Perseus Mining Limited (PRU) Earnings Call Transcript & Summary
January 15, 2020
Earnings Call Speaker Segments
Jeff Quartermaine
executiveThanks so much, and welcome to this conference call about Perseus Mining's December 2019 quarterly report, which we released to the market this morning. If you haven't had a chance to read the document yet, allow me to give you a quick summary. First off, during this quarter, Perseus's two operations at Edikan and Sissingué kept delivering very strongly and in line with our plans, producing 69,155 ounces of gold at a weighted average production cost of $843 per ounce and a weighted average all-in sustaining cost of $962 per ounce — those are the numbers. Our average cash margin on each ounce of gold produced came to $453 per ounce, which beat our stated strategic target of $400 an ounce. Production was roughly 5% higher this quarter compared with the previous quarter, and all-in sustaining costs were a touch higher than the previous quarter, but in context that wasn't a bad result, and I'll address this point a bit further in the presentation. On a half-year basis, we produced 134,980 ounces of gold at an all-in sustaining cost of $942 per ounce. This compared very favorably with our market guidance for the period of 120,000 to 140,000 ounces at $850-$1,000 an ounce, and it positioned us very well to deliver on our full-year guidance of 275,000 to 295,000 ounces for the year at a cost somewhere between $850 and $950 an ounce.
Jeff Quartermaine
executiveCarrying out our plan to create value by developing mineral resources went forward as scheduled. Yaouré, which is our third gold mine, now stands at roughly 33% complete; it remains on schedule and within budget, and our stretch goal of first gold pour in December 2020 looks clearly achievable for us at this stage. I should mention as well that in the quarter we fulfilled another important commitment tied to Yaouré — signing a mining convention with the government of Côte d'Ivoire. That agreement guarantees fiscal stability across the mine's life, making it a highly significant milestone for this project. Lastly, Perseus once again sustained a strong balance sheet thanks to robust cash flows and careful financial management over the quarter. Given the cash margin I mentioned earlier — $453 an ounce — we produced notional operating cash flow of $31.3 million, roughly 5% above the preceding quarter, the September quarter, and after accounting for $72 million invested in developing Yaouré this quarter, tax paid to the government of Ghana, exploration funding, and keeping our Perth corporate office running, our cash and bullion balance at the end of December came to $81 million, or $80.6 million to be precise, which leaves us with a net cash position of $31 million after our $50 million of debt drawn under the corporate cash advance facility.
Jeff Quartermaine
executiveSo to give you some context on that, of the $265 million required to develop the Yaouré gold mine, we've spent $99 million up to now, which leaves $166 million still to be paid. With $81 million in cash on hand and $100 million of undrawn debt available to us, the cost to complete development is more than fully covered, and that's before even factoring in the cash flow our operations are generating. In the last calendar year by itself, we generated net cash flow of roughly $110 million, U.S. dollars, and I expect that from now until the end of this calendar year, when construction of Yaouré is scheduled for completion, we'll have generated at least that amount once more, and probably considerably more given our production forecast. Financially, we're in a very strong position. Our operations are running well and on plan. When it comes to gold production and cash flow, our growth profile is second to none among our peers. And it has been another satisfying quarter for the company, both operationally and financially, and after a long wait by some of our shareholders, our success is starting to be reflected in our share price, which, as you'd know, has performed fairly strongly relative to peers both during the December quarter and into this new year.
Jeff Quartermaine
executiveThat covers the December quarter at a high level, but let's dig into more detail on what happened in each part of the business. On the operations side, as I said, we produced 69,155 ounces of gold across both operations. Edikan accounted for 48,250 ounces, and the remaining 20,905 came from Sissingué. That works out to roughly a 70/30 split between the two operations. It's 5% higher than the prior quarter and consistent with what we expected internally. Looking more closely at production, Edikan was well above our targets this quarter, while Sissingué fell a little short of internal targets, mainly because of the revised mining schedule put in place earlier in the year to successfully mitigate wet season risk, which meant we mined some lower-grade material in the recent quarter. Interestingly, this was the opposite of the previous quarter, the September quarter, when Sissingué outperformed and Edikan fell a little short of targets. Clearly, this demonstrates the very distinct benefits of being a multi-mine operation. Last quarter at Edikan, so in the September quarter at Edikan, we set about addressing some challenges we had previously experienced in getting ore through our mill due to hardness of the material coming out of Esuajah North.
Jeff Quartermaine
executiveSo, how we achieved this was by bringing in new technology and software that gave us tighter control over material flows, along with enhancements to our blasting methods that improved material breakage at the Esuajah North pit. The benefit of this work — while we did see some improvement last quarter — really became clear this quarter, as throughput rates kept climbing. We hit 909 tonnes per hour versus 880 in the prior quarter, and we managed to hold our runtime and recoveries steady at the same time. Of course, it also helped that grade rose quarter on quarter, but the key takeaway is that gold production at Edikan climbed roughly 90% quarter on quarter, which was a very satisfying outcome. I should mention as well that the success of the initiatives we put in place at Edikan wasn't only reflected in stronger operating performance this quarter — the company also received a rather prestigious award for collaboration on the successful deployment of this new technology in the mine processing area at the International Mining and Resources Conference, IMARC, held in Melbourne late last year. So it was great for our team to get some external recognition for what has been an excellent effort.
Jeff Quartermaine
executiveActually, mechanical performance at both mines—runtimes, throughput rates, and recoveries—was solid in the quarter, and the Sissingué processing facility did extremely well on those measures too. What differed at Sissingué this quarter was that, as I mentioned earlier, we were mining the lower-grade portion of the ore body, and because of that, gold production at Sissingué fell roughly 4% quarter on quarter owing to the grade. We do expect things to swing back this quarter, however, once we begin mining higher-grade material in the main part of the ore body, and we're already starting to see some of that come through as we speak. Turning now to group all-in sustaining costs: our all-in sustaining costs for the group in the quarter came to $9.62 an ounce, roughly 4% above the prior period's cost. That comprised costs at Edikan of approximately $1,035 an ounce, more or less unchanged from the previous quarter. Costs at Sissingué rose to $793 an ounce versus $709, a function of both the number of ounces produced and a couple of other one-offs there, which we'll come to.
Jeff Quartermaine
executiveActually, at both Edikan and Sissingué, among other factors, this quarter we had to account for a range of government charges that pushed costs up somewhat. In Ghana, the costs concerned back payment of mineral rights fees going back several years — we were surprised to get a bill reaching quite far back — and in Côte d'Ivoire, we accounted for customs charges tied to importing mine equipment and spares very early in the mine's life. Neither of these items is likely to recur, and we would not expect them to weigh on costs in the future. As I said at the beginning of the call, our performance this quarter meant the December half-year was very strong compared with market guidance, and we have built a solid foundation for a good result in fiscal 2020. Our guidance for the June half-year remains unchanged, so we forecast gold production of 140,000 to 160,000 ounces, and we expect costs to decline into a range of $750-$950 an ounce. That is quite an improvement compared with the December half-year, but we are comfortable with the forecast because we can see strong grade improvement coming through at both Edikan and Sissingué, as I mentioned, and if we can sustain that very good mechanical performance we have seen for a number of quarters now at both mines, then we should position ourselves very well against that stated guidance range.
Jeff Quartermaine
executiveAlso, I want to flag a further initiative that our technical services group took on in the quarter — it matters and deserves a mention. At both mines, we have gone back over our pit designs and built in the latest technical and commercial parameters we have actually achieved, and we have also examined the gold price, assuming $1,300 per ounce instead of the $1,250 per ounce we previously applied in our modelling. As a result of that effort, later in the quarter, once every sign-off is finished, we will release revised mineral resource and reserve estimates for each mine, and in every case they indicate an incremental gain in mine life. Beyond that, at Edikan we have likewise re-examined the question of mining the Esuajah South ore body and have assessed both open pit and underground options. Esuajah South presently accounts for roughly 312,000 ounces of the ore reserve estimate on the basis of underground mining methods, yet extraction of that ore body to date has not been folded into any of our life of mine plans, largely because of a historical perspective on risk-weighted returns from the exercise. Open pit alternatives, now, were reviewed previously but were not taken up, given the difficulty of mining a large open pit near Ayanfuri Village, and naturally that carries with it assorted compensation and relocation costs.
Jeff Quartermaine
executiveBut regardless, the work has gone extremely well, and the final results from it are going to be reviewed by our board later this quarter, and if approved for adoption, it will lead us to update a revised life of mine plan for the Edikan operation, which we will duly publish. At roughly the same time, of course, we also expect to publish a revised life of mine plan for Sissingué that will include mining of the Zanakan ore body, which will enter the reserve for the first time. Now, shifting from operations to finance, during the quarter, we sold 61,176 ounces of gold at a weighted average price of $1,415 an ounce, generating positive cash flow at both of our mines. In fact, the split between the two was about 60/40, as opposed to production, which was 70/30. Now, assuming the $4,015 gold price and our all-in sustaining cost of $962, as I said earlier, that gave us a margin of $453 an ounce, which, when multiplied by the number of ounces produced, gave us that net free cash flow of $31.3 million. So that was a fairly healthy contribution to be making to the coffers. It was necessary because during the quarter, we did spend $72 million on the Yaouré CapEx.
Jeff Quartermaine
executiveWe handed over $5 million in taxes to the government of Ghana. As I mentioned, we also covered corporate costs, exploration costs, and so on, along with movements in debtors and creditors. Once all of those items had been accounted for at the end of December, the cash balance came to $81 million. That figure is below where the cash balance sat at the end of September, though it should hardly come as a surprise, since we've entered full-scale construction at Yaouré and money is flowing out to that project at a healthy pace. One more thing worth noting: over the quarter, we drew an additional $10 million against our $150 million revolving credit facility. The total drawn balance now sits at $50 million, which of course leaves $100 million undrawn. What all of this means is that our net cash position, as I noted earlier, has shifted to roughly $31 million by quarter's end — a drop of approximately $50 million compared with the prior quarter. There's one further financial item I ought to raise, one investors often ask us about, and that's our gold price hedge book. Throughout the quarter, we kept actively managing that hedge book, consistent with the corporate hedging policy we've set out clearly.
Jeff Quartermaine
executiveWe've discussed this topic for a while now, and I believe it's pretty widely understood what our business does. When the quarter closed, our hedge position consisted of a forward sale of 276,000 ounces of gold at a weighted average price of $1,348 per ounce. These sales, then, give us protection against downside price moves for roughly 23% of the gold production we forecast across the coming three years. And noting that the position is currently out of the money, with the gold price holding up fairly strongly, investors often ask, "Well, what happens if the gold price stays at current levels or trends higher?" Well, the good news is that if that occurs, we'll be selling 77% of our production at the higher gold prices, and if it doesn't occur and the gold price falls, as it has done in the not-too-distant past, the good news is that we'll be selling 23% of our production at a weighted average cost of $1,348 an ounce, and in the process, ensuring that we can generate enough cash flow to remain liquid. Now, of course, this may not be the case if we decided to bet the entire house on the gold price or bet that the gold price is going to stay up at elevated levels forever.
Jeff Quartermaine
executiveNow, moving on to development and discussing our third project, Yaouré, of course. This quarter, the momentum that began building at Yaouré during the previous quarter has carried forward, and we've achieved very strong progress across every front. For those of you eager to see the progress for yourselves, I should note that each month we post video footage captured by our drone on the website, and this literally provides a bird's-eye view of what's happening on the ground. And I do recommend you take a look at this footage as well as the photos presented in Appendix A of our quarterly report, which also tell an interesting story. Excuse me. Off-site engineering is now roughly 99% complete, and the range of procurement contracts have been awarded. Approximately 98 of the 101 packages have been awarded, and we're currently reviewing another one. In terms of overall procurement and delivery, that's around 63% complete. So even though we've ordered just about everything, deliveries on site are still in progress and will continue over the next couple of months. Fabrication of structural steel, including the tanks, ball mill, SAG mill, is very well advanced, and these large and important items are on schedule for progressive delivery to Abidjan in the next couple of months, so they'll be turning up on site fairly shortly, we would think.
Jeff Quartermaine
executiveAdditionally, in the course of the quarter, we awarded a contract covering the provision of mining contract services. The winning bid came from an international mining firm headquartered in Spain, EPSA Internacional. They are a highly impressive organization, and they are already setting themselves up in Côte d'Ivoire as they prepare to move their fleet of vehicles to site, train local operators, and get ready to begin pre-stripping near the third quarter of this year. So from our perspective, that was a very good outcome. As I mentioned, at the site itself we have achieved a great deal of progress, and the videos show that, as I noted. Within the plant site area, you can see that the primary crusher vault walls are advancing very rapidly. Concreting stands at roughly 36% complete. The walls there are rising at about 22%. The lime storage facility is well advanced. On the SAG mill pedestal, we are now into the third lift of concrete, and on the ball mill pedestal, where the formwork for the second lift has been put in place, we will be proceeding. In fact, that reflected the position at year-end. We have actually moved beyond that point now. The CIL tank floors have been poured. Every one of them is now in position, and in fact, having looked at some photographs over the weekend, we can begin to see steel emerging from those tanks, which is very encouraging, and the concrete floor slab and bund are approximately 90% complete.
Jeff Quartermaine
executiveConstruction of the primary processing plant is genuinely progressing at pace. Regarding storage — the TSF, meaning the tailings storage facility — the entire 65-hectare footprint for stage one has now been cleared, and topsoil removal work continues. That work sits at roughly 60%-70% finished, along with backfilling of artisanal mine shafts across the area. To date, we have needed to backfill approximately 2,800 holes, which certainly confirms gold is present there. Around 100 holes remain, so this effort is quite far along. Turning to power supply, the main substation is now being built. Transformers have been ordered and should arrive on site soon. Fabrication of the transmission line and towers is nearly finished, with delivery to site expected before long. The overall power supply work is tracking toward our target. We intend to energize around September this year, and everything there is proceeding nicely. We have also been installing the perimeter fence, completing roughly seven km of it so far. We have cleared the corridor over about 12 km, I believe, which is likewise well advanced. The permanent camp buildings are coming together very well indeed.
Jeff Quartermaine
executiveThat's visible in the video footage. Building construction can now begin on every terrace, since all of them have been handed over, and there's a substantial amount of construction activity underway. On the upper benches, roofs and similar elements are beginning to go onto the buildings, so our aim is to have that fully and truly finished over the course of this current quarter. By the end of December, we had expensed $111 million of the project's cost, and we had physically paid $99 million to suppliers of goods and services. That works out to roughly 37% of the total $265 million budget. We've also put commitments in place amounting to $165 million. What that means is that, by the end of December, the cost for nearly two-thirds of the capital cost is pretty much locked in, which matters when it comes to limiting the potential for cost overruns in the later stages of the project. As I mentioned earlier, another significant milestone was that we finalized negotiations with the relevant departments within the Ivorian government on the terms of a mining convention that includes a guarantee of fiscal stability applying throughout the life of the project. It was signed in early December, it's now in effect, and I have to say that executing this document was a very, very important milestone for us.
Jeff Quartermaine
executiveWe don't really have any concerns, but it's reassuring to know the fiscal terms behind our feasibility study will remain unchanged throughout and won't shift as things progress. At this moment, assuming no additional delays, our stretch goal of first gold production by December 2020 can be reached. I can assure you completely that we and our contractors are doing everything possible to hit this milestone. The Yaouré project is unquestionably advancing and remains on track. Everyone at Perseus is very enthusiastic about this project, especially regarding what it means for us and our capacity to meet our corporate goal of 500,000 ounces of gold annually by 2022. Yaouré was plainly a key component of that. The other area we've been active in this quarter is exploration. As I noted at the close of last quarter, we've devoted considerable thought to building an organic growth strategy for Perseus driven by exploration, both on our leases next to existing infrastructure at the three mines and at nearby landholdings that host stranded assets.
Jeff Quartermaine
executiveSo this strategic planning effort wrapped up in the quarter, and at our yearly strategic planning retreat, which took place near our AGM in late November, we showed the board our plans. The board approved allocating capital and instructed management to proceed with implementation. As a result, during the coming 12 months, we intend to invest roughly $15 million in exploration. Most of that budget is going toward Yaouré, where we believe there is huge potential to make a substantial addition to our reserve inventory. However, we must actually do the work on the ground to turn that into reality. The remainder of the budget is going toward Edikan and Sissingué, where infrastructure already exists and we have developed several highly promising targets that we hope will also provide mill feed to extend the lives of both operations and sustain the 500,000-ounce plateau we achieved in 2022, carrying it forward well into the future. At Sissingué, we have enjoyed some recent success, and later this quarter we intend to report a new mineral resource situated south of the Sissingué pit at a location known as Zanakan. This is not a large standalone resource; instead, it will contribute incrementally to our resource and reserve inventory and will lengthen the life of the Sissingué operation.
Jeff Quartermaine
executiveAlso, toward the end of last year, we said we had signed an option agreement covering a mineral release known as Agyakusu, situated right next to Edikan. The documents for this transaction are now close to being given final approval by the government bodies involved, and physical work is set to begin in the very near future. This may prove to be quite an appealing chance for us. If things go well on this tenement, it could open up our thinking regarding a number of other opportunities in the region. So we're eager to get going at Agyakusu, and we're looking forward to finding out what unfolds there. At Yaouré, as I noted earlier, Yaouré will be the place where we devote most of our exploration effort over the next year. We have just finished drilling 3 deep diamond targets — holes aimed at the structure we believe will support a substantial underground mining operation for many years ahead off the flank of the CMA pit. The first 2 of those 3 holes intersected the structure at the intended depth, and they also showed mineralization in line with the CMA pit. The third hole failed to hit the target for some reason, yet we have enough information to help with the upcoming three-dimensional seismic survey to be carried out by HiSeis later this quarter, which will hopefully define the structure with greater clarity and more accurately guide future drilling programs aimed at what we hope will be mineralized dilations of this structure.
Jeff Quartermaine
executiveUpdates on each of those exploration efforts will come out gradually, and naturally we'll inform the market once we have results in hand. So to wrap up, as I mentioned when this presentation began, the December quarter was yet another strong one for Perseus. Indeed, we've kept hitting important milestones. We keep doing what we told everyone we would do, and at this point we're establishing a highly convincing record of steady operational delivery. In fact, this marks the 12th quarter in a row in which we've met our targets quite well. On the operations side, next quarter should come in slightly ahead of this one for both output and costs. As I noted, our market guidance stands at 140,000 to 160,000 ounces for the half year at $750-$950 an ounce. And as ever, that guidance leaves room for surprises, though should everything unfold according to plan, we ought to reach that target with room to spare. That holds even though it does require a step up from the half year just finished. On development, Yaouré, as I said, is firmly moving ahead, with superb progress achieved both on the ground and away from site.
Jeff Quartermaine
executiveSo we’ve got an excellent group of developers — some in-house, some contracted — who are working on our behalf. And we’re eager to keep showing investors how that progress is going by putting video footage on our website that’s captured with drones and fixed cameras. On the exploration side, like I mentioned, we’ll be stepping up what we’re doing so that we can both lengthen the life of the operations we already have and, we hope, find our next mine. We’ve definitely developed some intriguing targets, and hopefully we’ll get some good news coming through on that. Again, we’re getting ready for another extremely busy quarter here at Perseus, and hopefully the March quarter will be every bit as successful as the quarter we’ve just reported today. So thanks very much for being here. I’m glad to take any questions you might have now. Andrew Grove, who leads investor relations and business development for us, is here with me. So if anything is too complicated for me, I’m sure Andrew can help answer your questions. Thank you.
Operator
operatorThank you. Should you like to pose a question, kindly press star one on your phone and hold until your name is called. To withdraw your request, press star two instead. Should you be using a speakerphone, please lift the handset before asking your question. Our first question is from Reg Spencer at Canaccord Genuity. Please proceed.
Reg Spencer
analystThanks. Good morning, everyone. Congrats on yet another solid quarter. I have just a single question, and it has to do with what you're planning for a revised life of mine plan at Edikan. I suppose I'm just trying to think through what adjustments to your assumptions on the gold price could mean for your grade. And whether you can kind of give us some direction on how we should be thinking about that right now.
Jeff Quartermaine
executiveHonestly, regarding what you asked, there's not much I can say right now. Reg, the final work at Esuajah South is going before our board later this month. I don't want to get too far ahead of their approval. My confidence is very high that they'll give it. The gold price increase doesn't have a huge effect on it. Being able to hedge part of the underground gold at roughly $1,500 an ounce means we're guaranteed a pretty substantial margin, and if that's the route we chose, it genuinely removes a great deal of the risk involved. But the plans should be out fairly soon, and once they're released, I believe you'll get a clear picture of where things are going. What I can tell you is that the updated life of mine plan for Edikan will definitely extend the mine life past the current one, which I believe sits at about six years right now. It will definitely deliver a material increase to that mine life. So that's certainly something worth waiting for.
Reg Spencer
analystAlright, that's excellent. So to make sure I have this right, Jeff — at Esuajah South, you had earlier been evaluating an open pit, but because it sits so close to Ayanfuri, that option became somewhat harder to pursue. There is underground potential at that location, yet with gold prices high, you are now looking again at an open pit. Could you clarify that point for me?
Jeff Quartermaine
executiveWe examined every possibility available to us. So we considered an open pit; we considered a combination of open pit plus underground; and we considered an underground operation. Every one of those options carries particular attractions. What we have had to do is assess this work on a risk-weighted basis and ask, "At the end of the day, how much return do we get for how much risk capital?" And that is the decision we are bringing to the board. Now, risk surrounds each of those alternatives. I mean, clearly, with an underground mining venture there is risk, even though we believe the ore body is very straightforward and the mining techniques are thoroughly tried and tested. But risk does exist there for us. In the same way, with a large-scale open pit exercise, risk is present. The risk on open pit relates, as I say, chiefly to the expense of relocation and matters of that kind, because, since we began operating the Edikan mine, the Ayanfuri village has grown from a little country hamlet into quite a busy town now, and an open mine would in fact involve a great deal of relocation.
Jeff Quartermaine
executiveAll of those factors had to be balanced against one another, which is exactly why I'd rather not get ahead of any choices we'll make. We needed to examine every possibility in full detail and, as I mentioned, perform a careful risk assessment on each one prior to reaching any determination regarding what produces the strongest results for shareholders.
Reg Spencer
analystAll right, that's excellent. Many thanks. Appreciate it, everyone.
Operator
operatorMichael Slifirski from Credit Suisse has the next question. Please proceed.
Michael Slifirski
analystYeah. Thanks. Good morning, Jeff, and congratulations. It's really great to see how dependable your projections are. Very, very reassuring. A couple of questions. First of all, regarding the remarks about the Sissingué reconciliation issue during the quarter, is that limited to that lower-grade area in particular, or do you have any thoughts on why that actually happened compared with the strong positive reconciliation life of mine to date?
Jeff Quartermaine
executiveYes. So it has to do with the saddle zone that sits between two sections of the pit. When we were mining the very top benches there at the beginning of the mine's life, we saw a comparable outcome. Reconciliation came in over on tonnes, under on grade, and roughly matching on contained gold. Then, once we get into the main ore body, we were seeing positive reconciliation on tonnes, positive reconciliation on grade, and strongly positive reconciliation on contained metal. Right now, we're nearly through. As a matter of fact, the target date for being fully into the main ore body is around the 22nd of this month, I believe, and we're beginning to observe better grade at this moment. So we do anticipate that the patterns we experienced early in the mine's life will repeat going forward. So that doesn't worry us too much. Still, we are watching it very closely.
Michael Slifirski
analystAll right, thanks. And then second, regarding the mining convention, did any terms come out significantly different in a way that disappointed you? I mean, were there pluses and minuses across the whole package, or how do those compare with what you had actually expected and what you already had in place for Sissingué?
Jeff Quartermaine
executiveIf I were to share the specifics of how they went, that would amount to disclosing a negotiating approach, and that probably wouldn't be very wise. Well, look, the result turned out quite well, in fact. It was a well-balanced arrangement. The conditions are broadly comparable to Sissingué. There are one or two nuances that pertain specifically to Yaouré, though they aren't hugely different. To be honest, we're very pleased with how it came out. For an operation with a long life, or a fairly long life, that we're establishing, having that certainty regarding the terms in place is genuinely, genuinely important, and it gives us considerable confidence not just to develop what we're doing right now but also to consider extensions, so we're quite happy with all of that.
Michael Slifirski
analystYes. Wonderful. Many thanks. With that now secured, I’m not sure how the timing stacked up against what you had anticipated and possibly used as the basis for your activity levels, but I’m aware there was a cap on how much debt you were able to draw, and cash flow certainty was never achievable since nobody knew which direction the gold price would take in any case. So has anything in the development schedule so far been held back by that financing covenant, or is that the case?
Jeff Quartermaine
executiveDefinitely not. I mean, maybe we were being somewhat cautious when we thought about those matters, but we have not been affected whatsoever. As a matter of fact, the truth is I believe we could draw as much as $40 million or $50 million even without the mining convention. And that is what we did. We drew that sum in order to retire the existing debt, but the truth is we could still more than cover ourselves from existing cash and cash flow. So, to answer your question, definitely not. We have not been hindered in any way at all in developing Yaouré. Everything has been proceeding pretty much on target. I mean, we had a favorable stretch with the weather. Earlier on we were somewhat worried that weather might have hit us, but that did not happen either. I mean, for two reasons. First, we did not get a very wet season, and second, the ground conditions at Yaouré are better than they otherwise might have been. So, all things considered, it has been a solid run so far, and fingers crossed it stays that way for the remainder of this year. We still have to get through another wet season in July.
Jeff Quartermaine
executiveAll of that work will be above ground, and we're going to be laying cable, piping, and similar materials. As a result, weather conditions ought not to affect us at all.
Michael Slifirski
analystThanks. And last, regarding what you mentioned in the report about the old tailings leach — sorry, the dam lift at the old tailings storage facility — has any additional thinking or analysis been done on that material and whether it could serve as future plant feed for reprocessing? Has anything moved forward on that?
Jeff Quartermaine
executiveMike, which of those was it?
Michael Slifirski
analystMy apologies. Over at Edikan, there’s this float storage material holding a substantial amount of gold, but.
Jeff Quartermaine
executiveOkay, so this breaks down into a couple of pieces. The first piece is the standard float material, and then on top of that you've got the cyanide tailings.
Michael Slifirski
analystYes. Indeed.
Jeff Quartermaine
executiveRight, so the float material is the answer there. There's plenty of it, and it holds nothing of value — basically beach sand. As for the cyanide tailings dam, yes, there's some potential to do that. Actually, what we're doing — and Andrew can jump in on this in a moment — what we've been doing is putting in a carbon column, and we've been recirculating the water from that dam through it, and that's been producing a solid 300-odd ounces per month pretty consistently for several months now, which has definitely covered what it cost to install. But it actually looks kind of interesting. Andrew, want to add anything?
Andrew Grove
executiveYeah. Look, Mike, we're still carrying out the test work on fine grind and other recovery methods from that. That work is still in progress. It isn't a straightforward process. So we're still examining what opportunities exist there.
Jeff Quartermaine
executiveStill, that's worth emphasizing, since one thing we've managed quite well at Edikan over the past 2 years is putting in place a really active continuous improvement program, and it has produced plenty of solid ideas that have genuinely made our operation better by a fair margin, so examining that CTSF material is definitely included in that program, but before anything gets implemented it has to be researched thoroughly, because all of these things require capital, and we need to be convinced that a suitable return will be generated on that incremental capital before we move forward.
Michael Slifirski
analystYeah, thanks a lot, Jeff.
Jeff Quartermaine
executiveThat's great.
Operator
operatorThe following question is from Adam Baker of Global Mining Research. You may proceed.
Adam Baker
analystHello, everyone. Yeah, I just saw that you're revising the gold price assumption for Edikan and Sissingué from $1,200-$1,300. There's no mention of Yaouré that I can see. Are you making any adjustments to the gold price assumptions for that one?
Jeff Quartermaine
executiveRight now, we’re still relying on the base feasibility study, but once we carry out more mine planning at that site, we’ll be consistent across the group.
Adam Baker
analystSure. And slightly off-topic, I was just wondering whether you could address the geopolitical situation, and have you noticed any increase in terrorism activity in Ghana or Côte d'Ivoire? We've witnessed the tragic circumstances in Burkina Faso and how that impacted Semafo. I was just wondering if you could explain that a little.
Jeff Quartermaine
executiveI'm not going to set myself up as an expert on geopolitics, but from what we've observed, I'd simply say there's no sign of that kind of activity in either of the two countries. If anything, there's actually considerable evidence that both governments are being quite proactive, working hard to make sure that what has happened well to the north of our countries does not become the accepted pattern farther south. As a company, we therefore keep a very close watch on developments in our region, and we put together various plans aimed at keeping our people safe, especially at our assets. At this moment we feel very comfortable running operations in Ghana and Côte d'Ivoire. On what has taken place in Burkina Faso, I really can't offer a comment, since I don't travel there and we don't operate on the ground, so plenty of other people would know far more about that than I do.
Adam Baker
analystAlright, I’ve finished. Thank you.
Operator
operatorThat brings us to the end of the question-and-answer session. I'll turn things back over to Mr. Quartermaine now for his closing remarks.
Jeff Quartermaine
executiveAll right, thanks again so much for joining this conference call. It’s been a solid quarter for us. The progress the company is making is very encouraging to us. We’re also very thankful to our shareholders for the backing they’ve shown us in the market over the last six months. And what I can tell you is that we’re looking ahead to the future with a great deal of anticipation. Perseus, we believe, has a very exciting future, and we as a management team recognize that delivering on the commitments we’ve made is our responsibility, and that’s what we will be doing. So thank you very much, and we’ll speak again in three months’ time.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Perseus Mining Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Perseus Mining Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Perseus Mining Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.