Power Grid Corporation of India Limited (POWERGRID) Earnings Call Transcript & Summary

August 11, 2021

National Stock Exchange of India IN Utilities Electric Utilities earnings 71 min

Earnings Call Speaker Segments

Unknown Analyst

analyst
#1

Good morning, everybody. Thank you for joining us for the Q1 FY '22 Post Result Virtual Meeting of Power Grid Corporation of India Limited. On behalf of ICICI Securities, we would like to welcome the POWERGRID senior management led by Mr. K. Sreekant, CMD. Thank you, sir, for sparing your time. From the management along with CMD, sir, we've got Mrs. Seema Gupta, Director, Operations; Mr. V.K. Singh, Director, Personnel; Mr. Taj Mukarrum, Director, Finance and CFO; and Mr. Abhay Choudhary, Director, Projects. I would like to hand over the floor to CMD, sir, who will give a detailed presentation, post which we will have a Q&A session. Thank you, and over to you, sir.

K. Sreekant

executive
#2

Thank you. A very good morning. I'll just start with a brief presentation on the Q1 results for FY '22. Is the presentation visible?

Unknown Analyst

analyst
#3

Yes, sir.

K. Sreekant

executive
#4

Thank you. We'll be covering over the performance highlights, work in hand. As of 30th June, POWERGRID has grown to have 1,68,457 circuit kilometers, 1,310 and 4,400 -- 4,40,310 MVA transformation capacity at 259 substations. The interregional transfer capacity has grown to 90,090 megawatts, roughly 85% of India's interregional capacity. Market cap has grown to INR 1,23,000 crores, which are the third largest CPSE in terms of gross block. Briefly, in terms of the project execution, this quarter, we have done a CapEx of more than INR 1,100 crores and capitalization of INR 5,642 crores on a consolidated basis. Some of the key projects which got completed, transmission lines, 1,716 circuit kilometers. Ajmer-Phagi, this is a TBCB project completed. Jigmeling-Alipurduar, this is a cross-border interconnection with Bhutan for evacuation of Mangdechhu hydropower, this has been completed. Wardha-Aurangabad, long-standing line, this is the first 1,200 kV line which is, of course, charged initially at 400 kV. Sitamarhi-Motihari, Sitamarhi-Darbhanga are 2 lines under the -- our POWERGRID Mithilanchal TBCB project, these have been completed. Baharampore-Bheramara circuit 3 of second double-circuit line, this is the lead through Bangladesh. And Pugalur-Thrissur HVDC, the Monopole-I has been completed, with this to enter VSC system of 2,000 megawatt has been completed. We added one substation 400/220 kV at Sitamarhi under the Mithilanchal, and various ICTs have been added across the country for about 9,400 MVA. Coming to the operational performance. Availability has been 99.77% in this quarter, above the 99 point -- full incentive threshold. Trippings, flat. We had faced a couple of cyclones in this period, both on the East Coast as well as the West Coast and [ turnaround ] unstacked. There has been significant improvement in our preparedness for these cyclones. And also, we have developed the app in-house for the -- our patrolling. So far, we have been using a third-party app. Now the app has been developed in-house. It will provide greater inputs and also consolidate data analytics going forward. Coming to the financial performance. I'm sure you have seen the results and made an analysis at completion. Income has grown by about 9% on a consolidated basis to INR 10,392 crores, up from INR 9,817 crores. PAT is INR 5,998 crores. This includes the profit we have made on InvIT, which is shown on the slide next. And the -- excluding the exceptional items, that is the -- primarily the InvIT in the current year and the rebate which we gave last year, so if we do exclude these 2 exceptional items on a comparable basis, profits are up to INR 3,341 crores from INR 2,935 crores on a consolidated basis. This is a snapshot of the financials of the InvIT as far as POWERGRID is concerned. We have sold 74% equity holding in 5 SPVs. These SPVs were having 3,698 circuit kilometers and 6,630 MVA and 3 substations. Gross block was INR 7,239 crores. Equity deployed was INR 1,213 crores for the 100%. The Trust was valued INR 9,100 crores for the 74% equity. It had a component of Fresh Issue, INR 4,993 crores. This is primarily the debt provided by POWERGRID to the SPVs. And then for the equity, we transferred 74%. We received INR 4,107 crores, partly by way of units and partly by way of cash. 15% of the post listed units, that is about 1,350 crores, we had 65 crores, 13.65 crores of units we retained, the rest we offloaded. The 74% stake was about INR 898 crores. Expenses is about INR 40 crores. So we recognized a profit of INR 3,170 crores this quarter. These are the financials. Revenue, up 9%. We see a telecom dip of 42% in this. This is primarily because of a settlement we made with the BSNL. We had contracts which were not renewed since '18, '19. So '18-'19, '19-'20 and '20-'21, these 3 years, we had to agree on pricing and enter into a settlement that resulted in a rebate being offered about INR 86 crores. So that is the reason for this dip in the telecom revenue. Other income reduction is mainly on account of surcharge. Operating expenses, commensurate with the revenue growth. And reduction in interest because of debt repayment and reduction in the working capital borrowings as well. The exceptional item is shown. This is primarily this year on account of the profit from the InvIT. And last year, it is from the rebate we offered to the customers. Our consolidated results also are on the same lines. There is nothing different here. Gross block is today on a consolidated basis INR 2,47,421 crores; capital work-in-progress, INR 21,000 crores; INR 1,40,000 crores debt on the books; INR 76,139 crores net worth. EPS is INR 8.60. This includes the onetime InvIT profit. And book value per share is INR 109. Return on net worth is, again, inclusive of the profit from share as -- the InvIT. Some of the inputs you always ask, we try to put it. Surcharge, as you can see, has come down from INR 265 crores last year to INR 55 crores. On the back of payments as well as the reduction in the rate of surcharge, incentive income is more or less flat. Income from subsidiaries, INR 231 crores; dividend [Audio Gap] There is nothing significant in terms of [indiscernible]. Receivables, we have INR 7,619 crores. We have a separate slide on receivables, which we will be talking about. The other 2 segments, which are transmission, telecom, income was INR 97 crores. As I mentioned, INR 86 crores we had to offer rebate to BSNL for the past 3 years to settle the outstandings and the issues with them. Our network availability, 99.99%. We received the CERC approval for formation of telecom as a separate subsidiary. We are going to do it in the current quarter. Consultancy income has picked up a bit on the back of our North East contract which we are doing for the government for the NERSIP projects. The telecom network, I'm very happy to share that we have added roughly 6,300 kilometers of OPGW from DVC as well as West Bengal. So this adds to our network and provides us greater access in the Eastern states of West Bengal and Jharkhand. Commercial performance. Last year, we had, at the end of June, INR 8,243 crores. We were facing the issue of lockdown and COVID, and therefore, the outstandings were much higher. This year, in March, we -- because of our [indiscernible] models as well as the March collection [ buoyancy ], receivables came down to INR 3,583 crores. But end of June '21, we have again gone up to INR 7,080 crores. We had the second wave, therefore, collections were much lower in the month of April and May. June, that picked up. In July, we expect again to pick up. We are taking action in terms of notices for regulation [ pursuits ]. We hope to see a settlement particularly from Uttar Pradesh and J&K where we have large [indiscernible], and they are expecting some loans from PFC, REC, and this is expected to be cleared shortly. Works in hand today, there are about INR 35,000 crores. Normal -- our RTM projects are about INR 18,000 crores; and TBCB, INR 16,800 crores. Interstate transmission network works which are coming up, INR 9,300 crores; and the intrastate, INR 1,500 crores primarily in the state of UP. There are a few projects under intrastate. Besides these, I would also like to talk about the recent distributed -- distribution package, reform package, which has been announced by the government where an outlay of 3 lakh crores -- 3 lakh, 3,000 crores is expected. In that, the GBS support is of the order of INR 96,000 crores or so. So there is an opportunity for the investment of 2 lakh crores to come from either the state utilities or the private sector or the CPSUs. This has distribution infrastructure augmentation, roughly 1 lakh 50,000-odd crores; and smart metering, about another 1.5 lakhs. So we are looking at opportunities in this segment. We have identified a few areas where we can participate along with the DISCOMs or the state utilities in strengthening their infrastructure or augmenting the meters work and take it up with them. So this quarter, we are going to approach several of these state utilities and offer our services to support them in making the investment, also in the consultancy or project implementation. But our focus will be to support them through our low-cost funding options. And finally, happy to share that this year, we have been ranked 68th among the India's top 100 best companies to work by the Great Place to Work Institute. Last year, our rank was outside of this 100, and very happy to share that this year we have improved by more than 30 positions. And we are also recognized one of the best employers among nation builders. So I conclude the presentation here, and we'll be happy to take up your questions. Thank you.

Unknown Analyst

analyst
#5

Thank you, sir, for the detailed presentation. We will now begin the Q&A session. [ Divya ] from ICICI will be coordinating along with us. Thank you. [ Divya ], I hand over to you.

Unknown Analyst

analyst
#6

Thank you, [ Rahul ]. We take first question from the line of Mohit Kumar from DAM Capital.

Mohit Kumar

analyst
#7

Congratulations on a good set of numbers. So my first question is, sir, on the P&L, is the tax impact of gains booked on InvIT is around 20% of INR 32 billion, which has been booked, roughly INR 8 billion? Is that number right?

K. Sreekant

executive
#8

The tax impact is only on the units which have been sold, and we have provided about INR 350 crores on account of tax for this.

Mohit Kumar

analyst
#9

INR 3.5 billion is the tax impact. Am I right?

K. Sreekant

executive
#10

Yes. INR 3.5 billion on account of the InvIT, yes.

Mohit Kumar

analyst
#11

And so the income from the InvIT could get booked as other income. Is that understanding right? And we haven't booked anything in the Q1, but as we go forward in Q2, it will become as a part of other income. Is that understanding right?

K. Sreekant

executive
#12

No, we have booked everything in Q1. We have disclosed it as extraordinary item in the P&L.

Mohit Kumar

analyst
#13

No, no, I'm trying to -- I'm asking that as we go forward, the dividend from InvIT, will that get booked as part of the other income? Or the InvIT -- the entire income of the InvIT will be booked as an associate income in our P&L?

K. Sreekant

executive
#14

No, it will be booked as other income as and when the dividend is received.

Mohit Kumar

analyst
#15

Understood. So lastly, on the TBCB, bidding had been on the lower side in the last -- I think the past 12 months. There was some bidding which happened in the March or, let's say, Jan and Feb. How do you see going forward in the next 12 months and 8 months? How is the activity right now?

K. Sreekant

executive
#16

As I have shown, about INR 9,000 crores of projects are currently under closed-door bidding. A few schemes have been notified by [indiscernible] recently. Depending upon the progress in the RE, these will be taken up.

Mohit Kumar

analyst
#17

Is there something on the intrastate which should happen or should we believe there is some momentum?

K. Sreekant

executive
#18

In the intrastate, there is a momentum. There is a scheme for Mohanlalganj transmission network of UP. I think UP is the one where we are seeing some movement.

Unknown Analyst

analyst
#19

Next question is from the line of [ Seeta Ramanal ] from Spark Capital.

Unknown Analyst

analyst
#20

Okay. On the TBCB pipeline that you mentioned, which is close to INR 9,300 crores, can you give the details of the projects, please?

K. Sreekant

executive
#21

These are mainly for the RE projects in Rajasthan and Gujarat.

Unknown Analyst

analyst
#22

Okay. And on the InvIT sale, the sale of 5 assets, we see that the debt is -- that out of the entire enterprise value of INR 9,000 crores, close to INR 4,000 crores -- close to INR 5,000 crores is debt, and close to INR 4,000 crores the equity part of it. So what was the book value of this particular equity, the set of 5 assets that you sold?

K. Sreekant

executive
#23

The equity deployed was about INR 1,200 crores. But the 74%, it was INR 897 crores.

Unknown Executive

executive
#24

Yes.

Unknown Analyst

analyst
#25

Next question is from the line of Akhilesh Bhandari from IPRU MF.

Akhilesh Bhandari

analyst
#26

Any particular time line for further monetization of the TBCB subsidiaries which you have in mind?

K. Sreekant

executive
#27

We have no plan to monetize any further in the current financial year. Next financial year, again, a similar asset value is likely to be monetized. Depending -- the monetization will also take into account the TSA conditions and completion of assets. So in fiscal '22, '23, we can do maybe another INR 7,000 crores, INR 7,500 crores of monetization. Overall, we are targeting, say, about INR 7,500 crores next fiscal and then INR 15,000 crores for the next 2 years each year.

Akhilesh Bhandari

analyst
#28

Okay. Sir, and you mentioned that the collection rate has been improving sequentially. So any number which you can put for June and July what was the collection against the billing?

K. Sreekant

executive
#29

June and July. July, let me just give that...

Seema Gupta

executive
#30

130%.

Unknown Executive

executive
#31

130%.

K. Sreekant

executive
#32

July is about 130%. June was close to...

Unknown Executive

executive
#33

90%.

Unknown Executive

executive
#34

90%.

Akhilesh Bhandari

analyst
#35

Okay. Sir, any update on the Leh, Ladakh project? Last quarter, your presentation had a slide on it, but this quarter, there is no slide on it. So any further updates on that?

K. Sreekant

executive
#36

No, I thought I'll give the slide when it is allotted to us because right now, I can only show a file movement. The DPR has been submitted, and it is in the consideration of the Ministry. And the preliminary thoughts are gearing towards giving it to POWERGRID under the RTM route. Those discussions are still on. There is no slide does not mean it is out of consideration. It is still there very much.

Akhilesh Bhandari

analyst
#37

Yes, sir. Sir, on the system strengthening scheme, so any further thoughts on -- you mentioned a couple of things about helping the DISCOMs on a consultancy basis as well. So would you be looking to operate the smart metering assets also? Or that is something which is not under consideration?

K. Sreekant

executive
#38

It is under consideration. We are -- because in smart metering, there is a requirement of big investment. The government is going to provide 7.5%, 15%, depending on the state, subsidy for the smart metering infrastructure. And balance is supposed to be through kind of TOTEX model where the developer or the utility brings the money. So that is where one option we are looking at it. So that is really under consideration for investment -- increasing our investment program.

Unknown Analyst

analyst
#39

Next question is from the line of Sumit Kishore.

Sumit Kishore

analyst
#40

My first question is the INR 50 billion of cash that was received in lieu of the debt which was associated with the 5 TBCB assets. I mean that is sitting on your books because I see that debt has not been paid down as I had expected. So what do you intend to do with the cash? Can you basically also help us -- give us a sense of the time line for the special dividend that will come from the overall gain on the InvIT and the capital freed up? And you had made it clear that you will not keep any extra cash. That is my first question.

K. Sreekant

executive
#41

Yes, you are right. The funds will be utilized for the current year's CapEx. And definitely, we will make a dividend payout. The dividend payout -- we will do one final dividend after the AGM. And last year, we did 2 interim dividends. Similar plan we have for the current year as well.

Sumit Kishore

analyst
#42

So 2 -- dividend will be paid in 2 phases, 2 parts?

K. Sreekant

executive
#43

Two interim dividends last year we did. I expect similar 2 parts this year as well, yes.

Sumit Kishore

analyst
#44

Okay. Okay. Sir, the second question is interesting that you mentioned the INR 3 trillion package and the opportunity for POWERGRID. But it is very, very important to understand that incremental capital allocation for POWERGRID will make similar returns that you make in your RTM or the TBCB IRRs that you expect. So could you put some -- throw some light -- you mentioned you will give loans to states to execute this better. I want to clearly understand what is the return on -- in the business model. We would not appreciate any dilution of returns.

K. Sreekant

executive
#45

Yes. One, we do not intend to provide loans. We intend to provide investment, either as equity or maybe, depending on the structuring, it can be a kind of a leasing model, in which case it will be similar to a loan you may say so. That is one. Number two, we will look for similar returns, but I'm very sure that the RTM returns which we are getting, whether we'll -- we can get only on the equity component. We cannot get on the entire investment into these assets because if we say that we will take the -- on a rough estimate, about 40% of the funds the state utilities will have to find out on their own. And if we say the entire money will be given as equity at 15.5%, nobody will come to us. They will find alternate funding much, much cheaper. So we have to give them something which is attractive and which also makes sense to us in terms of the equity deployed.

Sumit Kishore

analyst
#46

So in short, you are saying what will be the return on equity. So what is the threshold for deploying capital -- equity capital?

K. Sreekant

executive
#47

Equity capital, I think anything above 14% should be fine.

Sumit Kishore

analyst
#48

Yes, 14% is fine. And finally, my last question is you mentioned the share of subsidiary profits for the quarter. Just wanted to understand, given 5 significant TBCB subsidiaries are now getting -- not getting consolidated for 74% stake at least for half the quarter, the extent of decline in the TBCB profit that I was expecting on a quarter-on-quarter basis was not visible. So I mean, what are we missing here? Or have the other TBCB subsidiaries which are operational contributed a very large portion of profit?

K. Sreekant

executive
#49

Okay. One of the subsidiaries which was in loss has turned around. We did some financial restructuring there. It has come out to be profitable.

Sumit Kishore

analyst
#50

What is the extent of the swing?

K. Sreekant

executive
#51

About 20, 25 -- INR 22 crores, INR 23 crores.

Sumit Kishore

analyst
#52

Of profit versus loss of how much earlier?

K. Sreekant

executive
#53

No, no, in the net impact.

Sumit Kishore

analyst
#54

Net impact. Which is the subsidiary, sir?

K. Sreekant

executive
#55

This is POWERGRID NM Transmission Limited. And the Commission, Medinipur-Jeerat System, which added to the profit. Mithilanchal, it added a little bit. Then Jawaharpur Firozabad transmission system, the first intrastate, it added. Then JP, which was our POWERGRID Himachal Transmission Limited, which was a joint venture is now a subsidiary, so it added to the consolidated profits. So there are additions to the companies as well as turnaround of some of the companies also.

Sumit Kishore

analyst
#56

Got it. Just a bookkeeping point. I mean, what is the total annual levelized transmission charge for all the operational TBCB subsidiaries on POWERGRID's books now, excluding the 5 which have been transferred?

K. Sreekant

executive
#57

I'll just give you 100 -- it must be around INR 1,300 crores.

Unknown Analyst

analyst
#58

The next question is from the line of Ajinkya Bhat.

Ajinkya Bhat

analyst
#59

Sir, 2 questions on P&L part. The sequential increase in interest expense, is that on account of ForEx considering that you have roughly, I think, about INR 43,000 crores of ForEx debt on the books? Is that what is leading to the sequential increase?

K. Sreekant

executive
#60

The sequential increase?

Ajinkya Bhat

analyst
#61

Yes. Compared to the March quarter, the interest expense has gone up.

K. Sreekant

executive
#62

First quarter interest expense has gone up primarily because of our exchange rate variation.

Ajinkya Bhat

analyst
#63

Yes, yes. Okay. So ForEx impact. Second question, the other income on a sequential basis has gone down. Is it predominantly because of the transfer of TBCB subsidiaries to the InvIT? Because if I remember correctly, in 4Q conference call, you had mentioned that you had collected about 95% of PAT of those TBCB subsidiaries as dividend in FY '21.

K. Sreekant

executive
#64

It has nothing to do with the InvIT. It is because of reduction in surcharge, primarily because of reduction in surcharge.

Ajinkya Bhat

analyst
#65

Okay. But sir, dividend income in 4Q -- what is the dividend income from subsidiaries in 4Q?

K. Sreekant

executive
#66

You are right. Last quarter -- okay, March quarter, we received INR 133 crores more on account of dividend which is not there, plus INR 86 crores reduction in surcharge. These are the 2 major causes of reduction in other income sequentially.

Unknown Analyst

analyst
#67

[Operator Instructions] Next question is from the line of Puneet Gulati.

Puneet Gulati

analyst
#68

My first question is on the new distribution support that you [ license ] to give for distribution companies. Would you need to build any further capabilities to team or processes for that? Or is the company prepared to give this sort of support to distributions?

K. Sreekant

executive
#69

We have been working in the distribution space in constructing the distribution infrastructure. So we have a team and the project execution capabilities in terms of distribution [indiscernible]. We also have a team which has been designing and providing consultancy in the smart metering and smart grid systems. We are now restructuring ourselves to organize all this into one single package and provide the services to the distribution entities. So really, other than actual implementation of these systems, [indiscernible] systems, in any case, we have to buy, integrate and provide them. We have the capabilities required for the services or the augmentation of network. [ NVCs ] will be new distribution scheme.

Puneet Gulati

analyst
#70

There might also be a need for credit assessment here. Is that also...

K. Sreekant

executive
#71

The credit assessment has to be done by us in terms of where to put the money because it is very paradoxical, the funds are mostly required by the utilities which are not that healthy financially. Opportunity is there, so we have to choose among them the ones which are better and have some kind of payment security mechanism for this.

Puneet Gulati

analyst
#72

And [indiscernible] the tripartite work there as well in these [indiscernible]?

K. Sreekant

executive
#73

If it is on the balance sheet of POWERGRID, perhaps it will work because it talks of outstanding view. So it may work. It is not tested.

Puneet Gulati

analyst
#74

Okay. Understood. My second question is on the balance 26% stake that you're still holding some of the TBCBs which went into InvIT. What is the time line for transfer for those? I think sometime...

K. Sreekant

executive
#75

January '22.

Puneet Gulati

analyst
#76

Sorry? January '24.

K. Sreekant

executive
#77

Sorry, February '22 to January '24, progressively, the 5 assets will be [indiscernible]. There are 5 companies with different TSA conditions and the lock-in period.

Unknown Analyst

analyst
#78

Next question is from the line of Apoorva Bahadur from Investec.

Apoorva Bahadur

analyst
#79

Sir, wanted to understand the smart metering piece. Do you intend to also provide the back end and the O&M services here or just the capital support?

K. Sreekant

executive
#80

So we will provide the investment for the entire back end as well as the metering infrastructure. The day-to-day operations will be mostly carried out by the utility or sometimes the service provided this contract because they do the [ end ] support.

Apoorva Bahadur

analyst
#81

Okay. And sir, the IT just needs to be created on the back end on data collection and analytics, basically?

K. Sreekant

executive
#82

Yes.

Apoorva Bahadur

analyst
#83

Could be done by us?

K. Sreekant

executive
#84

We -- I think we'll be only doing the system design. The actual implementation we have to catch all of the IT service providers. You may like to add, no?

Seema Gupta

executive
#85

Actually, we are working on various models. And as we said that our main contribution would be designing then facilitating those implementation to the contractors.

Apoorva Bahadur

analyst
#86

Okay. Got it. Got it, ma'am. Sir, secondly, I wanted to understand a lot of tenders have been put around power storage solutions on the utility scale. So do we see some opportunity for POWERGRID over there as well that we can deploy capital?

K. Sreekant

executive
#87

Definitely. For example, we have tweaked the DPR of the Leh system to include a battery component there -- a storage component, which will increase the utilization of the transmission line and also provide more round the clock kind of [ FR ]. So that is one of the things which has been incorporated into the DPR. And depending on the progress of the RE addition and the progress of this network, the storage system can be taken up a few years down the line. And we are also now putting more focus on the storage solutions. Internally, we are creating a team to look at the storage because going forward, there will be fungibility between transmission and storage, and that is an opportunity POWERGRID should be in a position to capitalize.

Apoorva Bahadur

analyst
#88

Sir, just wanted to understand on this Leh DPR front, so for example, what sort of capital cost can we expect [ in store ], let's say, for 1 megawatt hour?

K. Sreekant

executive
#89

Capital cost in the first phase, transmission system for 5 gigawatts will be of the order of INR 21,000 crores, INR 22,000 crores, okay? This is not having any storage component, okay? There will be a significant subsidy or a grant component in this because otherwise, the tariffs will not be viable. So on top of it, there is a plan to develop storage, a big storage which can cater to, say, another 8 gigawatts of installed capacity. It will be hybrid wind and solar. So idea is to increase the utilization of this transmission system and provide more continuous, stable power play for the DISCOMs.

Apoorva Bahadur

analyst
#90

Makes sense. Sir, just one last question, if I may ask, and please pardon my ignorance. But why exactly are we forming the telecom subsidiary? What's the requirement for this?

K. Sreekant

executive
#91

Okay. There is no specific requirement, but then we want to insulate ourselves from one other kind of demand which happened last time. So where the overall income was considered as part of the revenue, and there were demands, and then there was a lot of upheaval. So we want to avoid that and give it more focus and make it a bigger push because this is an area we see a significant opportunity to increase our nontransmission revenue, because going forward, there will be more digital -- digitization, there will be need for more network services. And that is what we want to capitalize through. So right now, it is around, say, INR 700 crores, INR 800 crores. Maybe this year, we will target around INR 900 crores to INR 1,000 crores of revenue from telecom, but we want to push it up because that is one possibility which we see a growth.

Apoorva Bahadur

analyst
#92

No, no immediate plans to monetizing this?

K. Sreekant

executive
#93

No immediate plan to monetize it. Not immediately, no.

Unknown Analyst

analyst
#94

Next question is from the line of Aniket Mittal from Motilal Oswal.

Aniket Mittal

analyst
#95

Yes. So just on this investment in the distribution part or for distribution entities, I think you mentioned that largely this would just involve providing designing consultancy. So what would be the capital investment that you're looking over here over the next, let's say, couple of years?

K. Sreekant

executive
#96

As I mentioned in my initial remarks, the scheme envisages an outlay of 3 lakh 3,000 crores. The GBS that is the funds to be provided by the government are INR 95,000 crores or INR 93,000 crores. So roughly, there is a gap of about 2 lakh crores, you can say, 2 lakh 10,000. That is the opportunity set which is available. And we want to go there and put money. Even if we got, say, INR 10,000 crores, INR 15,000 crores, it is still a big number, INR 20,000 crores, to INR 30,000 crores of investment potential that is there. So that is what we are going to target. And in the next 2, 3 months, our endeavor will be to meet the potential DISCOMs and engage with them and see what can come out of this.

Aniket Mittal

analyst
#97

So largely, we're still engaging with them. But just to understand, you mentioned that apart from the consultancy work is we look to add in some other services and package that to the DISCOMs. Just to get more clarity, what would these other services be apart from consultancy?

K. Sreekant

executive
#98

No, no. Consultancy is -- we can offer consultancy, but that will be very small and not sustainable. It is [ the one ] kind of revenue. The project is executed, finished. We are looking because the investment requirement being 2 lakh crore, where will the DISCOMs get this money? Either they have to get money from the REC, PFC or other financial institutions. Their own accruals are not that much. So we are going to provide them the technical solution as well as the investment support so that there is a win-win opportunity for them as well as for us as an alternate investment revenue. While doing this, we will be conscious of the kind of returns, as one of the earlier questioners has made, and also the credit quality of the consumer, what kind of payment security. So these are going to be addressed as a package. And we have the wherewithal, we have the capability to deliver systems, to strengthen the distribution infrastructure, to provide them the smart metering solutions.

Aniket Mittal

analyst
#99

Okay. Sure. My next question is actually on the execution front. And just to understand, I think there's been -- there's obviously been the issue of great Indian bustard that's been an override. And I think, recently, CERC has also called up some of your projects in the Rajasthan scheme that you won recently. So just wanted your current view. Do you see any execution risk now for some of the projects that you won on TBCB? And in terms of time line, do you see those can possibly be extended now?

K. Sreekant

executive
#100

What did you say about CERC? That bit I could not understand.

Aniket Mittal

analyst
#101

So I think there was a hearing in the CERC, which they have called out, I think, 3 of your projects which you won in Rajasthan last year. If I'm not mistaken, I think those would be Fatehgarh-Bhadla, the Aligarh I and the Sikar I as well. So with respect to the great Indian bustard being an issue over there. So this...

K. Sreekant

executive
#102

Okay. Let me address this great Indian bustard issue. There are about 150 of the GIB endangered species. There are -- in the Supreme Court, the issue was about undergrounding of low-voltage lines. So in that hearing, the Supreme Court said transmission lines -- low-voltage transmission lines in the priority and potential areas have to be underground wherever technically feasible. Low voltage has to be done, high voltage if technically feasible. Now there is no unanimity on what is a low voltage. There is unanimity that 400 kV and 765 kV are high voltage and extra high voltage. There is no doubt about that. And these voltages levels, you cannot underground the transmission lines. Technically, it is not feasible. So as far as our projects are concerned, we have about 6-odd lines of the 400 kV and a few more in the 765 kV. So as far as our system is concerned, there is no issue with reference -- with respect to this GIB. Second, all our lines and substations are in the potential area, not in the priority area. And if we talk of the priority and potential areas, the size is humongous. It is about 22,000 acres in the priority and another 80,000 acres in the potential. So these are huge tracks of land or areas we are talking about. If -- the issue is more, as I understand, with the solar developer because for them to bring the power from their plant to the cooling station, undergrounding could be an issue and there is an impact financially. There are discussions around this, and the government is contemplating to take up with the Supreme Court appropriately to resolve this. And there is also a deliberation that 33 kV or even lower voltage, which will be the threshold for undergrounding.

Aniket Mittal

analyst
#103

Okay. Okay. So in terms of our under construction TBCB projects, particularly in Rajasthan, there is no execution risk in terms of time line [indiscernible]?

K. Sreekant

executive
#104

There is no execution risk because even if we read the Supreme Court order, it says that where in case of high-voltage lines it is not technically feasible, there is a committee to which reference has to be made. And the committee has to be satisfied and they will permit your undergrounding. Nowhere in the world a 765 kV line is underground and 400 kV also only for short distances, beyond which it is not feasible. So it is not possible for us to build those lines, so we don't see any issue as such. Another matter is that these lines are to cater to the solar generation, right? So if the solar generators are delayed or if there is any issue there, we also need to defer our investment and match ourselves with that. So all in all, there is activity at the government level to resolve this issue, and we hope to come out of this for the entire RE sector and the transmission sector sooner than later for this.

Aniket Mittal

analyst
#105

Sure. Maybe one last question, if I may, is on the quarterly numbers. If I have a look, the number that is reported for adjusted PAT is almost a INR 4 billion increase on a Y-o-Y basis. And that is despite a lower [indiscernible] cost and the TBCB profits going on. So I'm just trying to understand, maybe the growth on a power plant seems extremely high despite the lower late payment surcharge. So am I missing out something here? Is there something additional that's coming?

K. Sreekant

executive
#106

There's nothing to miss out. There is a -- we have received many orders, and there is an increase on account of differential interest between finance tariff and provisional tariff. That is about INR 230 crores, which is a plus, okay? So that can be a one-off number. But then these things come up every quarter, so in the entire cycle of our regulatory business, something [ or other crops ]. But this quarter, this is the number which is there.

Aniket Mittal

analyst
#107

So around INR 230 crores of additional income that's come?

K. Sreekant

executive
#108

Yes. INR 230 crores of income from interest on the tariff differential, yes.

Aniket Mittal

analyst
#109

And this number, would this be continued in nature? Some portion of this will continue again in the next quarters as well?

K. Sreekant

executive
#110

No, no, next quarter, another set of assets may give similar numbers, they may not do. But this is not -- I cannot say that this is a continuous number. Whenever a true-up happens, this comes.

Unknown Analyst

analyst
#111

[Operator Instructions] Next question is from the line of Dhruv Muchhal from HDFC Mutual Fund.

Dhruv Muchhal

analyst
#112

Sir, my question was related to what Aniket asked. So this INR 230 crores is over and above the INR 141 crores that you have disclosed in the notes to accounts, which is the prior period item, is it?

K. Sreekant

executive
#113

It is interest on account of the interest differential. Yes, yes.

Dhruv Muchhal

analyst
#114

Sir, if you can please -- in the PPT, you have started disclosing a lot of numbers. If you can even give us this number because this number can be a bit volatile on a quarterly basis, so this will help us [indiscernible].

K. Sreekant

executive
#115

Okay. We will take it up from next quarter onwards.

Dhruv Muchhal

analyst
#116

Sure. And sir, one question was on the metering thing. So if I understand correctly, what you're saying is it will be the system integrators who will do the billing and the tenders which probably the government calls for smart meters, you will provide the capital for deployment of these smart meters and the implementation of this, probably you will hire IT consultants, probably the executioners, and recover the amount on a monthly basis through the OpEx scheme. Is that the plan what you're thinking of?

K. Sreekant

executive
#117

Yes, broadly, you are right.

Dhruv Muchhal

analyst
#118

Got it. So basically, you will be participating in upcoming smart meter tenders.

K. Sreekant

executive
#119

No, no, no. Okay, you can say we can participate there, but our idea is to more partner with the DISCOMs and engage with them maybe through a joint venture or through kind of some other arrangement which is acceptable to them.

Dhruv Muchhal

analyst
#120

Okay. So in that case, they will do all the billing -- all the tendering. And once the meters are procured, you will implement, then they will transfer to you, you will implement them, you will get the IT and everything done and fund for the capital cost and recovery of capital through the annuity payments that you get from the DISCOM?

K. Sreekant

executive
#121

Yes, broadly, it is that we will invest and get annuity payments. How much we will be involved in design, how much -- that's all to be discussed and finalized.

Unknown Analyst

analyst
#122

Next question is from the line of Anuj Upadhyay from HDFC Securities.

Anuj Upadhyay

analyst
#123

Sir, a few questions. One is on the key projects which we expect to commission in the current fiscal and the project costs, if you can mention the same.

K. Sreekant

executive
#124

Yes. The key projects which we complete are the balance one pole of the HVDC Raigarh-Pugalur system. In that system, one AC line and one pole are pending, 1,500 megawatts plus 1 line. So the pole is almost -- yes, it is ready. Only that line has to be ready. So the line we are having now in single-digit stringing work, hopefully we should be able to do in this quarter and commission this whole system. This is number one. Then fuel transmission systems in Rajasthan, Bhadla-Fatehgarh 2 system, [indiscernible] system, which -- in Gujarat, these are major -- Mithilanchal transmission, which has only now one more substation to be commissioned. So that is there. In Jeerat, we have a substation, a 765 kV substation and a line, Jeerat-Subhasgram line. And these are the major ones which we expect besides the various strengthening systems. Overall, capitalization in the current financial year, we are targeting something of the region of, say, INR 15,000 crores plus. So below [indiscernible].

Anuj Upadhyay

analyst
#125

Okay. So you mentioned about the INR 9,300 crores upcoming. Any time line when we -- INR 9,300 crores of upcoming opportunity in TBCB projects. So any time line when...

K. Sreekant

executive
#126

Yes, yes, some of them have already been announced. For example, the Gujarat 1 is under bidding. And then Rajasthan, once -- they are all expected -- we have to submit the bids and all very quickly, maybe in the month of August and September.

Anuj Upadhyay

analyst
#127

Broadly over next 6 months [indiscernible] these things should come on [indiscernible]?

K. Sreekant

executive
#128

In the next 6 months, the decision will be made about that.

Anuj Upadhyay

analyst
#129

Got it, sir. And if I just broaden my coverage area, over next 2 to 3 years, what kind of opportunity do we expect coming up in the profit line through the [indiscernible], depending upon the current pace at least, [ deliverable ] projects are getting...

K. Sreekant

executive
#130

Let me put it this way. Whether TBCB or not TBCB, the opportunity set which is there and which is under serious consideration or which is potentially is on the Leh transmission system. Two, [indiscernible] transmission system, where a 27 gigawatt of RE capacity is expected to be added, a 20 gigawatt of RE in Rajasthan. These are the 3 key systems where there will be significant investment in the transmission. This is the opportunity set which will crop up in the next 2, 3 years.

Anuj Upadhyay

analyst
#131

Can you quantify, sir, the project costs or the total opportunity in value terms?

K. Sreekant

executive
#132

Can be around INR 40,000 crores roughly. But again, this is a matter of debate because if there is more storage, then there will be less transmission. So all these permutation, combinations are evolving. So -- but if we look at it as a fuel transmission play, then maybe plus INR 40,000 crores.

Unknown Executive

executive
#133

Less intrastate.

K. Sreekant

executive
#134

Intrastate is a totally different segment. Intrastate is one where we have -- another point I would like to share is that there has been a review or there has been a study on the intrastate transmission systems. And one of the recommendations which has been accepted by the government is that the 33 kV system, which is currently as part of the distribution segment, we made a part of the transmission segment so that it is given more attention and strengthening can be made. And there, the government is looking to partner to support the utilities through joint ventures so that the transmission network is augmented and efficiencies are brought in. So this is another opportunity set which we are working on.

Anuj Upadhyay

analyst
#135

Okay. Any [indiscernible] where we already operated the DISCOM on this part? Or it's pretty [indiscernible]?

K. Sreekant

executive
#136

This is very, very early stages. The report has been accepted on the last month. So communications are going from the Ministry to the utilities to follow this practice. So it is too early. But since you are talking of a time horizon of, say, next 2, 3 years, I thought this is another point which has a potential.

Unknown Analyst

analyst
#137

Next question is from the line of Swarnim Maheshwari from Edelweiss.

Swarnim Maheshwari

analyst
#138

Sir, my first question is on NM Transmission. Now if you look at it, there were some cost overruns. And in this quarter, you mentioned that there is a financial kind of a turnaround where you have reported INR 25 crores. So what is it? Is it just related to financial restructuring because it is not that big a project where a financial restructuring could completely change it? Or have you received the tariff order on that or the cost overruns?

K. Sreekant

executive
#139

No, the tariff order is not there. We are still engaged with the CERC. The petition is before them. I think it is listed for hearing shortly, it will be. So that will give the true benefit of our additional cost. What we have done is mostly to do with the financial restructuring because due to high leverage, it was getting into [ pluses ] and all that. So that has been addressed. Plus, now both elements are in operation, so the issue of part element not getting tariff is also addressed. But the bigger question which you have raised, the cost overrun, whether it has been compensated, no, it is not yet. The petition is yet to be disposed.

Swarnim Maheshwari

analyst
#140

And when do we expect that, sir? Because it's pending for a long time now.

K. Sreekant

executive
#141

This financial year.

Swarnim Maheshwari

analyst
#142

Okay. Fair enough. Sir, my second question is on the TBCB projects that we intend to monetize in FY '23, '24, '25. Now what is the mode of the monetization? Is it going to be a normal transfer from PGCL to PG InvIT because I really doubt if that is feasible to be being a CPSE company? So will there be some sort of a bidding? Or how is it going to be? Some color on that.

K. Sreekant

executive
#143

That is to be decided. And then there is another [ comment ] now that the asset transfer, I think, may not happen. That is the -- like for example, in the first set, we have transferred the entire holding there for the life. But here, maybe for a part of the period, we may transfer only the revenue. So these are all things which have to be evolved based on the -- there is a national monetization pipeline, which is expected to come out. That will provide some guidance. And that's why I said in the current fiscal, we don't expect to do any more. It will be for the next fiscal, so we have enough time to address all these questions.

Unknown Analyst

analyst
#144

Sir, we've got 2 more questions and then a couple of questions on chat, if you allow us 10 more minutes. Is it okay?

K. Sreekant

executive
#145

Yes, please go ahead.

Unknown Analyst

analyst
#146

Okay. So the next question is from Bharani from Spark Capital.

Bharanidhar Vijayakumar

analyst
#147

Right. So I have just one question. So the 5 TBCB assets transferred to the InvIT, can you give us maybe final construction cost of these projects?

K. Sreekant

executive
#148

Around INR 7,300 crores was the gross block.

Bharanidhar Vijayakumar

analyst
#149

Okay. So why I'm asking this is if I calculate the equity which you mentioned earlier as INR 1,200 crores inputted in these assets, over INR 7,300 crores comes at 16% of the overall cost. So is that right?

K. Sreekant

executive
#150

Yes, that's fine.

Bharanidhar Vijayakumar

analyst
#151

Okay. Just wanted to clarify because we usually increase around 30%, so I just wanted to check that.

K. Sreekant

executive
#152

These are our TBCB assets.

Bharanidhar Vijayakumar

analyst
#153

Correct. Just wanted to check, sir.

Unknown Analyst

analyst
#154

The next question is from Subhadip Mitra from JM Financial.

Subhadip Mitra

analyst
#155

So my question is with regard to the Leh-Srinagar project as you mentioned that you are looking at a possibility on that coming on the nomination...

K. Sreekant

executive
#156

Sorry, your voice is not clear.

Subhadip Mitra

analyst
#157

Am I audible now?

K. Sreekant

executive
#158

Yes.

Subhadip Mitra

analyst
#159

Yes. So on the Leh-Srinagar project, you mentioned that there is a chance that it might come on nomination basis to VDCL. So what is the expected cost of this project? And if it comes to VDCL, how much addition do you see to your work in hand?

K. Sreekant

executive
#160

The project is expected in the first phase of 5 gigawatts transmission system, roughly INR 21,000 crores. And there will be a component of strengthening. So until it is allotted to us, it will be difficult to put a number.

Unknown Analyst

analyst
#161

The next question is from Girish Achhipalia from Morgan Stanley.

Girish Achhipalia

analyst
#162

Sir, while things are [indiscernible], I just wanted to understand that the smart meter project that you would probably enter into some kind of contracts with the states. The total capital employed, it would be how [indiscernible]? And secondly, in terms of tariff recognition, would it be fair to assume that this would be recovered over a 10-year period on your participation in these kind of projects?

K. Sreekant

executive
#163

Yes. The assets, they can have a life of around, say, 7 to 10 years. That will be more appropriate. If you reduce it too much, the per-month tariffs will go up. So we can expect 7- to 10-year kind of a time horizon for this investment to recover the costs.

Girish Achhipalia

analyst
#164

And what kind of capital employed can you -- I mean any ballpark numbers here that you can think of, of your balance sheet that you're willing to invest both as equity and debt?

K. Sreekant

executive
#165

See, there is no constraint as far as we are concerned. It is the opportunity set which is the constraint, how many discounts, who are reasonably good paymasters are willing to accept our offer and get into it. So from our side, there is no constraint in terms of how much we can allocate, but it is from the recipient side I see the difficulty.

Unknown Analyst

analyst
#166

So we've got a couple of questions on the chat, so I'll just ask them. Sir, the first question asked is that can you give us a CapEx and capitalization guidance for FY '22 and FY '23, please?

K. Sreekant

executive
#167

FY '22, we -- our CapEx is INR 7,500 crores. We expect to cross that. The capitalization, as I mentioned, will be around INR 15,000 crores. '23, we can take -- '23 CapEx will be around similar numbers, INR 7,500 crores to INR 10,000 crores. We are yet to finalize it. Our capitalization will also be around, say, INR 12,000 crores to INR 15,000 crores.

Unknown Analyst

analyst
#168

Sure, sir. Sir, the second question is the level of competitive intensity in the TBCB bids as we've seen many new entrants coming in. So can you elaborate something on the market share you are targeting?

K. Sreekant

executive
#169

No, there is nothing to tell. Every project we target to win will depends on the competition and how far we are willing to bid. Competitive intensity is more or less same. I don't see it has increased any significant pattern, but there have not been many bids in the recent past, so it is difficult to say. The next set of bids will determine how the market is moving.

Unknown Analyst

analyst
#170

Sure, sir. Sir, any upcoming cross-border projects that you can -- you're looking at?

K. Sreekant

executive
#171

One project which is there in discussions is -- it is not exactly a cross-border, it is the Katihar to Bornagar via Bangladesh. So this is one project which has been given to us. It has about INR 3,500 crores kind of investment, and it is to be taken up. Other is the link with Nepal, New Butwal to Gorakhpur. So that is another line that is going to come up. These are the 2 transmission lines which are there, where there is more visibility.

Unknown Analyst

analyst
#172

Sir, are these a part of the INR 35,000 crores of work in hand?

K. Sreekant

executive
#173

Katihar-Parboti-Nagar is a part of it but not the other one.

Unknown Analyst

analyst
#174

Okay. So one of the questions is can Africa or global projects revise CapEx for PGCL's international business?

K. Sreekant

executive
#175

We are looking at, with Africa50, an opportunity for investment in Kenya.

Unknown Analyst

analyst
#176

Okay. Any size that you [indiscernible]?

K. Sreekant

executive
#177

The total investment of that project will be about $150 million to $200 million. So of that, how much will be the debt and equity and all those are yet to be decided. But these are 2 transmission lines and some substations in Kenya.

Unknown Analyst

analyst
#178

Right. Sir, one of the question is that what is your dividend outlook given that you elaborated asset monetization schedule? So any thoughts on that?

K. Sreekant

executive
#179

Yes. Dividend will be better than last year, and it will deploy in the -- say, there were 2 interim dividends last year. So we would definitely maintain that kind of a cash flow. And final dividend, which anyway we will pay after [indiscernible].

Unknown Analyst

analyst
#180

Right, sir. Sir, the last question I would like to take from the chat is what is POWERGRID's addressable share for distribution CapEx of 3 lakh crores? And any update on the Leh-Srinagar project?

K. Sreekant

executive
#181

Well, I answered both the questions already.

Unknown Analyst

analyst
#182

Yes. I think we are through with all the questions. Mohit, do you have any last question? Your hand is still up. Then we can take your questions. Mohit Kumar from DAM Capital. I think, sir, he's not responding so...

Unknown Analyst

analyst
#183

I think we lost [ Rahul's ] audio, sir. I'll take over. Thank you so much for your time and detailed presentation and patiently answering all the questions. We would like to thank all the participants as well for attending the call today. Sir, any last comments that you would like to give?

K. Sreekant

executive
#184

Nothing. Thank you so much. We look forward to your support. Thank you.

Unknown Analyst

analyst
#185

Thank you so much.

Unknown Analyst

analyst
#186

Thank you, sir.

Unknown Analyst

analyst
#187

We can now disconnect the call. Thank you.

Unknown Analyst

analyst
#188

Thank you.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Power Grid Corporation of India Limited transcript — plus 248,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Power Grid Corporation of India Limited earnings transcripts and 248,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.