Sarda Energy & Minerals Limited (504614) Earnings Call Transcript & Summary
November 10, 2020
Earnings Call Speaker Segments
Operator
operatorLadies and gentlemen, good day, and welcome to Sarda Energy & Minerals Limited Q2 FY '21 Conference Call. [Operator Instructions] Please note that this conference is being recorded. I now hand the conference over to Mr. Pankaj Sarda, Joint Managing Director. Thank you, and over to you, sir.
Pankaj Sarda
executiveThanks a lot. Good morning, everyone. I extend a very warm welcome to all of you to the Q2 FY '21 earnings conference call of Sarda Energy & Minerals Limited. Our press release and investor presentation containing details of performance has been uploaded. Today's discussion may include some forward-looking statements, which must be considered in conjunction with the risks that industry in general and our business in particular face, and actual results may vary materially. COVID-19 impact, with gradual unlocking economic activities have geared up, but the resurface of coronavirus has also intensified regionally posting administration to impose localized restrictions. Still the economic recovery is faster than expected. And in fact, of COVID-19 is diluted to a great extent. RBI has projected current year GDP to contract by 9.5% with positive growth to be achieved in last quarter of the FY. During the quarter, all our manufacturing facilities operated near-normal capacity. The company has got sufficient liquidity to meet its obligations and to face the challenges evolving from research of COVID. Our external credit rating is reaffirmed by CRISIL at A plus, which reflects that the company is well positioned to face the challenges posed by COVID. Our subsidiary, Chhattisgarh Hydro LLP, which had availed COVID moratorium, has prepaid the moratorium amount in current quarter. Its trading was also upgraded from ICRA BBB to BBB+. I request Sri Manish Sarda to brief about global and domestic scenario of steel and ferro alloys.
Manish Sarda
executiveThank you, Pankaj. Global steel production was marginally up year-on-year. It's 7.8% quarter-on-quarter on base effect. China recorded growth of 10% year-on-year and 4.42% quarter-on-quarter, constituting more than 60% of global steel production. Ex China production saw a de-growth of 10.1% year-on-year and growth of 13.31% quarter-on-quarter. India's domestic crude steel production during quarter to FY '21 was 26 million tonnes against 27.12 million tonnes in quarter FY '20 and 16.29 million metric tonnes in quarter 1 FY '21, registering a degrowth of 3.76% year-on-year and growth of 33.6% quarter-on-quarter. Finish steel consumption fell from 26.22 million metric tonnes to 23.63 million metric tonnes year-on-year. Export of steel during current half year has more than doubled from 5.03 million metric tonnes to 10.98 million metric tonnes, and imports half from [ 5 ] million metric tonnes to 2.11 million metric tonnes over corresponding period of previous year.
Operator
operatorSorry to interrupt. Manish, sir, your audio is not very clear. If you could speak a little louder, please?
Pankaj Sarda
executiveThe government has announced various steps to boost the liquidity demand and credit flow in the economy, which will have a positive impact on demand of steel in the medium term. Sustained export growth will also help improved capacity utilization and stability of prices. Supply constraints of iron ore due to COVID at global level and auction of mines at domestic level have resulted in demand/supply mismatch and kept prices of iron ore and pellet at higher levels. The miners have been increasing iron ore prices regularly since May 2020. During the quarter, production in our plants was near normal. The pellet plant was under scheduled maintenance shutdown for 17 days during the quarter. At Raipur, 1 ferro alloys furnace was under shutdown for refurbishing and operationalized in the last week of September. Another furnace has been shut for refurbishing. As such, effectively, 4 out of 5 furnaces will be available during the current year. Our power unit was also under shutdown for repairing and -- from July 6, 2020, which has been restored on October 22, 2020. The shortfall of power was met by importing power from our subsidiary at Vizag, which has got surplus power capacity. This caused extra transmission costs, but helped in maintaining production levels near normal. Through -- this had some bearing on production of steel. Details of production sales and realization of products have been provided in our press release and presentation shared in public domain. The permission for increase in production capacity of pellet plant from 600,000 tonnes to 800,000 tonnes is expected by January 2021. Ferro alloys, the ferro alloys prices remained stable during the quarter. Ferro alloys exports have been falling -- have seen falling trend in quarter after peaking in June. During the quarter, the country exported 400,000 tonnes of ferro alloys against 364,000 tonnes in June quarter. Prices of manganese ore remained volatile during first half of current year. With the fall of prices in manganese ore, the prices of ferro alloys also have seen softening in recent times. Sarda Metals. Prices of steel products remain elevated on the back of global shortage of iron ore. In India, also production from mines in Orissa were adversely affected due to rainy season and delay in transition of mines to new allottees. Supply is expected to improve from next quarter. Prices of iron ore pellets also remain firm due to export demand and higher price of iron ore. Margin on downstream long products remain stressed due to poor uptake for infrastructure projects. Old mine owners were granted 1 more month up to October for removing the stacks from the mines. They have requested for 1 more extension. SAIL has also auctioned substantial quantity of iron ore finds. This has eased pressure on supply of iron ore. Newly auctioned mines in Orissa have also started production and ramping up their production. Mr. PK Jain will now brief the financial performance and position of the company.
Padam Jain
executiveThanks, Manish. The company has reported consolidated operating income of INR 548 crores during quarter as against INR 347 crores in the previous quarter and INR 550 crores in the corresponding quarter of the previous year. The company has reported EBITDA of INR 154 crores during the quarter against INR 98 crores in quarter 2 of previous year. Profit after tax at consolidated level is to date INR 84 crores, as against INR 68 crores in the corresponding period of the previous year and INR 36 crores in the quarter ended June 2020, resulting into EPS of INR 23.41 per share. Hydropower. Better monsoon helped in achieving better capacity utilization in hydropower generation during the quarter. During the quarter, we generated and sold 65.23 million units against 49.65 million units in quarter 2 of previous year, recording a growth of 31.37 year-on-year. Debt position. At a stand-alone level, the company is net debt-free company. In operating companies, the long-term borrowing is to date approximate INR 60 crores and total borrowing at about INR 760 crores. As on September 30, bank balance and liquid investments is to date to approximate INR 300 crores. Term debt net of cash and current investment is to -- about INR 1,350 crore. Loan repayable within next 1 year is INR 78 crores. The debt equity ratio is well below 1. All obligations have been met on time. Bank interest rates are falling on the back of ample liquidity. Effect of this will be reflected on reset. The company has refinanced 1 of its term loans with saving of more than 2% per annum. Environment is condition for renegotiation of terms or refinancing of the existing loans. Sri Pankaj Sarda will brief about second hydropower project, ongoing coal mine auction and industry outlook.
Pankaj Sarda
executiveSecond hydropower project. As explained in the last con call, the project is in final leg of completion. Heavy rains washed away [ Filicudi Ramco highway ] and also affected work at site of contractor. Heavy landslide has also affected work at site. Although we are putting best efforts to start generation by end of this quarter, this may cause delay 15, 20 days. Coal mine auction. The central government has auctioned 19 coal mines for commercial mining. We also participated in the auction process. We are highest bidder for Shahpur West, underground coal mine in Madhya Pradesh and Gare Palma IV/7 coal mine in Chhattisgarh. Gare Palma IV/7 was previously owned and operated by us prior to cancellation of all mines by the supreme court. The company is entitled to 20% rebate on coal to be consumed in gasification. Both the mines are at a distance of less than 300 kilometers from our manufacturing facility in Raipur. This will provide long-term security and consistent quality of 1 important raw material, coal. So the company had reasonable price and provide hedge against price fluctuation. Outlook. India is expected to record positive GDP growth in Q4 FY '21 with overall contraction of 10% for the whole FY. Increased export demand has balanced demand supply in the steel sector, enabling stable capacity utilization and improved pricing. Good monsoon, better condition in rural and semi-urban India and government stimulus, backed by focus on self reliance and infrastructure creation, should pull the demand further. On global supply concerns, price of iron ore is expected to remain firm. Since the company is sourcing part of its requirement of captive mines, high type of iron ore is positive for the company. Various states governments and central governments are also taking policy initiatives to incentivize fresh capital investment by the industry. Because of low leveraging, the company is well placed to take advantage of emerging opportunities. Commissioning of Sikkim Hydropower Project will further improve the financial performance of the company. We expect credit rating upgrade and further interest rate reductions on completion of the Sikkim Hydropower Project. This is all about the performance and outlook. Now we leave the house open for questions from the participants. Thank you.
Operator
operator[Operator Instructions] The first question is from the line of [ Shubham Agarwal from Equitas ].
Unknown Analyst
analystMy first question is regarding iron ore guidance. So actually, the voice was not very clear when you were updating about iron ore. So I understand that you said that prices will remain firm in the next quarter also. So can you just elaborate on that?
Pankaj Sarda
executiveYes, the prices of iron ore are expect to be firm because so many Orissa mines, which were auctioned, has not yet started. And prior allottees have still 1 more month. They were taking out the mines and materials till October end. So assuming that the new owners will start taking over the mines and will start operations in the mines, there will be a shortage of lumps and fines iron ore in the coming 3 to 4 months, or maybe 6 months.
Manish Sarda
executiveApart from this, the international prices of iron ore is also pretty strong because the demand from China is also very huge.
Unknown Analyst
analystSir, and in the existing iron ore mine. So there are some inventory, which is still pending, which is expected to be off taken. So what is the total amount of inventory? And will this reduce iron ore pricings in India as packaged?
Pankaj Sarda
executiveI'm sorry, can you repeat again?
Unknown Analyst
analystSir, in the existing iron ore, there are few inventories left, which is expected to be off taken. So once this is allowed, do you expect the iron ore price to go down? And what is the total inventory that is lying there in the mine, if you have any idea?
Pankaj Sarda
executiveNo, no. Are you talking about Orissa mine?
Unknown Analyst
analystYes.
Pankaj Sarda
executiveSo in the Orissa mine, I mean, the government is not giving extra permission to the past owners of the mine to take out the material. So they are not allowing it as far as I know about it. And the new owners will come into picture. And [indiscernible] have to buy their heavy machinery equipment, et cetera, and they will be starting their mines very soon. And since the premium quoted is very high, that will not allow the iron ore prices to go down.
Unknown Analyst
analystOkay, okay. Sir, and secondly, my question is regarding Sikkim. So in the presentation, it is mentioned that it is likely to start in December '20, but in the call just now you said that 15, 20 days, it may be delayed further. So can we -- so this can be expected in mid of Q4, am I right?
Pankaj Sarda
executiveNo, no, well before that. Maybe somewhere in January latest. We are trying to complete by December, but then maybe some delay, so I think in January, we should be able to start.
Unknown Analyst
analystOkay, and we...
Pankaj Sarda
executiveWe are trying -- still trying so is to complete by December end, but there may be delay for few days.
Unknown Analyst
analystOkay. And with regards to the refinancing, you said that the interest cost side is lowered by 2%. So what was the total amount on this, which has been lower?
Pankaj Sarda
executiveI think it was somewhere about INR 50 crores, INR 60 crores amount. That is only a small loan amount we have refinanced.
Unknown Analyst
analystOkay. So rest of it will go lower once the Sikkim starts?
Pankaj Sarda
executiveYes, major reductions will come only after commissioning of the Sikkim power projects.
Unknown Analyst
analystOkay. And sir, my question regarding...
Pankaj Sarda
executiveThere are certain reset also due, which will also have bearing on our interest cost.
Unknown Analyst
analystOkay. Got it. And sir, regarding the ferro alloys business. So this quarter, the margin was substantially lower compared to the last quarter. What was the reason you would attribute this to? If I see EBIT margin was 8.6% compared to 18.3% in last quarter.
Pankaj Sarda
executiveYes. The prices of [indiscernible] ferro alloys has gone from in -- when was the inventory low was because of the reduction in the prices that also affected the margins. So to some extent, it was contribution of the inventory loss and to some extent, it was basically fall in the prices.
Unknown Analyst
analystSorry, can you come again?
Pankaj Sarda
executiveThere are 2 contributing factors in ferro alloys EBITDA going down. One is the inventory loss because of the fall in the prices. Inventory loss and another is on account of the falling prices, margins ascend to some extent and as told, 1 of our furnaces is also under shutdown.
Unknown Analyst
analystSo if we're going ahead, what can we expect the margins to be? Because given some of the competitors, their margin was still healthy this quarter also.
Pankaj Sarda
executive[Foreign Language] It also depends how is the cost structure, what is the power cost. There are multiple scenarios which works. As I told, 1 of the reasons has been inventory loss, which may not be there that will definitely improve our ferro performance from here.
Unknown Analyst
analystOkay. Got it. And -- so in the last pellets shutdown was there, and the power plant also was shutdown from October 22, do we expect any more shutdown in the current year? Or all is done except ferro alloy?
Pankaj Sarda
executiveExcept ferro alloys, all is done.
Unknown Analyst
analystOkay. And regarding the Chhattisgarh 25-megawatt hydropower project, for which line has been acquired. So what is the current status of further investment there?
Pankaj Sarda
executiveWe have not yet started work on the project, but I think soon we will start work on that project, maybe within next 6 months work on the project will be started.
Unknown Analyst
analystNext 6 months. And what is the total investment expected?
Pankaj Sarda
executiveTotal investment is about INR 250 crores over a period of 3.5 years.
Operator
operator[Operator Instructions] The next question is from the line of Rahul Jain from Systematix.
Rahul Jain
analystSir, on steel, what are the trends you're seeing on pricing? Because what I see on Q-on-Q prices are not like very robust. I'm just wondering, is that small price increases to come from here?
Manish Sarda
executiveThe overall pricing of steel, I think, will remain more or less stable and firm because we are seeing the reopening also of the economy now in terms of COVID and a lot of government projects, which were stuck because of labor issues and because of COVID will start in a big way. There will be a lot of pent-up demand as well, which has been there. And we have seen imports being very negligible if you look at the previous year and this year the government has imposed a lot of curbs in terms of steel imports and is focusing more on made in India. So effectively, I think the steel prices will be stable and firm for the coming 6 months.
Rahul Jain
analystSo currently, by how much, they would be higher compared to our 2Q average? Are they similar? Or they would be like INR 1,000, INR 2,000 higher?
Manish Sarda
executiveNo, no, they have definitely increased, in some of the products they have increased up to INR 1,700, INR 1,800.
Rahul Jain
analystRight, right. And sir, could you also elaborate on your coal mines, which we are not the highest bidders. So essentially, where do we -- do you intend to use it for merchant sale or for in your steel plant? And how long will it take to get started?
Padam Jain
executiveI mean, regarding the coal mine, that's the best part about it. It's a complete merchant mine. Whenever if we see that the low-grade of material is coming out of the steams, we can sell it locally. Only high grade we could get to our plant. So that's the beauty about it. So regarding the Chhattisgarh coal mine, we intend to start this mine within 1, 1.5 years. All the permissions and clearances because everything is clear, and it was earlier with us, so we have complete idea about it. So we feel that we should be able to start it within 1 year. The Chhattisgarh mine...
Rahul Jain
analystI think it was something about the rated capacity within 1.5 years. Is that right?
Padam Jain
executiveSo 1 year -- within 1 year, we'll be able to start the mine. And within next year, we'll try to reach to the rated capacity.
Rahul Jain
analystAnd so how does...
Manish Sarda
executiveThe best part about this mine is this mine was operated and owned by us only. So we have the bank in place. We have our labor in place. We have -- we know the mines in and out. And apart from that, our whole perspective of this restarting of this mine would be to get the best quality coal to our plants for application of this coal into sponge, pellet, ferro alloys and whatever best we can do in terms of the logistics per GCV basis. We'll be trying to do that because now since it's a commercial mine, we are also allowed to sell the coal at the pit site to other power plants, and there are a number of power plants, which are there near our coal mines. So we can sell that coal easily.
Rahul Jain
analystRight. And how does system work? So you have a revenue share of, say, I think one is INR 2,600 at 36.8. So -- but whatever is the relevant whole India price of that particular grade, you have to share that percentage with the Ministry...
Pankaj Sarda
executiveSo if you see the earlier bidders [ Monet ] had bidded this at INR 2,600 per tonne.
Rahul Jain
analystRight. Over and above the royalty revenue?
Manish Sarda
executiveOver and above the royalty, yes, over and above the royalty. That's how they went up to. Whereas the 66.75% will be much below INR 1,000.
Rahul Jain
analystSo the equivalent grade is about INR 1,000, this is -- which is great? This is the...
Pankaj Sarda
executiveThis is the open cast mining has an overall grade of around G11.
Rahul Jain
analystG11. So particularly around say INR 600 is roughly you will have to share. Is that...
Pankaj Sarda
executiveINR 800 to INR 900.
Manish Sarda
executiveYes.
Rahul Jain
analystINR 800 to INR 900? Right. Even then your -- what is the cost of mining you expect? Around INR 500 or...
Manish Sarda
executiveIt should not go beyond that.
Padam Jain
executiveYes.
Operator
operator[Operator Instructions] The next question is from the line of Abhishek Maheshwari, an individual investor.
Abhishek Maheshwari
analystI have just 2 basic questions. Sir, are we exporting our steel also or on only ferro alloys?
Pankaj Sarda
executiveNo, we are not exporting our steel. We only export our ferro alloys. Steel is sold locally. And domestically, we sell it in India.
Abhishek Maheshwari
analystOkay. And sir, secondly, in like certain places in Maharashta like Mumbai and all, we are seeing realizations crossing 40,000. So in there could also that's the case? Or are we still seeing 35,000 to 37,000 realizations?
Pankaj Sarda
executiveNo, the case in Bombay is totally separate because you have to understand that in Bombay, mostly the steel is sold by the traders. And the traders have their credit margins and all. So there is a long -- because it's mostly for the real estate sector and the infrastructure sector in Bombay, the long products. And there is a big payment delay in terms of 30 days and 60 days, depending upon the customer. So the pricing is more or less 37%, 38%, but they had their own margins for financings. And the storage -- and the warehousing storaging cost is very high in Bombay.
Abhishek Maheshwari
analystOkay, okay. Fair enough. So your realization, sir, somewhere around 38,000 only?
Manish Sarda
executiveOn the product?
Padam Jain
executiveFor HB wire?
Abhishek Maheshwari
analystI mean wire rod and HB wire is somewhere around 35,000 to 38,000.
Manish Sarda
executiveYes, INR 37,000.
Operator
operatorThe next question is from the line of Vikash Singh from PhillipCapital.
Vikash Singh
analystSir, my first question pertains to your Hydropower Project of Sikkim. So any update on the base which could be fixed? Or what kind of utilization of the PLF we can take this plant in 1 year's time?
Pankaj Sarda
executiveNo. What presently is the lean season. So in the rainy season, we get the full -- in the first year itself, we will reach the normal capacity utilization level.
Vikash Singh
analystThat is roughly around...
Pankaj Sarda
executive50% around. In the first year...
Vikash Singh
analystAnnualize basis?
Pankaj Sarda
executiveIn the first year it will -- yes, in the first full year of operation. In the next season, we will register [indiscernible] capacity. But things we will be starting in the main season. Initially, we will be starting only with the 1 unit because presently, power will be on the low flow.
Vikash Singh
analystOkay. And any word on the provisional rates as of now?
Pankaj Sarda
executiveProvisional?
Vikash Singh
analystProvisional rates at which we would be able to say?
Pankaj Sarda
executiveNo. We have not yet got the order, but as I told the provisional -- the rates for smaller hydropower project of 225-megawatt is INR 6 plus. I think we should be getting the same provisional rate. We have not yet got the provisional rate approved.
Vikash Singh
analystUnderstood. Sir, my second question, pertains to dealing that your second hydropower projects starts. But we have a couple of more smaller hydropower projects, one you have mentioned INR 250 crore plus upgradation in the ferro alloys unit as well. So how do you see that the CapEx and the cash flows in next couple of years and overall the debt correction because of that?
Manish Sarda
executiveNo. As far as the Sikkim Hydropower Project, there capital outflow will slow. So far as this Chhattisgarh Hydropower Project water expansion we are going with water internal -- promoter contribution is required that project -- existing project will support that. Now from the Chhattisgarh Hydro existing project is generating sufficient surplus as to after mitigate that obligation. So that will be financed independently. That won't require any equity contribution or support from the promoter company.
Vikash Singh
analystNo, sir let me rephrase it in a different manner. So what I wanted to understand that we have almost INR 250 crore in Chhattisgarh. If I get it correctly then around INR 100 crore in this annualized kind of the CapEx, and we have the normal maintenance CapEx also going on for the next 2 or 3 years. So just wanted to understand that the total CapEx, which we are going to put in versus the cash inflows, which we could foretold beforehand from the Sikkim Power Project. So how the overall debt position would be, as per your calculation, would be there in, let's say, next couple of years down the line?
Pankaj Sarda
executiveNo. The debt position should remain more or less at the existing level. There may be some plus or there may be some minus, but they won't be material. In fact, because there will be some additional CapEx, and there will be some repayments. So it should remain within difference based on the existing plant CapEx.
Vikash Singh
analystOkay. So it's fair to assume that whatever the incremental cash flows are coming, or we are putting against the further growth project? So that should remain more or less a patent for, say, for next couple of years. Is that right assumption?
Pankaj Sarda
executiveYes. Existing gross -- our existing growth loan is about INR 1,650 crores, maybe INR 1,600 crores, gross loan. All the INR 300 crores we are holding on the cash. So if we are going with the coal mines. Also, we are going all those things so maybe in the range of INR 1,500, INR 1,600 crores, loans will remain. There won't be material addition. There won't be material reduction.
Vikash Singh
analystUnderstood. Sir, my second question pertains to our coal mines. So this 1.8 million tonne of total annualized production, which we have won in both the mines combine. So would that be able to supply the entire coal requirement? Or what portion would be available for us to sell in the merchant market?
Manish Sarda
executiveIt will depend upon the pricing. It will depend upon the pricing what we get in the merchant markets. But our whole efforts will be to first see and effectively choose our own coal and cut down on our imports in a big way so that we are self-sufficient, and we are away from fluctuations of the international market and the dollar movements.
Pankaj Sarda
executiveApart from this, we have a requirement of almost 1 million tonne in our Siltara plant, Raipur. So over and above, we can always sell merchantly outside to the third party. And over and above, the annual year gives us a clearance of increase our capacity by more than 50 -- by around 50%. So 1.8 million tonne, we can achieve -- if we want to increase our capacities without any annual year clearance, we can go above 1.8 million to 0.9 million tonne more.
Vikash Singh
analystUnderstood. Sir, the -- if I get it correctly that there is some 65% kind of the production performance guarantees with most of these coal mines which are getting auctioned but -- within 1 year. But you're saying that the next 1.5 years only, you would be able to start. So if you could just elaborate that what happens to that performance guarantee part of it?
Pankaj Sarda
executiveNo, no, no. It's basically this, that once the government gives you all the clearances in place within the specificated period of time, you have to start your production and have to achieve 65% of your production, it's not within the 1 year from the date of allocation.
Padam Jain
executiveOnce the government gives us the vesting order, we have 51 months to start the mine.
Vikash Singh
analystUnderstood. Understood, sir. And just 1 last question, if I may squeeze in. What is the current rate of the same grade of coal, which you are getting at your plant? Or what is the blended cost currently?
Manish Sarda
executiveThere are multiple grids. We are using different grids for power, different -- there are multiple grids. It's not a...
Vikash Singh
analystFor power grid, you can say -- for power grid, you can say whatever we are using for our power plants or what is the rate at which we are getting at the plant side?
Padam Jain
executiveWe are getting around INR 1.15 per GPP, around.
Operator
operatorThe next question is from the line of [ Atif Shah], an individual investors.
Unknown Attendee
attendeeCongratulations for very decent set of numbers. Sir, my first question is regarding your interest costs. So probably, I'm assuming that you would be capitalizing a lot of your interest cost at this juncture. That is why your interest cost comes to at around 5%, 5.2%. I just want to understand, once we are servicing the normalized rate of interest on our loans, which you just discussed about INR 1,500 crore to INR 1,600 crore. And after the interest reduction exiting, what sort of annualized interest costs are we looking at at this company on a consolidated level?
Padam Jain
executiveIf you consider that way, on average, even if you consider 10% on average then effectively at INR 150 crores is the total interest component. And definitely, there are interest incomes also because as I told, we are holding INR 300 crores of the cash and bank balances. In addition to that, we have certain loans, et cetera. So ultimately, my effective borrowing cost will be somewhere about maybe INR 1,100 crores or INR 1,200 crores, whatever we are incurring even after commissioning of the Sikkim Hydropower Project. My -- in net cost, if you consider, it will not exceed maybe INR 110 crores, INR 120 crores. Even after...
Unknown Attendee
attendeeWhich is against INR 82 crores, which we are having right now, right?
Pankaj Sarda
executiveYes, yes, yes.
Unknown Attendee
attendeeFair enough. Sir, I just want to understand, somehow there seems to be some sort of delay in the additional capacity commissioning of our pellet plant? What is the reason for such a long delay because I think this plan to add 2 lakh tonnes or since long. But we are not being able to take advantage of the current pallet price value?
Pankaj Sarda
executiveYes. There have been changes in the government policies in between NGT had come out with a different guidelines. So there are multiple changes in the government, changes in the government policy then and the -- because the Raipur area are aware of the increase in the basically critically polluted cities. So there are multiple agencies which are involved and that time to time, there have been changes in the policy, which has affected this.
Manish Sarda
executive[indiscernible] that this is is also because of the COVID pandemic, which has been ongoing for the last 7, 8 months. And the offices -- government offices have also not been working in that way, which is the normal way of working. And NGT also came into play. So all of this has added to that delay. From our side, there is no delay, it's basically the government policies that have to be cleared up with respect to Chhattisgarh and Raipur specifically as a zone.
Unknown Attendee
attendeeFair enough, sir. And sir, I also see that this quarter, our pellet realization was somewhere around 6,110. So I mean, is it less as compared to some of the peers? Or how it has panned out? And also I'd like to know, now that our plant operation maintenance is over, now we'll be running at full rated capacity. So in this quarter, at what rates are we booking the pellets at? So I'm assuming that will be a huge turnaround from this quarter, right?
Pankaj Sarda
executiveYes. Last quarter, because of shutdown during the price increase, we could not take advantage of debt increase because prices had moved from INR 5,800 to INR 8,000. So there were pipeline orders also and then a shutdown. That definitely affected our average realization of the pellet plant, which is less than market every realization because of the shutdown and pipeline orders. And this quarter, definitely, it will be plus INR 8,000, it should be.
Unknown Attendee
attendeeSo what volume we are targeting in quarter 3? And INR 8,000 you're expecting the ballpark number, right?
Pankaj Sarda
executiveYes, ballpark number is this -- I think on average, what we are selling is more than a -- let down of the pellet we sale in the market every quarter. Sometimes in some quarters, it may be less some quarter, it may be more. On average, work for net of resale of [indiscernible] year?
Unknown Attendee
attendeeOkay. And sir, last question regarding the iron ore scenario and also for our company, where the -- we have our own mine, but we are also buying from the market. So what is the percentage of our source that we are buying from the market? And what is the current blended cost of that? So I just want to understand 2 things. One is the blended cost of our ore fines for the pellet plant? And also at what rate is the current blended cost? And also talking about the annual scenario, Mr. Sarda very nicely explained that it could be a phenomena of a huge supply shortage for the next 3 to 6 months, what is the possibility that it can last for 6 months? Because if it lasts for 6 months and also year in commentary from very big steel manufacturer like JSW, the scenario looks very bad in terms of the supply. So this will really hurt production going ahead, what is your sense overall commentary on this?
Manish Sarda
executiveSo as far as shortage is concerned, I would say that we also expect that the shortage will be there for the coming 4 months or maybe it will extend to 6 months or 7 months. But at the end of the day, there will be some kind of solace in terms of imports because if the shortage goes on for a very long period of time, we will see a robust pricing of iron ore. Even the pricing may go up, and that will make it viable for imports, at least for the coastal based plants. The plants, which are based on the cost line, they will be able to import iron ore. And I think [indiscernible] because I guess all the guys who have invested in these mines would be also wanting to restart and wanting to consume the iron ore. Nobody is interested, no company would be interested to import iron ore in the country.
Unknown Attendee
attendeeRight. And sir, for us, the blended cost of fine for our pellet manufacturing, and what percentage are we using? And what is the blended cost?
Padam Jain
executiveWe are using around 50% to 60%. We are blending and our captive iron ore, we are using around 40% to 45%. Blended cost of -- there are various grades of iron ore fines that is available. So around 62.5 plus grade material from Orissa. It's coming around INR 5,500 to INR 5,800 in at the moment.
Unknown Attendee
attendeeOkay. But you're getting the supply for manufacturing use in your pellet?
Padam Jain
executiveWe are getting the supply, but the -- but availability is going down and down in coming months. The prices are going high. You have seen that NMDC also increased their prices by almost INR 150 to INR 200 a couple of days back. So the rates are going up.
Pankaj Sarda
executiveBut we have sufficient backup, so as to maintain the pace of our production. It won't have -- we have sufficient till end of the production.
Operator
operator[Operator Instructions] The next question is from the line of [ Amit Jain ], an individual investor.
Unknown Attendee
attendeeCongratulations for navigating this tough environment and coming off with good set of operational performance. My question is in [indiscernible] the last question, which is about the pellet prices. If I hear it rightly, so the price realization for the last quarter was approximately INR 6,100 per metric tonne. And though ongoing prices, I understand is more than INR 9,000 per metric ton, but I understand considering the various constraints, the realization, expected realization for the ongoing quarter can be, of course, of INR 8,000 per metric tonne, which is approximately 33% increase. Is that right direction?
Pankaj Sarda
executiveYes, yes. You are correctly understood. It would be INR 8,000 plus, what we have said. Because there are pipeline order, all those things, so we have to take average, and how the prices -- how long this price continues INR 9,000 plus all depends. So considering this, it will be more than that only. To our expectation, it goes up, it's very difficult to predict currently.
Unknown Attendee
attendeeYes. And as well as the iron ore prices, when I suddenly check on the China's Stock Exchange, Italian Stock Exchange, that is also, I think, multiyear high. So with greater probability and more certainty, you can probably -- your commentary is based on that we'll be able to definitely realize more than INR 8,000 per tonne?
Pankaj Sarda
executiveYes, definitely. Definitely, we'll realize more than that.
Operator
operator[Operator Instructions] The next question is from the line of [ Shubham Agarwal from Equitas ].
Unknown Analyst
analystSir, my last question is regarding the coal mine again. So what is the total upfront payment required for both this coal mine?
Pankaj Sarda
executiveFor this is coal mine of Madhya Pradesh, it is somewhere about INR 34 crores. And for this Chhattisgarh coal mine, it is INR 86 crores. But it is payable in 4 installments, depending upon the progress. For this Madhya Pradesh, we'll get almost from today, you can consider 4.5 years in the installments. And for [indiscernible] also it will depend. It is payable in 4 installments, 1 on the agreement, another on the mining lease, then mine opening and then after production. And that is also immediately refundable against the revenue share. 50% of the revenue share will be adjusted against the upfront payment. So as the mine staff immediately will start to get back the amount.
Unknown Attendee
attendeeOkay. Got it. And sir, regarding this MP coal mine, what would be the total investment required over this next 4 years to get the mine started?
Pankaj Sarda
executiveI think in the initial 2 years, there will be hardly negligible amount. It won't be materially -- major CapEx will be only in the last 2 years, 2.5 to 3 years, whatever it takes. So initial 2 years, there will be very low, but total investment will be INR 200 crores, plus/minus.
Unknown Attendee
attendeeINR 200 crores? Okay. And any investment for Gare Palma coal mine over the next 1 year?
Pankaj Sarda
executiveThere won't be material, except this upfront payment will also go in the installments, and there will be some on the mining lease execution, et cetera, because [indiscernible] is already in possession. It was operating mine. So maybe about, I think, we have to give maybe INR 25 crores, INR 30 crores to the existing prior allottee, and there will be some restarting CapEx.
Unknown Attendee
attendeeOkay. And lastly, regarding the ferro alloy expansion. So when do we think we'll start working on this INR 125 crore expansion?
Pankaj Sarda
executiveYes. I think next financial year we'll start work on this.
Operator
operator[Operator Instructions] The next question is from the line of Sachit Khera from Smart Equity.
Sachit Khera
analystAm I audible?
Pankaj Sarda
executiveYes, you are audible.
Sachit Khera
analystSir, I'm new to your company, so pardon me if the questions are a bit naive. In -- regarding the Sikkim Hydro Project, you mentioned that the first unit would get commissioned by January latest, right?
Pankaj Sarda
executiveYes, yes.
Sachit Khera
analystOkay. And what about the remaining unit, sir?
Pankaj Sarda
executiveIt also -- it will depend on availability of water. The plant can run only at full load only during rainy season. It does not run throughout they year.
Sachit Khera
analystMake sense.
Pankaj Sarda
executiveThis is run of the river project. So the full capacity of both the units will be running only during the rainy season, not throughout the year.
Sachit Khera
analystMakes sense. And you don't envisage any problems in being able to sell as much as you produce, correct?
Pankaj Sarda
executiveNo, we have already entered into PPA with the distribution utility. So there is no problem of sale. There is no problem of sale.
Sachit Khera
analystYes. It's just that the rate would be finalized between...
Pankaj Sarda
executiveYes, rate would be finalized.
Sachit Khera
analystOkay. Makes sense. The second question is regarding the mines. When you bid for the mine, sir, this is again, a broader question. How do you sort of calculate the kind of payback or IRRs while bidding for the mines?
Pankaj Sarda
executiveBid for actually directly linked with our blended cost and basically production core. What is my blended cost and what is my production cost, depending on that, we arrive at the formula definitely 1 is remittence security and other is training and based on the investment interest checkup.
Sachit Khera
analystOkay. So for example, Gare Palma, the agreement to part for, let's say, 66% is based on the decision that the upfront payment is less, and that it's had an in line, for example?
Pankaj Sarda
executiveUpfront amount will be recovered within a year or 2. Upfront is only a temporary advance or deposit, you can say, that is not a basically cost. But I'm because paying upfront, that will I get back refund maybe in a year or 2 at the basis.
Sachit Khera
analystMakes sense. And the 66% is on a base of 2,600 you mentioned?
Pankaj Sarda
executiveOh, no, no. It will be basically a [indiscernible] of the value average posted National Coal Index is declared for every grade by the government. Depending upon the -- they raise a basket of the import auction linkage. So they will arrive at pricing for every grade of the coal based on the exact outflow of the coal. From the mine, we have to pay on price of that grid.
Sachit Khera
analystAnd this varies every month? Or how does...
Pankaj Sarda
executiveYes, it will vary depending upon the quality of output from the mine. And the index also varies every month.
Sachit Khera
analystOkay, makes sense. And this is on the gross value, right? There's no floor plus concept. It's on whatever the index value is declared, flat, 66% will be shared with the government?
Pankaj Sarda
executiveYes, yes.
Sachit Khera
analystOkay. And will the mining cost be deducted? Or that could be coming out of your 33% share, 34% share?
Pankaj Sarda
executiveYes. It will be coming out of our 33% share.
Sachit Khera
analystOkay. And including the freight and the transportation cost, everything is yours?
Pankaj Sarda
executiveYes, yes. Everything is ours.
Operator
operator[Operator Instructions] The next question is from the line of [ Amit Jain ], an individual investor.
Unknown Attendee
attendeeSo this is in conclusion to my previous question. I -- as you -- it will be better if I get some clarification here. According to the press release, last Q1 FY '21, the company produced approximately 144 metric tonne of the pellets. And the sales were approximately 77 metric tonne of the pellets. So does it mean that we -- there is an inventory of approximately 70 metric tonne available with the company because the production in Q2 and the same number is approximately the same, which is approximately 140-plus metric tonne?
Pankaj Sarda
executiveNo, no, no. It is not like that. Basically, rest of the stock is consumed tactically for production of sponge iron.
Unknown Attendee
attendeeOh, okay.
Pankaj Sarda
executiveThat is also mentioned in the notes -- in the press release, if you see part of the production is tactically consumed at every stage. Part of the sponge iron also consumed in the production of billet, part of the billet is consumed in the wire rod then like that. So it is not the inventory buildup. It is only -- there is no inventory buildup. Our inventories are at low levels.
Unknown Attendee
attendeeOkay. And second question is that the 33% increased realization that we are expecting for this quarter in the pellets, I think that will directly add to the bottom line because most of the consumption of the raw material for the pellet production is our captive, correct?
Pankaj Sarda
executiveNo. As we told around 40% to 50% is our capital, remaining is market purchases.
Operator
operator[Operator Instructions] As there are no further questions, I would now like to hand the conference over to Mr. Pankaj Sarda for closing comments.
Pankaj Sarda
executiveThanks to all the participants for joining this conference call. We hope we have clarified the systems to the satisfaction of the concern investors. If anyone has any doubt, they can always approach to our investor relations team, which is also provided in our invitation as well as presentation. Thanks to all.
Operator
operatorOn behalf of Sarda Energy & Minerals Limited, that concludes this conference. Thank you for joining us, and you may now disconnect your lines.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Sarda Energy & Minerals Limited transcript — plus 251,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Sarda Energy & Minerals Limited earnings transcripts and 251,000+ others is available through the
EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.