Ørsted A/S (ORSTED) Earnings Call Transcript & Summary

November 5, 2024

Nasdaq Copenhagen DK Utilities Independent Power and Renewable Electricity Producers earnings 78 min

Earnings Call Speaker Segments

Mads Nipper

executive
#1

Good morning, good afternoon, everyone, and thanks for being on our earnings call. In the third quarter, we kept moving forward with our business plan and hit several significant milestones, among them CFD awards for three and a half gigawatts in the UK, favorable contract settlements for Ocean Wind 1, and the signing of a partnership agreement. Solid operational performance continues across our fleet of assets, and overall progress on our construction projects is good, though some unexpected challenges have affected construction at one of our US offshore projects. Turning to our financials for the third quarter, the underlying business keeps performing well, and our operational portfolio has delivered strong earnings. EBITDA, excluding new partnerships and cancellation fees, came to DKK 4.4 billion in Q3 of 2024, and earnings from offshore sites reached DKK 4 billion. Reported EBITDA for the first nine months was DKK 23.6 billion, up 22% over last year, and EBITDA, excluding new partnership and cancellation fees, rose 12% to DKK 17.2 billion. Given these solid nine-month earnings, we have narrowed our 2024 EBITDA guidance to DKK 24 billion to DKK 26 billion, again excluding new partnerships and cancellation fees.

Mads Nipper

executive
#2

In the quarter, we brought 550 megawatts of renewable capacity online, which takes our total portfolio—our overall portfolio—to 18.2 gigawatts. In the US, we completed commissioning of the last portion of the Old 300 solar project as well as the entire 471-megawatt Mockingbird Solar Project. Our construction portfolio also grew, thanks to the final investment decision on two onshore projects in the US totaling 500 megawatts. One key milestone came when we were awarded 3.5 gigawatts of offshore wind in the UK's allocation round six, which secured inflation-linked offtake for a 1.1 gigawatt share of Hornsea 3 and 2.4 gigawatts for Hornsea 4. We're highly pleased with how the auction turned out, and with this additional capacity we get closer to our goal of 20 to 22 gigawatts of offshore capacity by 2030. As we announced at our capital markets update, we intend to generate roughly DKK 70 billion to 80 billion in proceeds from partnerships and divestments across the years 2024 through 2026. We anticipate those proceeds being split approximately evenly across that three-year span, and we're making solid progress on the plan, helped by the recent transaction and several processes currently underway.

Mads Nipper

executive
#3

Last week, we announced that we're divesting a minority stake in four of our operational UK offshore assets to Brookfield. Brookfield has acquired a 12.45% minority share of Hornsea 1 and 2, Walney extension, and Burbo Bank extension, while Ørsted will retain a 37.5% ownership interest in these assets. The DKK 15.7 billion in proceeds is a significant contributor to our farm-down program, and at the same time, we've ensured a high level of value retention with the transaction, which we expect to close before the end of the year. The agreement includes a unilateral option for Ørsted, giving us the opportunity, but no obligation, to repurchase the assets between two and seven years after the closing at a pre-agreed price. We see having that call option that we can exercise as attractive, ensuring that we maintain a level of strategic and financial flexibility, as well as value upside. Regarding the farm-down of Greater Changhua 4 in Taiwan, our dialogue with Cathay Life Insurance is progressing according to plan. Cathay has obtained the approval from the Taiwanese Financial Supervisory Commission for the acquisition of a 50% ownership stake, which marks the last significant milestone prior to signing of the transaction, which we expect to happen before year-end.

Mads Nipper

executive
#4

Back in August, we closed down the Esbjerg Power Station in Denmark — our final coal-fired CHP plant. That wraps up one chapter of our green transformation and represents the last big milestone on the path toward our industry-leading, science-based target: cutting the emissions intensity of scope one and two by 98% by 2025. From here on, essentially all of the energy we generate will be fossil-free. Now let me move on to what's happening across our US offshore portfolio. We've made meaningful progress in de-risking the cessation of the Ocean Wind 1 project, having wrapped up negotiations to cancel several supply contracts, and the outcome is significantly better than what we assumed last year when we booked provisions for the project's cancellation costs. Thanks to these favorable settlements, during the third quarter we reversed more than DKK 5 billion of the cancellation fee provision, which gave reported EBITDA a positive boost. On top of that, we identified additional equipment usable in other projects within our portfolio, which had a minor positive effect on the provision as well. In Q3, we recognized a net impairment loss of DKK 0.3 billion, driven by our revised assumptions about market prices for our US portfolio, along with higher costs and a challenge tied to installing the offshore substation monopile at Revolution Wind.

Mads Nipper

executive
#5

Those effects were partially offset by the drop in long-dated interest rates. If we move to Slide 4, I'll provide an update on where our construction projects stand, beginning with Revolution Wind. At Revolution Wind, progress continues on both the onshore and offshore construction, and to date we have installed 52 turbine foundations, nine turbines and 20 array cables. Since we took FID last year, the risk profile of the project has been shifting. Under our direction and with our team on site, Eversource remains in charge of the onshore substation work, and nothing new has emerged in that area. Our expectation continues to be that we will follow the revised construction timeline, with the onshore work serving as the project's critical path. In addition, we have lengthened the contracted period for one of our installation vessels by exercising an option we had secured previously. This does carry costs higher than we had anticipated, but from the standpoint of risk and project execution, we view it as the right step to take. Those installation vessel costs are folded into the impairment we have recorded this quarter. We are working through a challenge involving the installation of one of our offshore substation monopiles. It is a complication tied to driving the monopile into the seabed, which has left the monopile in a condition where, even though it was safely driven to the target depth, it may not be usable in its current installed state.

Mads Nipper

executive
#6

This issue most likely stems from resistance found in the soil of the seabed, something that is very uncommon and that we have encountered on only a handful of occasions across our history of putting in over 2000 monopiles. The monopile for the offshore substation sits in a position that is safe and stable, and drawing on our broad expertise, our team is working out the root cause and determining the optimal route ahead for the project. Offshore construction work — foundations, turbines, and array cables included — is proceeding on schedule, and we do not anticipate any shift in the project's commissioning date. Because of this complication, we anticipate extra costs to finish the project, which, notwithstanding these events, continues to carry a positive value at an absolute lifecycle IRI level as well as an appealing forward-looking return. The situation is still developing, and we continue to weigh every option, but we have built a prudent cost estimate into the impairment calculation and raised our contingencies to match. On our German program, we are finishing the last elements of commissioning at Gode Wind 3. Every turbine at the project is now installed, and 21 of the 23 turbines are fully commissioned.

Mads Nipper

executive
#7

The last two turbines are in their final round of testing, and we anticipate commissioning the entire project very soon. Over at Borkum Riffgrund 3, every monopile has now been delivered and installed — one of the supplier contracts we watched closely and pursued mitigation measures on. Turbine installation stands at 85%, and the portion of the construction scope that falls to us remains fully on track. That said, the German transmission system operator has told us the grid connection will slip, so first power is now not anticipated before Q4 of 2025, with commissioning following in Q1 2026. Under market regulation, compensation will be paid for the delayed grid hookup, so the project's value creation is unaffected. In Taiwan, construction of Greater Changhua 2b and 4 is moving forward, and installation of the offshore substation is set to begin shortly. Foundation and cable fabrication are coming along nicely, and turbine foundation installation should get underway in the first half of 2025. On our Sunrise project, onshore construction is advancing in line with the updated schedule, and offshore installation should begin in 2025. The project is running to a tight timeline as we aim for commissioning at the end of 2026 or in the first half of 2027.

Mads Nipper

executive
#8

Like I said, we've locked in offtake for Hornsea 3 thanks to a 1.1 gigawatt award in the latest allocation round six, and that also allowed the project's capacity to rise to 2,955 megawatts. Turning to onshore, building out our European and US portfolio is going well, with construction underway in Germany and Ireland. We have an appealing pipeline of onshore development projects, and we recently reached FID on two US projects that offer strong value creation, and we expect to take more projects to FID over the coming quarters to underpin continued growth in our onshore business. With that, I'll pass the finances over to you, Trond.

Trond Westlie

executive
#9

Thanks, Mads, and good afternoon, everyone. Turning to the third quarter results, I'll begin on Slide 5 with the EBITDA for the quarter. Throughout this presentation, every figure is quoted in Danish Kronas. At the group level, we achieved total underlying EBITDA of DKK 4.4 billion. Total EBITDA, which includes the effects of cancellation fees, comes to DKK 9.5 billion. Let me take you through the key earnings developments in the quarter. At our offshore sites, earnings came in at roughly the same level as last year. That was driven by ramp-up generation, higher prices on our green certificates, and better earnings from our power trading activities. Those effects were offset by the divestment of London Array in 2023, along with lower wind speeds and availability stemming from the planned outages. Earnings from our existing partnerships were somewhat lower than last year and were mainly tied to constructional Borkum Riffgrund 3. Finally, as expected and as reflected in our guidance at the start of the year, we have incurred higher cost as a result of internal spend on ceasing execution of projects, and we have recognized the higher share of cost being expensed. For onshore, earnings rose by almost DKK 200 million thanks to ramp-up generation from new assets that have been commissioned.

Trond Westlie

executive
#10

In bioenergy and other, earnings from our combined heat and power plants rose by roughly DKK 100 million, driven by higher heat generation and compensation from Energinet for keeping three of our Danish power stations operational until August. In the gas business, earnings fell, since we had recognized temporary positive effects from reevaluation of our gas at storage in 2023, and those were not repeated to the same extent this year. Lastly, we have kept working through the contracts relating to Ocean Wind 1, and during the quarter we reversed cancellation fees of DKK 5.1 billion thanks to better than assumed outcomes of the contract settlements. Moving then to Slide 6 and our net profit and ROCE. As part of our Q3 2024, we recognized a net impairment loss of DKK 300 million related to our US portfolio. The main drivers are the negative impact of updated assumptions regarding power prices and costs. Those updates were partly offset by a decrease in the long-dated interest rate in the US during the quarter, which led to lower weighted average cost of capital levels across our US portfolio. The effect from the decreasing interest rates produced an impairment reversal of DKK 2.4 billion.

Trond Westlie

executive
#11

I'll take you through the developments on a project-by-project basis. On Sunrise Wind, we reversed DKK 1.5 billion; the effect of lower interest rates and the positive accounting impact from closing the purchase of the 50% stake in the project at a price below our recoverable amount was offset by adjustments to the tax basis impact and by weighing market appetite regarding a possible future farm-down. On top of that, there was a negative effect from revised power price assumptions. On Revolution Wind, we booked an impairment of DKK 1.2 billion in the quarter. The offshore substation monopile issue that Mads referred to, along with the extended vessel charter, has pushed up the expected cost of the project. We have also re-evaluated the risks tied to the project's offshore scope, which means higher contingencies have been added. Beyond that, we have reduced our assumptions for future power prices. Lastly, updates to the power price assumption in our US onshore portfolio produced impairment losses of DK 500 million. Let me remind everyone once more that, since we have previously had to recognize impairments on these projects, any changes to the business case — including movements in interest rates — will likely require further adjustment to impairments, as there is no headroom.

Trond Westlie

executive
#12

Also, it's worth remembering that after these projects come online, they'll deliver substantial earnings and cash flow across their operating life. Adjusted net profit came to DKK 400 million, and the gap versus last year stems mainly from exchange trade adjustments affecting our net financial income and expenses. Reported net profit stood at DKK 5.2 billion, thanks to the sizable positive EBITDA effect of reversing cancellation fees tied to Ocean Wind 1. Excluding impairments and cancellation fees, return on capital employed was 11.5%, matching the Q3 2023 figure. Reported ROCE came in at 8.1%, driven chiefly by lower EBIT resulting from the impairments and cancellation fees over the last 12 months. Now let's move to Slide 7, covering net interest-bearing debt and credit metrics. As of the close of the third quarter, net debt was just under DKK 63 billion. Although cash flow from operating activities got support from operational earnings, that was more than outweighed by settlement payments on Ocean Wind 1 contracts and a cash outflow tied to building Hornsea 3 transmission assets.

Trond Westlie

executive
#13

During the first nine months of 2024, we recorded a cash outflow of DKK 5.9 billion tied to cancellation fees from Ocean Wind 1, and DKK 1.8 billion of that came in the third quarter. Altogether, we've now reversed over DKK 6 billion, and because of the settlements we've made, roughly DKK 3 billion of the provision remains, with more expected to be closed out toward the end of the year. Gross investments for the quarter came to DKK 9.8 billion, largely reflecting what we're putting into building out our renewable project portfolio. In September, we carried out an early redemption of the remaining hybrids, whose first reset falls in November, consistent with standard market practice. On the net debt position, I'd like to point out that the proceeds from the minority transaction with Brookfield are not reflected in our third quarter accounts, so the benefit of that transaction will show up in the fourth quarter, since we expect to complete it before the year end. Looking at our key credit metrics, FFO to adjusted net debt was 13% at the close of the third quarter. Versus last year, the decline was mainly due to lower FFO stemming from payments connected to contract settlements, along with a higher net debt position.

Trond Westlie

executive
#14

But our FFO and net debt for 2024 should turn out better than what we expected at the start of the year, thanks to the favorable contract settlements tied to Ocean Wind 1. As we mentioned in February, that ratio is anticipated to be lower across the full year of 2024, before it begins recovering toward the target level above 30% by the end of 2026. Moving now to Slide 8 and our non-financial metrics. In the first quarter of 2024, our taxonomy-aligned metrics came in as expected. The renewable share of energy was 97%, versus 92% during the same period a year earlier. This development was driven by ramp-up generation in offshore high wind speeds, along with lower coal-based generation. For our renewable share of energy generation, we've seen an increase driven by a higher share of renewable projects coming online, combined with a decrease in coal-based generation. In addition, the shutdown of our last coal-based combined heat and power plant puts us on track toward our target of essentially having fossil-free energy generation by 2025. On safety, it's encouraging to see another reduction in the number of recordable injuries, both for our own employees and for contractors' employees. And finally, moving to Slide 9 and our outlook for 2024.

Trond Westlie

executive
#15

As Mads said at the start, our strong financial results across the first nine months have led us to tighten the full-year EBITDA guidance to DKK 24 billion to DKK 26 billion, from the previous DKK 23 billion to DKK 26 billion. Versus what we expected for the full-year earnings mix back at the second quarter, we now anticipate lower earnings in bioenergy and other business, driven by reduced volumes stemming from the delayed TR gas build and a less favorable trend in our gas at storage, plus lower earnings in our combined heat and power plant business. Our gross level sits in the range of DKK 36 billion to DKK 40 billion, a DKK 8 billion reduction from what we expected last quarter, or the second quarter. The reason is timing effects throughout our project portfolio, since significant milestone payments are now anticipated to shift into next year. With that, let's open it up for questions. Operator, please.

Operator

operator
#16

Our first question is from Peter Bisztyga at Bank of America. Go right ahead.

Peter Bisztyga

analyst
#17

Good afternoon, and thanks for the question. I'll start with just one for now. What I'd like to dig into is the risk exposure for Sunrise and Revolution Wind in the event that Trump wins the presidency this week — my assumption is that, at a minimum, the bonus ITC would likely be lost. From what your impairment tables show now, that would translate into an impairment of nearly DKK 5 billion. That said, do you have any worries that the administration might take steps to delay construction, or even block it outright, whether indirectly or directly, on those projects? Take, for instance, a refusal to defend certain legal cases that have been filed against BOEM concerning Revolution. So I'm keen to hear your perspective. Thank you.

Mads Nipper

executive
#18

Thank you, Peter. Yes, let me remind everybody that the 2 projects we currently have under construction offshore — Revolution and Sunrise — both hold all of their permits, and given that this is the part the federal level plays, that is an area where our risk assessment hasn't shifted in any way, and we feel confident that construction can proceed.

Peter Bisztyga

analyst
#19

Apologies — may I just add a quick follow-up? There's a chance, though, that you could lose the bonus ITC on those. Would that be right?

Mads Nipper

executive
#20

We aren’t treating that as a material risk. Our assumption is 40%, and we expect this to be firmed up with regard to the energy credits community, or energy community credit. So we view the chance of that occurring as immaterial.

Peter Bisztyga

analyst
#21

Alright, thanks a lot.

Operator

operator
#22

The following question is from Jenny Ping of Citi. You have the floor.

Jenny Ping

analyst
#23

Thank you very much. I have a couple of questions, please. First, returning to the Brookfield transaction: I'd like to understand what discussions you've had concerning the FFO net debt definition, since this will now effectively be treated as a minority stake? Is it still included? So does that artificially inflate your FFO net debt figures, given it's calculated on a consolidated basis? And related to that, obviously with the call option in place, it could look as though you've simply taken out a loan to repair the balance sheet for the time being. Can you give us any insight into the pricing of the buyback of the assets, or what rate you are effectively paying for that loan? And lastly, I note that today it's very much a buyer's market in some of these assets. A lot of assets are coming up for sale. I know you have a balance sheet fix to make, but do you have any aspirations to acquire some of these assets that are coming up for sale, to bolster the longer-term plans and growth profile of Ørsted? Thank you.

Trond Westlie

executive
#24

Regarding the (indiscernible) transaction, we evaluate every structure and each element of them, just as we do with all our farm-downs and deals. With this particular transaction, we're selling 25% — or 24.5% — of our share of the assets. Consequently, nothing beyond that amount factors into the consideration as such. Across all transactions, it matters to us that we examine the FFO multiple against where we currently stand, since we're in a transition and need to reinforce parts of our balance sheet. So that certainly plays a role, though it isn't what drives the structure of the transaction as such.

Mads Nipper

executive
#25

Yeah, and I can address that last question of yours, Jenny. So, when it comes to the assets for sale, our attention is entirely on delivering against our strategy. Of course, we'll evaluate possibilities, but there are no particular plans in place, nor any necessity, to hit the ambitions we laid out in the plan we introduced in February.

Jenny Ping

analyst
#26

Thanks a lot. Sorry, Trond—could I get you to be a little more specific on FFO net debt? So you'll calculate that at the group level. There's no minority adjustment at all stemming from the minority stake that you don't own anymore?

Trond Westlie

executive
#27

Well, naturally, that has to be recorded as a minority interest on both the P&L and the balance sheet. But beyond that, what you referred to was the discussion we had regarding FFO to net debt as a kind of condition of the transaction itself, and that hasn't really been any driving force. It's more the overall transaction, together with also, as you said, the option, which isn't really in the money as such. It's more an element of flexibility that we actually find very interesting relative to the position we're in today.

Jenny Ping

analyst
#28

All right. I may need to check back with our team on that, since I don’t think it’s very clear, but thank you.

Operator

operator
#29

The following question is from Deepa Venkateswaran at Bernstein. You have the floor.

Deepa Venkateswaran

analyst
#30

Thanks. I’ll likely pick up on that same topic as well. You said this transaction delivers a substantial amount of value creation. Given the accounting treatment, you clearly can’t quantify the book gains. Could you give any indication of what the book value was for the assets tied to the stake you’re divesting, so that we can calculate it under our assumptions—perhaps it’s DKK 5 billion of book value, and maybe you can bridge the difference? And second, on the call option, you’re saying right now that it’s not in the money. Presumably, if you exercise it after four or five years, the cash flows from those assets will have declined further. On average, I think they’re already five years old at this point. So presumably that valuation already captures the runoff value and so on. So, under what circumstances would you buy them back? Maybe you could help explain the conditions in which you might repurchase them. Is it assumptions about power prices, changes in interest rates, or your balance sheet being in a stronger position in a few years? Could you help explain that a bit? Thank you.

Trond Westlie

executive
#31

When it comes to how we'll account for the transaction, I mean, we've examined the — we're examining this deal as being recorded at the point we close it, and we're aiming for that in Q4 as a kind of minority, basically a minority sale. So we haven't examined the book values, and we haven't truly examined the other approach to booking it. So right now, I can't provide any guidance on that. And moving forward, the option value is of course a factor we're seeking in terms of flexibility and the dynamics. And like I said, because it isn't in the money today, I suppose that ties to what you can consider when you actually look at how the market price develops and so on in the UK market going forward, and that's essentially what the triggers will be then.

Deepa Venkateswaran

analyst
#32

Right. So that was tied to the higher power price, or something along those lines. All right, thanks.

Operator

operator
#33

Casper Blom from Danske Bank has our next question. Go right ahead.

Casper Blom

analyst
#34

Yes, thanks a lot. I also have a question about the Brookfield deal. You've now sold off part of what are actually operating assets, taking the stake below 50%, and you've mentioned before that this was likely part of the farm-down plan you laid out earlier this year. Is that portion of the plan now complete, or should we anticipate further farm-downs in the parts where you currently hold 50%? Thank you.

Mads Nipper

executive
#35

Yes, thanks, Casper. What I'd say is that we've made a very conscious choice not to disclose specifics about the transaction or the farm-down plan we launched in February, and the reason is that we want to keep full flexibility so we can go after whichever farm-downs are most attractive to us. So we won't be providing any specific guidance on that. That said, broadly speaking — and we've communicated this as well — the simplified approach is that there's a standard model of farming down 50%, and then in select cases we would also sell minority stakes in operational assets. One thing we did mention, and it's still likely to happen, is a minority stake in West of Dunddon Sands. We spoke about that in February, so that is something you can still expect to happen. But we won't be making any further comments on the details, because doing so would remove our flexibility to pursue the most attractive farm-down options.

Casper Blom

analyst
#36

Got it, that’s very clear. Thanks a lot, Mads.

Operator

operator
#37

We’ll now take the next question, from Harry Wyburd at BNP Paribas. Harry, please go ahead.

Harry Wyburd

analyst
#38

Hi, everyone. Thanks for taking my question. So I wanted to focus on the DKK 5 billion write-back that you made on the cancellation fees. I'm curious to learn how you'd deploy that extra headroom. Would you simply retain it as lower debt ratios? Would you want to use those funds to cut back on the number of farm-downs you carry out, or perhaps even scale up your organic CapEx plans? I suppose DKK 5 billion by itself is a not insignificant sum of money, but I'm also curious, more broadly, if other things go better from a cash perspective going forward, where would you prefer to put any incremental balance sheet dollar that comes in. Thank you.

Trond Westlie

executive
#39

Honestly, we're quite pleased with how this turned out, and with what the team handling the resolution of the situation has achieved — they had the idea and have gotten us this far. That said, and as you also pointed to, DKK 5 billion is a substantial sum, but if you look at the proceeds level we're actually aiming for in 2024, 2025 and 2026, it's roughly around the DKK 70 billion mark. So in that respect, it eases the pressure from this, yet it isn't a major figure in the overall funding of our business plan toward 2026 or 2030. So I don't believe this outcome from Ocean Wind really puts us in a spot where we'd want to go into detail about priorities going forward on that measure.

Harry Wyburd

analyst
#40

All right, that's fair. Thanks.

Operator

operator
#41

The next person in the queue is Alberto Gandolfi from Goldman Sachs. Your line is open, please proceed.

Alberto Gandolfi

analyst
#42

Hello, and thanks for taking my question. I’ll keep it to just one. I wanted to ask what percentage of Sunrise and Revolution US projects in general — what share of equipment or services is imported? The reason I ask is that, just in case we assume a levy gets imposed by a new administration, I was wondering whether your contracts provide for any kind of pass-through. And I suppose the answer is no, because you basically have a contract. So I’m just trying to gauge the risk here of, say, trades — I wouldn’t call it a trade war — but incremental levies, perhaps delaying delivery of equipment, leading to more impairments or maybe raising the costs of what you are developing. Again, I know it’s a what-if question, but if you could help us navigate understanding the contract and which percentage matters, it would be really helpful. Thank you.

Mads Nipper

executive
#43

Yes, thanks a lot, Alberto. I can't give you the specific percentage because we simply don't have that top of mind. As we said, we're actually quite well advanced on the construction of Revolution. I mean, 53 out of around 65 monopiles have been installed, nine turbines, and a lot of the equipment is already there. So in that sense, you can assume that the outstanding there would be relatively limited. And then if there is — I mean, and again, this is pure speculation, but there would be an implementation period, which we are convinced that should that even happen, that this would be something there where there would be a period to ensure that the effect is in any instance, even in a worst case scenario, quite manageable.

Alberto Gandolfi

analyst
#44

That really does help. Thanks a lot, Mads.

Operator

operator
#45

The next person to ask a question is Robert Pulleyn from Morgan Stanley. You have the floor.

Rob Pulleyn

analyst
#46

Hello, and thanks. Since there have already been plenty of questions on the topics we’ve been covering, I’ll take things in a different direction. One of your slides caught my eye: in Poland, Baltica 2 is now shown as pending FID. My understanding was that it had already been pending FID, instead of being marked with a 2027 COD. So I’m curious—what has changed? Is there any material capex that could result in some impairments there? A bit more detail on that would be really helpful. Thank you.

Mads Nipper

executive
#47

Glad to, Rob. No, nothing has changed. We’re in precisely the same position we’ve discussed previously. And the expected schedule remains unchanged. We’re working toward an FID, with the main outstanding item being the project finance for our partner PGE, while the EPC portions of the projects are well advanced and, as far as we currently know, free of any negative surprises. So there’s no material news on that, and we hope to work toward that FID at the very end of the year.

Rob Pulleyn

analyst
#48

Alright, thanks.

Operator

operator
#49

Our following question is from Jingjie Yang with UBS. You have the floor.

Mark Freshney

analyst
#50

Good afternoon. This is Mark Freshney from UBS — apologies, I should have said that first — and thanks for taking my questions. First, on Hornsea 4: that's obviously a very big jump in the strike price. What is your cost outlook telling you, and where do you land relative to that kind of WACC plus 150 to 300 bps return framework? My second question concerns wind speeds. We are now three and a half, nearly five years into a stretch where wind speeds appear to have been structurally weaker. I know you've commissioned work on this and done your own analysis to try to get to the bottom of it, but how confident can we be that a lot of the existing assets — built on a business case with a set IRR, a set wind speed and load factor — how certain can you be that those load factors still hold? Thank you.

Mads Nipper

executive
#51

Yes. Thanks a lot, Mark. You won't be surprised to hear that we're not going to comment in detail on the value creation of Hornsea 4, and therefore also not on where it falls within the 150 to 300 basis points spread to WACC. But as we've said previously, we're satisfied with the value creation of the projects, and since the award it has progressed further as we planned. Also, specifically on cost, we won't give you any details, but as you'd expect — and this is also why the price came in higher — the per megawatt CapEx is higher than it was for Hornsea 3, which was contracted largely before the steep end of that curve. But we're satisfied with the returns of both projects. In terms of the structurally lower wind, we're actually not, at least where we have our offshore assets, seeing a structurally lower wind this year. It's very, very close to normal wind speeds. And it was also close last year. So, therefore we have no concerns that where we have by far the majority of our assets that we are looking at this. We had one really challenging year in 2022.

Mads Nipper

executive
#52

But 2023 and 2024 up to now have been pretty much in line with typical conditions. I don't recall getting that wrong — in fact, wind levels this year have run slightly higher than usual.

Mark Freshney

analyst
#53

Alright, thanks a lot. That's quite interesting.

Operator

operator
#54

Dominic Nash from Barclays has our next question. Go right ahead.

Dominic Nash

analyst
#55

Good afternoon, and thanks for taking my questions. May I ask two? First, on your CapEx figures — I believe you've cut the 2024 guidance by 20%, which looks like a fairly large reduction this late in the year. I think you mentioned that timing is the reason. Could you remind me of your CapEx numbers again — are they on an accrual basis or a cashflow basis? And will that kind of reverse in later years? My second question: I was intrigued by what happened, I think, in Sweden yesterday, where the government apparently canceled a whole set of offshore wind projects on security grounds. Is this — could this become a trend across the entire Baltic given the Russian threat? And then, as you look at other assets elsewhere in the world, perhaps even Taiwan — if Taiwan wants to be able to see what goes on past their radar — I'd be intrigued by your views on offshore wind and security. Thank you.

Trond Westlie

executive
#56

Okay, let me handle the simpler portion of what you asked. Regarding CapEx, yes, that figure is measured on a cash flow basis. And the answer to your second point is likewise affirmative — it comes down to timing, which means those cash flows will consequently be shifted out into subsequent years.

Mads Nipper

executive
#57

I'm glad to address the defense-related questions, particularly regarding Sweden. First, though, let me say that we completely grasp why Sweden's armed forces and government want to make sure security issues are handled seriously—and they should be. That said, Ørsted has quite a lot of experience collaborating with other Baltic Sea nations, working alongside governments and militaries to use offshore wind farms constructively in ways that strengthen defense. And that means—well, I can't share specifics, but we're among the few developers with NATO-cleared staff dedicated specifically to solutions that can assist. We have that capability in Denmark, Germany, and Poland. And based on our conversations with those governments, we see no reason to think—to get to the heart of your question—that such security concerns will extend further and become something that halts or delays offshore wind.

Dominic Nash

analyst
#58

All right, thanks.

Operator

operator
#59

The following question is from Olly Jeffery at Deutsche Bank. Go right ahead.

Olly Jeffery

analyst
#60

Hello, and thanks. I'd like to go back to Revolution Wind, if I may. There are two questions there. First, could you break down the extra DKK 1.7 billion impairment taken this quarter? How much of it relates to the vessel monopile problem versus other matters? Second, I understand you're saying there's no risk as things stand through the commissioning date for that project in 2026, but I'd like to grasp this: if the monopile installation for the substation keeps running into trouble, at what stage — and how much time do you have to fix it — before that 2026 date starts to be a worry? And last, on Taiwan and that sale, may I confirm you're confident the closing price and the proceeds will arrive by year-end? Or is it simply your hope that the deal gets finished, with the proceeds landing next year? Many thanks.

Trond Westlie

executive
#61

Regarding what has shifted with the project, the key factors really center on Revolution — as Mads mentioned during his introduction, that's the vessel for which agreements have now been finalized — along with the monopile difficulties we've reviewed and are currently assessing mitigation options for in terms of resolving them. Those are essentially the components, plus a project review concerning the offshore scope and the contingencies we've allowed for. So those items are what make up the DKK 1.7 billion. Beyond that, we won't be getting into greater detail.

Mads Nipper

executive
#62

Let me also address the possibility of additional schedule effects. At present, Olly, we aren't seeing that exposure, and the reason is that the project's critical path, schedule-wise, runs through the onshore substation. So our present view is that even under a conservative case, monopile installation is not something we anticipate affecting the overall schedule. And that's also because we've made good progress—most of the monopiles are already in place. So we likewise can't see that posing any schedule risk. Turning to Changhua 4, this is a case where we do expect the signing—if I've understood your question right, both the signing and a closing—to come very near New Year. So it's expected this year, though it could potentially slip into early next year. But that is the schedule. And we are—given that the last regulatory hurdles have been cleared—very confident it will occur around that timeline.

Olly Jeffery

analyst
#63

Alright, thanks a lot.

Operator

operator
#64

Next up from DNB Markets is Helene Kvilhaug Brondbo. The floor is yours.

Helene Brondbo

analyst
#65

Yes, hi there. I’ve got a few questions as well about the impairments booked this quarter. The offshore piece has already been covered, so I figured I’d focus on the onshore side. I’m curious whether you can share any specifics on what portion of those impairments is tied to what you call higher costs versus lower prices, and which costs have gone up. Then my second question is about the farm-down on Sunrise. How do you expect that to move forward, and do you think it’s a function of both the supply chain problems in the US and the supply-demand balance for projects? Given that there are a lot of projects being sold in the US right now, how has that affected farm-down or the appetite for acquisitions?

Trond Westlie

executive
#66

On the onshore impairment, two elements are driving the effect in this quarter. There's the interest rate effect, which has a positive component. And the second item is a more technical one, related to how we adjust long-term market prices. That's purely technical, because it's an impairment taken essentially on the derivative — a financial derivative arising from a contract on one of our onshore assets — which drives the reduction in an NPV on the project. Consequently, it's effectively a technical downturn, even though it's a hedged accounting element. And that basically comes out as a DKK 700 million adjustment. So that's one element. So no cost element is driving the impairment items on the onshore. In our view, the adjustment to the impairment is purely technical. On the Sunrise, sorry, on the Sunrise follow-up, of course the market is challenging, of course, in the market. We have seen the changes. As usual, we're planning our process very diligently and are doing our sounding on the investors. But of course, as you're saying, the more negative trends coming out of the US market, of course it will challenge our way to go forward.

Trond Westlie

executive
#67

And looking at it right now, our perspective on the chances of completing a farm-down down the road hasn't shifted. That said, with the election happening today, a lot could unfold. Still, at this point, our thinking and our plans for the Sunrise farm-down remain unchanged.

Helene Brondbo

analyst
#68

I appreciate that.

Operator

operator
#69

Meike Becker from HSBC has our next question. The floor is yours.

Meike Becker

analyst
#70

Yes, thank you very much for taking my questions. If I could return, please, to the asset rotation on the founder program — I mean, as you walked through (indiscernible), it's moving faster than expected, but is the quality as expected, or better, or worse? And I suppose with the first round of deal announcements and the minorities treatment, that's difficult to assess. So, would you be willing to discuss the 2030 net income expectations? So, you've given guidance at an EBITDA level, but internally, I'm sure you have a view on, sort of, your net income expectations for 2030 as well. What you'd be willing to share with us is, relative to your in-house expectations, without saying what the numbers are, is it better, is it worse, or is it similar to what you said on the EBITDA range — the same? Thank you.

Trond Westlie

executive
#71

Regarding the goals we’ve set for 2026 and 2030, we’re progressing toward those figures, and right now we’re tracking in line with the guidance and targets we’ve provided. It feels more natural to give you updates on our longer-term targets once a year rather than responding to things that come up each quarter. Because of that, we really don’t think we’ll be providing any updates on the 2026 and 2030 targets as of now. Those targets remain in place. They’re still within our working scope. So at this point, we have no further update beyond saying that 2026 and 2030 are firm. As for the specifics you’re asking about, regarding minority interest, we haven’t really taken the effect of those into account, and that also depends on the farm-down processes we’ll carry out going forward. Overall, I view this as a broader, holistic overview that we won’t be addressing on this quarter’s call.

Meike Becker

analyst
#72

All right, thanks.

Operator

operator
#73

Ingo Becker from Kepler has our next question. The floor is yours.

Ingo Becker

analyst
#74

Yes, thank you very much. Good afternoon. I have a question about the Brookfield transaction as well, please. The DKK 37 per kilowatt price you received does look attractive compared with the DKK 44 average you achieved on the earlier 50% farm-down. I'm just wondering whether you could share if your own assessment for these projects in general has changed, or whether your internal IR calculations have stayed the same over time, and whether you would explain the drop of roughly DKK 17 in the price. And again, I don't think that's a lot for a five-year period on average, whether it's simply the passage of time or whether other things have changed. And also, if maybe that type of farm-down, where you keep consolidating a 50% stake, so that you have no — it doesn't cost you any EBITDA. You get cash in, and during that, debt funds flow from operation actually improves, if we might see that again or more often, it's not a viable way of doing a farm-down also maybe with other projects. The other questions I had would please still be on the Swedish situation. You have commented on that. I'm just wondering if there's a new element included here, I mean, as you mentioned, that you are generally in talks with governments on defense issues.

Ingo Becker

analyst
#75

What I’d gathered up to now was that you could perhaps deploy your (monolith) towers against particular radars or similar. And in this instance it appears the Swedes are in fact concerned that wind parks stop unfriendly actions from being detected, rather than the parks themselves being the target. Is there something new in that, or have you encountered worries of this kind in other circumstances previously? Is it genuinely specific to Sweden and Russia? Thank you.

Trond Westlie

executive
#76

On the Brookfield asset valuation, we're with you — we see this deal as accretive in value and financially appealing. What's different from earlier is, naturally, that interest rates have moved, and the CFT period has been made shorter. Because of that, greater merchant risk now feeds into the valuation. So overall, several factors play into this, yet as we view the transaction right now under present market conditions, we actually see a very strong degree of value retention. So all in all, it's a good deal for us. As for the components going forward — whether that ends up as minority interest or proportional consolidation — that hinges on where we can genuinely identify value creation across the individual transaction and which counterparties we'll be working with. So it truly comes down to the elements before us. We genuinely believe that the deal's value, its financial appeal to us, and the value retention are the main drivers, and that's what we'll be focusing on. So it's hard to give guidance on where that will land, but having some minority interest is not exactly natural for a company of our size.

Mads Nipper

executive
#77

Sure, I’m glad to address the Sweden question, since it’s a continuation of what came up earlier. In our conversations with other governments and armed forces, we haven’t encountered a situation in which using radars or other technology—sonar technology or other technologies—would create an added concern for the country. So, based on what I know today, this is a Swedish view that stands alone.

Ingo Becker

analyst
#78

All right, thanks.

Operator

operator
#79

David Paz from Wolfe Research has the next question. Go ahead, please.

David Paz

analyst
#80

Hello there, and good morning. I appreciate you giving me the chance to ask something. Am I coming through clearly on your end?

Trond Westlie

executive
#81

We hear you.

David Paz

analyst
#82

Thank you. I appreciate all the information about Revolution. I have a few follow-up questions, if I may. Regarding the monopile problems you mentioned and the vessel extension — did those come up only in recent weeks? I think you brought up a possible vessel extension previously, so is this something newer, or has it been building for a while? Also, how will you keep us updated on progress — you described it as a rare occurrence, I believe. How can we tell whether it succeeds, and is there an operational project that has dealt with this issue that you could cite? Thank you.

Mads Nipper

executive
#83

Yes, thank you very much. So, the matter we've referred to previously is that we're working on possible additional mitigations across the projects to safeguard the schedules, while also weighing the project risks and how best to address them. Now, this extended vessel lease is one that has come in at a cost higher than we had anticipated, and that negotiation was finalised very recently. So that is therefore new. And in the same way, the monopile issue is in fact very recent, and it's something that arose within literally the last couple of weeks, which is also why we've made an early yet prudent assessment of what the expected costs and the impact of that could be. And as for the second part of the question, on how to provide updates, we will of course do that on our quarterly calls, but this is new information. It reflects the best of our current knowledge. We believe we've taken a prudent approach. And as Trond said, we've also, in general, carried out a risk review and updated our contingencies for the project. You also mention — you also asked whether this monopile refusal has occurred before.

Mads Nipper

executive
#84

Like I said briefly during the intro, this has occurred on two prior occasions, with more than 2,000 monopiles put in place. So the frequency of it happening is extremely low. It isn't a situation where we perceive a prolonged exposure, but within this kind of EPC project it is a possibility — though only on very, very uncommon instances.

David Paz

analyst
#85

All right, and I’d assume the higher cost is tied more to the vessel than to this refusal — the monopile refusal issue. Is that right?

Mads Nipper

executive
#86

As Trond mentioned, we won't be disclosing how that breaks down. So we're not going to get into specifics on the individual buckets. The three categories, though, are the vessel, the monopile refusal, expected cost, and the higher contingencies and power price assumption. That's what the buckets are, and we won't be providing any further detail beyond that.

David Paz

analyst
#87

All right, thanks.

Operator

operator
#88

We’ll keep going with a few follow-up questions, and first up is Casper Blom.

Casper Blom

analyst
#89

Yeah, just one quick question. Thanks. You said you'd revised your assumptions for power prices, and that affected the US business somewhat. Could you perhaps expand a bit on what you've changed and what the new assumptions are, if you're willing to share that? And maybe also give a little more insight into your methodology for wanting to do this. Is this something you've chosen to do for some reason, or is it part of an ongoing process? Thank you.

Mads Nipper

executive
#90

No — it’s a fully… thanks, Casper. It’s a completely standard procedure in which, at a set interval, we refresh our long-term power price assumptions, and as a result we also revise how the business cases look. And once a project falls into impairment territory, any adjustment affecting that project will naturally show up in our accounts. In this instance, refreshing those longer-term power prices resulted in lower US power prices — unlike Europe, where that same update had not led to any additional decline. So this is an isolated matter, and it’s entirely consistent with a normal operating process that we’ve followed for a very long time and that we consider prudent to carry out at a set interval.

Casper Blom

analyst
#91

Got it. As a quick follow-up — mostly out of curiosity — when you form those longer-term power price views, do you carry out that analysis in-house, or are you essentially taking an average from outside consultancies? What does the process look like? And is there any particular reason you settled on a lower power price for the US?

Trond Westlie

executive
#92

So look, this is a process that's pretty thorough on our end. We've got a solid team of folks who really dig into the specifics of how market prices are developing in the territories where we operate, and there's a rigorous process inside the business. Naturally, we incorporate all the benchmarks — external ones — as part of that, but on top of it, we also form our own independent view. So the process is thorough. We run it both quarterly and annually. And that work is very much our own, done for ourselves, and we don't disclose it to anyone.

Casper Blom

analyst
#93

Alright, thank you very much.

Operator

operator
#94

Peter Bisztyga from Bank of America has our next follow-up question.

Peter Bisztyga

analyst
#95

Peter Bisztyga speaking once more. I'd like to pick up where we left off regarding how construction is progressing at Revolution Wind. Given that more than 80% of monopiles are now in place, the turbines are being erected, the bulk of the equipment sits on site, and a vessel has been contracted, would it be reasonable to say so? Sure, one monopile ran into a one-in-a-thousand problem, though hopefully a second such case won't arise. Can we fairly conclude that the scope for additional operational impairments has shrunk quite substantially at this point, or do other meaningful known unknowns exist that we ought to hear about, ones that might create trouble during the coming few quarters? Tied to that, do you consider the contingencies set aside for Sunrise Wind sufficient, in light of the difficulties encountered at Revolution so far? Thank you.

Mads Nipper

executive
#96

Absolutely, glad to address that. You’re correct, Peter. Even with the recent difficulties we’ve run into, construction on Revolution is quite far along. And it’s worth noting that unlike certain other disruptions this industry has seen, construction keeps moving at full speed right now despite the monopile installation issue we’re dealing with. So nothing is being held up in the remaining turbine monopile work, the turbine installation work, or the array cable installation work. All of that is proceeding at full speed concurrently, which ties back to the earlier question I received: we don’t see this creating any material risk of additional project delays. With 80% of monopiles in place and turbine installation underway and accelerating, all else being equal, risk is coming down, so with the contingencies we currently hold, we feel good about it. That said, no one can claim a project has zero risks remaining before it’s finished. Still, based on what we know today, we’re comfortable that this is a robust project. As for Sunrise Wind, yes, naturally we’re evaluating that continuously, as we noted, given what affected us last quarter, and because of that the overall onshore project timeline at Revolution is completely on track for Sunrise.

Mads Nipper

executive
#97

So that's one key bottleneck. And we also aren't seeing any updates regarding monopile deliveries. The monopile supply plan we announced last quarter still stands. So yes, based on what we know right now, we feel that is at an appropriate level.

Peter Bisztyga

analyst
#98

That's excellent. Thank you so much.

Operator

operator
#99

Mark Freshney from UBS has the next question.

Mark Freshney

analyst
#100

Hello, and thanks for the question. Mads, thinking strategically about the 2030s: since your pipeline essentially is almost entirely locked in through 2030, beyond that point the regions that have worked well for you — the UK and Germany — you've more or less exhausted the seabed, or at least the high-quality consented seabed there, which is arguably a good spot to be in, but you're very much at the mercy, perhaps, of the US and Taiwan, and yet you don't have particularly much consented seabed, and you'd be competing for bundled rights, projects, and contracts. So my question is: what options exist for handling this, and how are you thinking about the period beyond 2030?

Mads Nipper

executive
#101

Yes, thanks very much, Mark. You're correct — with the awards on Hornsea 3 and Hornsea 4, we've basically reached the point we'd need to hit by 2030. We're keeping our options open until then. But as things stand, this is what would get us there on the offshore side. We're developing new opportunities in the UK — for instance, off the Isle of Man — and naturally we'll also be keeping a close eye on the upcoming seabed auctions from the Crown Estate, watching for what would be a good and opportune moment to potentially pick up new real estate there as well. That said, it's something we'll be monitoring, and we feel no urgency to lock that in. Saying we're at the mercy of the US and Taiwan is a bit of a harsh way to put it. In fact, we view both markets as very attractive. But keep in mind that the centralized auctions — in, say, Denmark, Germany, the Netherlands, Belgium — those are options where you don't need to hold the proprietary seabed. And in the last couple of auctions in Germany, we didn't find the terms attractive, though we also have a number of additional projects in our pipeline, such as the 1.6-gigawatt greater Incheon product in Korea.

Mads Nipper

executive
#102

In Australia, we secured a lease of nearly five gigawatts. And of course, we'll keep watching for opportunities, together with the sizable remaining portion of lease area 500 in the US. So overall, we do feel that given a mix of what we expect to be a high volume of centralized tenders plus an appealing pipeline, we can pick the most attractive options against that backdrop, and we're in good shape as we head into the 2030s.

Mark Freshney

analyst
#103

Appreciate it — that’s very clear.

Operator

operator
#104

Next, we’ll take a follow-up from Harry Wyburd at BNP.

Harry Wyburd

analyst
#105

Hello, and thank you all. I appreciate the chance to ask one more follow-up. I'm not certain how far you can or are prepared to address this, but I'd like to ask about Equinor acquiring its stake in your company. What interests me especially is that there's a certain irony here, since you're clearly working to bring in substantial funding, and then Equinor steps in and purchases a large secondary stake in you. So, before Equinor took that stake, did any talks take place with them about whether they might consider purchasing some assets from you rather than buying into you, or perhaps taking a primary stake, which clearly would resolve the funding concerns? And does Equinor's presence alter how you view running the business and the balance sheet going forward? And might they become a partner for raising capital or for funding through asset sales down the road? Thank you.

Mads Nipper

executive
#106

That's a fair point, Harry. I won't go into specifics about the shifts in our shareholder base. We only learned about Equinor's larger ownership stake after their own public market announcements, and our attention stayed entirely on carrying out our strategy and meeting our mid- and long-term targets. As for Equinor's possible intentions, that's not something for us to address.

Mark Freshney

analyst
#107

All right, thanks.

Operator

operator
#108

Dominic Nash from Barclays has our next follow-up question.

Dominic Nash

analyst
#109

Yes. Hello, and thanks once more for the follow-up question. The UK NISO released its Clean Grid 2030 program this morning. I'm not sure whether you've had an opportunity to review it, but I simply wanted to ask what your views are, and what opportunities it presents for Ørsted, along with zonal pricing in the UK. Do you support or oppose zonal pricing in the UK, and what effect would that have on Ørsted? Thank you.

Mads Nipper

executive
#110

Yeah, thanks very much, Dominic. Your assumption is correct — things have been a bit too hectic today for us to get through that material. My suggestion is that you continue the conversation with IR, and we'll gladly share our perspectives.

Dominic Nash

analyst
#111

Zone pricing isn’t new—it’s been in place for quite a while. What’s your take on it?

Mads Nipper

executive
#112

That isn't something we're going to disclose at this point.

Dominic Nash

analyst
#113

All right, thanks.

Operator

operator
#114

The next question in the queue is from Deepa Venkateswaran, who is with Bernstein.

Deepa Venkateswaran

analyst
#115

I appreciate you taking a follow-up question. I'd like to circle back to a point you made earlier, Mads, regarding a possible US tariff being introduced gradually. At this moment, Revolution Wind is clearly quite far along, whereas with Sunrise you're only at the beginning. So could you perhaps walk us through how you envision a transitional period being structured, and is there any route to bring some of the equipment from Europe into the US sooner? I'm not sure whether your turbine supplier has even produced it yet, but yes, perhaps some thoughts on how that transition could take shape. Thank you.

Mads Nipper

executive
#116

Thanks, Deepa. No, I mean, this was really prompted by a question about what could potentially occur, nothing more. We don’t have any particular scenarios in hand. It’s simply that, where Revolution is concerned, the great majority of that is brought in from abroad. And as for Sunrise, we’d be at ease with the project’s present timeline — what would, even if this were to come in, and again that is purely speculative, then we would feel that this is something manageable given what would be expected to be a facing, but we have no specific hypothesis or knowledge on that subject that we’re able to share.

Deepa Venkateswaran

analyst
#117

Okay, thank you.

Operator

operator
#118

The final question in today's conference call is from Olly Jeffery at Deutsche Bank.

Olly Jeffery

analyst
#119

Thanks. I wanted to touch on the DKK 3 billion provision that remains on Ocean Wind, particularly after the sizable cancellation fee reversal you recorded in Q3. Regarding what those provisions specifically cover, how much confidence do you have that we could see an additional cancellation reversal in Q4? Given the nature of what these provisions are for, is that a realistic probability or not? Thank you.

Trond Westlie

executive
#120

Thanks. The estimate we’ve taken this quarter is, of course, our best estimate of how we’ll end up. And because of that, that’s of course why we have the DKK 3 billion. And the reason for mentioning the DKK 3 billion is really to show that we actually come down to such a low level that the concern around sort of winding up Ocean Wind is coming very much to a close, and that was really the reason for mentioning the DKK 3 billion.

Mads Nipper

executive
#121

Thanks a lot. And with no more questions coming in, I simply want to express my appreciation for all of your questions. We always value your engagement, and I hope you have a good and safe day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ørsted A/S transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Ørsted A/S earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ørsted A/S or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.