Portland General Electric Company (POR) Earnings Call Transcript & Summary
July 25, 2025
Earnings Call Speaker Segments
Nick White
executiveThanks, Victor. Good morning to all of you. It's great to have you with us today. Before we get started this morning, I want to note that a presentation has been put together to go along with what we'll be discussing, and we'll be pointing to it during the call. You can find the slides on our site, investors.portlandgeneral.com. If you'll turn to Slide 2. A portion of what we say this morning will be forward-looking statements. We want to warn you that those statements carry inherent risks and uncertainties, and what actually happens could differ materially from what we expect. To learn about some of the factors that might make actual results differ materially, please see our earnings press release along with our latest periodic reports on Forms 10-K and 10-Q, all of which you can access on our website. Moving to Slide 3, the people guiding our discussion today are Maria Pope, our President and CEO, and Joe Trpik, our Senior Vice President of Finance and CFO. Once they've finished their prepared remarks, we'll open up the line for your questions; at this point I'm happy to hand the call over to Maria.
Maria Pope
executiveHello everyone, and thanks for being here this morning. Let's begin on Slide 4. During our second quarter, we saw solid performance throughout the company and meaningful strides on all 5 of the strategic priorities we've discussed on earlier calls. Those are: number one, putting money into clean energy objectives that our customers want; number two, doing everything we can to hold customer rates down; number three, backing the expansion of data centers and high-tech businesses along with economic development in the region; number four, cutting risk by how we run the system, hardening our infrastructure, and pursuing wildfire strategies; and number five, fostering a climate where Oregon's energy future attracts investment, refreshing our corporate structure, and bringing legislative and regulatory policy into alignment. Right now, we find ourselves where rapid expansion meets Oregon's ongoing dedication to clean energy, and at the same time we're working hard to serve customers dependably and at a cost they can manage. Let me walk through what's been accomplished in each of those areas. Clean Energy. So that we line up with the one big, beautiful bill and capitalize on the modifications made to investment tax credits along with production tax credits, we are doing a price refresh on our 2023 RFP while speeding up procurement under our 2025 RFP. Our company, our region, and the customers we serve are still solidly behind a decarbonized future, and we're adjusting so we can build on what we've recently achieved, and deliver the greatest possible value at the same time. Our attention is on locking in projects that satisfy the newest timing and domestic content stipulations, which lets us get the most out of crucial federal tax credits. Those credits play a major role in bringing down clean energy costs and holding customer prices as low as we can. Joe will get into the specifics of that soon. Customer affordability. Our pledge on customer affordability and our multiyear cost management initiative are in motion and producing results. During this quarter, we arrived at the hard choice to cut 330 employed and contracted positions, and process improvement efforts are now active throughout the whole company. No part of Portland General will be left untouched, and every person is taking part. Customer-driven growth. The robust growth we're experiencing keeps going. Notably, we continue to see steady expansion from data center and high-tech customers, over 16% versus the same quarter a year ago. That growth comes from more than a dozen text manufacturing and infrastructure companies, among them the imminent return of a major semiconductor company to PGE's cost of service. This powerful demand extends the substantial high-tech and data center growth path we've observed for more than 7-plus years, and it helps every customer by making grid-wide enhancements and infrastructure upgrades possible while distributing the company's fixed costs over a wider base. We're also happy that the Oregon legislature approved the POWER Act, which encourages growth and delivers more certainty around the ratemaking framework, opening the door to regulatory flexibility in how costs are allocated and enabling direct long-term contracts with data center customers. Risk management. There's still more for us to do when it comes to wildfire policy, and our efforts are aimed at backing policies that make mitigation standards clear, put financial backstops in place, and ensure victims get timely recovery. On the operations side, we're sharpening our attention on preventing and mitigating wildfires through system hardening and monitoring, fast response, and working alongside first responders, such as the U.S. We also worked with the Forest Service and the Oregon Department of Forestry, along with focused deployment of public safety power shutoffs when conditions are dangerous, toward an energy future for Oregon that can attract investment. Then, as we mentioned on our previous call, we intended to seek approval for a holding company. That notice went out on May 23. As of today, we have finished submitting paperwork to the Oregon Public Utility Commission seeking approval of a holding company, which would place the current utility alongside a distinct transmission business. The aim of this proposed update to our corporate structure is to bring down the expense of infrastructure and investments as we pursue clean energy objectives and meet growing demand for electricity from society, all while trying to hold customer rates down as much as we can; in addition, we collaborated closely with customers and the Citizens Utility Board to secure passage of the FAIR Energy Act, which provides significant clarity for upcoming regulatory cases. This shifts Oregon toward multiyear ratemaking that is more predictable and delivers added flexibility and chances for securitization, plus the ability to change when new customer prices begin. In proceedings before state regulators, we have deepened cooperation with every party, and a recent MOU with interveners and staff covers both the Seaside Battery Filing submitted in May and the Distributed System Plan Alternative Recovery Mechanism, or DSPARM, which we are submitting later today. These results make us quite pleased, since they fold in the FAIR Energy Act's requirements and lay out a clearly defined route ahead. Together, multiyear rate making, that MOU, and further regulatory enhancements push Oregon toward greater predictability in regulation, while helping us plan and execute with more accuracy. I'd like to acknowledge PGE's legislative and regulatory groups for their outstanding efforts and the results obtained this quarter; that covers meaningful advances on many intricate matters, results that propel PGE in serving its customers; let's now move to Slide 5 for the financial figures, after which I will hand things to Joe. During the second quarter, GAAP net income came in at $62 million, equal to $0.56 per diluted share. Excluding certain items, net income stood at $73 million, or $0.66 per share. That is measured against second quarter GAAP net income of $72 million, or $0.69 per diluted share. The Q2 2025 non-GAAP figures leave out business transformation and optimization costs tied to our commitment to customer affordability and the changes to our corporate structure; this quarter has been a hectic one for Portland General Electric. We keep extending the momentum from the first half of 2025, meeting expectations and producing results. Our strategic priorities and ongoing execution remain our sharpest focus. I thank the whole PGE team for what you did this quarter, delivering safe, dependable energy to our customers and strengthening our solid operational abilities to create value for our stakeholders and the communities we serve. With that, I'll pass it to Joe.
Joe Trpik
executiveThanks, Maria, and good morning to all. For PGE, the second quarter was certainly a hectic stretch, and we managed to get over numerous obstacles throughout the company. If you look at Slide 6. What we see in our numbers is a large rise in demand from industrial clients, gentle spring weather, and our cost management and optimization program reaching maturity. Overall, total load rose 4.9%, and on a weather-adjusted basis it was up 6.1% versus the second quarter of 2024. Residential load fell 2.3% from one quarter to the next, yet on a weather-adjusted basis it gained 1%, which shows how much warmer April and May were compared with typical conditions. The number of residential customers grew 1.4%, though ongoing energy efficiency offset that. Commercial load was up just a bit, 0.3% on an overall basis, or 0.7% when adjusted for weather. Industrial load, especially from data centers, kept speeding up, with second-quarter demand rising 16.5% both nominally and on a weather-adjusted basis; we anticipate that demand from our industrial customer class will keep growing, which supports our reaffirmed weather-adjusted 2025 load guidance of 2.5% to 3.5%; over the longer term, following the 2023 CEP/IRP update released in June, we incorporated new load inputs that further strengthen our long-term growth expectations of 3% through 2029. Let me now walk through the earnings driver for the quarter; total revenue went up by $0.32, which came from a $0.12 gain tied to the 4.9% demand growth and a $0.20 gain from the average price of deliveries thanks to better recovery, partly offset by shifts in delivery composition; power costs produced a $0.20 decrease, reflecting a $0.12 EPS drop from power cost performance in 2024 that flips for this comparison; and an $0.08 decline from current-year power cost performance caused by less favorable conditions in the wholesale and environmental credit markets; a $0.06 EPS gain from reduced operations and maintenance expenses as we start to capture the benefits and savings of our cost management and optimization efforts; a $0.13 EPS drop from other operating expenses tied to ongoing rate base investments, split into $0.10 from greater depreciation and amortization and $0.03 from increased interest expense; an $0.08 reduction from other items, comprising $0.04 from dilution and $0.04 from other miscellaneous items; and finally, a $0.10 decline from business transformation and optimization expenses as we revise our practices and corporate structure to gain better financing flexibility and bring down our long-term cost. That takes us to GAAP EPS of $0.56 per diluted share. Once we adjust for the $0.10 impact, we arrive at Q2 2025 non-GAAP EPS of $0.66 per diluted share. Let's move to Slide 7 for our five-year capital forecast. We made a small cut to 2025 — our 2025 forecast — because of efficiencies in our capital execution this year. On the whole, we plan — our plan keeps supporting our growth trajectory and the rising needs of our customers and region; moving to Slide 8, I'll go into the meaningful regulatory and stakeholder progress that Maria mentioned earlier. Following extensive engagement with regulatory stakeholders, PGE signed an MOU in June with OPUC staff, the Oregon CUB and AWEC, which will oversee 2 important cost recovery proceedings. To start, the Seaside Battery Project came back into service faster than expected — it started delivering power to customers in early July — and this filing proposes wrapping up in October 2025. Then there's the DSPARM, a different cost-recovery route for distribution system assets, with a proposed finish of April 2026. Thanks to the MOU, the soonest we could file for our next general rate review would be after Q2 2026, and the soonest new rates could take effect is May 1, 2027. Together, those 2 cases spanned roughly $600 million in essential rate base investments that serve customers, while also making our regulatory route and forward-looking strategy clearer. Now on Slide 9, where we'll cover resource planning and procurement. Once the federal legislative package passed, PGE decided to run a price refresh for conforming bidders in the 2023 RFP. We ran something quite comparable during our 2021 RFP, which likewise had to work through changes in tariff and tax policy. That refresh is clearly a net plus, since bidders can now price in what used to be uncertain, which reduces risk and sharpens how key macro factors get weighed. Working alongside the RFP independent evaluator, we'll update bid scoring and ranking over the next few months to capture the pricing changes. Contract execution is still expected by year-end, and our 2027 COD target for these projects remains a firm commitment. Broadly speaking, we anticipate a comparable opportunity set from the 2023 RFP CapEx investments, which backs up our long-term growth expectations. As we mentioned in the recent CEP/IRP update, substantial procurement needs lie ahead of us, which is what drives the 2025 RFP — we intend to bring it to market within the next few weeks. Under the current time line, a final short list lands in the first half of 2026, with contract execution later next year, as we aim to finish the projects by the end of the decade. Our selection approach will keep using lease cost and lease risk, and it will adapt to reflect the shifting tax policy landscape and the effects on customer prices for RFP projects. Right now, tax credit exposure looks limited for the 2023 RFP projects, particularly with the firm end of 2027 COD requirement. When it comes to the 2025 RFP projects, tax credit eligibility will be crucial as we weigh acceleration to hold customer prices — price impacts — as low as we can. Across both the 2023 and 2025 RFP, our focus is on capturing the most tax credits possible to soften customer price impacts. Next, Slide 10 covers our liquidity and financing summary. Liquidity totaled $980 million at the close of Q2, and since last quarter our credit ratings and outlook haven't moved. As of June 30, we have $104 million of equity priced but not yet drawn under our ATM. Our overall equity target for 2025 stays at roughly $300 million to support our capital program. While our holding company application moves forward, we'll keep assessing our financing needs as we pursue the most efficient choices for our customers and shareholders. This strategy allows us to lower expenses, provide better service to customers, and open up flexibility in the way we finance essential grid projects that back the rising need for clean, dependable power. It also aligns nicely with the wider cost-management effort we have underway, which is expanding according to plan to cut expenses throughout the company. Nothing is being overlooked, and we have — as we sharpen our methods and streamline our structure so we can operate safely, fulfill our financial obligations, and hold customer rates down as much as we can. We feel good about how we have performed so far this year and stay dedicated to hitting our plan for the entire year. What we accomplished in Q2 has us positioned for a strong result. We are restating our 2025 adjusted earnings guidance of $3.13 to $3.33 for each diluted share, along with our long-term projections for earnings and dividend growth of 5% to 7%. We continue to concentrate on operations that are safe, dependable, and efficient, pushing our strategic goals forward, and meeting our pledges to bring value to customers, communities, and shareholders; and at this point, operator, we are prepared to take questions.
Richard Sunderland
analystThere's a great deal happening right now. Thanks for all the detail. Perhaps I'll begin with the MOU along with the Seaside and distribution recovery cases — in your view, how does that MOU shape the route to genuinely making headway through those 2 cases, as opposed to a broader general rate case? What I'm wondering is how you expect these cases to differ. Is the sole emphasis really on whether the capital was prudent? To put it in wider terms, how are you viewing that $600 million of rate base you called out as sitting inside those 2 cases, and how will intervenors assess it given what the MOU says?
Maria Pope
executiveWonderful. That's a wonderful question. So to begin, I believe we've truly put much of the conversation up front concerning the Seaside Battery Projects, which, incidentally, run at full capacity and deliver enormous benefit to customers, holding power costs down as we move through these sweltering summer months. Yet since we also incorporate the Distributed System Plan, plus a great share of our capital sitting in the distribution network for customer growth and reliability alike, we can hold many of these discussions prior to ever entering a rate review case; that creates genuine comprehension and jointly reached results when we submit the filings under those MOUs. The initial one, we're hoping to wrap by October. That one concerns the Seaside Battery Project, and the DSPARM comes in April. Still, once more, I believe we're bringing interests into line, sharing an understanding of the effort we're undertaking, which ought to produce certainty, predictability and value creation.
Richard Sunderland
analystGot it, that's been really useful. Let's move over to the RFP subjects. You said that being eligible for tax credits matters a lot for the '25 RFP. I suppose, if we look back at 2023, what's your thinking on the price refresh and the chances to get those projects done in the second half of the year? Could some of the procurement from the '23 RFP be sped up, since that's where you appear less worried about tax credit eligibility? I guess when it comes to '23 against '25 RFPs, are there any other dynamics worth pointing out?
Joe Trpik
executiveRichard, when it comes to the 2023 RFP, yes, there is a chance to accelerate. The reprice is going to be available to every bidder who made the original short list. That means the selection will get broader. I mean, we do see it as a — I think it's a solid chance to create certainty here. We're expecting performance along the lines of what we saw in the prior case. But the entire purpose of this reprice RFP is really to give these bidders clarity. And then too, I know we've been discussing '23, but with '25, to begin moving fast on '25 so we can hopefully find — to have the time to figure out which bidders possess the tax credit capability for those projects as well.
Richard Sunderland
analystUnderstood, that's useful. And then, apologies, just one last housekeeping item from my end. Regarding the business transformation work and the associated expense, will those carry on through the remainder of this year and into the next one? Or is it more of a one-time item tied to this quarter?
Joe Trpik
executiveYes. When it comes to the business transformation, we're only at the beginning. I'd say we're quite enthusiastic about the momentum we've built up. Our expectation is that we'll take on cost or investments tied to the business transformation into next year — a set of expenses connected to change management plus other items. But obviously, the benefits will begin to truly materialize later this year and then generate fairly substantial momentum going into next year; however, on the cost exclusion side, that's something that will extend into '26.
Chris Ellinghaus
analystMaria, could you speak a bit about 3179 and a few of the constraints contained in that piece of legislation, regarding rate timing and similar matters. Would that lead you to make changes when attempting to schedule investment? Or do you believe it's simply something you can navigate?
Maria Pope
executiveCertainly; to begin with, the legislation you mention is the FAIR Act, and it was something we developed jointly with the Citizens Utility Board, with customers, and we're quite happy that it opens the door to genuinely examining multiyear rate making. And we're likewise concentrated on making certain that every one of our systems and our processes line up with customer prices taking effect from April through November, rather than across winter's hardest months. So a great deal of that is internal effort on our part and isn't an issue, though it's simply work that needs completing. On the whole, we're quite satisfied with the chance to have greater securitization. And we've held many productive conversations about what sound long-term rate making resembles in today's conditions and as we move ahead. I believe our MOUs that we just mentioned while responding to Richard's questions align with that same thinking of how we collaborate more effectively for results that guarantee sufficient investment for our state of Oregon's economic growth, for customers and for reliability and affordability, all while providing value to every stakeholder and solid returns on equity.
Chris Ellinghaus
analystAll right. Regarding SB688, could you describe how you see us making use of PBRs?
Maria Pope
executiveWhen we consider what you — the legislation you're mentioning is something we refer to as the POWER Act, and in looking at it, we're focused on performance metrics tied to our fundamental operations. In terms of performance-based ratemaking, I don't believe we've spent much time discussing this with our regulators, and I'm not particularly worried about resolving these matters. Clearly, we require clean energy along with energy efficiency, and these concepts aren't novel. In fact, you may be aware that we operate some of the most effective energy efficiency programs anywhere in the nation. And for Portland General Electric's customers, we offer the #1 clean energy program. Yet as we also consider serving a customer base that is both diversified and expanding, especially data centers and semiconductors, all of these elements function in tandem.
Chris Ellinghaus
analystAll right. Regarding that MOU — and it likely doesn't matter much, considering when the next GRC filing lands — but looking ahead, will that MOU affect how ARMs get utilized down the road?
Maria Pope
executiveNo. My sense is we'll keep those discussions going and keep evaluating what will work best, given the various work ahead of us and how we can serve customers most effectively. Joe, would you like to add anything?
Joe Trpik
executiveAbsolutely. That MOU represents a one-time matter tied specifically to these, and then you have the same situation when it comes to the arm. The ARM itself is a particular item, and from our perspective on ARM Seaside, it serves as a solid bridge connecting where we stand today, the upcoming rate review, and eventually a plan spanning multiple years. In our view, this fits well alongside the legislation that has emerged regarding when rate cases should occur. It also remains connected to our broader growth strategy — specifically how these rate reviews might be structured so that we can keep costs as low as possible for the customer. We're able to control our own expenses and handle certain internal matters that genuinely carry us across what amounts to a longer stretch of time, while also bringing some clarity and certainty as we navigate the regulatory framework in the years ahead.
Chris Ellinghaus
analystAlright, that's useful, Joe. And one final thing — you handed us a number of dockets to sign off on over the weekend. Do you still anticipate that the Seaside intervener testimony will get filed at some point today?
Maria Pope
executiveWith any luck. I'd add as well that additional items are still on the way. So Chris, the DSP should be landing in your inbox later this afternoon. And obviously, the Holdco and Transco filings have all come through this morning.
Chris Ellinghaus
analystYes. You certainly handed us plenty to work through. I'm grateful for that.
Brian Russo
analystThis is Brian Russo, filling in for Julien. Given House Bill 3179 along with the DSP filing in the ARM, how do you anticipate your ROEs moving before you secure new base rates? My understanding is that 2025 guidance presumes 8.8% to 9.1%, compared with your 9.34% allowed ROE. Do you believe you're able to hold that kind of return level? Or ought we to anticipate some erosion because of when the next base rate case falls?
Joe Trpik
executiveOur aim in this situation is that combining our cost management actions with the timing of these cases really keeps us in that same kind of earnings position. We don't anticipate any further lag. The range you calculated on the earned ROE side, I believe, remains where our expectation sits, even when factoring in this legislation. Honestly speaking, our regulatory plan and our growth plan envision something quite close to this. Therefore we would anticipate our performance, that relative earn to allow, staying consistent across this period.
Brian Russo
analystAlright, excellent. So the update for 2023 on the CEP and IRP is asking for an additional 800 megawatts of renewables plus storage. And I'm wondering, given the OBBB, does that make Portland General more competitive, basically boosting the win rate, which as I understand it has been around 25% historically?
Maria Pope
executiveWe refer to 25% as roughly a baseline embedded in our financial forecast. However, what we've actually delivered has gone beyond that number. When we collaborate with parties on projects that ultimately become owned assets, our sole focus is on Portland General Electric customers. Serving other customers isn't what we're considering. So our attention stays on satisfying the needs of this particular region, while also ensuring we remain very cost conscious and cost competitive, since every one of these projects is lease cost, lease risk competitive. Our track record in the past is strong. Beyond that, we have several PBAs entering our service territory too; and in fact, those show up in the financial statements, since we break them out somewhat separately under the energy procurement line. So we maintain a balance with all parties to ensure we're delivering least cost, lease risk, clean energy options for customers.
Brian Russo
analystOkay. Then finally, if we assume the Holdco review and approval takes 12 months, what should our expectations be regarding the new structure and capital markets initiatives around August 2026? Does the $300 million per year still stand, with 50 to 50 financing for RFP related investments? Or could this Holdco structure change that and, I suppose, simply improve efficiency?
Joe Trpik
executiveRegarding the Holdco, we are eager to move through the proceeding here into next year. Driving flexibility is the purpose of the Holdco. So once the Holdco is finally defined and established — and keep in mind, there would also be a Transco — we will assess the flexibility it offers, how it lets us deliver greater benefits for our customers and for us; and during that period, we will also reconsider what that means for our financing plan. We simply want to hold off and observe how this unfolds, and then determine how we can most efficiently, over time, generate whatever benefits the Holdco will bring.
Nick Campanella
analystYeah, those are several solid questions. Let me ask a brief follow-up regarding the RFP repricing. From what you're saying, it appears you continue to perceive a strong chance to retain ownership under whatever scenario plays out, though with rates possibly coming in greater — does that add to the existing 9% rate base CAGR presented on your slides? Might there be other places within the plan that offset it? Could you discuss how capital gets prioritized across the plan right now? After that, what's your thinking on how to fund it?
Joe Trpik
executiveAbsolutely. Regarding the foundational plan, which we refer to as specific capital, it clearly leaves out whatever comes from the RFP, and beyond that sits the illustrative growth. What I'm saying is this merely supports that illustrative growth we presented at a 25% rate, correct? Back in 2021, we achieved roughly a 60% win rate. Still, our view is simply that repricing at this point creates a chance to build in certainty. In our estimation, it produces a quite comparable set of opportunities both for total megawatts and for how we perform across the whole portfolio. Basically, our take is that this repricing brings certainty into what had been somewhat uncertain times.
Nick Campanella
analystAll right. All right. So regarding the distribution filing you plan to release today, assuming it receives approval, you would then proceed to submit the following case afterward. If this kind of structure is in place moving forward, how would rate cases appear? My guess is that from an ask perspective they would be less burdensome, though perhaps you could walk through a few of the pluses and minuses regarding what that benefits?
Maria Pope
executiveMy view is that we consider the pluses and minuses as a whole, in the aggregate, and it truly comes down to solid discussions with every stakeholder, making sure there's alignment regarding the efforts we're undertaking, holding customer prices down to the greatest extent we can, while also making certain we back and facilitate the expansion throughout the region that is creating an impact in our economy.
Joe Trpik
executiveNick, if I may jump in here, right? So when we look at these situations, right, I mean, we've said fairly plainly that there's the Seaside tracker, followed by the DSP, and then some form of rate review during the committed period, correct? What we're aiming for is predictability, on our end and for the stakeholder as well. It gives us room to keep pushing the cost benefits we're bringing into the organization so they can yield here. But in the end, I view all of this as stages on the road toward the multiyear — a multiyear plan, one that arrives at a point, I think, for both sides where clarity is possible and we can have clarity across longer stretches of time here, rather than these smaller steps, though I'd say at this moment, I think there are some fairly clear, thoughtful, aligned steps that we have?
Gregg Orrill
analystI wanted to ask whether you might discuss how the remaining portion of the year's earnings bridge compares with the prior year — specifically the variable power margin factors that reconcile that difference, which I believe sits near $0.40 at the midpoint?
Joe Trpik
executiveComparing 2024 with 2025 presents some difficulty. In '24, as you remember, the front end carried a great deal of weight. Actual results did land above the midpoint of our guidance, yet much of those earnings arrived during the initial six months, tilted toward rather strong market conditions that showed up both in load consumption and in favorable pricing simultaneously. And in Q3 and Q4 of the prior year, as you recall, things fell away rather sharply, with Q4 turning in a notably weak showing. This year, given how the energy markets have positioned themselves and how cost management and the cases have positioned themselves, we view the plan as far more evenly spread; from where we stand today, we simply need to keep progressing along our path of remaining on our net variable power cost plan for the year so we achieve our results; so in our view this year looks considerably cleaner, with a less unusual flow, correct? It's the prior year that generates the greater share of the uncertainty; and our confidence is fairly high. That is, given our cost management position and recognizing that April and May ran warmer, we believe we're positioned quite well to deliver a solid performance, assuming market price and load consumption stay within normal bands.
Sophie Karp
analystI appreciate the detailed briefing you provided earlier today. I'd like to dig a little deeper into the topic Nick raised. With the Seaside tracker now operational, I'm curious about distribution recovery as a separate matter — what amount of capital would be preserved, and might it later be exposed to general rate reviews and rate cases? Could you offer any percentage that would clarify how much the importance of rate cases might shrink going forward?
Maria Pope
executiveAbsolutely. Sophie, the most useful approach there is to look at our forward-looking capital plan. If you look at slide 7, you'll notice that the bulk of what we're spending on capital goes toward distribution. A significant portion of that involves the reliability-focused work we perform. A lot of the territory we cover experienced fairly dramatic growth roughly 40 to 60 years back, so that infrastructure is aging and requires considerable replacement. On top of that, there's the renewable adjustment cost, or RAC, which applies to every wind and solar project. That gives us an additional mechanism to bring customer prices into the picture. And then for wildfire, we also have the AAC. A great deal of solid effort has gone into making things more predictable, and that also improves what we can do when it comes to planning operations and carrying out disciplined plans spanning 5 years.
Sophie Karp
analystOkay, okay, okay. So yeah, it sounds like a significant portion of that capital is going to be recovered closer in time to when these mechanisms are in play. Could you remind us what determines, I suppose, the permitted ROEs across this whole set of capital expenditures? Will an ROE be established during this rate review, or through some other proceedings? How exactly does that function?
Maria Pope
executiveWell, examining the ROE would necessitate a general rate case, and we intend to file one down the road. However, at present, we have a very solid bridge thanks to excellent recovery — recovery possibilities for the capital we just talked about, along with several other enhancements stemming from our cost structure and financing options.
Sophie Karp
analystGreat. Great; and finally from me, I suppose. My assumption is that your upcoming rate case would already be a multiyear one?
Maria Pope
executiveThat is — we're going to begin holding that conversation with parties, and I wouldn't want to get ahead of those talks. There are advantages to that, since it allows for more certainty regarding the sort of blocking and tackling type of capital that we do, which we've benefited from for a long time when it comes to clean energy.
Joe Trpik
executiveIn my view, Sophie — and this is our view as well — we see a definite route to eventually arriving there. What I mean is, it will come down to simply collaborating alongside the groups to figure out whether that scenario fits, but we believe we're making solid progress along that route; and really it's only about — only about which scenario it ends up falling into.
Anthony Crowdell
analystI'd like to follow up on what Nick asked, and I believe Nick was building on Richard's question, though my sense is you might prefer not to address it; during another earnings call held earlier this week, a certain company discussed how, when you examine renewable projects and there are shifts in tax law, or to put it another way, simply some turbulence affecting the entire business model, such changes have helped particular developers while harming others. And when I — you folks had said, I believe your projection rested on a 25% win rate from the RFPs, yet you've realized, I think you stated, a 60% figure. Do you expect those figures to shift as the RFPs get repriced?
Maria Pope
executiveNo. I believe as we look ahead, we'll see which sorts of projects emerge; we do have quite a few highly advantageous partnerships with developers, yet we likewise have quite a few entirely third-party developers that submit bids. That 25% you're mentioning serves as illustrative within our forecast and roughly a baseline. As Joe said, our latest build percentages came in at approximately 60%.
Joe Trpik
executiveBuilding on that, when you consider where the IRP update landed, our view is that this reprice leaves ample space for everyone involved. We're anticipating fairly strong results. And going back to what Maria said, the 25% figure we're using serves purely as a guideline.
Maria Pope
executiveIt's worth keeping in mind that there's a strong window available to us as long as investment tax credits and production tax credits remain in place, since those can bring down clean energy costs quite a bit when it comes to what customers pay.
Anthony Crowdell
analystGot it. Now I want to pick up on Richard's earlier question. I think it had to do with transforming and optimizing the business. You said those charges would keep going through 2025, and that in '26 we'd start to see the benefits? I just want to check that I understood you right. And beyond that, should we expect the same magnitude — or the same actual amount — for those charges? Or does it improve as we get closer to when the benefits begin?
Joe Trpik
executiveThe charges will taper into '26, but at this point they're more front-end loaded, right? We're putting some pretty significant investments in here. When it comes to spending, the largest outlays will occur during 2025, with some spillover into 2026; the actual payoffs won't truly begin showing up until then. Naturally, some gains are coming this year, and more will arrive next year. As we discuss, we see those next-year gains plus the regulatory matters as forming a solid, well-defined route for us to keep delivering on our earnings spend; on the whole, looking at costs, that's fairly strong performance. Still, since transformational change is what we're after, we intend to move into these shifts carefully, one step at a time. Even so, when you look at how long it takes for the money you put in to come back as genuine profit, we're talking about roughly twelve months — a year at most.
Anthony Crowdell
analystWhen we look at our projections — and I think this ties into what Brian Russo asked — once this program begins producing results, ought we to revise the assumption we use for earned return, or is that not the message you're conveying?
Joe Trpik
executiveWhat I'd say is this: regarding our guidance on earned return, as I recall, at the midpoint we provided you a figure of roughly 70 basis points. Our view is that with the plan we currently have in place, we will maintain something along those lines — that figure is lower than what you've witnessed previously. Even so, we're confident the cost management plan will keep enabling us to achieve that earned ROE within the elevated range we referenced in our guidance.
Travis Miller
analystI believe you've already addressed the various follow-ups to everything I asked, but here's something at a broader level, perhaps a separate topic. As industrial demand keeps expanding and ends up representing a bigger portion of your overall demand, what's your current view? Or what changes do you expect when it comes to purchase power costs, those variable costs, and anything else tied to the wholesale market. I'm just curious whether industrial demand brings along a pricing environment of a different kind, if that's the proper term?
Maria Pope
executiveWell, to begin with, that's an excellent question and one that isn't simple. The first thing is that through certain legislation that was passed not long ago, the POWER Act. And keeping with Chris's approach, I'll share the figure, which is UM2377. We can enter into long-term contracts with major customers, especially data centers, agreements spanning 10 years or more, and that's going to matter a great deal for our ability to securitize that infrastructure investment and secure improved financing over the long term. When it comes to power cost, that extends all the way to generation projects, and overall that ought to ease power cost pressure for every customer. On the power cost front, a lot of what we've already been doing has delivered an enormous impact. I'd point out that we have slightly below 500 megawatts of battery storage, and that genuinely stabilizes customer prices, especially through those crucial stretches of summer and during cold winter days, plus we're making progress across Western-wide energy markets. We've stated our plan to join the energy day-ahead market, which the California Independent System Operator leads, and that too is going to matter significantly for procurement West-wide and for capitalizing on surplus renewable energy produced in the Desert Southwest and in California. We've already observed striking shifts in power flows, and we anticipate even more, all of which will solely help customers throughout our region as we strive to bring costs down.
Travis Miller
analystAlright. That's excellent. I appreciate it. Everything you mentioned, particularly regarding the contracting opportunity — will that lower some of the earnings exposure tied to net variable power costs, or does that earnings exposure stay the same overall?
Maria Pope
executiveI believe the place we need to focus on concerning net variable power costs is genuinely examining the fundamental rate design, certain enhancements we can implement within our PCAM mechanism, along with the volatility that we simply observe as the region grows and markets become tighter in general, plus finding a balance with the energy day-ahead market. We will need to work out how these fit together, since some conflicts are going to arise for us in late fall of 2026 once EDAM goes live.
Travis Miller
analystAll right. That's great, thank you. Just one small point to clear up. That base rate case's timing — does it fall under the DSP, or is it within the MOUs? Or are you simply anticipating when a base rate case or a DRC might become necessary?
Joe Trpik
executiveWithin the MOU, nothing has been settled regarding a not-before date for filing, nor a not-before point of Q2 — or the start of Q3 in 2026. So no agreement exists on that.
Travis Miller
analystAlright. Though it isn't mandatory, just...
Joe Trpik
executiveYou aren't required to submit it. That's the soonest point at which we would be able to...
Travis Miller
analystAnd once that's done, no filing is required on your end. All right.
Joe Trpik
executiveExactly right.
Maria Pope
executiveExcellent. We’re glad you could all be with us today. We’re grateful for your interest in Portland General Electric, and we look forward to reconnecting with you before long. Thanks so much. Have a wonderful day.
Operator
operatorWe appreciate all of you joining this call today. That brings the session to a close. Please go ahead and hang up at this time. Wishing each of you a wonderful day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Portland General Electric Company transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Portland General Electric Company earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Portland General Electric Company or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.