Hello everyone, and thanks for joining us for PSEG's earnings presentation covering the third quarter of 2023. With us today are Ralph LaRossa, our Chair, President, and Chief Executive Officer, along with Dan Cregg, Executive Vice President and Chief Financial Officer. You can find the press release, any attachments, and the slides for this discussion on our IR website, investor.pseg.com, and we'll be filing our 10-Q shortly. Today's call includes PSEG's earnings release and other topics that involve forward-looking statements and estimates, and those carry various risks and uncertainties. We'll also be talking about non-GAAP operating earnings, which is different from net income or net loss reported under Generally Accepted Accounting Principles, or GAAP, here in the United States. Reconciliations of our non-GAAP financial measures, plus a disclaimer about forward-looking statements, are available on our IR website and in today's material. After Ralph and Dan give their prepared remarks, we'll hold a question-and-answer session lasting 30 minutes. At this point, I'll hand the call over to Ralph LaRossa.

Ralph LaRossa

executive
#2

Thanks, Carlotta. Morning, everybody, and I appreciate you being here as we go over what PSEG delivered in quarter three. PSEG announced earlier today that net income for the third quarter of 2023 came in at $0.27 per share, versus $0.22 per share of net income in the third quarter of 2022. On a non-GAAP basis, operating earnings for quarter three reached $0.85 per share, against $0.86 per share during the third quarter of 2022. Items laid out in Attachments 8 and 9, which came with the earnings release, are excluded from our non-GAAP results. Both PSE&G and PSEG Power and Other are performing in a way that keeps fully satisfying our planning expectations, and we're quite happy about that. Nine months in, PSEG remains positioned to hit full-year 2023 non-GAAP operating earnings guidance of $3.40-$3.50 per share; this morning, alongside the release of our third quarter results, we also reaffirmed PSEG's full-year 2023 earnings guidance as well as our long-term 5%-7% earnings growth outlook, and Dan is going to get into more detail on that after I finish. Several fronts made it a very productive quarter for us. PSE&G, our utility, put roughly $1 billion into energy infrastructure across quarter three, which lifts year-to-date spending to $2.7 billion. Capital spend for the whole of 2023 is now projected to reach $3.7 billion, a touch above the $3.5 billion we originally planned, running ahead of scheduled execution on our Clean Energy Future — Energy Efficiency and Infrastructure Advancement programs. Turning to advanced metering, PSE&G has finished installing and placed into service a bit more than half — or $1.3 million — of the $2.3 million smart meter replacements planned. All told, we're staying on schedule and inside our cost parameters. Demand for PSE&G's energy efficiency solutions has been strong, and that's helping customers cut their energy use and shrink their bills. For a sense of just how strong that demand is, think about this: PSE&G today sells more energy efficiency solutions in one month than we sold across a full year only a few years back; beyond that, we keep backing the energy transition and decarbonization of the New Jersey economy by upgrading the last mile of our distribution system, and by adding new electric infrastructure, driven partly by more electric vehicles on the road. These essential New Jersey energy investments also underpin our rate-based growth trajectory of 6%-7.5% through 2027. The bottom end of PSEG's rate base CAGR presumes an extension of our investment programs at the annual levels they currently run at. Sitting inside the top end of that rate base range is a possibly larger volume of infrastructure investment plus forthcoming filings for energy efficiency beyond their present run rates. Last week, the BPU shifted the start date for the second three-year energy efficiency period, so it now begins January 1st, 2025, and continues through June 13th, 2027 — a total term of two and a half years — while tacking a six-month extension onto the current three-year period. The BPU asked for refreshed utility submissions so they would line up with this new timeframe. Under the BPU's revised framework, energy efficiency in the state gets a strong go-ahead, and it sets utility-by-utility targets for net annual energy reduction in the filings ahead. Utilities are further instructed to put forward measurable performance metrics that match those updated net annual energy reduction targets within the shortened 2.5-year window. For gas, the earlier annual reduction goal of 0.75%, and for electric, 2%, across the 2026 and 2027 program years, stay as they were. Earlier this month, the BPU signed off on a settlement extending our existing GSMP II program through December 2025, and it set aside $900 million of investment to swap out at least 400 miles of cast iron and unprotected steel main, running at a slightly higher pace than our earlier programs. Out of that $900 million from the settlement, $750 million gets recovered via three periodic rate update clauses, while the remainder will be taken up in a later rate case. Under GSMP II, we cut methane leaks by roughly 22% across the system compared with 2018 levels. Thanks to this extension, we stay on course toward our long-term methane emissions reduction goal of at least 60% across the 2011 through 2030 span. PSEG's larger GSMP III filing is currently on hold. That filing, which also features pilot projects for bringing renewable natural gas and hydrogen blending into our current distribution system, should get going again once the natural gas utility stakeholder proceedings wrap up. The approval of the GSMP two extension allows for the GSMP three filing to restart by January 2025, aiming to kick off the next phase of this work in January of 2026. Even as we make these investments, customer affordability stays a priority, and we keep managing our O&M expense carefully; we just finished new four year labor agreements with every one of our New Jersey unions. I want to stress how much this matters for our costs, since labor ranks among our biggest expenditures. Four years of certainty on labor costs lets us hold customer bills down and gives our represented employees predictable wages. On a shared wallet basis, PSEG keeps stacking up quite favorably against peers, in the region and across the country. Typical residential natural gas customers' monthly bills are still some of the lowest in the region. On top of that, for the coming 2024 heating season, the BPU granted PSEG's request to bring the gas commodity charge down to about $0.40 per therm, starting October 1st. That gas commodity charge, a mere pass-through for the utility, has fallen by 38% in total since January 1st, 2023. Now, moving to our nuclear operations, the PSEG nuclear fleet ran at a 95.8% capacity factor in the year-to-date period that ended September 30, generating 24.3 TWh of carbon-free baseload energy. Salem Unit 1, which we own 57% of, has just finished yet another breaker to breaker run and gone into its planned fall refueling outage, after 508 continuous days of operation between refuelings. We're still working on moving Hope Creek's boiling water reactor from a refueling cycle of 18 months to one of 24 months, using projects with lower capital costs. As for the competitive transmission proposal we filed with PJM under its 2022 Window 3 solicitation, the staff of their Transmission Expansion Advisory Committee recently suggested including a PSEG project within a comprehensive solution. A $447 million investment is laid out in PSEG's project, with an anticipated in-service date of 2027. In December, the PJM board will reveal its final decision. Here's one more instance of regulated opportunities we're chasing, and when similar chances come up, we plan to apply our substantial transmission expertise. Let me shift briefly to sustainability: you'll remember we made a commitment in September 2021 to the United Nations-backed Race to Zero campaign, intending to submit proposed targets covering Scopes 1, 2, and 3 emissions to the Science-Based Targets Initiative; our submission went in during September, and SBTI's validation process now has it under review. To wrap up, I'd like to go back over some of the strides we've taken toward our aim of making our business more streamlined and predictable.

Ralph LaRossa

executive
#3

The divestiture of the fossil business and our departure from offshore wind generation mean we now carry a reduced business risk profile. Back in February and in August, we managed to cut a substantial portion of pension variability affecting future results, thanks to the regulatory accounting order and the lift out, and we'll look at whether to pursue further mitigation in our upcoming rate case. By deciding to keep our carbon-free baseload nuclear fleet, we have assisted in safeguarding the financial viability of vital New Jersey energy assets, bolstered by revenue stability from a production tax credit set to start in January 2024. Such steps assist us in extending our record of delivering on PSEG's enhanced business strategy. The nuclear PTC gives us a decade-long view of cash flows, which will help us preserve a strong financial profile — one that doesn't call for issuing new equity or offloading assets to finance our five-year capital investment program — and it backs our capacity to pay a competitive, growing dividend; to wrap up, I'd like to outline how we plan to deliver 2024 earnings guidance along with other key financial updates. As you're aware, this December we will submit our electric and gas distribution-based rate case, and once it becomes public, we'll fill you in on the parameters. Our standard business planning wraps up in mid-December, so expect us to offer 2024 non-GAAP operating earnings guidance soon after that business plan finishes. Come early December, we plan to refresh our existing 2023 to 2027 CapEx and rate base projections so they capture the recent GSMP2 extension through 2025, plus two forthcoming energy efficiency filings. The first would extend the current EE program through the close of 2024, with a new filing to follow that covers the subsequent round of EE programs through 2027. These updates will shape our longer-term assumptions regarding capital and rate base projections, and we anticipate posting a full roll forward of the capital plan, rate base, and long-term earnings CAGR in the January 2024 investor update. I'll hand the call to Dan now for further specifics on the operating results, and we'll take your questions once he's finished speaking.

Dan Cregg

executive
#4

Thanks, Ralph. Morning, everyone. To build on what Ralph said, PSEG's net income came in at $139 million, or $0.27 per share, for Q3 2023, versus $114 million, or $0.22 per share, in Q3 2022. Non-GAAP operating earnings for Q3 2023 totaled $425 million, or $0.85 per share, against $429 million, or $0.86 per share, in Q3 2022. You can find details on slides nine and 11 showing how each business contributed to non-GAAP operating earnings per share for Q3 and year-to-date 2023. Slides 10 and 12 have waterfall charts walking through the net quarter-over-quarter and year-to-date shifts in non-GAAP operating earnings per share by major business. Turning to PSE&G, which posted Q3 2023 net income of $401 million, or $0.80 per share, versus $399 million, or $0.80 per share, in Q3 2022. PSE&G's non-GAAP operating earnings were $403 million, or $0.80 per share, for Q3 2023, against $399 million, or $0.80 per share, in Q3 2022. What mainly drove both GAAP and non-GAAP results this quarter was growth in transmission and distribution margins from ongoing infrastructure replacement and clean energy investments, plus reduced O&M expenses. Those gains were partly offset by the lower pension income and OPEB credits we expected, along with increased depreciation and interest expense tied to added investments made since the prior-year quarter. Versus Q3 2022, transmission rose $0.03 per share. Electric margin increased $0.02 per share, driven by returns on Energy Strong II investments. Gas margin was up $0.01 per share, largely from clause recovery of our GSMP investment. Reduced distribution O&M expense contributed $0.01 per share versus Q3 2022, while depreciation and interest expense each rose $0.01 and $0.02 per share, respectively, against Q3 2022, reflecting ongoing investment growth. Lower pension income from 2022's investment returns, plus reduced OPEB credits set to expire during 2023, produced a $0.05 per share unfavorable comparison to last year's quarter. Finally, the timing of taxes recorded through an effective tax rate—which nets to zero across a full year—and other flow-through taxes yielded a net favorable $0.01 per share impact this quarter versus Q3 2022. Weather in Q3, based on the temperature-humidity index, ran 11% warmer than normal but 5% cooler than Q3 2022. As noted before, the CIP mechanism, active since 2021, caps how weather and other sales variances—whether positive or negative—affect electric and gas margins, while letting PSE&G push broad adoption of its energy efficiency programs. The number of electric and gas customers is still climbing, which is what drives margin under the CIP mechanism, and both were up roughly 1% year to date. Turning to capital spending, PSE&G put about $1 billion to work in the third quarter and remains on schedule to carry out the biggest investment program it has ever run in one year, at $3.7 billion. Upgrades and replacements at our T&D facilities are part of that program, along with Energy Strong II investments, last mile spend under the Infrastructure Advancement Program, our GSMP2 program as it continues, the ongoing build-out of clean energy investments in energy efficiency and the Energy Cloud, smart meters included, plus new electric infrastructure to handle rising EV penetration. Over the course of 2023, steps have been taken to reduce how much our pension affects earnings and to make our financial results more predictable; back in February of 2023, the BPU gave approval to an accounting order that lets PSE&G change the way it calculates amortization of the net actuarial gain or loss component for rate-making purposes. That change applies starting with calendar year 2023 and going forward. PSE&G's forecast of non-GAAP operating earnings for the full year 2023 is still $1.5 billion-$1.525 billion. Shifting to PSEG Power and Other, the third quarter of 2023 saw a net loss of $262 million, or $0.53 per share, mostly because of the pension settlement charge tied to the lift out transaction. That's against a net loss of $285 million, or $0.58 per share, in the third quarter of 2022. The one-time non-cash settlement charge came to $332 million, $239 million net of tax, and related to roughly $1 billion of PSEG Power and other pension obligations and associated plan assets that went to the Prudential Insurance Company. Once the effect of the lift out is accounted for, our pension plans are still well-funded, and there's no material impact on our non-GAAP operating earnings in 2023. non-GAAP operating earnings came in at $22 million, or $0.05 per share, for the third quarter of 2023, versus non-GAAP operating earnings of $30 million, or $0.06 per share, in the third quarter of 2022. As we said earlier, in the first quarter of 2023, PSEG Power captured the bulk of the roughly $4 per MW hour rise in the average price of our 2023 hedged output, which climbed to approximately $31 per MW hour, with most of that gain coming from higher winter pricing. In the third quarter of 2023, gross margin increased by $0.03 per share in total, mainly due to the roll-off of certain full requirement BGS load contracts that carried a higher cost to serve, which produced a $0.04 per share benefit versus the prior year. Higher generation also contributed to the gross margin improvement, adding $0.01 per share, because there was no Hope Creek refueling outage, which had begun at the end of last year's third quarter. Those favorable differences were partly canceled out by decreased capacity income amounting to $0.02 per share relative to the same quarter last year, which aligns with capacity auctions from the previous year. When looking at O&M costs for the third quarter, things got better by $0.03 per share, thanks to not having Hope Creek refueling outage costs that had been partially taken on during 2022's third quarter. Depreciation expense came in lower, adding $0.01 per share on a favorable basis versus the year ago quarter, but interest expense ran higher, creating a $0.01 unfavorable impact. Reduced pension income stemming from 2022 investment returns along with OPEB credits resulting from a smaller amortization benefit added up to $0.03 per share unfavorable against third quarter 2022, and taxes plus other items were $0.04 per share unfavorable relative to the third quarter of 2022, which mirrors a partial reversal of the effective tax benefit recorded in the first quarter of 2023; turning to operations, the nuclear fleet generated roughly 8.1 TWh in the third quarter and 24.3 TWh across the year-to-date period in 2023, operating at a capacity factor of 95.3% and 95.8% for the quarter and year-to-date periods, respectively. Looking ahead to the full year of 2023, PSEG expects generation output between 30 and 32 TWh, and has hedged roughly 95%-100% of that production at an average price of $31/MWh. As for 2024, the nuclear fleet is projected to generate 30 to 32 TWh of baseload output, with 85%-90% of that generation hedged at an average price of $38/MWh.

Dan Cregg

executive
#5

Our projection for non-GAAP Operating Earnings at PSEG Power and Other stays the same, at $200 million-$225 million for the entire year. That outlook takes into account that most of the anticipated bump in the average 2023 annual hedge price was realized during the first quarter of 2023, as we talked about earlier. Over the rest of the year, greater interest expense — mostly factored into what we shared back in our November 2022 update — should bring down PSEG Power and Other results. Let me turn to a few recent financing items. At September 30, PSEG's total available liquidity came to $3.8 billion, which included $57 million of cash on hand. PSEG Power's net cash collateral postings stood at roughly $350 million as of September 30, well under the heightened level we saw a year ago; during August, PSEG brought to market $500 million of 5.2% secured medium-term notes maturing August 2033, plus $400 million of 5.45% secured medium-term notes maturing August of 2053. In September, PSEG paid off at maturity $325 million of 3.25% secured medium-term notes. After the third quarter closed, PSEG brought to market $600 million of 5.88% senior notes maturing October 2028, along with $400 million of 6.13% senior notes maturing October 2033. Before those notes were priced, 800 million of treasury locks were executed, carrying a positive fair value of $14 million, and that benefit gets amortized across the life of the senior notes, partly offsetting interest expense. Money raised from selling the senior notes goes toward general corporate purposes, among them repaying $750 million of PSEG debt that comes due this November. At September 30, 2023, PSEG had $500 million outstanding under a 364-day variable rate term loan maturing in April 2024, while PSEG Power had $1.25 billion outstanding under a variable rate term loan maturing March 2025. By quarter's end, PSEG had swapped $900 million of the power term loan from variable to fixed rate, which helps soften the effect of higher interest rates. At September 30, taking our swaps into account, roughly 5% of total debt carried a variable rate — half of what it was at year-end 2022. Thanks to a better collateral position, a staggered maturity schedule, and PSEG Power cash generation that supports funding our regulated business, we keep a solid financial position with limited exposure to variable rate debt. To wrap up, we are reaffirming PSEG's full year 2023 non-GAAP operating earnings guidance of $3.40-$3.50 per share. PSE&G is projected to contribute between $1.5 billion to $1.525 billion, while PSEG Power and Other is projected at $200 million-$225 million. That wraps up our formal remarks. Operator, we are ready to start the question and answer session.

Nick Campanella

analyst
#6

Hi there, and good morning. I appreciate you taking my question.

Ralph LaRossa

executive
#7

Morning, Nick.

Nick Campanella

analyst
#8

Okay. Hi there. So, I simply wanted to inquire, you know, when we look ahead toward 2024, if the market at large were to perform poorly, that might perhaps influence the pension headwind you face, though, you know, we also recognize that you've undertaken substantial de-risking during the last year in order to remove that volatility. You had the lift out, you have the accounting order. Could you simply provide any indication of how we ought to consider pension contribution as a share of earnings for 2024, or even against the drag experienced so far this year? Is there a drag we should be contemplating for 2024? And any specifics regarding how pension has done so far this year compared with what you expected would also be useful. Thanks.

Ralph LaRossa

executive
#9

Yes, Nick, certainly; so look, to begin with, I appreciate that you acknowledge the efforts Dan and his team, and, and the regulatory team, have already made here. We are witnessing the advantages from it, correct? To use engineering language, we've shrunk the amplitude of the sine wave, and, there is diminished volatility. So, nothing we have observed or anticipate will turn into a problem for us when we consider 2024. But I'll let Dan supply whatever further specifics he wishes to offer regarding that, though it's simply the outcome of solid work we've completed this year.

Dan Cregg

executive
#10

Yes, Nick, that was essentially our goal. It won't remove the impact of market fluctuations, since we still hold a pension, but we've managed to reduce how large those swings can be. So, as the year has progressed, markets have shifted. Over the past few months, they've declined somewhat. There are still a couple more months before we know where things stand. I'd say we aren't fully shielded from those movements, though I believe the efforts we've made will soften that impact. And based on what we're seeing right now, the size of what we expect, or what we anticipate, as we head toward year-end is still something we can handle within the overall OM budget.

Nick Campanella

analyst
#11

All right, that's useful. And it's good to see you're running ahead of schedule on the CapEx. Clearly, there's an upward bias as you move forward, and I suppose we'll receive additional specifics on that in January; but when we consider running greater CapEx through the model, how are you viewing equity proceeds, if at all?

Dan Cregg

executive
#12

No, there hasn't been any, and we don't intend to issue any equity as we work through the capital plan we've laid out for you; so for the utility, we've had $15.5 billion-$18 billion through 2027 the entire year. Across the five years, we remain inside that range. That $3.7 billion represents excellent performance, so we've kept moving ahead on it. But you know, what you see there is excellent and it helps, yet it stays inside our overall range, and even to fund the high end of that range, no equity will be required from us.

Ralph LaRossa

executive
#13

Nick, I want to reinforce that point, okay? We've told everybody that we're able to do this without issuing equity — none of that type of equity — and without selling off any assets.

Nick Campanella

analyst
#14

Thank you.

Ralph LaRossa

executive
#15

Yep.

Shar Pourreza

analyst
#16

Hey, good morning, guys.

Ralph LaRossa

executive
#17

Good morning, Shar.

Dan Cregg

executive
#18

Shar.

Shar Pourreza

analyst
#19

Good morning, good morning. I want to tweak Nick's question slightly when it comes to 2024. Obviously, PSEG has a massive year coming up, given the rate case filing, the PTC guidance you've provided for nuclear, and the ZECs sunsetting — is that right? So when you roll forward at 42, even if we're only looking at this directionally, how do you plan to incorporate those various scenarios into your 2024 guidance? Obviously, a fast resolution of the GRC could play into that. So what should we be assuming as your base case there? Regarding revisions to the interest rate projection, plus that $0.30 shortfall drag at PSE&G discussed twelve months back — are there other pluses or minuses related to regulatory lag from the prior year? Thank you.

Ralph LaRossa

executive
#20

Indeed, Shar, those are excellent questions, and once more, I'll let Dan handle the specifics here. However, you've identified every variable we're weighing, and much of that shapes the schedule we've set, meaning we'll release our earnings during December. So Dan, please elaborate further on any of those points.

Dan Cregg

executive
#21

Yes, of course. We'll lock in our final direction and then share it with you. I mean, whenever you move ahead, there are inevitably certain assumptions you're going to make. Regarding the rate case, we'll be submitting it at some point in this quarter. As we've mentioned, the process typically takes somewhere in the range of 9 to 12 months, so our assumptions will be built around that. I wish I could say that we'll have PTC guidance available and know precisely how everything shakes out; however, until those regulations arrive, there's a sensible set of assumptions you can work with, and that's what we'll do. What we project for interest rates is really going to depend on market conditions; we've factored in the movements observed over the past year or so. So all of that will factor in, and I believe we can still speak confidently about an overall guidance range for 2024, and we'll provide that shortly.

Shar Pourreza

analyst
#22

Once more, I'm not trying to trap you here, yet it does appear that as you consider that move from 2023 into 2024, there are likely more things pushing in your favor than dangers working against you. Would you say that's a reasonable read?

Dan Cregg

executive
#23

Well, here's the thing — I believe what we'll present is a well-rounded perspective. From what Nick asked earlier, plus a few of the items you brought up, those are exactly the sorts of factors that will factor in when we build the estimate. Even so, given how this business is structured, weather swings shouldn't be a concern for us thanks to our decoupling. Our pension variability is reduced, as Ralph just pointed out. The bulk of interest rate shifts have already been captured. So the effort we've invested across the past 12 months or so, closer to 18, should genuinely bear fruit, letting us speak with assurance about that range once we release it.

Shar Pourreza

analyst
#24

Understood; and finally, regarding what you're picking up about the nuclear PTC guidance, and how are you building a business case that accounts for it? After all, there's a refueling cycle, and some modest CapEx improvements for nuclear have been sitting on the back burner. With that guidance in place, are those plans nearing a point where you'll make a decision?

Dan Cregg

executive
#25

Yes; so certainly, a few points I'd make there. As you know, to underscore once more the stability we rolled out last year, we anchored it at the PTC floor, correct? Which means we aren't relying on anything more than that, and that's how our plan has been established; so for all of you that ought to be fairly evident and fairly transparent in that regard; and then when it comes to CapEx, we've mentioned on a few occasions that things are advancing quite nicely with the refueling cycle at Hope Creek. That effort is moving along as anticipated, and nothing unexpected has come up; and you'll likely hear from us at some point during 2024 with a bit more about the upgrades we're planning for Salem and when those will occur.

Shar Pourreza

analyst
#26

Alright, that's great.

Dan Cregg

executive
#27

Still, there's a significant impact on 2024 CapEx. Down the line, though, that spending will pay off.

Shar Pourreza

analyst
#28

Understood. And once more, I apologize — I'm just being flooded with questions right now. One thing I wanted to ask: at what point do you intend to provide guidance for 2024?

Dan Cregg

executive
#29

What we've communicated is that it will come once the business planning process with our board wraps up. There's a board review we conduct in December, so December is when that will happen.

Shar Pourreza

analyst
#30

Alright, that's great. Thanks so much, everyone. Hope you all have a wonderful morning. I really appreciate it.

Dan Cregg

executive
#31

Yep. Take care.

Dan Cregg

executive
#32

Hey, Durgesh.

Ralph LaRossa

executive
#33

Hey.

Durgesh Chopra

analyst
#34

Hey, Ralph, good morning. Thanks for giving me time.

Ralph LaRossa

executive
#35

Morning.

Durgesh Chopra

analyst
#36

One quick clarification regarding equity—this probably falls to Dan—but that slide from the June investor presentation referenced $4 billion of balance sheet capacity. Where does that stand today? There are clearly pluses and minuses, as you're aware. Where does that stand today? Second, just so it's clear, as you move the plan forward—with energy efficiency and, of course, the transmission opportunity—should we anticipate no equity as you carry that plan forward through 2028?

Ralph LaRossa

executive
#37

Right. So, I'll hand it over to Dan once more to fill you in on some specifics, but either one of those developments is really positive for us — the transmission chance, plus the gains in energy efficiency we're seeing come out of the triennial that the BPU introduced. Still, I think Dan will tell you the very same thing: we have no need for equity or anything resembling it.

Dan Cregg

executive
#38

Yes, Durgesh, Ralph's point is correct. So, as you know, we continue to proceed using the very same capital range that was mentioned previously. An update is going to be provided by us. In his comments made before, Ralph brought up this matter, based on what we have received as feedback from PJM, as well as from what the state is reviewing, regarding energy efficiency during the upcoming triennium—that being the following 3-year span. Therefore, that update will be delivered by us moving ahead. Listen, that is going to be precisely it. The manner in which this flows through is that we possess a capital range. That range will be refreshed by us, and beyond that, we will have whatever is left over from the perspective of that debt capacity. However, my view is that you ought to continue looking at us with assurance that funding this can be done by us absent any requirement for additional equity.

Durgesh Chopra

analyst
#39

Great, thanks. That's very straightforward. And then, regarding nuclear PTCs specifically, I noticed you've boosted hedges for 2024, the share of output that's hedged. What's your thinking for 2025? I mean, clearly we're still waiting on guidance, but as you move ahead into 2025, will you be hedged less than previously, looking forward to some clarity on the nuclear PTC, or what's your overall approach there?

Dan Cregg

executive
#40

Okay, so here's what we've told people: we don't know precisely how the math will work out, and our approach has been to reason through what might be headed our way, correct? When that kind of ambiguity exists, you attempt to anticipate the final outcome, and then you evaluate whether those options are workable and where they could end up. And we've sort of shaped our response to that line of thinking given some of that ambiguity. That isn't to say we'd stop doing any hedges at all; it means we'd keep advancing at a steady pace while considering how that PTC might ultimately be resolved. Those rules are going to be issued at some point, and we're hoping it's sooner rather than later, for precisely that reason, right? It ought to influence how you're approaching this; but I'd say, don't think too differently from what we'd already been doing, in terms of our hedging compared with what we're doing now within 25, as a broad guideline.

Durgesh Chopra

analyst
#41

Much obliged for that detail, Dan, and well done to both you and the group on this quarter.

Dan Cregg

executive
#42

Thank you, Durgesh.

David Arcaro

analyst
#43

Hi, Ralph. Hi, Dan. Morning to you.

Ralph LaRossa

executive
#44

Hi there, David.

David Arcaro

analyst
#45

Let's take a look here. I'm curious whether you might speak to what you're now anticipating regarding the rate case. Has any part of your outlook on the revenue requirement shifted? Anything regarding capital or O&M that might alter what you expect to submit when you file later this quarter?

Ralph LaRossa

executive
#46

Yeah, no, nothing that I'd really pointed to. As we've consistently stated, our plans are what they are. The one item you'll likely notice is that the rate case provides an opening to fold in plenty of the other matters folks have raised, such as interest rates or pensions, correct? Plus how pension costs could affect us; so those are really the sole two fresh items I'd mention, and we continue watching CapEx; yet the bulk of the things we discussed, like GSMP, on which we closed, the transmission chance that's out there, which wouldn't involve the state of New Jersey, or energy efficiency, would be a clause mechanism. So nothing, in my view, is really causing a major shift for us. And, Dan, is there anything you'd like to include?

Dan Cregg

executive
#47

No, hold on—just one point. David, there's a single item I believe we shouldn't overlook and could easily miss: with everyone concentrating so much on the higher interest rate environment, we've been getting questions about how this might affect, in any way, the rate case moving forward; and I've been telling people this marks our first rate case filing since 2018, so during the early stretch between rate cases, our interest expense came in lower. And so yes, in the current environment what we're seeing is higher, which means certain costs could flow through the total revenue requirement tied to the weighted average cost of capital. But when you consider moving through years when interest rates sat lower and now find ourselves in a higher rate environment, on balance, that doesn't translate into a significant rate increase driven by interest rates. So as a reminder, that isn't a rate pressure we're heading into.

David Arcaro

analyst
#48

Yeah, understood. All right, that's useful. So then, as you know, the commission now has new leadership. I was just curious whether you might share your thoughts on, you know, what you believe the commission's broad priorities are and, you know, how they might handle things like settlements, or just your general sense of, you know, the chances for you to engage with them going forward, given new leadership and a different group of commissioners. Thanks.

Ralph LaRossa

executive
#49

Yeah. Yeah, David, of course. Look, I would... what people think really counts for less than what actually gets done; and I have to say, I'm extremely happy with the board and what they did regarding our Gas System Modernization Program; that swift and firm move to push it ahead demonstrates a few things. First, the efforts we're making and the way they benefit the environment when it comes to methane reduction line up with the state's policies. And I'd add that the board's wish to keep arriving at settlement was on display there too, correct? So those two items are genuine positives and ought to reassure not just us and what we think, but all of you, that we're in the same position we occupied previously.

David Arcaro

analyst
#50

All right, that's excellent. Wonderful. Thank you very much. I appreciate that.

Jeremy Tonet

analyst
#51

Hello there, good morning.

Ralph LaRossa

executive
#52

Hey there, Jeremy.

Dan Cregg

executive
#53

Good morning, Jeremy.

Jeremy Tonet

analyst
#54

Hi. I'd like to expand a bit, I suppose, on a few things you mentioned earlier. Regarding the GSMP2 extension, could you describe how the settlement compares with the assumptions in the capital plan and with the longer-range objectives of GSMP3? Do the state's continuing discussions about the energy transition play a role in this settlement, taking a more comprehensive view?

Ralph LaRossa

executive
#55

Yes. Here's how I'd put it. The 2 years we settled on carry a higher run rate than would have applied otherwise under our filings. That's clearly a plus. In my view, the 2 areas that drew concern during the discussion involved very little investment. One was the renewable natural gas component of our filing, while the other involved hydrogen blending. Those are reasonable policy matters that ought to be addressed, so the board preferred to proceed, in terms of commitment, to complete the work needed to keep methane reductions going. On that, we're fully in agreement. The run rate came in higher, and I think we simply take part and watch where policy heads on those remaining 2 items, then decide accordingly. Still, from the perspective of long-term strategy, our pledge to remove cast iron from our system stands, and the commission currently backs it. So from that angle, I don't see much shifting.

Dan Cregg

executive
#56

Okay, so considering the capital plan, Jeremy, we'd mentioned that the bottom of that range matched where we stood, while the top of it resembled what we saw for this specific item — closer to what was submitted for GSMP3. As a result, we exceeded our run rate, yet stayed below what we'd filed, which puts us solidly inside that capital plan range.

Jeremy Tonet

analyst
#57

Understood. That's quite useful. Then, moving on to hydrogen, if I may, what's the newest update on the messaging around the hydrogen hub assessment in the Northeast Mid-Atlantic region, and what should our thinking be regarding the hydrogen chance spanning local industry, PSEG's nuclear fleet, gas and blending, plus regional renewable electrification as a whole? What are you able to tell us?

Ralph LaRossa

executive
#58

Yes. Jeremy, to start, we took part in 2 of the hub applications. The Northeast Hub was one, and MACH2 was the other. The one chosen by the DOE in this region was the MACH2 hub, and being included in that solution makes us genuinely glad and proud. My view is it will give us plenty of long-term growth possibilities in the region. I say that from the perspective of economic development for the state. I believe there will be a genuine chance for us to put an electrolyzer in some part of South Jersey. I believe there will be a chance for us to leverage certain pipelines already present in South Jersey along with some storage already present in South Jersey for hydrogen, plus some end users located in that area, in Delaware as well as across the river in southern Pennsylvania from a refinery perspective. That covers the broad economic angle. I believe what we actually do here will truly be settled once we see the rules issued from the IRA and how the PTC will work alongside the nuclear PTC, and the, and what might — so you could think of it as stacking hydrogen credits on top of that or not. So that's something we'll examine. None of that is included in our plan. I believe that's the main point for you to remember. For us, it's upside. I'll also say that we hold no expectation of taking part in anything that would generate commodity risk for us regarding hydrogen. So we'll, we'll evaluate this. We'll assist the state in achieving some economic growth out, you know, that, that they have down in that, the initial portion of our state, and then we'll, we'll determine what specific role we play inside it as an enterprise.

Jeremy Tonet

analyst
#59

Understood; that's quite useful, and I believe you folks have been quite, quite explicit regarding no equity, so I will completely stay away from that topic, but just—

Ralph LaRossa

executive
#60

I could repeat it if you want, Jeremy.

Jeremy Tonet

analyst
#61

No, we heard you loud and clear.

Ralph LaRossa

executive
#62

Okay.

Jeremy Tonet

analyst
#63

I suppose the only thing is, when it comes to December, is there anything new to share on that front? In other words, should we expect some sort of CapEx refresh in December, and would that then get revised afterward during 2024 as certain incremental pieces land and things become clearer on a few of those items? And assuming that happens, how would the EE filing you anticipate line up against the way you were viewing things at the time of last year's CapEx update?

Ralph LaRossa

executive
#64

Right. Jeremy, what we'll do is provide a partial CapEx update covering the period through 2027, and then in January we'll come back with additional detail, looking at it from a capital roll forward perspective. That's roughly the cadence. What comes in December will include a portion of the run rate we referenced for GSMP, plus the EE filings we're required to submit, which are due at the start of December for the BPU. With that said, our message has been that this filing will... If you consider the triennial, your expectation would be for somewhat more than what we've historically observed on a run rate basis. We're still in the process of evaluating it. I haven't personally laid eyes on the final version from our team, so there's nothing further I could share even if I wished to; nonetheless, the signal from everyone who has reviewed that order issued by the BPU is that we'll have greater opportunity there.

Jeremy Tonet

analyst
#65

Understood. That's really useful. I'll stop there. Thanks.

Julien Dumoulin-Smith

analyst
#66

Hi, good morning, everyone. Thanks so much. I appreciate it.

Ralph LaRossa

executive
#67

Hi, Julien.

Julien Dumoulin-Smith

analyst
#68

Appreciate the chance to ask. Hello there, everyone, and thanks. So I'm just attempting to pull this discussion together and wrap it up a bit. Listen, you mention December, and after that January. There are numerous separate elements converging for you folks, correct? So you have the GSMP, you have energy efficiency, you have the rate case proposal, and you have PJM transmission. From what I heard in your remarks, you referenced December, most likely, and once more, you also touch on that fresh load growth update from PJM, December and January too. What I'd like to do is perhaps pose it more bluntly: what's your thinking on that rate base CAGR? In your comments again today, you stated specifically that the run rate sits at the lower end of it. A moment ago you told Jeremy, along with others, that you're seeing a newly elevated run rate. What's your take on that 6%+ rate base outlook? In what way does it align with the 5%-7%, and which components are we overlooking that feed into the culmination, so to speak, in January? It appears there are many positives, no equity, rate base CAGR at the bottom end, and clearly a higher run rate emerging. I'm simply attempting to connect all of this, if possible. That 5%-7%, I suppose.

Ralph LaRossa

executive
#69

Yeah, no, Julien, I'll let Dan take a shot at part of this as well, but I want to emphasize something. My apologies if I claimed we sat at the low end. I certainly did not, and saying that was not what I intended. If it came out earlier, that wasn't my intention. So we remain inside the range; that's what we've stated, and I'd concur with you that plenty of positive momentum exists here, yet nothing has been finalized; that's the reason we're in this position, and we'll hand you that information once we reach later in December regarding the two items I brought up, the EE and GSMP, and then more will come in January. But, Dan, anything you'd like to add?

Dan Cregg

executive
#70

No, I believe that covers everything, Julien. Regarding those figures, nothing new came out today. Today we did reaffirm them. As we move ahead, it has been a range, and it remains one; so PJM has given us some signal that there might be additional transmission spending. That's around $400 million. Through the BPU triennial process, we've also received some signal that EE might pick up somewhat. Honestly, GSMP was running at a higher rate, yet it fell short of what GSMP three was submitted for. So you'll have gains and losses. What I think we're indicating is that you will get that update in its entirety, and a few of those ranges will carry somewhat more detail, since we've gone through yet another set of months as we near the close of the year and shift into year-round.

Julien Dumoulin-Smith

analyst
#71

Understood. A few points to clarify, if that's alright. As I mentioned before, 6 to 7.5 — at minimum that 6% lower bound appears to require an increase by 2027. Would you be extending the plan out to 2028? And beyond that, more precisely, how are you thinking about the linearity — if we raise this topic once more — when it comes to earnings, not simply relative to 2023, but perhaps relative to a 2024 baseline, if you would?

Dan Cregg

executive
#72

Yeah, Julian, we stated 6 to 7.5, and that remains our position. So if you're attempting to move me above that figure, we're at 6 to 7.5. What we're merely attempting to accomplish is that as we progress, we'll provide guidance regarding how these items begin to appear. The filing for E hasn't happened yet, and we lack that conclusive response from PJM regarding that transmission. So I believe those will come afterward, and as we progress, that base will rise, and we'll require some additional capital as we lengthen the forecast horizon — it will need to increase somewhat. These are the sorts of things that will accomplish that. So I think you should regard it precisely as we laid it out. We're reaffirming those figures as we progress; we'll provide somewhat more detail on 2024 in December, and after that we'll transition to a longer-term update following the finalization of our plan overall.

Julien Dumoulin-Smith

analyst
#73

Great. Okay, everyone. We'll speak with you at that point. Best of luck. Talk to you before long.

Dan Cregg

executive
#74

Thank you, Julian.

Ralph LaRossa

executive
#75

Thanks, Julian.

Dan Cregg

executive
#76

Hello, Michael.

Michael Sullivan

analyst
#77

Hey, everyone. Hey, how's it going?

Ralph LaRossa

executive
#78

Hi, Michael.

Michael Sullivan

analyst
#79

Hi, apologies for pressing on this, but I just want to close the loop regarding the update on the year-end call. So, is it fair to say the earnings CAGR will cover 2024 to 2028? Is that correct?

Ralph LaRossa

executive
#80

That will happen around January. That is what we mentioned in the prepared remarks. We would provide that update at that point. Exactly.

Michael Sullivan

analyst
#81

All right. And roughly in line with what you presented during Analyst Day — regarding the nuclear segment, we ought to expect the nuclear PTC 4 level, with, you know—

Ralph LaRossa

executive
#82

That's right.

Michael Sullivan

analyst
#83

Anything else being... Okay.

Ralph LaRossa

executive
#84

Right. Yep.

Michael Sullivan

analyst
#85

All right. Then finally, regarding the credit aspect. I believe earlier in this week I noticed Moody's had taken a positive rating move or view concerning the power business. Is there any chance of looking into the consolidated picture there, and the way they could be evaluating your metrics and thresholds?

Ralph LaRossa

executive
#86

Yes, nothing that I — that we know about at the parent level. However, I'll say, once more, some solid efforts from Dan, his group, our treasury team, in clarifying what has occurred on our power side, and we felt quite pleased, and I'm grateful you noticed Moody's letter that was issued. So thank you for that. Yes, I believe what they did, Michael, was logical, correct? When you consider what nuclear used to be and what it is today, that PTC gives precisely the floor you're mentioning. Therefore we plan to keep discussing that in our figures, and nothing past that, but certainly that stabilization backs up precisely what Moody's did.

Michael Sullivan

analyst
#87

All right, excellent. Many thanks.

Carly Davenport

analyst
#88

Hi there, good morning. Appreciate you fielding these. The majority have already been covered, though I have a couple of brief, more administrative items regarding nuclear, if that's alright. The first: is there anything new on the nuclear PTC — any sense of when that might become clearer? And then second, is there anything worth mentioning at this point about the Salem 1 refueling outage, specifically regarding how things are going on both the schedule side and the cost side?

Ralph LaRossa

executive
#89

Sure, look, I'll handle that second item. Our folks keep doing outstanding work on it, and beyond a routine outage that lines up with what our business plan calls for, there's nothing else for us to bring up; so it's a nice chance for me to offer praise to the crew working there. Thanks for raising it, and Dan will address the PTC portion.

Dan Cregg

executive
#90

Sure, I'd say Treasury is doing great work down there as well, but they aren't giving us updates on a specific date, so we don't have any real detail about when it might happen, except to keep stressing that earlier would be preferable to later, but we still haven't gotten any response.

Carly Davenport

analyst
#91

That's helpful context, thank you. I won't push further on that.

Dan Cregg

executive
#92

Thank you, Carly.

Ralph LaRossa

executive
#93

Thank you, Carly.

Travis Miller

analyst
#94

Hi, everybody. I appreciate it.

Dan Cregg

executive
#95

Hi there, Travis.

Travis Miller

analyst
#96

Just briefly, I want to ask about capital expenditures. That figure of $200 million — would you describe it as fresh initiatives? Does it reflect cost increases on what's already underway, or money moved up from later periods? I'd appreciate it if you could shed some light on that quickly.

Dan Cregg

executive
#97

Yes, Travis, my sense is that what's happening there is our group has done an excellent job completing the tasks laid out before them, and on a few items they've gotten out in front. That is essentially, picture it as simply having portions of the effort finished somewhat faster than we'd expected, and we'll come back with a fuller picture down the road.

Travis Miller

analyst
#98

Alright. Does any of that end up spilling out of 2024, or is there no connection there?

Dan Cregg

executive
#99

No — well, my take would be that perhaps that isn't the right frame for you. Still, once we provide an update, you'll see how things shake out. That's because a portion of 2025 might shift backward into 2024; things stay somewhat in flux as they move ahead, and should they be running ahead of where they stand today, you might see additional items return to 2024. So I wouldn't frame it as a cut to 2024. I'd frame it as simply completing a bit more work sooner, and we'll keep reconciling that as things move ahead. One more point from me: what I said earlier also signals considerable appetite when it comes to energy efficiency, and we've kept growing in that area. So everything lines up with what I said about the Triennial and the backing we receive from the BPU.

Travis Miller

analyst
#100

All right, that’s useful. Then here’s a broader one: offshore wind. I realize you’ve stepped away from that business, but clearly there’s plenty happening in New York. Are you picking up anything from regulatory talks, from political circles, anything at all regarding New Jersey’s offshore wind efforts?

Ralph LaRossa

executive
#101

No, no.

Travis Miller

analyst
#102

—liability?

Ralph LaRossa

executive
#103

Yeah, no, I mean, look, we're just — we're reading what you're all reading; and again, just happy with the decision that we made at this point.

Travis Miller

analyst
#104

Okay, that's everything from my side. Appreciate it.

Ralph LaRossa

executive
#105

Thanks. Thanks,

Anthony Crowdell

analyst
#106

Hello, and good afternoon to you, Ralph. Also, good afternoon, Dan.

Ralph LaRossa

executive
#107

Hi there, Anthony.

Dan Cregg

executive
#108

Good afternoon there, Anthony.

Anthony Crowdell

analyst
#109

Wishing you a happy Halloween, Ralph.

Ralph LaRossa

executive
#110

I simply was hoping to— Ralph LaRossa: And a happy Halloween to you.

Anthony Crowdell

analyst
#111

Sorry about this — just a quick process question. There's the rate filing in December, and then we receive 2024 guidance, the earnings guidance, in December, plus a small CapEx update. After that, on the 4Q call, we get a refresh on rate-based CAGR and earnings growth CAGR. Is that right? Did I catch that properly?

Dan Cregg

executive
#112

That's roughly the pattern we're anticipating. I'd rather not commit to an hour a day, but yes, that's the pattern we're anticipating.

Anthony Crowdell

analyst
#113

Got it, thanks. Quick one from me — earlier on this call you mentioned the financing and possibly some interest rate hedges. You've already handled a bond maturing in November, I believe. Another one comes due in June of next year, I think, and it carried an appealing 2.9% rate. Does that one sit inside your hedges, or how do you intend to handle that maturity?

Dan Cregg

executive
#114

Sure, we'll address that when we get there. Anthony, the key point, I'd say, is that back in November, when we provided that update, we assumed rates — spreads included — fairly similar to today's levels. We didn't lock in each and every dollar, but the gap, I'd argue, between our assumption and the current market sits inside the range. So I think we've positioned ourselves well ahead of it, and we will address it. As with many of our refinancings, flipping them will bring somewhat higher rates, though our forecast already reflects that.

Anthony Crowdell

analyst
#115

Great. Then finally, may I follow up on what Mike asked about earlier regarding that outlook revision for PSEG Power over at Moody's? I mean, do you have any thoughts about possible shifts at the parent level? As I understand it, Baa2 for PSEG Power, and you know, the balance sheet there is stronger. The utility also has, you know, a strong balance sheet. Is there any read-through on, you know, perhaps your interest in moving PSEG Power — sorry, the parent — up to a Baa1?

Dan Cregg

executive
#116

Yeah, I mean, when you take a look at that situation, the rating on power wasn't moved by them. It's only a positive outlook in that case. And so I think the ripple effect, as you look at the parent, would be lesser; but all things considered, it's just that if you consider the overall mix of the business, and how it reflects PTCs and what we've done from, from an overall set of strategic decisions, I think going forward we're in a better position.

Anthony Crowdell

analyst
#117

Great. Thanks for taking my questions.

Dan Cregg

executive
#118

Thanks, Anthony.

Carlotta Chan

executive
#119

Operator, we'll take our last question.

Carlotta Chan

executive
#120

Sorry.

Ralph LaRossa

executive
#121

Right, no. Thanks so much, and apologies — there was a lot of interest, but unfortunately we needed to keep things moving. Look, I simply want to express gratitude to everyone for the interest you keep showing. What our team keeps delivering astonishes me. I'm genuinely pleased about the stability and the certainty we've built here. Some internal information went out earlier today, and the sheer number of items we keep getting done is remarkable, so let me point to just a handful of them here. One, for instance, was that gas system monetization plan and the effort we finished. We keep getting acknowledged through awards, various recognitions from best employers and best companies to work for; we brought gas bills down once more for customers, starting October first, and we brought fresh faces onto our board of directors. So these are things plenty of people often find difficult, yet we appear to deliver them again and again. So huge thanks to our team. I hope you sense it, not just from how we sound, but from others too, that we're a company you can rely on, and we're getting done the work we promised. And one last note — Anthony mentioned it, but Happy Halloween to everybody. May all of you have a Halloween that's safe and healthy, and not only for you, but for your families as well. Have a great day. Take care.

Operator

operator
#122

Everyone, that brings an end to today's teleconference. At this point, you're free to hang up your lines. We appreciate you taking part.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Public Service Enterprise Group Incorporated transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Public Service Enterprise Group Incorporated earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Public Service Enterprise Group Incorporated or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.