Riot Platforms, Inc. (RIOT) Earnings Call Transcript & Summary

February 24, 2025

NASDAQ US Information Technology Software earnings 69 min

Earnings Call Speaker Segments

Phil McPherson

executive
#1

Thanks, Michelle. Hello everyone, and good afternoon. This is Riot Platforms' conference call covering results for Q4 and the entire 2024 fiscal year. I'm Phil McPherson, serving as VP of Capital Markets and Investor Relations. With me today from Riot are Jason Les, our Chief Executive Officer; Colin Yee, Chief Financial Officer; and Jason Chung, Executive Vice President, Head of Corporate Development and Strategy. Our earnings press release for the fourth quarter and full year 2024, along with the earnings presentation that goes with it, is available on the Riot Investor Relations website. Those materials are meant to complement the prepared remarks we're making now, and they contain a discussion of certain non-GAAP items. Non-GAAP financial measures we provide shouldn't be viewed as a replacement for, or as better than, financial performance measures determined under GAAP. We include them as extra clarifying items to help investors gain a deeper understanding of how the company performed in the fourth quarter and full year 2024. Today we'll be offering forward-looking statements about possible future events. Such statements rest on management's present expectations and assumptions, and they carry risks and uncertainties. Actual outcomes might differ materially because of factors covered in today's earnings press release, in remarks and answers given during this call, and in the Risk Factors section of our Form 10-K and Form 10-Q, including for the year ended December 31, 2024, which will be filed later today, along with other filings made with the Securities and Exchange Commission. With that said, I'll hand things over to Jason Les, Riot Platforms' CEO.

Jason Les

executive
#2

Thank you, Phil, and hello everyone on this afternoon's call. Prior to reviewing Riot's 2024 results, I'd like to zoom out and consider the wider sector. When Riot first began its Bitcoin mining operations in 2017, the entire network's hash rate was just 3 exahash. By the time 2024 arrived, Riot alone had grown its self-mining hash rate by 19.1 exahash, bringing its total to 31.5 exahash, even as the global network hit a record peak exceeding 750 exahash. The Bitcoin ETF's approval in January 2024 brought in more institutional participation, resulting in what stands as the most successful ETF debut ever as measured by AUM. And by July 2024, Bitcoin had emerged as a major issue in the Presidential campaign. And after the election, Bitcoin reached new all-time highs of $75,000 and subsequently $100,000. Riot has mined Bitcoin since 2017, holding conviction in this long-term value proposition; in January 2024, Riot ceased selling Bitcoin generated through its mining operations so it could retain more Bitcoin. On top of that, we bought Bitcoin for the first time in December 2024, after our inaugural successful convertible debt offering, ultimately adding more than 10,000 Bitcoin to our balance sheet across the year, finishing 2024 with 17,722 Bitcoin valued at $1.7 billion, using the Bitcoin price of $93,354 as of December 31, 2024. Our efforts to get the most out of our unique power assets shouldn't be read as a shift in how we see Bitcoin over the long haul. Right now Riot controls about 4% of the worldwide network, and as a key operating metric we'll continue chasing a compounding rise in the value of Bitcoin held per share, while also working to get the most value out of every asset we own for our shareholders. In 2024, demand from AI/HPC for power access caused Bitcoin mining power assets to be repurposed for AI/HPC use. That pattern has continued into 2025, pushing up what large-scale sites with secured power access close to major metropolitan areas are worth — places like our Corsicana and Rockdale facilities. Riot shareholders have a rare, time-sensitive chance to capture the worth of what we own and to drive shareholder value as high as possible, and I'm glad to provide more news on how hard we're chasing that opening. First, let me walk through what Riot got done in 2024. We brought the Corsicana site online successfully. After roughly two years of work, Riot energized a 400-megawatt substation, built 4 buildings, and rolled out immersion systems along with miners, finishing the year at about 14 exahash of self-mining hash rate from Corsicana by itself. Our Bitcoin yield strategy. At the start of 2024, ETF greenlights were about to happen and the halving for that year was drawing near. Riot chose to keep every Bitcoin it mined and to concentrate on boosting how much Bitcoin each share represents—what we call Bitcoin yield. That strategy delivered close to a 40% Bitcoin yield across 2024, plus over $100 million of added asset value growth during 2024 by itself. Now, about our convertible senior notes offering: matching Riot's method of producing yield from Bitcoin and our aim of consistently expanding the Bitcoin we hold per share, we took advantage of favorable market conditions and wrapped up our inaugural convertible senior notes offering. That deal brought down what it costs us to raise capital, broadened the pool of institutional investors involved, and the money raised went toward purchasing Bitcoin and further boosting Bitcoin yield. Turning to the Block Mining acquisition. That marked Riot's first deal in over 2 years, and it was also our initial move to expand beyond Texas, taking us into an appealing new jurisdiction that provides 60 megawatts of mining capacity today, with room to grow to 305 megawatts and beyond. Then there's the E4A acquisition, the latest one we've made, which complements our engineering operations and strengthens our core operating abilities as well. As we look ahead to 2025, our plan is to grow our Bitcoin mining hash rate by about 22%, and at the same time we'll be aggressively pursuing opportunities in AI/HPC so that we can maximize the value of the unique assets we hold. We believe this approach brings the biggest return for our shareholders, and it also allows us to stay flexible as fresh market opportunities continue to emerge. With a strong balance sheet, a reliable operations team, and leadership focused on value creation, I have real excitement about our future; with that said, I'll turn the call over now to Riot Platforms' CFO, Colin Yee.

Colin Yee

executive
#3

Thanks, Jason. It's great to be here to walk through Riot's financial results for Q4 and the fiscal year that ended in 2024. To make things easier to follow, we've put the key metrics on Slide 6, which gives you a snapshot of the important financial and operating figures for the full year 2024. That said, let's dive right into the specifics on the slides that follow. Over the course of 2024, Riot grew its self-mining hash rate from 12.4 exahash up to 31.5 exahash — that's a 154% jump across the year, which beat the growth in the global hash rate, which climbed 67% during 2024. On top of that, Riot mined 4,828 Bitcoin in 2024, which is 27% less than what we mined in 2023, mainly because of the halving event that took place in April 2024. Even so, despite that April halving, Riot finished the year at roughly 16.6 Bitcoin produced each day, versus 16.8 Bitcoin per day when the year began. Back in January of last year, Riot halted sales of mined Bitcoin so we could build up our holdings before the halving; along with December's convertible notes offering, whose proceeds went toward buying Bitcoin on the spot market, we've grown our Bitcoin holdings per million fully diluted shares from 31.8 to 44.3, which works out to a Bitcoin yield increase of 39% for the year. Looking ahead, we'll stay focused on growing Bitcoin yield so that our shareholders can take part in the long-term value creation opportunity we think Bitcoin offers. Riot closed out 2024 with 17,722 Bitcoin on hand, up 141% from the 7,362 Bitcoin we held when 2023 ended, and Riot keeps retaining 100% of every Bitcoin it self-mines; for the full year 2024, Riot posted total revenue of $376.7 million, up from $280.7 million in 2023, which is a 34% year-over-year gain; the main driver behind that increase was stronger Bitcoin prices. Gross profit for the full year 2024 came in at $147.6 million, compared with gross profit of $97.6 million for the full year 2023. Non-GAAP adjusted EBITDA for the full year 2024 reached $463.2 million, compared with non-GAAP adjusted EBITDA of $214 million for the full year 2023. Riot adopted FASB's final standard on crypto assets issued in December 2023, and under that standard Riot now recognizes its Bitcoin holdings at fair value, which means changes in fair value are now recognized in income. For reference, Bitcoin's price at the end of 2023 was $42,265, and at the end of 2024 it was $93,354. That produced a mark-to-market upward adjustment of $458.7 million for 2024. Net income for the full year 2024 was $109.4 million, or $0.40 per share, versus a net loss of $49.5 million, or $0.28 per share, for the full year 2023. Full year 2024 net income includes stock-based compensation expense of $125.2 million, an unrealized loss on marketable equity securities of $69.5 million, and depreciation and amortization of $212 million. Just to remind everyone, starting in Q1 2024, we changed how we depreciate mining equipment, moving from a 2-year schedule to a 3-year one, after reviewing how our own operations have performed historically. Across all of 2024, revenue from Bitcoin Mining came to $321 million, which is a 70% gain over the $189 million in Bitcoin Mining revenue for all of 2023. The cost of revenue for Bitcoin Mining is mostly made up of direct production expenses from Bitcoin Mining operations, such as electricity, labor, insurance and other costs, though it leaves out depreciation and amortization. Gross profit from Bitcoin Mining this quarter reached $165.5 million, a 52% margin, versus $163.6 million, or an 87% margin, for all of 2023. Our cost to mine, excluding depreciation, came to $42,011 per Bitcoin in Q4, with power cost making up $33,281 per Bitcoin, or 79% of the total cost per Bitcoin. Looking quarter over quarter, power costs rose from $0.031 per kilowatt hour to $0.038 per kilowatt hour, since a larger share of our power was bought at the Corsicana facility at spot market prices, which on average at the time of purchase were higher than the fixed rate under PPAs at the Rockdale Facility, and we had proportionally fewer offsetting power credits than we did the quarter before. Over the whole of 2024, our all-in cost of power was $0.034 per kilowatt hour, still among the lowest in the industry. Direct non-power costs, covering direct labor, miner insurance, repairs to miners and miner related equipment, land lease and related property taxes, network costs and other utility expenses, came to $8,730, or 21%, per Bitcoin, a decrease from Q3 2024, when direct non-power costs were 25% of total costs. That decline comes from Riot's ongoing achievement of economies of scale at our operating facilities. As Riot keeps expanding hash rate, we anticipate non-power direct costs, as a share of the total cost per Bitcoin, will move lower. I'd like to hand the call over now to Jason Chung, Riot's EVP and Head of Corporate Development and Strategy, to talk about our latest acquisition.

Jason Chung

executive
#4

Thank you, Colin. It's a pleasure to discuss Riot's most recent acquisition. In December of last year, we completed our purchase of E4A Solutions, paying $52 million in cash at closing. Headquartered in Houston, Texas, E4A Solutions ranks among the top providers of consulting, commissioning and procurement services tailored to meet electrical project requirements for substations, spanning low voltage through high voltage. Roughly 50 people work at E4A, and the company serves power plants, transformers, substation equipment and switch gears for a blue-chip client list that features FirstEnergy, Hitachi, Hyundai and Toshiba, along with numerous others. During 2024, E4A brought in $28.2 million in revenue, which marks a 31% gain compared with 2023 revenue of $21.5 million, plus $4.6 million in EBITDA, equal to margins above 16%. Acquiring E4A Solutions delivers multiple strategic advantages to Riot and substantially strengthens our engineering segment. To put it more precisely, ESS Metron, our engineering business, will gain the capacity to introduce higher-margin recurring services revenues for customers. Offerings built on E4A's service know-how in maintenance, servicing, training and repair may now be provided on equipment that ESS Metron manufactures, and because the services business tends to be countercyclical relative to ESS Metron's operations, we also expect it to lower overall revenue volatility within our engineering business moving forward. Through this deal, Riot has acquired in-house proficiency in developing, maintaining and servicing medium- and high-voltage substations, which will further reduce infrastructure development risk and deliver cost savings, while additionally enhancing our capacity to carry out on-site maintenance on switch gears and, above all, driving additional gains in operating uptime for our Bitcoin Mining business. Riot's engineering business produced $38.5 million in revenue during 2024, a decline from $64.3 million in 2023. That drop in top line revenue stemmed mainly from a single large manufacturing contract for a governmental entity, which required more time to finish than expected because of supply chain constraints experienced during the year, leading to fewer material receipts and postponed revenue recognition. Custom electrical products made by Riot's engineering business, including switchgear and power distribution centers, serve as especially critical components in data center development as well as in power generation and distribution facilities, and demand for these products has risen significantly thanks to the ongoing growth in AI/HPC data center development and the ever-growing need for power. Given our newly broadened engineering business product and service capabilities, Riot stands in a strong position to seize this expanding demand and, together with the recent E4A Solutions acquisition, has a clear route toward hitting $100 million in revenue in 2025, while also growing meaningfully. Having said that, I would like to hand the call back to Jason Les now.

Jason Les

executive
#5

I appreciate that, Jason. At this point, I want to shift the presentation over to how Riot approaches its treasury strategy. Every Bitcoin that Riot mines itself, we continue to keep. By retaining all of our Bitcoin rather than selling it when it was mined, we gained $120 million in value during 2024. Our conviction in Bitcoin remains as strong as ever, and we think that keeping Bitcoin and raising our Bitcoin yield will deliver more shareholder value as time goes on; this slide shows the difference we captured over the year by holding the Bitcoin we produced instead of selling it at assorted year-end Bitcoin prices. A core principle of Riot's strategy has involved keeping a robust balance sheet, supported by the Bitcoin balance we have been building since 2018. That has let Riot move opportunistically and expand our asset portfolio, which in turn has opened up the fresh set of opportunities that we are now pursuing. Riot has historically been cautious about long-term debt, yet the higher value of our Bitcoin combined with appealing conditions in the convertible debt market prompted our first-ever debt issuance in December 2024. We see this as a way to leverage our solid balance sheet for acquiring additional Bitcoin at an appealing cost of capital. We follow a hard and fast internal guideline: additional borrowing is off the table whenever it would cause our debt-to-Bitcoin-value ratio to exceed 40%. In our view that leverage ceiling is prudent, and we think it allows us to create incremental value for shareholders. On top of that, because we continue to grow our Bitcoin holdings month after month by retaining what our mining operations produce, our leverage naturally declines over time. Riot's total capital expenditures forecast for 2025 comes to $198 million. Even though we've halted the buildout of Bitcoin mining at Corsicana, the costs we've already committed—chiefly the 600-megawatt substation project—are still being incurred. Beyond that, construction continues on the different sites comprising our Kentucky footprint — roughly $23 million going toward infrastructure costs and $110 million allocated for mining rigs. Even so, keep in mind that $35 million of that total represents deposits tied to hash rate scheduled to activate in the first six months of 2026. With this spending and the work happening on the ground, we expect to close out 2025 at 38.4 exahash of deployed hash rate — a 22% gain over the 31.5 exahash we ended 2024 with. Our assumption is that this will more or less match the pace at which worldwide network hash rate expands during the year, allowing us to hold our approximately 4% slice of the total network. In 2024, a dominant theme in the market became the rapid growth of AI use cases along with the resulting surge in demand for the massive power access that large language models and inference compute require. For a long time, we've viewed our Bitcoin Mining operation as being on the leading edge of the intersection between energy and sound money. Now that AI/HPC is coming to the fore, we see ourselves situated at the heart of where energy meets high-performance compute. As a result, Riot's portfolio of premium energy assets—which is positioned in a way few others can match—can now be viewed from a broader perspective. What lies at the core of Riot's business is obtaining, constructing, and operating energy infrastructure for Bitcoin Mining via a vertically integrated approach. Thanks to that emphasis, Riot now owns and operates 2 premier power assets, and those assets serve as the foundation for the broader set of possibilities that is uniquely on the table right now as we look at every avenue for squeezing maximum value from the energy assets throughout our portfolio. The value of AI/HPC contracts hasn't escaped the market's attention, and companies that made this pivot have been rewarded with elevated valuation multiples. On Page 21, the chart shows both the multiple expansion that a number of our public peers have enjoyed as they pivoted portions of their power assets to also include AI/HPC, and the trailing valuation multiples that the remaining Bitcoin Mining pure-play players are seeing. Short-term fluctuations in Bitcoin Mining revenue are possible, yet AI/HPC agreements deliver dependable, long-horizon cash flows supported by trustworthy counterparties. That can reduce how volatile our financial results are overall, and the market tends to reward it through richer valuation multiples. One of the hottest topics in the current market is the massive electricity demand major hyperscalers are confronting as they race to bring more high-performance compute capacity online, plus the associated capex budgets they have pledged in order to hit those targets. Microsoft, Meta and Alphabet alone have collectively committed to spending plans exceeding $200 billion this year, and the remainder of the industry is quickly doing the same. Hyperscalers are up against a pressing requirement for power on a massive scale if they're going to meet their ambitious growth objectives, and industry projections indicate close to 30 gigawatts of extra power demand will be needed within the next 5 years. Riot, as I'll explain, is positioned with an obvious and distinctive chance to take advantage of this enormous supply-demand gap. In their ongoing hunt for large-scale power access, hyperscalers tend to place the most weight on 3 essential criteria: first, being close to major markets; second, being able to move quickly and get compute deployed fast; and third, having access to power at a large scale, in the hundreds of megawatts. Each of these core requirements can be met especially well by Riot's main assets located in Rockdale and Corsicana, which I'll discuss in a moment. From our perspective, the Corsicana site presents the single best chance right now for a hyperscaler to secure a big block of power without delay, and it sits very near Dallas, which ranks among the most in-demand data center locations nationwide. Being there puts hyperscalers next to an established connectivity hub, which means reduced latency. Even more significant: 400 megawatts at Corsicana are available for use as of today, and we are building another 600-megawatt substation on an active basis, slated for completion in early 2026. Add those together and you get 1 gigawatt of power that a hyperscaler could bring online nearly right away — and paired with the site itself, we think that makes Corsicana an exceptionally uncommon proposition. On top of that, we hold ownership of the land at Corsicana. We can secure water, and that availability keeps expanding, plus we currently have several fiber sources that are redundant. Those are the main things hyperscalers check first when they assess a location, and in our view Corsicana fits those requirements exceptionally well. For a lot of the same reasons that make Corsicana an unusually strong choice for drawing hyperscalers, we see Rockdale as another promising possibility. Over at Rockdale, a 700-megawatt substation has already been built out, along with capacity that could be brought online right away. Today's Rockdale property covers over 200 acres, and the bulk of it is cleared, open ground, so a hyperscaler could start building there immediately and capitalize on that big-time power access. Much like Corsicana, Rockdale sits only 45 miles away from Austin, another significant data center market that hyperscalers want to be near. On top of that, we think the fairly modest gap of roughly 100 miles separating the Rockdale and Corsicana campuses opens up yet another attractive chance for a single hyperscaler to bring as much as 1.7 gigawatts of power to bear at the two locations, which sit not just near one another but also close to two leading data center markets.

Jason Les

executive
#6

Toward the end of last year, hyperscalers started reaching out to Riot on their own initiative, eager to look into possibilities tied to our power assets. As those conversations moved forward, we recognized a major chance sitting in front of us. So from that point on, we've carried out several actions aimed at seizing this enormous opening. To start, back in January, we brought in Altman Solon, a top telecom strategy consulting firm, to assist us in running a study assessing whether our Corsicana site could feasibly serve AI/HPC purposes. That study has been running for several weeks now and should wrap up next month. Next, earlier this month, we made substantial adjustments to our Board of Directors, adding 3 new independent Directors and growing the Board so it now holds 6 Directors altogether. The fresh independent Directors joining our Board bring a distinctive mix of abilities, among them considerable expertise in data center development, deep experience in real asset development, a background in capital allocation, and wide-ranging corporate governance know-how. Our reconstituted Board will keep supervising and guiding the management team on this initiative as well as other important efforts at Riot. Third, we've brought on Evercore and Northland as our financial adviser to guide us in working with prospective AI/HPC partners using an approach that maximizes value. Both companies possess considerable experience and robust ties to hyperscalers, data center developers, and financing partners, and they've advised businesses such as Riot. Fourth, while we'd already disclosed that Phase 2 expansion of Bitcoin Mining at our Corsicana facility was halted, it matters to point out that we're still building out the extra 600-megawatt substation there so the site becomes even more appealing to hyperscalers and data center operators. We're taking tangible actions to make sure we're extracting the greatest value from the chance in front of us right now, and we'll share more updates on how things are progressing as they happen. Thanks to the groundwork laid across earlier years, we think 2025 will prove an exciting and rewarding year for Riot shareholders; we're pouring a huge amount of resources into pursuing AI/HPC opportunities. We're also staying committed to boosting Bitcoin yield, powered by our Bitcoin Mining operations and a disciplined capital strategy. What anchors our mining operations is our industry-leading cheap power, and Riot keeps posting outstanding results across what is now a multiyear track record. Over the last few quarters, we've discussed our emphasis on operational efficiency, and the payoff from those efforts has become visible in recent months, as our monthly production results show. Operational excellence remains among our priorities, and our teams are working diligently to achieve top-tier outcomes. To wrap up, I and everyone else at Riot couldn't be more thrilled about where the company is going. The resources, funding, and personnel we need are in place to drive meaningful increases in shareholder value. We appreciate everyone taking the time to hear our presentation. At this point, we'd like to invite your questions. Operator?

Greg Lewis

analyst
#7

Jason, thanks for walking us through that — it was definitely more illuminating than what we got in earlier quarters. So I suppose my opening question concerns the HPC opportunity, and I realize this is something we've discussed intermittently for some time. Still, when you survey the landscape — thinking back to last year — there was consistently this notion that prompt power would be needed, and that a window existed for it. Now that you've been engaging with more hyperscalers and having more and more conversations, do you see that window perhaps getting wider? In other words, sure, it's wonderful to have prompt power in 2025, but securing power in later years is nearly as valuable, isn't it?

Jason Les

executive
#8

Yes. Greg, I'd say power is enormously valuable in 2025, yet any power you can get, whether that's in '26 or '27, carries enormous value too. As we showed in the presentation, you're looking at roughly 30 gigawatts of AI/HPC demand — and that figure is AI/HPC demand by itself across the coming 5 years. Approvals for transmission and new interconnects require 4, 5 years. Long-lead substation items are now taking 4 to 5 years just to ship, and the growth is outpacing what transmission can handle. So having capacity in 2025 earns a genuine premium, which explains why we consider our assets so valuable — we have hundreds of megawatts ready right now and that number keeps expanding <<inaudible>> seeking a solution to, and Riot is ideally situated to serve as that solution for hyperscalers.

Greg Lewis

analyst
#9

All right, that's helpful. Then there's another thing I wanted to ask about: clearly, we're in conversations with hyperscalers about getting them to commit—or possibly commit—to HPC deals. Is this sort of a two-pronged approach, meaning that Riot is simultaneously speaking with EPCs and certain firms or vendors who'd assist in constructing these facilities? Or does it work more like, let's bring the hyperscaler aboard first and afterwards determine things, sort of having them steer how the conversion gets built out, or how the greenfield site gets built out?

Jason Les

executive
#10

Greg, what I'd say is that several parallel efforts are underway simultaneously. These opportunities could come together through quite a few different routes. And we're leaving all our choices on the table so that we can be certain we land on the approach that delivers maximum value. Interest has come to us from hyperscalers as well as big AI firms. Those talks have been proceeding alongside our new financial partners; we are currently also contacting extra infrastructure partners and financing partners. So there's plenty happening across the board; and where we'll land is on whichever route yields the greatest value once we've examined essentially the entire market here; yet, as I pointed out, at the same time we keep expanding capacity at this site; we're moving forward on what would be the initial phase of development regardless; so I'd describe it as several parallel efforts being pursued simultaneously.

Nick Giles

analyst
#11

To start, with hyperscalers competing to secure available capacity quickly and at scale, there’s obviously an appetite for developing sizable campuses, which calls for a lot of land. So I wanted to know how much more capacity Corsicana might be able to support past the 1 gigawatt target. Or, given what you said earlier, might Rockdale actually be in a stronger position for that?

Jason Les

executive
#12

We view Corsicana as a fantastic location since it already has the approved 1 gigawatt interconnect, power capacity that’s usable right now, and it’s still growing. We’ve got two fiber sources, water access, and proximity to a major data center market. We’re very enthusiastic about the role Corsicana can play in these conversations. When you consider land for AI/HPC projects, there’s a range of what those developments can require, and that shapes design choices. Typically, having more land makes construction less costly and simplifies layout and cooling. With less capital to spend, you lean more on newer rack and cooling technologies, which can end up costing more. Even so, as you mentioned, we hold a lot of land at Rockdale. We also have a solid amount at Corsicana, and we’re currently growing that land portfolio there too. One last thing: often, when hyperscalers discuss campuses, they don’t usually mean facilities are right next to one another. At times they can be as much as 100 miles apart. That’s why we’re growing our land holdings—to boost the optionality for what we can pursue in this effort.

Nick Giles

analyst
#13

Jason, that's really useful, and I appreciate the feedback. What I wanted to ask about next is that the economics have differed somewhat across the deals already made public. So when you consider the terms of a possible HPC deal, what matters most to you? Is it margin, how much capital is put in, how long it runs, how big it is, or a bit of everything?

Jason Les

executive
#14

Nick, I'd say that for a project on this scale to get completed — the hundreds of megawatts, the gigawatts we're discussing — the financing piece is essential. So for financing to work, you truly need a blue chip counterparty, one that's extremely well capitalized, whose cash flows we could securitize on the most favorable terms possible. And beyond that, when we're talking hundreds of megawatts, that really only draws the biggest player in the space; so besides shaping the financing terms, the kinds of counterparties we'd sign with will have a major effect on valuations. So one of the main things I keep stressing that we weigh is that the counterparty type is required if we're going to maximize shareholder value here. When it comes to other terms, there's an entire mix of ways all these elements can interact. I believe it's a bit too soon to say which one might matter more or less relative to another. Ultimately, what matters is that Corsicana and Rockdale, and Corsicana in particular, is positioned ideally; we view it as a premier asset that earns a premium because of its quality and the timing of getting power online, which is clearly something hyperscalers are putting first. And that — these qualities will in the end produce better deal terms that capture what those assets are worth.

Darren Aftahi

analyst
#15

To start, Jason, regarding what you said about Corsicana, you mentioned acquiring more land. Could you give any sense of just how big an extra parcel might be? And have the parties you might be negotiating with actually requested that sort of thing?

Jason Les

executive
#16

Conversations have happened with counterparties. For certain ones, it's important. For others, it isn't. As I mentioned a bit earlier, what ultimately matters is the sort of buildout you intend to pursue. When it comes to data center construction, technology is getting extremely efficient at packing density onto racks of 100, 200 kilowatts today, direct chip liquid cooling — every one of these pieces, every one of these technologies, is boosting density. So it varies. Various customer categories have varying requirements for this plan. Even so, we're concentrated on growing and maximizing the optionality available to us; therefore I can't give you a particular figure, though I can say we're buying up hundreds of acres so that — as I noted — we can be sure to serve as broad a market as we can.

Darren Aftahi

analyst
#17

Great. Then, if I could, just one more. In the deck, you're sort of promoting Corsicana, promoting Rockdale, and then you might be discussing possibly building a fiber loop and advertising the entire campus. So I suppose, the way things stand right now, Rockdale has always been a Bitcoin Mining facility. Is there an economic scenario analysis in which you'd consider switching and turning that entirely into an HPC campus?

Jason Les

executive
#18

Yes. If the chance existed to — if there were interest in that location and the economics made sense for taking over the capacity we have there, we would definitely be interested in doing that. I think when you consider 30 gigawatts of demand, 1 gigawatt at Corsicana and then 700 megawatts at Rockdale, that's a really meaningful portion of something that could satisfy that demand. 1.7 gigawatts would be roughly 5%. If someone held both of those sites, 5% of hyperscaler AI demand over the next 5 years, I think that would give those players a genuine strategic advantage. So if that interest exists and the economics are there for converting that site, we will definitely be looking at and evaluating that closely.

Brett Knoblauch

analyst
#19

My first question, which is kind of like the previous one, is whether all of Corsicana is available if a hyperscaler wanted the complete gigawatt at that location.

Jason Les

executive
#20

So what we have is 600 megawatts currently sitting unused that has already been built out; that would be the path of least resistance for getting a deal done, Brett. However, should a party come along who wants the whole 1 gigawatt, taking the site in its entirety as it stands and possessing the economics to make it accretive for Riot shareholders, then absolutely, we would consider it. And it's always conceivable that such an opportunity arises, since that's a substantial amount of power being brought online, 400 megawatts at present and then the other 600 megawatts 12 months from now — or roughly 12 months from now. So we are evaluating demand, and we intend to maximize the value of these assets.

Brett Knoblauch

analyst
#21

Got it. Then perhaps regarding the electricity contract that's currently in effect at those locations, is it necessary for those to be rewritten so they can accommodate AI and HPC? And possibly specifically for Rockdale — since you take part in numerous demand response and curtailment initiatives — would that have to be changed from a flexible load into a firm one?

Jason Les

executive
#22

No, no changes are required. Nothing in our power supply contracts obligates us to take part in demand response. Whatever we do in that regard is entirely by choice, as part of how we approach power strategy. That fits Bitcoin Mining, given that the load can be interrupted. Clearly, that isn't compatible with AI or HPC; therefore we engage in it with Bitcoin Mining on a voluntary basis to achieve the strongest economics, though it's never something our supply agreements demand.

Reggie Smith

analyst
#23

Congratulations on both the quarter and the year. I've got a question for you. I was reviewing your OpEx trends, and I don't mean to dampen the mood here, but I noticed — when we examine SG&A excluding stock comp, that figure has risen quarter over quarter. It sounds like you've made a few acquisitions. There could be some deal costs baked in there; but what is causing that? How do you benchmark OpEx growth and similar things? And I was wondering whether you could share an employee count, since I was attempting to work out stock comp on a per-employee basis. And then I have a follow-up question.

Jason Les

executive
#24

All right. Going in reverse order, Reggie, an exact employee count isn't something I have for you. That will be in the 10-K, which ought to be filed very soon now. Regarding G&A, our G&A has been elevated, in both '23 and '24 — pardon me, Q3 and Q4 2024, because of onetime M&A and legal — litigation expenses. Those aren't recurring costs for operating our business and aren't part of operating a Bitcoin Mining operation or AI/HPC operation. So that was fairly significant, particularly in Q4. We had roughly $22 million in one-off costs. As I mentioned, mostly litigation expense; we had certain stock-based advisory services that were wrapping up a 3-year engagement. We had some M&A expenses too; so clearly, we'd like our litigation resolved promptly, so we stop incurring those expenses, and we can bring cash SG&A down. And I do have an employee count for you, with help from someone in the room here, 783 full-time employees.

Reggie Smith

analyst
#25

Understood. Okay, that clarifies things. Alright. So it seems like a few one-time items are in play. Could you help us estimate what you'd want that to look like on a recurring, forward-looking basis? If we set aside all the noise, what do you believe you could achieve running your Corsicana site, plus Rockdale and whatever else you bring online, going forward?

Jason Les

executive
#26

First, regarding how expenses get allocated, there's a division involving direct operating costs. Those sit within cost of goods along with power, even though power represents a substantial expense. Beyond that, we have certain other expenses of a more corporate nature, facility-wide ones, that appear under SG&A. But to answer you directly, we expect our 2024 cash run rate quarter will come in at or slightly higher than the prior guidance we gave for the Q4 2024 run rate, roughly $30 million to $33 million; predicting litigation or possible one-time M&A items, or advisory fees that could arise, is extremely hard. Still, on a run rate basis, that's our expectation each quarter: $30 million to $33 million in cash. And we're concentrating on optimizing that, particularly in relation to our broader hash rate portfolio.

Reggie Smith

analyst
#27

Understood. That's logical. All right. Excellent. Then may I squeeze in one final question? I'm wondering whether the advisors you've been in touch with have offered any sense of the timeline for closing the transaction. Basically trying to gauge how fast this could wrap up, or how long it might stretch out. And it seems — though perhaps I'm overinterpreting — that should nothing be finalized before late 2025, you'd look at returning to Bitcoin Mining and growing that Bitcoin Mining business. The reason is it appears you've reached a point of comfort regarding your hash rate's position versus the network hash rate. Is that the correct way to view it?

Jason Les

executive
#28

Well, I wouldn't frame it as — if the capacity isn't entirely committed by the close of this year, we'd restart Bitcoin Mining. Given the demand and the caliber of the assets we hold, I'd say we're fairly confident something will get completed. The duration required is likely hard to forecast from start to finish, though there will be milestones along the way. Based on whatever final deal structure emerges, several milestones might involve executing the lease, bringing in a development partner, say, obtaining financing, say, and those things may happen in various sequences; so we're pursuing this quite aggressively. We aim to share updates as they happen; but we don't view this as — we must finish by a certain date or else we revert to Bitcoin Mining; we find these assets genuinely compelling for AI/HPC data center development, and we're eager to accomplish something substantial there.

Reggie Smith

analyst
#29

Understood. Fantastic. And, well, once more, I simply want to express my congratulations to you all. I recall that during earlier quarters we discussed enhancing uptime and operations. You folks have performed well on that front. So I wanted to recognize it; excellent work on that, and I'm eager for further updates regarding the HPC side.

Jason Les

executive
#30

Thanks, Reggie. I appreciate it. Every bit of the praise belongs to the people out in the field — the men and women in the field putting in hard effort daily to get operations approved.

Mike Grondahl

analyst
#31

Two things I'd like to ask. First off, could you give us a bit more detail? My particular question, I suppose, concerns the 400 megawatts over at Corsicana along with the 700 at Rockdale — has any concrete interest come in for that capacity as of yet? Or would you characterize everything so far as tied to the 600 megawatts at Corsicana? Then second, are there any operational targets for '25 when it comes to mining?

Jason Les

executive
#32

Let me take those in reverse order, Mike. On operational targets for the Bitcoin Mining side, our aim is to grow hash rate roughly 22% over this year. The main driver behind that is expansion at our Kentucky facilities. Operational excellence is where our focus sits. We intend to keep carrying out our power strategy and boosting uptime as the month progresses. So there's a solid amount of work in front of us to make that business line better too; and my sense is we're taking all the right steps to deliver stronger results there and reach those growth targets in Bitcoin Mining, finishing the year at 38.4 exahash. Regarding interest in the power, what I'd say is that hyperscalers, large companies, have taken note of our access to power, and they'd like to get a share of it. It hasn't — the inquiry hasn't really been as specific as, "We want your next 600," or, "We want the 400 here," or anything along those lines. It's more like, "Hey, we need power fast. We'd like to have a conversation with you about how that might work with your assets."

John Todaro

analyst
#33

I've got a pair of questions. I realize it's still very early in these discussions, and I take your point about all that demand out there and what folks are anticipating; however, my sense is the market is beginning to doubt some portion of it, particularly on a day like this one. So my first question is simply this: as those talks with hyperscalers have unfolded, has anything shifted lately compared with, say, a few weeks back or roughly a month back? Any hints you can share? That's question one.

Jason Les

executive
#34

Nothing has shifted as of yet, from what we can see. Together with our financial advisers, Evercore and Northland, we're broadening the set of counterparties we're engaging with at present, so that we can capture the most complete picture of the market. That said, I think there have been plenty of fresh reports concerning AI demand and the way it has swung around. The news regarding Microsoft today appears, quite rapidly, to have much of it contested, and it began as somewhat misleading or misconstrued information. But I'd also draw attention to things such as Grok 3 now holding the #1 rating among AI. And what allowed them to reach those results with that AI? They carried out a substantial amount of pre-training, since xAI brought 100,000, moving toward 200,000, video GPUs online quickly. So despite efficiency gains that are being realized or being examined, it remains the case that large-scale access to power — and, by extension, compute — hands hyperscalers, hands AI developers, an advantage with these products. So provided there's demand for AI, which in my view will only keep growing, I expect we'll keep witnessing rising demand for power to construct data centers in order to gain a competitive edge within that sector.

John Todaro

analyst
#35

Excellent. For my follow-up, could you lay out that argument once more? I'm aware you've previously explained how the Bitcoin operation and HPC fit together, and what I notice is that you're essentially increasing your Bitcoin commitment — particularly regarding Bitcoin held on the balance sheet — while also intending to pursue HPC aggressively. From what I hear from the investors we speak with, though, the people who favor HPC tend not to favor Bitcoin. So would you separate one of those businesses? Or in what way do the two actually support one another?

Jason Les

executive
#36

Sure. Right now, I'd describe Riot as sitting at the intersection of 2 industries experiencing fast growth: Bitcoin, plus demand for AI/HPC data centers, which has become a very familiar theme. Bitcoin's swift movement toward institutional acceptance, along with its price gains, is precisely what has made Riot one of only a small number of firms holding direct Bitcoin exposure. That balance of ours, together with the Bitcoin Mining operation, gave Riot the structure needed to bring in capital on favorable terms and put it into efforts such as Corsicana and the expansion at Rockdale. That is what produced the set of opportunities we have before us now, and we believe substantial value can be created from it. When it comes to the AI/HPC opening, it offers us an additional route — apparently a superior one — for deploying our energy assets and producing meaningful economic returns. In my view, staying flexible and seizing opportunities is what will deliver our shareholders a diversified route toward stronger returns. So, John, I'd put it this way: Bitcoin is the reactor that expanded our company and our assets and brought us to the position where we can now pursue this. We expect it will keep creating opportunities for us going forward, and the capacity to build AI/HPC data centers or strike deals within that space is simply one more tremendously exciting method by which we can grow value.

Martin Toner

analyst
#37

Nice work on the deal and the better efficiency we saw this quarter.

Jason Les

executive
#38

Thanks, Martin.

Martin Toner

analyst
#39

One brief thing about the transaction, that $100 million run rate, and the margins. I'm just curious, when do you think this business might generate margins that are more consistent with the industry and more consistent with what the acquired company has?

Jason Les

executive
#40

Thanks, Martin. I'll hand that over to Jason Chung, our EVP and Head of Corporate Development.

Jason Chung

executive
#41

Absolutely, Martin — that's a great question. When we look at what the engineering segment looks like right now, especially after bringing E4A Solutions into the fold, it's clear that a services-oriented operation naturally carries better margins. And that improved margin picture really shows up in the numbers they've been delivering. This business sits right in the middle of the tremendous surge we're seeing in demand tied to power generation and data center buildouts. Historically, their revenue has kept climbing while they've held margins at a solid level, and our expectation is that this pattern carries on ahead; that's essentially what shapes our big-picture outlook for how engineering performs in 2025. There's another piece to this as well — namely Metron. With that one specific contract now behind us, we're expecting a meaningful rebound in that operation. Consider where things stood back in 2023 — revenue at that level, margins in a comparable range; but once you layer E4A on top, with revenue projected to keep expanding robustly this year and margins staying healthy, then on a combined pro forma basis, we believe the engineering segment will deliver a substantial margin gain. Looking a bit further out, we still see genuinely compelling synergy potential from putting these 2 operations together, whether through cost reductions or cross-selling. And just consider that E4A Solutions calls Houston home, where we believe some of the capacity constraints currently holding back the ESS Metron operation might be relieved. So now that these 2 businesses are united, I'd say there are some truly compelling near- to midterm chances to push that margin profile up even higher.

Patrick Moley

analyst
#42

I want to ask about the Rockdale site. As far as I know — and correct me if I'm mistaken — you're currently leasing that location. It's not owned by you the way Corsicana is. So I'm curious: could you maybe lay out what that lease involves, and does renting the land instead of owning it make it less attractive to hyperscalers who are evaluating locations for a data center?

Jason Les

executive
#43

Yes. That's correct, Patrick. We own the land at Corsicana. With Rockdale, we hold a land lease. It does run for quite a while, however. Ten years is the initial term, followed by several renewal periods of ten years each that we can exercise at our discretion. Altogether, I think that adds up to somewhere between 40 and 50 years. The ground lease in question runs for quite a while. In my view, the kind of transaction being pursued is what would make or break a deal in that location. It really comes down to how hands-on the customer wants to be, and that, in the end, determines whether Rockdale works for them given that the property is under a lease. Still, when you strip it all down, the dominant issue we're looking at is power scarcity. And our sense is that as that scarcity grows increasingly tangible and hyperscalers alongside AI firms find themselves bidding against one another for capacity, considerations of that sort could carry less weight if the trade-off is securing capacity faster.

Patrick Moley

analyst
#44

All right, understood. Now, as a quick second question. Naturally, what a tenant requires will differ; however, a number of comparable transactions we've observed completed in this sector have involved lease durations exceeding 10 years — or rather, terms of 10 years for AI/HPC agreements; therefore, drawing on the discussions you've had, might you describe what maximum duration a contract might have, should you decide to enter into one? Has this topic emerged at all as questions regarding demand over a longer horizon have come up? Any details concerning how long such deal terms might run would be appreciated.

Jason Les

executive
#45

Sure. In my view, demand over the long term is — apologies, the duration of an agreement represents a crucial matter, and that holds true for both the customer side and for us; after all, we will be constructing infrastructure. Capital will be deployed by us for this. Furthermore, favorable terms can be secured at present. Securing a long-term agreement is what we want, so that we can lock that in and provide ourselves with visibility into the financial return on the assets across an extended period. Thus, I believe both parties share a comparable appetite for long-term agreements, spanning 10 years and more.

Bill Papanastasiou

analyst
#46

Nice work on the transaction. First thing I want to ask about is how you push Bitcoin yield higher — I'd like to know what management's view is on dilution as you go after more Bitcoin per share. Also, might Riot put out additional kinds of structured offerings later on?

Jason Les

executive
#47

Making dilution as small as we can is central to doing well on Bitcoin yield. For a Bitcoin miner like us, the main engine behind that is mining itself — our direct production cost is extremely low. That's the foundation for how we grow Bitcoin yield organically. Naturally, whenever we bring in capital, we'll aim for the approach that dilutes least and carries the cheapest cost of capital, so that Bitcoin yield improves. That's exactly why this metric carries so much weight. In our view, it keeps entire teams, including ours, on the hook to keep dilution to a minimum. From there, that shapes how we approach tapping the equity market. You've probably seen that for the last several months, we've gone easy on our ATM program. It's also what pushes us toward locating other financing avenues — given our assets and everything we've built at Riot, we believe we're in a strong spot to secure those alternative financing options. Every bit of that helps lift Bitcoin yield. On the subject of other structured offerings, I take it you mean what our strategy has pursued — that isn't something we've examined very closely so far. Right now our attention is mostly on the AI/HPC opportunity. Still, I expect we'll keep a close watch on how such products emerge and on what demand from the investor market looks like.

Bill Papanastasiou

analyst
#48

Thanks for that detail. And second, I apologize if this came up before I joined, but could you give us a bit more insight into what the design and engineering side of an AI/HPC data center might involve? Would you have to bring in or team up with additional outside firms to get it operational? I'm interested to know what the approach would be.

Jason Les

executive
#49

I believe that ultimately hinges, Bill, on what kind of deal materializes. As we mentioned previously, our goal is to chase whatever delivers the greatest value when adjusted for risk, and there are several distinct paths we could take to get there. With certain of those paths, we already have people ready to handle it; our power capacity build-out is going quite well. We've proven exceptionally capable at that. And picking up E4A only strengthens our ability to construct what you might call the power shell of an infrastructure — of a data center development. Beyond that, at Riot and Bitcoin Mining, we've built our infrastructure using cutting-edge cooling methods, and that know-how carries over into backing data center development, particularly given the cutting-edge cooling methods emerging there; so I'd say we possess a solid amount of talent. Even so, our attention is on adding further support to enable execution there, and we're pursuing that both internally and through third parties.

Joe Flynn

analyst
#50

I was thinking, perhaps drawing on those prior discussions you've had with your consultants, whether you could provide any operational metrics — for instance, what PUE you might ultimately achieve, plus your build cost per megawatt, and how that might vary between the 600 megawatts at Corsicana and the Rockdale site, since power infrastructure already exists in the ground there.

Jason Les

executive
#51

Yes. My sense is that it's likely premature to say what PUEs might look like, particularly given how quickly the technology is evolving; a great deal will hinge on the sort of customer involved. Rockdale and Corsicana, I'd note, sit in quite comparable climates, separated by just 100 miles; as a result, the two would be alike on either side. That said, at both locations we enjoy very ample water access, particularly at Rockdale. Thus we're positioned to accommodate a broad range of cooling technologies there. So Joe, I couldn't say at this point what it would be like. The discussions, I believe, would have to move ahead further. We'd need to be somewhat into the design phase to understand what that specific customer aims to achieve.

Joe Flynn

analyst
#52

Then, circling back to simply getting the most out of those sites — does that involve possibly selling capacity outright? And regarding that, has anyone come to you, or have you even received bids, for selling an asset outright?

Jason Les

executive
#53

You're looking at a full range of ways a deal might be structured. On one extreme, it might be leasing land. It might be a powered shell. It might be constructing something tailored to what amounts to a big, fully built-out data center; and at the opposite, largest extreme you'd have selling the asset outright; so as conversations move forward here, we're receptive to any of those. And we're — our aim is to run a fiercely competitive process here; that's the reason we brought in Evercore and Northland, so we get the widest — the broadest reach into the market that we can.

Phil McPherson

executive
#54

Everyone, thanks for joining our earnings conference call today; we're eager to share news about upcoming developments at Riot Platforms. As ever, feel free to reach out to us at ir@riot.inc with any additional questions down the road, and we'll speak again soon. Thanks so much.

Operator

operator
#55

We appreciate everyone joining us. That brings the session to a close, so you're free to leave the call at this point. Have a great rest of your day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Riot Platforms, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Riot Platforms, Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Riot Platforms, Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.