Ratnamani Metals & Tubes Limited (520111) Earnings Call Transcript & Summary
June 3, 2021
Earnings Call Speaker Segments
Operator
operatorLadies and gentlemen, good day, and welcome to the Q4 FY '21 Earnings Conference Call of Ratnamani Metals & Tubes Limited hosted by Monarch Networth Capital Limited. [Operator Instructions] Please note that this conference is being recorded. I now hand the conference over to Mr. Sahil Sanghvi from Monarch Networth Capital. Thank you, and over to you, sir.
Sahil Sanghvi
analystYes. Thank you, Rutuja. Good evening to all. On behalf of Monarch Networth, we welcome you all for the Ratnamani Q4 FY 2021 Earnings Call. We are glad to host the management of Ratnamani today. And from their side, we have the MD, Mr. Prakash Sanghvi; and their CFO, Mr. Vamil Katta. So without taking much time, I'll hand over the call to Prakash for the opening remarks. Thank you, and over to you, sir.
Prakash Sanghvi
executiveYes. Good evening to all. Of course, you might have results on hand plus as well as FY 2021. But I can read the figure for the entire year. This is INR 2,331.5 crore and net profit INR 278.3 crore. During the year, we have completed, of course, with the challenging time COVID-19 pandemic, but our team, really congratulations to my team, they -- even the difficult time, they performed really good compared to our expectation. We have completed both the CapEx plan in division as well as targeting low. Approximately, you can say about INR 290 crore we are supplied in the year, but spending that and in is about INR 190 crore, about 150,000 ton line pipe capacity. And in behind this ERW pipe, we have increased the capacity putting new finishing lines to about 60,000 tonnes of capacity increase. So these are the 3 new investment that we did in the U.S. and now we are running successfully products and also of course and pharmacies and going on. And in ], we also did good number of , but still some more price we have to do. And the number of approvals, we applicate at the new plant. So hopefully, this year, we will get from both the dividend, additional turnover. And then other on and that is on the about INR 1,498 crore total. And things are, of course, in first quarter of the new year also not good because as the pandemic and second wave was there. And now things are increasing slowly and gradually and numbers of cases are coming down and we hope simply improve much more. And we will start, of course, we also a single order of INR 82 crore. So like that things are improving year. And of course, you might have seen the improving the oil prices, so about $70. So this all hold projects are getting that. And they are renegotiating because gone off. So we had asking a new . Because some of the order last year, they make a on the order. So the last year, one of the bus was decent, and this is price was different. So we are asking some price increase, and that is negotiation is going on on some of the big order of industry. So we hope now with this new oil price and this good demand is coming from U.S., Europe and we all Middle East. So we are quite hopeful on the demand side for oil and gas in the country, pharma, PI, chemical, even in oil and gas also, we think things will improve in next quarter, definitely. And one more new thing that happened that if China had withdrawn the export benefits about 10% to 13% of different products opportunity for India to have put more in the European countries in the U.S. and country . And what we heard, they are thinking kind of our thinking on putting export tax they would like to use more for domestic using what that we have. So then again, we see a good opportunity for the Indian manufacturers because 13% of the and 10% that are putting new exporter. That become 23% is a big amount, and it really will improve slightly or enlargening. It will be definitely help always did good bookings. That is what we see. And I think in country also, things will improve. Of course, raw material is over years because of the prices have gone up in both as well as steel. But still that if they want, they have to consider the -- because again, . It's not only in India, that on up, which is internal on the pipe for raw material. And hopefully, wherever somewhere possible, we will also go need to in a price with the old order, what is us, something there , something we have to . So what our idea is to have more and more order booking is because the new facilities are there. So there actually we are looking for new new orders from other . Thank you.
Operator
operator[Operator Instructions] The first question is from the line of Ashutosh Tiwari from Equirus Securities.
Ashutosh Tiwari
analystCongrats on the good numbers. Sir, first question is that you talked about this 13% export risk weight in China, which is withdrawn. So was it there on the asset price as well?
Prakash Sanghvi
executiveYes, it was, it was. All items, whether this was pipe, tube .
Ashutosh Tiwari
analystOkay. So now that if it is withdrawn, in that case, basically, in India as well as overseas market growth will get evented?
Prakash Sanghvi
executiveYes. look, our competitiveness will increase, what I miss in the international markets.
Ashutosh Tiwari
analystYes, yes, because I think there are some 2 or 3 big players well from the China.
Prakash Sanghvi
executiveAnd they are talking further 10%, they would like to exclude tax. We go on to you domestically less in their product. Steel and stainless steel. There is good export taking place from India to China with .
Ashutosh Tiwari
analystOkay. Okay. Yes, that was. So even if that 10%, I don't know whether that comes when it comes, but even if without tax...
Prakash Sanghvi
executiveIt is on the top on this.
Ashutosh Tiwari
analystOkay. But with this 13% rebate itself going off from their export rebate. In that case also, I think, for us, opportunity in -- I think even in the distributor side that we had initially targeted there also will get a rebate, right?
Prakash Sanghvi
executiveEvery year, because the cost will increase definitely to everyone, whether it be U.S., or Middle East or Europe. Or even India support some people are importing from China. So there also then be effective. And there another more one thing had happened. We put the BI quality control. So any manufacture outside the country versus our BIS registration and our product comes under that or in the side.
Ashutosh Tiwari
analystAnd when did this thing happen? Basically, when did this particular thing escalated?
Prakash Sanghvi
executiveIt is already there. It is already there. So the imports are getting less and less drastically. Earlier, imports were coming in the low from China. But now you can say, last quarter of the year, it has reduced like anything. And we are...
Aalok Shah
analystFrom Q4, you think, from January '21.
Prakash Sanghvi
executiveYes. For -- yes. And our and ]. And we are quite monitoring also and time to time informed to the to the custom officers also. Because some more up . They do an imports, so we notice this is what coming. So that...
Ashutosh Tiwari
analystAnd on these products that come from China, like tubes and all, there is some custom duty as well in India, right, on that already?
Prakash Sanghvi
executiveYes, there is a custom duty. There is a custom duty. 10%.
Ashutosh Tiwari
analystThat means that if the prices go by 13% or that there is a custom duty also so I think net-net, 15% kind of increase in...
Prakash Sanghvi
executive15%, it will be 15% higher.
Ashutosh Tiwari
analystThat is a for us basically. Okay. So that is one good thing, okay. Secondly, so last time we had mentioned that some of the customers basically were delaying the -- this tender finalization because steel prices have gone up sharply, and they're probably waiting for it to fall, but there's no fall per se. So are you seeing that those customers or contractor are now started placing orders or they are still different?
Prakash Sanghvi
executiveYou can even only we got after that a big order of one single by INR 92 crore. And another one, when we INR 82 crore. So now they are taking this as an uplift started. Because some the we are the work as to , there's no way to go. Up to somewhere well the project time is 26 months or something like that, 24 months, where they still want to wait for 3, 4 months, 6 months, if there something will go down or something. Or whatever they require, say, 20% of the required material, they will buy right now and further 80% going back. Because everybody wants otherwise, they are loosing from there.
Ashutosh Tiwari
analystOkay. And then lastly, on this asset seamless side. Now that the plant is ready in commission. We said that there's still some parsing on this exclusion part of it. So in this year, what kind of extra earnings you expect from this new plant in 2023 -- '22, sorry.
Prakash Sanghvi
executiveYes, INR 150 crores to INR 200 crore.
Ashutosh Tiwari
analystSorry?
Prakash Sanghvi
executiveBecause I'd say, INR 150 crore to INR 200 crores extra turnover.
Ashutosh Tiwari
analystOkay. And also does the combine basically, the customers have to come and do the and all or some of that already started?
Prakash Sanghvi
executiveNot everywhere. Somewhere, we take a somewhat because customer to customers, their different policies are there. So people like, yes, we are already doing we were importing and get coding and so our registration or approval is there. But we want to show them to the top of 1 technology is that for more for delivery, quality terms of you that we want to do, whether we would like to have get together for all VIP customers to show that this is . but because of this . We will wait and we'll see in normal December if everything is some good .
Ashutosh Tiwari
analystAnd then lastly, if I may, we have seen very good ramp-up in the carbon steel order book, okay? But asset order book, obviously, has remained stable. But do you -- I mean, are we seeing a trend, let's say, that even in the order booking in that area, I would also go up for next maybe 4 to 6 months of the -- some project that we have in pipeline?
Prakash Sanghvi
executiveYes, definitely. See right now, the program is number of we have driven, but the is taking time. So -- but this forward staging of, then things will improve more and more and more. Because last 2 months they were working from home and some extent where we get close to people. But overall small order, we are regulary getting and that . So anytime INR 300 crore to INR 400 crore order is there.
Operator
operatorThe next question is from the line of Kunal Shah from Carnelian Capital.
Unknown Analyst
analystSir, basically, I you did mention in the opening remarks, what is the total capacity that is going to be since you've commissioned few parts. So to capacity in both the segments, if you could reiterate, please?
Prakash Sanghvi
executiveCan we sell you capacity. See about additional capacity will be increase in ...
Unknown Analyst
analystSorry, sir.
Prakash Sanghvi
executive150,000 tonne in line pipe, we are capacity in . And in side, we have increased about 30,000 tonnes capacity. And in carbon steel, we have further increased 50,000 tonnes from the existing capacity. So all put together in carbon steel say about it 50,000 tonnes. So all put together on carbon steel, say about 50,000 tonnes, all put together , all put together. And in stainless steel, we are ready with a new capacity, 30,000.
Unknown Analyst
analystOkay. Okay. Okay. And sir, the second question is, what do we intend? I mean, how do we plan to use the cash, net cash that we have on our balance sheet? And also, the second question was that we took a Board approval for INR 500 crore debenture range, so it is a normal resolution? Or how should we look at these 2 things, sir?
Vimal Katta
executiveSee, I'll answer. Prakash may not be. See, basically, this NCD resolution is enabling because as per the existing guideline, any incremental borrowing for large corporate is large entities or , we are recurring to approach the bond market. So it is an enabling regulation in company requires to go for any cash borrowing for to fund it growth, so then we may not wait for the approval. Okay. So it is an enabling regulation. There are no plans right now, immediate plans to raise any funds. And about the cash, which company is doing, companies, as the business grows, working capital requirements will keep on increasing because something continues to follow the practice of between the back-to-back basis. So some portion of it will go towards funding the increased working capital requirements. And remaining will be there with the company to take advantage of any opportunity, which may be there. Because, see, this year, we are targeting INR 3,000 crores plus of top line. So anyway, I think at retirements are bound going to go up. And if everything goes according to our expectations, then perhaps, we should be ready with our next phase of growth in the next few years' time. So we need to start working on that also in current financial year because it takes time before the capacity can be available. So those things, but will require certain cash out. So these funds will be used. And anyway, something we'll always be there as a buffer.
Operator
operatorThe next question is from the line of Vikash from PhillipCapital.
Vikash Singh
analystCongratulation on good set of numbers. Sir, my first question pertains to the visibility of order books. Like you said in your initial remarks that now people have started to award the order. So in next 6 to 7 months or for that matter, 1 year, what kind of order book pipeline for the order bookings you are expecting kind of the to come in your way in access as well as CS segment?
Prakash Sanghvi
executive[Audio Gap] quite hopeful, we will definitely book from what new capacity also as well as additional capacities because of one more good reason, which is the 2 good reasons. One is oil price is going up. It is now, it is $20, $22. So with this that we started the investment, like the then recently we got some other some so like that Saudi Aramco has a huge investment, ADNOC, everybody there also using different the plan. And we have some we quoted. But it takes a little more time because of the service situation, but now things are improving in this corridor. So postally, if everything goes well, then we might have any kind of INR 1,500 crore to INR 2,000 crores of the booking anytime.
Vikash Singh
analystOkay, sir. Okay. And sir, sir, 1 more question regarding this order booking. So what we have seen in the -- that we usually do the bidding and nowadays, yours have to wait for a longer period of time before the order has been awarded. In between the steel prices has been rising pretty sharply. So are we bidding with the clause, where the -- any -- before awarding any increase in space should be covered or on an anticipation, we are doing some back-to-back booking in order to protect our margin, if you could explain that part of it?
Prakash Sanghvi
executiveYes. No, mostly, it is all the auction. Okay. So first, we have to quote a particular price. So we definitely see and could . And then because the reverse option fixed rate after months or 2 or something like that. So we always take some buffer and then we go down from that. Okay. While we were take care the current merchant size and we did see on raw material. And based on that, we will make it down and we become . So once we become , then we will be sure we were going to get the order. So we book a back to back order, raw material. So more or less, we are not getting any some time, of course, we are late by 10, 15 days and in between the price has gone up, then that it is taken . But sometime we are gaining also. .
Vikash Singh
analystSo if I understand this correctly, then most of our order booking or the bid books would have kind of a margins have already been locked in. And this sharp increase in sales prices might not have any meaningful impact on our profitability going forward, is that a fair assumption?
Prakash Sanghvi
executiveYes, it is a correct assumption.
Vikash Singh
analystUnderstood , sir. And sir, just 1 last question, if I may, on. In terms of our -- basically in terms of our approval, so by and when do you think that we would be able to manage all the approvals for both as well as mill? And then would the full potential could be unleashed from both of these CapEx, so any time line which you have in mind?
Prakash Sanghvi
executiveWe have already started production, and we have some order book so the it is needed because we were doing to earlier as , I think at that time, we were importing them overall and doing the pricing. Now we have our own measure in the year. So more or less, it is there. But it is a stake of our facility, you would like to call out and so then we will be a quick delivery in the quality, being at less lesser testing equipment. So we would like to increase them on getting more on us. That's what we are going to do. And somewhere, of course, it is a new line. It is a audited by them. This, we are doing just after this so it is over a second wave. And once people starting traveling in that many . But , we already did this a were off-line .
Vikash Singh
analystOkay, sir. Okay. Sir, when -- like you said, the Chinese material are now becoming expensive. So is it possible that for us also the to export market is now a more feasible option? And at least for -- unless we get an approval for these products, we can say the general merchandise in the export market and utilize our mill to full extent?
Prakash Sanghvi
executiveYes, you are right that we are going to start now. But for that, we have to travel actually for the first time. Because so far, the company is importing from China. Of course, we have exported, in fact, 1 or 2 in China also. But now there is big change because 13% what they are reduced. And then 10% they're going to put an export tax. So if their domestic market is also high. We may at some chances, but this is all we have to impact and have a of the market and try one of the order or something.
Vikash Singh
analystOkay. So is that opportunity would only come if China inforces another 10% import duty? Or is it already there?
Prakash Sanghvi
executiveSo it is already there for for some good niche products. The ordinary product, they might be having good capacity, but some new products still that are importing, we are still that importing. So there we may get a chance. And in to.
Operator
operator[Operator Instructions] The next question is from the line of individual investor?
Unknown Attendee
attendeeI'm from Unrated Capital Limited Kolkata. Sir, you likely said the present import, export ratio in India and China. But is there any chance this after this crisis, we overcome maybe after 6 months or 1 year and the import, export ratio will change? And if it is changed and how it will impact the business?
Prakash Sanghvi
executiveIt depends because we as a raw material for everyone as we can, whether it is China, whether India. So far 65% is the cost of the raw material. So remaining, they all depend on how you manage your business with the labor charges, electricity and other. So you want to there now in. We were doing good exit from here to all right from Japan, Korea, Middle East, Europe, USA. So we are competing them. But we are now -- our percentage will increase, our export will increase. Because there is a good demand, of course, in our country, see it will come. But the demand is coming more from the U.S., Europe as well as Middle East side, quite big quantity we have quoted right now, but of course, we knew it could be 2 to 3 months' time, 4-month time to materializing order. Because oil prices are also supporting ago. Only a is, say, $30 to $40 or something like that. And now this year, it is $65 to $75. So the things are improving in their areas also.
Operator
operatorThe next question is from the line of Pritesh Chheda from Lucky Investment.
Pritesh Chheda
analystYes. Sir, just a broader question, we could understand your capacity expansion in stainless steel, which is a lot import substitute, but when it came to carbon steel expansion, what exactly did you see in terms of evolving demand scenario? Because this industry has largely been flat for the last 6, 7 years. So we have been in a certain volume range or competitor has been in a certain volume range, global markets have been in a certain volume range. So what exactly are you seeing incrementally for you to be investing and expanding carbon steel? And my second question within that is, what would be so far the business side globally for carbon steel, if you could for hundred million tonnes revenue? And when you're mentioning China rebate and benefiting other countries. So what is the extent of export that China used to do?
Prakash Sanghvi
executiveSee first question is, first of all, there is a big domestic visibility what we are seeing in the line side because a country as in with oil and their transmission by the a new number of pipeline, the , IOCL, they have already planned. But because of this last year all-time has gone in this COVID and still people are not sure of how this third wave or something like that. So I see the of this last 1.5 years, you can say, still improve definitely very requirement in the country with the city activation orders have been given to all domestic EPC contractor, and they have to buy a pipe. And even in ERW, we have booked up to up to December. In so there is a working it in domestic market and partnering more or less with the domestic market, this is LNG line is coming, a number of LNG lines is coming. Because we have onto about 70% of LNG complete requirements on the different countries. So we definitely -- and we have replaced this with our old capacity was about 40,000 tonnes of LSW, that is a very old . So it is that we would like to add some more. Once we are putting new capacity, we had to add with the size and grade and shipment or requirements. So it is a new capacity that 30,000 tonnes, 150,000 tonnes, with additional of line pipe. we are not doing a line pipe, and some people specifically asking for longer business to a pipe. So that is the reason we have added. And w, we see a lot of visibility up to prices 8 years because of this particular satiation. And we are quite busy in that running with 100% capacity that we are . So we have to put new capacity or not. So it is a very reasonable capacity in a core category of pipe. Now there is one single, it is , all such in charger. Your second question, of course, was China. Definitely . China is focused is in the domestic market.
Pritesh Chheda
analystHow much they must be exporting, sir? And what would be the global market size for the carbon steel pipes? Is it 10 million tonnes or more?
Prakash Sanghvi
executiveIt is too big a market. People have a one company have about 4 million, 5 million tonnes capacity in . Even in-country also 2 million in capacity. So it is a huge market. It is not some of which a 10 million tonnes or something like that, that are just currently I'm talking. So huge market and number of countries are requires on 1 product from here to Ethiopia. We have given EPC in Middle East, and they are laying the pipeline over there. So mispriced number of -- and our very limited capacity in all 4, 5 manufacturers in the country. In 550,000 tonnes of total capacity of pipe.
Pritesh Chheda
analyst550,000?
Prakash Sanghvi
executive50,000 tonnes, yes, 550,000 tonnes in all 4 categories. .
Pritesh Chheda
analystSir, 700,000 -- 700,000 to 800,000 is done by the largest guy in terms of volume. You'll do about 2.5 -- 200,000 to 250,000 like so 1 million so INR or going to be 1 million so -- between you and .
Prakash Sanghvi
executive[Audio Gap]
Pritesh Chheda
analystOkay. Okay. Okay.
Prakash Sanghvi
executiveExport from China. The data is available still maybe around may be in the range of 50 million to 60 million tonnes per year of exports. But in , roughly between 50 million to 60 million tonnes per year of export.
Pritesh Chheda
analystThat is a full steel export, right?
Prakash Sanghvi
executiveSo the entire range.
Pritesh Chheda
analystWithin that, our -- that is sir full steel export, what would be pipe export in that?
Prakash Sanghvi
executiveThat figure will not be available about this.
Pritesh Chheda
analystNo problem. No problem. My second question is, sir, on the stainless steel utilization side. And so we've added this 30,000. When do you think you would be using this capacity fully? And what should be the volumes for the next 2 years, that is '22 and '23?
Prakash Sanghvi
executiveSee the first year '22, you can say we will definitely go up to 3,000 to 4,000 tonnes because in your first year, there are a lot of approval, a lot of internal trials, number of . But next year onwards, it definitely go with 30%, 40% equity in spite what we can pay 30,000 tonnes. It is more depending on the diameter and shipment, what we are producing. Sometime it may 20,000 tonnes sometime, it's my 35,000 tonnes. But it is always average what we are talking.
Mihir Manohar
analystOkay. And sir, in CS, you never mentioned about what's happening in the water side because all the , if I remember, were more -- we were seeing opportunities in water. So what's happening there?
Prakash Sanghvi
executiveSee water is totally not moving because all state government is in the COVID as possible from their end to saves the life and that the facility was not. So their entire focus on COVID since last year. So far not much for the . But the things will include the project well but maybe can still Prime Minister totally depending. It is just announced but nothing had happened on that one. So once this will improve a normal situation of the country and the COVID, definitely, the more good number of requirements on all the spacing to get.
Pritesh Chheda
analystOkay. So lastly, some total, you see the carbon steel industry, some total volumes and for us also moving significantly higher over the next 3 years versus the last 5, 6 years, where it was absolutely flat in terms of volumes for us and the industry as a whole?
Prakash Sanghvi
executiveSee really with this high in the steel and other things, all the metal is. But still where the demand is coming from very high. Europe, Middle East, see after 1 year because everybody is under , what we feel the way we are quoting right now inquiry. So things will definitely increase. We improved over there. Of course in our country also announce the second wave is over and everything is in the country.
Pritesh Chheda
analystHow much is a big interest higher than what it was a year back? If you were quoting for 1 project or 2 projects or 5 projects or, let's say, let's say, 100,000 tonnes, how much bids are you putting now for 3x, 2x projects, 3x?
Prakash Sanghvi
executiveWe are putting right now, the 2x to 2.5x right now. So there are more facilities with materialize .
Operator
operatorThe next question is from the line of Saket Kapoor from .
Saket Kapoor
analystSir, firstly, sir, how is this steep increase in steel prices going to affect the dynamics for the steel pipe industry? Sir the way the prices have moved up and international prices being still higher than what the domestic prices are and the steel manufacturers have taken another round of hike from the beginning of this month. How is this rise going to dampen the -- since it is going to increase the cost of project for everybody? What could be its negative impact on the demand side, sir?
Prakash Sanghvi
executiveThis is what you have seen last 1 year, it is a low order booking, you can say. Because people are taking decision because all these EPC might have a good order but are not able to fund. Because first 6 months, they took in engineering, and then they are done for months in some of the . So by that time, the size has gone up so slowly gradually we have whatever emergency requirements, that's what they are deciding. They are seeing spending, hoping the prices go down or something like that. Or they see some . But ultimately, they have to complete the project, it is somewhere it is 20,000 tonnes or 30,000. They are waiting. And we don't see there is any of decreasing in the next 2 to 3 months or 4 months. Because it is a net China was the export of . It is an importer. Even our country, India is exporting a huge quantity of pipe to them. Like that demand in U.S. increase like anything what people are talking over there. So, but we are not any order, anything we are our value is very less for 7 days or 10 days or something like that. If anything goes increase, we also send an increase price or something like that. So we also making it ourselves are taking and our people of marketing there completely work on international agenda domestic type of steel and .
Saket Kapoor
analystAnd sir, how has this duty reversion that happened in the last budget for the stainless steel help people like us?
Prakash Sanghvi
executiveIt is 2.5% from 10%, it had gone to 7.5% so not much. But of course, we are not imposing much anything. We are all on domestic some of the special grades and that we need to import. Otherwise, then buying from .
Saket Kapoor
analystRight. All right. And sir what will be the sort of incremental depreciation going forward for the next financial year, since a large portion of the CapEx is ? What would be the impact of that?
Vimal Katta
executiveRoughly INR 30 crores.
Saket Kapoor
analystINR 30 crore annually.
Vimal Katta
executiveYes.
Saket Kapoor
analystRight. And sir, now coming to the refinery part of the story. As has already informed that lot of stock has been done, but on the ground, things have not changed at all, have not been to that extent. What is the ground selling for the refinery CapEx that can happen going forward? What is the talk of the bid pipeline looking like that?
Prakash Sanghvi
executiveSee, number of expansion are their plan, but investing is because of sold. But now because one reason more, the oil price has gone up about $70 or so. So they will restart. Only in or countries, the problem was the second wave. You can say Karnatika, Gujrat. So things are because . but now things are improving in also. So think we improve -- and I already , we are disputing regularly in person as not many other will also come up. Even naira, that is old , they are also having a good expansion plant because of this , but now things will come definitely. And in export side also, there is huge investment from Saudi Aramco, Qatar, IOC and this is that we are getting with the requirement also somewhere we are quoted also.
Saket Kapoor
analystAnd sir Out of the total revenue for this year and if for the order book breakup also what portion will be contributed to the export market?
Prakash Sanghvi
executiveAbout 20% to 22%.
Vimal Katta
executiveLast year was even better than what we did in 19 and 20 to INR 560 crore from of experts. So I didn't get you said 26%, 25% turnover has usually been coming from excess. , we like to see it maintain or other increase.
Saket Kapoor
analystAnd there any investments you are going for the renewable energy segment, sir, either in the solar part?
Prakash Sanghvi
executiveYes. Solar, the policy is not cover yet from our Gujrat government, there we are having plan of INR 50 crores because our power cost is too high. So we would like to reduce, but the policy is still not clear, once it becomes clear, we definitely go for investment of say INR 50 crore to INR 60 crore.
Saket Kapoor
analystYes. And lastly, sir, the distribution part is, as per the outlay from the government side, the district, which are going to be covered, how much is the total demand of ERW pipes? And how much has been bid as of now, sir? Since they have increased the number of districts also, what is the outlook based?
Prakash Sanghvi
executiveSo there we've seen rather good visibility in the ERW . And that the reason, we have increased the capacity over there putting 1 more finishing line, . So if I keep coming although the contractors are billing to them and they are getting and they are buying from us. And if you look good requirements what we see. And we see this will go on if the country hopefully get in the next 10 years. Then whole business will also go with them in the next 7 to 8 years continuously. And this is in plus 3 years.
Saket Kapoor
analystRight. And what is the top line sir you told, I missed the part for FY 22, we can expect for this year?
Prakash Sanghvi
executiveMore than INR 3,000 crores.
Saket Kapoor
analystThank you for all the answer. And thank you to the Board for the incremental dividend also for this year, sir.
Operator
operatorThe next question is from the line of from Motilal .
Unknown Analyst
analystSir, first question is, you said you do back-to-back contracts for commodities. Now in a rising commodity, customers are not complain. But what happens in, let's say, steel prices, the way they have gone up, they can also come down. What will happen then? Will they ask repricing down in your experience, what happens?
Prakash Sanghvi
executiveSo , it is because all back-to-back, and it is some price from over end and they have to look also and we have to deliver also. But wherever our validity is over where we said then that because relates have just gone up and . And they have to agree. There are, of course, some which keep margin also because ultimately, we keep customer happy finally. So that is able affect .
Unknown Analyst
analystOkay. And sir, now that you have commissioned DSS line. How is the margin that is coming through? Or how is the top line velocity that is coming through from the line? Is it satisfaction or is it better than your satisfaction? I just wanted to understand that.
Prakash Sanghvi
executiveNew CapEx what we we did, really a state-of-art facility what we have put, we have already started production also. Of course, starting some program might be there. But from Europe, so this is really new state of our facility for in that we are the size-wise, grade-wise, we are the largest in the country for persistence in pipe. And once anybody sees a facility that maybe the increase and without anything on the of course price net or over will always prospect for any requirements.
Unknown Analyst
analystYes. So for the gross margins for this plant be of the, this could be higher than 35%, which is, let's say, a year?
Prakash Sanghvi
executiveThe capacity into a something we'll do more valuation in our and something will go as it is whole finish what we were importing in past time. So it is a mix of the product. You can say 60% we are going to do, , 1 operation. The 40% side we are going to do with more value-added. So it is more or less same, you can say. We are getting less and we are getting more -- the margin remain EBITDA level same or some and any product somewhere higher also, it is a standard product. So ultimately average, it is same.
Unknown Analyst
analystOkay. And sir, 2 more questions. One is, as you plan for your next leg of CapEx, focus will be on new product or a different location, what will be our preference?
Prakash Sanghvi
executiveOf course, location definitely, you are right because we had of of our entire country because we've become a volume item. So of course, we are thinking even last year also before COVID. But after that time, we had stopped also. But of course, there is a plan. But once we see over then we will relook everything in the , also exploring possibility in the international market also in a .
Unknown Analyst
analystAnd sir the last question is, did you have MEIS income in FY '20? And yes...
Prakash Sanghvi
executivewe have certain income because whatever license we got in the starting second quarter. And after that government had a and with that, we also affected because we have booked order base on that calculation. But all of a sudden, they are nothing being they have given some figure up to who we are going to get and our order booking in a large value. So we have gone with the court, high court. Saying that still that whatever order we are booked, there we have to put benefit. So this is not wanting to frequently. So it is under court, you can say. And we hope to let -- and everybody has gone through the court because it is a quite substantive amount about INR 10 crore to INR 12 crores.
Unknown Analyst
analystSir, if you ca tell me, what was the NEI income in FY '20? And how much you booked in your books in FY '21?
Vimal Katta
executiveSee, FY '20 or roughly INR 12.9 crores, okay. And '21 has been INR 3.8 crore.
Unknown Analyst
analystINR 3.8 crores. Yes. So you have not booked INR 10 crores, INR 11 crores under .
Vimal Katta
executiveNo, we cannot now. We ].
Prakash Sanghvi
executiveSo something -- even something we can apply applications we have to do, but they are close the window. So of course, something will definitely, they will offer the . And now return on apply even though we are .
Unknown Analyst
analystRight. And last one housekeeping question. Sir what is the net cash position now? And is it around INR 450 crores, is that right?
Vimal Katta
executiveSee net earnings, they will be in the range of INR 400 crores to INR 500 crores. As we see for based on how the inventory happen. So right now, on net-net, it is more than INR 400 crores.
Operator
operatorThe next question is from the line of Dewang Sanghavi from ICIC Securities.
Dewang Sanghavi
analystAnd congrats on a good set of numbers. So my first question is regarding the API segment. There is a notable CapEx in the API sector it planned and going on. So how is the ordering from that side of the business from API?
Prakash Sanghvi
executiveAPI, the orders all in carbon steel mostly from API side only.
Dewang Sanghavi
analystOkay. That's the side of it.
Prakash Sanghvi
executiveAgain. So there we just keep going . And he has good business we are getting from side.
Dewang Sanghavi
analystAre the margins better in the API pharma side? Or is it like similar to our current margin.
Prakash Sanghvi
executiveIs the reasonable margin intent. Yes. Because they need good quantity, very short delivery it as a good market.
Dewang Sanghavi
analystRight, sir. My second question is regarding the Q4 margins, we looked at a very strong operating margin. So do we maintain the same guidance of 16% to 18% or there is a scope of upper division out there?
Prakash Sanghvi
executiveIt is all depend because it is a margin strength on the quarter, and suppose in some quarters are doing more despite of niche products, so automatic margin increase. So ultimately, it is in the range of 15% to 18%. Of course, sometime you make it because we are adding more and more in each quarter. So might be 1% here and there in a totality.
Dewang Sanghavi
analystRight. So and my question is regarding the asset order book. What -- on a ballpark basis, what kind of aggregate press orders we are targeting for the current year?
Prakash Sanghvi
executivePardon me?
Dewang Sanghavi
analystMy next question is the asset order book side? Yes. On a ballpark basis, what kind of aggregate price order bookings you are targeting for the current year, additional orders what you expect?
Prakash Sanghvi
executiveAbout our order booking target is about the 1,000 to -- INR 1,200 crore to INR 1,300 crore.
Dewang Sanghavi
analystINR 1,200 crore to INR 1,300 crore. Right, sir. And our top line guidance for FY '22 is INR 3,000-plus crores, if I get it right?
Prakash Sanghvi
executiveYes.
Dewang Sanghavi
analystOkay, sir. And on the maintenance CapEx for our business?
Vimal Katta
executiveIs between INR 20 crore to INR 50 crore.
Prakash Sanghvi
executiveSee, right now, INR 76 crores is. Yes. No, they already work in progress, it is there. And addition maintenance CapEx might be INR 40 crore to INR 50 crore.
Dewang Sanghavi
analystINR 40 crore to INR 50 crore.
Operator
operatorThe next question is from the line of from Holding.
Unknown Analyst
analystCongrats on overall a good set of performance and exciting growth story. As a key question, if I see you got a big order of INR 800 crores in carbon Steel during the quarter, there already the steel prices were at very high level. So then then what's the sense that if you've got such large orders the higher sale prices were and are we concerned that the further hikes? Obviously, quarter 1 has seen further sharp hike, the momentum of new order flow slowdown? Or this was expected that quarter 1, the steel prices were on uptrend so oil smartly placed orders before the steel price, right?
Prakash Sanghvi
executiveSo it was long-term pending. And of course, we are -- we've become all one. We have a more than 50%, 60% things that we are going to get the order we be conversion. And also once you get the order, we add finalize. So there is not much unit on price increase of and now it definitely was every -- you can say, uniquely what are the sites and what to quote and how the keep margin for negotiation or we have to be a desire to them because if you were very volatile recent 1 side in the .
Unknown Analyst
analystRight. And quarter 4 saw a very big jump in EBITDA margin. So that was purely may be holding some low-cost inventory, and that resulted in the -- there is...
Prakash Sanghvi
executiveNo inventory in because ways all the under for order booking only. But of course, some good order with the margin, we have booked some new products that we are booked to. So because of that, and place. So we get happen.
Unknown Analyst
analystOkay. So you said you're looking for close to INR 3,000 crores turnover next year. So what kind of EBITDA margins are you predicting there? Are you already INR 1,800 crores order in hand. So what's the outlook on the margin front going ahead?
Vimal Katta
executiveAs for the entire product be 16% to 18%, plus ].
Unknown Analyst
analystOkay. And what's the export order book is INR 1,800 crore?
Prakash Sanghvi
executiveYes. Our orders will be INR 1,498 crore. I mean so about INR 1,500 crore.
Unknown Analyst
analystSorry, INR 1,500. So how much of is export in that?
Prakash Sanghvi
executive[Audio Gap]
Unknown Analyst
analystAnd I missed out on the point on the export business, were you eligible for export incentives? And is the road tap rates have not been announced? So are you being hit on that? And have you provided, not provided for the same?
Vimal Katta
executiveSee, in the book, we are not provided for any ECOT income. There because of government policies, we may not be in a position to get further. So that is the thing, whatever was available that has been booked. So roughly extent of roughly INR 8 crores will be there in the book for the entire year. Thereafter, this window has been closed. So one cannot even apply. That is the situation.
Unknown Analyst
analystOkay. And what would be the CapEx of FY '22 and '23 probably?
Vimal Katta
executiveIn total, we should expect roughly INR 125 crores of addition to fixed assets, which may -- it will include INR 26 crores of which is laying there. And anything between INR 50 crores of normal CapEx plus maintenance or .
Operator
operator[Operator Instructions] The next question is from the line of from Solidarity Investment managers.
Unknown Analyst
analystI actually want to in FY '21.
Operator
operatorSorry to interrupt you, but you are not -- your voice is not audible. Can you speak a little louder?
Unknown Analyst
analystYes, yes. So I actually want just a breakup of our capacity that we have today. Within Carbon steel, we have 4 segments and get a segment subsegement wise breakup of capacity?
Vimal Katta
executiveIf you don't mind, can you share your e-mail ID, I'll just mail it to you because it will take some time for you to note it down here.
Unknown Analyst
analystYes. Okay. I have an email ID you can email me.
Vimal Katta
executiveJust send me the email. I'll share that with you.
Unknown Analyst
analystSounds good. Okay. No. And sir, my second question is on the export business, we have good visibility in recognition typically is our export business a higher-margin business compared to domestic?
Prakash Sanghvi
executiveIt is depend sometimes some special grade, some special . Otherwise, we see both the price margin for 1%, 2% here and there otherwise more or less same thing.
Unknown Analyst
analystOkay. And just one final question. In terms of our CapEx plan. Whenever we look to set our new capacity, that just to confirm my understanding that will be -- we'll be looking at at a plant in looking to go overseas and set up facilities?
Prakash Sanghvi
executiveWe are not go to correct. But can you repeat, please?
Unknown Analyst
analystYes. No, I just wanted to confirm whatever future CapEx plans you might incur, so will that be for stepping up manufacturing facilities in India itself? Or they're also open to setting up facilities outside of India?
Vimal Katta
executiveSo for sales, we are open to explore there opportunities we see outside. And for carbon steel, we have open for anywhere in the country where opportunities are going to be there, that to show on the transformation cost.
Unknown Analyst
analystOkay. And what would the benefit be of setting up a capacity outside of India, like what would the logic be for that?
Prakash Sanghvi
executiveSee, there are -- in second quarter, we price benefits at Middle East somewhere we are getting as well if you have become a local, when you get program. the main user things, and we'll get a continuous business commitment, something like that, .
Operator
operatorThe next question is from the line of Panthaki from Securities.
Unknown Analyst
analystI had some 3, 4 questions. One is on the margin side, as you stated that there was some execution of niche product during the quarter as a result of which were substantially higher during this quarter. But if I analyze your financials, so the overall share of stainless steel pipes, revenue share has declined in this quarter, and carbon steel pipe share has improved. So within carbon steel pipes, should I assume that there was some execution of more project piping orders rather than helical so pipes, which come on lower margin?
Prakash Sanghvi
executiveNo, no more on -- you can see ERW with coating of line side which quoting is sometime coating some time external coating. So we are getting at a few different margins. Once they make a bar time, then there is a coating, then there is internal coating, we like that. So what type of order has with the coating also. So then I come reflect sometimes we only at their price, then the coating of the -- sometime in the coating is . I depend on various type of order and what order we have executed during the quarter, it depends. Of course that volume goes more on the side. Sometimes that revenue is like because the run is about, say, it's something like that.
Unknown Analyst
analystOkay. So what you're saying is that the margin improvement was more because of more coated pipes execution?
Vimal Katta
executiveMore value-added products.
Prakash Sanghvi
executive[Audio Gap]
Unknown Analyst
analystOkay. Okay, sir. So as far as the existing order book is concerned, they are also largely for the value-added and quoted pipes only in carbon steel?
Prakash Sanghvi
executiveYes. Right now, it is there.
Unknown Analyst
analystOkay. So is there a possibility that we shift our margin trajectory higher from the 16% to 18%? Or you are still being conservative and...
Vimal Katta
executiveNot conservative. We are actually practical. So 16% to 18% range in such we to the hold good over a longer period, not withstanding whatever happens in the market. That is a win. So for all practical purposes, the good.
Unknown Analyst
analystOkay. Okay, sir. And as far as your new plants are concerned, you stated that commercial production has commenced from Q1 in both the plans, so I just wanted to ask in stainless steel, you had stated in earlier con calls that there were some traveling restrictions as a result of which the final approvals from the inspector, auditors was being delayed. And that was the reason why the plant has not commenced. So that all has been over now? Or...
Prakash Sanghvi
executiveSee in some of the places, not in all the spaces. So we -- right now, we will plan it wherever it goes without approval also in a distinct. Some more, we are already there. Domestically, we are already we are up to that. It is not made. But some of the companies, they would like to use it and start giving some parity like that. So it is a mix of that. So more or less, we were doing earlier also on the. Earlier we are importing set pipe. And doing . Now we have our own measure it.
Unknown Analyst
analystOkay. Okay. So, sir, roughly, if you can give us some estimates of what kind of utilization your new plants will operate both and CS in this FY '22? Can we expect this 20%, 30% of utilization, which you stated earlier?
Vimal Katta
executive15% to 20%, of course. As anything between 50% to 70%. And other item can be higher based on opportunities. And again is, I think it should be closer to 30% to 40%.
Unknown Analyst
analyst30% to 40% for what for FY '23?
Prakash Sanghvi
executive.
Unknown Analyst
analystFor FY '22, you're saying?
Prakash Sanghvi
executiveYes. Yes.
Unknown Analyst
analystOkay. 30% to 40% for carbon steel and 15% to 20% for stainless steel? Okay. So sir, this 15% to 20% for stainless steel at this low utilization, will you be able to break even on EBITDA level?
Vimal Katta
executiveSee, that one right now does not have much fixed cost in the , and other . Okay. Only and interest portions up there. So nothing much of any we are at 20%.
Unknown Analyst
analystOkay, sir. Okay. Sir, one last question from my side. Are we in any of the orders currently? Or we expect some orders? Can you in the, say, 3 to 4 months, can you just elaborate more on that?
Prakash Sanghvi
executiveThere are a number of quotations that need what we have bided and us to go. I have to open that if you have a result of some or something use the number of inquiries we are everyday. So are there.
Unknown Analyst
analystSir, can you, if you can share with us your current bid pipeline, is it possible?
Prakash Sanghvi
executiveOf course, it not.
Operator
operatorAs this was the last question for today. I would now like to hand the conference over to Mr. Sahil Sanghvi for closing comments.
Sahil Sanghvi
analystYes. Thank you, . We would like to first thank the management for patiently answering all the questions. And on behalf of Monarch Networth, I would also like to thank all the participants. Prakash sir, would you like to give any closing comments?
Prakash Sanghvi
executiveSo this is not on what we have answered and what we have told is the most important thing company had 2 new CapEx what we did. And now we have to in times to come, let's say, a beast of our plant. And this is what we have to in coming years. And for everyone because of this is a challenging time for everyone. And we have to take the of our own health, safety and then we have to do hardware, that's all.
Operator
operatorThank you. On behalf of Monarch Networth Capital, that concludes this conference. Thank you for joining us, and you may now disconnect your lines.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Ratnamani Metals & Tubes Limited transcript — plus 255,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Ratnamani Metals & Tubes Limited earnings transcripts and 255,000+ others is available through the
EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.