Power Grid Corporation of India Limited (POWERGRID) Earnings Call Transcript & Summary

February 3, 2020

National Stock Exchange of India IN Utilities Electric Utilities earnings 50 min

Earnings Call Speaker Segments

Rahul Modi

analyst
#1

On behalf of ICICI Securities, we welcome you all to the Power Grid Q3 FY '20 results conference call. We have with us the senior management of the company, comprising of Shri K. Sreekant, Chairman and Managing Director; Shrimati Seema Gupta, Director of Operations; Shri R.K. Chauhan, Director of Projects; and Shri V.K. Singh, Director of Personnel, along with Shri K.S.R. Murty, CFO; and Ms. Divya Tandon, Company's Secretary. Thank you for the opportunity. Over to you, sir. Thank you.

K. Sreekant

executive
#2

Thank you, Rahul. I'm Sreekant, Chairman and Managing Director of Power Grid, and welcome you all to the Power Grid Q3 FY 2020 Earnings Call. On this call, we have Mrs. Seema Gupta, Director Operations; Shri R.K. Chauhan, Director of Projects; Shri V.K. Singh, our new Director Personnel; Shri Sanjeev Singh, ED with CMG; Shri Anil Jain, ED, Corporate Planning; and our CFO, Mr. K.S.R. Murty and other officials. On 31st January 2020, the company has announced unaudited financial results for the third quarter. And I hope you have the opportunity to go through them. And let me begin with the performance highlights for the quarter and 9 months ended 31st December 2019. Project execution: The company and its subsidiaries added about 3,566 [ circuit ] kilometers of transmission lines, 3 number substations and 27,985 MVA of transformation capacity during the 9 months ended 31st December 2019. During the Q3, major elements commissioned include Pole III of plus/minus 800 kV Champa-Kurukshetra HVDC project in October '19; 765 kV double circuit Bhadla-Bikaner line, October '19; 400 kV single circuit Singrauli-Allahabad in October '19; Purnea-Farakka portion of 400 kV double circuit Rajarhat-Purnea line in November '19; second circuit of 400 kV Edamon-Muvattupuzha line in December '19; and STATCOMs at Udumalpet and Trichy in December '19. After the quarter ended December '19, we have also commissioned the balance elements of Power Grid tariff-based competitive bidding subsidiary, the [ PSITC ]. This is the -- these elements are the 765 kV double circuit Vemagiri-Chilakaluripet and Chilakaluripet-Kadapa lines in the Chilakaluripet substation. With this, we have 8 TBCB companies which have become fully operational. CapEx during quarter 3 was INR 3,953 crores, which included INR 977 crores of CapEx by the subsidiaries. For the 9-month period, the CapEx on stand-alone and consolidated basis was INR 8,125 crores and INR 10,485 crores, respectively. This year, we are targeting to incur CapEx of INR 15,000 crores on a consolidated basis, and we are likely to meet the CapEx guidance. Capitalization during the quarter ended December 31, 2019, the company capitalized assets worth INR 5,230 crores, excluding FERV, of which INR 60 crores are attributable to TBCB subsidiaries. The total capitalization for the 9-month period is INR 10,917 crores, including INR 253 crores attributable to TBCB subsidiaries. If we add capitalization of approximately INR 2,770 crore in January 2020, on account of PSITSL and other assets, capitalization in the current year till January 20 is approximately INR 13,700 crores. The company envisages a capitalization of INR 20,000 crores to INR 25,000 crores during the financial year '19/'20, on a consolidated basis, subject to completion of some elements of the Raigarh-Pugalur HVDC project. As I mentioned in the previous interactions, there we were facing severe RoW issues in the past. Much of it has been resolved, and the progress has picked up in the project substantially, and we are making all efforts to commission the same in this financial year. The capital work in progress as on 31st December '19, on a consolidated basis, was INR 37,956 crore, including INR 6,279 crore attributable to the TBCB subsidiaries. Coming to operational highlights. Power Grid's total transmission network, including that of its subsidiaries, as on 31st December '19, comprised of [ 1,61,864 ] circuit kilometer of transmission lines, 248 substations and 399,897 MVA of transformation capacity. With the use of state-of-the-art technologies, automation and digital infrastructure, the company continued to maintain very high levels of availability and reliability of its transmission system. The average availability of the Power Grid's transmission system up to December '19 was 99.81%, while the tripping per line during the period was contained to 0.32 trippings per line. Turning to the key financial highlights for the quarter and 9-month period ended 31st December '19. The total income increased by 7%, both on stand-alone as well as consolidated basis. On the stand-alone, the total income for the quarter was INR 9,497 crore as against INR 8,890 crore in Q3 FY '19. On a consolidated basis, the total income increased from INR 8,879 crores in Q3 FY '19 to INR 9,541 crores in Q3 FY '20. For the 9-month period ended December 31, '19, the total income on a stand-alone basis was INR 27,908 crores, which was 7% higher than that achieved in the corresponding period of FY '19. While on a consolidated basis, the total income increased from INR 25,793 crore (sic) [INR 25,973 crore] to INR 28,163 crore, registering a growth of 8%. EBITDA for the quarter was INR [ 8,588 ] crores and INR 8,621 crores on stand-alone and consolidated basis, respectively. For the 9-month period, EBITDA was INR 24,769 crore and INR 25,124 crore, respectively, on stand-alone and consolidated basis. In Q3 FY '20, the stand-alone profit after tax was INR 2,673 crore versus INR 2,332 crore in the corresponding period previous year, registering a growth of 15%. On a consolidated basis, profit after tax in Q3 FY '20 was INR 2,672 crores as against INR 2,346 crores in the Q3 of FY '19, an increase of 14%. For the 9-month period, the PAT on a stand-alone basis was INR 7,629 crores, which is 11% higher than that achieved in the corresponding period of FY '19. And similar growth was there on a consolidated basis as well. Other financial highlights. The company's gross assets as on 31st December '19 stood at [ INR 2,18,838 crore ] on a consolidated basis and [ INR 2,09,163 crore ] on a stand-alone basis. The company's net worth stood at INR 65,188 crore on a consolidated basis and INR 65,042 crore on a stand-alone basis. Total long-term debt as on 31st December was INR 1,44,027 crore on a consolidated basis and INR 1,43,737 crore on a stand-alone basis. The debt-to-equity ratio was 69 to 31. Financial highlights of the subsidiaries. As of 31st December '19, 7 TBCB subsidiaries were fully operational and PSITSL was part operational. Aggregate EBITDA of this TBCB subsidiaries was INR 391 crore, and INR 1,159 crore for the quarter and 9 months ended December '19. For the 9-month period of the current financial year, total income in fact for all subsidiaries on an aggregate basis was INR 1,193 crore and INR 242 crore, respectively. Power Grid has received a dividend of INR 145 crore from its operational subsidiaries for the 9-month period of current year as against INR 71 crore in the corresponding period of the previous year. Total of 11 TP subsidiaries are currently under implementation, of which 7 were secured in this financial year. Of the 11 subsidiaries under implementation, 7 are in the interstate and 4 in the intrastate. Trade receivables as on 31st December on a consolidated basis were INR 5,715 crores and INR 5,539 crores on a stand-alone basis. Book value as of 31st December was INR 124.33 on a stand-alone basis and INR 124.60 on a consolidated basis. The company realized an amount of INR 24,957 crore against a billing of INR 25,721 crore for the 9-month period ended December 31. Other business segments. Telecom. Telecom income in the quarter 3 was INR 174 crore as against INR 176 crores in quarter 3 of FY '19. And for the 9-month period, Telecom income grew about 6% to INR 517 crore. On the operations side, the cumulative backbone availability for the quarter was 99.92%. About 40 new customers were added during the quarter. I will now touch upon the issue of AGR-related license fee demanded by DoT. During our analyst meet in November '19, we had explained as to why the additional demands by DoT were not in line with the license conditions. And therefore, the Supreme Court order was not applicable to Power Grid. Based on the legal advice, we have filed an application before the Honorable Supreme Court for clarification [indiscernible] modification of its order dated 24th October '19, and our next course of action will be based on the outcome of this application. On the Consultancy business, our income for the quarter was INR 143 crore, and for the 9-month period was INR 439 crore as against INR 155 crores and INR 442 crores in the corresponding period of previous financial year. 7 new orders were received during the quarter. These include renewable energy generators and state power utilities. We have entered into an MoU for project management consultancy for transmission system to evacuate power from 1,500 megawatts of solar projects in Madhya Pradesh. During the quarter, Power Grid became the first Indian PSU to be accredited as Registered Education Provider of Project Management Institute. With this accreditation, Power Grid aims to provide various corporate and government agencies with relevant project management skills. And this is expected to provide an additional opportunity for consulting in the area of training and project management. On the international business front, total 15 assignments are -- were ongoing as on 31st December in Nepal, Kenya and Bhutan and other countries. We have secured 5 assignments during the quarter in Nepal and Bangladesh. These assignments were secured amidst stiff competition from global consulting firms. During the quarter, Power Grid opened in Kathmandu its first international branch office. The company also signed a cooperation agreement with Africa50 in November '19 for evaluating opportunities for development of transmission infrastructure in Kenya on PPP model through a joint venture in which Power Grid shall have equity stake. Other businesses, energy management. During the quarter, Power Grid signed an MoU with NIT Warangal to provide sustainable energy solutions in areas like space cooling, heating, water pumping, waste to energy. Discussions were also held for replacement of agricultural pumps under an annuity model in the state of Bihar. EV charging. During the quarter, fast chargers were installed at 2 more locations at Hyderabad, taking the total Power Grid chargers in Hyderabad to 4, and 2 more are under implementation. A charging station is also in operation at Kochi. And recently, Power Grid has also been sanctioned to deployment of 11 number EV charging stations, comprising 55 chargers in Shillong, Meghalaya, under FAME Phase II scheme of the Government of India. Business outlook. As on 31st January '20, the works in hand stood at about INR 61,000 crore, comprising of ongoing and new works [indiscernible] I mean in the RTM framework, about INR 48,000 crore; and TBCB works of about INR 13,000 crores. These include projects worth about INR 3,384 crore assigned to Power Grid on regulatory tariff mechanism in the month of January 2020. Projects in pipeline. For various RE integration in -- of the RE potential zones, the transmission schemes of about INR 42,900 crores are expected to be executed. Of this, INR 14,700 crore of works have already been allocated, awarded till November '19. Subsequently, INR 2,900 crore works have been assigned to Power Grid on RTM basis. And another INR 11,000 crores have been recommended for implementation through TBCB. Of this, bills have been floated for 2 projects, estimated at about INR 1,250 crores. In addition, intrastate transmission works in Jharkhand estimated at about INR 5,400 crore are also under bidding. Awards and recognitions. During the quarter, the company won the D&B Infra award for 2019. With this, I conclude the initial remarks and would be happy to receive your questions.

Operator

operator
#3

[Operator Instructions] The first question is from the line of Sumit Kishore from JPMorgan.

Sumit Kishore

analyst
#4

My first question is on CapEx for FY '21. So basically, we looked at the union budget documents, and there it was mentioned that Power Grid has been earmarked with a CapEx of INR 105 billion for FY '21 versus INR 150 billion in FY '20. Your comments, please? And how much would be stand-alone and how much TBCB?

K. Sreekant

executive
#5

Yes, there is -- INR 10,500 crores is what is the expected CapEx for the 2021. This is on a consolidated basis.

Sumit Kishore

analyst
#6

How much of this roughly do you expect to be under TBCB, given that you have about INR 13,000 crores of TBCB projects in hand?

K. Sreekant

executive
#7

I'll give you that number separately. I mean -- just let the question pass, I'll give you this number separately.

Sumit Kishore

analyst
#8

Sure. And after your guidance of capitalization of 200 -- INR 250 billion this year, how do you see it panning out over FY '21, '22 with the works in hand that you have and the fact that CapEx next year is going to fall further?

K. Sreekant

executive
#9

See CapEx -- capitalization will arise partly from the CapEx and mostly from the works which are currently under execution, the CWIP which we have. Next year, the capitalization will be of the order of INR 15,000 crores. And out of the INR 10,500 crores, about INR 6,000 crores is on account of regulated business -- I mean -- I'm sorry. TBCB is about INR 3,400 crores. The rest will be on a stand-alone basis.

Sumit Kishore

analyst
#10

Got it. And when you say capitalization of INR 15,000 crore next year, that is on a consolidated basis? How much of that is expected to be TBCB roughly?

K. Sreekant

executive
#11

Next year, of the INR 15,000 crore, we'll just give you the TBCB capitalization separately. I'll give you that number, okay?

Sumit Kishore

analyst
#12

Sure. And sir, when you said that your works in hand is INR 61,000 crore, could you break that up into ongoing projects, new projects and TBCB projects as you usually do? I couldn't get those numbers.

K. Sreekant

executive
#13

Ongoing is INR 41,200 crores, new INR 6,800 crores. I gave you INR 48,000 crores as RTMs and INR 13,000 crores as TBCB.

Sumit Kishore

analyst
#14

Okay. So this is explaining that breakup. INR 41,200 crores plus INR 6,800 crores plus INR 13,000 crores?

K. Sreekant

executive
#15

Right.

Sumit Kishore

analyst
#16

And finally, in the new wins that you have had since your second quarter analyst meet, could you give some color on how much has been won? And how much is through RTM? And how much is TBCB?

K. Sreekant

executive
#17

Since the second quarter, we have got around INR 2,900 crores of works. On -- INR 3,384 crores were assigned on regulatory tariff mechanism in the month of January '20. There was no bidding in the TBCB after second quarter.

Sumit Kishore

analyst
#18

Okay. So basically the third quarter, INR 2,900 crores was entirely TBCB?

K. Sreekant

executive
#19

No, no. RTM.

Unknown Executive

executive
#20

INR 3,300 crores.

Sumit Kishore

analyst
#21

You gave 2 numbers. One was INR 2,900 crore.

K. Sreekant

executive
#22

No, no.

Unknown Executive

executive
#23

In '20 [Foreign Language] INR 2,900 crores is because of renewal. Yes.

K. Sreekant

executive
#24

We said, INR 2,900 crores related to renewable energy zones and 438 are -- [ INR 435 crores ] are other ISTS works. Roughly around INR 3,384 crores were assigned to us under RTM.

Sumit Kishore

analyst
#25

Okay. This is all RTM. Okay.

Operator

operator
#26

The next question is from the line of Abhishek Puri from Axis Capital.

Abhishek Puri

analyst
#27

Sir, could you elaborate on the dividend numbers that you have given for the quarter, that is INR 148 crores, right?

Unknown Executive

executive
#28

INR 145 crores.

Abhishek Puri

analyst
#29

INR 145 crores.

K. Sreekant

executive
#30

[indiscernible] has been received as dividend, which is INR 71 crores more than what we received in the last year.

Abhishek Puri

analyst
#31

And this is largely coming in from TBCB? Or is it from -- what will be the TBCB number?

K. Sreekant

executive
#32

We're talking of operational subsidiaries.

Abhishek Puri

analyst
#33

But operational will also have JVs also. This includes for JVs also? Or this is only from TBCB?

K. Sreekant

executive
#34

We are talking of operational subsidiaries, TBCB.

Abhishek Puri

analyst
#35

Right. Okay. That's INR 145 crores in the current quarter?

Unknown Executive

executive
#36

9 months.

K. Sreekant

executive
#37

9 months.

Abhishek Puri

analyst
#38

9 months. Okay. Okay. Okay. Got it. And secondly, with this new dividend distribution, tax removal from your -- from the company side, what is the thought process there? So the entire amount that was pushed out through tax will also be included in the dividend going forward?

K. Sreekant

executive
#39

More likely, from the company point of view, you're talking of Power Grid payment of dividend?

Abhishek Puri

analyst
#40

Yes.

K. Sreekant

executive
#41

That is very likely. Because that much of dividend will be reduced from the companies [indiscernible] to the government. I think they will increase the payout. Very likely.

Abhishek Puri

analyst
#42

Okay. And lastly, in terms of the utilization of cash going forward. And you are making close to about INR 11,000-odd crores profit now plus depreciation -- similar depreciation, and CapEx rate is going down to about INR 10,000-odd crores. So you'll be generating significant amount of additional cash flows? What are the debt repayment schedule that we have over the next couple of years? And potential to increase dividends?

K. Sreekant

executive
#43

No, no. Debt repayment will have to be met out of depreciation. Depreciation recovery cannot be used for payment of dividend. Okay? So we will have to balance between whatever is the CapEx and increase the payout of dividend if we have no CapEx to meet. So -- and that has been the trend so far. Successively, we have been increasing. And last year, we paid [ INR 8.33 ] overall dividend. Definitely, we will not like to keep idle cash.

Abhishek Puri

analyst
#44

Right. And if I may ask 1 more on the potential pipeline that you mentioned, you've said that INR 14,000 crore is ordered out, and balance is 30,000-odd -- or INR 28,000-odd crores has to be bid out?

K. Sreekant

executive
#45

Right.

Abhishek Puri

analyst
#46

And what is the pipeline? When will it be bid out? And if you can highlight on the other intrastate projects apart from Jharkhand that is available?

K. Sreekant

executive
#47

See, intrastate, the pipeline is not as usual as we expected. Interstate, we are expecting about INR 12,000 crores [ of works ] in the next 3, 4 months to be bid out.

Abhishek Puri

analyst
#48

That's from TBCB or intrastate?

K. Sreekant

executive
#49

Interstate, TBCB.

Abhishek Puri

analyst
#50

Interstate. Okay.

Operator

operator
#51

The next question is from the line of Bhavin Vithlani from SBI Mutual Fund.

Bhavin Vithlani;SBI Mutual Fund;Analyst

analyst
#52

Could you give us some color on the dividend? Because this year you have paid only INR 2.5.

K. Sreekant

executive
#53

That was the final dividend of the last year, right? So...

Bhavin Vithlani;SBI Mutual Fund;Analyst

analyst
#54

Because you haven't declared any dividend in this quarter, so I was just wondering on...

K. Sreekant

executive
#55

We will declare in the month of February and pay it in the month of March, more likely. Likely, [ we every time ] pay interim dividend only in the month of March. Similar time lines, you can expect a dividend payout.

Bhavin Vithlani;SBI Mutual Fund;Analyst

analyst
#56

Sure. And just going back to the earlier question. Given that your CapEx is declining, and now the dividend distribution tax is also gone, would it be comfortable for you to pay out 60% of your profits because the depreciation takes care of debt repayment?

K. Sreekant

executive
#57

No, it depends on the -- see, 60% payout is very likely. There should not be any issue.

Bhavin Vithlani;SBI Mutual Fund;Analyst

analyst
#58

Okay, fine. Yes. And just a last question. We have seen some intrastate TBCB projects from states like U.P. If you can give some color on a 3-year basis, maybe not 1 year, what is the total opportunity that you are seeing from the intrastate on TBCB? And are you seeing more states going the TBCB route vis-à-vis the regulatory tariff mechanism?

K. Sreekant

executive
#59

See, states are following 3 models. Some states are doing it themselves. For example, Kerala or even Tamil Nadu, Andhra -- Telangana, they do it themselves. So we don't even know what is the opportunity and what kind of work they are doing. States like U.P., Jharkhand, they are coming out with TBCB project. So Jharkhand, I have told that there is about 2,000 -- INR 5,400 crores, which is under bidding. But this has been under bidding for quite some time now. It is not progressing into award stage. So state project pipeline to predict for 3 years is quite tough. What is likely to come out is very, very difficult.

Bhavin Vithlani;SBI Mutual Fund;Analyst

analyst
#60

Okay. And any color on the projects for connecting Leh for the solar or connecting projects for Bangladesh and Sri Lanka?

K. Sreekant

executive
#61

Bangladesh, nothing much significant is coming up. In fact, there was an HVDC link, which was to be under consideration, but then the Bangladesh government, they -- the Bangladesh Power Department has now expressed that this is no more required. As far as Sri Lanka is concerned, discussions are in progress. Instead of crossing the sea through an undersea cable now, overhead line possibility is being explored. So that is under active consideration of the Joint Working Committee and JAC formed between the 2 governments.

Bhavin Vithlani;SBI Mutual Fund;Analyst

analyst
#62

And Nepal also -- Nepal, Bhutan or...

K. Sreekant

executive
#63

Nepal, already 1 line has been approved between...

Unknown Executive

executive
#64

Gorakhpur.

K. Sreekant

executive
#65

Gorakhpur and new Butwal. New Gorakhpur and New Butwal. That has been approved as a joint venture between NEA and Power Grid by the Joint Working Committee. It's a small line. I mean about INR 400 crores is the investment. And then Arun III, there is already 1 line, which is being developed by the joint venture, or the subsidiary of SJVN, which is developing this project. And we are providing the project management consultancy for implementation of this project. So generation asset is not very much visible in Nepal. And generation where the power will flow into India, that is still not clear. So hasn't -- there is immense potential. They talk of 20,000, 25,000 megawatt of hydro potential. And few months back, there was a discussion between our power -- Union Power Minister and the Honorable Prime Minister of Nepal in improving this interconnectivity and promoting the hydro of -- potential of Nepal. So in the long run, more interconnections between Nepal and India, Bhutan and India, India and Sri Lanka are expected.

Operator

operator
#66

The next question is from the line of Atul Tiwari from Citigroup.

Atul Tiwari

analyst
#67

Sir, for the 7 TBCB projects which were operational and which had INR 242 crores PAT, what was the corresponding equity invested in all of them?

K. Sreekant

executive
#68

I'll just give you the equity investment [indiscernible] TBCB [indiscernible]

Unknown Executive

executive
#69

[Foreign Language]

K. Sreekant

executive
#70

All TBCB projects?

Unknown Executive

executive
#71

[Foreign Language]

Unknown Executive

executive
#72

30.

Unknown Executive

executive
#73

30, 30%.

K. Sreekant

executive
#74

The total investment in all TBCB is about INR 2,500 crores. Of these projects, it will be roughly around 16 -- INR 1,500 crores to INR 1,600 crores.

Operator

operator
#75

The next question is from the line of Mohit Kumar from IDFC Securities. As there is no response, we'll move to the next question.

K. Sreekant

executive
#76

Just a minute. There was a question regarding capitalization next year, how much TBCB and how much RTM? The -- out of INR 15,000 crores estimated, INR 1,250 crore is expected out of TBCB, and the rest will be through RTM projects.

Unknown Executive

executive
#77

INR 1,163 crores operational.

K. Sreekant

executive
#78

INR 1,163 crores.

Operator

operator
#79

Can we move to the next question now? It's from the line of Apoorva Bahadur from Jefferies.

Apoorva Bahadur

analyst
#80

Sir, I wanted some update on the InvIT that we were planning and we discussed in the last analyst meet. So what has been the update there? And if you have identified which assets will be moving?

K. Sreekant

executive
#81

The update is that we have engaged the merchant bankers, the lawyers and various agencies. Application has already been made to the SEBI for creation of the trust. At this point of time, we are contemplating to shift some of the TBCB assets to the InvIT, given that there are some taxation and stamp duty issues associated with transfer of RTM assets.

Apoorva Bahadur

analyst
#82

[ Sir, does the size ] will be significantly smaller than, I think, the INR 10,000 crores target that government was probably -- had given?

K. Sreekant

executive
#83

Not necessarily. Depending on the time line and all, we are expecting to move enough assets to raise around INR 10,000 crores.

Apoorva Bahadur

analyst
#84

Okay. Got it, sir. Sir, some time back, we had formed a JV with NTPC, I believe, in the power distribution space. What has been the progress over there? And if you see some -- any opportunities coming up, given that most likely the Electricity Amendment Act will be passed?

K. Sreekant

executive
#85

No, there has not been much progress on this JV front.

Apoorva Bahadur

analyst
#86

Okay. Got it, sir. Lastly, if I may know, if there were any one-offs in this quarter's results?

K. Sreekant

executive
#87

Nothing [indiscernible] has been disclosed. I think there have been a few order impacts which were disclosed.

Operator

operator
#88

The next question is from the line of Mohit Kumar from IDFC Securities.

Mohit Kumar

analyst
#89

Two questions. The first, sir, what was the trade receivables greater than 45 days? And have you seen it coming off in January?

K. Sreekant

executive
#90

No, it has been increasing, unfortunately. It is not yet -- it is not on a declining trend yet. And above 45 days, the outstanding is -- I think I'll just [ give ] the number. Outstanding more than -- is INR 3,658 crores.

Mohit Kumar

analyst
#91

INR 3,658 crores will get to the 45 days?

K. Sreekant

executive
#92

Right.

Mohit Kumar

analyst
#93

Okay. Out of INR 5,000 crores? That's a significant number.

K. Sreekant

executive
#94

Yes, that's a -- few states, Telangana, J&K, U.P., they have significant outstandings.

Mohit Kumar

analyst
#95

Do you expect this thing to come down, sir, by March?

K. Sreekant

executive
#96

We are doing our collection drive. Let us hope -- we hope to reduce it. Actually, Biswanath Chariali-Agra order. Final order has come only recently, and that has pushed up the billings as well significantly. So if you recollect, the grant -- final order due to the grant element was not issued until recently. So because of that, there has been some pileup in the outstandings also.

Mohit Kumar

analyst
#97

And secondly, sir, how confident you are to -- for the commissioning of Raichur, Pugalur, the element of it prior to March?

K. Sreekant

executive
#98

See, the position is much better than what it was, say, 6 months back. Let me put it -- I mean since the first call, we have been saying that there are severe right of way issues. But significant progress has been made thereafter. Out of -- the whole 1,765 kilometers has been divided into 10 packages. As on date, I think we are almost through with about 7 packages. And in 1 package, about 26 kilometers and another 20. Roughly around 60 kilometers of line is what is currently under execution. And the -- one of the challenges which we are encountering is also in the Krishna and Tungabhadra, where the water has not receded to the levels we have expected previously. So that is the thing. We are looking for various ways to cross these 2 rivers. That is one challenge. We are fairly confident, I would say, of completing it in this financial year. Otherwise, it may slip by a month or 2.

Mohit Kumar

analyst
#99

Understood, sir. And then lastly, sir, as far as InvIT is concerned, are we exploring only public InvIT? Or are we also exploring private InvIT too so that these -- so the process can be [ hastened ]?

K. Sreekant

executive
#100

More likely, [ we'll do the public one ].

Operator

operator
#101

The next question is from the line of Deepak Krishnan from Goldman Sachs.

Deepak Krishnan

analyst
#102

Sir, bookkeeping question. If I look at the segment results line in this quarterly result and I subtract the stand-alone from consol, I'm actually seeing that there is a negative number in terms of segment results. Could you please explain, is this because of some loss made at TBCB? Or if there's some other reason for that?

K. Sreekant

executive
#103

Just hold on.

Deepak Krishnan

analyst
#104

So transmission segment results in consol is lower than transmission segment results in stand-alone by a magnitude of about INR 56 crores. Historically, this has been a positive number to the tune of INR 270 crores, INR 280 crores.

Unknown Executive

executive
#105

Just wait. We're just getting the [indiscernible]. Negative.

K. Sreekant

executive
#106

Okay. We'll come back to you. Can you...

Unknown Executive

executive
#107

Next question.

K. Sreekant

executive
#108

Next question. We'll come back to you.

Deepak Krishnan

analyst
#109

Sure. No worries, sir. There's no other question from my side.

Operator

operator
#110

Can we move to the next question or should we wait?

K. Sreekant

executive
#111

You move to the next question. We'll just answer them.

Operator

operator
#112

Sure. The next question is from the line of Murtuza Arsiwalla from Kotak Securities.

Murtuza Arsiwalla

analyst
#113

Most of my questions have been answered. I wanted to be updated on the InvIT process.

Operator

operator
#114

The next question is from the line of Bharani Vijayakumar from Spark Capital.

Bharanidhar Vijayakumar

analyst
#115

We'd like to know what is the current regulated equity for the -- as on Q3?

K. Sreekant

executive
#116

No, that's not available as of now.

Operator

operator
#117

Next question is from the line of Abhishek Puri from Axis Capital.

Abhishek Puri

analyst
#118

I'm sorry. My questions have been answered.

Operator

operator
#119

The next question is from the line of Girish Achhipalia from Morgan Stanley.

Girish Achhipalia

analyst
#120

Just a quick question on InvIT. Now given that this development happened yesterday on dividend distribution tax -- sorry, rather on the weekend, how does one look at the appetite for unitholders? Because for corporate entities, you had this issue. But now, anyways for InvITs, it was exempt. So how does one weigh the attitude for investors? I understand foreign investors, or I believe, foreign investors were anyways indifferent, but domestic investors, how does the tax treatment change now?

K. Sreekant

executive
#121

We understand it will be taxed in the hands of the dividend investor -- I mean the unitholders. So to that extent, there will be some impact. But dividend distribution tax will not be there. So there will be less of -- I mean there will be more of payout, only to the extent the arbitrage between the dividend distribution tax and the tax in the hands of that individual unitholders. To that extent, it may impact the appetite. So those...

Girish Achhipalia

analyst
#122

Basically, domestic investors would have lesser appetite, right? I mean given if they had to choose between investing in the stock versus investing in an InvIT?

K. Sreekant

executive
#123

Why?

Girish Achhipalia

analyst
#124

Because the DDT is generally on the corporate side, and -- which was anyways not the case there. So there was a reason where you had an InvIT where the vehicle was supposed to be more tax efficient.

K. Sreekant

executive
#125

That is true. But if the -- again, it will all be priced. We have to -- the investors will have to absorb this. Maybe instead of domestic, there will be more foreign investors into this.

Operator

operator
#126

The next question is from the line of Dhruv Muchhal from HDFC AMC.

Dhruv Muchhal

analyst
#127

Sir, how do you see the phasing of this WIP projects of about INR 61,000 crores? So next year, we are about INR 15,000 crores. So do we see a bulkier FY '22 and '23? Or it will extend beyond FY '23?

K. Sreekant

executive
#128

No. [indiscernible] In the next 3, 4 years, this will all be completed.

Dhruv Muchhal

analyst
#129

It can go to about 4 years? Okay. Okay. And sir, any update on the Leh project? There was a question earlier.

K. Sreekant

executive
#130

No, there's no update on the Leh project. It was bid out as part of the solar tender, but I think the responses have not been good on that. So there is a talk of separating it out, generation as well as transmission. Let us see. As Power Grid, we feel we are -- this is a project which will be taken up under RTM, and we are the right people to do this project. But let us see.

Dhruv Muchhal

analyst
#131

And sir, in these -- in the RE projects, which are linked to TBCB -- I mean TBCB-linked RE projects, we are seeing some slowdown here, I mean in terms of the tendering. Only INR 14,000 crores versus -- I mean you had to complete -- all the projects have to be completed by December '21, '22, but not much has come.

K. Sreekant

executive
#132

December '22.

Dhruv Muchhal

analyst
#133

December '22, so as you need 2 years to complete a project, you had to tender the projects now. So not much has come. So could it be that we'll get more projects on RTM? Or I mean that's unlikely?

K. Sreekant

executive
#134

No, it is not likely that there will be more projects on RTM. There -- if we see recently, out of around INR 15,000 crores decided, INR 11,000 crores has gone to TBCB only.

Dhruv Muchhal

analyst
#135

Yes, but on an incremental basis? Because there seems to be some -- probably for some reason, there seems to be some delay there, so to quicken the execution?

K. Sreekant

executive
#136

No, no, no. I don't think so. In any case, it's the decision of the government and the NCTs.

Dhruv Muchhal

analyst
#137

And sir, you did mention about agri firms -- financing agri firms in your opening remarks. Is this a big thing or it would be something -- I mean as a CSR thing?

K. Sreekant

executive
#138

No, no, no, not a CSR. [ It will be -- we meant an ] annuity model, not CSR. Right now, in fact, we had discussions with U.P. and it was quite an advanced stage. But somehow, due to change in the officials there, it slowed down a bit. We have been in discussions, when we have recently initiated discussions with Bihar. So depending on the number of pumps, initial start, it may be investment of about INR 200 crore to INR 250 crore.

Dhruv Muchhal

analyst
#139

Okay. But can this be a significant portion? Or that's not the plan?

K. Sreekant

executive
#140

No, we are looking to make it a significant portion of the new investments.

Dhruv Muchhal

analyst
#141

Okay. Because the government's presumed plan is [ huge ], so what would be the model, if you can share something?

K. Sreekant

executive
#142

No. The model is to identify the -- see, the payoff for the distribution utilities is the savings in the energy, which is provided either free or at a very subsidized rate to the farmers. So out of those savings, they are procuring, say, for example, at INR 6, INR 7 and supplying it at INR 1 or even giving free. So every unit saved will add to the -- I mean will save their subsidy or their cost of power purchase. So out of that savings, we expect them to fund these pumps. This is the basic premise of this exercise.

Dhruv Muchhal

analyst
#143

And you will ensure your minimum return threshold?

K. Sreekant

executive
#144

Right, right.

Dhruv Muchhal

analyst
#145

Okay. Okay. Okay. Got it, sir. And just sir, lastly, on the dividend. Now given that the CapEx is declining significantly, I mean 60% -- could be higher than 60% because 60%, you'll have a decent amount of cash unless there is some increase in CapEx? You mentioned this before, sir.

K. Sreekant

executive
#146

That's -- no, no, I didn't mention any number. Someone asked me whether a 60% payout is possible. I said, there is a possibility. I never said this is a number. I mean it has to be approved by the Board. I'm only saying, again and again, that we are not against distribution. To the extent we require for our CapEx, we would like to use the funds. But if there is a surplus available, we'll definitely increase the payout. No issues there.

Dhruv Muchhal

analyst
#147

Okay. And sir, last question, if I may squeeze. The TBCB are the -- we are seeing that mostly now it will be TBCB projects. But looking at the under -- I mean already commissioned projects, it seems [ difficult, ] how would you do INR 10,000 crores? So will there be a change in the norms in terms of what you can offer in TBCB -- in InvIT? Or I mean how do you plan to do it, at least INR 10,000 crores?

K. Sreekant

executive
#148

See, there is a requirement of SEBI that 51% minimum equity holdings should be held by the InvIT in the SPVs. But for PPP project, it has been reduced to 49%. And the TBCB projects, which we are having, also qualify as PPP project for the purpose of transfer to InvIT. That means we can transfer more number of projects under the InvIT.

Dhruv Muchhal

analyst
#149

Okay. But we thought there was a -- I mean a clause of 3-year lock-in before you can transfer a TBCB project?

K. Sreekant

executive
#150

That's right. The clause says that you should hold 51% till 3 years and minimum 26% for 2 years thereafter, okay? So when you hold 51%, you can transfer 49%. So 49% is also permitted for PPP projects under the InvIT route. Yes, just a minute, before the next question. There was a question regarding the segment result.

Unknown Executive

executive
#151

Earlier, as per the ICI -- EAC opinion, we are taking the deferred tax assets to deferred tax liability by netting of the tax excess. But after EAC opinion, we are taking you to the regulatory deferral account balances. So the regulatory deferral account balance, which included in your Q3 2019 number, is INR 272 crores and corresponding is INR 834 crores. If I adjust these 2 figures, then the figure stands at INR 3,300 crores against INR 2,982 crores.

Unknown Executive

executive
#152

That's the reason it is negative.

Operator

operator
#153

Can we move to the next question? The next question is from the line of Sumit Kishore from JPMorgan.

Sumit Kishore

analyst
#154

A quick follow-up. You mentioned that trade receivables are at about INR 3,658 crores. What is the late payment surcharge in other income for the third quarter of FY '20? And how much higher is it on a year-on-year basis?

K. Sreekant

executive
#155

The...

Unknown Executive

executive
#156

Surcharge [indiscernible]

K. Sreekant

executive
#157

Late payment surcharge in Q3 was INR 70 crores, okay? For the 9 months, it is INR 204 crores. Last year, it was INR 167 crores.

Sumit Kishore

analyst
#158

Okay. And for the quarter last year?

Unknown Executive

executive
#159

INR 49 crores.

K. Sreekant

executive
#160

INR 49 crores.

Operator

operator
#161

The next question is from the line of Apoorva Bahadur from Jefferies.

Apoorva Bahadur

analyst
#162

Just a quick bookkeeping question. You spoke about this Biswanath Chariali order pushing up their billing. So how much has been the impact, sir, on the revenue? Incremental impact?

K. Sreekant

executive
#163

So revenue, no, no. This is not impacting revenues because we would have already booked income in the rest of the year.

Apoorva Bahadur

analyst
#164

Okay, you're already booking?

K. Sreekant

executive
#165

Yes.

Apoorva Bahadur

analyst
#166

Okay. Okay. So cash flow has improved basically?

K. Sreekant

executive
#167

Yes.

Apoorva Bahadur

analyst
#168

Okay. And sir, secondly, are we seeing -- I mean post this implementation of LC mechanism, is there any link for an increase in our receivables? So basically, the states, are they prioritizing paying off gencos over us?

K. Sreekant

executive
#169

No, I don't think so.

Operator

operator
#170

The next question is from the line of Ravi Naredi from Naredi Investments.

Ravi Naredi;Naredi Investments;Managing Director

analyst
#171

Sir, congratulations to [ Shri Vinod Kumar Singh ji ] to become director personnel, and we wish all the best. Second thing, any specific reason to postpone the dividend to March month instead of February?

K. Sreekant

executive
#172

Instead of?

Ravi Naredi;Naredi Investments;Managing Director

analyst
#173

February. February month.

K. Sreekant

executive
#174

No. We basically pay in the month of March only.

Ravi Naredi;Naredi Investments;Managing Director

analyst
#175

Okay, okay. And sir, how much debt is on 31st December? Around INR 1.44 crores, right?

Unknown Executive

executive
#176

Debt as of 31st December was INR 1,43,000 crores.

Ravi Naredi;Naredi Investments;Managing Director

analyst
#177

Okay. And sir, asset is INR 2.88 net crores, right?

Unknown Executive

executive
#178

[indiscernible]

K. Sreekant

executive
#179

INR 2,18,838 crores.

Ravi Naredi;Naredi Investments;Managing Director

analyst
#180

INR 2,18,000 crores. And sir, we are earning only a [ INR 10,000 ] net profit, so do you think it is a very less amount in compared to our size of assets?

K. Sreekant

executive
#181

Our returns are based on equity, so I don't think this has...

Operator

operator
#182

As there are no further questions, I would now like to hand the conference over to management for closing comments.

K. Sreekant

executive
#183

Right. Thank you so much for all your participation, and have a good day.

Rahul Modi

analyst
#184

Thank you so much, sir and ma'am, for your time and the opportunity. Have a great evening. Thank you so much.

Operator

operator
#185

Thank you. On behalf of ICICI... [Audio Gap]

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Power Grid Corporation of India Limited transcript — plus 248,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Power Grid Corporation of India Limited earnings transcripts and 248,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.