft supply chain had been caught completely off guard, stuck in a survival-in-the-bunker mentality, and lacked the frame of mind to swiftly scale back up and satisfy the returning demand, and on top of that, because the supply chain firms had let go of such an enormous number of workers, they simply lacked the personnel to support the industry's ramp up in any case. Those firms attempted to rehire the workers they had dismissed. Yet, as has been extensively covered, doing so proved far from simple, and on top of that, the government was handing out money to people for staying away from their jobs. So that was no help whatsoever.

Brian Shore

executive
#7

So what did all that produce? A whipsaw: the supply chain serving commercial aircraft got caught off guard, and now it's struggling—sometimes severely—to keep up with demand that came back stronger than anyone expected as the commercial aircraft industry recovers. That's a whipsaw, basically, since everybody had been hunkering down just to survive, and then suddenly we had to ramp right back up, and the reaction has been, I'd call it, tepid. That's the dynamic in today's commercial aircraft supply chain—a tough one. Slide 26—but at Park, we weren't buying every bit of that doom and gloom. We weren't buying the idea that the end was upon us. Here's what we said. This is interesting. On May 14, 2020—when the pandemic began, when the crisis began, a time ruled entirely by confusion, uncertainty and fear—this is what we stated. Take a look at it. I'm not going to read it out loud, but work through it; it's really quite interesting. We weren't going into the bunker; we were moving forward. And guess what? We were basically on our own. I can't remember many folks signing up for what—I'm not sure what you'd call the mission we're on. But that final item, here's one for you: we believed aviation's glory days were returning, and we plan to be a part of it. Now let's go to Slide 29. At Park, the timing of a commercial aircraft rebound was uncertain to us, yet our conviction that one would occur remained firm. We aimed to be prepared and involved when that happened—walking away from that sector is not our plan. Honestly, our stance is the reverse of that. So we put structures in place. As previously mentioned regarding MRAS, we maintain floor-level monthly output to sustain essential production capacity, which lets Park retain the capability to increase manufacturing whenever required. This point is extremely important. If we had fallen below those thresholds, we would have faced a serious issue, since we would lack the necessary scale to increase production again, and that would create difficulties for us—significant ones; for MRAS, significant ones; and for certain aircraft manufacturers, significant ones; and although workforce reductions were common and extensive—we were unaware of anyone who had not released sufficient staff in commercial aerospace—we did not release anyone, none of our employees, throughout the most challenging and apparently bleak periods in commercial aerospace; it turns out that deciding to retain all our staff was truly vital for Park, because had we let people go, we would be in a terrible position when attempting to scale back up; it would be extremely, extremely challenging for us. Slide 30. Turning to GE Aviation jet engine programs — both the Park ones and those where Park is heavily involved in the ramp — apologies, the programs Park is focused on are scaling quickly, and that climb looks aggressive. To give you a sense of it, we went over this with you during the prior quarter: check out Q3 of 2021, $1.8 million. Then jump ahead 2 quarters to Q1 2022, $7 million. That works out to a 4x jump across 2 quarters — 4x within the quarter. For a manufacturing business, that is extremely, extremely meaningful. We aren't in the business of just selling things. We have to build it. We have to source the raw material. Getting it built is one thing. Testing has to happen, and then we've got to move it out the door — that's an enormous lift, an enormous lift. For context, when you look at the first two quarters of fiscal '22, they're already tracking at pre-Covid numbers — already, in Q1 and Q2; and there's still a considerable distance to go on the ramp — a considerable distance still ahead. Now, an important thing to ask: as this steep ramp unfolds, how well is the commercial aerospace manufacturing supply chain coping? My grade would likely be a C minus — not so great. It's a daily challenge that we contend with. Slide 31. When it comes to that steep ramp up, how is Park managing the GE Aviation program? It all comes down to our people. I'm going to try to move even quicker here since I realize we're running really long. Our headcount right now sits at 114. Last quarter we were at 105. So we're bringing our headcount up somewhat, but it remains a challenge. We — there are still quite a few folks we're looking to bring on. 2 steps forward and 1 step back when it comes to the hiring process. So Park's people rose to the occasion once again; that's what Park people do to make sure everything got finished in Q2. We've already covered the challenges that needed to be overcome, so I won't revisit those. Once more, we should be grateful for the customer flexibility program at Park. I won't go into details, but as we note almost every quarter, this initiative has proven absolutely vital for Park, especially when you're trying to scale operations back up. Turning to Slide 32, how is Park managing the continued steep ramp-up of the GE Aviation program? Beyond our team — we cannot praise our team enough — we should be thankful for Park's outstanding team. Without them, no job would get finished. Park is lucky and blessed to have such outstanding team members, and each Park employee got a $150 bonus in recognition of their commitment and exceptional efforts in the second quarter, which was well earned and well deserved. We experienced quite a bit of change, with fewer problems in the supply chain, less trouble with freight, and fewer COVID quarantine complications. Planning logistics was a major hurdle, yet thanks to hard work, loyalty, and dedication, we still hit our Q2 goals. Moving to Slide 33—I'll go through this fast. The figures are right there for you to see, so there's no need for much commentary. My only point is that this forecast comes from GE, naturally. Comparing one quarter to another is difficult, because the way inventory gets handled allows items to move across quarters—some get delayed, others get moved up—which makes it even harder. The way I see it, a major unknown is the timing of when the figures will climb enough to match the projections, particularly the targets Airbus has been putting out that we discussed earlier in this presentation, since a gap exists right now; our output is nowhere close to those volumes. So eventually, either Airbus will lower those figures or the figures will need to rise. It can't work both ways. So something has to give somewhere. Will it happen in Q4? Will Q4 be when it begins? I can't say—it's genuinely hard to say. Should any hunch come to me, you'd be the first to hear about it. As things stand, though, all I can do is point out that this matter remains unresolved, and every one of us understands that a breaking point is coming. A shift is inevitable. The picture could change completely, however, if Airbus were to reverse course and declare, "Wait a moment — we've had second thoughts, and we're lowering our figures once more, back to 55 or 57 each month."

Brian Shore

executive
#8

However, if Airbus doesn't pull back significantly—and I mean a substantial retreat—then something will have to change, since our current operating level is nowhere near sufficient to sustain that program. That also applies to the other programs we mentioned that are scaling up. Turning to Slide 34, the figures there are quite clear, so I won't drill into them at length. I'll simply note that for Q3, we're expecting roughly $400,000 in ablative sales, which is positive. For Q4, however, we anticipate around $2.5 million from sales of the critical essential component—margins on that aren't great—plus approximately $1 million from ablative materials sales, which carry comparatively strong margins. Same question applies. If you'd like to revisit those factors we discussed concerning Q2 on Slide 5, please do, since they remain relevant for Q3 and Q4. Those factors haven't disappeared; we keep bringing them up. Now the same question regarding the GE programs, especially Airbus. When will our output align with what they need? Right now, it doesn't align. Eventually, something has to give, as I said. Either they lower their figures, or we have to raise ours. When exactly that occurs? I can't say. But it's looming. It's sort of hanging over us. And we're prepared, we're set to move. Naturally, we face supply chain difficulties that won't go away, but Park stands ready. As I mentioned, it's fortunate we didn't halt that expansion—we had only slowed it—which matters greatly for Park. Moving to Slides 35 and 36; these are the final ones, so I'll move through them quickly, though they matter to us, shifting topics considerably here. What's most important at Park? We feel profound sorrow over what's happening in our world right now. We hear that people who work for a living don't count. We hear they're disposable. We hear they should be given up for some vaguely defined or undefined greater good. To us, that's truly heartbreaking. Yet we recognize we're a small company, and our words or beliefs don't carry much weight on these bigger matters. What does carry weight is what we say and think regarding our own people; so at Park, our people aren't disposable; at Park, our people count above all; at Park, our people are everything; at Park, our people are our family. We don't abandon family. Our people won't be deserted. Our people won't be given up; at Park, our people are treasured; at Park, we're the luckiest when it comes to our people. I say this often, but that's because I truly mean it deeply. Let's move to the slide—our final one, number 36. At Park, the folks on our team earn their living by working—that's simply what they do. Here at Park, our employees generate profits for the owners; that's their focus; it's something every one of our people is dedicated to. I mean every single one of them. Throughout this pandemic and economic crisis, we turned a profit each quarter. Did everyone manage that? I doubt it. Most businesses in the aerospace supply chain, I suspect, likely didn't. But our team pulling that off wasn't simple during the whole pandemic and the economic downturn. Our employees accomplished it, earning money for owners each quarter. That's their way. It's no coincidence, not fortune. It stems from deep commitment and dedication, deep commitment and dedication; so I just wanted to share that. Park is an odd and distinctive company, full of amazing and remarkable individuals. At Park, we differ from the rest. At Park, we're in it to win. So we consistently highlight—at least over the past several quarters—a photo of one of our teams; in this instance, we're showcasing 2 teams, the customer service and purchasing planning groups. Going from left to right: Jordan, Teresa, Jonathan, Chris, Dakota, Sara, and Elaine. These individuals, everything we've discussed in this presentation, they're on the front lines dealing with all the supply chain challenges, freight problems, international freight problems, balancing customer orders, quarantine efforts, production planning, and the unpredictable circumstances because typically, you'd want some predictability in production planning, you don't want changes weekly, daily; but these issues that kept arising, like COVID quarantine, are impossible to foresee. So plenty of juggling, lots of shifting schedules—a major task, sheer effort was likely the theme of the quarter for these folks. Yet this group ensured we hit our targets for Q2. They constantly find ways to get past the hurdles. So thank you so much. Apologies for taking so long. I was hurrying a lot and probably made it tough for some of you to keep up with these accounts so rapidly and perhaps glossed over details. But operator, our presentation is now complete; so if anyone has questions, we'd be glad to answer them.

Brian Glenn

analyst
#9

I've got 2 questions for you. First off — thanks, obviously, for the run-through, like always. Question one concerns the supply chain. You touched on that somewhat. Could it be that you folks, who are more than sufficiently ready for a ramp, end up constrained by everyone else in the industry? I'm aware Airbus has several thousand suppliers, at minimum, for that program. I'm aware that not every one is sole source, so there's a bit of wiggle room to switch. But is that an actual danger ahead that you'd call potentially material? Then question two — I'm aware you haven't established guidance yet or reinstated it. But going back to pre-COVID, I'm aware that during COVID, you folks did work on certain military programs and there were some extra efforts in that area. You mentioned the Lightning Strike material through NORDAM; that's on the Passport 20, and that appears to be a new program that might occur, or that is occurring. So setting commercial aside, thinking long term without discussing figures, is there sort of a net addition when it comes to programs you might be involved in, or that you are involved in, compared with going back to 2019, when that forecast of yours was in place?

Brian Shore

executive
#10

All right. Thanks; so let's take a look, question one is supply chain and whether that will pose a problem for us as we ramp up. As you — I suppose, as you at minimum hinted, we hold sole source status on these — every GE Aviation program, among them the Airbus A320 family programs. So I believe the chance of us being swapped out doesn't exist on the programs already in place, if that's your point. But there definitely is a significant hurdle for us, which means our supply chain. Since we're ramping up and also running trials and all the rest. So there's even more labor there, so it's a significant hurdle. And when will this sort of thing stabilize? I have no idea. I mean, there's plenty of coverage about it. When will the suppliers sort of catch up and sort of regain their cadence? I have no idea, perhaps near the end of the year, that's what I hear in some coverage; though naturally, it's on a case-by-case basis. We have 3 or 4 key suppliers that we rely on for these GE Aviation programs. And we truly need to examine every one separately. Certain ones are performing well. Certain ones are having difficulty. And I can't think of another way to put my answer except that it's simply a significant effort and at times a brute force effort. But then again, looking at it from the opposite angle, I'd say, our folks are incredibly resolute and deeply dedicated to discovering methods that get things to function, and largely we've managed to accomplish exactly that. So honestly, Brian, I can't tell whether my response fully addressed what you asked. Is that the sort of detail you were hoping for? Or were you actually after something different with that question?

Brian Glenn

analyst
#11

Appreciate that. Yeah, I realize you folks are the only provider when it comes to the GE program. Yeah, it was really about personnel — even vendors beyond your own sector, correct? They feed into the 320, and assuming this lies completely beyond your influence, right, and it's a choke point for everyone.

Brian Shore

executive
#12

Correct. Alright. I follow that question; it's actually a strong one since, suppose we had everything in order, our vendor is fine. Yet should Airbus fail to obtain other critical parts, they won't be able to build the planes, and that hits us. I see your angle. Well, that's a genuinely good question. I can't predict that one. My sense is — purely my sense — it's going to be rough and chaotic for some time. My sense is eventually, the supply chain, a few of these enormous firms that aren't truly nimble, that don't shift fast, eventually, will get up to speed and sort of adjust to the fresh cadence, the fresh rates and all the rest. When exactly that happens is a fair question. I have no idea. But I figure likely, I'll simply offer my — this is entirely my guesswork. My sense is near the close of the year, we'll begin to sense that matters are improving somewhat, not fixed, not that there'd be zero problems. And I'm not only referring to our own supply chain, I'm referring to what you're inquiring about, the supply chain behind these planes, which as you mentioned, thousands upon thousands of distinct parts are needed to build these planes. You're likely not shocked to hear this, yet Airbus would maintain they possess a huge operation handling supply chain management, and they devote considerable time with vendors, they attempt to pinpoint where dangers lie and attempt to concentrate on those. I'm certain it doesn't shock you that any decent OEM would behave that way; so I don't know whether that's useful, but I don't wish to as what more I can do. Yes. Now onto the following question. We haven't put out our long-range projection again yet, Brian. Though perhaps during the third quarter, we'll attempt it. We're somewhat uneasy at present since there's considerable ambiguity around the matters we discussed across the presentation; but definitely, yes, the initiatives we've been pursuing and building over the past 1.5 years since the pandemic began, those aren't merely fleeting items just across the factory. Those are items we hope and anticipate will deliver long-range effects for us; now within aerospace, I just want to mention, you must do this since certain initiatives you operate, they will disappear; so even if they merely roughly break even or hold identical levels, you must keep securing new initiatives. Our goal isn't simply to hold our sales levels where they are — it's to grow them. Take Lightning Strike, for instance; it's a commercial success story. Our hope is that we can also land Lightning Strike on the ARJ-21, the regional jet from COMAC. Should we succeed in getting Lightning Strike onto that aircraft, we'd then have every one of these platforms carrying it — a clean sweep. Lightning Strike delivers revenue that's fairly substantial, and the margins are pretty attractive too. It's something we genuinely enjoy selling. Beyond that, there are numerous military programs — we discuss them each quarter, and we show a small graphic. A few are minor; a few might not be minor at all. The key is getting your foot in the door, starting out, handling a modest amount of content, then working to expand into bigger and bigger content. We displayed a graphic of GBSD. GBSD represents a truly major opportunity, and SpaceX as well. Those programs hadn't been highlighted by us previously, so that's a positive. We're winning positions on them, and halting isn't in our plans. After we penetrate, our aim is to keep doing more and more and more. For our company, it's always beneficial to engage with the customer in some way; we get to showcase what we can do, demonstrate our service, our responsiveness, our program support. It's far harder to simply say, put us on your program since we excel at all of this — because everyone makes that claim. Yet once we're actually given the opportunity to begin working alongside a customer, that's when we can prove how we believe we stand apart from other suppliers — that is, our competitors.

Brad Hathaway

analyst
#13

I appreciate you taking the time, and I appreciate all the specifics provided during this call. There was one question: earlier on this call, you brought up that at first, the new plant was primarily intended as sort of a backup capability, yet now it's genuinely needed. Could you frame it in a sort of broad-stroke figure, I suppose — the overall kind of revenue capability you'd have once that new plant is up and running?

Brian Shore

executive
#14

We've discussed this previously. I believe we stated it's roughly $60 million of capacity, of added capacity. However, keep in mind — you might recall, at least we haven't gone over this for a few quarters, I believe; but inside the factory, there's a large space, and we're discussing back, it's not a small room, an enormous space reserved for an additional line, which could be a hot melt line or a solution line. Thus, if we determine we require additional capacity, it would be very simple to install that there. We don't need to construct a brand-new factory; the factory already exists, the equipment is already engineered, we merely purchased the equipment; therefore, it would be simple to install an additional line in that spot. So at that stage it could be scaled up to far beyond that figure. So what I was expressing, I simply want to make clear, is that the factory was initially consented to alongside GE Aviation and MRAS, as we've completed in the factory. Why is that so? We just discussed being sole-sourced; qualifying a composite material supplier on these major commercial aircraft programs takes 3 years — 3 years. So it's somewhat a frightening notion. What occurs if something were to happen to one of our factories instead? I mean, it's like a truly frightening notion of — they've had this conversation with individuals previously, and it's sort of — the room becomes very silent. So they requested, quite reasonably, that we build onto the factory, which we did. If you examine the small photograph of the new factory, it's in fact a distinct building connected via a passageway for transporting people and material, featuring a fire door on each side. So it's sort of the ideal combination. We operate it as 1 factory, yet it's in fact 2 factories that are entirely redundant. So if something occurs to 1 factory or even 1 line, the other line, the other factory, remains accessible. However, that was the initial idea, yet since business has expanded so greatly, and that's growing stronger and stronger, it's no longer an issue of redundancy, which is truly essential in aerospace when you're sole-sourced on something. It's also an issue of capacity. What I'm getting at is that it's a very good thing we acted the way we did, since we're beginning right now — hold on a second, if we had a capacity issue at this point, we'd be in serious trouble, because it would take us three years to — roughly three years back, construct a plant, complete all the design work, assuming we were starting from scratch. After that, the equipment has to go through testing, we need new machines approved by the vendor, and then there's qualification, which, even though it's just a plant qualification rather than a material qualification, still requires a substantial amount of time. So my estimate is around a three-year window. But in that case, we'd be facing a genuine crisis. It would be past the point of no return, and in my view, we wouldn't have sufficient capacity.

Brad Hathaway

analyst
#15

Understood. Fantastic. That's useful. Is there additional insight you could provide regarding the M&A side, and anything else you're observing out there? I'd really like to hear your perspective on that.

Brian Shore

executive
#16

Absolutely, the M&A side. We keep working in that space, the strategic space we pinpointed. I believe we may have brought it up, but these goods get used by our clients to produce composite structures. They aren't composite materials, but other items get used — other goods that get used to produce composite structures. That's one space we've stayed focused on. We've likely gotten in touch with, well, Matt, I'm not sure whether you have the count, but 12 or more of these businesses, and we keep reaching out to additional businesses, and we keep attempting. That's something we feel genuinely positive about since we believe it makes so much sense for us to operate in that space. The difficulty is locating the proper opportunity because clearly whenever you contact somebody, it's thank you very much for that sale, that sort of thing. These aren't auctions where certain things are for sale, we saw bankers listing it for sale. So it's somewhat harder from that angle. There are a few businesses we're sort of observing, monitoring to see how they're performing. They could be public and we're watching how they're performing and sort of perhaps the timing isn't quite right at this point. We're considering them. And then there's this other space we discussed, which is more of a sort of joint investment alongside very large OEMs and new aircraft programs. We've had conversations. We've had initial conversations with one of these large ones — we've reached out to 2 of them; and that first conversation is at the start of the conversation, yet it was with very senior people and I sensed there was genuine interest in the report. They know us extremely well too; it isn't like, who are you. So we're optimistic. We're optimistic that will be a solid avenue for our investment and truly a fantastic opportunity for Park's future.

Brian Shore

executive
#17

Appreciate it, operator. Thanks to all of you for tuning in. My apologies for running over. Whenever we attempt to — well, at least whenever I attempt to keep things a bit tighter, it doesn't — I haven't had much luck with that. Enjoy the rest of your day. Matt and I are around. Reach out whenever you like, and we'd be glad to speak with you. All right. Have a good one. Thanks.

Operator

operator
#18

This concludes the program. You may now disconnect. Everyone, have a great day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Park Aerospace Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Park Aerospace Corp. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Park Aerospace Corp. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.