Resolute Mining Limited (RSG) Earnings Call Transcript & Summary

July 28, 2022

Australian Securities Exchange AU Materials Metals and Mining earnings 45 min

Earnings Call Speaker Segments

Operator

operator
#1

Appreciate everyone joining us, and welcome to the June 2022 quarterly report for Resolute Mining Limited. <<operator_script>> A presentation will come first, and after that we'll open it up for questions and answers. <<operator_script>> At this point I'll turn the call over to Mr. Terry Holohan, CEO. Go ahead, sir.

Terence Holohan

executive
#2

Thanks so much, and good morning, everyone. I appreciate you all making time to be with us this morning. With me today is Doug Warden, our CFO — he's been on a number of these calls before. Also joining us is Geoff Montgomery, who has taken over the Chief Operating Officer role from me, overseeing operations. He'll walk you through the operational side in a bit more detail. Just a quick bit of background: Geoff has spent more than 35 years in this industry and has been working on this project for over 12 months now on the technical side, so he has a strong grasp of our operations. I'm pleased to say the transition from me to him has been seamless. My plan is to run through the highlights — go through them quickly — then hand things to Geoff for a more detailed look at operations, then to Doug for the financials, and after that we'll open it up to questions and answers. Beginning with safety: we're very proud that we're now below the magical 0.9 recordable injury frequency rate. We've gotten there, I think, through a very tough stretch. This marks the first time in 12 months that we've returned to these levels.

Terence Holohan

executive
#3

And as you may recall, we discussed this at length during the previous quarterly call. We also factored the 60,000 man-hour stoppage at the sulfide plant into Q1. Back then, we weren't able to bring in much outside labor. So we worked mainly with 90% of contractors drawn from within Mali and Syama depth. And we take a lot of pride in our safety record, where it stands today. On the Malian situation, you've likely heard that ECOWAS has at last lifted the sanctions, which we noted in early July. I believe we said last time that we anticipated this happening in June. It came a month late, but everyone welcomed it. The country is now recovering. That will take a bit of time, and they are already beginning to turn their attention in the city toward the elections, which they expect will now happen within 2 years. There are still security issues and activities ongoing in the country. We continue to watch things very, very closely. And once again, as of this point in time, we have experienced no scares or interruptions to our business, and we have continued operating as usual. On production, we once again poured slightly more gold than we had planned.

Terence Holohan

executive
#4

Once again, we've drawn down a modest amount of metal from inventory. And at this point, across the most recent quarter, we're running at a rate above 350,000 ounces per annum. This is precisely where we anticipated and hoped we would land, and in fact we flagged it a couple of quarters back. Even more significantly, we've now posted 4 consecutive quarters of steady gains, and we anticipate that carrying on into the future. Looking at the individual operations, Mako is running smoothly. Geoff will share a little additional detail on that. The sulfide is a major development for us. Following 18 months of intense attention on the sulfide plant, which we've consistently described as the constraint, mining has now become the new constraint. It's shifting over at this moment toward mining and toward the milling circuit, where the teams -- teams are genuinely concentrating on figuring out how we can unlock those areas. The Syama plant is currently running at a rate of 2.4 million tonnes per annum. If you recall last year, we achieved a record 2.1 million tonnes per annum through that plant. And so we're finally pleased that, after roughly 30 years, we believe we've checked the box on processing this challenging double refractory gold mineralization at Syama.

Terence Holohan

executive
#5

And we see that as a pretty significant leap forward. I know I've mentioned this in the past, yet I'll say it once more: sulfides represent what lies ahead for Syama, where our books already hold a respectable 7 million ounces, though the count continues. We keep building on that total. I'll get into that soon. Right now, as we speak, more sulfide material is being added to our balance sheet. Since we now have a steady sulfide operation, at last we can concentrate on operational costs and efficiencies within that circuit, where we think opportunities are present, while we keep seeking ways to grow it further. Turning to the oxide circuit, with rain arriving early in June this year, we devoted considerable time during the first half of the year to getting the open pits ready for the rainy season and beyond, focusing on both grade control and pre-strip. And the mining team continues to hold that they will achieve their overall plan, which is always back-end loaded, with the highest grades arriving through Tabakoroni in Q4 this year. Given the cost and price pressures all of us face across the industry, this is a circuit where we are most sensitive to cost fluctuations, so we're making productivity the priority in all our efforts.

Terence Holohan

executive
#6

Over the longer term, we're currently evaluating whether the oxide plant could be converted into a sulfide plant through the addition of a flotation section. And once again, Geoff will provide a bit more detail on that as well as on all the other points there. Regarding all-in costs, yes, we posted a headline figure showing an 11% rise quarter-on-quarter. However, I'd like to draw your attention to the fact that when we examine pure cash costs alone on a quarter-on-quarter basis, that is, leaving out the noncash adjustments, we were in fact flat thanks to the additional units we produced during the month. Worth noting are the surges in diesel prices in Mali. We experienced some panic buying and limited availability. This is obviously also connected with the sanction lease, et cetera. We observed prices swinging between $1.2 and $1.3 a liter. By contrast, in neighboring Senegal, prices sit near $0.76 per liter. We're all aware, having lived through this in the past, that if such prices persist, if these elevated energy prices persist, they tend to have <<inaudible>> an impact on every raw material price and consumable. And we're keeping our focus on both the additional gold units, as I mentioned earlier, on the previous call, and on greater productivities, along with enhancing our dosage systems and effort -- sorry, in order to offset any potential increases.

Terence Holohan

executive
#7

On top of that, there are certain one-time expenses, and these relate to open pit grade control. At this point we're running several months ahead of the mining schedule — earlier I said a couple of quarters — because that gap needs to be established ahead of mining, and as I noted, we've completed a substantial amount of pre-stripping. There are also noncash charges tied to the additional release of Golden Circuit and the sulfide operations. Doug will provide a bit more detail on where things stand with those costs. Exploration — I'd say once more that, with the big tick in the box on sulfide processing, this is turning into a step change for us at Syama. Our geologists have headed back out there with renewed energy, and they're searching for higher-grade sulfide. As I said, we already hold 7 million ounces. But we've gone back to the original A21 satellite pits, located 4 kilometers north of the Syama complex. You may recall that in '21 we upgraded those pits. At year-end, we reported a mineral resource of 1.4 million ounces at a grade of 2.14. This year, meanwhile, we've drilled a 2.5-kilometer fence line using 150-meter deep holes. So at this point they aren't deep holes.

Terence Holohan

executive
#8

Beneath the spacings, we've encountered anomalous gold in every hole, and beyond that we identified a broad set of higher-grade intercepts, which we released during the past quarter. At the moment we're infilling this initial pass, and finishing it will consume most of the remainder of the year, at which point we should have a complete MR estimate, likely by year-end. That said, we will put out an interim mineral resource covering some of the easily accessible mineralization, which in terms of grade and tonnes is quite exciting. By September, aiming to give ourselves room — if we're looking at another 18 months or so — we'd like to actually develop this in competition with the underground, which also lets the underground advance and raise its output at a somewhat slower rate, so the grade isn't compromised. We've also started a helicopter-borne low-level, high-density aeromagnetic survey. It's now flying east-west lines at 50-meter spacing across the entire 85-kilometer strike, and we're very excited to see what that work is. Since the helicopter flies only 20 meters above the ground, this should be a very high-resolution aeromagnetic survey. And we've also finished our first underground core exploration drilling bay, though it is covered at grade control.

Terence Holohan

executive
#9

We now have an exploration drill at the 950-meter RO level. This is adding on the higher-grade southern section, which we've talked about before, which we know contains some higher-grade material and some long-haul open stope opportunities. Since the original exploration model makes up roughly 5% of the total underground ore reserve, and this was at the higher-grade end. Okay. So that's exploration. On debt, you'll see we've paid down an additional $15 million on our RCF facility. So to sum up, I feel it's been a very busy quarter, but a very rewarding one. I think we took some key, key steps here. And we do keep our 2022 guidance of 345,000 ounces at $14.25 per ounce. And with that, I'll hand over to Geoff to give you a bit more color on the Mako operation -- sorry, on the operations. Thanks, Geoff.

Geoff Montgomery

executive
#10

Thanks a lot, Terry, and good morning, everyone. I'll begin with Mako. Safety is clearly one of our main priorities, just as it is across all of our operations. I'm happy to report that we recorded 0 LTIs during the quarter. That said, one thing we're focused on is fatigue. We're seeing a number of high potential injuries resulting from fatigue incidents. I'll say a bit more about our plans to address that when we get to Syama, where we have a pilot program running. On the mining side, we got better grades in the pushback area, with much less impact on scheduled mill stoppage. I'm really pleased that the mill optimization software we've been developing for almost a year now is close to completion, and we've seen better grind and better recoveries. That has let us cut the number of mill relines from 43 per year. Also, the TSF lift is now finished. On the metallurgical side, we're currently using hydrogen peroxide as a temporary measure. That has helped us lift our recovery by 0.6%. We've placed an order for an oxygen plant, which we expect to be operating in quarter 1 of 2023, and that will sustain this higher recovery.

Geoff Montgomery

executive
#11

Recoveries have stayed 2% over budget, and for the rest of the year we're projecting a 92.5% recovery rate. On the mining side as well, we're on the verge of signing the contract extension for contract mining at AMS. Another item we're working on is the power plant contract, which comes up for expiry in October. We're also quite near to switching that contract to a different service provider. Once that's done, we'll put investment into using solar power to cut our greenhouse gas emissions. On the ESG front as well, we have an exercise underway examining water conservation through water captured from the pit, better water recycling, and also cutting the water in the TSF. That has led to 10% less extraction from the Gambia River. This remains an ongoing process. We've launched a cost reduction exercise in response to the cost pressure Terry alluded to, and Doug will go into that a bit later. Another of the main focus areas we're continuing at both operations is continuous improvement. And I'm pleased that this isn't just a manager exercise — staff at every level of the mine have taken it on.

Geoff Montgomery

executive
#12

Turning now to Syama more broadly. On safety and the fatigue problems, I want to expand a bit. We've had several high-potential incidents involving heavy vehicles where operators fell asleep. Monitoring equipment is now fitted in the cabs. So, for instance, if you yawn, it speaks to you — yawning and <<inaudible>>. Should your eyes shut, it speaks to you and gives a warning. If you pick up your cell phone, it warns you, along with a few other things. And I'm happy to report that the 60 incidents we saw at the outset are down to 10 per day. There's still a long way to go — it remains unacceptable — but that's something we're working on. We're also examining putting solar power on the TSF. For us that's a longer-term project. Beyond that, the culture of continuous improvement we've mentioned is being taken up by both the management and lower management teams. We're doing this through the most consultants. Turning to sulfide. Starting once more with the mining side. Our focus is on underground fleet availability. We're not where we want to be, and we're also reviewing the fleet type. Over the quarter, we concentrated on dewatering the underground to boost safety and operability and efficiencies in the underground.

Geoff Montgomery

executive
#13

Additionally, one new area we will be developing during 2023 is the Syama site, where long-haul stoping will be carried out. What benefits us there is that it should deliver a higher grade compared with the current Syama block, and it makes use of infrastructure already in place. As Terry mentioned, the A21 pit is beginning to look quite promising. And drilling and modeling work there is ongoing. Regarding the underground grid outlook, we are continuing the shift from transverse to longitudinal in order to enlarge the grid. That said, we only do this in suitable areas, where the geology permits. Turning to the processing plant: roaster performance in the quarter gave us record tonnage. In fact, we can now process 10% more than the mill equivalent. That provides us with catch-up area, catch-up capacity. As a result, we have been able to lower our gold in circuit by recovering gold from ponds and various villages on the floor. This will carry on through the next quarter. We expect to begin depositing in-pit field at the old Beta pit in quarter 4. So our last capital intensive TSF raising for a number of years has now been completed.

Geoff Montgomery

executive
#14

Unfortunately, we ran into some delays getting the cleaner flotation cell circuit and the onstream analyzer commissioned. The cause was problems with the presentations to the sampler. I'm happy to report that we made breakthroughs on that front during the last two weeks. And my hope is that over the coming few months, we can bring the cleaning circuit on OSA online, which would let us run a reduced mass pool and achieve the higher recoveries we had expected earlier in the year. We've also finished the new reagents, efficient circuits, <<inaudible>> and they cover sulfate, and that gives us tighter control and a greater ability to cut reagent consumption. Given the long stoppage in quarter 1, we can now extend the interval between roaster shutdowns. So we anticipate the next shutdown 3 years out from the March shutdown, which we'll carry out to swap out the burners and perform some work on the spray color. Once that work is complete, we'll shift to 5 yearly shuts, a substantial improvement over the biannual shuts of the past. Our focus remains on debottlenecking the milling circuit to -- as we work to utilize the installed capacity around the motors.

Geoff Montgomery

executive
#15

A consultant has been on site with us lately, and he is examining which near-term actions we can take and what the longer-term alternatives are. Beyond that, we have kicked off what we refer to as the enhancement project, which will be examining roughly a 30% rise in -- sorry, a 25% to 30% rise in mill tonnes ounces. That study was carried out at a prefeasibility study level, and we are hoping to have it finished by year-end. The mine operating system, MOS, has performed very well in the processing plant and maintenance. We now self-manage it in those 2 areas. That said, we are currently attempting to roll it out to mining and supply across a couple of other areas. The oxide circuit gave us a tough quarter. Even so, we finished our wet season preparation for <<inaudible>> season. On top of that, we will finish the prestrip at Taba within this quarter. As a result, we will see a meaningful drop in strip ratio in quarter 4, which clearly will lower our cost and provides us with access to higher grade ore. Another thing worth noting is that we were very much operating hand to mouth with bit control drilling and mining.

Geoff Montgomery

executive
#16

I'm really happy that control drilling is now a number of months ahead, <<inaudible>>, which lets us plan the mine better and mine more efficiently. Across the six months left in the year, our focus will be on grid dilution of the pits. The other — regarding the processing circuit for oxide materials, we've made some modifications to the oxide combination circuit, and that has produced a 4% gain in throughput, which has partly offset the decrease in grids. Thank you very much. We can now hand things over to Doug.

Terence Holohan

executive
#17

All right, thank you, Geoff.

Douglas Warden

executive
#18

Terry, please proceed.

Terence Holohan

executive
#19

As I was mentioning, everyone can understand there remains plenty of work still to be done on the technical front. And I believe we now have a highly capable team in place concentrating on all of these productivity enhancements. All right. Let's turn things over to Doug so he can walk us through the financials.

Douglas Warden

executive
#20

Yes. Thank you, Terry. Yes. Well, I'll spend just a few minutes giving a little more detail on all-in sustaining and cash costs, the cash flow waterfall during the quarter, and a brief update regarding the hedge book. Starting with unit costs. The June quarter cash cost of $14.72 per ounce came in broadly consistent with the March quarter figure of $14.86, as Terry mentioned, since greater sulfide and Mako throughputs and grades offset increased cash costs, extra tailings storage CapEx, and a smaller quarter-on-quarter benefit from gold recovered in circuit along with the oxides already discussed. As is the case across the industry, we are dealing with rising input costs, concentrated largely on diesel, but also consumables and heavy fuel oil, which fuels the Syama power plant. To give one illustration, fuel costs ran roughly $4 million above Q1 levels during Q2, and that increase was entirely tied to Syama. Costs in Senegal were in fact marginally lower, owing to the way the government sets diesel pricing there compared with what we pay in Mali, as Terry already referenced when quoting cents per liter. So although unit cash costs per ounce stayed broadly consistent with the March quarter, the June quarter all-in sustaining costs, as reported, clearly rose 11% to $1,540 from $1,383.

Douglas Warden

executive
#21

That rise was mostly driven by noncash inventory adjustments, which we lay out on Page 2 of our quarterly. What I would encourage you to focus on, I guess, is where we stand at the half year. So despite the quarter-on-quarter shifts, which take in the effects of the roaster shutdown and the substantial gold recovered from circuit during the first quarter, in the March quarter — when you view it at the half year level, group all-in sustaining costs came in at $1,463, and those noncash movements were in fact a benefit of only $14 an ounce. Yet if you work through it quarter by quarter, the inventory shows some sizable swings, and I'm glad to field any questions on that. I'd note, as I said and as Terry said, the greater sustaining capital in the second quarter that also feeds into that all-in sustaining cost — it's roughly, it came to about $6.3 million more in the June quarter than in the March quarter. And as Terry and Geoff have both mentioned, that was mostly tied to the periodic spend on tailings facilities. So we ought to be set for a while now when it comes to tailings facilities. Let me just turn to cash flow.

Douglas Warden

executive
#22

And I’d like to point you to the waterfall chart in the quarterly as I walk through it. Operating cash flow came to $42.3 million for the quarter. We’ve already covered CapEx, $19 million, which was above normal and more weighted toward sustaining CapEx, and therefore it affected all-in sustaining costs. Exploration was broadly in line with prior quarters, largely focused on that drilling Terry mentioned at Syama, plus some work at Mako as well. On working capital, which we’ve just highlighted here, there was a negative impact of nearly $24 million. This was really, as we said in the quarter — sorry, the quarterly report, tied to the timing of creditors and also some build-up of consumables inventories given the inflationary environment we’re facing, the wet season in terms of building up stocks ahead of it, and also the ECOWAS sanctions, which were only lifted after the quarter ended. So we’re just sort of preparing ourselves for those events. And so that working capital moved up a bit in the quarter. We would expect it to normalize in the third quarter, but it was a drain on cash flow for the June quarter.

Douglas Warden

executive
#23

Regarding the asset sale process, selling our stake in Turaco brought in $4.5 million. We've discussed the $15 million voluntary repayment on the revolver. As for the government dividend withholding tax, it's bigger than in other quarters since we paid the annual withholding tax to the Senegalese government tied to the dividend we distribute there, both to ourselves and to the Senegalese government. That withholding tax gets paid all at once. So $4.5 million of that $5.4 million came from that. Once all of that is factored in and cash and bullion balances are netted off, we ended the quarter with net debt of $182.8 million. A quick update on the hedge book. As you know, under the debt facilities, we're required to hedge a minimum of 30% of forecast production for the next 18 months. As at 30 June, we had 230,000 ounces hedged at an average price of USD 1,875 an ounce. With that, I'll hand back to Terry to wrap up. Thank you.

Terence Holohan

executive
#24

Thanks, Doug. So following on from that, I'd say the story now is 4 quarters in a row. We're hoping for a few more. Right now we're putting real effort into sweating our assets, hunting for better sulfide materials that let us add some flexibility to the underground mine expansion, and clearly examining how to unlock some of the large mineral resources and oil reserves sitting on our balance sheet. And we're glad to take questions. Thank you very much.

Operator

operator
#25

Thanks. <<operator_script>> The first question is from Andrew Bowler at Macquarie.

Andrew Bowler

analyst
#26

You just touched on the widely recognized worldwide inflation situation, along with rising diesel costs and consumable prices. Yet I noticed wages didn't come up at all. Could you walk me through what you're observing in West Africa regarding wage inflation — that is, whether any exists?

Terence Holohan

executive
#27

At this moment, we aren't observing any inflation. And I'd say that moving forward, taking a nearer-term look now, we've tidied up operations at the site, particularly at Syama. Going forward, we're likely looking at some consolidation there. I mean, obviously, a couple of months ago, given how the plant was running, we were actually spilling a lot of material onto the floor. Then you need crews cleaning up continuously. Those crews are still working around the clock, cleaning up while GICs is there. And as Geoff has mentioned, we've probably got another quarter of that. But after that, I'd suggest we should see some thrifting. So at this point in time, we don't see any major headwinds when it comes to wage increases.

Andrew Bowler

analyst
#28

Okay, and this will be my final question. Clearly, the removal of sanctions on Mali is welcome news. But could you elaborate specifically with regard to Resolute on why that is beneficial? And roughly what positive effects does it bring? Or, I suppose, what negative effects had you been observing prior to the sanctions being lifted?

Terence Holohan

executive
#29

I think at first, the cost savings from being indirect are not direct, so to speak. So initially we ran into a lot of trouble bringing raw materials in via the usual channels. As a result, we had to take alternative routes. Four of the seven countries were shut, meaning we needed to reroute plenty of equipment and so on. We stockpiled somewhat. I wouldn't claim we'd definitely ease those stock levels, particularly given the price pressures we face at the moment, but there will be additional indirect savings. I don't believe we've truly seen a step increase in cost as a result of sanctions. And for us, it's very much business as usual. The modest cost reduction, I think, was probably more COVID related over this period. That said, we're aware that freight costs represent a major issue and freight times represent a major issue throughout the industry. So we remain continuously focused on that. We now have a dedicated freight forwarding company concentrating on all our freight. But I wouldn't say -- I'd say we're neutral at this point, Andrew.

Andrew Bowler

analyst
#30

That's fine. And I believe someone noted that a portion of that $23.9 million working capital build involved stockpiling inventory ahead of the sanctions being lifted. Could you share some detail on how much of it came from accumulating processing inventory along with consumables and similar items? That way, we can work out what a more normalized pace for working capital would look like going forward.

Terence Holohan

executive
#31

Could you help with that, Doug?

Douglas Warden

executive
#32

Yeah. Andrew, I’d say, just speaking broadly, probably two-thirds of that comes from creditors — a decrease in creditors, just back toward a more usual level after the roaster shut. And what’s left is roughly inventory and the buildup of those inventories. So that probably gives you a sense of it.

Operator

operator
#33

Thanks. The next question is from Reg Spencer at Canaccord.

Reg Spencer

analyst
#34

Terry and Doug, I want to pick up where Andrew left off regarding working capital. Is it fair to expect that to reverse out? I may have missed this, but Doug, did you say you'd anticipate most of that unwinding during the September quarter?

Douglas Warden

executive
#35

Yes. By that, I don't mean it will necessarily flip around and produce a nice big boost to cash flow. What I meant was simply that we'd expect the swing in creditors to be less pronounced during the third quarter. So if we saw a reduction in creditors of roughly $13 million, as we did in the second quarter, we're not expecting that to be significant in the third quarter. So more or less flat, give or take.

Reg Spencer

analyst
#36

All right, that's clear. So with that in mind, Doug, from here forward, given the gold sales you reported and your all-in sustaining costs, ought we to anticipate improved cash conversion?

Douglas Warden

executive
#37

Right. Right, since you aren't observing pressure stemming from working capital tied to inventory buildup and a decrease in creditors. I believe at this point, with sanctions finished and once we make it through getting ready for the wet season, creditor levels will likely return to a more typical point, and that's when the large fluctuations could show up.

Reg Spencer

analyst
#38

I might have missed this, but were we supposed to be anticipating tranche three of the Bibiani sale during this quarter? Or am I slightly ahead of things there?

Douglas Warden

executive
#39

You're slightly ahead of schedule on that. It's expected in roughly one month — arriving in late August.

Reg Spencer

analyst
#40

Alright. Alright. That's fine. And then finally, perhaps one for you, Terry. Clearly, Syama North has had fantastic drilling that you've put out. You've mentioned on the call that, that may ultimately give you some more flexibility with the underground. But are you able to give us at this early stage an idea of how that material or how those resources might fit into any mine plan, when that could be developed and how soon could that be developed?

Terence Holohan

executive
#41

We could begin prestripping during the final quarter of this year, provided the results turn out as favorably as we anticipate. You're likely aware of how swiftly we can move into new areas once we've completed the ore reserves. Our setup allows us to update our mineral resources every month. That's the reason we wanted to release some figures during this quarter. Right now we're carrying out our initial ore reserve counts. These are preliminary, since not all the drill results have come in yet — those results arrive daily, and we're simply trying to draw a line and say, alright, let's put some numbers down at this point. Let's get them released. But as I mentioned, with every hole we drill, we're seeing a bit of gold. And we've hit some really high-grade intersections. It's exciting. It's longer, with a 2.5-kilometer slide length. We've done some test work on the metallurgical side, and it's behaving much like the individual Syama type material. So recoveries are relatively good. So we just need to complete that study now on the oxide plant and determine, at what point do we consider converting that?

Reg Spencer

analyst
#42

Could you...

Terence Holohan

executive
#43

Apologies, that relates to the longer-term picture. If you want to add a flotation circuit at an oxide plant, the minimum you're looking at is 12 to 18 months. And that assumes a new swing. What I'm really getting at is our earlier statement that we'd typically operate the oxide plant on upside for the next 4 years. And with the aeromags we're currently doing, there's a good chance we'll uncover some additional material. But that material will now be competing against the sulfides, which is a favorable position for us to be in.

Reg Spencer

analyst
#44

All right. Is there any sign of improvement in the resource grade you currently have? Or clearly, the current resource sits at roughly 2 grams. Your underground comes in at what, 2.6 for reserve grade. Could there be a stage where that underground material might displace some of — sorry, could the open pit displace some of the underground, assuming the grade is there and depending on ore availability? Because I do recall what you said about that flexibility letting you reduce the pace of underground production so as to protect the grade, or the integrity of the grade, for want of a better phrase. Is...

Terence Holohan

executive
#45

Yeah, so honestly, it's too soon right now to say something like that. That said, I'd say my hope is that we'll see solid competition between the open pit sulfide and the underground sulfide.

Reg Spencer

analyst
#46

Alright. Great. And finally, could you give me some sense of how much of your total operating expense — this is probably one for you, Doug — fuel and diesel represents, just in broad percentage terms?

Douglas Warden

executive
#47

Right. So before this year, it was likely 12%, 13%. I'd say it's now climbing nearer to 15%.

Operator

operator
#48

The next person to ask something is G Khan, who is calling in from Group G7.

Speaker

unknown
#49

My question concerns the balance sheet. As has been the case each quarter lately, output appears steady, yet the cash coming in has been cut back considerably — so is there some way to tackle that, and can cash get better from here on?

Douglas Warden

executive
#50

Terry, shall I handle that question?

Terence Holohan

executive
#51

Absolutely, go ahead.

Douglas Warden

executive
#52

Yes. So, clearly, during this quarter we dealt with the working capital issue we've mentioned before, and that alone hit cash flow by roughly $23 million. On top of that, we moved 27% more material through the oxide operations while producing fewer ounces that quarter. Those are really the main drivers behind the weak cash flow generation. So essentially, it comes down to reaching a steady state with our working capital and ramping up the ounces — clearly in oxide, but also delivering incremental improvement in sulfide. To put it in a roundabout way, we've got to produce more ounces and return working capital to normal levels. And we should look at our overall cash costs wherever possible, as Terry was hinting at when he answered the question about wage inflation.

Speaker

unknown
#53

Okay, so on CapEx and working capital — does that sit inside AISC, or is it separate from AISC?

Douglas Warden

executive
#54

No. On sustaining capital — that ties into another point about this quarter, and why all-in sustaining costs came in higher — because sustaining capital gets counted within the all-in sustaining cost. And most of the capital this quarter — over $16 million out of that $19 million, I believe — was sustaining capital, and so it shows up in that all-in sustaining cost.

Speaker

unknown
#55

So going forward, in the next quarter, do you think the cash flow is going to improve? I mean, do you expect CapEx and working capital to come down?

Douglas Warden

executive
#56

Yes. As we mentioned, a sizable portion of that sustaining capital—roughly $7 million—related to tailings facilities. So we don't anticipate that recurring, definitely not in the second half and not next year either. It's a periodic investment. And on working capital, I believe I've addressed that—around creditors it should normalize. So we don't expect it to be a drain on cash flow the way it was in the second quarter.

Speaker

unknown
#57

Right, right. So, from where you sit, you're expecting cash flow to get better and the balance sheet to get better as we go forward?

Douglas Warden

executive
#58

That is definitely the intention.

Speaker

unknown
#59

Yes, there’s a plan in place. Yes, it is a plan. Steady production is taking place. All is as it should be. What I mean is, the situation in Mali is now improving. So with output where it ought to be, clearly the shareholder wants to see the money. At the end of the day, the balance sheet has to get better, regardless. I mean, we’ve put in a lot of effort, a lot of production. But when all is said and done, cash flow remains as it is and continues declining. So it kind of creates panic, a rather alarming situation in the market that our Resolute is not performing. Yet I’ve been at Resolute for roughly 4 years and, yes, it has gone up and down. But right now things have reached a point where everybody believes improvement will come, because everything has now been put in place. The groundwork is done. And yes, even so, there is still no cash coming in. That is what everyone is watching for. And so my question is, will it get better in the coming quarters? Or will it remain flat or keep declining?

Douglas Warden

executive
#60

Terry, should I take that question? Well, I think...

Terence Holohan

executive
#61

Yeah, I'd say you've got a point there.

Douglas Warden

executive
#62

Go ahead, Terry.

Terence Holohan

executive
#63

Yeah, I'd say that's accurate for where we stand. What I mean is, our attention has been very, very heavily on repairing the circuitry and repairing the mine. I believe stabilization is beginning to show. At this stage it's almost as if we've hit the reset button. When you've been in the kind of situation we faced over the last couple of years, there are plenty of problems you need to work through, and those are now starting to produce cash. But we're beginning to get our head above water now, you're right. And beyond that, we do expect our cash flow to get better over the months ahead.

Operator

operator
#64

Thank you. That brings us to the end of the question session. I'll now return the floor to Mr. Holohan.

Terence Holohan

executive
#65

Alright. I really appreciate everyone taking the time to focus on this today. I realize it's a hectic day and a hectic quarter. And as I mentioned, the key takeaway from all of it, in my view, is that we're keeping our guidance intact as we move ahead. To me, that represents a significant move for this company. Thanks so much.

Operator

operator
#66

Thanks. That brings today's conference to a close, everyone. We appreciate your participation. You can go ahead and disconnect your lines now.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Resolute Mining Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Resolute Mining Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Resolute Mining Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.