operatorGood day, everyone, and welcome to Ørsted's Q3 2026 Earnings Call. This is Lorenzo, your Chorus Call operator. <<operator_script>> Please note that this conference is being recorded. <<operator_script>> Recording this conference for publication or broadcast is not permitted. Right now, I'm happy to introduce Group President and CEO Rasmus Errboe, along with CFO Trond Westlie. Please proceed.
Rasmus Errboe
executiveHi, everyone, and thanks for being on today's call. With geopolitical uncertainty and volatility in global energy markets still with us, it's become clearer and clearer how important it is to strengthen European energy independence and industrial competitiveness. You can see this reflected throughout the wider European energy debate, and there's recognition that renewable energy, offshore wind included, will be critical to delivering on those objectives. The most recent reminder of Europe's unsustainable exposure to fossil fuel price volatility came last week, when gas prices hit EUR 100 per megawatt hour for the first time since 2022. Among industry organizations, policymakers and energy companies, there's growing alignment that we need to accelerate electrification, expand domestic renewable energy production and strengthen energy infrastructure. Electrification will sit at the heart of Europe's energy transition, from industry and transport to heating and new sources of demand like data centers and AI. Making it affordable for industry and households means expanding competitive renewable electricity, along with the grids and infrastructure to deliver it. That calls for the right conditions on both the supply and demand side: a credible deployment target, investment frameworks that reduce risk, faster grid development and permitting, cross-border coordination, stable regulation and stronger incentives to electrify. This has also been the trajectory for the European offshore wind industry, where regulatory frameworks for upcoming opportunities keep improving, strengthening investment certainty for future projects.
Rasmus Errboe
executiveFrameworks have improved in a number of our core European markets, among them Denmark, the U.K., Poland, Belgium and the Netherlands. And in the latest development, Germany has approved a draft amendment to the Offshore Wind Energy Act that brings in contracts for difference, CfDs, for the upcoming auction. The fact that CfD-based frameworks are being adopted more and more shows a widening political acknowledgement that enabling regulatory conditions are needed if offshore wind capacity is to be realized at scale. In the third quarter of 2026, we demonstrated precisely the benefits that we, working alongside partners, suppliers, customers and regulators, are able to deliver when it comes to secure, affordable and homegrown energy. With 1.6 gigawatts commissioned from Borkum Riffgrund 3 in Germany and Revolution Wind in the U.S. over recent months, we are taking a significant step toward delivering on our sizable offshore wind construction portfolio. And thanks to the strong strategic progress achieved over the past 21 months, we have reinforced our position with a market-leading Offshore Wind portfolio that offers significant revenue visibility, and we have made sure we are in a robust position to pursue new value-accretive opportunities. Over the long term, we are convinced that Offshore Wind is going to become an even more critical element of the energy mix, particularly in Europe.
Rasmus Errboe
executiveAnd over the near to medium term, we're beginning to witness considerable regulatory momentum. In 2027, auctions for over 15 gigawatts of new capacity are coming in our core markets across Europe and Asia Pacific. And between 2028 and 2030, nearly every country in our core markets has already committed to further auction rounds, among them Germany, the Netherlands, Denmark and the U.K. We're ready to chase these opportunities in a disciplined manner. Let's move on to Slide 5 and an update on strategic priorities plus our operational performance. Strengthening our capital structure is our first priority. And since we set out our strategic priorities at the start of 2025, we've made significant progress on this. Under our divestment program, the sole remaining item is the closing of the divestment of a 55% stake in our Greater Changhua 2 project in Taiwan. Completion of the transaction is anticipated after the final commissioning of the Greater cn 2b and 4 project. In September, we got a final opinion concerning the taxation rights tied to the Warning extension in Hornsea 1 offshore wind farms in the U.K. That result aligned with our long-held reading of international tax regulations, and we're pleased with it.
Rasmus Errboe
executiveAlso, together with the favorable result in the ISAM matter right before summer, these represent meaningful moves toward further reducing risk on our balance sheet. Delivering our Offshore Wind construction portfolio stands as priority number two. Beyond completing final commissioning at the 1.6 gigawatt offshore wind projects, we have made substantial headway on every project, and each one is tracking to plan and within budget. I'll walk through the construction progress in detail shortly. Priority three is maintaining a focused, disciplined stance on capital allocation, with our main emphasis ahead falling chiefly on Offshore Wind in Europe plus chosen APAC markets. And we'll remain disciplined, centered on creating value across all our core markets. We're likewise continuing to build out our U.S. Onshore business, which keeps performing strongly and gains from robust fundamentals. During September, we began construction on our Blackwater solar project — a 200-megawatt solar farm located in Roseville County, New Mexico. That project is expected to supply power via a long-term Corporate Power Purchase Agreement, which shows our capacity to satisfy customer demand through dependable, affordable power solutions while drawing on a domestic supply chain.
Rasmus Errboe
executiveWe expect the project to hit commercial operations during the second half of 2027. We're also continuing to advance our U.S. onshore pipeline, and there we gain an advantage from holding over 6 gigawatts of safe harbor equipment for tax credits. Back in October, we used a long-standing buyback right to pick up the remaining ownership stake in the Gunfleet Sands 1 and 2 projects in the U.K., with total consideration of roughly GBP 15 million. Owning the projects in full will let us capture the asset's full value potential and gives us more flexibility when we look at options for a lifetime extension. Improving our competitiveness is our fourth priority, and across the organization we're carrying on as planned with numerous measures aimed at achieving a stronger and more competitive <<inaudible>>. Now to the operational highlights for the first 9 months. I'm pleased with how we performed operationally. Our EBITDA, excluding new partnerships and cancellation fees, comes to more than DKK 20 billion, an increase of almost 20% versus the first 9 months of 2025. That was driven by ramp-up generation in Offshore, wind speeds somewhat above normal and higher power prices. On safety, our Total Recordable Injury Rate has risen compared with the first 9 months of 2025.
Rasmus Errboe
executiveThat rise came mainly from incidents involving people we employ directly. Among contractor employees, we've observed fewer incidents, though hours worked were also lower. Safety stays a leading priority for the company and its workforce, and we keep stressing our safety commitments via focused efforts — among them tighter supervision, more frontline visibility, and exchanging best practices with suppliers — all with the goal of preventing incidents and getting our people home safely each day. Moving to Slide 6, here's an overview of our construction projects. First I'll cover those that have either begun commercial operations or are nearing that point, then go through the remaining projects one by one in detail. In August, our Borkum Riffgrund 3 project in Germany started commercial operations. At 913 megawatts of installed capacity, it ranks among the biggest offshore wind farms currently operating in Germany. This project shows how large-scale offshore wind can bolster energy security by supplying dependable, domestically produced electricity to German industry and households. The project drew on a wide European supply chain, using wind turbines and foundations from Germany and Denmark, cables from Germany and France, and installation vessels from the Netherlands and Belgium.
Rasmus Errboe
executiveBringing the project into commission is a huge milestone — for us, for our suppliers, and for Germany's offshore wind sector. And with our sixth wind farm now up and running in the German North Sea, we strengthen even further our position as market leader. Over at Revolution Wind in the U.S., we finished installing the last turbines in the quarter. And after that, the project entered commercial operation under the PPAs, and it is now delivering power to Rhode Island and Connecticut under the project's offtake contracts. The electricity from the project will be sufficient to power over 350,000 homes and businesses. That's a major milestone, and I'm very pleased with the resilience and the effort the team has shown in getting there. At Greater Changhua 2b and 4 in Taiwan, commissioning of the project keeps moving forward. In the third quarter, we finished installing the export cable for Greater Changhua 2b and then began delivering power from the turbines already installed. During the quarter, the project had a thermal incident and a blade incident at two separate turbines that had already been commissioned. Nobody was injured, and the project's other wind turbines are still operating. The turbine supplier is heading a thorough investigation into both incidents, and the preliminary analysis has identified where the incidents originated.
Rasmus Errboe
executiveIt's now been confirmed that the blade incident should be a one-off event, and that the thermal incident's root cause can be addressed going forward through steps that are already part of regulatory maintenance. The wind turbines affected are covered by supplier warranty, and a repair plan for the two turbines has been developed and agreed with the supplier. First power has been delivered by all 66 turbines. And apart from two turbines, all are now commissioned. We're working alongside key suppliers to commission the final two turbines and expect full commissioning to be achieved during Q4 -- commissioning during Q4. Moving to Slide 7 and an update on our Baltica 2 project in Poland. In the quarter, the project reached a significant milestone as installation of all 111 monopile foundations was finished, including the 4 foundations for the Offshore substations. Manufacturing of the 4 Offshore substations was likewise completed in the quarter, and they are now in transit to the site so they can be installed before the end of the year. Thanks to the progress made in the quarter, the degree of completion has risen to approximately 45%, up from 40% last quarter. Fabrication of the export and array cables is also progressing well.
Rasmus Errboe
executiveRegarding the export cables, 2 of the 4 are finished and are on their way to the site so that installation can begin around the end of the year. The array cables are likewise in transit to the site, with installation set to kick off in Q1 of 2027. Work at the onshore substation is moving forward as well, with testing and commissioning as the main focus. Over the next stretch, the project's attention will be on wrapping up the installation of secondary structures for the foundations and getting started on installing the 4 <<inaudible>> and export cables. If we move to Slide 8, here's where things stand with our Sunrise Wind project in the U.S. Solid headway has continued on this project over the quarter. That covers finishing turbine foundation installation, along with ongoing work installing turbines and array cables. Thanks to the headway made this quarter, the degree of completion has risen to roughly 60%, compared with 50% in Q2. At this point, several major scopes have had their installation finished, among them the onshore substation, the export cables, the offshore converter station and the turbine foundations. What's left to install involves the turbines and array cables. Out of the project's 84 positions, 31 turbines and 78 array cables have been installed in total.
Rasmus Errboe
executiveWork on installing the array cables should wrap up before this year ends, and turbines will keep going in over the winter months, with that work finishing in 2027. The project is also concentrating on ongoing commissioning activities at the offshore converter station. Commissioning of the initial turbines is scheduled to begin near the close of the year, and the project is still on schedule for full commissioning during the second half of 2027. On turbine fabrication, every piece of equipment still awaiting installation has already been built. In line with current activity, the project will keep bringing in planned shipments of various components — blades, towers and nacelles among them — into the U.S. as installation moves forward. Moving to Slide 9 for an update on Hornsea 3 in the U.K. The project advanced considerably, with installation of the second offshore converter station now finished. The project has also moved ahead on turbine foundation installation, with 95 of the total 197 positions now in place. Thanks to the progress made this quarter, the degree of completion has risen to roughly 40%, compared with 30% in the second quarter. In late September, the first enabling and reinforcement work got underway at the <<inaudible>> main substation, the point where Hornsea 3 will connect to the U.K.
Rasmus Errboe
executiveWork on the transmission system came in on schedule. The outages needed for back-feeding Hornsea 3's first link are now done, so Hornsea 3 has an initial grid connection, and we remain on track toward planned first power and commissioning. Of the two export cables, one has been fully installed, and on the other we have now put in both the near-shore and mid-shore sections, with installation of the far-shore section moving ahead as planned. Over the coming period, the project will focus on advancing foundation installation, with manufacturing and supplier foundations still on track. In addition, array cable and turbine installation is set to begin before year-end. The two turbine installation vessels are presently working on other projects before they start on Hornsea 3. Lastly, construction is finished on the 300-megawatt Battery Energy Storage System located alongside the Hornsea 3 onshore converter station. That battery system will rank among Europe's largest and will now enter the testing phase. With that, I'll hand things over to you, Trond.
Trond Westlie
executiveThanks, Rasmus, and good afternoon to everyone from my side as well. Let's begin on Slide 11 with the EBITDA for the third quarter. And as usual, unless I say otherwise, the figures I mention are in Danish kroner. During the quarter, our financial results came in as expected, and we posted an EBITDA of DKK 5.3 billion, excluding new partnership and cancellation fees. Let me take you through the key developments. In our Offshore business, total earnings reached DKK 3.7 billion, up 68% versus last year, with gains across every segment. Sites earnings showed positive progress, powered by ramp-up of Greater Changhua 2b and 4 and Revolution Wind, stronger wind speeds, higher power prices and greater contributions from our trading activities. Earnings from existing partnership rose thanks to the Hornsea 3 construction agreement, while the negative effect last year tied to Greater Changhua 4's array cable did not recur. In our Onshore business, earnings climbed to DKK 1 billion, a rise of 24% versus last year. That was mainly driven by new generation from Badger Wind and stronger wind speeds. Partly offsetting this were lower earnings after the divestment of the European onshore business earlier this year.
Trond Westlie
executiveUnder Bioenergy & Other, earnings rose to DKK 400 million, versus negative DKK 100 million a year earlier, thanks to stronger power prices, which drove more condensing power generation at our combined heat and power plants. Now let's move to Slide 11 -- no, apologies, Slide 12. During Q3, we booked an accounting technical noncash impairment loss of DKK 3.4 billion tied to our U.S. Onshore and Offshore projects, stemming from the 75 basis points rise in long-dated U.S. interest rates over the third quarter. Net profit for the quarter came to negative DKK 700 million, which is an improvement of DKK 1 billion year over year. Although net profit took a hit from those noncash impairments, it was partly offset by stronger EBITDA in the quarter. Net profit adjusted for impairments, new partnership and cancellation fees reached DKK 2.2 billion this quarter, compared with negative DKK 400 million in the same quarter a year ago. And adjusted for impairments and cancellation fees, return on capital employed was 7.4%, down from last year because of higher capital employed. Let's go to Slide 13 and look at our net interest-bearing debt and credit metrics. By the close of the third quarter, net debt stood at DKK 38 billion, an increase of roughly DKK 16 billion over the quarter, which is also in line with expectations.
Trond Westlie
executiveOperating cash flow takes in what our operational earnings contributed, along with work in progress tied to the Offshore construction portfolio and movements in Other working capital. The divestments are mostly adjustments connected to the legacy divestments of our upstream oil and gas business. Gross investment came in at just above DKK 10 billion, which mirrors the ongoing investment into our renewable construction projects. Once the announced divestment of a 55% stake in Greater Changhua 2 project closes, net debt will come down by roughly DKK 25 billion. That transaction should close around year-end, after final commissioning of the Greater Changhua 2b and 4 project. On our key credit metrics, FFO to adjusted net debt was approximately 37% at the close of the third quarter, which sits well in line with our target of more than 30%. The rise comes from higher Funds From Operation over the last 12 months, the proceeds from the rights issue and closing of various farm downs. At quarter-end, our total liquidity reserve stood at more than DKK 105 billion. Our liquidity and debt portfolio are well shielded from interest rate increases, since more than 90% of our outstanding gross debt is fixed rate with an average modified duration of around 5 years.
Trond Westlie
executiveNow let's move to Slide 14 and what we expect for '26. Since operational performance and progress in our construction portfolio came in as expected for the third quarter, we are keeping our full year EBITDA guidance, excluding new partnerships and cancellation fees, at more than DKK 28 billion. Regarding CapEx, gross investments should come to DKK 45 billion to DKK 50 billion, and that's DKK 5 billion below the prior guidance. This reduced expectation stems from a change in the timing of payments on certain offshore wind construction projects. We don't anticipate any change to total project investments. With that said, let's begin the Q&A. Operator, please?
Operator
operator<<operator_script>> Our first question is from Kristian Tornøe at SEB.
Kristian Johansen
analystMy question concerns how much new capacity you can add beyond the construction portfolio you have now, which we talked about before. My contention is that Hornsea 4 is likely among your strongest options. So the U.K. Energy Minister's statement that the government intends to pause before running <<inaudible>> looks like a possible risk for you. Could you explain the situation in more detail and tell us what it would mean for you if they wind up, for instance, pushing <<inaudible>> back by a year?
Rasmus Errboe
executiveThanks, Kristian. Naturally, we've taken note of what the Chancellor said, and afterward what the Energy Minister said in the U.K. To us, nothing meaningful has shifted—neither regarding the general backing in the U.K. for renewables nor specifically concerning the Hornsea 4 plans. Affordability remains the key issue. Value for money remains the key issue, and the recent statements made that plain as well. In our view, bottom fixed offshore wind provides precisely that for the U.K. On Hornsea 4 specifically, we don't interpret those statements as indicating any delay for AR9 in any case. And we're continuing to push Hornsea 4 ahead. As you know, the project is back in development, and it remains a significant asset in our portfolio. It's too early to say when and how we'll bid in.
Operator
operatorOur following question is from Peter Bisztyga with Bank of America.
Peter Bisztyga
analystPeter Bisztyga here, from Bank of America. I just wanted to ask why you aren't feeling more optimistic about your EBITDA outlook for the full year at this point. It seems fairly clear that wind output has come in above expectations. You appear to have gained from power prices that were higher than expected, especially in your Bioenergy business. So I'm wondering, over the roughly 2 months that remain, what do you see that kept you from feeling confident enough to raise your guidance at this stage, please?
Trond Westlie
executiveThanks, Peter. As we've said, our guidance sits above 28, and like you mentioned, we've had solid momentum across the first 9 months, particularly during the third quarter. That said, when we compare what the analysts are forecasting for the full year against the progress we're seeing, we really believe that our outlook of above 28% is the correct one given how we expect the year-end to play out. That being said, there's obviously strong momentum in the market at the moment. So — and we're only guiding on the average wind speed.
Peter Bisztyga
analystFor the rest of the year, I'm assuming average wind speeds — that's for Q3, sorry, for Q4 overall?
Trond Westlie
executiveYou've got that right.
Operator
operatorHarry Wyburd of BNP Paribas has the next question.
Harry Wyburd
analystOkay, forgive me, because this question is somewhat strategic in nature, though it comes up for fairly good reasons given the derisking we are observing in your U.S. portfolio. And my sense is that this will likely cause us to concentrate a bit more on the longer-term growth of the business and on earnings growth, and you may possibly present a CMD or a market update next year. And clearly, you appear to have steered clear of large dividends. It does not seem that you will pursue growth. So here is my question: I believe all of us are essentially pushing toward a figure a couple of billion short of roughly DKK 40 billion by 2028 in EBITDA. If you wished to be a growth company and produce a high single-digit EBITDA CAGR, you would likely need to at least double that EBITDA across the following decade, so you would be seeking to find DKK 40 billion plus. And by very rough calculation, and I know there are many pitfalls involved, you have a lot of subsidies rolling off. And I am not claiming I have this exactly right, but perhaps something near the DKK 10 billion, maybe even DKK 15 billion mark of subsidy roll-off in 2030.
Harry Wyburd
analystSo you'd be aiming at roughly DKK 60 billion in annualized EBITDA that would have to be added during the decade following your arrival at 2028 in order for you to count as a growth company. And that is a very large amount. And if you translate that into a rough EBITDA-to-CapEx ratio, you'd be talking about something like DKK 0.5 trillion of CapEx that would need to be deployed to reach that kind of EBITDA growth. So my question is, how realistic is that? Do you genuinely believe you can get the auction pipeline up and running, operating at something like DKK 50 billion plus per year of CapEx, and thereby deliver a high single-digit EBITDA CAGR? Is that something you'd feel confident guiding to if you had a CMD next year? Or have I gotten anything wrong in those mathematics?
Trond Westlie
executiveThank you, Harry. Your question contains a fair number of underlying assumptions, but let me offer just a few points of perspective from where I sit. To begin with, we are growing quite substantially at present, as everyone can plainly see. Last year our EBITDA came in at roughly DKK 25 billion. For this year, our guidance is above DKK 28 billion. As part of the rights issue, we have guided to more than DKK 32 billion for the following year. So based on those figures, you are looking at year-on-year growth of something like above 10%. That is, needless to say, a very steep rate. And as I mentioned earlier today as well, if you simply compare our earnings for the first 9 months against the first 9 months of last year, EBITDA is up 19% for us. In the stretch that follows, from '28 to 2030, it will decelerate. Growth will ease off compared with what I just described. That much is certain. Growth will still be there during that stretch. We also have our U.S. Onshore business and so forth. And beyond that, naturally, it hinges on how successful we are in the tenders we are currently seeing, which will shape growth in the early 2030s.
Trond Westlie
executiveAs you know, we view ourselves as a growth company, and that's also why we've guided the way we have regarding our expectations for a dividend next year. And everything I've seen over the last 20 months since I took over has only made me more convinced about the prospects for offshore wind in our core markets. More than 15 gigawatts are being tendered out in our core markets over the next 12 months. Most markets have confirmed further rounds after that. So yes, I do see us -- we do see ourselves certainly as a growth company also within the 2030s, and also considering the effect that will come off very likely, but of course, it's far out in time. There is an effect coming obviously from subsidies rolling off. But then you start to make assumptions about power prices in the mid-2030s. Many things can happen in between also in terms of our possibilities for improving the revenue line on our projects. So we see ourselves as a net growth company in the 2030s. And that is as far as I can take it, Harry. And then you are right, we will probably come back and give a bit more feedback to the market during 2027.
Operator
operatorOur next question is from Rob Pulleyn at Morgan Stanley.
Rob Pulleyn
analystLet's move on to the U.S. and the subject of tax credits. This is a bit of a multipart question, if you will, but it's still just one question. First, can you update us on how the marketing of the tax credits is going? Given some of the changes in the U.S., should we feel more optimistic about demand for this? And to be specific, if I remember correctly, there's a 10% tax bonus, or kicker, that required Treasury sign-off when Revolution and Sunrise were commissioned. We've now reached that point with Revolution. Can you tell us whether Treasury has signed off on that final tax credit tranche, or is it still pending?
Trond Westlie
executiveOn the tax credit side, the process for Revolution is moving forward—as we've mentioned, it's a bit better than at the start of the year, though it's largely tracking the same trend we described last quarter. So we're in a solid selling mode, with companies basically signing up, and we believe we're essentially delivering as planned. As for the additional 10% tied to the community component, that requires a sign-off at the project's end, and it has been confirmed. So yes, everything is in order, and as I said, progress is moving ahead. On Revolution, on Sunrise, we're structuring that process as well and pulling together the equity investors for it—not signed yet, but it's progressing as we expected. So overall, good progress, and at present we're still delivering as planned.
Operator
operatorOur following question is from Jenny Ping with Citi.
Jenny Ping
analystI have a couple of questions, if I may. First, regarding how you're using your balance sheet while waiting for some of these projects — sorry, for some of these auctions — to reach a final decision. You've spoken before about opportunities in project-level M&A. I'm not asking whether you'll do anything specific, obviously, but I was wondering if you could offer some commentary on what you're seeing in the market, whether any opportunities exist, and where they'd be geographically. Second, on the onshore business, you mentioned the safe harboring opportunities. If I heard you correctly earlier, Rasmus, you referred to growth from Onshore in roughly the '28 to '30 time frame. So can we rule out a sale of that business now? It's a separate entity, obviously, and you could take that route, but all the signs seem to point to this being a business you'd want to keep, at least for the time being?
Rasmus Errboe
executiveThanks, Jenny. So, two questions, and let's take them one at a time. On project M&A, you're correct that alongside our proprietary pipeline and sensitized tenders, it's one of the three buckets for potential growth on our side. We keep watching whatever comes up. In that respect, nothing has changed. And you're right that speaking about it with more specificity is a bit difficult for me. What I'd say is that, as you know, we only potentially talk about project M&A. And beyond that, I wouldn't place too much emphasis on it relative to the opportunities we see from tenders. In our core markets, we continue to see the framework for centralized tenders improving. We're seeing it now in Germany with CfDs, CfDs in Denmark, CfDs in the Netherlands, CfDs in Belgium. We talked about the U.K. next year. So more than 15 gigawatts over the next 12 months in our core markets. So the best expectation remains that our main bucket for future growth is still that. As for our U.S. Onshore business, Jenny, as you know, I never comment on M&A rumors, and that applies here too.
Rasmus Errboe
executiveWhat I can tell you is that our U.S. Onshore business keeps making us quite happy. As you mentioned too, we've devoted some time to this by now, and we've essentially finished carving it out as its own unit, with a separate U.S. leadership team, processes, and so forth. You also heard it right that in our view we have a highly attractive pipeline, illustrated by over 6 gigawatts of projects, or equipment destined for projects, that is safe harbor for tax equity purposes. And the projects that get brought to <<inaudible>> by our U.S. Onshore business appear quite appealing when you look at them from a value standpoint. So our U.S. Onshore business, and how that business is performing, continues to please us.
Jenny Ping
analystJust to make sure I heard you correctly — earlier, did you mention growth coming from the Onshore business between '28 and '30?
Rasmus Errboe
executiveThat's correct — you did.
Operator
operatorOur following question is from Alberto Gandolfi with Goldman Sachs.
Alberto Gandolfi
analystI'd like to follow up on what Rasmus said earlier regarding turning into a growth company while still keeping a disciplined approach. Could you expand on that and give us more detail about how you're approaching bids for new Offshore projects — specifically in terms of IRR minus WACC and absolute IRR, and whether that's a metric you now consider adopting? Also, what steps have you taken so that the cost overruns and cost control problems from the last growth cycle don't happen again? That's all from me.
Rasmus Errboe
executiveThanks, Alberto. So first off, when it comes to hurdle rates and the spread to WACC and so on, as you're aware, our public guidance is a minimum spread to WACC of 150 basis points to 300 basis points on whatever we propose for investment. And beyond that, we clearly also use internal hurdle rates on un-levered IRR. Naturally, you do that as well in order to hit your ROCE targets and so forth. And those hurdle rates, we'd prefer to hold onto for ourselves. But since day one, when I took over, you've heard me speak about value over volume, and our actions have shown you that we're highly disciplined on value. So it isn't merely words. As for the steps taken within our business model to ward off, you could say, the difficulties of the past — I think the simplest way to see it is to look at how we've performed on the construction side over the last 20 months. Across every one of our projects, we're on time and on budget. We keep devoting a great deal of effort to getting it right, and we keep delivering.
Rasmus Errboe
executiveThat's one way of looking at it — it shows we hold the reins firmly. And from a risk-management standpoint too, in how we frame it — something I've mentioned previously — we'll increasingly go into partnerships before possible upcoming opportunities, largely so we avoid carrying a big farm-down risk, and so we keep the flexibility to farm down only when we judge there's enough value. Logically, that connects to the final piece of why our position now is quite different: our balance sheet is extremely strong compared with earlier times. So there's no situation where we must trade away value to protect the balance sheet, including when we consider farm-downs and how we allocate capital. So I'd say those are a few of the steps we've taken. And clearly, all the effort we're putting into shifting how our organization works also contributes to how competitive the bids are that we submit.
Operator
operatorOlly Jeffrey with Deutsche Bank has the next question.
Olly Jeffery
analystLet me return to offshore wind and the auction rounds that are going to deliver quite a few outcomes next year. What I'd like to know is this: apart from AR9, among those other auction processes, are there any where you believe your odds are especially good? And if there are, what makes you say so? Then, if I can, a second question about the plans being proposed in Germany. As I understand it, the idea is merchant generation <<inaudible>> would shift to a CfD. If that's an accurate reading, do you consider that structure a suitable one?
Rasmus Errboe
executiveI appreciate that, Olly. Olly, I don't want to let you down, but I won't give direct or indirect guidance on which specific tenders we might be leaning toward — in a highly competitive environment for offshore wind in Europe, that wouldn't be a sensible thing to do. What I can do is repeat the opportunity space we have, where everyone, of course, knows we have submitted a bid in Taiwan. And then just look at what is coming. There is a tender coming in the Netherlands now, a couple of gigawatts. There is a tender coming in Belgium, there's a tender coming in Germany. There is a tender coming in the U.K. And then on the other side of that, you will continue to see tenders coming in our core marketing. So we will look and we will be patient, look for value, but I'm not going to indicate which ones we go for and which ones we decide not to go for. In terms of your question on the framework for the upcoming CfD auctions in Germany, you are right that the way it is framed right now is that there is this first stop with <<inaudible>> and then followed by CfDs.
Rasmus Errboe
executiveIn our opinion, that first step isn't necessary. Going directly to CfDs, as we observe happening in essentially every other market apart from Germany, would serve the industry better. After that, if a developer decides moving the project ahead under a PPA works better — should that situation arise — they can opt out later on or at the start of the CfD. So we regard that initial step as an unnecessary one. And we believe what the industry needs in order to bring costs down is consistent, repetitive tendering of offshore wind through CfDs throughout Europe. That provides the predictability required, which in turn pushes costs lower. We have — we don't want empty factories, and we have also seen with Germany's tenders in '22, '23 how that can indeed be the case. But on the whole, we are pleased with the direction of travel in Germany too when it comes to tendering these out with CfDs as well.
Operator
operatorMark Freshney from UBS is up next with a question.
Mark Freshney
analystOn the question of options to repurchase some of the wind farms you've partnered on — obviously we're seeing gun fleet here. Do you plan to exercise that option to buy back the U.K. CfD asset minority stake from Brookfield? My understanding is the option kicks in right at the very end of this year. And is there anything similar you could do across the portfolio? And just to pin you down on something you mentioned earlier — the tax equity on Revolution, where I think DKK 7 billion of cash in is a fairly conservative assumption — how much of that DKK 7 billion have you actually managed to monetize so far?
Trond Westlie
executiveThank you, Mark. Let me address the last question first. I won't say anything about the share of tax equity that has been signed up or how much has been monetized until the tax equity piece is close to finalized. It is well advanced, and investors are signing up. We therefore feel confident that the assumptions in the projects will be delivered. But at this point, I won't go into further detail. Turning to the auctions, we do have a few — the portfolio holds a few options, not many. The <<inaudible>> is, of course, one of the larger ones. As I mentioned, that one is coming up at the end of — or toward — 2030. We also have a few smaller ones from the early stage. We won't comment on those, but I don't think you should expect that this will be all growth going forward.
Operator
operatorMoving on, our following question is from Louis Boujard at ODDO.
Louis Boujard
analystI'll keep this to a single question, but if you could, maybe give us a bit of sensitivity, or some volumes that could eventually line up with the growth you're targeting? You point to 15 gigawatts of European offshore capacity coming up for auction by the end of 2027. In your view, how many projects can you realistically go after while still keeping your FFO net debt at 30%? What do you think the right level would be?
Rasmus Errboe
executiveThanks, Louis. Just to make that clear — the more than 15 megawatts that are reaching our main markets, which means not only Europe but Thailand as well. Then on the other side of what you asked, regarding how much we could actually absorb while still staying above our FFO to net debt of 30%, that's something I'd rather not answer, since that isn't how we approach it. When value exists and the projects exist, we'll find a way. When value isn't there, we won't. So really it comes back to value, not to engineering the balance sheet. Our balance sheet today is very robust, with plenty of flexibility.
Louis Boujard
analystCan I just ask a really quick follow-up on that?
Rasmus Errboe
executiveYes.
Louis Boujard
analystSo does that mean, on the financing side, that you might eventually look at extra financing tools—things like a rights issue or a hybrid—if they're needed, to actually capture more growth potential if the market is ready for a large wind on your side?
Trond Westlie
executiveOkay, Louis — on the funding side and how the project is structured as we move forward, what we're really after is partnerships at an early stage. We're seeking chances for asset-level project financing where that's feasible, alongside teaming up with partners. So we do see how the structure works for aligning within this industry and for taking on larger projects. And also having an <<inaudible>> organization capable of handling a project like that through a somewhat different funding approach — an alignment with partners we've worked with previously. So we're weighing quite a few other things, but when you look at Ørsted's equity portion compared with hybrids or equity in that sense, that isn't an option.
Operator
operatorCasper Blom from Danske Bank has the next question.
Casper Blom
analystI've got a question on Sunrise Wind, if I could. We've seen the U.S. not really issue a decision on the Section 232 tariffs, but instead mention a 180-day pause. So does that mean you can bring in the remaining components for Sunrise under the rules as they stand now, and in that way perhaps sidestep any future risk of higher tariffs, should something like that arise?
Rasmus Errboe
executiveCasper, you're certainly correct that we've taken note of the recent Section 232 proclamation issued by the U.S. So it isn't something that affects Sunrise's construction operations right away. We're — in the — purely because it's an estimate indicating no additional tariffs will apply for up to 180 days. Naturally, if you presume nothing whatsoever will occur over those 180 days, that takes you into May of next year. And at that stage, yes, we will be quite far along with the project. But I won't get too specific about precisely how many blades, towers, and Mercedes we'd still need to import at that stage, though we would be quite far along with the project. We optimized the fabrication and import schedule along with the project itself some time ago. That's something we always do — a standard part of how we operate. It's no different here. And the recent Section 232 statement changes nothing regarding how we build the project.
Operator
operatorLadies and gentlemen, that was the final question. At this point, I'd like to hand the conference back to Rasmus Errboe so he can offer any closing remarks.
Rasmus Errboe
executiveThanks so much, everyone, for being here. We value the engagement and the curiosity. And, as usual, if anything else comes to mind, feel free to reach out. The IR team will be on hand to address every question. Thanks again. Stay safe, and have a wonderful day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Ørsted A/S transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Ørsted A/S earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ørsted A/S or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.