Nathan Ryan
unknownGood morning, everyone, and welcome to the investor conference call held by Perseus Mining regarding the quarterly report for March 2021. <<operator_script>> At this point I'll turn things over to Perseus Mining's Chief Executive and Managing Director, Jeff Quartermaine. Jeff, the floor is yours.
Jeffrey Quartermaine
executiveThank you so much. And thank you, Nathan. I'd like to welcome everyone to this webinar, where we'll be going over Perseus' quarterly report for March 2021, which came out to the market earlier today. At the risk of sounding like a broken record every quarter, Perseus has once again delivered a strong quarterly performance — our production rose by 29%, and this is the clearest signal yet that the company is genuinely well on its way toward its targeted output of 500,000 ounces of gold per year at a cash margin of USD 400 per ounce or more. We finished commissioning our third mine, Yaouré. And by the end of March, that mine had turned cash positive, and we were in a position to declare commercial production from 31 March. That represents the final major milestone in developing this highly important project. In fact, each — over the course of the quarter, all 3 of our mines — Edikan in Ghana, along with Sissingué and Yaouré in Côte d'Ivoire — performed very much as we had expected. At the group level, we produced 88,458 ounces of gold and sold 87,215 ounces, roughly 31% above the prior quarter. And pleasingly, our all-in site costs came in below USD 1,000 per ounce.
Jeffrey Quartermaine
executiveAnd thanks to a gold price that's held up reasonably well, we can produce a substantial amount of cash, which leaves us well placed to fund the future. Our organic growth strategy is beginning to demonstrate that it can deliver results. As we reported earlier this month, certain work at Bagoé and at Yaouré looks quite promising. And down the track, we anticipate putting out more positive news flow regarding genuine organic growth from those sites. We've made very good progress on managing sustainability — a materiality analysis and a gap analysis to pinpoint exactly where more effort is needed so we align with global standards. Our newly appointed Head of Sustainability finished that work recently, and it will all be set out in our highly comprehensive 2020 Sustainability Report, due out very soon, so that's worth watching for. So in summary, Perseus is in a very good place, and that comes from a great deal of hard work and support from our highly dedicated and professional team of employees and their families over a number of years. And I'd like to sincerely thank them all for their efforts.
Jeffrey Quartermaine
executiveFor anyone who hasn't had a chance to go through our March quarterly yet, let me spend a little time going a bit deeper into a couple of the key elements of how we performed, and then we'll open things up for whatever questions you might have. So first, as I mentioned, the big accomplishment for us this quarter really was getting the Yaouré mine and its associated infrastructure successfully commissioned, which culminated in commercial production by the end of the quarter. As you'll remember, in the prior quarter we ported our first gold at Yaouré in December, and then not long afterward we ran into some equipment failure at the site. That meant we had to put a few contingency plans in place to commission the remainder of the plant until the failed equipment could be replaced. After we managed to procure and install a replacement transformer for our SAG mill late in February, things progressed very, very quickly, and we were able to meet all of our completion tests and show that the mine was in fact cash positive by the end of March, rather than a declaration of commercial production. We produced 22,095 ounces of gold at Yaouré during the quarter, including nearly 10,000 ounces in the month of March. And as we move forward into the June quarter, we expect to begin introducing higher-grade fresh material from the CMA pit, which will ensure that we comfortably meet our production and cost guidance at Yaouré for the June half year.
Jeffrey Quartermaine
executiveAnd just to remind everyone, that guidance ranges from 48,000 to 52,000 ounces, with an all-in site cost between USD 1,100 and USD 1,300 per ounce. And we think we can achieve that quite easily, or quite readily. Now, we're planning to put out an updated life of mine plan for Yaouré near the end of the June quarter. That plan is going to rest on a mineral resource incorporating a modest resource increase relative to the original DFS, though it's unlikely to capture the extra resources coming from recent drilling or the other studies we've carried out. Once those additional resources have been estimated, they will materially extend the life of the mine. But that further update will come later in the year, after we publish this life of mine plan that's due out at the end of the quarter. The June 2021 life of mine update will, however, reflect actual costs, and this, I expect, will demonstrate improved project economics relative to the DFS. So Yaouré is up and running, and may I take this opportunity to sincerely thank and congratulate everyone who contributed to what really has been quite a remarkable achievement given the challenges seen as a result of the COVID pandemic last year.
Jeffrey Quartermaine
executiveA great number of people have contributed in outstanding ways, and I don't mean just our superb development team and the contractors responsible for constructing the mine. Considerable effort went into discovering, engineering, financing, licensing and administering the property. And naturally, finally, I want to recognize the enormous backing and partnership we have enjoyed from the communities hosting us and their traditional leaders, along with officials from the government of Côte d'Ivoire, among them former Ministers Brou and Kouassi. Thanks to what all these individuals have worked to achieve, we can now anticipate that Yaouré will deliver tangible returns to every one of our shareholders over many years ahead. Meanwhile, so as not to be overshadowed, the Edikan and Sissingué mines turned in very robust results too during the quarter. Together, those 2 mines delivered 66,364 ounces of gold, with a production cost of USD 852 per ounce and a weighted all-in site cost of $999 per ounce. Output therefore rose slightly versus the prior quarter, which hardly matters either way. However, the 7% and 4% declines, respectively, in output and all-in site costs mattered far more when it came to producing additional cash flow.
Jeffrey Quartermaine
executiveThat was a really strong result, especially if you factor in that Sissingué lost close to 10% of the production time it had available in the quarter, because of interruptions tied to what a small group of young people from a village nearby did. And over at Edikan, the equipment availability from our mining contractors fell short during parts of the quarter, owing to maintenance difficulties related to COVID. I should note that both of those problems are now mostly behind us. Even so, pulling off what we did while dealing with those obstacles was genuinely a fine achievement. There's one item about Edikan I'd especially like to point out to you, and that's the gold recovery rates we delivered in this quarter. Anyone who follows our quarterly reports regularly will be aware that through a number of quarters last year, we had a hard time optimizing the feed blend at Edikan and finding the ideal balance among head grade, throughput rates and recovery. And at times, the recovery rates we posted were disappointing. I'm happy to report that, with the Bokitsi fresh ore now finished and new ore sources opened up in the Fetish and AG pits, recovery rates have been rising steadily. In fact, during March they came in at an average of roughly 88.5%, which is far above the 74% recorded in December.
Jeffrey Quartermaine
executiveWe do anticipate that these higher recovery rates will now be standard going forward, and that has definitely held true so far this month. We will still have to strike a balance between head grade and throughput rates, since certain ores are harder than others, but that is far more manageable -- far more manageable than the metallurgical difficulties we encountered previously. So that represents a meaningful improvement at Edikan. Now regarding Sissingué, despite the production time lost, everything else there has gone extremely well during this quarter, and on most, if not all, of the key parameters, we have consistently surpassed our internal targets: run time, throughput rates, grade recovery, et cetera. The sole thing that even remotely looks like a cloud on the horizon at this mine, ironically, is unrelated to Sissingué's operating performance as such. This quarter, we have once again been frustrated by our inability to secure approval from the Ivorian Cabinet of Ministers for the mining lease required to mine the Fimbiasso deposit. Now since late last year, a series of matters have taken precedence in the cabinet over approving mining leases, including a presidential election, reconciliation of opposition forces post-election, preparation for the legislative election that was held in March, the death of the second Prime Minister in 8 months and most recently, a cabinet reshuffle.
Jeffrey Quartermaine
executiveSo I do think we're going to sit down with the new minister this week in Abidjan, and Fimbiasso will be right at the top of what we discuss. The problem is this: should the license slip any further, our mining schedule will take a hit toward the end of this year, and we'll have to run lower-grade ore stockpiles until we can get full access to the higher-grade ore at Fimbiasso. Now, none of that affects the rest of this financial year, nor our capacity to hit market guidance for this year, but it could turn into a problem later in the year if it isn't sorted out. So it's plainly something of real importance to us. Now, turning to the future. Our production and cost guidance to the market for the 6- and 12-month periods ending 30 June is -- for the 6 months, 175,000 to 190,000 ounces at USD 950 to USD 1,150. And for the full financial year, roughly 313,000 to 327,000 at USD 970 to USD 1,070. Now, I think we've still got 2.5 months of the reporting period left, and a lot can go wrong in that time.
Jeffrey Quartermaine
executiveHowever, based on how we've performed so far, covering both the March quarter and the June quarter to this point, we have strong confidence that we will not only hit both our production and cost guidance but, with luck, do very well against those targets. Turning to our financial results for the quarter, the average cash margin we earned on every ounce of gold produced at Edikan and Sissingué came to USD 629 per ounce, a modest decline from USD 651 in the previous quarter, which reflected a lower weighted average sales price, which fell from $1,687 to $1,628. Even so, that cash margin exceeded our strategic target of $400 an ounce by more than 50%, and it allowed us to generate roughly USD 42 million in notional cash flow from Edikan and Sissingué on their own. Because we had not declared commercial production at Yaouré until the close of the quarter, under International Financial Reporting Standards we capitalized all revenues and costs at Yaouré through that date. As a result, cash flow from Yaouré is not included in our totals. Starting 1 April, though, Yaouré's costs and cash flows will be reported alongside those of the other mines. As I mentioned before, Yaouré was in fact strongly cash positive in March.
Jeffrey Quartermaine
executiveWe do expect a substantial increase in our notional cash flow from operations over the coming quarters, assuming things at all of the mines unfold as we anticipate. And lastly, across the March quarter, Perseus succeeded in preserving the strength of its balance sheet via those robust cash flows along with prudent financial management. As I mentioned, notional cash flow from operations came to $42 million this quarter, which let us settle outstanding bills from developing Yaouré, finance exploration across all 3 operating sites, pay income tax in Ghana, cover corporate overheads, and still hold cash and bullion of USD 136 million at the end of March, up from USD 118 million in the prior period. That left us with net cash of USD 6 million once our outstanding debt of USD 130 million is taken into account. Now, when you consider that since late 2016 we have invested close to USD 400 million in bringing first Sissingué and then Yaouré online, and we have still managed to finish in a cash positive position without major equity raises along the way, we have done quite well and, I guess, positioned Perseus to really reap the benefits of this hard work as we go forward.
Jeffrey Quartermaine
executiveTurning to the future — with Yaouré now up and running, folks ask me often these days about how we intend to grow the business. Our attention has shifted squarely to rolling out a range of strategies aimed at holding our planned output of 500,000 ounces per annum steady going forward, whether through organic or inorganic routes. Over the near term, Perseus' priority is straightforward: replace what mining depletes by way of organic growth, while laying the groundwork for organic growth over the longer term. To get there, during the coming 6 to 12 months we will concentrate on adding mineral resources and ore reserves step by step from near-mine deposits that are right now under exploration and/or feasibility study. As I mentioned before, a little over a week ago we released drilling results from a couple of the exploration programs we have run lately. One came from Govisou, on the Yaouré tenements, and the other from the Bagoé tenements situated near Sissingué. Should you not have seen those results, I would encourage you to look closely at the release, since as people will remember, the results were very encouraging and, I expect, will be the first of many such results emerging from our work over the months and indeed years ahead.
Jeffrey Quartermaine
executiveAt all 3 of our mines, we have some truly strong targets to go after. And with our recent mine development program now finished, it's the first time in quite a long while at Perseus that we've actually had the wherewithal to fund exploration properly. Now, following the Bagoé results we released the other day from drilling at Antoinette, Véronique and Juliette, we're putting together a definitive feasibility study for developing these deposits. That will be finished by the end of the June '21 quarter. This is a bit later than I had flagged before, but it came about because of a slow turnaround in results from overworked assay labs in Côte d'Ivoire. Now we do expect a significant addition of mineral resources and ore reserves, and we estimate this will extend the forecast life of the Sissingué operation quite considerably. So that's very pleasing indeed, given how efficient that particular operation is. Now, on the subject of feasibility work, I'd be remiss if I didn't mention our evaluation of developing an underground mine at the Esuajah South deposit at Edikan.
Jeffrey Quartermaine
executiveAfter weighing the economics of the proposed development carefully, and even though additional technical work has boosted our confidence in several key technical parameters — including estimated tonnes and grade, plus the size of the mineable resource, which actually rose by about 63,000 ounces — we've reached the conclusion that the project's overall risk/return ratio, as things stand right now, fails to satisfy our investment criteria. Consequently, we've chosen to postpone, for the time being, the planned commencement of implementation of the Esuajah South underground development. I should add as well that this project has not been abandoned by us. More technical reviews are going to be carried out in order to look into the potential for adding to the ore reserve at depth. On top of that, further optimization of designs and mining methods is going to be undertaken. During this period, we'll be engaging with the government in Ghana, holding various discussions there, and also completing licensing. And something else we'll do is honor all outstanding commitments owed to our host community with respect to the project, so that if circumstances shift enough, we can turn this project on without any drama. In the meantime, however, past the June quarter, we do have a number of large targets identified that could potentially be converted into mineral resources and possibly ore reserves near infrastructure at the mines.
Jeffrey Quartermaine
executiveLike I mentioned, the priority organic growth targets at Yaouré take in the CMA underground plus additional targets defined through the first pass interpretation of the 3D seismic survey finished at the site in the prior year. That looks extremely compelling there, I must say. Over at Edikan, assuming we secure access to drill, a program is set for the Breman deposit on the Agyakusu permit, where considerable mineralization has been found at surface in artisanal mine workings. Regarding that access, we've achieved quite solid progress lately, and we're hopeful a final agreement gets reached, which would permit access before long. At Sissingué, there's definitely more potential for adding mineral resources and ore reserves from the Bagoé area. In fact, a drill rig is on its way back there — I believe this week or early next week — to restart drilling in that area. I should add that potential inorganic growth business opportunities involving mergers or acquisitions also get assessed on a regular basis by our in-house technical and commercial teams. Considering the difficulties of executing value-accretive M&A and applying strict financial discipline when evaluating opportunities, we aren't pinning our hopes on this activity to deliver growth in the immediate future, preferring to focus on near-mine and early exploration growth strategies.
Jeffrey Quartermaine
executiveHowever, I can tell you that we're actively searching. I think the strategic acquisitions of Amara, which gave us the Yaouré project, and more recently Exore Resources, which gave us Bagoé, have demonstrated our ability to successfully spot value and complete transactions when the right M&A opportunity arises. What this means is that, with Yaouré now up and running, we're actively engaged in shaping this company's future and doing so in a manner we believe will create -- will be significantly value accretive for our shareholders. Our news flow across the coming few quarters will show that progress, and I do expect a steady stream of positive news to share with you as we push forward. So to conclude, as I mentioned at the beginning of the call, the March quarter has been yet another very solid quarter for Perseus, just as we promised it would be. The June 2021 quarter has begun very well. Edikan, Sissingué and Yaouré is building up, hitting all the key parameters and trending -- certainly trending in the right direction. On the financial side, we're getting stronger by the day thanks to the solid production results, containment of costs and strong gold prices.
Jeffrey Quartermaine
executiveOn the exploration side, we have a well-defined strategy along with a budget, and we're pressing ahead with the work of growing the business organically and delivering value to shareholders. And as I mentioned, when it comes to inorganic growth or M&A, we are active participants. And though we're not making any commitments on that front, we are positioning ourselves so that we can execute a transaction and capture shareholder value should conditions line up favorably. And lastly, we've reached a point where we can have a serious internal conversation about returning capital to shareholders through a dividend or a share buyback. And it ought to be just a question of time before the market recognizes the quality of Perseus' performance -- both the recent results and the earnings capacity -- and our patient shareholders will be fully rewarded for the support they've given this company. So thank you very much for listening, and I'm now glad to take any questions you might have.
Nathan Ryan
unknownThanks, Jeff. <<operator_script>> Our first question comes from Mike McLincoln. He asks, "Hi, Jeff. Good to see another strong quarter of production. If you get the grant to the mining license for Fimbiasso in the June quarter, will that allow time for mining to start in the September quarter?" And he continues, "In regards to gold hedging, do you plan to maintain the 20-80 profile, i.e., 80% unhedged?" So there are 2 questions there.
Jeffrey Quartermaine
executiveAll right, let me fix that one thing. It isn't Fibinso — it's Fimbiasso.
Nathan Ryan
unknownMy apologies, Fimbiasso — sorry about that. It did say that, I'm sorry. Sorry.
Jeffrey Quartermaine
executiveYes. No, look, I mean, there's a wet season on us at the moment. We began constructing the road to Fimbiasso last — well, earlier this year, late last year. So the first leg is done. Now we have to wait a couple of months and let the wet season do its thing, and after that we'll complete that road. So we're very hopeful we can mine without interruption. But when it comes to timing, the Ivorian government is difficult to predict. They do have their own important priorities. But I can assure people that we'll be working extremely hard to bring that forward as early as we can and to avoid any disruption to production schedules, if that's at all possible.
Nathan Ryan
unknownYes. And on the second question, about the gold hedging? The...
Jeffrey Quartermaine
executiveOn gold hedging — right, sorry. No, look, we aren't expecting any meaningful shift in what we're doing right now. As everyone knows, our policy allows hedging of as much as 30%, so that's 30-70. At the moment we're at roughly 20%, and we don't see much reason to alter that. If conditions made it seem wise, though, we could add a bit more hedging. But look, we manage that position actively. And I think over a long stretch now we've shown that this approach handles downside risk — a significant downside risk for us — and ensures we keep generating cash flow, so we can meet the benefits we've promised to all of our stakeholders.
Nathan Ryan
unknownAdam Baker has the next question. He asked if we could take him through which portion of Esuajah South underground failed to appeal — whether that stemmed from anticipated higher costs or from grades being lower — and whether a fresh Edikan life of mine plan will be published.
Jeffrey Quartermaine
executiveYes. Look, like I mentioned, the work completed lately has in fact boosted how confident we are about the technical parameters. So the resource — when we initially carried out the study, the genuine worry was the risk surrounding the resource. But through additional drilling we've satisfied ourselves that this risk is, in fact, not of the high order we had estimated before. Now I think what it really boils down to at the moment is commercial matters. We — mining costs have risen, and that definitely has an impact on what we're doing. There has been some element of fiscal creep. And I guess when we look at the situation and say, well, we understand what the maximum exposure is and the risks around it, and we ask ourselves whether this is the best use of capital in our company when it comes to creating value — and when I say the best, I mean the best return relative to the risk — the question — the answer to that right now is no, we have other ways of deploying capital that will create more value for shareholders, and that's what has driven that decision. Now as to the second part of the question, will we be producing an updated life of mine plan?
Jeffrey Quartermaine
executiveYes, we will, and that will come out in due course. But it does — and actually, we've already examined that quite closely, obviously, as part of this evaluation. And the thing is, it doesn't really have much effect on our production profile. And we — and as I mentioned earlier, we do have alternatives that will likely be brought online as a replacement shortly in any event. So all things considered, we don't think this decision we've taken now is going to be a major negative for the company. And as I also said, we're putting ourselves in a position where perhaps we can reverse that decision down the road if we can find better ways of doing what we're trying to do.
Nathan Ryan
unknownThank you, Jeff. Since we don't have any more questions right now, I'll pass things back over to you so you can give our closing remarks.
Jeffrey Quartermaine
executiveAlright, thanks, Nathan. So, as I mentioned earlier, we are genuinely well along the road toward the goals we laid out for ourselves a while back. In operational terms, in financial terms, and in terms of growth, we're in exceptionally strong shape. And I believe this company is now heading into a very different place from where it has been historically, and at this particular moment I'd think it certainly deserves close attention from all investors. We're also eager to keep delivering further strongly positive results in the periods ahead. Thank you very much for joining us.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Perseus Mining Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Perseus Mining Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Perseus Mining Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.