PNE AG (PNE3) Earnings Call Transcript & Summary
November 12, 2026
Earnings Call Speaker Segments
Heiko Wuttke
executiveMorning, everyone — Heiko joining you too. Appreciate you spending time with us for this call covering the first nine months of 2026 results. I'm Heiko Wuttke, and I serve as CEO of PNE AG; our CFO Dirk Simons is here alongside me. Let me begin by taking you through the presentation and explaining how today's webcast is structured. Following our usual format, I'll open with a summary covering the first nine months of 2026, and afterward provide an update on operating business developments. Dirk will then step in to cover the financials. Once he's finished, I'll close out the presentation by sharing the outlook for what remains of 2026. We'll then open the line so you can ask questions. You can find the slides, as usual, on our investor relations website. Now, please turn your attention to slide four. But before we go through the highlights for the first nine months of 2026, I'd like to briefly mention our latest update: on 13th October we issued an ad hoc announcement about our guidance for the 2026 financial year. The primary reason for that guidance revision is that some individual projects have shifted into the following year. Transaction processes are taking longer than we originally expected, and some permitting procedures have run into delays. On top of that, we chose to keep certain operational wind farms in our own generation portfolio that we had originally planned to sell. Although this does affect this year’s earnings, the projects haven’t been lost. We anticipate that sales from the delayed projects will be completed in 2027, which ought to provide us with solid momentum as the year begins. In addition, the projects in our IPP portfolio that we’ve chosen not to sell right now keep generating energy for us and gain from better power prices. Even at the reduced level, EBITDA for 2026 is expected to be among the strongest results of the past 10 years. That said, I’ll return to the outlook later during the presentation; for now, I’d like to move on to the highlights of the first nine months. We hit some significant milestones this quarter, even though the market has been tough. We managed to sell projects across Germany, Poland, and France totaling 361 MW in capacity — that includes eight wind projects adding up to 320 MW and a single PV project at 41 MW peak. On top of that, we commissioned two wind projects with 52 MW: one at 18 MW for our IPP and another at 34 MW for third parties. After selling the Bokel wind farm, which is 25 MW, and bringing Gnutz Ost, at 18 MW, into the fold, our own IPP portfolio stands at 484 MW. Meanwhile, our later stage project phase three continues to expand, growing by 22%. I'll walk you through the details on the upcoming slides. If you look at slide seven, our onshore wind pipeline is 14.3 GW. Germany, which is our home and core market, still appears solid at 6.1 GW, and that represents more than 40% of the project pipeline we have. As I mentioned earlier, we sold off five wind farms with a combined capacity of 84.6 MW. That group consisted of three turnkey wind farms, including Bokel, with 70 MW of capacity. One 18 MW wind farm was completed for IPP, and another one of 34 MW was completed for third parties. In addition, in Germany one wind farm of 14 MW was in the construction phase, together with six additional wind farms totaling 104.2 MW for third parties. We also obtained new permits there covering 10 wind farms, 265 MW altogether. Turning to France, our core market, the project pipeline is steady at 1.5 GW, and we divested the project rights for a 10.8 MW wind farm. In Poland, another core market, we likewise sold project rights covering two wind farms, 225 MW combined. Moving to slide eight, our PV pipeline stands at 6.9 GW peak. Things are moving along well on the development side, since projects keep reaching more advanced stages. That pushed phase 3 projects up 44%, to 1.2 GW peak, compared with 842 MW peak when 2025 ended. In Germany, we're concentrating on hybrid projects that pair PV with BESS. We finished selling off a PV project in Poland with 40.8 MW peak capacity, and we secured permits in South Africa for 130 MW peak, in Poland — one of our core markets — for 197 MW peak, in Italy for 68.9 MW peak, and in France, another core market, for 13.1 MW peak. Turning to slide nine and our own portfolio for the first nine months of 2026, operating megawatts declined a bit compared with where we ended 2025, given the Q1 2026 sale of the Bokel wind farm at 25.2 MW, offset by the Q2 2026 addition of Gnutz Ost at 18 MW, and the figure was flat versus the first half of 2026. As of the close of Q3 2026, our operating capacity totals 484 MW. Of that, wind onshore in Germany accounts for 468 MW, wind onshore in France adds 11 MW, and the wood-fired combined heat and power plant Silbitz supplies 6 MW. Thanks to somewhat stronger wind yields, green energy output for the first nine months of 2026 reached 589 GWh, a 12% increase, while CO2 emissions avoided amounted to 445 kt. Hidden reserves accumulated within our portfolio decreased to EUR 151.7 million, compared with EUR 159.3 million at the end of 2025, due in part to their gradual recognition over project lifetimes and in part to project sales. Over 90% of our IPP projects rest on feed-in tariffs lasting 20 years, giving the IPP portfolio an average weighted contracted tenor exceeding 15 years. That points to appealing upside from short and medium-term opt-out opportunities that beat the EEG remuneration. I’d like to add a bit more detail on slide 10 about our services business, because it kept performing strongly—delivering growing high-margin returns through long-running contracts spanning at least five years. To start with, operational management and technical inspections are still expanding. Assets under operational management rose to 3.28 GW. For operational management, our customer retention rate stood at 100%. After entering the market successfully by the close of 2025, we now have a third BESS asset signed, and more contracts are being negotiated. And finally, we performed around 800 technical inspections at wind farms over the first nine months of 2026. Wind & Sites also delivered strong results, with roughly 490 wind assessments and expert opinions during the first nine months of 2026. We finished approximately 270 LiDAR verifications. In addition, our PPA-as-a-Service business did very well under the new Wattmate brand, with wind and PV PPA projects amounting to about 570 MW of output and a transaction volume of roughly 2,146 GWh. That's 2,146 GWh, of course. Bitbloom continued overseeing roughly 4.5 GW while holding onto customers at a strong rate. Within this segment, following a successful trial, we broadened our monitoring offerings to a single EU fund and one German IPP. During Q2 and Q3, a number of extra standalone performance verification assessments took place. We won a tender to assess the performance of an offshore wind farm belonging to one of the largest operators globally. The services segment's results make us very happy. Having said that, I'll pass things along to Dirk for the financials.
Dirk Simons
executiveAppreciate that, Heiko. Moving to slide 12, we saw revenue climb to EUR 150.7 million, a 6% gain versus the prior year, driven mostly by stronger project sales. Gross profit reached EUR 134.8 million, which is 21% higher than 2025. Normalized EBITDA jumped sharply to EUR 45.4 million, compared with EUR 26.6 million in the same period last year, powered especially by project sales both in Germany and abroad, along with stronger power generation results stemming from high wind yields and better pricing. Within other operating expenses there are extraordinary items that have offset the positive effects we've already captured from our cost reduction measures. We anticipate that the substantially lower cost base will start to show through in 2027. The drop in the financial result was driven primarily by an IFRS 9 fair value valuation effect of roughly EUR 5.6 million tied to a financial PPA. So it's basically a non-cash valuation effect and doesn't reflect any rise in actual financing costs. Moving to the segments on slide 13, I'd like to point out again that prior-year figures were adjusted due to changes in segment reporting. Consolidation now covers all group consolidations along with general overhead costs that couldn't be reliably allocated to operational segments. As a result, consolidation was renamed corporate functions and consolidation. Having said that, during the first nine months of 2026 we're seeing expansion in power generation and services, while output from project development has declined. Revenue in the project development segment went up, driven by an increase in project sales. However, total output declined, coming in at EUR 136.6 million versus EUR 220.4 million the year before, reflecting reduced construction activity. Consequently, EBITDA for project development fell to EUR 5.7 million, down from EUR 22.3 million in the prior year. In power generation, total output climbed to EUR 71.2 million from EUR 61.0 million a year earlier, supported by relatively stronger wind yields and better pricing. During the opening nine months of 2026, power generation's EBITDA rose 13%, reaching EUR 48.2 million. A robust order book pushed services segment total output up to EUR 29 million, compared with EUR 27.7 million a year earlier. The service segment's EBITDA contribution held steady at EUR 5.8 million. At the consolidation level, intergroup profit eliminations for the first nine months of 2026 came in considerably below the same period last year — largely a reflection of greater external sales and reduced intergroup construction work — which produced a better result. Turning to the balance sheet. Turning to the asset side, slide 14 shows that property, plant, and equipment along with inventories make up the biggest categories. These we view as investments held at stable values together with the current cash flows. Our cash position dropped to EUR 43.6 million because of spending on project development, yet it remains at a solid level. Equity declined to EUR 127.1 million, which mirrors the negative net income. The equity ratio came in at 12.1%. Despite this, our midterm goal is still an equity ratio of at least 20%, and we already expect a clear improvement in 2026. After adjusting for hidden reserves, the equity ratio was a comfortable 23.1%. Bank liabilities fell to EUR 492 million, which produced net debt of EUR 631 million; beyond that, it deserves mention that most of those bank liabilities consist of non-recourse project financing. To optimize our maturity profile further, during the first nine months of 2026 we issued the 2026/2031 corporate bond with a volume of EUR 36 million, thus taking early steps toward extending our maturity profile and partially redeeming the corporate bond maturing in mid-2027, whose former face value was EUR 65 million. We keep examining a range of options for strengthening our capital base; among them is consideration of possible capital measures, including debt financing. No final decision on this matter has been made as yet. With that, I would like to hand things back to Heiko for the outlook.
Heiko Wuttke
executiveThank you, Dirk. Ladies and gentlemen, that brings me to the outlook, which you can see on slide 16. As with others in the industry, conditions have been challenging for us through 2026 so far. As I noted at the start, we were forced to adjust our guidance in October. For the 2026 financial year, our normalized EBITDA expectation now sits at somewhere between EUR 65 million and EUR 80 million, with EBITDA of between EUR 60 million and EUR 75 million. As I said earlier, even at this reduced level, the EBITDA we anticipate for 2026 should still place among the strongest results achieved in the past 10 years. On the operating side of the business, our goal is to divest additional projects during the rest of the year. Our IPP portfolio's expansion will be consolidated during this year, before we build it up further over the midterm. Given our sharper emphasis on chosen core markets, we are targeting completion of exits for Turkey and Canada in 2027. Through our Focus & Deliver transformation and cost reduction program, we continue to be firmly on track. During the first nine months of 2026, though, those cost positions still contain program-related expenses tied to implementing the transformation measures. As execution of the program continues, we anticipate additional efficiency gains in the quarters ahead. As was mentioned last time, our focus now leans even more toward projects and solutions that offer high system and grid compatibility, including BESS applications, in order to meet German legislation that is upcoming. At present we are advancing several hundred megawatts of BESS projects both in Germany and internationally, though these are not yet reflected in our pipeline. Before wrapping up my presentation, I want to say a few words about the sales process we launched in order to identify investors as part of developing our business strategy further. That process remains underway, with several interested parties involved. The outcome, of course, remains open. I would ask for your understanding that we cannot share additional details about the process while it is ongoing, but we will keep the market informed of any relevant further developments as required under applicable law. As I near the end of my presentation, I want to stress once more that we are dedicated to sustainable growth and value creation that will hold up in the future. Even within a demanding market environment, we hold a substantial project pipeline along with a strong position in our core markets. At the same time, we keep evolving our business model, which positions the PNE Group for what lies ahead. That concludes our presentation, and I would now like to open the call for your questions.
Simon Scott
analystHi there. Could I just ask something about process, with respect to the sale process you're currently running? Do you have any indication when it comes to timeline, or any target you're aiming for? And just so we're clear on the technical side, if it does reach a conclusion, will you give the market the courtesy of an announcement right away?
Heiko Wuttke
executiveYes, thanks, Simon, for that question. Well, as I said in my last statement in the outlook, we can't provide more details, particularly regarding timeline or details of what's ongoing. But as soon as there's information we have to provide under the laws, we will inform the public and the market on this immediately. At this stage, we can't give any additional information, but information will follow as we have decisions that are open for the public.
Simon Scott
analystGot it. Thanks.
Holger Steffen
analystHi there, everyone. I've got a few questions for you. First off, I'd like to ask about the work you're doing to build wind farms. By the close of September, just one of the company's own wind farms in Germany was in construction. To me, that seems like the smallest volume in quite a while. Could you walk us through what's been happening and share an outlook for the quarters ahead?
Heiko Wuttke
executiveThanks for the question, Holger. If I heard you right, you're asking whether we can offer more of an outlook on the number of wind farms we'll construct over the next quarters. Is that right? I just want to make sure.
Holger Steffen
analystThat's right, and it explains why the volume is actually so low.
Heiko Wuttke
executiveOkay. Well, as you know, we're always in a sort of cycle in which we develop wind farms, get certain permits, and then either sell the projects at the turnkey level or make project right sales. The current cycle is simply at the point where some permits we now — and I believe we've announced this previously — we've obtained several permits and gone into auctions, and we're about to then see the projects, and that's mainly in 2027, when we will construct and then have a higher number of that as well. There will be additional projects in the remaining quarter, so in Q4, that are planned or where construction will begin; it will be roughly two to three projects that we will construct. But as I said, there's always a cycle of permits. Then construction starts, which isn't always the same each year.
Holger Steffen
analystGot it. On to my second question: in your service segment, EBITDA and EBIT came in fairly weak during the third quarter. Were any exceptional factors involved there, and how do you see the fourth quarter shaping up?
Dirk Simons
executiveThat really ties back to cyclicality as well; so nothing extraordinary is going on. In fact, the service business is performing quite well, as Heiko explained, since the order book is actually better filled than it was in previous years.
Holger Steffen
analystAll right, understood. Up to this point in the present year, you've taken on a fairly heavy tax load, presumably because of changes made to deferred tax assets and liabilities. Would you mind giving a quick explanation of that, and does this pattern carry on into the fourth quarter, or does it partly unwind?
Dirk Simons
executiveThose deferred taxes are in fact driven by the accounting under the IFRS percentage of completion. Truthfully, forecasting deferred taxes down the road is quite hard. Frankly, when it comes to deferred taxes, I'm not in a position to offer you any guidance.
Holger Steffen
analystAll right. That is, I think, a tricky subject. During Q3, you raised quite a lot the assets you classify as held for sale on the balance sheet, taking them to EUR 88 million, and the debt tied to them has climbed considerably, to EUR 98.7 million. Could you perhaps walk us through those numbers briefly?
Dirk Simons
executiveJust as Heiko said earlier, we are in fact still intending to divest assets out of our IPP portfolio as a whole; so the assets held for sale at the close of the third quarter take in the Heidelburg wind farm, along with the Heidelburg substation, and the wind farms at Stuvenborn, Hamwarde, and Boitzenhagen. Since we intend to sell these wind farms together with the substation, we have in fact reclassified them as held for sale. And clearly, we have to do the same with the corresponding debt positions too.
Holger Steffen
analystAll right, I understand. As you mentioned, or as we can see in your updated outlook, sales from the portfolio are now being carried out, and at this point they are not being carried out to the extent originally planned. I think you wanted to improve your equity ratio through these sales. Are you now counting on a new investor here, or are there other solutions for strengthening the equity ratio?
Dirk Simons
executiveStrengthening the equity ratio has nothing to do with finding a new investor, right? Going forward, we will strengthen our equity ratio mainly by achieving a positive net income. That is our objective going forward, and we are actually very confident that we will achieve this. There is no actually. The consolidation of the IPP portfolio is also not actually related to strengthening the equity ratio. It is actually-
Heiko Wuttke
executiveA result.
Dirk Simons
executiveA result, in fact, of deciding where our cash should go, right, and where the greatest value creation can be achieved, yeah.
Holger Steffen
analystMm-hmm. All right. For my final question, the new rules under the EEG and the grid connection package are still being debated. Are you anticipating any additional improvements regarding the critical points?
Heiko Wuttke
executiveWell, you referred to them as new regulations. In fact, since no decision has been made yet, we can't say whether this is final or whether calling them new is even accurate. What appears in the most recent drafts is really still a set of moving targets. As you've probably noticed, the decisions got pushed back in the parliamentary rounds to December. So there are still plenty of matters being discussed. From where we stand, we don't perceive, let's say, significant effects on the EEG as currently reflected in the draft. Naturally, on the grid package, it remains under discussion whether we'll see this redispatch topic or whether the focus will be only on, let's say, maximum capacities under the so-called systemdienliche Anschlussleistung; those, I believe, are the key points, but no decision has been reached yet. So there's no genuine improvement up to now, though it hasn't moved in the opposite direction either; we remain confident based on what we hear in the, let's say, in the background, that in the end for us, and as I said, we will focus our projects on a more systematic approach, including BESS, and by having projects that are not, from the majority standpoint, located in grid-constrained areas, the impact on our side won't be what it perhaps is for others. But once again, there's still a great deal of discussion in the background.
Holger Steffen
analystAlright. I really appreciate you answering my questions.
Heiko Wuttke
executiveHappy to help. Thank you.
Guido Hoymann
analystYes. Good morning, gentlemen. I have two questions, please. First, once more about the sell-down of own plants. Could you outline your plan there again? From what I understand, you still have one project or one asset that's ready for sale, and that would be all? Or what's the plan at this point? Have you now ended this process of selling it down? When do you want to build it up again? Maybe a summary of your plans here once more. My second question concerns this disposal process, or sales process. Are you in fact seeking a 100% owner, or would you also accept somebody taking a majority stake? Could you perhaps elaborate on that a little, please?
Heiko Wuttke
executiveOkay, thanks, Guido, for your question. On the IPP side, or the projects we intend to sell this year, yes, that's still upcoming. At the end of the day, we're talking about two or three projects that are under final negotiations, and that's it so far. As I said in my earlier comment, we then want to increase our IPP base again in midterm. That's an effect we plan for this year.
Guido Hoymann
analystAll right.
Heiko Wuttke
executiveRegarding the second part, well, I won't go into specifics, since as I said, there isn't much more I'm able to share with you about it. Ultimately, it comes down to what the offers are, and if in the end there is 100% that can be sold or can be purchased, that's the result we would, of course, welcome. That said, it isn't final, so we can't say how things will turn out; but 100% is something that, of course, makes a further process easy, as you can imagine.
Guido Hoymann
analystOkay, that's perfectly clear. Thanks.
Heiko Wuttke
executiveNo problem.
Heiko Wuttke
executiveAlright, since no one has anything else to ask, we want to thank all of you for joining today's webcast. We're looking forward to seeing you again next time—perhaps at the Eigenkapitalforum in Frankfurt on the 23rd of November, or on our next webcast when we publish our annual report 2026, which is set for the 24th of March 2027. Have a wonderful day, and thank you.
Operator
operatorLadies and gentlemen, this conference has now concluded. We appreciate your choosing Chorus Call, and thank you for taking part in the conference. You can disconnect your lines at this time. Goodbye.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete PNE AG transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to PNE AG earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in PNE AG or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.