Pinnacle West Capital Corporation (PNW) Earnings Call Transcript & Summary

November 3, 2026

New York Stock Exchange US Utilities Electric Utilities earnings 47 min

What were the key takeaways from Pinnacle West Capital Corporation's November 3, 2026 earnings call?

In the third quarter of 2026, Pinnacle West Capital Corporation reported strong financial results, with earnings per share (EPS) of $3.49, reflecting a year-over-year increase of $0.10. Revenue growth was driven by a 9.5% increase in weather-normalized sales, with commercial and industrial sales up 14.5%. Management raised their 2026 EPS guidance to a range of $5.05 to $5.25, up from $4.55 to $4.75, signaling confidence in continued strong demand and operational performance despite rising costs associated with infrastructure investments.

What topics did Pinnacle West Capital Corporation cover?

  • Earnings Guidance Increase: Management raised the 2026 EPS guidance to $5.05 to $5.25 from a previous range of $4.55 to $4.75, citing strong year-to-date performance and robust sales trends. Andrew Cooper stated, "Given our strong year-to-date performance, robust sales trends across our retail customer base and continued economic momentum in our service territory, we are raising our 2026 earnings guidance."
  • Sales Growth: Weather-normalized sales increased by 9.5% in Q3, with commercial and industrial sales up 14.5% and residential sales up 4.5%. This marks the second consecutive quarter of over 9% growth, demonstrating strong demand across all customer segments. Cooper noted, "This marks our second consecutive quarter of more than 9% weather-normalized retail sales growth demonstrating the strength and sustainability of demand across our service territory."
  • Regulatory Outlook: Management is awaiting a final decision on their pending rate case, expected before year-end. They emphasized the importance of achieving a constructive regulatory outcome that supports reliability investments and customer affordability. Geisler mentioned, "We seek an outcome that supports reliability investments keeps affordability at the center and provides a timely durable framework for future cost recovery."
  • Infrastructure Investments: Pinnacle West is focused on expanding system capacity and enhancing reliability through significant capital investments. The company raised $700 million in senior unsecured notes to support these initiatives. Cooper stated, "We continue to execute a disciplined financing strategy, that balances capital investment needs, balance sheet strength and financial flexibility."
  • Direct Pricing Contract with TSMC: The company executed a 25-year direct pricing contract with TSMC, expected to serve approximately 1.8 gigawatts of demand, which aligns infrastructure investments with customer demand. Geisler noted, "Simply put, TSMC pays its own way. Residential customers will not subsidize this growth."

What were Pinnacle West Capital Corporation's November 3, 2026 results?

  • EPS: $3.49 (+$0.10 YoY)
  • Revenue Growth: 9.5%
  • Commercial and Industrial Sales Growth: 14.5%
  • Residential Sales Growth: 4.5%
  • 2026 EPS Guidance: $5.05 to $5.25 (up from $4.55 to $4.75)
  • Long-term Sales Growth Outlook: 8% to 10% (up from 5% to 7%)

Pinnacle West's strong Q3 performance and raised guidance reflect a solid investment thesis, supported by robust demand and strategic infrastructure investments. Investors should monitor the outcome of the pending rate case and the execution of the TSMC contract as potential catalysts for future growth.

Earnings Call Speaker Segments

Amanda Ho

executive
#1

Thanks, Matthew. I want to express my appreciation to all of you for joining this conference call and webcast, where we'll go over the third quarter earnings, recent developments, and how our operations performed. With us today are our Chairman, President, and CEO, Ted Geisler, and our CFO, Andrew Cooper. Jacob Tetlow, COO, and Jose Esparza, SVP of Public Policy, are also present. Before we begin, I should go over a few items. The slides we'll be referencing can be found on our investor relations website, together with our earnings release and related information. Our remarks today and the slides include forward-looking statements that reflect current expectations, and actual results could differ materially from those expectations. Our third quarter 2026 Form 10-Q was filed this morning. Please consult that document for forward-looking statements, cautionary language, and the risk factors and MD&A sections, which set out risks and uncertainties that may cause actual results to differ materially from those in our disclosures. A replay of this call will be posted on our website shortly and will remain available there for the next 30 days. It can also be accessed by telephone through November 10, 2026. I'll now hand the call over to Ted.

Ted Geisler

executive
#2

Thank you, Amanda, and thanks to everyone for being with us today. We posted solid financial results for the third quarter and met customer needs dependably through yet another demanding Arizona summer. In my remarks, I'll cover that performance, the way we are accommodating growth while shielding customers, our resource strategy, and the regulatory picture. Andrew will follow with a review of our financials and the refreshed 2026 outlook. Before I get to the performance discussion, our thoughts go out to the families and communities throughout Arizona working to recover from the floods of the past week. APS is donating $250,000 to the Navajo Nation and the Hopi Tribe for emergency relief in the Four Corners area, and we are evaluating what more is needed in Northern Arizona after this weekend's flash floods. Beyond that, we are making $5 million in company-funded assistance available to customers dealing with financial hardship, whatever the cause; we are here to support our customers and communities through these hard times. As I said at the start, our long-range planning and preparation was put to the test this summer, and it paid off. We got customers through 12 peak demand days that set records, even while extreme heat and storms strained our system; that outcome reflects what our employees do well before the hottest days come, and how they respond when conditions are at their worst. I could not be prouder of how our team delivered strong operational excellence for customers through yet another record-breaking summer season. Palo Verde played an essential role in that performance. Over the summer, the plant ran at a 100% capacity factor, providing reliable carbon-free electricity to our customers and bolstering the wider desert Southwest grid. On growth, weather-normalized sales for the third quarter rose 9.5%, as commercial and industrial sales climbed 14.5% and residential sales gained 4.5%. Arizona's economic strength and the appeal of our service territory keep drawing investment. Amkor Technology illustrates the point. In September, the company announced the second phase of its advanced packaging and test campus in Peoria, lifting its planned investment to approximately $12 billion from $7 billion and backing more than 3,500 Arizona jobs. Our recent TSMC agreement demonstrates how we accommodate this growth while shielding customers. Signed in October, our first direct pricing contract runs 25 years and, subject to regulatory approval, will serve approximately 1.88 GW of demand at full build-out across TSMC's chip manufacturing campus. Upfront capital contributions and credit support mechanisms tie infrastructure and resource investments to TSMC's demand. Put simply, TSMC covers its own costs. Residential customers will not be subsidizing this growth. The agreement offers a repeatable framework for other large customers, and we expect to submit it to the commission for approval in the coming days. Our recently filed Integrated Resource Plan shows just how large this growth is. By 2041, we project our customers' annual energy requirements will more than double, to approximately 80,600 GWh, while peak demand reaches 14.5 GW, more than 5 GW above today's level. Under our preferred plan in the IRP, we identify nearly 15 GW of new resources and approximately 2.6 GW of additional transmission capacity across the 15-year planning horizon. The IRP serves as a planning roadmap—it does not determine ownership of any individual resource. Our dedication to a competitive, all-source procurement approach is unchanged, and we'll compete by drawing on our demonstrated record of bringing reliable generation projects in on schedule and within budget. What we're aiming for is a balanced portfolio of dependable generation plus new transmission, designed to support growth in a way that is both reliable and affordable. Turning to regulation: closing briefs have now been filed by the parties in our pending rate case, and we're waiting for the administrative law judge's recommended opinion and order. Given the schedule as it stands, a final commission decision is expected before year-end. We're seeking an outcome that backs reliability investments, puts affordability at the center, and delivers a timely, durable framework for recovering costs going forward. With year-end approaching, our priorities are unchanged: provide reliable, affordable service in the present, move forward the dependable generation and transmission Arizona will require in the future, and secure a constructive regulatory result that safeguards customer affordability while cutting regulatory lag; now that we have the rate case decision and the TSMC agreement, we look forward to sharing an update on our long-term financial outlook during our next earnings call. Significant opportunity lies ahead, and we're determined to seize it with discipline and a long-term perspective benefiting both customers and shareholders. Thank you for joining us today; I'll now hand the call to Andrew.

Andrew Cooper

executive
#3

Thanks, Ted, and I want to thank all of you once more for being with us today. Earlier this morning we posted strong results for the third quarter of 2026, which show momentum that keeps building throughout our business. Let me walk you through the main drivers behind our performance and then share our revised outlook for the year. For Q3, we delivered earnings of $3.49 per share, which is $0.10 higher than a year ago, and that came from exceptional sales growth across every customer segment, ongoing customer expansion, and favorable weather. Those factors did more than offset the effects of the investments we keep making in our system, including higher depreciation and amortization as well as both debt and equity financing costs tied to supporting long-term growth. With our strong year-to-date performance, robust sales trends across our retail customer base, and continued economic momentum in our service territory, we are raising 2026 earnings guidance to $5.05-$5.25 per share, up from the prior range of $4.55-$4.75 per share. Sales and customer growth added roughly $0.35 per share of earnings growth in the quarter. Customer growth stayed healthy at 1.8%, while demand trends kept surpassing expectations across all customer classes. Weather-normalized retail sales rose 9.5%, including 14.5% growth in commercial and industrial sales and 4.5% growth in residential sales. Importantly, this is our second consecutive quarter of more than 9% weather-normalized retail sales growth, which shows how strong and sustainable demand is across our service territory. Because of that, we are lifting our full year 2026 retail sales growth outlook to 8%-10%, with 5%-7% growth expected from large Commercial and Industrial customers. Weather gave us an additional benefit in the quarter as well, with every month seeing more cooling degree days than the same period a year earlier. As expected, depreciation and amortization expense rose as we keep placing significant capital investments into service. These investments are expanding system capacity, improving reliability, and positioning us to meet growing customer demand. Interest expense also went up, reflecting financing activities that support our long-term infrastructure program. We continue to carry out a disciplined financing strategy that balances capital investment needs, balance sheet strength, and financial flexibility. In an environment where rates rose significantly, we executed our financing plan efficiently during the third quarter. We raised $700 million of senior unsecured notes, including a $100 million reopening of our 2035 notes, which let us maximize the execution of the financing transaction. We also priced approximately $235 million during the quarter under our ATM program, bringing year-to-date to nearly $920 million; we have priced the majority of our expected 2026 and 2027 equity need while maintaining a balanced, constructive capital structure. We will keep looking for opportunities to use the ATM program so we stay proactive about our future needs. Looking ahead, the demand outlook for our business continues to grow. Based on the increased load forecast in our recently filed Integrated Resource Plan, we are raising our long-term sales growth outlook through 2030 from 5%-7% to 8%-10%, with large C&I customers contributing 7%-9%; this reflects the substantial economic development occurring across our service territory. Beyond that, throughout that same timeframe we still anticipate consistent population expansion, which underpins yearly customer growth of 1.5%-2.5%. Every remaining element of our guidance is being reaffirmed, and we anticipate wrapping up our pending rate case by year-end. Given robust customer growth, rising demand, and substantial investment opportunities in front of us, we stay well-positioned to provide safe, reliable service and to create long-term value for both our customers and shareholders; that brings our prepared remarks to a close. I'll now hand the call back to the operator for questions.

Julien Dumoulin-Smith

analyst
#4

Great. Morning, everyone. Well executed, particularly regarding the sales forecast. We never doubt you folks; that said, however, when you consider all these customer-backed projects entering the plan, I wanted to get a bit ahead on the cash flow metrics and think a little about what the defining or limiting factor is here? Is it FFO to debt, or does the equity capital structure at the utility itself become the driving factor for incremental new equity issuance? We have obviously witnessed this as a trend, and you folks obviously appear to be saying more on this subject. Just as we prepare for some of these projects to enter the plan, I realize none of it is necessarily awarded here, but how would you approach this?

Andrew Cooper

executive
#5

Morning, Julien, and thank you for asking. Yeah, the most important thing certainly is that we can provide financing updates once the rate case is complete, together with the update to our capital plan. So all of that will sort of occur in sync. Yeah, I believe we do examine both metrics. Both matter and both sort of shift together. If you consider what will drive our external financing needs, two key ones will change between sort of our regular way and going forward. One is that the formula rate will give us improved cash flow, improved FFO, which assists with our credit metrics. It assists in pushing down our dividend payout ratio. It truly places us in a better position, both through the catch-up of the under-earning and the ongoing improved cash recovery. That will be a significant part of supporting both the equity Cap structure of the utilities and supporting our credit metrics. Then certainly, as Ted mentioned, the direct pricing contract model will provide upfront cash, which will assist in defraying those external financing needs. Both metrics matter. We generally aim to keep our equity Cap structure above 50%. We favor the 52%+ range that we are in this rate case. We do not want to fall too far behind that. Ultimately, the way we have designed things such as our DPC structure and the way we consider the formula rate, both also support our credit metrics as well.

Julien Dumoulin-Smith

analyst
#6

Could I perhaps ask a related follow-up question? When you consider converting rate base into earnings growth, keeping in mind the equity remarks you just offered, how are you viewing dilution? Clearly, some HoldCo dynamics might be at play here, but what is your thinking on the translation factor? Because it does seem, particularly in light of the elevated sales growth and the subscription programs here, like this could be a double-digit rate-based growth program.

Andrew Cooper

executive
#7

Yes, absolutely, over time and via those mechanisms I mentioned, there ought to be improved convergence between rate-based growth and earnings growth. Definitely, as we aim to earn nearer to our authorized return. We are pursuing accretive projects; we are taking actions that, especially with the FRAM, will position us to achieve more contemporaneous return and narrow that gap. The direct pricing contract structure likewise enhances the rate-making at the same time. All of it tends to push toward better convergence between rate-based growth and earnings growth.

Julien Dumoulin-Smith

analyst
#8

Yes, exactly. Of course, it looks as though your forecast will be anchored to 2027, and that year does include part of the FRAM step-up from the start, if I'm remembering correctly.

Andrew Cooper

executive
#9

You will-

Julien Dumoulin-Smith

analyst
#10

Great, understood. Thanks once more.

Andrew Cooper

executive
#11

reach a decision, right. Yes.

Julien Dumoulin-Smith

analyst
#12

Oh, yes, sir.

Andrew Cooper

executive
#13

Yep.

Julien Dumoulin-Smith

analyst
#14

Great. OK, then. Nice work, everyone. Thanks.

Ted Geisler

executive
#15

Appreciate it, Julien.

Shar Pourreza

analyst
#16

Hey, guys.

Ted Geisler

executive
#17

Hey, Shar.

Shar Pourreza

analyst
#18

Morning, morning. I’ll jump in with a quick follow-up, and perhaps I can sharpen Julien’s question a bit. In the past, the lag has tended to be roughly 200 basis points. When you look at the 5%-7% EPS and the 7%-9% rate base, that’s a couple hundred basis points right there. Given the 8%-10% sales growth, do you see that narrowing? What structural lag should we be thinking about as you consider the 200 basis points?

Andrew Cooper

executive
#19

Shar, this is Andrew. Good morning.

Shar Pourreza

analyst
#20

Hi, Andrew. Good morning.

Andrew Cooper

executive
#21

How are things? Yeah, absolutely. What I'd say is the management objective is still to earn within 50 basis points of our authorized return by the point we've largely closed the lag, and that goal hasn't changed; it'll come about through how the formula rate works, and it's something that will play out over time. Direct pricing contracts are going to help narrow that gap as well. Sales growth is precisely the kind of trend we've discussed before that generates tailwinds toward getting us closer to the 50 basis points, brings us inside that 50 basis points, and eventually may open the door over time to giving funds back to customers once you factor in nuclear production tax credits and similar items. So it's certainly among the drivers. A major piece of that mix over the long run is the large C&I customers. Each percentage of growth there ultimately has a smaller impact, sure, but it definitely contributes and acts as a tailwind for hitting our management goal.

Shar Pourreza

analyst
#22

Understood. So one final thing—clearly you've pointed out that the GRC order will arrive before the year is out. I just want to double-check this, though I suspect I already know the answer: depending on when that GRC order lands—say it's early December—would a special call be completely off the table at this point? Because obviously, once the GRC is behind us, that'll be a huge update. Could there be a chance to hold a special call and refresh the plan in December, or does the focus remain on a February update when you report year-end results?

Ted Geisler

executive
#23

Yes, Shar, right now we're focused on making use of the Q4 call in February; we'll assess that depending on when the final rate case decision lands. That said, at this moment, I believe you can safely count on that Q4 call and expect a decision sometime mid-December on the rate case.

Shar Pourreza

analyst
#24

Understood. All right. No, that's just right. That was everything from me. Thanks a lot. I'll see you folks in a few days.

Ted Geisler

executive
#25

Great. Thanks.

Richard Sunderland

analyst
#26

Hey, good morning, and I appreciate you making time today. I'd like to begin with the IRP update. Could you go into a bit more detail on the high-level plans regarding the in-service dates for that 15 GW of generation and 2.6 GW of transmission that you mentioned in the script?

Ted Geisler

executive
#27

Yeah, glad to, Richard. Thanks for asking. Like you mentioned, the plan lays out 15 GW of resources that are needed. The important thing is that this 15 GW is calculated based on what will be required to serve only the demand that has been committed. We did raise that committed demand compared with earlier figures; it now stands at 5.8 GW, roughly 1.3 GW more than previously. That figure excludes any forward-looking view regarding additional or new data centers, or additional and new extra large manufacturing past what we've already committed. So bear that in mind — that 15 GW covers only what has been committed or contracted, which makes up that committed bucket of 5.8 GW now. Of that amount, roughly half sits in development; we have around 4.5 GW of resources slated to be in service by 2028, plus about 2.8 GW more of thermal generation. Every one of those projects has been discussed before — the Redhawk expansion, Cholla conversion, Saguaro, and Desert Sun — with each one respectively having its first phases in development. Within those figures, roughly 40% is APS owned. Then remember that the remaining half is still to be procured. Both Saguaro and Desert Sun have room to expand. We're also securing turbine reservations at present for projects down the road, and pinpointing future development sites. After that, we'll keep running our RFP process to seek incremental opportunities past that. That covers the generation side. On transmission, we laid out that the IRP by itself is driving 2.6 GW of new incremental transmission on top of what the 10-year plan contains. This transmission is required simply to support connecting new generation resources; combined with what's in the 10-year plan, it runs through 2035; that's a fairly substantial quantity of transmission just to keep pace with reliability and resiliency and to connect the new generation resources. We'll keep assessing those needs as we complete transmission studies. Finally, to repeat, as we assess additional large manufacturing or data center customers we might contract with going forward, we would add them on top of this resource plan — both the demand and the resources sized to serve that demand, in incremental form. But we're taking a conservative approach and adding them only after they're contracted.

Richard Sunderland

analyst
#28

Got it, that's clear. Very thorough. Perhaps just to dig a bit deeper on the thermal side—sounds like there are efforts underway regarding additional turbines. Could you tie that together with your anchor shipper position on the new gas pipeline? Essentially, what has been committed at this point on your side for that pipe when it comes to these outlined resources? Is all of that also linked to committed customers? How does the gas supply side line up with all these puts and takes as things stand today? Thank you.

Ted Geisler

executive
#29

Yeah, absolutely. The Southwest Pipeline is definitely a vital infrastructure project for fueling some of the incremental thermal generation that will come into service during the 2030s. The generation we have already announced will take service from that pipe, but there is definitely additional capacity we have contracted from the pipe to support generation beyond the projects we have announced; so we will keep working with the developer to make sure that pipeline stays on course, and we will keep looking at the best-fit projects to develop in order to serve our customers beyond those we have already announced, so as to take advantage of that pipe. Given the solar irradiance available in Arizona, we still believe a balanced portfolio is the right mix for our customers. That blend of incremental natural gas, utility scale solar paired with battery storage—that is what we keep finding in our model as the best reliability solution at the lowest cost; it really will remain an all of the above approach, but since we have had so much utility scale solar and battery storage developed in recent years, we are now balancing that out with incremental gas. Then, as we look ahead, it will likely be a blend of both.

Richard Sunderland

analyst
#30

That's quite useful. I'll stop here. Thanks.

Ted Geisler

executive
#31

Thanks.

David Arcaro

analyst
#32

Oh, hey, thanks. Good morning.

Ted Geisler

executive
#33

Morning.

David Arcaro

analyst
#34

I wanted to ask about the IRP — could you walk me through how you'd sequence the RFPs as you keep moving through this process, to pin down the megawatts, the project, and how much will be utility owned versus none?

Ted Geisler

executive
#35

Sure — we're basically on an annual RFP cadence; it doesn't line up exactly with a calendar year, but at the moment we're still reviewing project proposals for the 2030 and 2031 timeframe; we issued a solicitation for projects that would deliver more than 1 GW of supply. Once we've worked through those results and the analysis wraps up, we'll put out a fresh RFP. Going forward it'll be roughly one RFP per year, just so we keep testing the market, spotting resource opportunities, and then any development projects we find through our own pipeline will compete in that process, which keeps it competitive as we move ahead and commit to those projects so we can serve growth; that's broadly how we expect it to unfold.

David Arcaro

analyst
#36

All right, understood. So would you leave those projects out of your CapEx plan right up until you might actually secure them once those RFP outcomes come in?

Ted Geisler

executive
#37

The way we look at it is this: once we feel sure those projects can compete — either because we've got sufficient insight into market pricing, or because the RFP has wrapped up — that's the moment we'll put it into the capital forecast. Take Cholla conversion, Desert Sun, and Saguaro, for instance: we've stated that we're confident about how competitive they are. Whatever capital tied to those projects lands inside the present guidance window would be captured. Should we see any doubt regarding a project's competitiveness, we wouldn't put it into the capital forecast until we're sure it can compete and get developed. Naturally, any resources tied to a DPC contract are contracted with that customer, and as soon as that commitment is made, they'd go into the capital forecast too.

David Arcaro

analyst
#38

Okay, understood. Right, that's clear. I'm just wondering about the transmission side of things too. Are there certain milestones required on your side to make sure they're needed and get regulatory approval before you'd factor transmission CapEx additions into your own forecast?

Ted Geisler

executive
#39

Well, for visibility and awareness, we do file the 10-year transmission plan with the Corporation Commission, and there are transmission workshops where each of those projects gets walked through. Those projects fall under FERC regulation and clearly show a significant reliability and resiliency need so that resource adequacy is maintained in our service territory. Since there's no excess available capacity on the transmission system in our service territory today, any new generation we connect needs incremental transmission so that new capacity can be incorporated into the grid reliably. We're very confident that every project we identify has already gone through the study process demonstrating its prudency and need, and so we're comfortable that, when we put it in our plan, it's necessary from a reliability standpoint, and therefore we're counting on its need and its ability to be developed.

David Arcaro

analyst
#40

Okay, excellent. Thank you. Appreciate it.

Ted Geisler

executive
#41

Thank you.

Nick Campanella

analyst
#42

Hi there, good morning. Appreciate you fielding the questions and for all the excellent responses you've given up to now.

Ted Geisler

executive
#43

Hi, Nick.

Nick Campanella

analyst
#44

Hi, everyone. Well done on the DPC framework — that's obviously a significant step. It seems designed for the manufacturing customer base that includes TSMC. Could you tell us how something like this could be reproduced for data centers or for other manufacturing customers? Now that the DPC exists, how much visibility do you have into moving more of that 20 GW of uncommitted capacity over into the committed bucket? Can you start replicating it? Is this more of a longer-term matter, or might we see something in what's coming in the fourth quarter? Thank you.

Ted Geisler

executive
#45

Yes. Thanks, Nick. Replication was a key consideration when the DPC was built. This is a fairly typical arrangement, in our view, and it achieves the proper balance: it shields our current customer base from reliability effects and cost reallocations, and at the same time it locks in what we need to construct the infrastructure that lets us serve these especially large customers dependably. So our view is that this is the correct strategy, and we also believe it can be duplicated elsewhere. As a reminder, the DPCs typically carry credit support — cash CWIP along with deferred revenue prepayments — collateral terms covering both liquid and non-liquid situations, termination terms, direct assignment cost terms that guard existing customers against cost reallocations, and naturally minimum energy and demand thresholds too. All of that, in our view, is necessary to make sure we're responsibly serving this new growth, and we believe it can be replicated; on serving more from the 20 GW queue, we do have other negotiations underway with customers in that queue. It's far too early to say whether those will turn into a DPC or not, but those discussions are happening. Importantly, beyond the extra large customers in the queue, we keep seeing incredibly robust — what I'd call organic, non-data center — growth in the service territory. A significant share of the growth in our committed queue — which is now at 5.8 GW — comes from customers outside the data center space who are just powering and driving Arizona’s economy. So we’re being very careful to continue expanding the grid and to hold onto the capacity required to serve that growth: residential growth, small to medium-sized business growth, and ongoing manufacturing growth in the service territory. We’ve promised Arizona that we’ll back it promptly, extending the grid to meet that kind of ordinary societal demand from non-data center customers, and we want to be sure we retain the capacity to do that. Once we have clearer visibility into which incremental generation and transmission projects are buildable, we will assess the ongoing demand outside data centers, determine when capacity from those new incremental projects will come online, and talk with customers in the queue to match new capacity with the projects that fit best.

Nick Campanella

analyst
#46

Thanks for sharing that. I was just wondering — with the long-term sales forecast now raised to 8%-10%, that clearly matches the resources you've said you're building toward at present. 7%-9% for large C&I. Could you speak to how that breaks down? For TSMC in particular, I know — does this cover essentially all of their expansion? Might there be additional amounts past that, simply given what's been announced? Is there a way to get a handle on that?

Ted Geisler

executive
#47

Yeah, Nick. What makes our load growth so exciting to us is how diverse it is. Actually, when you break down where that load growth comes from, manufacturing accounts for a bigger share than data centers do, and it spans a wide range of manufacturing. Advanced manufacturing like chipmaking, sure, but other kinds too. As an example, Kimberly-Clark recently announced a big manufacturing center down in Yuma, Arizona, and we've got additional ones across the service territory. We're also still seeing extremely strong growth from residential, which is the biggest category of growth for us. Then, naturally, there are data centers and advanced manufacturing, TSMC among them. The 1.88 GW of committed service in our DPC contract with TSMC is part of the IRP and shows up within the 5.8 GW of committed demand. So it's included there. We'll keep working with TSMC on whatever future plans they have and any service they might require past that.

Nick Campanella

analyst
#48

Okay, thanks.

Ted Geisler

executive
#49

Thank you.

Paul Patterson

analyst
#50

Hey, good morning.

Ted Geisler

executive
#51

Morning, Paul.

Paul Patterson

analyst
#52

Much of what I had has already been addressed. I simply wanted to ask about the long-term sales growth, which shows a significant increase — it sounds like rate lag is providing some kind of tailwind there. I'm curious whether you think that will have any meaningful effect on affordability, in terms of the rate impact, from having that much more volume, or will something else offset it?

Ted Geisler

executive
#53

Yes, Paul, we definitely believe these new extra large customers, which make up a meaningful portion of that new load growth, will bring an affordability benefit to existing customers. Looking at what pushes our expenses up as we keep providing dependable service, the fixed portion keeps climbing to make that possible. Consider the added spending on cyber defenses, wildfire mitigation, and IT platforms. Each of those outlays is required simply to serve our customers dependably, no matter how much load there is. Bringing on these very large customers lets us lower the costs that residential ratepayers would otherwise have faced, so those households come out ahead. It's difficult to put a precise figure on this, since you'd need a more granular view of how much each customer uses and their volumes, but we know a substantial share of that 5.8 GW of committed demand comes from these extra large customers, and the volume they bring will deliver an affordability benefit. That said, I also want to make clear we aren't counting on that alone to safeguard affordability for customers. We're taking steps of our own too. We're approaching roughly three years of O&M that has stayed fairly flat despite an inflationary environment. The Commission recently approved a 1% reduction tied to their resizing of the DSM plan, and in November they also approved roughly a $14-per-month decrease by returning savings from our Green Power Partners program to customers. And if you look at our rate CAGR over just the past seven years, it has stayed well under inflation even as we served record growth. I believe customers will get an affordability benefit from that higher volume, but we're also taking every management action we can to safeguard affordability too.

Paul Patterson

analyst
#54

Awesome. Thanks so much.

Ted Geisler

executive
#55

Thank you.

Travis Miller

analyst
#56

Hi, everyone. Thank you.

Ted Geisler

executive
#57

Hey there.

Travis Miller

analyst
#58

Thanks for all the detail. That covered most of what I had, but I've got a couple of quick follow-ups. On the transmission side, how do you expect the costs to be split between the large load customers or that subscription program and then the traditional retail FERC rates?

Ted Geisler

executive
#59

Yeah, Travis. The first thing is that it's rate-based within the FERC rate base, but how the cost gets allocated will hinge on the driver; it's hard to lay out in detail because it just comes down to what that incremental transmission is needed for. Some of it is simply required so we can replace aging infrastructure and boost resiliency. Some of it is for adding capacity to the transmission system, given the growth we're seeing across the broader service territory, and then some of it comes from adding new generation. Transmission that's specific to a customer premise is governed by the tariff rate formula and will call for customer payments and contribution as well as, of course, any benefit from that transmission to the broader system winds up contributing to the broader rate base; it truly is a mix of all those drivers, but the bottom line is similar to assigning generation investments to the growth that's driving it; we're making sure these large customers pay their appropriate share of the transmission costs that they're causing as well.

Travis Miller

analyst
#60

Alright, understood. One more thing — the 50 basis points, the path to getting that 50 basis points, how are you thinking about the timing, or what's your objective when it comes to the timing on that lag?

Andrew Cooper

executive
#61

Sure, Travis; this is Andrew. We recognize it will take a while to catch up in a meaningful way from the lag, simply because we're still operating under a historical test year dating back to the middle of 2021. Our expectation is that rates will be in effect from the rate case through 2027. Under the timeline we've put forward for the formula, our first formula filing would happen in May of 2027, and those rates would take effect toward the end of 2027. That's essentially the first chance for us to start meaningfully catching up at that point. We're moving it forward from a 2024 test year to a 2026 test year. Then, with that second formula filing in May of 2028, that will be the first chance to be on a full annual cadence of formula rate filings. Once that 2028 filing is processed, we'd expect you to be in a position to earn substantially closer to your authorized return, and those rates would become effective at the end of 2028. You won't see much impact from them in 2028, since December is when we anticipate rates taking effect under the formula rate. So really, 2029 turns into the run rate going forward, with the ongoing benefit from the formula rate that we expect to come out of this rate case.

Travis Miller

analyst
#62

All right, that's great. Understood. Just one more quick thing. Could the election results possibly push back when the GRC decision comes, or has that happened before?

Ted Geisler

executive
#63

Yes, as of right now we don't see any link between the two for the rate case. The first thing we're waiting for is the administrative law judge to finish his recommended opinion and order, and we expect that in the next few weeks. The commission has stayed quite focused on making sure this case gets wrapped up this year. So we would still expect that to happen in December, no matter when the election falls or how it turns out.

Travis Miller

analyst
#64

Okay, perfect. No, appreciate it.

Ted Geisler

executive
#65

Thank you.

Andrew Cooper

executive
#66

Thank you, Travis.

Sophie Karp

analyst
#67

Good morning to you. I appreciate your time in answering my question.

Ted Geisler

executive
#68

Good morning, Sophie.

Sophie Karp

analyst
#69

You mentioned this DPC element that's essentially prepaid revenue. Could you expand on that a bit more, and perhaps can we start to put a number on how much of the capital requirement that feature could cover?

Ted Geisler

executive
#70

Yes, Sophie, we can address that in general terms. This all falls under the wider credit support we look to put in place so that these new big projects and the related infrastructure can be backed by additional credit support, which keeps the company financially healthy while we serve these sizable infrastructure investments. That support combines cash CWIP and deferred revenue prepayments. We determine it with each counterparty based on how the investment spend is profiled, its timing, and its size; so it's a general framework, but the timing and cadence of that cash will be unique depending on what the infrastructure requires, how much infrastructure there is, and what's needed to keep the company's credit profile intact throughout that build.

Sophie Karp

analyst
#71

Understood, thanks. So regarding the IRP, I suppose, have you given any consideration to nuclear upgrades? A number of your peers out east, non-regulated, are pursuing quite a few of those. Could that be an option in your case?

Ted Geisler

executive
#72

Yes, Sophie, we've examined whatever opportunities might exist at Palo Verde, but every meaningful upgrade has already been completed there. All the steam turbine generators have already been replaced, for instance; so I think any remaining opportunity would really not be very measurable. Rather, our focus is more on investing in the plant over the long term, making sure we can reliably support its subsequent license renewal, and then also putting money into digital modifications. But as for incremental upgrade opportunities, we don't believe they exist in any meaningful form at this point.

Sophie Karp

analyst
#73

Understood. That's great. Thanks. I'm finished.

Ted Geisler

executive
#74

Thanks.

Andrew Cooper

executive
#75

Thanks.

Anthony Crowdell

analyst
#76

Morning, everyone. Great work. I’ve got just one quick question, on—I believe you lifted the midpoint of your 2026 guidance by $0.50. Q3 year-over-year rose only around $0.10. So what portion of that increase was weather versus sales growth, and how much of it continues into 2027?

Andrew Cooper

executive
#77

Hello, Anthony. Sales growth that beat our forecast across customer classes was the main force behind the guidance raise. It has simply been sizable. We’re seeing residential sales growth, including new customers coming into the service territory plus higher usage, and then some of our large C&I ramping faster than forecasted—that is the key driver. We also got a small lift from weather, and that's been fairly steady all year. It hasn't come as a single sharp spike from one weather event. We saw weather-related gains in Q1, Q2, and Q3. The revised guidance does account for what we know about October, which was milder. But at bottom, this has been a sales-growth story, and we've used part of that to offset some O&M risk down the road. On whether that's sustainable, I think you can see we've carried that 8%-10% sales growth beyond 2026 as well. The mix shifts a little there. You'll note that for 2026, large C&I accounts for a meaningful share of it. We've seen large C&I growth in the double-digit teens, while residential growth came in above average this year. We believe customer behavior accounts for part of that; in Phoenix we had a March with nine days over 100 degrees, which prompted our customers to cool earlier than usual, and it looks like they simply never turned it off. If residential usage patterns return to more normal trends next year, and we combine that with the ramp we're seeing from both our manufacturing and large C&I customers, that gives us sustained continuous 8%-10%, just with a somewhat different mix than this year.

Anthony Crowdell

analyst
#78

Great. That's really useful. That's everything from me. I suppose I'll see you guys at your home court this weekend.

Ted Geisler

executive
#79

See you soon. That's right. Looking forward to it.

Ted Geisler

executive
#80

Steve, you there? If you are, we cannot hear you.

Stephen D'Ambrisi

analyst
#81

Hello?

Ted Geisler

executive
#82

Hey, Steve.

Stephen D'Ambrisi

analyst
#83

Hi there, is this coming through? My apologies for that.

Ted Geisler

executive
#84

Yep.

Stephen D'Ambrisi

analyst
#85

I'm not sure what happened—I think my headset dropped out. Good morning, and thanks for taking my questions. Apparently this is my first conference call. Just two quick ones. I'm wondering how we should think about scaling this IRP opportunity beyond the existing plan, and then any incremental committed load coming into a future IRP. For the first part, does that two-to-three-to-one kind of multiplier you're seeing of new resources to committed load hold as you keep adding new committed load? Then I think you mentioned that 40% of projects within the window are APS owned. Does that mix shift over time as penetration of DPC agreements increases, or is it more stable? Thanks.

Ted Geisler

executive
#86

Yeah, thanks for that question, Steve. I tend to view the incremental opportunities as falling into two buckets. First, we keep witnessing strong growth outside of data centers across the service territory. That's partly what drove the guidance increase. Sure, it's at a fairly high level of sales growth that we updated, but all the new projects and growth we see coming in sustain and defend it. There's always upside potential there from the current level, certainly, but it really is quite elevated, and we believe it's durable over the medium to long term. The clearer opening, though, is that our outlook leaves out any potential new large manufacturers or additional data centers that could sign contracts down the road. Until we're certain we've committed to serving them and have a contract in hand, those wouldn't go into that load growth forecast. Considering the queue of more than 20 GW, any project emerging from it during the 15-year span the IRP addresses would sit on top of the existing IRP, and serving each of those projects would require additional generation and transmission. Turning to your follow-up about ownership, Steve — we've consistently maintained that shifting away from the 10%-15% incremental generation ownership we've had historically toward roughly a 50/50 split represented a better-balanced strategy, and we're confident in our capacity to compete effectively at that level of ownership. At 40% we're moving nearer to it, though we continue to see room for further ownership upside, since we've demonstrated a record of bringing these projects in on schedule and within budget while making sure they deliver the reliability traits needed to serve that load. And one final point, Steve: within our service territory, there's no surplus generation. Each time we bring on a substantial new customer, we inevitably must secure additional generation capacity—there's no way around it. Beyond that, you'll also need to build out the transmission system so that fresh generation can be linked into the grid we already operate. Any time we add a customer or experience organic sales growth beyond the levels contemplated in our present guidance, meeting that demand will call for more generation and transmission capacity. That is one reason we are already developing plans for phases of Desert Sun and Saguaro beyond the ones we have announced, since we recognize that this capacity will be needed both to cover the later years in the IRP and to give us an opportunity to serve growth on top of what we have already committed to.

Stephen D'Ambrisi

analyst
#87

That's really clear, Ted. Many thanks. I appreciate you taking the time.

Ted Geisler

executive
#88

Thanks.

Operator

operator
#89

Thank you. That wraps up our question-and-answer portion. Everyone, that brings today's event to a close. You're welcome to hang up now, and we hope you have a wonderful day. We appreciate your participation.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Pinnacle West Capital Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Pinnacle West Capital Corporation earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Pinnacle West Capital Corporation or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.