PSP Projects Limited (PSPPROJECT.BO) Earnings Call Transcript & Summary
July 19, 2021
Earnings Call Speaker Segments
Operator
operatorLadies and gentlemen, good day, and welcome to PSP Projects Q1 FY '22 Results Conference Call hosted by AMBIT Capital. [Operator Instructions] Please note that this conference is being recorded. I now hand the conference over to Mr. Varun Ginodia from AMBIT Capital. Thank you, and over to you, sir.
Varun Ginodia
analystThank you so much, Ayesha. And good afternoon, everyone, and I hope everyone is keeping in good health in these unprecedented times. Today, we are pleased to host the management of PSP Projects for 1Q FY '22 earnings call. From the management, we have Mr. P. S. Patel, Chairman, Managing Director and CEO; and Mrs. Hetal Patel, Chief Financial Officer. In terms of the format of the call, the management will give the brief remarks on the results release, and then we will open the floor to Q&A. Sir, over to you.
Prahaladbhai Patel
executiveThank you. Good evening, ladies and gentlemen. This is P. S. Patel, Chairman, Managing Director and CEO of PSP Projects Limited. Along with me is Mrs. Hetal Patel, our CFO, welcomes you all to this earnings conference call, which is focusing on our company's performance in quarter 1 FY 2022. First of all, I hope you all are safe at your place and taking care of yourself and your family. As we are meeting on this call, within a very short gap of almost 1 month from our last call of quarter 4 FY '21 results, operationally, I think there is not much to update to share as I had covered all the areas in the previous call. However, I'm covering a few of the updates. Revenue. Company has booked the revenue from operations of INR 317.35 crores in quarter 1 FY '22, which is about 197% higher compared to year-on-year. As you know that the first 2 quarters of previous year, they're badly affected due to [ mining of oil ], lockdowns, worker migration, etc. This is -- hello? Hello?
Operator
operatorSir, you can go ahead. We are able to hear you.
Prahaladbhai Patel
executiveThis is by far the biggest quarter 1 revenue we have achieved, but we believe that this could have been higher. But once again, the operations were affected due to the second wave of COVID. This is by far the highest quarter 1 revenue we have achieved, but we believe that this could have been higher. But once again, the operations were affected due to the second wave of COVID. Most of the laborers, who generally go to their village during Holi, didn't return back till end of May. Also, there were partial lockdowns, night working restrictions, reduced staff working, etc. which has interrupted the operations in quarter 1. The situation now is really very well, and I would say all the sites are working with 100% labor strength. We are very optimistic that the upcoming quarter should be good without obstacle of third wave or something else disrupt the operations. Order book. At the end of quarter 1 FY 2022, company stands with the order book of INR 3,852.21 crore. As informed in the last call, all the projects are fully mobilized and that means work is going on in full swing, except 2 projects. And third is UP Medical College and Hospital. As informed in the previous call, the designs are getting approved by -- very aggressively and the physical process of -- at hindsight have started from first week of July. Remaining 2 sites are fully mobilized in terms of plant and machinery and manpower. Just waiting for the design clearance, which should be completed by end of this month. So these were the key highlights from my side. For detailed financial disclosures, I will request our CFO, Mrs. Hetal Patel, to take it forward. Thank you, everyone, to be a part of this call.
Hetal Patel
executiveThank you, sir. Good evening, everyone, and welcome on the call. Let me first give you highlights on stand-alone financial results for the quarter ended on 30th June '21. Company has booked revenue of INR 317.35 crores for the quarter ended on 30th June '21. The revenue generated from Surat project was the...
Prahaladbhai Patel
executive[Foreign Language]
Hetal Patel
executiveI think -- are we audible?
Operator
operatorYes, ma'am, we can hear you.
Hetal Patel
executiveOkay. So revenues generated from Surat project was INR 92 crores during this quarter. Cumulative revenue till 30th June '21 is INR 1,486 crores booked for Surat project. EBITDA for the quarter is INR 39 crores, which is 12.42% of the revenue from operations. Net profit for the quarter is -- arrived at INR 25.11 crores, which is 7.82% of the total revenue. There is no change in revenue for the year ended on consolidated basis. Net profit as per consolidated financials is INR 24.91 crores, which is 7.76% of the total revenue. Total expenditure incurred for the precast unit is INR 85 crores till 30th June 2021. Working capital days on the stand-alone basis are as follows: debtor days are 82, creditor days are 52 and inventory days are 25. During the quarter, company has increased credit facility limit from INR 610 crores to INR 1,047 crores. Out of total credit facility of INR 1,047 crores, utilized limit is INR 551 crores, of which INR 120 crores are fund-based utilization and INR 431 crores is nonfund-based utilization. Work on hand as on 31st March '21 -- 30th June '21 is INR 3,852 crores, which comprises of INR 289 crores for Surat Diamond Bourse project. As on 30th June '21, the company has total fixed deposit of INR 220 crores, out of which [ 3 deposits ] of: INR 73 crores; equities worth INR 140 crores are under lien with bank for credit facilities; and equities given to clients as security deposits amounts to INR 7 crores. The increase in fixed deposit is attributable to the receipt of mobilization during the first quarter from a couple of projects. With this, I end up giving key highlights on the company's financial performance. And now we are open for the question-and-answer session. So request the moderator to take it forward. Thank you.
Operator
operator[Operator Instructions] The first question is from the line of Chintan Sheth from Sameeksha Capital.
Chintan Sheth
analystAm I audible?
Operator
operatorYes, sir, we can hear you.
Prahaladbhai Patel
executiveYes. A little bit louder, please.
Chintan Sheth
analystSure. Sure, Prahaladbhai. Good set of numbers, sir, managing margins as well, that is commendable. Couple of updates, sir. Bhiwandi, what is the update there? Then UP already you mentioned. And anything you want to talk about the bid pipeline and the outlook, if you can, for this year?
Prahaladbhai Patel
executiveSee, regarding bid pipeline, it is again ranging in the range of about INR 3,000 crores as a whole. And about Bhiwandi, the matter is in the court, and they are going to file their answer. So we are waiting for the matter to go on hearing.
Chintan Sheth
analystSo when is the next hearing, now?
Prahaladbhai Patel
executiveYes.
Hetal Patel
executiveNext hearing.
Prahaladbhai Patel
executiveNext hearing, I think, 26th of July.
Chintan Sheth
analyst26th of July. Okay. And in the bid pipeline, anything -- any large project, [ Google ] is still there?
Prahaladbhai Patel
executiveYes. Yes. Still the bid book is in the range of INR 3,000 crore, and most of the projects are what we discussed and discussed in the last con call, that's on the same line. Yes.
Operator
operatorThe next question is from the line of [ Sitaraman ] from Spark Capital.
Unknown Analyst
analystCan you give me the receivables, including retention and unbilled revenue for the quarter ending?
Hetal Patel
executiveSorry, can you please repeat the question because it was not audible?
Unknown Analyst
analystOkay. Can you give the receivables, including retention and unbilled revenue at the end of quarter 1?
Hetal Patel
executiveSee, receivables is -- just a minute. Retention is around INR 99 crores in total, and receivable is INR 281 crores.
Unknown Analyst
analystOkay. And the unbilled revenue part?
Hetal Patel
executiveUnbilled revenue is also in the range -- means, in line with last year only. There is no significant change.
Unknown Analyst
analystWhat is -- where does it currently stand at the end of first quarter?
Hetal Patel
executiveSorry?
Unknown Analyst
analystAt the end of first quarter, where does it stand, the unbilled revenue part?
Hetal Patel
executiveUnbilled revenue?
Unknown Analyst
analystYes. Yes, ma'am.
Hetal Patel
executiveJust a minute.
Operator
operator[Operator Instructions] The next question is from the line of Kaushal Shah from Dhanki Securities.
Kaushal Shah
analystYes. Sir, just wanted a clarification on the UP projects. You were saying the design, et cetera, is under approval. So when do we actually start work on the ground? And will we start billing from maybe the October quarter? Or it could actually start even in the current quarter, the second quarter?
Prahaladbhai Patel
executiveNo, I said 5 projects, we have already started work on ground. And on 2 projects, the design is in the process of approval. So 5 projects, we have already started. And yes, we will book the revenue in this quarter only -- next quarter only.
Operator
operator[Operator Instructions] The next question is from the line Aditya Choksi from PSP Projects.
Aditya Choksi
attendeeYes. First of all, sir, congratulations for a decent set of numbers. Sir, I have 2 questions. One is what -- is there any execution issues right now going on in any project? And my second question would be what would be the revenue projection and EBITDA for the current financial year? As now the scenario is open, so if you can just throw some light on that?
Prahaladbhai Patel
executiveSee, as far as revenue is concerned, it will be in the line with the same every year what we say the growth of about 25% to 30%, and it's been the same thing what we have done last year. So we can expect 25% to 30% growth from revenue. And related to any other project, which is as of -- first issue, that was the Bhiwandi project and one second is this Pandharpur project. Pandharpur project, we have to slow down the project because there is no payment. And Bhiwandi, you are aware that it is in the [ first ].
Aditya Choksi
attendeeOkay. So sir, 25% to 30% revenue growth before the previous year from pandemic, right, sir?
Prahaladbhai Patel
executiveYes.
Operator
operator[Operator Instructions] The next question is from the line of Shravan Shah from Dolat Capital Markets.
Shravan Shah
analystSir, just a clarification. The previous guy -- you said 25% to 30% revenue growth on FY '21 numbers or FY '20 numbers?
Prahaladbhai Patel
executiveFY '21.
Shravan Shah
analyst'21. So that comes to close to INR 1,600 crores, even if I take 30% because last time we have talked about around INR 1,700 crores to INR 1,800 crores revenue. So it is lower, so are we slightly lowering what we said last month in the call?
Prahaladbhai Patel
executiveWe are not lowering, but to be on the conservative side, we are saying it should be in the range of 25% to 30%. And every year, whatever figures we say, it is almost -- every time, we try to do better than what we expect.
Shravan Shah
analystOkay. Sir, here, just to reiterate in terms of the SDB, now INR 290-odd crores is remaining. So this quarter, that is July to September, can we see -- because this quarter, we have seen only INR 92 crores, so now can we see INR 150 crores plus? And by third quarter, it would be 0 in terms of the order book?
Prahaladbhai Patel
executiveSee, as far as the overall revenues coming from SDB is concerned, I would say it will be somewhere in the range of 60% to 70% will be closed in this quarter only. But maybe about 30% revenue may be left after this quarter because there are few issues related to position, there are few issues related to commissioning and there are few percentage hold due to commissioning. So [Foreign Language], you can consider 60% to 70% revenue -- left up revenue should be booked in the next quarter, and rest of the revenue, they may go in the last quarter.
Shravan Shah
analystAnd for UP project, now as we have started the work, so if you can broadly -- roughly idea -- because INR 1,491 crore total order book, so per month, it's INR 83 crore. So this quarter, can we see a INR 150-odd crore kind of a revenue because it is just a quarter? And the third quarter, can we see a normal INR 80 crore per month, so that is around INR 250 crore a quarter?
Prahaladbhai Patel
executiveAs far as the monsoon is going on and there is heavy rains in UP as of now, and at the same time, when we are in the [ print ], volumes will not be generated in this first quarter only. So it can -- we can see a reasonable revenue in the third quarter.
Shravan Shah
analystOkay. So this quarter, it would be a much lower number, maybe a INR 50-odd crore? Or can it be INR 100 crore?
Prahaladbhai Patel
executiveRight now, we can't see INR 100 crore in this quarter for UP. Because presently, we have started only 5 projects, and we are expecting last 2 -- the other 2 projects to start by end of July. So in excavation, the only -- there are 2 activities, which is going on excavation and the RCC [ to claim ], and which is always a time-consuming job. Once we are out of [ claim ], you can have a set of numbers as what we planned.
Shravan Shah
analystOkay. Okay. Okay. Got it. And sir, a couple of things in terms of the balance sheet numbers. The left one is mobilization advance, how much is mobilization advance?
Prahaladbhai Patel
executiveIt is in the 89%. Presently, we have...
Shravan Shah
analystNo, ma'am -- sir, I was saying, as of June, last time, it was INR 31 crore. So now what is the outstanding mobilization advance number?
Hetal Patel
executiveINR 100 crores. INR 100 crores because this quarter, 2 project mobilization advance money -- the residential project and the UP project also we received around INR 60 crores.
Shravan Shah
analystOkay. And cash is -- cash on bank balance is?
Hetal Patel
executiveYes. I have already mentioned, mainly we are...
Shravan Shah
analystYour voice was not clear, so that's why I was asking.
Hetal Patel
executiveYes. Total FD currently is INR 220 crores. So that includes the receipt of mobilization advance, we have kept it as it is and we'll be utilizing the overdraft facility as and when required. So out of INR 220 crores, the pre-FD is around INR 73 crores.
Operator
operatorThe next question is from the line of Prem Khurana from Anand Rathi.
Prem Khurana
analystSo 2 questions. So one was, I think in your opening remarks, you said the utilization of our fund-based limit is around INR 120-odd crores, which appears to be higher on a sequential basis. Whereas when I look at scale of operations, we've done lower revenue sequentially. I understand I mean there's a seasonality, which would have kind of played out during the quarter. But I was wondering if you could explain why this increase was there in utilization of our fund based? Because as I see it, you've also been able to manage good amount of mobilization advances from these UP orders as well as your residential. So if you could help me understand what is the total debt? And why did the utilization of fund-based limits go up in this quarter?
Hetal Patel
executiveSee, I have already mentioned this, the fund-based facility -- total facility has been increased. And as on 30th June, the fund-based utilization of INR 120 crores was there. And yes, you said that mobilization was received, but we are keeping that separately for those projects. And the fund-based utilization is mainly used for working capital as well as procurement of some of the assets as we have not taken any specific project finance for precast, so we are utilizing for that also. Because we have...
Prem Khurana
analystOkay. So it's fair to assume the increase that we have seen on a sequential basis is not because of the business operation, but because of precast facility, incremental CapEx that you would have done during the quarter?
Hetal Patel
executiveYes. You can say it, yes.
Prem Khurana
analystSure. And also ma'am, on this precast given the fact that you've already spent INR 85 crore, which is -- I mean, eventually, I mean, we've spent a large part of the money that we were supposed to spend for this facility. Have we started engaging with the clients now because it is the facilities nearing completion, so the idea would be to kind of don't let it sit idle. And the idea would be the day I finish it, I mean, I get to have some works wherein I would be able to utilize this facility. So have we started engaging with the clients for works which would be carried out on a precast basis?
Prahaladbhai Patel
executiveYes, we have started going into inquiries. We have almost near to closing of inquiries to 2 of the people, which may happen maximum within this month. So we'll be having some, but as and when it is concluded within the next week or maybe next 2 weeks from here. There are 2 projects on which we are discussing on. And one is I'm hopeful that it will be concluded in a week or so.
Prem Khurana
analystSure. And sir, we are already engaging with the clients. I mean if you could share your thoughts on the margin. I think last time you said the margin could be slightly lower than the -- I mean the conventional method of construction because of the raw material that we would be required to use. So margin would be -- I mean you still believe that the margin will be lower or it still could be in line with what we've been doing?
Prahaladbhai Patel
executiveIt will remain in the same rate what we expect in the construction business. So the -- and the cost of the material, it is always a pass-through whenever we bid for any project in precast also, we have to go through base rates only because this is cement and enforcement basic raw material for the business. So that has to be get pass-through. And usually, the trend is the same. So we'll be bidding as and when we bid for any precast elements, it will be on a base rate. So there won't be any impact of rates going up because of market [ sustainability ].
Prem Khurana
analystSure. And any more mobilization advances expected from UP? How much will be the balance from UP, I mean, that you are yet to realize?
Hetal Patel
executiveSee, 5% we have already received. One project is remaining. The other 6 projects, we have received 5%. And balance will be received when the stage comes. We have to provide them bank guarantees and they will be giving us mobilization advance for this.
Prem Khurana
analystAnd just one last, if I may with your permission. On this Maharashtra projects, I mean, Bhiwandi and Pandharpur, I think our experience has not been that great. I mean we started with Pandharpur and we were going good, but suddenly it has come to a stage wherein, I mean, we're going a little slow on this and Bhiwandi has -- we still don't have the workfront available. So when we approach, I mean, these kind of orders in the future, I mean, what are the checks and balances that you would want in place to be able to make sure that you don't get to have a similar kind of situation in the future? Because I mean, we've spent time on this, we have put in efforts, but then some of these efforts are yet to bear fruit, which is where I mean the idea also is to try and understand what are the changes that you would...
Prahaladbhai Patel
executiveCheckpoints is more related to the market over there and the department on which it is being constructed. See, if it is from the state government directly and it makes the difference. And if it is from a corporation or another [ colleague, ] it makes a difference. So we have to be careful while choosing. And at the same time, we have to be careful in terms of location also. You can see that there is a difference between the government who is operating and the central government who is operating. So that's also one of the issues that these types of projects are not being [ entered platform ].
Operator
operatorThe next question is from the line of Debashish Mazumdar from Edelweiss.
Debashish Mazumdar
analystCongratulations on a very good set of execution. So my first question is to Prahaladbhai. Sir, I wanted to understand that how is the demand scenario in the market and the macro perspective, are you seeing very high competitive, intense bidding? Or you are seeing that bidding...
Prahaladbhai Patel
executiveSir, speak louder, we are not able to hear anything.
Debashish Mazumdar
analystHello? Hello? Can you hear me?
Prahaladbhai Patel
executiveYes.
Debashish Mazumdar
analystYes. Sir, the question that I have was, in the macro scenario, how is the bidding situation, sir? Are you seeing very aggressive bidding from the competition? Or the bidding scenario is light? And the second is whether there are sufficient amount of projects for everybody to lap up? So definitely, the intensity is lower. So any color on that side, sir?
Prahaladbhai Patel
executiveYes. As far as bidding is concerned, I personally feel the competition is niche. There won't be any aggressive bidding. And it again depends on type of project and the type of qualifying criteria. And as I've always said that we are always going to be a little bit conscious on the bidding side, and we are not too much aggressive in whatever maybe the bidding other people are doing. And as such, I don't see any aggressive bidding on all of the projects. Maybe we have some of the projects like we have taken some such types of projects that most of the companies are qualifying, maybe that person is aggressively over there, but as far as general projects where we are bidding, we don't bid that aggressively.
Debashish Mazumdar
analystOkay. So what is the target of order inflow that you have in your mind for FY '22, sir?
Prahaladbhai Patel
executiveThat will be in the range of the same revenue what we do, at least minimum 25% to 30% most of our revenue what we are expecting this year or it should be minimum INR 1,800 crores to INR 2,000 crores.
Debashish Mazumdar
analystOkay. Great. So basically, we are saying that from INR 3,000 crores of the pipeline that we are chasing, we are confident that at least INR 1,500 crores to INR 1,800 crores of conversion from that pipeline?
Prahaladbhai Patel
executiveYes, INR 3,000 crores bid book is on present state. Still we have left about 9 months. So let us hope for the best.
Debashish Mazumdar
analystOkay. Great. The second question is for Hetal. Ma'am, you have said that the receivable number is around INR 281 crores, which is around INR 20 crores of increase sequentially. So I'm trying to get some sense that is there any specific where money is getting stuck? Or it's just because of the lockdown and macro challenges, which will be normalized going forward?
Hetal Patel
executiveNo, no. Actually, there are no specific -- hello?
Debashish Mazumdar
analystYes, ma'am.
Hetal Patel
executiveYes. See, mainly some of the payments which we were supposed to retain last week of June, that was received in -- that is the main difference. If we see by 15th of July, we have already received around INR 88 crores of outstanding. So there is no significant amount which is being stuck. So it's just a matter of one big tendency in collection. That's it. Normally in Surat, advance in last week of -- in the week of submission of lease, that was received in first week of July.
Operator
operator[Operator Instructions] The next question is from the line of Dhananjay Mishra from Sunidhi Securities & Finance Limited.
Dhananjay Mishra
analystYes. Most questions were answered. Just wanted to know, I mean -- yes, can you hear me?
Operator
operatorYes, you are audible.
Hetal Patel
executiveActually, there is much disturbance is coming in the line.
Dhananjay Mishra
analystOkay. You're hearing background noise?
Hetal Patel
executiveYes, there is a background noise. It's like...
Dhananjay Mishra
analystJust one question I'm asking. Just one question. Sir, can you see any delay because of UP election year? So any delay happening in education in UP Medical project?
Hetal Patel
executiveNo, no. There is no such delay noticed.
Operator
operator[Operator Instructions] The next question is from the line of Jiten Rushi from Axis Capital.
Jiten Rushi
analystYes. Jiten Rushi from Axis Capital. Sir, one question on the bid pipeline. So as you said, you're expecting an order inflow of INR 3,000 crores. So sir, what is the outstanding bid as on date? And when can we expect the opening of this bid? And can you highlight on which segments we have bidded for?
Hetal Patel
executiveSorry, actually, there was urgent call, which needs to be attended for P. S. Patel, sir. So I think bid pipeline is around INR 3,000 crores. That is the normal...
Jiten Rushi
analystSo any project specific, can you highlight? Or when can we expect a few projects, the opening of the bids? So we can just -- any update on that, ma'am or...
Hetal Patel
executiveNo, no. Actually, currently we don't have that status, but it's an ongoing process. So business is under bidding. So as and when means a prequalification stage and final stage comes, awards will be there.
Jiten Rushi
analystSo this time, this INR 3,000 crore, it is mostly from Gujarat or you are trying to bid outside Gujarat also, like we did in UP and other states?
Hetal Patel
executiveYes, it's around 70% only.
Jiten Rushi
analyst70% is Gujarat. Okay.
Hetal Patel
executiveYes.
Jiten Rushi
analystAnd ma'am, what is the outstanding gross debt number as on June?
Hetal Patel
executiveYes, if you see, I've already mentioned the current facility which we have utilized, current borrowing is INR 120 crores.
Jiten Rushi
analystINR 120 crores. Okay. And ma'am on the Central Vista, has the bidding started or we expect this to get delayed further by 3 to 6 months, where we can qualify and how we bid independently after solar projects, we are targeting to get over by August, September, right? We'll get the qualification certificate for that.
Hetal Patel
executiveNo, no. Still we are not being qualified because of this noncompletion of Surat project. So we haven't bidded yet.
Jiten Rushi
analystSo Surat, we are targeting to complete by August, right? August, we're targeting to complete, right, Surat?
Hetal Patel
executiveNo, See, sir has already mentioned, there will be like, say, a finalization. So it may extend to the third quarter also.
Operator
operator[Operator Instructions] The next question is from the line of Dhruv Bhimrajka from Monarch AIF.
Dhruv Bhimrajka
analystMa'am, I just have one question regarding our EBITDA margin. So like we have posted around 12.4% EBITDA for this first quarter. So what is the range of EBITDA that you expect for this financial year FY '22?
Hetal Patel
executiveSee, as we are normally saying that it will range between 12% to 13% of the revenue. It may range 11.5% to 13%.
Dhruv Bhimrajka
analystSorry, 12% to 13%?
Hetal Patel
executiveYes.
Operator
operatorThe next question is from the line of Amber Singhania from Asian Markets Securities.
Amber Singhania
analystJust one clarification I wanted to understand regarding the previous question. So you mentioned Surat Diamond Bourse will get completed by Q3 FY '22, right?
Prahaladbhai Patel
executiveMaximum Q3.
Amber Singhania
analystAnd sir, will -- so in that case, are we not eligible entirely for bidding of Central Vista, any of the packages now?
Prahaladbhai Patel
executiveThat depends on again the prequalifying prices. If they allow for 90% residential completion, we may qualify.
Amber Singhania
analystOkay. And what is the time line for Central Vista, sir, when it is expected to come for bidding and tendering?
Prahaladbhai Patel
executiveSee, that we cannot envisage to like how they are going to get all the tenders. So presently we can say out of INR 20,000 crores of project, 3,000 -- almost INR 5,000 crores order has -- tenders have come up. So still there's a hope of INR 13,000 crores to INR 14,000 crores of work to come.
Amber Singhania
analystOkay. So it all depends on whether they allow 90% completion to consider for bidding or not? And secondly, how fast we will be completing the Central Vista, right, sir -- sorry, Surat Diamond Bourse?
Prahaladbhai Patel
executiveYes. Yes.
Amber Singhania
analystSir, apart from Central Vista, could you name a few large projects which are coming or which are already there in the pipeline on bidding side or which are coming in the next 6 to 8 months?
Prahaladbhai Patel
executiveSee, as I said that we have a bid book of about INR 3,000 crores, the major is Gujarat Housing Board about INR 750 crore. And there are a few projects from Adani airports over INR 300 crores to INR 400 crores. There are a few projects from Adani commercial also. And one more project I think, Medical College [indiscernible] that is about INR 250 crore. We are also bidding to AM/NS, ArcelorMittal that is about INR 300 crores. But most of the projects which we are bidding presently is in the range of INR 300 crores to 400 crores and exceptional [indiscernible] Gujarat Housing Board project, that is more than INR 700 crores.
Operator
operator[Operator Instructions] As there are no further questions from the...
Prahaladbhai Patel
executiveI think if there's no question from anybody's side, let us conclude the call.
Operator
operatorSure. Mr. Varun Ginodia, I would request you to please have any closing comments.
Varun Ginodia
analystCan you hear me now? Can you hear me?
Prahaladbhai Patel
executiveYes. Yes. Yes.
Varun Ginodia
analystYes. Yes. Thank you so much, Ayesha. And thank you, sir and thank you, ma'am for patiently answering the questions. And I really apologize for the background noise that was there, some disturbance in the call.
Prahaladbhai Patel
executiveYes. There was a little bit disturbance today.
Varun Ginodia
analystYes, really sorry for that. And yes, I'll hand over the call to you for any closing remarks, sir.
Prahaladbhai Patel
executiveThanks to all of you, and stay safe and take care.
Hetal Patel
executiveThank you, everyone.
Varun Ginodia
analystYes. Thank you.
Operator
operatorThank you. On behalf of AMBIT Capital, that concludes this conference. Thank you, everyone, for joining us, and you may now disconnect your lines.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete PSP Projects Limited transcript — plus 248,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to PSP Projects Limited earnings transcripts and 248,000+ others is available through the
EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.