Public Service Enterprise Group Incorporated (PEG) Earnings Call Transcript & Summary

April 30, 2024

New York Stock Exchange US Utilities Multi-Utilities earnings 58 min

Earnings Call Speaker Segments

Carlotta Chan

executive
#1

Hello, everyone, and thanks for joining us for PSEG's presentation of results for the first quarter of 2024. With us on this call are Ralph LaRossa, our Chair, President, and CEO, along with Dan Cregg, our Executive Vice President and CFO. You can find the press release, the attachments, and the slides for what we'll cover today on our investor relations site, investor.pseg.com, and our 10-Q is going to be filed later on today. Within PSEG's earnings release, as well as other topics we'll address on this call, there are forward-looking statements and estimates that carry a variety of risks and uncertainties. Our discussion will touch on non-GAAP operating earnings, which is not the same as net income reported under generally accepted accounting principles in the United States. Reconciliations of our non-GAAP financial measures, together with a disclaimer about forward-looking statements, appear on our IR website and in today's materials. Once the prepared remarks are finished, we'll hold a question-and-answer session lasting 30 minutes. At this point, I'll hand the call over to Ralph LaRossa.

Ralph LaRossa

executive
#2

Thanks, Carlotta. Morning, everyone, and I appreciate you being here as we go over what PSEG delivered in the first quarter of 2024. On the financial side, our results for that quarter match what we projected for the whole of 2024, so we're restating our non-GAAP operating earnings guidance at $3.60-$3.70 per share. We're also still carrying out our long-range plan to expand PSEG's non-GAAP operating earnings at a rate of 5%-7% through 2028, and we're restating that figure today as well; getting there means putting money into energy infrastructure and energy efficiency programs, which back more electrification of transportation, homes, and workplaces, all while cutting greenhouse gas emissions and helping our customers keep their bills down. Turning to what happened in Q1 2024: PSEG's net income came in at $1.06 per share, compared with $2.58 per share during 2023 — a gap that stems from mark-to-market gains having boosted that quarter's GAAP earnings a year ago, while nothing comparable exists today. For non-GAAP operating earnings, the figure was $1.31 per share this quarter, lower than the $1.39 per share recorded in 2023. Bear in mind that the non-GAAP numbers exclude those items spelled out in attachments 7 and 8, both of which come with the earnings release. The quarter's main driver was continuous rate base expansion tied to infrastructure replacement investments, even as greater investment-related expense created a drag. Those expenses will accumulate across the rest of 2024 while we wait for our pending distribution rate case to be resolved later this year; separately, the nuclear production tax credit took effect on January 1, 2024, giving our nuclear fleet downside price protection through 2032, a key reason PSEG's results are becoming more predictable. Dan will walk through the financials in detail later on the call, but for PSEG Power and Other, I want to flag that some margin contribution will lean toward the back half of 2024, since we anticipate realizing the bulk of 2024's gross margin increase over 2023 in that second half. Turning to operations, we're pleased to report that operational excellence continues to be evident in both our utility and nuclear segments. When severe rain and wind storms struck earlier in the year, PSE&G and PSEG Long Island stepped up, restoring power quickly for tens of thousands of customers. Meanwhile at PSEG Power, the nuclear fleet also turned in a strong quarter, reaching a 96.8% capacity factor and supplying New Jersey and the surrounding region with more than 8 TWh of dependable, carbon-free baseload energy. Turning to the rate case we still have outstanding: this is our joint electric and gas base distribution filing, and it represents 57% of our rate base. At the BPU, things are proceeding as we expected. We're currently in the discovery and documentation stage, responding to information requests from the parties involved, and we've just submitted updated test year financials. Written into the procedural schedule are multiple weeks reserved for settlement talks, which get underway later in the second quarter. Based on both recent and historical rate case outcomes, we anticipate this one will be resolved at some point later in 2024. First, a quick note for everybody: this filing, which covers electric as well as gas, is asking for an overall revenue increase of 9%. If you look at a typical residential customer who receives both electric and gas service, the increase we're proposing comes to 12%, which amounts to less than 2% compounded annually over this six-year period. During those same six years, we've continued to perform strongly on our reputation for reliability and affordability, along with customer satisfaction scores that place us at the top nationally. With a relentless focus on keeping costs down, PSEG continues to manage its O&M so that customer bills remain as low as possible, and we still compare favorably with regional peers for residential, electric, and gas service, while ranking among the lowest in the country on a share-of-wallet basis. Moving on to how we're investing capital: we still expect to execute the five-year plan at PSEG, spanning 2028 and totaling between $19 billion and $22.5 billion. Within that overall program, the regulated portion accounts for $18 billion to $21 billion, and it's focused on swapping out infrastructure as well as our Clean Energy Future EE initiative. Out of the 2.3 million smart meters targeted under our AMI program, about 1.8 million have now been installed and put into service by PSEG — completion remains slated for the end of the year, with both timeline and cost staying as planned; from these investments, we anticipate rate base compounding annually at 6%-7.5% over the course of 2024 through 2028. This assumes PSEG had a rate base of $29 billion at the close of 2023 — a figure that was up 10% compared with the year before — and we continue to look for possible investment chances that could drive regulated growth down the road. One area we're assessing right now involves competitive transmission requests for proposals in the Mid-Atlantic, much like the $424 million project PSEG won through PJM's 2022 Window 3 process. PSEG filed bids in April of 2024 with the New Jersey Board of Public Utilities, also known as the BPU, for its pre-build infrastructure project tied to offshore wind. The BPU is anticipated to reveal which bidder or bidders prevail in that pre-build infrastructure solicitation during the latter half of 2024. On top of that, PSEG is reviewing two additional regulated transmission solicitations expected to arrive this July. Two solicitations are underway. One comes from the BPU — its second public policy request for offshore wind transmission infrastructure, run through a State Agreement Approach. The other is PJM's 2024 Regional Transmission Expansion Plan Window 1 solicitation, and it should factor in the effects of stronger load growth projections, shaped by rising electrification expectations along with data center load growth across PJM. Meanwhile, at PSEG Power, our nuclear fleet is chasing several growth avenues that require only modest capital spending. We've already discussed our intentions regarding thermal upgrades at the Salem Nuclear Station — upgrades that might add as much as 200 MW of capacity and, under existing rules, would meet the criteria for clean hydrogen tax credits on both additionality and hourly matching. PSEG Nuclear has told the Nuclear Regulatory Commission it plans to seek another 20 years of license renewals for its trio of New Jersey reactors. Under that scenario, the operating lives of Salem Units One and Two and Hope Creek would extend beyond 2036, 2040, and 2046, reaching 2056, 2060, and 2066 respectively. Beyond those nuclear options, recent discussion has touched on the idea of selling electricity straight to data centers from Artificial Island, where 3 units are located. During the last several months, our discussions have spanned both sides of the meter. On one side, PSEG has received new business inquiries regarding mid-sized data center construction in the range of approximately 50 to 100 megawatts. On the other side, there have been behind-the-meter inquiries concerning co-located facilities that place a high value on baseload power that is highly reliable and carbon-free, sourced from facilities already in existence, with none of the challenges associated with generation that cannot be dispatched. For a considerable period, PSEG has positioned itself in step with New Jersey's policy objectives. A connection between economic development and energy policy may emerge from this data center opening, and as New Jersey recently moves to establish an in-state artificial intelligence hub, we stand prepared to support that effort. In New Jersey, our nuclear facilities might provide a very dependable, emissions-free baseload power source, along with infrastructure that big data center builders and hyperscalers increasingly view as essential. One thing we know for sure at this point is that any of these nuclear possibilities would be additive to the 5%-7% growth rate guidance we've projected for the long term through 2028, tied to that PTC threshold price. Another factor that distinguishes PSEG overall is that having nuclear operations allows the company greater leeway to finance its existing regulated investment plan without selling assets or issuing additional equity. In closing, I'd like to express our appreciation to the team for all their efforts and their commitment to safety, dependability, and the people we serve. At this point I'll pass things over to Dan, who will walk everyone through the financials and guidance in more depth, and after he wraps up, I'll be available to take your questions.

Dan Cregg

executive
#3

Thanks, Ralph, and good morning, everyone. During the first quarter of 2024, PSEG recorded net income of $1.06 per share, compared with $2.58 per share in 2023, as Ralph mentioned earlier. Our operating earnings, on a non-GAAP basis, were $1.31 per share in Q1 2024, compared with $1.39 per share in 2023; details on the contribution each business made to non-GAAP operating earnings per share for that quarter can be found on slide 7... A waterfall chart on slide 8 takes you through the net quarter-over-quarter changes in non-GAAP operating earnings per share for our main businesses. Start with PSE&G, which posted first-quarter net income of $0.98 per share in both 2024 and 2023. For the first quarter of 2024, PSE&G reported non-GAAP operating earnings of $0.98 per share, compared with $0.99 per share in 2023. The main factor behind both net income and non-GAAP results in this quarter was growth in rate base tied to continuing investments in replacing infrastructure. That was partially offset by higher depreciation and interest expense connected to distribution investment that current rates do not yet recover, as well as increased O&M costs. Compared with the first quarter of 2023, overall margin came in $0.07 higher, with transmission contributing $0.03 per share, gas margin contributing $0.01 per share, and other utility margin contributing $0.03 per share. For distribution O&M, we saw a per-share increase of $0.05 compared with 2023's first quarter. The main drivers were inspections of gas meters and corrective overhead maintenance work following heavy rain, wind, and flooding earlier in the year, along with tree trimming. Depreciation went up $0.01 per share, and interest rose $0.03 per share, both relative to the first quarter of 2023, reflecting our ongoing investment growth; we're awaiting recovery of those costs through our distribution rate case, which should conclude later this year. Lower pension and OPEB income — a result of OPEB-related credits ending in 2023 — created an unfavorable $0.01 per share comparison against the prior-year quarter. Finally, tax timing recorded through an annual effective tax rate, which nets to zero across a full year, delivered a net favorable impact of $0.02 per share this quarter versus 2023. Weather in the first quarter, measured in heating degree days, ran 17% warmer than normal yet 9% colder than the first quarter of 2023, which stands as the warmest first quarter in PSE&G's records. As noted before, the Conservation Incentive Program, or CIP, curbs the effect of weather and other sales variances, whether positive or negative, on electric and gas margins, while assisting PSE&G in broadly encouraging uptake of its energy efficiency programs. Looking at our customer numbers for both electricity and gas — the metric that drives margin under the CIP framework — those grew by about 1% over the last twelve months. Turning to capital spending, PSE&G deployed roughly $800 million during Q1, just as Ralph mentioned, and we remain on schedule to execute the $3.4 billion regulated capital investment plan we laid out for 2024, which focuses primarily on modernizing infrastructure and electrification efforts. That includes upgrades and replacements across our T&D facilities, last-mile expenditures through the Infrastructure Advancement Program, continued spending on gas infrastructure replacement, Energy Strong II investments, along with an ongoing expansion of clean energy investments in energy efficiency, smart meter deployment, and EV make-ready infrastructure. We are also reconfirming our five-year regulated capital investment plan totaling between $18 billion and $21 billion. The 2024 to 2028 plan includes the $3.1 billion CEF-EE II filing submitted in December 2023, which would allow commitments to begin January 2025 and run through June of 2027, in line with the BPU's EE framework, with investments spread across a six-year period. Resolution of this proceeding is anticipated at the BPU later this year. Turning to PSEG Power and Other. PSEG Power and Other posted net income of $0.08 per share for the first quarter of 2024, versus $1.60 per share in the first quarter of 2023. non-GAAP operating earnings came to $0.33 per share for the first quarter of 2024, against non-GAAP operating earnings of $0.40 per share for the first quarter of 2023. Net energy margin for the first quarter of this year improved by $0.03 per share, which included a $0.02 favorable contribution from nuclear, driven by the net impact of the nuclear production tax credit that took effect January 1 of this year, partly offset by a reduction in capacity revenue. Within energy margin, gas operations also rose by $0.01 per share versus the year-earlier quarter. For 2024, it matters that even though the PTC begins this year, our quarterly results are going to take a certain shape as the months go by. Given how our underlying hedges are structured, we anticipate capturing most of the improvement in 2024 gross margin relative to 2023 gross margin in the back half of the year. That's a different pattern than last year, when PSEG Power captured the bulk of the annual hedge price step-up in Q1, reflecting cheaper pricing during winter 2022 versus 2023. O&M was up $0.03 per share, largely because we began the planned refueling outage at Hope Creek, our 100% owned nuclear plant. We saw a $0.01 hit from interest expense, driven by elevated rates, though that was partially balanced out by reduced short-term borrowings. On taxes and other items, there was a $0.06 per share negative variance versus Q1 2023, largely because a higher effective tax rate was applied this quarter—a situation that will unwind during the remainder of 2024. Turning to operations, the nuclear fleet generated roughly 8.2 terawatt hours in the first quarter of 2024, down from 8.4 terawatt hours a year ago, with a capacity factor of 96.8%. At our Hope Creek Nuclear Unit, a planned refueling outage is now underway, and it will involve some initial activities related to the fuel cycle extension project. So because Hope Creek is a unit we own entirely, an outage there always means the same thing: somewhat elevated O&M and reduced generation during Q2. Now, a few updates on financing from recently. When March ended, PSEG had $5 billion of total available liquidity, and $1.2 billion of that was cash on hand. In Q1, the revolving credit facilities we hold, which add up to $3.75 billion, got a 1-year extension, so they now mature in March 2028. By the end of March, PSEG had $500 million still owed on a 364-day variable rate term loan that came due in April 2024, and PSEG Power had $1.25 billion remaining on a variable rate term loan set to mature in March 2025. Every one of those term loans was converted from variable to fixed through swaps, which reduces exposure to interest rate swings. At March's end, our variable rate debt stood at a minimal level thanks to those swaps and our cash position. During the first part of March, PSE&G sold $1 billion in secured medium-term notes across 10- and 30-year maturities, split between $450 million at 5.2% maturing March 2034 and $550 million at 5.45% maturing March 2054. A portion of those funds was used to settle $250 million in 3.75% secured MTNs that came due on March 15. Then, during the same month of March, PSEG brought $1.25 billion of senior notes to market: $750 million carrying 5.2% and maturing in April 2029, plus $500 million carrying 5.45% and maturing in April 2034. Some of that money will be applied to retire $750 million of 2.875% senior notes when they mature in June, and our investment grade ratings remain strong. Going ahead, we believe PSE&G's substantial cash generation, combined with the improved cash flow visibility PSEG Power gains from the nuclear PTC, will enable PSEG to carry out its five-year capital spending plan — which is mostly regulated CapEx — with no requirement to issue new equity or divest assets. Wrapping up, I want to restate that PSEG is holding to its 2024 full-year non-GAAP operating earnings outlook of $3.60 to $3.70 per share. That figure captures the ongoing rate-based expansion coming from regulated investments we currently have underway, with those gains partly offset by depreciation and interest costs that are set to rise across the rest of 2024 while we wait for our distribution rate case to be resolved later in the year. On top of that, we're confirming our projection of 5%-7% compound annual growth in non-GAAP Operating Earnings over the long term, running through 2028, which our capital investment programs and the new nuclear PTC underpin. That concludes our prepared comments, and now we're ready to take your questions.

Nick Campanella

analyst
#4

Morning, everybody. Appreciate you fielding my questions today.

Dan Cregg

executive
#5

Morning to you as well, Nick.

Nick Campanella

analyst
#6

Hi there. I appreciate the background you provided regarding the opportunities for direct power sales involving your nuclear facilities. Could you share your thoughts on the possible timing for any announcement, and also how we ought to view when that might add to EPS assuming it came together? Also, you know, I realize you mentioned being at the intersection of economic development and energy policy. So is there anything specific you need from the state before you proceed with this? Or what information should investors watch for to determine whether this is turning into more of a reality? Thanks.

Dan Cregg

executive
#7

Yes, Nick. So here's how I see it: the key takeaway for us is that we view this simply as us continuing to follow the state's policy rather than establishing it ourselves. I believe the governor has made it quite clear that he wants to bring AI jobs into New Jersey, and data center infrastructure along with other IT assets are things he wants put in place. As for when something like this happens, I think multiple factors drive that, correct? The hyperscale data centers have their own schedules, so I won't speak on their behalf, and I won't get ahead of the governor regarding matters he might or might not be pursuing. Our role is to provide support, and on the question of timing, from an overall perspective, I would simply track what the state announces and the policy efforts tied to this initiative.

Nick Campanella

analyst
#8

... All right, I appreciate that. I suppose, you know, I believe you also mentioned during your prepared comments that an update might come later on in the fall. I suppose that would hinge on how the rate case sort of moves along; but if you're providing, you know, a refreshed sort of financial outlook, you know, at what point would that happen? And beyond that, could the data center opportunity be part of that, or would it truly sort of come after that 25 and beyond?

Ralph LaRossa

executive
#9

Yeah, Nick, I believe those are really sort of a few separate components there, correct? So we'll roll forward later in the year as we roll forward each year. I believe we kick off with the CapEx and some other items at the end of the year, and then our earnings at the beginning of next year. But regarding the data center specifically, we're not going to alter our plan. You know, power remains a very small portion of this company's earning stream. It is all upside, so I get the attention to it. But what we'll do is we'll fold in any PPAs, whether that be on data centers or hydrogens opportunities or anything else that we have down at the plant. We'll optimize it, and once we agree on terms around something like that, we'll fold it in and be transparent about it. But at present, our plan as we look forward is to continue to project ourselves out based upon that PTC floor.

Nick Campanella

analyst
#10

That seems reasonable. I'm very grateful for the opportunity to talk. Thank you.

Ralph LaRossa

executive
#11

Thank you, Nick.

Jeremy Tonet

analyst
#12

Hi, good morning.

Ralph LaRossa

executive
#13

Good morning, Jeremy.

Jeremy Tonet

analyst
#14

I just wanted to ask about something outside the data center topic. You've been paying close attention to what states and regions need for transmission when it comes to offshore, and with data centers now part of the picture and having an outsized effect, how do you expect the transmission system to evolve overall, and what role do you see PSEG playing in that?

Ralph LaRossa

executive
#15

Yeah, Jeremy, I think it's really... What I'd tell you is to watch the PJM RTEP process extremely carefully. As they keep reassessing how the transmission grid is laid out, I believe there will be chances throughout the PJM footprint. Take Talen, for example — it's a pretty clear-cut case. That generating facility was connected to the Susquehanna-Roseland circuit. A chunk of that electricity, roughly 100 MW at minimum, won't be moving out of the plant and onto the grid anymore, which changes the topology, to keep it simple. On top of that, data centers keep popping up in different spots. Our utility has received quite a few applications that we're working through — not hyperscale-sized, mind you, but more along the lines of smaller edge computing setups. Each of those items will have some impact, and the spot where everything converges—I'd suggest you check it out—is the RTEP process. Offshore wind is going to be among the generation options for that, though the grid will also require further adjustments, and none of us knows yet what those will be.

Jeremy Tonet

analyst
#16

Understood. That helps. And stepping back to look at the bigger picture, when it comes to designing tariffs so they don't put a burden on other ratepayers — I'm curious whether you have any further perspective there. I suppose it's about ensuring this gets built out in a manner where additional burden doesn't fall on other ratepayers.

Ralph LaRossa

executive
#17

Sure. So, consider a behind-the-meter option: the way you keep ratepayers protected in that case is that no extra infrastructure fees would apply, meaning they wouldn't carry added infrastructure costs — unless new generation is brought online and we... Well, it must be delivered to the grid, and there are various routes for that. In today's PJM market, those interconnection agreements are how cost allocations get worked out. So in my view, that's handled in a quite equitable and open manner. And as I see it, for in-front-of-the-meter data centers or loads that keep emerging, each state arrives at its own answer. Those are state-specific tariffs, and I suppose each state will evaluate it through an economic development lens and decide how it wishes to proceed. That said, in New Jersey we haven't observed any shifts to the tariff requirements for new business expansions.

Jeremy Tonet

analyst
#18

Understood, that answers my question. I won't take up more of your time. Appreciate it.

Durgesh Chopra

analyst
#19

Hello, everyone, good morning. I appreciate you making room for me.

Ralph LaRossa

executive
#20

Good morning, Durgesh.

Durgesh Chopra

analyst
#21

Hi there. Morning, Ralph. Dan, is there anything new regarding the nuclear PTC and the guidance we're expecting from the IRS? It feels as though we've been waiting an eternity for it. And then, what effects do you anticipate that guidance will have on your financial plan?

Ralph LaRossa

executive
#22

Durgesh, I wish my response could be more helpful, but guidance from Treasury is still something we're awaiting. I'm aware that many different methods have been made to Treasury in an effort to get some details released. But I'm sure you're aware that the PTC kicked off on January first, so we're in it now.

Dan Cregg

executive
#23

..; and I remain of the view that the key definition — the one we've all been mulling over — is what counts as gross receipts. That's the thing we're awaiting above all else. I believe we're, you know, progressing, learning a bit more about how 2024 is shaping up with each passing day in 2024. And we keep doing what we've been doing, attempting to consider what various possible results might emerge from Treasury, and attempting to place ourselves as well as we can given that uncertain environment. And I think we're managing okay on that front, though we'd rather have it. A date isn't something I can give you. An estimated date isn't something I have either, and I haven't heard that one is coming soon. I think we're in the same situation, Durgesh. I think we're simply waiting.

Durgesh Chopra

analyst
#24

Thanks for that detail. It sounds as though you're laying out a few different scenarios, and you've sort of incorporated both the risk and the upside into the 2024 guidance you've given. Would that be a fair characterization, Dan? Yeah. Yeah, I'd say that's precisely correct.

Dan Cregg

executive
#25

All right; and then, you previously had this really helpful chart you'd show, I believe it might be somewhat out of date at this point, that laid out the capacity of your balance sheet when it comes to, you know, financing additional or greater CapEx, and you have all this opportunity, be it transmission, you know, linked, or on the nuclear front, I realize that one will be capital light; but broadly at the utility, be it energy efficiency, be it the transmission opportunity, could you just give us a feel for, and the CapEx plan was lifted not long ago, correct? In December, 13% above the previous five-year. So perhaps you could give us a feel for how much additional capital the balance sheet could absorb with no equity issuance, if there's a way to accomplish that? Thanks, Dan. Yeah, you know, we have discussed this, and it will come off of the FFO to debt. And I believe that, you know, one item is that when that capital increase you mentioned did appear, the implications for FFO to debt differ, based on precisely what that capital consists of. And sort of at the two extremes, our energy efficiency program carries a recoverable life, depreciable life, amortizable life, whatever term you prefer, of, you know, nearer to 10 to 12 years, whereas our investments that lean more toward infrastructure have a longer recoverable life; so when you examine those specific investments, you'll observe a far smaller effect on your FFO to debt, since you'll see plenty of cash returning to you more rapidly to the degree that it's EE benefits, versus something that's more steel in the ground, whether that's on the transmission side or the electric or gas side. And then, you know, regarding your other point, I completely agree with what you said that on the power side, it would be capital light, yet it could be FFO positive in a rather substantial way. So those are the pieces that shift around. If we're in the mid-teens, our present threshold for where we stand is 13, 14, depending on whether you mean Moody's or S&P; so, we have some room there, but I think it's not a..; it will hinge somewhat on what kind of investment it is; and I think as you witnessed more of that increase originating from EE recently, it was more credit-friendly for us to head in that direction.

Durgesh Chopra

analyst
#26

That's useful. Thanks. I appreciate you taking the time.

Dan Cregg

executive
#27

Thanks.

Analyst

analyst
#28

Morning, everyone. This is Constantine, sitting in for Shar. Appreciate you letting us ask a few things.

Dan Cregg

executive
#29

Constantine, hey there.

Analyst

analyst
#30

Yeah, I truly value what you shared regarding the nuclear possibility. Perhaps some added subtlety here. In your view, does behind the meter represent something that can grow at scale for data centers located in New Jersey, or does it feel more like a singular situation when you examine it? And possibly, like you brought up, there exists some degree of possible reliance on the grid, and do you think that turns into a worry at all for regulators, or is that sort of being resolved through different channels, regulatory channels?

Dan Cregg

executive
#31

Yeah, look, the grid. Let me work backward on that one. That reliance on the grid, Constantine, I believe is, it isn't only data centers, correct? We observe electrification happening everywhere, and as policymakers keep heading that way, we must stay mindful and ensure the system gets constructed properly. I believe it's being addressed through several paths; it's being addressed at FERC. It will get addressed within every single state, yet there are numerous routes for such discussions to occur and to hold the cost borne by customers as low as possible. So no worries regarding that; when it comes to the scalable aspect, I'm going to hand it over to Dan, since his group does considerable work on the commercial side. I'll simply set it up that there are, you know, there are various angles from which to view it, and Dan's group is doing an excellent job engaging with numerous parties and evaluating numerous options, and he can provide you with additional specifics on that. Yeah, Constantine, that's a wonderful question, but it, if I attempt to consider precisely the character of how you're posing it, I believe by definition, if you're going to pursue something behind the meter, you're going to pursue it at scale. And so I believe that, you know, you wouldn't enter that scenario with something lacking scale and expand at that scale, aside from the obvious reality that I think you won't get a data center of scale showing up right away; and so it's more probable, and based on what we've observed, you'd see something agreed upon as being of scale that would arrive gradually. And so if you — if that fits your meaning of scalable, meaning it will expand as you move forward through time, I believe the response would be affirmative, but I believe you'd want to establish all of that properly from the very start. Yeah. And Constantine, the sole item I'd tack onto what Dan stated, just a reminder, you know, the position we occupy-

Ralph LaRossa

executive
#32

In terms of geography, it's a fantastic location, but I want to make clear to everybody as well that ours is the sole merchant site featuring 3 units on it. So scaling there works a bit differently, and being able to support the supply side is quite different too. That's why we're genuinely thrilled about any of those possibilities that could emerge later on down the line.

Shahriar Pourreza

analyst
#33

Thanks. That's very clear. Perhaps, taking a broader view of supply and demand across power markets and the prices for power, which for the 2025 and 2026 strip are now significantly above the PTC levels — and those PTCs, you know, remained essentially the central planning assumption. As you recontract or begin to recognize those revenues, do you intend to update guidance? And do they turn accretive to the credit metrics and the investment capacity you mentioned before?

Dan Cregg

executive
#34

Yeah, I'd say that if the way we view things shifts and what we're observing holds and is locked in for some period, such that we can make a statement about it, that strikes me as a sensible moment for us to act. Constantine, you've watched these markets for a very long time. You're aware they rise, they fall, and they move in cycles; therefore, at a moment when they're elevated, our aim is to be more predictable and to step forward to investors and tell them what they can rely on, and where upside opportunities exist, to discuss them, yet not let that be baked in before it's real; we're attempting to keep everything grounded, so my feeling is that with that approach, you'll likely see that from us as you keep moving forward.

Shahriar Pourreza

analyst
#35

Great. That's the kind of issue you don't mind having.

Ralph LaRossa

executive
#36

Right, and one thing to keep in mind, Constantine — the PJM West Hub, being so liquid and in plain sight, doesn't automatically mirror the whole PJM market. So those figures aren't exactly right for everyone.

Shahriar Pourreza

analyst
#37

Completely reasonable. Thanks for making room for me today. I appreciate it.

Dan Cregg

executive
#38

Thank you.

Carly Davenport

analyst
#39

Morning, everyone. Appreciate you letting us ask.

Dan Cregg

executive
#40

Morning, Carly.

Carly Davenport

analyst
#41

Thanks for all the information up to this point. Turning to the Hope Creek outage, you said some initial work is underway there related to the fuel cycle shift during that outage. Could you describe the scope of what is being completed and how much will remain before that transition happens as we reach 2025?

Dan Cregg

executive
#42

Sure, Carly — what is happening right now is only one very small portion of the overall picture. A great deal of engineering effort is taking place. Work is also being performed on a generator rewind that came with this outage. We have an upgrade in progress; essentially we are removing some old insulation from the cooling tower, and that gives us roughly 8 MW of extra capability. These are minor individual items, I would say, yet they genuinely assist us under certain weather conditions and given the rates that are required. So there is considerable effort going into optimizing the unit in preparation for that fuel change we will undertake later on. The investments at Hope Creek will occur across the next couple of fuel cycles, and after that we will be prepared for the final switch to the 24-month cycle.

Carly Davenport

analyst
#43

Understood. All right, that's useful. Then perhaps you touched on it briefly — you know, elevated O&M tied to the Hope Creek outage — and earlier you spent a moment discussing certain storm activity you had to deal with in the early part of this year. Any perspective on how O&M across the entire year might move relative to the prior year, keeping those early variables in view?

Dan Cregg

executive
#44

Yes, Carly, it could come in somewhat higher. You know, it's amusing — we spoke briefly about weather during the earlier comments, and the winter turned out fairly mild, yet extremely wet, and we faced storms that weren't so much driven by temperature as by precipitation. So a portion of that pushed costs up somewhat, and so did... You know, whenever a Hope Creek outage occurs, it's 100% owned, so the effect there is somewhat larger. Certain years that happens, certain years it doesn't. So that will show up on the power side; but truly, the storms ranked among the factors behind the first quarter's O&M impact.

Carly Davenport

analyst
#45

Understood. All right, that added context is helpful — thank you.

Dan Cregg

executive
#46

Thank you.

Dan Cregg

executive
#47

Good morning, Andrew.

Andrew Weisel

analyst
#48

Hello, and thanks for filling us in on the nuclear side of things. If I may, I'd like to push you for a little more detail so I can get a sense of the scale of this opportunity. How much nuclear generating capacity do you currently have that isn't already committed to state programs like the ZECs or to other obligations? To put it another way, how many megawatts could realistically be set aside for a completely new dedicated customer?

Dan Cregg

executive
#49

Sure, Andrew. I'd say you can point to what took place at Talen as a rough benchmark for the unit sizes that hyperscalers have in mind. One quick note — our state plan is scheduled to wrap up around May 2025, correct? So at that location, I don't anticipate a data center getting constructed ahead of May 2025. It's possible we'll be talking with interested parties and could share news earlier, yet I don't anticipate electricity actually being delivered to a data center prior to May 2025, which is when that program concludes. After that, well, we'll find out what the IRA's provisions dictate and how the PTCs apply to whatever sorts of arrangements get worked out.

Andrew Weisel

analyst
#50

All right, so you're figuring that the whole set of assets can be put to use?

Ralph LaRossa

executive
#51

... My view is that long-term agreements could cover all of the portfolio; and once more, that would depend on a variety of possible situations.

Dan Cregg

executive
#52

No, I wouldn't say anything here amounts to a limitation, and we'll keep pushing ahead while making sure you're kept informed.

Andrew Weisel

analyst
#53

All right, excellent. I simply wanted to get that cleared up. Then, moving on to the utility's energy efficiency segment, the EE2 initiative that you submitted in December requires $3.1 billion in expenditures, which is far larger than the initial program at roughly $1 billion. Could you explain a few of those factors behind why every additional kilowatt hour of savings costs so much more? And perhaps even more significantly, are you encountering any resistance from the BPU or important stakeholders, or is this entirely comprehended and backed?

Ralph LaRossa

executive
#54

Yes, Andrew, the reason the cost per megawatt saved increases is fairly straightforward, correct? I mean, you begin with swapping out light bulbs, which was the initial initiative we launched long ago, along with adjusting thermostats, and now you're modernizing HVAC equipment and expanding into commercial and industrial activities. So from the perspective of dollars per megawatt hour saved, that's quite a different situation. Regarding the resistance, you know, all of this formed part of the BPU's triennial process; therefore much of what was presented stemmed from the requirements recognized by the Board of Public Utilities, and truly isn't unexpected. The remaining issue will be, purely in terms of overall spending, how far they wish to proceed. I doubt there will be many disputes regarding the cost per unit, given, firstly, our past results, which have been quite strong, and secondly, the nature of the work we'll be undertaking in the future.

Dan Cregg

executive
#55

Yes, Andrew, and I’d add that as part of what the BPU carried out, I believe they deserve credit for attempting to adopt a certain philosophy when going about this—they aimed to use this program to go after items they believed wouldn’t occur absent it. So, as you know, these bulbs serve as one illustration, since incandescent options are available on store shelves. But there are other cases as well: things that would have taken place regardless aren’t a strong candidate for a program like this. Its purpose is to broaden what would take place in any case. Therefore, I think that broadens the scope somewhat, helps move them toward a stronger position, though accomplishing it might require somewhat higher costs.

Andrew Weisel

analyst
#56

Okay, very clear. Thanks so much.

Dan Cregg

executive
#57

Thanks, Andrew.

Steve Fleishman

analyst
#58

Hi, good morning.

Ralph LaRossa

executive
#59

Hey, Steve.

Steve Fleishman

analyst
#60

Apologies — one more nuclear-related item. Over the past, say, 6 to 9 months, we've discussed this in hypothetical terms, including hydrogen. My understanding is there may potentially be something like an offshore wind port adjacent to the plants or nearby, and then clearly data centers are in the picture now. Should we view all of these as options available at that site, or is it necessary to pick just one — and is data centers currently at the top of that list?

Ralph LaRossa

executive
#61

No, Steve; that's an excellent question; the port has already been constructed. What I mean is, an enormous amount of work has been completed down there, and the New Jersey Economic Development Authority has carried out a great deal of that effort. Whether a ship can currently be brought in there, I'm not certain, but we are very close. So a tremendous amount of activity has been finished. They've begun leasing some space to certain offshore wind developers. From the state's perspective, I'd say that's progressing well; beyond that, there's more land that remains available, and you could site a data center there, you could site — the question is how large it can be, correct? You know, all of that has to be determined according to each individual developer's design criteria, what they may be considering, and the size they're seeking. A hydrogen unit could be placed there. An electrolyzer or something similar might make sense at that location, or perhaps it ends up slightly off the property, right? And once again, everything hinges on the rules that emerge, what we ultimately see from IRA implementation. So our thinking treats it as all of the above within an optimization strategy. Simply determine the best approach for us to, you know, utilize that electricity generated by the units and do so in a manner fully consistent with the state's policy; so doing all of it is possible. The only question is, you know, what the state's policy happens to be and how large any single one of those opportunities grows.

Dan Cregg

executive
#62

And regarding hydrogen, Steve, just to recall, an increase in capacity at that site would satisfy both additionality and hourly matching, assuming those restrictions remain in place for hydrogen; therefore, we genuinely feel fairly confident about what we can accomplish in that region, and we don't perceive any constraints requiring a choice between one option and the other.

Steve Fleishman

analyst
#63

All right. Then the remaining piece, I suppose, is really about reliability across New Jersey as a whole, and, you know, there's a great deal of attention on offshore wind that has slipped and so forth. And so, I suppose from that angle, that latter angle, could you kind of, you know, how are you, how are you positioned in terms of alignment with the state, considering that dimension, to be able to do something behind the meter at nuclear?

Ralph LaRossa

executive
#64

Yes; so, Steve, that electricity moves in a great many directions, correct? Not only within New Jersey, but in other states as well, correct? So it's really more of a PJM matter when it comes to that particular unit and those particular megawatts. But I'll tell you this, and you know, we've mentioned it in a number of forums, so I apologize if this repeats something, but that 2003 blackout provided the chance to rebuild the transmission infrastructure, and that's what we did; then Sandy arrives, and we rebuilt the switching stations and substations. So we are well prepared for this. I believe New Jersey is uniquely prepared, and I've got my economic development hat on here for a moment, but I believe we're in a really good place, and the margins aren't quite as tight as some others might have; so I think we're examining this and trying to determine what's the best solution for the state, and we're doing it in partnership, not one-off of the state's plans; so we feel pretty good.

Steve Fleishman

analyst
#65

Excellent, thanks very much.

Ralph LaRossa

executive
#66

Thank you, Steven. There's no need to say sorry for bringing up a nuclear topic; staying in was our decision, so we're glad you asked.

Steve Fleishman

analyst
#67

Oh, right. Understood.

Ryan Levine

analyst
#68

Hello, everyone. I suppose I had one or two additional questions regarding nuclear. When it comes to how long the contracts might run that your counterparties would be prepared to commit to, I believe during your remarks you brought up the long term. Could you provide any detail on what long term actually means in your view? And then, given that there are transmission constraints in PJM, how does the schedule for any investment in that area factor into the capacity to meet that lengthier outlook?

Dan Cregg

executive
#69

Yes, Ryan, I believe the straightforward response to your first question is that if someone is going to arrive and construct a data center, that represents a tremendously, tremendously substantial outlay, and it will be present for quite a while. Therefore, I cannot offer a particular figure for years, but I believe long term is fairly comfortably regarded as long term. And I believe regarding the transmission aspect, Ralph essentially provided, I think, the correct answer. Regardless of how much we have expanded the transmission network, considering what we experienced roughly 20 years back and 10 years back, I do believe we are ready for whatever flows must occur in the area. So, I think both of those are in fairly solid shape.

Ryan Levine

analyst
#70

And so, picking up where we left off with that final question, if there are policy chances to potentially draw this kind of customer base into the state, is there any legislation you're watching that could make it easier for other stakeholders to bring this load into the service territory?

Ralph LaRossa

executive
#71

Yeah, no. So, again, I'm wearing my other hat here. I think the state offers plenty of options for new companies to relocate to New Jersey or launch here. The EDA has a number of different programs that could bring businesses in, and nothing I've come across would need further legislative adjustments. Some might exist to accelerate things or widen opportunities for people, but I'm fairly confident the state possesses the tools in its tool chest to go after the opportunity set it has.

Ryan Levine

analyst
#72

I appreciate you fielding my questions.

Travis Miller

analyst
#73

Hello, all. Thanks. Given that there's no need to say sorry for asking about nuclear, I guess I'll come in with a different one. I'm just considering how an agreement for a co-located site would appear at a really broad level, and my main focus is on which party would bear the danger of, say, a failure to perform or a similar matter. Would that be a risk you feel at ease holding, or will you basically require the offtaker to carry it?

Ralph LaRossa

executive
#74

Travis, all I'd say is that discussing anything of that nature is far premature for us. As you know, we can't address specifics or any talks. That said, I'll share this with you: this question has been answered by us many times, and I'll connect it to the hydrogen possibilities; getting into commodity risk, that commodity risk scenario is not what we want; so essentially our view is that a meter gets placed by us at point A, and from there people can take it and determine what they'll do with the power. And to me, data centers, electrolyzers, or whatever else could occur in that area are no different. And, Dan, anything to add?

Dan Cregg

executive
#75

No, what I'd add is really just from a hands-on standpoint, when you picture a site with three units, you have quite a bit of redundancy and the capability to handle those kinds of situations. So of course, the contractual terms and conditions will get hammered out across the full scope of whatever agreement you end up reaching; but I believe we begin from a strong position there.

Travis Miller

analyst
#76

All right, that works. No, that is, that is excellent. That seems reasonable. Then I have another thing to ask regarding the transmission component in the bids and proposals you submitted. To what extent does what you offered or included in those submissions rely on a second round of offshore wind projects arriving? Is it none of it, or is it a portion?

Ralph LaRossa

executive
#77

Yes, indeed; so Travis, I believe there are two, two ways to respond to that. To start with, the PBI, that pre-build chance does not call for that. Essentially it is quite comparable to what took place during the initial solicitation, where, to draw a comparison, it functions as a catcher's mitt for pipes arriving or wires arriving from the offshore wind farms; therefore that element truly does not hinge on it. I believe the magnitude and reach. The subsequent solicitation obviously hinges on the, the so, you know, what, the extent of that offshore wind chance for the state overall. And that, we have not yet observed the reach of what that could be.

Travis Miller

analyst
#78

All right. Would that go through the PJM process, or would it go through the New Jersey process?

Ralph LaRossa

executive
#79

That would be handled through PJM, kicked off by the State Agreement Approach coming from New Jersey. So New Jersey gets on the line, reaches out to PJM, and requests that they conduct the process on the state's behalf. Yep.

Travis Miller

analyst
#80

Alright, that's excellent. I really appreciate it — thank you very much.

Ralph LaRossa

executive
#81

Thanks.

Ralph LaRossa

executive
#82

Paul, hi there.

Paul Patterson

analyst
#83

How's it going?

Ralph LaRossa

executive
#84

Doing well.

Paul Patterson

analyst
#85

So, as a quick follow-up regarding the transmission matters, I'm curious whether you could share what you think about the transmission policy agenda that will be taken up shortly with FERC in the coming weeks. Do you have any views on what could emerge from that and how it could impact your company?

Ralph LaRossa

executive
#86

No, I believe. Well, there are 5 or 6 items on that list; within our wires organization we have people who are deeply engaged in transmission, along with some of the others. So we're keeping up with it. In my view, under the present chair, FERC has stayed balanced, and I don't anticipate any extreme shifts in what comes out of it, but at this moment we're watching it carefully, Paul, and beyond that I wouldn't have much else to say.

Paul Patterson

analyst
#87

All right. Turning to a different significant policy initiative that various officials are promoting — grid enhancing technologies. I'm curious whether you anticipate any effects on your company or your operations over the coming years.

Ralph LaRossa

executive
#88

Sure. A good deal of that grid enhancing work has been quite targeted. I believe a New York Times piece covered it — regarding conductor upgrades that have been put in place; we've examined a portion of that and run pilot programs on some of it. As we've mentioned before, we've completed numerous transmission upgrades. Our system has also been designed to accommodate certain further upgrades, though in my view that ultimately comes down to a cost benefit for the customer, depending on how much extra capacity it would deliver, and whether — you know — we'd prefer not to get ahead of the need. So we'll keep watching it, and it's something that, you know, PJM, once again, will have available in their tool chest to make certain determinations about how they wish to address some of the gaps that could emerge going forward as electrification progresses.

Paul Patterson

analyst
#89

Okay, awesome. Thanks so much.

Ralph LaRossa

executive
#90

Thanks.

Ralph LaRossa

executive
#91

Well, I really just want to express my gratitude to each of you for the trust and backing you keep giving us. Every one of these questions is welcome, and we genuinely can't wait to meet up with the majority of you at AGA in May. So once more, my thanks go out to our team members, the people who buy from us, and those who invest with us — and we'll be seeing all of you in California. Stay well.

Operator

operator
#92

Everyone, that brings us to the end of today's call. At this point, feel free to hang up your phones. We appreciate you joining us.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Public Service Enterprise Group Incorporated transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Public Service Enterprise Group Incorporated earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Public Service Enterprise Group Incorporated or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.