Power Mech Projects Limited (POWERMECH) Earnings Call Transcript & Summary
November 15, 2023
Earnings Call Speaker Segments
Prasheel Gandhi
analystThank you, Rohit, and good afternoon, everyone. It's a pleasure for Nirmal Bang Institutional Equities to have all of you join us for Power Mech Projects Limited's 2Q FY '24 Earnings Conference Call. With us from the management team today are S. K. Ramaiah sir, Director, Business Development, and Jami Satish sir, CFO. I'll hand things over to management now for their opening remarks, and afterward we'll open the floor to questions from the participants. Thanks, and over to you, sir.
Jami Satish
executiveYes, thank you, Prasheel. Hello, everyone. This is Satish. Good afternoon, and best wishes to all of you. I hope you all had a good Diwali. Accompanying me here are Mr. S. K. Ramaiah, Director, Business Development, and Ch. Speaking as Kotaiah, GM Finance: Power Mech has turned in one more robust quarter, posting solid figures and solid execution. The broad roadmap we have laid out for Power Mech stays exactly as it was. How we are executing and the business plan now underway both match our forecasts and the targets we set internally. It is encouraging to watch a growing stream of opportunities arrive in our main segment, power projects, as a mix of fresh and existing plants come back to life. We're also quite enthusiastic about the many opportunities we're seeing in operations and maintenance, in both the domestic and international markets. This year, a substantial addition to our order book will come from the O&M space through various projects in the pipeline that are at an advanced stage, and orders from O&M during this year are going to reach an all-time high across Power Mech's 24-year history. At Power Mech, we're seeing quarterly execution bandwidth rise from one quarter to the next. Looking ahead, we'll see the numbers climb significantly. In any given financial year at Power Mech, execution in quarter 3 and quarter 4 contributes considerably more than quarter 1 and quarter 2. As a result, we expect the quarterly execution cycle to improve considerably across the remaining quarters of financial year FY '24. Turning to the quarter 2 and H1 figures: reported total income for quarter 2 FY '24 stands at INR 937 crores, while EBITDA came in at INR 118 crores and PAT at INR 51 crores. In quarter 2 of the prior financial year, reported total income was INR 774 crores, EBITDA was INR 89.5 crores, and PAT was INR 44 crores. So, comparing quarter to quarter, Power Mech has shown roughly 21% growth on the top line, and alongside that top-line growth, EBITDA rose by almost 32% and PAT increased by 17%. For the second quarter of FY '24, here's how revenue broke down. Mechanical brought in INR 148 crores; Civil, which includes railway and water distribution, INR 496 crores; O&M INR 272 crores; Electrical close to INR 17 crores; and others close to INR 5 crores. Back in Q2 of FY '23, Erection contributed INR 161 crores, Civil INR 367 crores, O&M INR 226 crores, Electrical INR 17 crores, and others INR 3 crores. Growth in O&M was roughly 20% and in Civil about 30%. Erection was more or less flat, though that number should rise considerably going forward. Regarding Electrical, we've made a deliberate choice not to pursue new projects, so that segment is essentially holding steady. Now looking at the first half of FY '24: total income reached roughly INR 1,808 crores. EBITDA stood at INR 223 crores, with PAT at close to INR 102 crores. During H1 of the prior year, total income was INR 1,523 crores, EBITDA came in at INR 175 crores, and PAT was INR 83 crores. That works out to about 19% growth for H1 compared with last year, and together with the top-line increase, EBITDA has risen substantially—by nearly 27%—while PAT has gained almost 23%. Likewise, the O&M and Civil businesses have grown 17% and 33%, respectively. Mechanical is down 8%, but it should keep growing through quarter 3 and quarter 4, while the Electrical business is declining since not much order booking is taking place there. This year we expect a significant contribution from the water business, given that its order book is quite healthy. O&M remains the backbone of the company, contributing roughly 27% to 28%, and by the end of the year that percentage should stay more or less the same. In FY '24, thanks to the healthy order book, water will keep contributing close to 20%, 25% of total business. O&M will stay at 25% plus. Mechanical, both domestic and international, will stay at almost 18% plus. Railways is rebounding, helped by the metro coming in, and this year we're looking at close to 4%. Over FY '25 and FY '26 there will be a notable change in the mix of our business, since water, with the healthy order book it has, is set to account for roughly 18%, 20% across the coming 1.5 years. Erection should grow to about 25% to 26%, while railway ought to reach 7%. MDO starts this year at a modest level and should expand substantially across the following 2 years. For FY '25 we expect close to 8%, and for FY '26 close to 16%. As the O&M portion and the MDO business expand, the mix of our business is going to shift considerably. Beyond that, we're observing gains in the overall margin profile, and that should continue getting better step by step; then, when MDO hits its peak in FY '26, the margin profile will improve by a far larger degree. Depreciation expense as a share landed on the lower end, which we owe to disciplined CapEx spending. Finance cost—leaving out the interest on tax impact—as a proportion of revenue likewise came in lower and is still being kept in check, thanks to stronger working capital and cash flow. You all know that the Income Tax Department conducted search operations under Section 132 of the Income Tax Act 1961 in July 2022. Following discussions with the assessing officer, and as a prudent move to avoid any further prolonged litigation, the company has made a provision of INR 16 crores for assessment year '18 and '19. To date, the company has supplied all the information requested by the department. With better capital deployment and improved margins, we have also seen an improvement in ROC, and it should rise significantly once again. We've mentioned on previous calls too that our overall capacity to execute is rising each quarter, driven by several initiatives and a significant increase in internal resources. The company can now comfortably handle projects worth between INR 1,200 crores and INR 1,800 crores per quarter. A few other updates: operating cash flow for this period came in positive at close to INR 70 crores, and system-generated free cash flow was just over INR 50 crores for the period, which is quite healthy.
Jami Satish
executiveWe’re continuing to work on the same things to make further improvements. The company’s average monthly collection also stayed healthy. More importantly, net current base, excluding cash and cash equivalent, improved substantially because of a better working capital cycle, a change in business mix and a change in customer concentration. Net current days have fallen to a range of 130 to 135 days. And once the MDO business stabilizes from FY ’25 and ’26 onward, we can expect a significant improvement in net working capital days, and that can help the system generate larger operating and free cash flow. We can see a quantum jump in free cash flow. More importantly, gross debt and net debt stayed controlled despite growth in the business and order book. As of 30th September 2023, gross debt is close to INR 450 crores and net debt is INR 226 crores; but if we look today, we can proudly say Power Mech is a net debt-free company. And the debt equity ratio as of 30th September stands at 0.3, which has come down significantly because of the improvement in cash flow. But if you look at net debt today, it is nil because net debt is almost 0. Coming to these 2 MDO projects, a lot of developments and ground activities are happening at both projects. For the first project, Kotre Basantpur, we received Stage I forest clearance in November — from the government we got it in November. Environment clearance we have also obtained. Now the project is ready to start because EC and FC were the major milestones we achieved now. And we have applied for consent to establish; that is expected within the next 1 month. Therefore, we can start ground activity from this year itself; and coming to the second project, establishment of mining activities was already completed by October. And more important is the heavy equipment, which is very important to start excavation — we have started procurement and transporting the equipment, and these equipments are expected to reach the site within the next 1 week to 10 days. And core drilling activities already started on 3rd of November. And the EP consultant, M/s Vardan EnviroNet, the finalist for the washery. Apart from that, the electrical connection, okay, for 1.46 MV allotment along with the demand note received for JVVNL during October. R&R Colony fencing work already started. Apart from that, mining area fencing work already started. So we are expecting the bhumi puja in the next 1 week. Therefore, we can start excavation work — during end of this month itself. Therefore, we would see revenue picking up from this financial year itself. Coming to the order book. Order backlog as of 30th September is around INR 53,100 crores with both the MDO, and excluding the MDOs, the backlog is almost INR 13,400 crores. In a similar way, the backlog in our order book today stands at roughly INR 53,500 crores when you include both MDOs, and if you take the MDO out, that figure comes to INR 13,750 crores. Across the full year, FY '23-'24, the company is looking at a target of INR 10,000 crores, and that target stays unchanged. We feel confident about getting to that number, counting the orders already booked so far of INR 1,800 crores plus, along with projects sitting in the pipeline at L1 status worth close to INR 1,800 crores; we have also identified an opportunity size of about INR 46,000 crores plus. On top of that, we anticipate a healthy volume of order booking and an education cycle in the international market as well. Through FY '24, we expect a large uptick in orders from the power sector, in both O&M and Mechanical and Civil construction. As we said before, our focus going forward will stay on consolidation and on leveraging growth, and we will keep concentrating on the industrial plan, operation and maintenance, railway and metro, water, and to some degree road and MDO projects. The execution cycle across FY '24, '25 and '26 should be robust and healthy, thanks to a better order book backlog and the targeted projects in the pipeline, and even more importantly, greater bandwidth in the execution cycle each month and each quarter. As projected, the margin profile appears to be improving and is expected to keep improving gradually year-on-year. Our plan is to build a business model that delivers recurring long-term service income of INR 3,000 crores to INR 3,500 crores plus, combining O&M plus MDO, for sustainable long-term growth starting FY '26 if possible; this model will help us considerably in improving the margin profile, the working capital cycle and, to a large extent, the free cash flow. Power Mech is well positioned to show execution and conversion of 34% to 35% of its opening order book within a year. Beyond that, revenue from the MDO business is also ramping up at the coking coal production plant. Looking ahead, the O&M and MDO business will drive substantial growth in a significant way. And we have some further developments on the business side. I'll ask Mr. Ramaiah to add to that, please.
Sudha Kodandaramaiah
executiveYes, thank you. Good afternoon, everyone, and thanks, Satish, for those opening remarks covering the various Q2 figures. As Satish mentioned, the outlook remains bright, and the reason is the enormous spending by the government sector across all these areas — energy, infrastructure, drinking water schemes, water systems, railways and the metros. That is where the company is going to align with this business. And of course, in O&M, a lot of revival is being seen. As per the numbers, as Satish laid them out, segment-wise: in ETC and Mechanical, the current backlog stands at about INR 7,052 crores versus INR 6,878 crores at the start of the year; the Civil part of the work is INR 6,074 crores against INR 6,736 crores. O&M is INR 353 crores versus INR 600 crores — of course, certain numbers still need to be added, and those will come up now. Then Electrical is INR 255 crores against INR 118 crores; and MDO is a major component of our business, with roughly INR 39,732 crores of backlog across both MDOs; that should give us a very healthy backlog in the near term — 2 to 3 years — and for the long term, say 25 years. On the MDO side, INR 53,111 crore as of September end, and as of today INR 53,500 crores. Now, when we look at opportunities, what we see is what appears to be a substantial revival of the power sector market. This is mainly driven by the apprehension of a load mismatch that will occur in a couple of years between coal-based power generation and the non-coal side, that is renewable power — if present renewable capacity is about 125,000 megawatts, I mean, with a total installed base of 4,11,000 megawatts and all. Renewable power will be further augmented as the years go by, and that is why the government has taken some remedial actions by fast-tracking investment in new projects. Present indications are that, apart from NTPC, which is planned and has already ordered Lara for BHEL, other projects are going to be in the pipeline, like Sipat, Daripalli, Singrauli, Meja, Ramagundam and Patratu as well. Then the GENCOs, the generation companies, have a plan of about 10,500 megawatts. That is going to come up substantially. Recently, the government also approved the Yamuna Nagar project. And looking at these projects, the expected capacity addition over the next couple of years should be about 23,300 megawatts. These are all new projects, is what I am trying to say. On top of that, projects are being revived for both — action has already been taken on many of the first projects totaling 5,270 megawatts. We've also made some moves already toward securing orders there, with Vedanta and with <<inaudible>> as well. Recently, the government — a Policy Minister, on direction from the Power Ministry — has said that another 5,500 megawatts of stuck projects also need to be revived, and it has directed that state government undertakings participate in these bids too, so that revival happens. So the revival of close to 10,000-plus megawatts, plus a new addition of 23,000 megawatts — that should provide a very good outlook for growth in the power sector. And in terms of — our business aligns quite well with that when it comes to the main installation work, erection testing, commissioning, the O&M jobs and all of it. So that's one aspect, on the new units, and also the revival of the old units I mentioned, about 10,000-plus megawatts. Well, O&M opportunities have picked up substantially. Recently we've seen that we took 2 major jobs — Hindustan Zinc Limited, with compensation for O&M of about INR 279 crores plus O&M contracts; that's a very important break-through, in the 2 mining and metal sector, the non-power sector, that we've taken. And then Raichur 2x600 megawatts at INR 163 crores; and then Adani at Mundra, where we've taken roughly INR 100 crores of jobs across various O&M packages. Now the opportunities we're tracking in terms of new projects coming up include Khurja 2x660 megawatts, Ghatampur 3x360 megawatts, North Chennai possibly 1x800 megawatts, and then Buxar, of course, as commissioning comes to that, and then there's a major project at Balco with the Vedanta group, which we're also having a look at. So all these opportunities — the ballpark figure in terms of BTG, installation plus civil and CHP, which is our core strength flow, because coal handling and material handling is one of our core strengths that we've established — comes to about INR 12,000 crores of opportunities with these new projects coming up. And then revival of the old projects as well can add another INR 4,000 crores to INR 5,000 crores. Now it can anyway reach between INR 17,000 crores and INR 20,000 crores of opportunities, both with the addition of new capacities and with the revival of old projects where half-completed jobs are to be taken up. And there, execution — fast-track execution is there, and Power Mech is a preferred bidder for that. And as you've seen in the case of the Vedanta group for the <<inaudible>> job. And recently we have one more major order with BHEL for Talcher at INR 354 crores, the main part equipment associated work and civil work as well. So with that type of initiative, this will continue to play out in the coming months and coming quarters too. Turning now to the remaining water-related projects, we've largely pinpointed a very large opportunity, especially in Madhya Pradesh, followed by Karnataka and Tamil Nadu, and Madhya Pradesh again, as I mentioned. So across all of these projects, the overall opportunity comes to roughly INR 18,000 crores. Madhya Pradesh on its own is planning around INR 9,000 crores across different schemes covering drinking water, the AMRUT scheme, urban water requirement kits for various towns and cities, sewage treatment plants, and so on. Given our fast track execution expertise, what we're developing in UP for the drinking water scheme, we're probably well qualified for a good number of these jobs. And wherever needed, we can also form tie-ups with other parties, since micro irrigation, lift irrigation and schemes of that kind are also arriving in a big way, and that ought to help us. The different segments of these water systems, or the sewage treatment plants, urban renewal schemes and the AMRUT scheme, then water supply schemes, lift irrigation schemes, canal works, and then, naturally, the most important one is Jal Jeevan Mission, which is a flagship initiative of the Government of India. It's encouraging to learn that nearly 70% of rural villages are now well connected.
Sudha Kodandaramaiah
executiveSo we're performing quite well on the drinking water schemes in UP across our 4 major areas — roughly INR 2,800 crores, somewhere between INR 2,750 crores and INR 2,800 crores. And we've finished close to 40%, 45% of that work. Naturally, this gives us a solid reference base and expertise, since the kind of organization we set up there is a distributed one. What I mean is a distribution setup that reaches right down to the grass-root level — village level, area level, then block level, district level and zone level. So it's a well-structured organization, with nearly 4,000 people working. And already in about 100 villages we've completed the 100% water supply scheme, water is flowing to those villages, and people are seeing the benefits. What matters even more is the organization we built — about 4,000 people across engineers, supervisors, field and all the working staff, subcontracting staff — that should give us a strong base for undertaking many important water projects, drinking water projects, et cetera, as well. Then another important thing that came up recently: as we finalized these contract agreements with the Jal Jeevan Mission scheme with the UP government, the numbers for the operation and maintenance scope of the work are finally out. Previously only a general future was involved in the LOI, but now they've firmed up the figures for operation maintenance, because as we complete execution of these projects village by village, it's estimated that 3% of the capital cost will come for the O&M over the 10 years, with an escalation provision. And the current estimation is that the UP government has given numbers of about INR 681 crore. And we hadn't been counting this in our order book so far; we've only just figured it out now. And of course, in another 3 to 6 months, we'll start opening up that O&M front as well, with more and more villages coming onto the front line. Now this is on drinking water and water systems. And then, of course, in railways, we've seen the experience we're gaining in Bangalore, Challaghatta, INR 427 crores. And we're doing about 14 railway projects worth INR 1,500 crores, apart from the — including the BMRCL job. And that is given, and recently we've taken some jobs on the railways. And then Raebareli, we've taken an infrastructure facility for the Vande Bharat infrastructure facility. And then we're working with — Mumbai, also, we've taken foot over bridge, some jobs as well. So these opportunities will keep coming, and railways and metro together offer huge opportunities in terms of railway infrastructure in maintenance depos, workshop, repair shops. And then all of this, revamping of the station and all those things. And it's a strong advantage that the organization is now set up to carry out these jobs. That, I believe, is part of what lies ahead for Power Mech. We keep building organizational capacity wherever we have diversification, and we want to maintain those kinds of organizations for long-term growth and so on. And naturally, whenever viable projects exist in the railway — in the road sector as well, we will take them on. For instance, the Telangana job we took from Adani, the EPC, we've completed almost 70%. That's very fast progress, we can say, that we've achieved; and then the other 2 projects too, we've done close to 60% of the work in Mizoram and then Karnataka as well. Given this background of these road projects, the railway projects ought to give us a solid background; and then the new initiative is going to come up in West Africa and Nigeria, Ghana, Tanzania and other places, with support from the Middle East. Some new projects are expected to come with 4,000 to 5,000 megawatts in the Middle East, Saudi Arabia then UAE and so on. And already, we have the organization there of about — as of today, 1,600 people are working in the Middle East and then West Africa and so on. For that organization setup too, it keeps helping us to see that we can take on the new jobs and implement them as well. So, as Satish rightly said, there is a substantial opportunity in the market as part of the National Infrastructure pipeline, which is in the fourth year of its implementation — part of the fourth year of the implementation of the INR 111 lakh crores. And many of the organizations that can keep pace with that are benefiting, including us. And we have been greatly benefited by this investment from the government side. And then private sector investments will also come up in the steel sector, mining sector and then the coal side. And then Coal India is coming with first mile connectivity around 50 projects with an investment of INR 20,000 crores. So there are plenty of opportunities. We have to select the right technology, the right partnership wherever it is required for the association where we don't have that in some of the new areas. And then the implementation mechanism has to be established with the learning we have achieved. And one of the features I can mention is that while our margins can improve further, it's the learning curve we were undergoing, with not much addition in the capacities for manpower and also the equipment base that we have — if you see the turnover, it is continuously growing up year after year, and that is a good future for our operations. And that means margins can be pushed lower as we go forward; and as additional opportunities arrive, maybe we will see improved margins in the market as well; so that is my take. At this point we can move on to the questions and answers.
Jami Satish
executiveYes, yes. Prasheel, I appreciate the chance. Let’s go ahead to the Q&A.
Pratiksha Daftari
analystI've got an initial question about that tax provision you brought up. Could you say the figure again — how much has been set aside because of the search?
Jami Satish
executiveSure. We've made a provision of roughly INR 16 crores, madam. That figure includes some interest on this tax. So all told, it comes to INR 16 crores that we've provided for.
Pratiksha Daftari
analystAll right, so that's the entire provision then. And going forward, you don't expect any additional provision to be required?
Jami Satish
executiveCorrect. What they've done, you see, is finish things up for a number of the assessment years, so we're not anticipating any larger sum coming through, all right? Perhaps over the coming 2 quarters, we'll find that this matter is fully settled, 100%. So the provision might stay at roughly a slightly lower level than the amount we've provided for. That said, though, we've received refunds of close to INR 40 crores, INR 45 crores and more, so where cash flow is concerned there's no effect; it will, however, have some effect on the provision side of things.
Pratiksha Daftari
analystGot it. Now on the O&M side, we've already used up nearly INR 500 crores of revenue during the first half. I just want to ask what target we're working toward for this year. How much growth do we expect versus FY '23 on O&M?
Jami Satish
executiveThis year O&M will likely come in near INR 1,150 crores to INR 1,180 crores — that's what we're aiming for. It will probably still account for roughly 25% to 25.5% of our overall business this year.
Pratiksha Daftari
analystAll right, got it. So what's the monthly collection run rate at the moment?
Jami Satish
executivePratiksha, this is the one speaking — it's currently sitting at roughly INR 350 crores to INR 400 crores. And — look, in general, quarter 1 and quarter 2 have historically made up something like 35% — 35%, more than 35% of our total business; but even so, in quarter 3 and quarter 4, there will be a pretty significant jump in quantum. So we expect that figure to start climbing from around quarter 3, December onward. And I'm saying that figure ought to gradually go past INR 400 crores, INR 450 crores.
Pratiksha Daftari
analystAll right. All right. Got it. So we had roughly INR 3,000 crores plus in orders coming from the water segment; so I just wanted to ask what execution guidance you're giving for water projects in FY '24?
Jami Satish
executiveFor water projects?
Pratiksha Daftari
analystYes.
Jami Satish
executiveYes. Look, water is going to account for a meaningful slice this year, since the order book is substantial. If everything goes according to plan, in FY '24 we're looking at roughly INR 900 crores; that figure sits at the low end, and it could reach INR 1,000 crores, or INR 1,050 crores at the top end.
Pratiksha Daftari
analystOkay. Right. Fine. Now, our interest expense rose quite a bit this quarter — is that due to bank guarantees or something along those lines, since the debt figures haven't increased in Q2?
Jami Satish
executiveTo be candid, finance costs stayed under control. As mentioned, there's some interest cost impact stemming from IT. The INR 16 crores provision therefore includes a portion of that interest. That's why you see a rise of roughly INR 3.5 crores to INR 4 crores. Apart from that, if you take it out, finance cost is flat. Yes, so this is a — it isn't a recurring item, it's more or less a onetime thing. So water perhaps will close this year, so that no ambiguities remain on this fund, okay? So you'll see that figure declining, because looking at net debt as of today, we're almost debt free. I don't expect this number to shoot up.
Arun Subrahmanyam
analystSir, I'd like to ask what sort of order inflow you're aiming for in non-MDO during this current financial year?
Jami Satish
executiveSir, we've set a target of roughly INR 10,000 crores, so that target stays as it is; up to now we've closed about INR 1,800 crores of additions; beyond that, the projects sitting at L1 come to roughly INR 1,800 crores plus. And we expect a healthy volume of additions to come from the power plant, on the O&M side as well as civil and mechanical; taken together, we're looking at close to INR 4,500 crores. So we'll have a mix of orders arriving from power plants, okay, both the old plants and the new ones. And in O&M this year, we may go past INR 2,500 crores to INR 3,000 crores of addition. And beyond that, we're also aiming at close to INR 1,500 crores of projects connected with water. Aside from that, if everything works out, railway and metro, we may add close to INR 800 crores to INR 850 crores. And other civil plus international taken together, we're planning INR 10,000 crores.
Arun Subrahmanyam
analystGot it. Sir, why might the order inflow have been a bit slow in the first half? And what will actually be different going forward?
Jami Satish
executiveIn the first half, you see, we were focused more on the domestic side, largely on the power sector and part of the railway, besides the road projects, alright. Naturally, O&M has been pretty much at the finalization stage, okay. Even so, when it came to awarding, it took a somewhat longer period. Beyond that, some of the state selection code and such, some of it may have spilled over into December and so on. So more crucially, what matters is that the negotiation piece is nearly finished at this point. We could see that conversion taking place over the next 30, 35 days. So perhaps in December and January is where we'll see a big number come through; and besides that, on road projects, we've seen the tender get pushed back a couple of times. Naturally, this is close to INR 800 crores to INR 950 crores, which is what we were expecting. And in Chennai, things were somewhat slow when it came to discussions and negotiations. That portion we have now finished. Beyond this, Vedanta took a somewhat longer period; but naturally, order conversion has begun to happen. On top of that, we are also in talks on some O&M projects with Vedanta and BHEL as well. Perhaps we'll see that — normally, historically, if you look at it, conversion in the first half is historically lower, but the second half is higher, even when it comes to execution order inflow too.
Sudha Kodandaramaiah
executiveYeah, I believe Satish has it right. Look, what's also going on is, of course, the elections — state elections are underway. Most likely the centers are out, and that's where our confidence comes from: there are identified projects, drinking water, the power side, railways, and roads too. And international is in there as well. So the opportunity size is substantial, given the inquiries coming in. Inquiries are plentiful. Whoever picks the right mix of these products — projects and their execution, and our fit in there — and then makes sure we sell into the current projects with proper execution, that's one of the themes. Maybe the first half is always like that because of the rainy season, and then a lot of the clearances have some issues, so they may take longer to firm everything up. And in the case of drinking water and the water system, what's happened is this is perhaps the last phase of ordering, or maybe the last but one as well. So they're now trying to finish that exercise. That's where there are roughly INR 18,000 crores to INR 20,000 crores of opportunities. And the new power projects, because Lara has been awarded — there was a delay in awarding it too; now it will move ahead. On Talcher, they've already taken action and all. Now with the revival of projects, what's happened at Athena, we've seen the benefits of that, and there will be more opportunities there as well. And if the second phase of reviving the old projects, another 5,500 megawatts, also happens, more opportunities will come too. Maybe there's a bit of adjustment in the time lag and all. But overall, opportunity-wise, there's no shortage of it in the domestic market. At least we're very bullish on that across all these segments and all. And railways — in fact, if you look at the track record of 14 projects that we're doing and the metro projects we've taken, there are a lot of huge opportunities there as well. And we're into many of those things. And the usual second time, once it happens, actually we'll be able to close it by the third and fourth quarter, somewhere around there.
Arun Subrahmanyam
analystSir, so only as a follow-up, from all of your order backlog, once you account for any projects moving slowly, the ones taking longer than you expected, and if that is the case, are things going to be getting better in your...
Jami Satish
executiveSir, could you say that again, sorry?
Sudha Kodandaramaiah
executiveYes, sorry, there was a lot of disturbance.
Jami Satish
executiveYeah, there is some disruption.
Arun Subrahmanyam
analystSir, I’d just like to ask about the order backlog you’re holding: is there any slow-moving project you would want to flag, one that is running a bit behind what you originally expected, including the large one you received — the big one you got last year — is any project slow-moving? And will that improve at some point soon?
Jami Satish
executiveNo, no, none of the projects are old or suspended. All of them are ongoing projects. The plan remains intact. Sure, there were some schedule changes when it comes to ordering and all, but the plan itself has not changed — the overall plan.
Prasheel Gandhi
analystI have a couple of questions. First, can you give us an update on where our FGD order stands and on the potential revenue booking that will occur across the next few quarters?
Sudha Kodandaramaiah
executiveYes, the first matters, or problems, concerning the layouts and engineering of certain types are needed in that, most likely; at present the engineering orders have been placed, and tracking will follow on that. Take the Udupi projects, for instance, 2x525 megawatt — we are taking action on that one. And that is — it should be roughly around INR 800 crores that would take shape now on a priority basis. And then other projects should follow as well. So with FGD, if you look at it per se, what is happening is that the major <<inaudible>> implementation is, to some extent, fitting the system into the limited space, along with the technology selection and the fitting of that. And as of today, if you see 12,000 megawatts — sorry, about 10,000 megawatts are in capacity addition on the activity side, out of 1,69,000 megawatts identified. But ordering has built up on about 1,05,000. Therefore, in most of these things, there is a general amount of a little bit of lag initially, because of the finalization of engineering, layout issues and all. And of course, on the other side too, there can be some issues related to fixing the tariff as well, those inferred with the DISCOMs and electricity boards also. And that is where the government is also a little bit giving the — giving way for them to implement it, but they are very firm on that. Now for all the projects, the latest update is that the government has extended the deadline up to 2027. That is the overall requirement for the entire country; but where the ordering has been done, the usual contracts and schedules will be there, barring the issues related to engineering fit-ups and then the layout issues finalized, all the access availability and those type of...
Jami Satish
executiveYes. So revenue-wise, Prasheel, probably around FY '24 — perhaps quarter 2, quarter 3, quarter 4. For quarter 3, we may expect somewhere between INR 50 crores and INR 100 crores. Then quarter 4, it could rise to somewhere around INR 250 crores to INR 300 crores. And for FY '25, maybe within the range of INR 1,000 crores to INR 1,200 crores, or it might increase a bit more by another INR 200 crores, INR 250 crores. That's the plan we currently have. We'll likely have more of an update for this quarter 3 — we'll take it at the end of quarter 3 or perhaps at the beginning of quarter 4. We'll look at the scheduling side and see if anything can be improved in FY '25.
Prasheel Gandhi
analystSure, sir. Sir, second thing, regarding your margins — you're saying they went up quite a lot, roughly 19 bps year over year; so can we expect this — first, what's driving it? And second, how should we think — would you anticipate more margin improvement? So what do you see as needed to reach sustainable margins, could we assume something like 13% or 14% margins?
Jami Satish
executiveLook, we had — the first priority is to bring the overall project mix down. So our royalty cost, which hits our EBITDA margin directly, ought to decline, and that is already happening; there's a natural mix shift as a result of rebuilding the PQs in-house directly. So to some degree, and to a bigger degree, that's helping us push margins up. So the first priority is getting back to our usual historical margins, which we used to report at 13%, 13.5%. And that's quite achievable in FY '25, '26. And once MDO stabilizes by FY '26, we could see that figure rise to 13.5% plus from '26 onward; so the first priority is restoring our normal margins to 13%, 13.5% by FY '26. So we'll see gradual improvement in the margin profile each quarter. And beyond that, we've issued a clear instruction to our business development team, mainly concerning any projects that fall below threshold margin limits. So we're not rushing into projects at low margins simply to build the order book; that too is helping considerably in adding quality orders and keeping the margin profile intact.
Prasheel Gandhi
analystSir, just one more question on that. What's the present mix across your legacy projects? In other words, how much of the order book still carries those older projects that come with higher royalty payments? And when should we expect that to finish?
Jami Satish
executiveBy FY '25 this will settle down. So we could put it at another 25% to 35%, within that range.
Analyst
analystWell done on a really strong set of numbers. Apologies if I'm covering old ground here. The thing is, you mentioned earlier that finishing the MDO projects could mean you'd need to take on some debt in addition to the equity you've already raised. So do you have any plans to raise more debt, or not?
Jami Satish
executiveYes. Sir, for the first project, Kotre Basantpur, KBP, which is the smaller one, okay, we've already secured Power Finance Corporate, PFC, INR 260 crores, and that's project specific, with servicing handled by that SPV; so that arrangement is already in place. As for the second project, we need to put up the infrastructure; beyond that, we also have to construct a washery plus coal-handling plant, which is bigger in size. So that one is expected to come to roughly INR 790 crores plus. So we've raised the equity, meaning we have enough equity. That said, we've lined up some debt portion from our existing banks, and whether we use it or not, we'll decide, because the internal system itself is generating some surplus cash flow. So whether we want to use it or not, we'll probably make a gradual call. Of course, the PFC part we will use. But on the second part, Tasra washery, we'll take a call gradually, sir; we'll take it if at all it's needed, but at least for the next 16 months there won't be any increase of debt in the Tasra project.
Analyst
analystAll right, that's very helpful. I have just one question. We're now nearly 1.5 months into Q3, so what's your estimate for the Adani project? You did mention it, but I'm asking because we're already almost 1.5 months into Q3 — what's the status there? Could there be any possibility, and what kind of revenue booking might happen there?
Jami Satish
executiveLook, for Adani, as I said, in quarter 3, perhaps somewhere between INR 50 crores and INR 150 crores is the maximum we can achieve in quarter 3; we're working toward that and we've already spent some money. And out of all the packages, Udupi is fairly active; so gradually, by FY '24, the most I'm expecting is INR 250 crores to INR 300 crores, INR 350 crores. That's for the Udupi package, we may reach, possibly...
Analyst
analystFor the second half overall, you're looking at somewhere between INR 300 crores and INR 400 crores. Is that a fair estimate?
Jami Satish
executiveNo sir, across all of FY '24, I expect something in the range of INR 250 crores to INR 350 crores. For Quarter 3, perhaps somewhere between INR 50 crores and INR 150 crores.
Analyst
analystAll right. One final point about exports. That order book you're aiming at and have referenced at INR 10,000 crores — does it cover both domestic and export business, or is it purely domestic orders?
Jami Satish
executiveSir, it's combined. On exports, we haven't set a bigger target for this year. The most we're looking at is perhaps INR 250 crores to INR 300 crores. Out of that, INR 180 crores to INR 200 crores is O&M on its own.
Analyst
analystThat's negligible, so it isn't...
Jami Satish
executiveFor FY '25, probably, we might have to maintain a bigger target. But this year, we've kept a softer target.
Bharanidhar Vijayakumar
analystSo when you talked about the opportunity in the power sector from these new projects, you said projects totaling 5,270 megawatts from reviving projects are also included; so my question is just whether these are projects that were already announced but got stalled for various reasons and are now coming back up?
Sudha Kodandaramaiah
executiveNo, they are firmed up. All of these are well-regulated; that comes under what is called inflator schemes, and then they were tendered and awarded, for instance, JSW has taken the job in Orissa, then Meenakshi in Andhra Pradesh, Vedanta has taken it. So with the final round of rebidding now complete for the Amarkantak 2x660 project involving Reliance, PFC had originally been the frontrunner, but Reliance has since come in with a stronger offer — pardon me, it's Adani that has put forward a more attractive bid. So in that sense, the bulk of the project's first phase — the roughly 5,000-plus megawatts I mentioned — is more or less locked in. What I'm getting at is that this alone will get us perhaps halfway there, and it will require a sizable outlay — typically somewhere in the range of INR 15,000 crores to INR 20,000 crores in total investment. Within that, our own share, our opportunity size, comes to between INR 4,000 crores and INR 5,000 crores. Turning to the second set of NCLT projects, the government has now provided more detail, noting that state GENCOs and other companies have likewise said they can take part in those as well, and it has published a list of those projects too. That too amounts to a substantial figure, roughly 5,000 to 3,000 megawatts. When that materializes, it will add to the opportunities. So that's essentially the situation, as I see it — the government is being quite resolute about this revival, and that's mainly due to the alarm that's been raised. But when you look at it as a renewal factor — the rising share of power growth — there's potential for major disruption on the grid. They're keen to prevent that, and such a scenario could emerge at any point within the coming two to three years. Their aim is to close those gaps quickly, ensuring base load operations get properly established, with coal-fired plants on hand for daytime operation, after which renewables take over the majority of generation and so forth. So I believe our understanding on this is quite clear. That is also the reason we believe our organization, our setups, and our people—what we have and what we're achieving—are key, and we're putting major focus on these new projects as well.
Bharanidhar Vijayakumar
analystAll right. All right. Got it. For my second question: naturally, you brought up NTPC's new projects. And this turnaround plus the NCLT projects, another INR 10,000 crores. Yet nothing is said about any projects coming from state GENCOs — why would that be? Do you also see state GENCO projects in the pipeline?
Sudha Kodandaramaiah
executiveYes. I think the government has stated that — why the state government, for instance, the private sector is stepping in; for instance, Adani has taken over. Vedanta has taken over. Reliance is also bidding for <<inaudible>>; then JSW has taken that Orissa project of the IPP. And then JSL has taken over <<inaudible>>. Now what the government is doing is they want to announce the basket of this one for the bidders; and that's the way — I think this came just 1 month before. I have seen on the website of power industry, and with a clear guideline, and they want to push these balanced projects as well. They've got a list of projects; if required I can share that separately.
Bharanidhar Vijayakumar
analystAll right. Perhaps I'll reach out to you afterward to obtain that. Actually, what I wanted to ask about was state GENCOs — for instance, TANGEDCO or AP GENCO — these state GENCOs aren't stepping forward...
Sudha Kodandaramaiah
executiveRight, right, precisely. What you're saying is precisely the position we're in at the top. Yes, the government has backed them to take part. That is — they put out a circular. They put out a dedicated circular on this. If it's needed, I'll forward it to you.
Operator
operatorSince no one else has a question, at this point I'd like to pass the conference back to management so they can offer closing remarks. I'd like to turn the conference over now to Mr. Prasheel Gandhi for closing comments; on behalf of Nirmal Bang Equities, that brings this conference to a close. Thank you for being with us, and you can disconnect your lines at this time.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Power Mech Projects Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Power Mech Projects Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Power Mech Projects Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.