Power Mech Projects Limited (POWERMECH) Earnings Call Transcript & Summary

February 12, 2025

National Stock Exchange of India IN Industrials Construction and Engineering earnings 69 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, everyone, and welcome to the Power Mech Projects Q3 FY 2025 earnings conference call. I'd like to remind you that every participant line will be in listen-only mode, and once the presentation wraps up, you'll have a chance to ask questions. If you need help at any point during this call, just signal an operator by pressing star, then zero on your touch-tone phone. Please be aware that this conference is being recorded. At this time, I'll turn the conference over to Ms. Teresa John from Nirmal Bang Institutional Equities. Thank you, and over to you, ma'am.

Teresa John

analyst
#2

Speaking for Nirmal Bang Institutional Equities, I'd like to welcome everyone to Power Mech Projects' Q3 FY 2025 earnings call. Joining us from management today are Mr. Nani Aravind, the company's CFO, and Mr. S. K. Ramaiah, Director of Business Development. I'll now pass things to management for their opening remarks, and after that we'll open the floor for Q&A. Thanks, and over to you, sir.

Nani Aravind

executive
#3

Thank you, Teresa John. Good afternoon, everyone. I'm Nani Aravind, CFO of the company. Joining me is Mr. S. K. Ramaiah, Director of Business Development. I welcome all of you to our Q3 FY 2025 earnings call. Our performance in Q3 and for the nine months of this financial year stayed in line with the targets we set for the full year. Reported total income for Q3 financial year 2024 to 2025 came in at INR 1,347 crore, versus INR 1,115 crore in Q3 FY 2024, which is a 21% year-on-year increase. EBITDA stood at INR 160 crore against INR 141 crore, a growth of 13%, and PAT was INR 87 crore, up 39% compared with INR 62 crore in Q3 FY 2024. EBITDA margin fell from 12.66% in Q3 FY 2024 to 11.87% in Q3 FY 2025 because overhead costs rose. PAT margin rose from 5.6% to 6.5% on account of lower tax and higher other income. The revenue mix for Q3 FY 2025 breaks down as follows: Mechanical business contributed INR 277 crore against INR 230 crore in Q2 FY 2024, an increase of 20% year-on-year. Civil business, which includes railways and water distribution, contributed INR 522 crore against INR 596 crore in Q3 FY 2024, a decrease of 12%.

Nani Aravind

executive
#4

O&M revenue came in at INR 481 crore, compared with INR 260 crore in the same period a year earlier — that's growth of 85%. The electrical business posted INR 25 crore versus INR 21 crore, up 19%. Mining brought in INR 34 crore, against zero in Q3 20FY 2024 last year. Other income was INR 9 crore, compared with INR 7 crore in Q3 FY24. So in Q3 FY 2025, the split between domestic and international business was 95% and 5%, respectively. The power sector's contribution held at 65%. The non-power sector accounted for 35%. In the same way, total reported income for the nine months of FY 2025 came to INR 3,409 crore, versus INR 2,922 crore in the nine months of FY 2024 — a year-on-year rise of 17%. EBITDA was INR 417 crore against INR 360 crore, up 15%. PAT stood at INR 218 crore, compared with INR 164 crore in the nine months of FY 2024 — a year-on-year increase of 33%. So, on a nine-month-to-nine-month basis, the EBITDA margin fell from 12.4% in FY 2024 to 12.22% in the nine months of FY 2025, because overhead costs went up. The PAT margin rose from 5.7% to 6.4%, thanks to lower finance costs, lower tax expenses, and higher other income.

Nani Aravind

executive
#5

For the nine-month revenue mix: our Mechanical business brought in INR 608 crore, compared with INR 517 crore in the nine months of FY 2024 — that's an 18% year-on-year rise. Civil business, which includes railways and water distribution, came in at INR 1,459 crore versus INR 1,586 crore last year, an 8% year-on-year decline. O&M revenues were INR 1,213 crore, up against INR 755 crore in the same period a year earlier, which works out to 61% growth. The Electrical business posted INR 42 crore versus INR 47 crore, down 10% year-on-year. Mining business was INR 60 crore, compared with zero last year. Other income came to INR 28 crore, against INR 17 crore of other income in the prior financial year. Across the nine months of FY 2025, the split between domestic and international business stood at 94% and 6%, respectively. The power sector's contribution held at 62%. The non-power sector accounted for 38%. On the other financial parameters we're watching, net current days — excluding cash and cash equivalents — rose from 147 days in Q2 to 155 days in Q3, driven by delays in certification of the waterworks and delays in realization of receivables, which pushed up the company's current assets.

Nani Aravind

executive
#6

When it comes to stabilization of the MDO business from FY 2025 and FY 2026 onward, we can expect a meaningful enhancement in net working capital days. Gross debt and net debt stayed under control even with delays in water bill certification and in realization of receivables. As of 31st December 2024, gross debt is approximately INR 614 crore, while net debt is at INR 141 crore. The debt-to-EBITDA ratio as of 31st December is 0.39x. On order book status so far this financial year, the company has won orders valued at INR 4,242 crore through December. The order backlog as of 31st December is roughly INR 57,915 crore. Excluding two MDO, the unexecuted order book is INR 18,284 crore. We are actively chasing upcoming tenders, aiming for INR 3,000 crore in fresh orders by March 2025. In addition, we have been declared the L1 bidder for the 49 km Deoghar Bypass Highway project in Jharkhand, worth about INR 973 crore. This is under HAM, and we are awaiting issuance of the LOA from NHAI. Regarding the MDO businesses, we are making substantial progress on our two MDO projects. At Kotre Basantpur KBP Mining, we achieved a key milestone when the State Forest Department released 564 hectares of notified forest land in July.

Nani Aravind

executive
#7

After we obtained permission for tree felling in October, with felling getting underway on December 24, we expect OB removal to kick off next month, in March 25, and coal supply is slated to begin from April 25. Our other MDO — the Kalyaneshwari Tasra project — is picking up momentum. Equipment mobilization for the first phase of mining is done, and on October 24 we secured environmental clearance for a washery of 3.5 million tons per annum. OB removal and coal production have been running since January 24, and as of January 25 roughly INR 5.38 lakh tons of coal has been excavated and dispatched to SAIL. SAIL's offtake is presently below plan because washery capacity outside is limited, and we are working to resolve that constraint and ramp up production. At this point, I'd ask Mr. Ramaiah to give an update on developments on the business side.

Sudha Kodandaramaiah

executive
#8

Okay, thank you, Aravind, for that rundown on the headline figures. Appreciate your comments. Like I mentioned, Aravind is giving his update. Now, on the business front, the order backlog stood at INR 17,362 crore when the year began, and it has climbed to INR 18,284 crore — an upside of 5.3% — with total additions of INR 4,242 crore, which have accumulated across the three quarters, and here a few things stand out: the mechanical and ETC business rose by 7%, moving from INR 6,422 crore to INR 6,857 crore. Civil backlog went from INR 7,814 crore to INR 7,310 crore, a reduction of 6%. In O&M, there is a huge uptake when it comes to order booking. There is a positive indication, with backlog moving from INR 2,197 crore to INR 3,228, roughly 47% more. Electrical saw a modest decrease, from INR 930 crore to INR 887 crore, minus 4.6%. The overall order backlog has risen by 5.3%, from INR 17,362 crore to INR 18,284 crore. And the domestic business keeps driving the business substantially, more than 95%-96%. As for international operations, recently mainly on the O&M and the maintenance jobs, we are now trying to catch up.

Sudha Kodandaramaiah

executive
#9

There's also a balance portion. After that, the power sector keeps fueling a significant chunk of the business, thanks to the enormous spike in opportunities that have come available — in installation work, civil work, and the O&M business as well. And then MDO provided an update on where things stand overall regarding current execution and the steps being taken. Now, what we can say is that on the opportunity side, there's something positive when it comes to investments, especially in the power sector. What I can offer — that's an important element driving the business. What I can report on this is that BHEL has received sizable orders in both EPC and main plant works, along with the civil works. That amounts to nearly 24,000 MW over the last two years. In the EPC business, they've booked about INR 81,680 crore. And for main plant installation, main plant works in supply and installation, and then civil works too — civil works, that is the main plant boiler and turbine — INR 55,302 crore. And L&T is now entering as well. They're showing further interest in this. They've picked up two major jobs of 4,000 MW, and that's roughly INR 27,523 crore.

Sudha Kodandaramaiah

executive
#10

So in that sense, the total ordering placed over the past two years comes to roughly 28,900 MW. Within that, the biggest participants: Adani Group has picked up six projects, around INR 10,920 crore, and they've placed those orders. Haryana Power Generation Corporation Limited, 800 MW. DVC, INR 1,600 crore. And then, as recently reported, they've reached a decision on Raghunathpur for the boiler island portion of the work — that comes to something in the area of INR 6,500 crore. Then Mahagenco — this too is a recent development — Koradi. They've moved ahead with the addition that had been pending on the Koradi investments, 2x800 MW. That now amounts to 1,600 MW. And they've placed an order with BHEL worth roughly INR 8,000 crore for main plant works. Then NTPC has ordered a substantial amount from BHEL, about 11,580 MW. Altogether that adds up to 28,900 MW. Of that, the EPC share, as I walked you through, the BHEL EPC share works out to INR 81,680 crore. Now, the remaining ordering still has to happen in a number of places. Koradi — they need to order approximately 1,600 MW. Adani, since they're handling the packaging themselves across about 10,920 MW, are doing it in-house.

Sudha Kodandaramaiah

executive
#11

Naturally, that chance exists across plenty of civil works, mechanical works, coal handling, miscellaneous works, and so on. Then there's NTPC — the recent bulk tender awarded in Telangana, two packages to L&T and one to BHEL, roughly 6,400 MW. That opportunity could be substantial. Now, the latest on Raghunathpur: about INR 6,000 crore awarded — this was in yesterday's news — to BHEL for the boiler island. So they've divided the whole EPC into two EPCs. One covers the boiler island, the other the turbine island. On the boiler island, they've picked up this job. Then MPGCL, and there are new projects expected from the eight sets as well. So, taking the combined opportunities in the power sector together, I'd like to start there. Our main business interest is the installation business, civil and structural work for the main plant and wherever balance of plant exists. We've sized the total opportunity at about INR 27,250 crore. New projects allotted come to about 13,560 MW. Then there's a recent development in which KSK Mahanadi, the NCLT project that had gone for liquidation, has been awarded to JSW.

Sudha Kodandaramaiah

executive
#12

So basically, three units are already operating — three into 600 — and they're going to finish one additional unit. That comes to 600 MW. Then for two more units, they'll switch the configuration from 600 MW to 660 MW. Those are the main points. On other fronts, yes, where infrastructure is concerned, the government remains bullish about spending on railways, drinking water schemes, roads, and metro projects, and so on. So our focus is this: given the experience we've picked up in drinking water, we want to grow that business, since this drinking water scheme has now been extended through 2028. Total investment could go from roughly INR 3.6 lakh crore to almost INR 5 lakh crore. Much of it is expected in the southern states — Karnataka, Andhra Pradesh, Tamil Nadu, Kerala, and Maharashtra. We expect a lot of investment there. Now, drawing on the experience gained in UP, where we've carried out substantial work worth about INR 2,723 crore across about 1,969 villages, that work is in progress. A substantial portion has been finished. That's where the focus lies. As for O&M, what I can say is we're very bullish on it, because for one thing, plenty of new projects are getting commissioned.

Sudha Kodandaramaiah

executive
#13

Actually, the expectation for commissioning last year was roughly 6,000 MW. This year, that figure will rise to between 8,000 MW and 10,000 MW. And if that pace holds, since the government's plan involves ramping up installed power plant capacity from the current 218 GW to 218,000 MW, or nearly 3 lakh MW — which means 80,000 MW — a great deal of ordering is underway, and numerous players are arriving with investments. JSPL has two projects in the works, one located in Odisha and another in West Bengal. They have taken Sailong. As of yesterday, the news is that they have been awarded. That is JSW Energy. JSPL, the sister group, likewise intends to build two major plants, in Odisha and also in Chhattisgarh. Other players are anticipated as well. Beyond the utilities — sorry — many utilities are expected to invest, among them Coal India and various other public sector government undertakings; Uttarakhand is also planning 13,200 MW for whatever requirements exist. Then Coal India, as I mentioned, is planning investments on a joint venture basis in Odisha and Rajasthan. So we are genuinely bullish — sorry — on power sector investment over the next two to three years, with execution continuing for another four to five years.

Sudha Kodandaramaiah

executive
#14

Two big opportunities are going to come out of this. The first one is the complete installation business — that's going to be available, and it will be our major player. The second one is the follow-up O&M jobs, which will come up as part of the new commissioning that happens every year, roughly 8,000 MW, and that's a substantial business opportunity — and we've already seen it in the major orders we've taken recently across a lot of O&M jobs. For instance, the biggest O&M job we took last year is the drinking water one, at about INR 681 crore, as part of the commissioning operations that are going to take place. Then there's the Meenakshi Rehab and O&M job, INR 685 crore. And then INR 951 crore for Talwandi, 3x660 MW. Tuticorin, INR 392 crore for 2x600 MW. Singareni, 2 MW into 600 megawatts, INR 343 crore. And there was a job we took in Nigeria, where we carried out the commissioning of the Captive Power Plant, INR 139 crore. Then other jobs for the JP Group in Bara. Udupi Adani jobs, we've taken about INR 100 crore, and JSPL Angul as well, where we've taken a colony of INR 68 crore. All in all, that's how it adds up.

Sudha Kodandaramaiah

executive
#15

Now, there are certain things we need to take into account here. First off, election processes keep happening, state after state. That brings about a certain postponement of ordering, and also of the decision to call tenders and so on. There's another positive development that companies are attempting to venture into. That is, trying to see how far we can make the most of our experience when it comes to complete installation, O&M, then civil structural, then material handling jobs, and then main plant works, etc. Especially in trying to pursue Balance of Plant packages. Because NTPC has plans to do the Balance of Plant packages, and we are working with BHEL. Then other customers are also meeting. Also, Singareni — there is an opportunity coming up. Koradi, I spoke about 2 MW into 18 MW, that too is coming up. And then other opportunities may arise. So balanced opportunities can throw up at least around INR 12,000 to 15,000 crore, more than INR 15,000 crore of opportunities. Then we have to see how to take that call. And then the other things we are doing in the international market — the focus is more on the domestic market.

Sudha Kodandaramaiah

executive
#16

Turning to railways — yes, railways — especially the metro work. By metro work, I mean the maintenance shifts. Opportunities there amount to roughly INR 10,000 crore. We're already active in a number of these maintenance shops, as well as in railway workshops. That's what I wanted to say. Thank you very much.

Operator

operator
#17

Are we ready to move on to the Q&A portion?

Nani Aravind

executive
#18

Yes, ma'am.

Operator

operator
#19

All right. We're moving into the Q&A portion now. To ask a question, you can press star and one on your touchtone phone. Should you want to drop out of the queue, just press star and two. We do ask that participants use their handsets when posing a question. Ladies and gentlemen, we'll hold for a moment as the queue fills up. Thank you. Our first question comes from Dhruv Bhatia at AUM Fund Advisors. Please go ahead.

Pritesh Chheda

analyst
#20

Yes, hello there. Can you hear me okay?

Nani Aravind

executive
#21

Yes, sir.

Sudha Kodandaramaiah

executive
#22

Yes, sir. Thank you for the presentation. My question is this: sir, clearly the opportunity here is extremely large. What you're going after is already reflected in your order book. But when it comes to execution, what challenges stand in the way of growing considerably faster than the 20% sales growth you've achieved? After all, you have a massive order book. If you could share some guidance on execution, and also what we might expect next year and perhaps in FY 2027 — just focusing on FY 2026 and 2027, what is the internal target? What are the instances for growing much faster in terms of people, CapEx, materials, or working capital? Is there any constraint? And tied to that question: what margins do you expect as scale keeps rising? Where should margins stabilize? Both across the non-MDO business and in the MDO business as well. Thank you.

Nani Aravind

executive
#23

Yes, thank you, sir. That question is about the size of our operations. In the prior year, we reached an execution capability of nearly INR 1,500 crore each quarter. Because of the number of new lines of business we have launched, we may increase this. And with O&M too, on the operational side, we picked up additional orders over the year. So we could reach, we can deliver as much as INR 1,800 crore, or we might even get to INR 2,000 crore in revenue. So the target for next year, our guidance for 2026 and 2027, is that we had previously committed INR 7,500 crore. What we are aiming at for 2026 and 2027 is roughly INR 9,500. That includes the MDO operation together. But there has been a delay when it comes to the start of the MDO projects. In all likelihood, perhaps 10% or 15% here and there, so it will probably land between INR 7,000 crore and INR 7,500 crore. In between, we may reach that in 2026, and around INR 9,000 crore is what we can hit in 2027. As for profitability, the MDO business will deliver higher EBITDA margins once we get to peak rated capacity, which we expect from FY 2028 onwards.

Nani Aravind

executive
#24

Up until then, while we're in the development phase, we shouldn't really count on much of an EBITDA increase in overall margins. In the regular business, though, we're selective about taking the right orders, and we intend to carry out the highly profitable ones. We're also going to grow our O&M orders. So for O&M, the EBITDA margin perhaps year-on-year versus roughly 0.5%, over the next two to three years, somewhere in the 1%-1.5% range is what we can expect to grow, sir.

Sudha Kodandaramaiah

executive
#25

Yes, I'll add a few points on top of what Aravind said. Another thing we've built on is the capacities and the methodologies we can use to ramp up revenue and growth as well. That obviously comes from the capacity the organization has built up over the years. In fact, one basic thing is that the organizational capacity we've seen was around 30 to 32,000, including all the manpower — direct and indirect manpower, plus engineering supervisors and the contracting labor. So it has gone up to 37,000. That itself shows that for O&M in the last six months, we have ramped up the organization strength of both execution, operation maintenance, skilled people, engineers from a total of 12,000 to 13,000 to 17,500. Therefore, that is because of the large pool of piece rate workers and the skilled people we are having in our roles from our piece rate workers or contractors and other agencies and all. The second thing is that the organization has finally gathered a lot of expertise in terms of site execution that they want to convert into high-end value jobs. That is mainly in conversion in the civil works, for example, end-to-end solution, civil structural mechanical, and then O&M.

Sudha Kodandaramaiah

executive
#26

So we’re probably right up there with L&T or a few of the larger firms that don’t participate in this traditional kind of work. We may be the sole company able to deliver an end-to-end solution across the whole of construction as a construction partner. That capability is to be set up in terms of the physical capacities for mechanical works — roughly four to four and a half lakh tonnes at any one time. We’ve shown that. And then for concrete, two and a half to three lakh cu m — that’s substantial. And once we’ve hit those kinds of capacities, when the new orders are anticipated, and every plant for a 2x 800 MW or 600 MW facility carries a capacity of 150,000 to 400,000 tonnes. And running a couple of jobs in parallel isn’t a challenge for us — we’ve demonstrated that before. And so, beyond that, on the infrastructure side as well, considerable expertise has been built up over recent years. Sorry.

Pritesh Chheda

analyst
#27

Sir, regarding margins, should we expect them to remain steady at around 12% for at least the next two years?

Nani Aravind

executive
#28

Yes, I see what you mean. Look, one fundamental shift has taken place in the market. The reason we're somewhat bullish about the market is that the O&M share of execution work has risen considerably in the backlog, by 47%-50%. As everyone knows, O&M delivers better EBITDA margins and so on. Now, regarding the bullish trend in main plant power plant ordering, it's now evident that a great deal of order holding exists, and competition has become somewhat subdued at present owing to historical reasons. We are well positioned to handle that. Average value realization has increased roughly 20%-30% over the last couple of years. This applies to mechanical works, civil works, and the O&M side alike. That is the primary reason why Aravind may be working with these figures, and in the years ahead, we ought to be able to demonstrate improved margins.

Pritesh Chheda

analyst
#29

Aravind, what do you think the margins would be going forward, just as an indication, for the power business or the non-MDO business? And then for the MDO business over the next year, what would they be?

Nani Aravind

executive
#30

Sir, MDO, our mining operations are moving along well, and we anticipate that this segment will add roughly INR 2,000 crore to our top line by 2028. Once we hit full operational capacity, that growth will further strengthen our market position and help our overall revenue targets as well, and in fact we are aiming for annual growth of about 25%-30% in top line over the next four to five years, and the EBITDA margin, at present we are at 12.2% average that we are giving, so the O&M division, with margins exceeding 15%, is a key contributor to the major increase in the O&M, the EBITDA margins, so going forward, we are projecting a rise in EBITDA margin of 1%-1.5% over the next three to four years. As mining revenues also keep growing alongside and contribute to the major top line. So both combined, maybe 1.5% at peak rated capacity, which we expect within the next two to three years, sir.

Pritesh Chheda

analyst
#31

So that comes to 1.4%, right, Aravind?

Nani Aravind

executive
#32

Across 3 years, that adds 1.5% more. Both of those combined across a span of 2 to 3 years. Once we get to peak rated capacity, it won't occur right away. It'll come year by year, that's how it will build. And at the point we hit peak rated capacity, we'd anticipate a further 1.5% improvement in the EBITDA margin.

Sudha Kodandaramaiah

executive
#33

Also, one further point to mention: because a single organization handles multiple disciplines of construction work — specifically civil, structural, and mechanical — we can bring our overheads down by a fair amount. That should help produce improved margins. On top of that, both the O&M backlog and our capacities are rising, which will certainly contribute additional margin improvement going forward. Another trend worth noting is that customers now favor outsourcing O&M on a comprehensive basis. That delivers substantial added value, and not just among private-sector players. The private sector has begun doing this. The public sector has begun as well. A number of public-sector firms, including KPCL and GMDC, plus many others, are set to follow, since they prefer not to grow their own establishments, and this approach is the better way to proceed. Certain private customers are taking the O&M scope even further, to the point where we assume full responsibility, thanks to our capacities and the performance we have shown up to now.

Pritesh Chheda

analyst
#34

Thanks very much, sir. I appreciate you taking my question.

Operator

operator
#35

Thanks. Our next question comes from Pritesh at Lucky Securities. The line is yours — go ahead.

Pritesh Chheda

analyst
#36

Sir, is there any reason that, looking at your nine months figure and also at this quarter’s figure, O&M has climbed fairly substantially within your revenue mix? And the growth—a larger share of growth—is also coming from O&M revenue itself. So why is it that your operating margins are rising? Have you booked some civil orders that carry a lower margin? If you could tell us, what is the main reason?

Nani Aravind

executive
#37

Sir, we are carrying that out.

Pritesh Chheda

analyst
#38

Look, if you're telling me that O&M is what's going to push your margins higher, then that ought to be showing up already, shouldn't it?

Nani Aravind

executive
#39

Right, I’ll get to that, sir. Look, in the last year, delays in realizing receivables happened because of the general elections. On top of that, we received new O&M orders during last year. A lot of manpower has been added to the company’s rolls. As a result, conversion will be slow. At the outset, we’ll carry more overheads from starting the new projects. That’s one reason. And for the UP Water Division, we’re executing this project under Jal Jeevan Mission. Due to the general election, no fund allocation existed at that point. So there are delays in realizing these bills. And afterward, the Jal Jeevan Mission timelines expired in November. Again, there is no fund allocation for this project. So again, the department has not certified a lot of bills that are pending certification. So this led to more overheads, and we are drawing on working capital limits to keep running the projects further. So that caused the higher expenditure and increased overheads in the current year, sir. Next year, once these O&M operations stabilize, automatically the initial cost that we incurred gets normalized, and we may improve — perhaps from Q4 onward, there may be an increase in EBITDA margins compared with Q3.

Pritesh Chheda

analyst
#40

So what I'm hearing, if I've got your answer right, is that expenses tied to new projects have already landed in the P&L, while the revenue that goes with those same new projects has not yet shown up in your P&L.

Nani Aravind

executive
#41

No, no. The revenue that matches it does come in, but at the outset there will be startup costs — significant overheads we must take on in order to get these works going. We need to establish the site and set everything up. So that brings in more cost on the overhead side. We do realize the revenues, but this cost will be normalized over the following quarters. During the early period when actual operations begin, more cost will have to be incurred in mobilizing the resources.

Pritesh Chheda

analyst
#42

When it comes to O&M contracts, what margin do you typically bid at?

Nani Aravind

executive
#43

It really varies by case, sir. It hinges on how much work is involved and so on. So the range is 15%-20%; 21% shows up too. In certain cases we see 21%-22%. Typically, what we get is an average of 16%-17%.

Sudha Kodandaramaiah

executive
#44

Really, this breaks down into two categories. The first is long-term O&M contracts, which carry a steady margin. Then there are short-term shutdown jobs, repair jobs, maintenance jobs, and those can earn a better margin as well. That's because the customer is in a hurry to get the work done owing to the shutdowns and all. There's some opportunity cost involved there. That's how the overall O&M pie — both the AMC and the shutdown jobs — can deliver better margins. As I told you, in the main plant installation business, the civil work, since competition has eased a little bit and demand is also higher, the margin profile has gone up, and that realization will come through in coming years.

Pritesh Chheda

analyst
#45

Alright. Sir, finally, regarding orders — or rather, the order visibility that exists in the power sector. You all provided quite a substantial analysis. But if I were to shorten it and grasp it, of the BTG orders that various utility companies have awarded to BHEL, how much of that order has yet to be placed for main plant erection and for balance of plant? If you could.

Sudha Kodandaramaiah

executive
#46

I want to pull out the aggregate numbers I shared with you regarding what the BHEL order has accounted for over the past two years.

Pritesh Chheda

analyst
#47

So that's roughly 29,000 MW, correct, based on what you mentioned?

Sudha Kodandaramaiah

executive
#48

At 29,000 MW, that works out to almost INR 140,000 crores, roughly. Okay. And then L&T recently picked up INR 27,523 crores. So all of that is going to come through. Sure, some orders have been converting and so on, but the majority still need to be converted. And in this year and the next, most of the ordering will take place. That's the basis for the figure I gave on the total opportunity side — when it comes to the ETC civil package, for the remaining ordering to be done out of all this, somewhere around INR 27,000 to INR 30,000 crores will be involved. That's with the orders BHEL has already placed on BHEL and L&T. After that, utilities will have to do new ordering for another 13,560 MW — various utilities, if they are to place the order, because acting with urgency matters a great deal to ramp capacity up to 80,000 MW by 2030 to 2032, from the current 220,000 MW to 3,000,000 MW. That also means better margins will come, driven by the higher demand. As you know, when demand rises, margins can edge up a bit as well.

Pritesh Chheda

analyst
#49

Okay, so to put it simply, of everything that’s been ordered with BHEL and NTPC combined, the main plant erection valued at INR 27,000 crore and the balance of plant valued at INR 15,000 crore have still not been awarded to various contractors such as yourselves. And on top of that, there are going to be fresh tenders for BTG, or fresh tenders for power plants.

Sudha Kodandaramaiah

executive
#50

We had 13,560 MW.

Pritesh Chheda

analyst
#51

13,500 MW — that hasn't been fully ordered yet, right?

Nani Aravind

executive
#52

Yeah, yeah.

Pritesh Chheda

analyst
#53

Alright. So you hold a 50% market share — is there any shift happening there as far as BTG is concerned? And on that first participant's question, which you didn't answer: why do you have orders today in the non-MDO area? In non-MDO — but when it comes to executing on revenue, why is it slow?

Nani Aravind

executive
#54

See, on revenue execution, another factor was that drinking water had some problems with fund allocation. That’s where we came up short. Then there were some delays—local issues that come up on certain projects, due to engineering matters and clearances and so on. That also played a part. And when you’re running many projects in open areas, you can run into local problems with land acquisition, clearances, approaches, and those kinds of things are all going to be there. That’s how you get some of this. But even so, as I said, with INR 3,380 crore, and then our figure was to exceed INR 5,000 crores of revenue this year—that we are confident of doing.

Pritesh Chheda

analyst
#55

Alright, alright.

Operator

operator
#56

Does that answer your question, Mr. Pritesh?

Pritesh Chheda

analyst
#57

Yes, ma'am. I've finished. Thanks.

Operator

operator
#58

Thank you. Our following question comes from Anupam Gupta with IIFL Securities. You may proceed.

Anupam Gupta

analyst
#59

Yeah. Appreciate the chance to weigh in. You laid out the opportunity side fairly well, but we’ve observed BHEL securing orders a while ago. So at what point do you actually expect BHEL to put these out for tender, and for you to be in a position to book those ETC or BoP orders incrementally? Should we anticipate anything landing in the fourth quarter? Or when ought we to begin seeing tendering take place on BHEL’s side, considering that they themselves carry a sizable order book?

Sudha Kodandaramaiah

executive
#60

Take a couple of tenders, for instance — we're already involved in bidding on those. If nothing gets extended, I'd say it runs one to two months. In particular, the BoP Koradi tender is coming up, and that's the one where we're working alongside BHEL, and the Singareni tender is also coming, 1 MW into 800 MW. That one is due as well, but BHEL first has to secure the order, and that's in the final stage of submitting the offer and so forth, and after that, in all likelihood, it needs approval from the state government at cabinet level. Beyond that, other projects are also anticipated there. That's the reason I put out a figure of INR 15,000 crores in the BoP. And then, regarding the installation, civil and other opportunities that BHEL has secured, and L&T too has secured roughly INR 27,000 crore, what I stated is that this ought to materialize at the latest within another six months to nine months. Because counting Adani direct orders, BHEL main plant orders, and then balance of plant orders, whatever they hold there, plus L&T as well. Then all of these across various areas — main plant, balance of plant, coal handling, the civil works, structural works, piping works, etc.

Sudha Kodandaramaiah

executive
#61

That's the point where you know. But in the worst case, it stretches to 9 months to 10 months. Because if they don't award all these things by the end of another 8 months to 10 months, perhaps your projects get delayed. That's all I can say. Sorry.

Anupam Gupta

analyst
#62

Got it. So next year, when you say you'll deliver revenue of short INR 7,000 crore, what's the minimum ordering you're looking at for this year, at least?

Nani Aravind

executive
#63

If we look at the trends, naturally, this election process, that ongoing phenomenon, a lot of the projects sit within these segments and so on. And then maybe around INR 10,000 crores ought to be reasonable.

Anupam Gupta

analyst
#64

Is total ordering for this year 10,000 crores?

Nani Aravind

executive
#65

No, it's next year — next year.

Anupam Gupta

analyst
#66

So next year. All right. All right, got it. And regarding this INR 18,000 crore order, we should take it that the same thing you mentioned on the previous call applies — namely that the Adani orders that haven't begun won't be executed, correct? Roughly INR 4,000 crores. That's correct, as I'm sure?

Nani Aravind

executive
#67

Well, actually—actually.

Sudha Kodandaramaiah

executive
#68

No, Mir.

Nani Aravind

executive
#69

Yes, Mirzapur is something we're talking about. That's Mirzapur, and after that, Kodarma.

Sudha Kodandaramaiah

executive
#70

Kodarma, Mahan. Then Mahan phase three. Phase two is already being carried out. Phase three, after that, the new units at Mirzapur. And then Amarkantak, which we have acquired. They're also planning Kawai and so on. Naturally, at Kawai, two of the four units were moved to the projects in Madhya Pradesh. All of this is to be expected.

Anupam Gupta

analyst
#71

Is it your position that the INR 4,000 crores may still be carried out, or will they not be carried out?

Nani Aravind

executive
#72

I apologize, Anupam — could you say that question again?

Anupam Gupta

analyst
#73

I'm asking about the FGD orders from Adani worth INR 4,000 crores where work hadn't begun — will that go ahead or not? What clarity do we have on that too?

Sudha Kodandaramaiah

executive
#74

Right now, apart from that INR 900 crores sitting in Mundra that they've pulled out for the moment, we're working on this Udupi project. As for the other projects, yes, as things stand today, that's where it is. One more thing I can mention is that the Supreme Court recently made a pretty firm decision — they're not willing to compromise when it comes to pollution — and there could be some postponement in putting the new orders into effect, since there are other related matters around tariff adjustment and tariff compensation from the regulatory boards, plus discounts, and that's among the reasons all this implementation is getting delayed somewhat. Apart from that, in our view, I doubt they'll give much ground on the FGD. It's going to take a bit more time.

Anupam Gupta

analyst
#75

Got it. Moving to the MDO question. Clearly, revenue is fairly volatile, since sales — well, clarity on washing capacity just isn't there. Still, looking at the big picture, say for FY 2026, what revenue range would you anticipate from the mining MDO on the CIL projects and on the CCL projects, each on its own?

Nani Aravind

executive
#76

Probably somewhere in the INR 300 crore to INR 400 crore range. In Tasra, we're executing about 1 lakh tons each month. We might start executing from April. So roughly INR 200 crore to INR 220 crore is what Tasra should be able to execute over the next year. And with CCL as well, for the O&M portion for MDO, the initial capacity we have to execute is around INR 50 crore to INR 80 crore. So combined, we can probably execute between INR 300 crore and INR 400 crore in the MDO business.

Anupam Gupta

analyst
#77

And for that washery where you held the groundbreaking, what's the timeline for getting it executed?

Nani Aravind

executive
#78

We need to have the washery finished by September 26. All the permissions and everything we need are already in hand, so the designs for the major equipment are done as well, and we have ordered — we have identified and finalized the vendors, and we have ordered some of the equipment too, so the rest is still being negotiated and discussed. In all likelihood, the ordering will take place over the next two to three months.

Anupam Gupta

analyst
#79

Right, since September is the last one.

Nani Aravind

executive
#80

Yeah, yeah.

Anupam Gupta

analyst
#81

Alright. Got it. I have nothing further to add. Thanks.

Operator

operator
#82

Thanks. Our next question comes from Deepak Poddar at Sapphire Capital. You have the floor.

Deepak Poddar

analyst
#83

Hello there. Am I coming through clearly for you, sir?

Sudha Kodandaramaiah

executive
#84

Yes, sir.

Deepak Poddar

analyst
#85

Yeah. Thanks a lot for the chance to ask. So first off, I just wanted to get a handle on the debt side — I mean, when it comes to debt, what does the outlook look like for us?

Nani Aravind

executive
#86

Sir, at present our fund exposure stands at roughly INR 700 crore, or INR 714 crore without utilization. And as we go forward and execute this CapEx requirement — I mean the washery requirement within the power order book — there may be a need for capacity addition of about INR 700 crore to INR 750 crore over the next two years. So approximately by 2028, we'll have roughly INR 1,200 crore of addition happening insofar as CapEx is concerned. Debt loads will be added on top of that. And on the working capital side, perhaps another INR 100 crore to INR 150 crore will be added. Because we are talking about the BOP ETC projects. So roughly, by 2028, we may touch somewhere around INR 1,800 crore to INR 2,000 crore.

Deepak Poddar

analyst
#87

So by FY 2028, the debt would be INR 2,000 crores. Is that the figure we're looking at?

Nani Aravind

executive
#88

Correct.

Sudha Kodandaramaiah

executive
#89

Which one is it at the moment?

Nani Aravind

executive
#90

No, no — that’s not debt, sorry. That figure is a total for CapEx. Debt is going to be only about 500. We’re increasing the CapEx. 500 plus another, so roughly 800 gets added onto that. 800 plus another 700 — by 28, the debt number will be approximately 1,500 to 1,600.

Deepak Poddar

analyst
#91

So by FY 2028, we're talking about INR 1,500 crore to INR 1,600 crore of debt, correct? And at present that figure stands at INR 600 crores, right? On a gross debt basis?

Nani Aravind

executive
#92

Yeah, INR 714 crore.

Deepak Poddar

analyst
#93

Currently, debt stands at INR 740 crore. By FY 2028, that figure should reach roughly INR 1,500 crore to INR 1,600 crore. Regarding this increase — I mean, will it be something like INR 200 crore to INR 300 crore each year? In other words, will the additions come in a phased manner, or will there be?

Nani Aravind

executive
#94

Capital expenditure needs come to somewhere in the vicinity of INR 700 crore to INR 750 crores. Of that INR 240 crore, equity is available — the QIP money we brought in. As a result, INR 450 crore to INR 500 crore will be added over the coming two years. Add to that the routine CapEx tied to new orders we've won, so roughly INR 100 crores per year of ordinary CapEx gets added on top.

Deepak Poddar

analyst
#95

All right, all right. So INR 750 crores is the CapEx for the next two years. Out of that, INR 400 crore to INR 500 crores of debt will be added over the next two years, correct?

Nani Aravind

executive
#96

Yeah, yeah.

Deepak Poddar

analyst
#97

Is that the correct way to understand it?

Nani Aravind

executive
#98

Yeah, yeah.

Deepak Poddar

analyst
#99

All right, understood. And on execution — for this year, FY 2026, we're looking at revenue somewhere in the INR 7,000 crore to INR 7,500 crores range, correct? FY 2026.

Nani Aravind

executive
#100

Correct.

Deepak Poddar

analyst
#101

Of that total, what portion is coming from MDO within this year, FY 2026?

Nani Aravind

executive
#102

For FY 2026, our projection is somewhere in the range of 300 to 400, depending on how order intake from sales gains momentum, sir.

Deepak Poddar

analyst
#103

You said 300 to 400, and you mentioned that by FY 2028, optimally MDO can do INR 2,000 crores of revenue. So at optimal levels, what kind of EBITDA margin should one look at in MDO? Is it close to 20%?

Nani Aravind

executive
#104

If you combine the two, we can take an average of 20%-22%, sir. Tasra gives us better margins, while KBP has a lower margin. We can take a weighted average of roughly 20%-22%.

Deepak Poddar

analyst
#105

Earlier this year, I believe our aim was roughly INR 5,500 crores of execution. So now, considering the execution we've completed over nine months, what would the revised target be for this year, FY 2025?

Nani Aravind

executive
#106

We might land somewhere around INR 5,000 crore to INR 5,200 crore this year, sir, roughly speaking, and as of nine months, we've executed about INR 3,400 crores.

Deepak Poddar

analyst
#107

That's right.

Nani Aravind

executive
#108

We're running INR 1,800 crore short. The certifications for the water utility are still pending. There's work worth roughly INR 200 crore in the WIP where certification has taken place. We can execute another INR 1,600 crore to INR 1,700 crore in Q3.

Sudha Kodandaramaiah

executive
#109

Regarding Q4.

Nani Aravind

executive
#110

Regarding Q4, both government and private sector clients will probably speed up certifications and payments. That means we should be able to hit at least 25% growth for the current year. So we're targeting INR 5,200 crores.

Deepak Poddar

analyst
#111

What was that amount? I didn't catch the final item.

Nani Aravind

executive
#112

About INR 5,200 crore, more or less.

Deepak Poddar

analyst
#113

With INR 5,200 crore, so for Q4 we're looking at execution of INR 1,700 crores plus, right?

Nani Aravind

executive
#114

Yes. Since the water division still has some certification pending, that 150 is already in place. It was meant to occur in Q3, but certification has slipped because of the Jal Jeevan Mission timeline expiring. So the latest budget has extended those timelines as well.

Sudha Kodandaramaiah

executive
#115

That's right.

Nani Aravind

executive
#116

The certification is going to be handled by them. The funds will be released by them in April.

Deepak Poddar

analyst
#117

Got it. And on the order book accretion side, we're expecting roughly INR 10,000 crores of order inflow next year, FY 2026, correct?

Nani Aravind

executive
#118

Understood.

Deepak Poddar

analyst
#119

Right, right, right. I believe that clears things up. That's all from me, then. Wishing you the best of luck. Many thanks.

Nani Aravind

executive
#120

Thanks.

Operator

operator
#121

Thanks. Our next question comes from Manthan at Nexus Equity. Your line is open.

Manthan Jhaveri

analyst
#122

Hello?

Nani Aravind

executive
#123

Hello there.

Manthan Jhaveri

analyst
#124

Can you hear me?

Nani Aravind

executive
#125

Yes, sir. So I think previously our target for order inflows this fiscal year was roughly INR 10,000 crore to INR 12,000 crores, and now, up to December, I think we've received only INR 40 crore to INR 100 crores of orders, and as you mentioned, we might get another INR 3,000 crores of orders over the remaining three months, so we were in L1 on INR 973 crores of road projects, so we're waiting for the LOA, so that will also get added to that.

Manthan Jhaveri

analyst
#126

Okay, so what amount of order inflows are we expecting in total?

Nani Aravind

executive
#127

Somewhere in the range of INR 7,000 crore to INR 8,000 crore, sir.

Manthan Jhaveri

analyst
#128

Since earlier our target was in the range of INR 10,000 crore to INR 12,000 crore, is it that order bidding has been delayed, or will some orders roll over into the next fiscal year?

Sudha Kodandaramaiah

executive
#129

So actually, what occurred was that with the election process — and then also some tenders ended up getting postponed. The big BoP tenders were pushed back by five to six months. After that, Koradi — that earlier project ought to have begun quite a while ago, six months back, eight months back. Typically, they've kicked off some of the tendering activity. And the main plant has already been awarded. Then there were certain orders themselves placed with BHEL and L&T, and the utilities caused some delays there. That's a major factor behind it.

Manthan Jhaveri

analyst
#130

Alright. But sir, in that case, for next year we're aiming at roughly INR 10,000 crore of order inflows. Now, if I take it that INR 4,000 crore that was actually going to come in FY 2025 gets received in FY 2026, then next year the incremental order will only be INR 6,000 crore. So despite you having, I mean, despite having such a strong order book, the pace of order inflows is slowing down. You mentioned that L&T also has a strong order book, and Adani as well. So why can't we aim for much more aggressive order inflows? Because our order inflows have been flat for the last nine to ten months.

Sudha Kodandaramaiah

executive
#131

Yes, I see your point. Really, though, the key thing to grasp is that a lag can occur between when choices get made and when they take effect. Beyond that, at a few sites there are technical problems to work through. On top of that, we ran into layout problems. And then there are the standard approvals to secure. Those are the items we typically pushed back. So we've performed strongly on some large orders, as in prior years. And naturally, starting this year, among the large orders we're counting on is BoP, and there's a delay there. That's precisely where our earlier optimism had us at INR 10,000 crore-INR 12,000 crore.

Manthan Jhaveri

analyst
#132

So for this year, as you mentioned — and the earlier participant brought this up too — we feel fairly confident about hitting a top line of INR 5,000 crores to INR 5,200 crores. Is that right, that we're staying with that?

Sudha Kodandaramaiah

executive
#133

Since we showed in the last Q4 that we can execute as well. As I mentioned, in Q4 the build and the certification process are going to be better on the customer side too, because he wants to free up his funds and then build it as well. Payment too.

Nani Aravind

executive
#134

Look, the UP government certifies bills only at the point when money is present in the system, so they're holding back certification, and that's why we're treating it as WIP. Once funds get allotted, they certify. And we check based on that certification, so in that way we're confident of securing the certification by March, and we'll be able to hit our target.

Sudha Kodandaramaiah

executive
#135

Go on, I’m listening.

Manthan Jhaveri

analyst
#136

So, what you're saying is that the INR 200 crores is just INR 200 crores of revenue booking, and it's simply delayed due to certification. The moment you get the certificate, that INR 200 crores of order revenues will come in right away. Is that right?

Nani Aravind

executive
#137

Yes, sir.

Manthan Jhaveri

analyst
#138

All right. And sir, given that we may need to borrow within the next 1 or 2 years, right now we're targeting a PAT margin of about 6%. So should we expect that PAT margin to be 6% — net net 5.5%-6% — or will it come down?

Nani Aravind

executive
#139

The finances are essentially in good shape, and that is the reason we can operate at a PAT margin level of 6.5%-6.8%. Now, should the EBITDA margin get better, then this margin will rise as well, automatically. So the principal bottleneck is occurring right at this EBITDA margin level, and nothing else. Therefore, whenever we receive the, I mean, the 2 profitable orders added into the portfolio, EBITDA will rise on its own, and your PAT margins will rise too, sir.

Manthan Jhaveri

analyst
#140

Alright.

Nani Aravind

executive
#141

Even at this point, we remain comfortably inside the number we planned, and relative to earlier figures, our finance costs are lower. That said, looking ahead, since the bulk of what we're rolling out consists of new hybrid models, no working capital is needed for those. So it's only on EPC projects — if I bid for those, I'd need additional working capital, and my finance cost would rise. And should I put more CapEx onto the balance sheet, that too means adding further interest costs. Up to now, we're handling it well and staying inside that. So once more, what lies ahead hinges on how we grow and on BoP works. It's likely we'll have to bear higher finance costs, which means PAT levels will shift.

Manthan Jhaveri

analyst
#142

Alright. MDO revenues came in at INR 34 crores for this quarter, and that marked a pretty big rise versus the prior quarter. So should we be looking for that kind of QoQ increase in MDO revenues, or is it once again the case that within MDO revenues, H2 carries more weight than H1? What's the pattern when it comes to MDO orders?

Nani Aravind

executive
#143

On the Tasra project — the platform there is genuinely ready and available. Mining got underway because an earlier MDO promoter had already carried out the excavation. That meant we could step in right away, and we're billing directly. At this point there's no appointed date; we haven't received one yet. SAIL provides material whenever quantities are available, which hinges on washery capacity elsewhere. So starting in April, we may be given the appointed date, and from then on it becomes a binding agreement with SAIL for lifting the material under the contractual terms. On that basis, we expect to be able to raise a bill to SAIL each month in line with the agreement conditions.

Manthan Jhaveri

analyst
#144

Alright. Within that MDO order book mix of INR 17,000 crore to INR 18,000 crore, what portion is slow moving? Or is all of it executable over the coming two to three years? The current INR 18,000 crore order book mix for MDO?

Nani Aravind

executive
#145

Aside from roughly INR 4,600 crores of FGD, which is FGD orders and non-moving, the remaining order book currently stands at only about INR 14,000 crores.

Manthan Jhaveri

analyst
#146

So the INR 18,000 crores figure takes in the FGD slow-moving order of 4,200 from Adani, right?

Nani Aravind

executive
#147

Yes. Yes, yes.

Manthan Jhaveri

analyst
#148

All right, so that comes to INR 14,000 crore that you intend to execute over the coming one, two, or three years — meaning, based on the current order? On average, you can figure two to one and a half years.

Sudha Kodandaramaiah

executive
#149

40%.

Nani Aravind

executive
#150

The conversion rate is 40%.

Manthan Jhaveri

analyst
#151

Yeah. All right, all right. That's fair. I've got nothing more to add. Thank you.

Operator

operator
#152

Thanks. Our following question comes from Anush Mokashi at Yadnya Academy. The line is yours — please go ahead.

Anush Mokashi

analyst
#153

Hello?

Sudha Kodandaramaiah

executive
#154

Hello.

Anush Mokashi

analyst
#155

Can you hear me, sir?

Sudha Kodandaramaiah

executive
#156

Yes, sir. Yes.

Pritesh Chheda

analyst
#157

Yes, thanks for taking my question. So it relates to the recent news on the nuclear energy mission. I just wanted to get a sense of what benefits Power Mech sees coming out of this. And really, does Power Mech have the capability to build these small modular reactors? And if it doesn't, would you think about moving into that segment?

Sudha Kodandaramaiah

executive
#158

Yes, that's a government initiative. Jindal has already launched a joint venture. I believe they're about to get going. Then there's NTPC, and after that Nuclear Power Corporation — they've set up a joint venture too. The concept is to install 200 or 250 MW units. Naturally, all of that still needs to be developed. Naturally, we recently secured a job worth INR 550 crore in Kawai covering the main plant works and so on. We're evaluating it, though it will be a challenge, since the technology is there, the sourcing is there, and many other aspects come into play. Still, one positive is that these plants will operate for a long stretch — 30 years, 40 years. It makes sense. And that's just something we're considering. We haven't made any decisions as of now.

Anush Mokashi

analyst
#159

All right, and then just one follow-up: as you mentioned, that INR 200 crore of revenue recognition has slipped into Q4. So has the cost slipped as well? In other words, is the cost also being booked in Q4? Or is it currently booked only in Q3?

Nani Aravind

executive
#160

No. Once we recognize the WIP, sir, it flows straight into revenue. So this project has some back-to-back contractors. In any place where back-to-back contractors exist, the cost hasn't been booked, and the revenue hasn't come through either. Wherever it's direct execution, we've already recognized the WIP. As for the remaining portion — wherever back-to-back contractors are involved — we haven't recognized either the costs or the revenue there, since we haven't received the bills from the clients' subcontractors either.

Anush Mokashi

analyst
#161

All right. Thanks. Thanks, sir. That's all I had. Thanks.

Operator

operator
#162

Thanks. Our following question comes from Kamlesh Jain at Lotus Asset Managers. Your line is open.

Kamlesh Jain

analyst
#163

Yeah. Thanks for the chance to ask. So just one thing — I wanted to get your view on the fact that Ambuja recently came out with tenders to upgrade their cement plants.

Operator

operator
#164

My apologies for cutting in, Mr. Jain. Your audio isn’t coming through clearly for us, sir. Would you mind turning up the volume?

Pritesh Chheda

analyst
#165

Okay, okay. Can you hear me now?

Operator

operator
#166

Sure, go right ahead.

Kamlesh Jain

analyst
#167

Yeah, yeah. So sir, I just wanted to get your thoughts on the development that Ambuja has come out with — the tenders for some of their cement plants to operate on an MDO basis, or on a contract basis, or through outsourcing. So, since we are looking to diversify into other sectors, would we be pursuing that particular opportunity going forward?

Nani Aravind

executive
#168

So, when you mention Ambuja, are you talking about capital consumption power plants?

Kamlesh Jain

analyst
#169

No, I mean the whole of the cement plants.

Nani Aravind

executive
#170

Okay. So at this point, we're working on Dalmia Cement in Bihar, Andhra, and Tamil Nadu as well. They're actually making plans to set up captive power plants, solar power plants, and wind power plants. So their intention is to come in as the 26% partner, and we would install the solar and wind capacity in megawatts that's needed. And we would have to supply under a 25-year PPA — they'll enter into it with Dalmia. So negotiations are underway. We've submitted our quotes to them. So we're waiting for them to confirm on that, sir. So there's a new solar business that we're actually looking at starting with. For moving into the green hydrogen business down the road, we want to have this kind of experience requirement in place for solar power. So under that plan, we're in touch with them, sir.

Kamlesh Jain

analyst
#171

What I meant was running the whole cement plant. So Adani has issued tenders for operating all of their cement plants — a few of their cement plants, that is, on a pilot basis. So that's how it will be.

Nani Aravind

executive
#172

And that's how the oil refineries and the power plant get wrapped up. Yet should that type of work present itself, there's probably a chance for us to explore it too, and we'll be looking into that as well.

Sudha Kodandaramaiah

executive
#173

Refineries represent one possibility. BPCL has pledged an investment of INR 60,000 crore in Bina. HPCL, meanwhile, is carrying out an expansion there. We already possess some experience in this area. We have handled certain jobs in Ruwais as well as other locations. So this is a viable option, since we would need to apply that same expertise and execute the work. The only difference is that quality and safety concerns would largely be the focus.

Kamlesh Jain

analyst
#174

But is that potential there, or are we aiming to run the whole cement plant — the grinding, the clinker making capacity, all of it?

Sudha Kodandaramaiah

executive
#175

We have the capability to run a very sophisticated power plant, including control room operations. For instance, we've begun work at some O&M plants with NMDC, and then JSPL for the steel plant and so on. That's an option you could look into if we're able to secure a reasonable return from it. Every cement plant will have a captive power plant. Then there's kiln operation along with the other ancillaries and all of that. The skills needed for those things, along with the operating characteristics, production characteristics, and the various parameters in the cement plant — we have to become accustomed to those. That can be a matter of making the right call and then proceeding with it. As of today, we're reasonably well satisfied with the MDO initiatives we've undertaken, and more opportunities will keep coming up owing to annual capacity additions of 8,000 MW-10,000 MW over the next four to five years.

Kamlesh Jain

analyst
#176

Thanks, thanks. And finally, sir, I’m not sure whether you’ve already discussed this. But regarding the Tasra mines, we’ve observed operations from SAIL that are very suboptimal. So how confident should we be about executing those orders going forward?

Nani Aravind

executive
#177

As of right now, sir, no appointed date has come through for the Tasra project. So at this moment there isn't a binding obligation on SAIL's side either to lift the material. Starting April, we'll be getting the appointed date. Once that happens, the contract clauses will take effect. Then it becomes binding on them to lift the material regardless of whether capacity exists there or not outside. So our rights are protected by the contract. So there's no issue when it comes to hitting our targets for the next year.

Kamlesh Jain

analyst
#178

Much appreciated, sir.

Operator

operator
#179

Thank you. Ladies and gentlemen, that was the final question for today. At this point, I'd like to pass the conference over to management for some closing remarks.

Sudha Kodandaramaiah

executive
#180

Yes. Appreciate everyone joining. I mean, the questions have drawn out — it's been quite an engaging conversation. In my view, the power sector looks very bullish. As for infrastructure, we're well established at this point — drinking water, railways, roads, and other related projects, plus metro maintenance shops and so on. And naturally, business ought to pick up. BHEL is ramping up orders, and L&T is also stepping forward. There are plenty of new areas that will certainly emerge. And we stay aggressive in how we approach both marketing and execution, surpassing INR 5,000 crores this year for sure. Then next year, roughly INR 10,000 crores, as we mentioned — that reflects looking at some of those O&M opportunities, which are major items. And then the non-power sector jobs we're establishing in railways, roads, plus material handling, coal handling, and mine site development work, etc. So let's view it that way. And regarding the company's capacity to boost execution capability, that's always in place. And we're able to do it. Thank you.

Operator

operator
#181

Appreciate it, management team members. That wraps up this call on behalf of Nirmal Bang Institutional Equities. Thanks for being with us, and you're free to hang up your lines at this point.

Nani Aravind

executive
#182

I appreciate that.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Power Mech Projects Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Power Mech Projects Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Power Mech Projects Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.