Terje Pilskog
executiveGood morning, everyone, and welcome to our Q3 presentation. Q3 has been quite an eventful quarter, with activity levels very high right across the Scatec Group. Underlying performance has been strong, particularly in the D&C segment. We've kept making headway on our strategic priorities and on our growth targets as well. The case for renewables keeps getting stronger. Renewables are growing ever more competitive. As I've said on many occasions, not just as an intermittent energy source, but also when it comes to delivering baseload or dispatchable energy. We're also seeing energy security climb higher and higher on the agenda. Broadly speaking, these developments are opening up more and more opportunities for Scatec. That said, the quarter has also brought us a challenging backdrop in terms of macroeconomic developments, the geopolitical situation, and some regulatory changes as well. I'll return with more detailed comments on the revised EBITDA outlook for the power production segment, obviously particularly regarding the Philippines. During the quarter, we've also taken impairments. This concerns Ukraine and Pakistan. Ukraine, obviously, continues to be impacted by the war, and because of increased disruptions in the energy sector, we've taken significant impairments in Ukraine.
Terje Pilskog
executiveTo wrap up today, following Hans Jakob’s review of the financials, I’ll also give you an update on strategy and our targets looking out to 2030. Our ambition here is to double the self-funded growth space we have within that time frame. Let me begin by walking through a few of the quarter’s highlights. As I mentioned, we keep making solid headway on the growth agenda. On the key figures: proportionate revenues reached 2.3 billion, EBITDA was 1.2 billion, and cash flow to equity came to 385 million. That represents a 35% increase versus the same quarter a year earlier once you adjust for the roughly 250 million in refinancing gains we booked in the Philippines. Among other notable items, construction has begun on Shadwan as well as phase one of DANDARA in the Philippines. Shadwan is a 900-megawatt wind project — the biggest wind project in Africa — and once fully operational it will generate about 4 terawatt-hours. We intend to bring it online in stages across the first half of 2028, and we’re delivering this project at record speed. Then there’s DANDARA, which is Egypt’s first corporate PPA.
Terje Pilskog
executiveEarlier this week, we signed loan agreements with EIB, EBRD, and AfDB as well. We also signed agreements involving NBE — the National Bank of Egypt, a commercial bank — to step in and acquire a 20% equity stake in the project. During the quarter as well, we signed an equity platform agreement with EBRD, and EBRD is taking 40% of that platform and has committed $221 million to it. Obviously, this lets us lower the capital required for pursuing the portfolio we hold in Egypt. Related to this, EBRD will enter Obelisk through the platform, and our equity stake in Obelisk is being cut to 24%. We have also secured an equity bridge loan amounting to $150 million. That relates to enabling equity last in our product portfolio in Egypt. Lastly, we have issued a new bond of 1.5 billion as well, at a credit margin of 250 basis points. These are very attractive terms, and we will use this to refinance more of our expensive debt — or we have already done so — and this will contribute to 50 million in reduced interest costs annually. As I mentioned, finally, we have also recognized an impairment loss of roughly 1.1 billion in the quarter.
Terje Pilskog
executiveAs I mentioned, this relates mainly to Ukraine, though there's also some in Pakistan. Hans Jakob will return with further details on that. On the power production side, during the quarter we generated roughly 1.5 terawatt-hours, which represents a 22% rise compared with the same quarter a year ago. A substantial share of that comes from new projects. Over 400 gigawatt-hours is being delivered by new projects, and that spans South Africa, Tunisia, Botswana, Egypt, and Brazil. What this demonstrates is that a meaningful portion of the growth we've been pursuing is now actually entering operation. We're also seeing lower generation in the Philippines. That stems from reduced water availability, and I'll return to it shortly. Generation in Ukraine was lower as well, clearly because of the war. On revenues, we lifted segment revenues to 1.3 billion, up 10% versus the same quarter last year. There, new projects are contributing around 140 million, and we also have a modest increase in the Philippines, whereas Ukraine was a negative contributor. To sum up, on the power production front, we're now beginning to see substantial contributions from the new projects that are entering operation.
Terje Pilskog
executiveOkay, moving on to the Philippines now. For the third quarter, that was a solid one. As we entered the quarter, there were a few worries regarding water levels, which were rather low at the start of July. Over the course of the quarter, those water levels rose. By the time we exited the quarter, they stood above normal. Water levels were at healthy levels. During the quarter, production was lower, at 218 gigawatt-hours, yet prices were elevated across every segment in that period. Looking at this slide, you'll notice as well that ancillary services pricing jumped during the quarter, and that was pushed by higher prices in the reserves market. Our earlier guidance for Q4 likewise presumed these price levels would persist. On revenues, they reached 411 million, with robust levels across all the segments. As the chart also shows, there has been a shift of revenues toward the ancillary services segment away from pure energy sales. EBITDA was 367 million. That's roughly 10% higher than the same quarter a year ago and matches the outlook we had provided for the quarter.
Terje Pilskog
executiveTo sum up, we keep creating value in the Philippines by leveraging our flexible asset base and our capacity to fine-tune the commercial approach across the various segments we observe. Now let me also cover the reserves market in the Philippines, since that was a key item in our revised full-year outlook. Trading in that reserves market was halted on October 14, and the reason was extremely high prices in the Visayas and Mindanao region. Prices were elevated in the Luzon region too, where our operations are located, yet they were not as extreme as those in the other two regions. The regulator has since asked for the ancillary services market to be redesigned within six months. We anticipate it will be operating again once that six-month period ends. Relative to our Q4 outlook, the estimated impact on us comes to roughly 80 million, as SNAP had likewise assumed continued high prices during the fourth quarter. Then, a few brief words on how the reserves market came about. It was set up in January 2024, nearly three years ago. Right after it launched, prices were extraordinarily high, and it got suspended following only a little over one month of operation, in March 2024.
Terje Pilskog
executiveAfter that, the regulator wanted an audit conducted on how prices are set within the market. That audit took place. It came back clean. New price limits, or ceilings, were introduced into the structure. Following that, the reserves market was relaunched once more in September 2024. From September 2024 onward, it has run without major disruptions, with price levels in line with expectations. Of course, in Q3 we have now observed price levels reaching peaks. Naturally, we along with the industry are not standing idle. We are pursuing measures aimed at offsetting the present situation. The industry has promptly put forward measures on how to handle the current situation and the elevated prices. On the industry side, we have also asked for the reserves market to be reinstated right away, since suspending that market also shifts costs onto other producers in the market who are not being compensated for them. When it comes to our JV, SNAP, we are likewise working on compensating measures. We aim to move delivery of replacement and contracted ancillary services to our BESS units, which frees up capacity at the hydro plants so they can sell more energy into the spot market. We also provide bilateral ancillary services contracts to the market operator, and beyond that, we do intraday trading with our BESS in the energy market.
Terje Pilskog
executiveEvery one of those represents a compensating measure, though clearly the true fix here is getting the reserves market back up and running as quickly as we can. To sum up, demand for ancillary services in the market remains strong, and that demand is only going to grow as the share of renewables in the power segment and on the grid keeps rising. We anticipate the reserves market will be reinstated within the timeline that has been announced, and we anticipate normalized prices once the market is back. Prices of the kind we have historically seen — the change we consider most likely is that additional price caps get introduced, but in all likelihood they will not affect the average prices we have typically observed. It's also worth remembering that the marginal capacity in the Philippines ancillary services market costs significantly more than our batteries and our hydro power plants do. From a longer-term standpoint, we expect this to have limited economic impact. Moving on to construction and the D&C segment, where activity levels are at record highs: we have revenues of 948 million, gross margin of 26%, and an EBITDA of 168 million. That is partly tied to the COD of Obelisk, where we have since been able to release more contingency now that this project is finalized.
Terje Pilskog
executiveOn the activity side, roughly 1.4 gigawatts of solar is under construction, along with 1 gigawatt of wind, and nearly 700 megawatt-hours of battery storage is being built now that Shadwan and phase one of DANDARA have entered construction. Our remaining contract value stands at approximately 10.5 billion, compared with 3.0 billion in the prior quarter — an increase of almost three times. And one last item: COD for the Mogobe BESS project in South Africa has slipped to next year because of delays in Eskom's interconnection works. I'll now pass things to Hans Jakob, who will walk us through the financials.
Hans Jakob
executiveThanks, Terje, and thanks for being here today. I'll take you through the group's financials and how each operating segment performed. I'll also go over the guidance and the improvements we've made to our capital structure. Turning to the quarter at the group level, we kept delivering EBITDA growth, driven by new assets in operation and strong execution in D&C. Consolidated revenues came in at 1.7 billion, versus 1.1 billion in the same quarter a year ago. We delivered an EBITDA of 1.1 billion, up from 70 785 million last year, and that increase comes from a combination of new assets in operation and 220 million of construction revenues from Takadu? in South Africa. On a proportionate basis, revenues were 2.3 billion, compared with 3 billion last year. That reduction comes from D&C, since the same quarter last year had very high construction activity on Obelisk in Egypt. Power production revenues rose by approximately 10%. Proportionate EBITDA was 1.2 billion, up 14% from last year, driven by assets in operation and a closeout effect on Obelisk in D&C. Now let me take you through the segments. Our power production segment delivered revenues of 1.3 billion, 10% up year on year.
Hans Jakob
executiveEBITDA came in at 1.1 billion, compared with 955 million before, and the increase was driven by new projects that are now in operation. Across the past 12 months, we generated 3 4.3 billion in revenues and 3.4 billion in EBITDA. The decline versus last year is largely explained by asset sale gains, which added 1.2 billion to EBITDA during the prior 12-month period, primarily from divestments in Uganda and Vietnam. Those underlying figures also take in EBITDA contribution from the divested assets. As additional new projects reach COD, we anticipate that the underlying contribution from operational assets will keep growing. Now let's turn to D&C. In the development and construction segment, revenues reached 948 million, versus 1.8 billion year on year, driven by construction activity on Obelisk, which was at its peak last year. EBITDA was 168 million, up from 135 million last year. That reflects closeout effects of 140 million on Obelisk, reflecting timely and cost-efficient execution of the project. If you exclude those effects, the underlying gross margin was 11%, in line with our guidance of 10% to 12%. Across the past 12 months, D&C revenues were 5.1 billion, up 14% from last year, and EBITDA almost tripled to 753 million, driven by strong execution and disciplined cost control, which has resulted in contingency releases of 340 million so far this year on Obelisk.
Hans Jakob
executiveLooking forward, we anticipate a pickup in activity as construction accelerates on Shadwan and DANDARA in Egypt. With the remaining contract value of — and I have to say this is impressive — 10.5 billion currently under construction, we enjoy solid visibility on D&C revenues as we move ahead. Let me begin by walking through the changes we have made to our impairment assessments. In the quarter, we recorded an impairment of 1.15 billion on a consolidated basis and 1.066 billion on a proportionate basis tied to Ukraine and Pakistan. In Ukraine, the war tragically continues, and our thoughts are with the Ukrainian people, who are doing a courageous job amid a devastating situation. Russia has stepped up attacks on critical energy infrastructure, and restoration of the plant that was hit in '25 is being pushed back. The drawn-out war is further weighing on the country risk premium and on the outlook for longer-term power prices. Those developments produced impairment losses of 1 billion on a consolidated basis and 952 million on a proportionate basis during the quarter. That is on top of the 816 million impairment loss booked in 2022, when the war began. In Pakistan, the updated assessment was set off by a rise in the discount rate, mirroring a higher country risk premium and higher long-term USD interest rates, together with greater uncertainty about the timing and amount of future cash flows.
Hans Jakob
executiveSo because of that, we booked an impairment loss of 150 million on a consolidated basis and 114 million on a proportionate basis in the quarter tied to these assets. Our free cash position finished the quarter at 1.2 billion, down from 1.6 billion in the second quarter. From operations, we got 147 million in distributions from power plants, and we produced 137 million in EBITDA from D&C and corporate. Working capital moved negatively by 746 million, mostly because of Obelisk reaching COD. After the quarter closed, we began construction on Shadwan and DANDARA, which will have a positive effect on working capital. We put close to 700 million into growth projects, and we paid 147 million of interest. Net charges in corporate financing came to 854 million, largely reflecting the drawdown of the RCF to cover short-term working capital fluctuations. Counting the 1.5 billion in undrawn RCF, total available equity liquidity stood at 2.7 billion. And 3.9 billion once you include the additional RCF capacity that is now available — and thanks also for the banks' support in making these arrangements. Corporate gross interest-bearing debt rose from 6.4 billion to 7.1 billion as a result of the RCF 700 drawdown.
Hans Jakob
executiveWe expect that to be paid back during the first half of '27. When it comes to long-term corporate debt, there's no change, since we've used the money raised from the new bond to pay off existing corporate debt. Our strategy regarding corporate debt remains the same. Our aim is to bring corporate debt down. At the project level, gross debt held steady at 19.5 billion, while debt for projects in operation rose to 14.2 billion, and debt for projects under construction dropped to 2.2 billion, largely because Obelisk Phase 2 shifted from construction into operation, and cash held in SPV remained stable at 3 billion. Now, turning to the outlook. As we announced on October 21st, we've lowered our full-year EBITDA guidance for power production to 3.3 to 3.6 billion, which is 300 million below the prior midpoint. The bridge on the right illustrates what's driving the full-year power production EBITDA guidance, with operational effects making up 214 million. The Philippines was cut by 80 million, reflecting the suspension of the reserves market. Pakistan, 40 million, tied to delays in the true-up tariff, which we had previously expected to be settled in the fourth quarter of this year. South Africa, 40 million, mostly linked to delayed connection work on the Mogobe asset by Eskom, the state-owned utility.
Hans Jakob
executiveRegarding Ukraine, 30 million, since repairs to the damaged power plant have been pushed back. On FX, a negative 86 million. Although a number of these delays and updates are in fact delays, we keep working on compensating measures for the impact of reserve market revenues, as Terje has explained. Full-year power production is now expected at 4,950 to 5,150 gigawatt-hours, which is 150 gigawatt-hours below the earlier estimate, driven by third quarter performance, delays in Ukraine, and another minor adjustments to the portfolio. For the fourth quarter, production is expected to be 1,300 to 1,400 gigawatt-hours, and EBITDA in the Philippines of 2 to 300 million. In D&C, the remaining contract value is, as I said, 10.5 billion, and we still expect a gross margin of 10% to 12% on average across the portfolio for project under construction. For corporate, we expect a full-year EBITDA of -110 to -120 million. That is an improvement of 15 million from our previous guidance. Then it's time for the strategy update, Terje, please come back on stage.
Terje Pilskog
executiveThank you, Hans Jakob. Regarding strategy, we laid out a clear plan 2 years ago: invest in profitable growth, recycle capital by way of divestments, and lower debt at the corporate level as well. On all 3, we've made good progress. That has placed us in a strong position — an even stronger one. Our near-term growth portfolio stands at a record high, our cost of borrowing has fallen considerably, and our integrated business model keeps generating value through the entire project lifecycle. Today we'll present the next phase of our strategy, in which we aim to double our equity investments, targeting 8 billion Norwegian kroner in equity investments toward 2030, while we keep cutting debt and more than double cash flow to equity over that period. This will be a fully self-funded plan, just as we've done previously, with no new equity requirement and also the possibility of available liquidity toward the end of the period. Let me walk you through it now. On the industry side, the competitive position of renewables, as I mentioned, keeps getting stronger. Costs are declining, and in the markets where we operate, renewables is the most competitive source of new power generation.
Terje Pilskog
executiveThe reason for this is clearly that module prices have fallen 60% in the past three to four years, while battery systems are down nearly 80% over those same three, four years. On top of that, renewables deliver energy security, predictability, and independence — something that matters enormously in a lot of the markets where we operate. It's the generation source that can be deployed fastest and most flexibly. For Scatec, that opens up new applications we can target, gives us a stronger value proposition, and we're seeing plenty of fresh opportunities in the market. Energy Valley is one illustration — a hybrid project in which we pair renewables to supply energy on a 24/7 basis, plus we're installing battery systems that provide frequency control and regulating power to the grid. If we take stock of where we stand, we're making good progress against the targets we announced last year as well. We're ahead of the target for equity investments into new profitable projects, and we estimate hitting 1.3 billion in equity investments this year, well above our 1 billion target. We've also secured projects in construction and in backlog totaling 5 billion of investment over the coming two, three years — that's growth already secured.
Terje Pilskog
executiveOn the capital recycling goal, we're making solid headway too. Out of a 6 billion target, 2.6 billion is already done. Another 300 million in proceeds should come our way tied to EBRD coming in to set up the platform and, in principle, also taking a stake in Obelisk. Regarding the remaining 3.1 billion, our confidence is high, though the timing and price have to be right. Reaching that target will involve a mix of smaller and larger transactions. On deleverage as well, we remain on track to bring corporate debt down to 4 billion by 2030. By the close of the quarter we are down 2 billion, to 7.1 billion. As Hans Jakob noted too, drawing on the RCF because of working capital swings produced a modest uptick this quarter. Given all this, we are raising our targets looking out to 2030. That means doubling our equity investment targets to 2 billion annually. Of that 2 billion a year, 60% is already secured for the period from now through 2030, and it is already either under construction or in backlog. On growth, our focus will stay on scalable markets, the integrated business model, and our multi-technology approach, along with markets where renewables fundamentally make sense and where we see a good value proposition for renewables.
Terje Pilskog
executiveSecond, we're also setting a new target for cash flow to equity. Our goal here is to double cash flow generation to 2.5 billion starting from 2030. During this period, D&C cash flow is going to rise given the growth we're seeing, and that will fund a big portion of the equity investments made in the period. We also expect a substantial share of the higher cash generation to come from long-term PPAs, which will give us predictable cash flows. We anticipate new assets contributing roughly 1.2 billion in cash flow during the period. Lastly, we remain focused on strengthening the balance sheet as well. Our target of cutting corporate debt to 4 billion in the period stays in place. 40% of that has already been delivered, 3.1 billion is left, and we're confident we'll get there too. The business plan we're presenting here is fully funded via divestments and through robust cash generation from both the power plants in operation and the D&C segments. Under this plan, we'll very likely be in a position to generate available liquidity toward the end of the period — liquidity that could go toward growth, deleverage, or shareholder distributions.
Terje Pilskog
executiveNow, first, let's discuss the growth piece. The near-term growth portfolio accounts for roughly 60% of the target toward 2030. On the generation side, we've got 2.3 gigawatts under construction and 4.3 gigawatts in the backlog. That brings total generation capacity to 12.3 gigawatts by 2028, at the end of 2028. When it comes to storage, we have 0.7 gigawatt-hours in construction and 4.7 gigawatt-hours in backlog, which takes us to 6.8 gigawatt-hours by the end of 2028. That's an increase of four to five times compared with where we stand today. Beyond that, we have a robust pipeline that has grown considerably in battery storage, since we're also pursuing permitting for batteries tied to the projects we have on the PV side. Looking at further growth, we see significant potential in markets where we already hold a strong position, such as South Africa, the Philippines, Egypt, Tunisia, and Romania. All of these markets share very strong characteristics, including competitive economics, renewables being the most competitive solution, and scalability — they are large and growing energy markets. We have established offtake routes in these markets, which matters to us for maintaining a long-term perspective in developing a pipeline.
Terje Pilskog
executiveOur competitive position is solid, and it lets us leverage what we can do in these markets. On their own, the markets we're showing here account for over 50 gigawatts of renewable growth potential for us through 2030. We have South Africa and the Philippines. Both are sizable markets with appealing frameworks, and they also need to move away from coal — that could happen fast or take somewhat longer, but the potential is meaningful. Egypt and Tunisia, along with the North African region, have tremendous resources. Right now they rely on imported gas at very high prices, and shifting to renewables matters for them both to cut the cost of generating power and for energy security and independence. Then there's Romania, a big market with a supportive framework, backed as well by the EU via contracts for differences, and it will also be an appealing market for BESS. Beyond that, we'll stay opportunistic. We'll keep examining other markets too, but those markets have to meet these criteria. The economics need to be attractive, and the market needs to offer attractive scale. Energy markets keep changing when it comes to maturity, offtake routes, and deregulation, and we have to take that into account as well.
Terje Pilskog
executiveWhat these capabilities give us is the ability to compete across all these kinds of markets, and renewables these days bring the competitiveness and flexibility needed to claim a big share of them. As for traditional markets, ours are regulated ones. Egypt and Tunisia are examples. In those places, a single buyer purchases the electricity and offers long-term PPAs at a set price. That's our home turf. There we enjoy predictable cash flow, high leverage, and capital efficiency that is very high. Then certain markets will deregulate, as we've experienced in South Africa and as we've also observed in Colombia, and typically they open up for direct sales to the private sector. What matters here, beyond the development capabilities we have, is being able to originate offtake and optimize generation and customer portfolios. Take our Lyra platform in South Africa as an example: that's precisely what we're doing there, setting up an entity to manage this well. Lastly, there are deregulated and merchant markets such as the Philippines and, to some extent, Romania and Brazil. In these, building a flexible mix of generation and storage assets matters. On that basis, you can capture value through a mix of contracted revenues, on which you can obtain leverage, and selling into the merchant market.
Terje Pilskog
executiveLike I mentioned, deregulation is happening in markets. We operate across various market types, yet our capabilities allow us to compete within each of them. Looking ahead, regarding future growth beyond what's already been secured, our focus will remain on those three pillars. The traditional IPP business, with long-term contracted offtake, is our first pillar. Growing through this route is the most capital-efficient approach. We still foresee enormous growth potential for us in this area—for instance in Egypt, in Tunisia, and throughout the North African region as well. Very likely, this will account for the majority of our growth through 2030. Next, we'll keep positioning ourselves in markets that have mixed offtake portfolios, such as the Philippines, Brazil, Europe, and to some degree South Africa. Such markets call for flexible generation and storage portfolios. A typical strategy involves a contracted revenue base that enables leverage, while capturing upside from market volatility and managing downside risk. We anticipate this will form a significant portion of future growth, but since we're already very present in the Philippines and generate substantial cash flow there, we don't expect this to rise significantly as a share of our overall portfolio.
Terje Pilskog
executiveNow, regarding new demand and offtake routes, what we're seeing is that competitive and baseload renewables are going to increasingly unlock new infrastructure projects across all of our markets as we move forward. We've been exploring green hydrogen, we're examining desalination, and we're also looking at data centers. Across this space, our track record, our market position, and our integrated business model give us a strong foundation for engaging and competing here. Converting this will take more time, but we do see an attractive longer-term opportunity space for us here as well. That covers growth. Let's now turn to the cash generation target. Our cash generation target is underpinned by our capital-efficient integrated business model. Over 50% of the equity needed for our growth is secured and covered by cash flow from the D&C segment. This slide is fairly busy with a lot of numbers, so let's begin in the middle. The total CapEx tied to our projects in construction and backlog comes to roughly 54 billion. Assuming 80% leverage and an average 40% equity stake for Scatec, it's somewhat below 50 because we're going quite down in Egypt, the equity investment for this portfolio will be approximately 5 billion.
Terje Pilskog
executiveNow regarding the D&C business, shown on the left side here, if we assume 70% EPC scope and an 11% gross margin, that gives us roughly 4.2 billion in gross profit. This time, let's take it all the way down to cash flow. After OpEx and tax, that comes to about 2.8 billion in total cash flow over the coming years in the D&C segment, which is over 50% of the equity to be invested during this period. Obviously, on the right-hand side, our equity investment has to clear our hurdles, and this will build a portfolio of operating assets with attractive cash flows and returns over time. We use 1.2 times cost of equity as a hurdle, along with a 20% to 30% services margin. On that basis, this portfolio should deliver roughly 750 million in average annual cash flow once the full portfolio is complete. That works out to an average of about 15% cash yield across the portfolio. Then, let's go one step further and look at how this appears across the total portfolio at the corporate level as we approach 2030. The current run rate for cash flow is in the range of 1.2 billion, and we aim to more than double that by 2030, to 2.5 billion.
Terje Pilskog
executiveThat 8 billion in equity investments ought to generate roughly 1.2 billion of fresh cash flow. With us investing at a quicker rate, cash flows from D&C should rise by around 0.5 billion as well. Clearly, we will lose some current cash flow in power production as we divest, farm down projects, or leave certain markets. That said, because corporate debt is lower, reduced interest costs will also lift cash flow during this period. All of this takes us to a yearly cash flow target of roughly 2.5 billion looking out to 2030. The plan is fully funded and, on these targets, could even produce available liquidity near the end of the period. Once more, looking at the overall growth numbers, equity investments across four years total 8 billion, and over 50% of that will be funded by D&C. The remainder will come from cash flow from operations. On deleverage, the 3.4 billion in targeted divestments we have during the period can fund corporate debt repayments. As I mentioned, that potentially leaves free capital toward the end of the period. To sum up on this point, the plan is self-funded. Equity investments do not hinge on divestments.
Terje Pilskog
executiveWhen it comes to divestments, those are what we use to bring leverage down. Should the plan generate free liquidity, that leaves room for additional growth, further deleveraging, or alternatively shareholder distributions as well. Moving to the balance sheet, our target, as I've mentioned, is to lower corporate debt to 4 billion by 2030, and that target remains firm. We're on track to get there. Since we announced this target, we've cut debt by over 2 billion, leaving 3.1 billion to go before we reach 4 billion. The target divestment proceeds cover this. We're already seeing meaningful deleveraging and refinancing effects today. A significant cut in credit margin has been delivered since our 2023 bond, which carried very high levels. We've now issued a new bond in Q3, 1.5 billion at 250 basis points of credit margin, and that bond has gone toward refinancing older debt that was more expensive. On its own, this saves us roughly 50 million a year in interest costs. Then, to sum up today, first of all, on the quarter, we've delivered solid financials, particularly in D&C with a gross margin of 26%. Construction has begun on Shadwan and DANDARA, and we now hold 10.5 billion in remaining contracted revenues in the D&C segment.
Terje Pilskog
executiveWe’ve locked in equity platforms with EBRD, and we’ve also secured EBLs for the Egypt projects so that we’re able to carry them out on an equity-last basis. Now, when it comes to strategy, renewables keep making the value proposition stronger. From our perspective, that means more opportunity opens up in the markets where we operate. Our goal is to double equity investments and cash flow to equity by 2030, and 60% of that growth is already secured. We take a self-funded approach, and we have the ability to have liquidity available toward the end of the period to fuel either—as I mentioned—additional growth, more deleverage, or shareholder distributions. Thank you very much. After that, we’ll move on and take questions.
Andreas Austrell
executiveThanks, Terje and Hans Jakob. We'll move on to questions now. As we normally do, we'll begin here in the room and then take a few from our online listeners. First up is Andreas from Arctic. Thanks. Now that the Philippines situation is behind you, looking ahead — I think you did a nice job laying out the market, what's happening, and what we can expect going forward. Good to hear. Big ambitions ahead, 2 billion of equity investments each year. Could you elaborate, because in Egypt especially, you do this on a fully funded basis. Are you referring to 2 billion in book equity or in cash equity?
Terje Pilskog
executiveWe're discussing $2 billion in cash equity. Do cash flows move from corporate down to the SPVs? Yes. Okay. When we look at Egypt, those structures are certainly very attractive, and the projects there are enormous in scale. What should we expect next from Tunisia and Romania? I know that in Romania, the EPC scopes within what you have in the backlog right now aren't that high compared with what you're doing in Egypt. Should we anticipate higher EPC shares on those projects, and in Tunisia, how will that look? In Tunisia and throughout the North African region, I believe we see significant ambitions when it comes to speeding up renewables deployment in basically every country. In Tunisia, we hope to see bigger projects and faster deployments there. In that market, we'll take the full EPC scope the way we typically do, and the way we've done on the projects we've implemented in Tunisia so far. In Romania, our ambition is likewise to take the full EPC scope and have a fully integrated business model. Typically, in Romania you have to expect a different contracting structure, and the leverage will be slightly lower.
Terje Pilskog
executiveLooking at it that way, equity versus D&C margins will move a bit. Clearly, we still apply the same hurdle rates in Romania that we use elsewhere, and as I mentioned, our ambition is to handle the full EPC scope in Romania as well. Okay. That's clear. One more question on Tunisia. What is preventing us from seeing gigawatt-plus solar projects in Tunisia going forward? As I said, Tunisia is a fully regulated market, and for now it is the authorities who determine how fast they will build out and which type of procurement mechanisms they will use for that build-out. Tunisia has been running tender processes so far, whereas in Egypt we can conduct bilateral negotiations — those are slight differences. Rest assured, we are actively engaging with the authorities in Tunisia and trying to demonstrate what we can achieve elsewhere, for example in Egypt, so as to encourage them to speed up the pace of renewables in Tunisia too. Obviously, Tunisia today relies heavily on imported gas for electricity generation, and from an economic standpoint renewables are a significantly more attractive solution. Okay. Thank you.
Andreas Austrell
executiveAnders from SEB here. I think we have to bring up the Philippines, even though you've already covered it. In this presentation, you haven't given the overview of the drivers in the Philippines for the quarter — the one you did in previous quarters, where prices were broken down. I see that it's in the charts, and that's appreciated, but volumes and prices — could you give us that for this quarter as well, and going forward?
Hans Jakob
executiveYes. As you mentioned, the chart shows the prices — the main factors are, of course, somewhat lower output, but quite high prices, as Terje explained, including spot and reserve market. During earlier quarters, you gave a separate slide that breaks out transaction volumes and prices by segment. You did, yeah. If we could add that, it would be very good if you could supply that to the market, given the uncertainty and confusion about how those revenues look. That's a request. A second question about the transaction volumes, because in the past you've indicated ancillary service volumes, and you've given a figure for the effective ancillary service price. Could you say something about how volumes split between contract and the reserve market? What portion of those volumes is contract, and are the volumes comparable?
Terje Pilskog
executiveRight, doesn't part of that already appear on one of the slides — the one we shared?
Andreas Austrell
executiveI believe we'll include that slide.
Terje Pilskog
executiveYeah. Mhm. Okay. So are the volumes similar, or? The volumes are similar. Those contract volumes do fluctuate across the year. Usually, contract volumes will be lower when we think — and when the forecast says — that energy prices in the market will be higher, since we can use more of the water to sell energy. Contract volumes will usually be higher when there is typically less appeal in the spot market for selling energy. In terms of overall volumes, they are similar, yeah.
Andreas Austrell
executiveOn the annual volumes — you can actually locate this in the Philippines, in some of the documents over there. Finding it isn't straightforward, but it comes to roughly 3 gigawatt-hours on the ASPA contracts. Yes. As for the contracted volumes in ancillary services, that stands at 2.25. I believe you put that out in a press release some time ago. Is that right?
Terje Pilskog
executiveYou're talking about the ASPA price, correct? That's the contracted portion of ancillary services. Yeah. In Q2, your ancillary services average selling price came in at 2.6. You also reported that figure for Q2. That points to a very large share of your volumes being under contract. Is it fair to assume that? Yes, that's fair to assume.
Hans Jakob
executiveYeah, considering what time of year it is, yeah. Mhm. Is that 90%?
Terje Pilskog
executiveI don't have that number — I think you'll need to revisit this later.
Hans Jakob
executiveYeah, we'll get you that slide. And just to wrap up, I genuinely value the improved transparency here, and I really think you ought to keep sharing the information that you've shared before.
Terje Pilskog
executiveYeah, just to add to that — obviously, the ancillary services market in the Philippines also has three separate segments, correct? There's immediate, short-term, sort of medium-term, and long-term. Prices differ across those various service types, as is typically the case in any deregulated energy market, including what you have in Europe. Contracted volumes are tied to two of those segments, with differing price levels as well. We'll give the information at an appropriate level of aggregation, but there are some nuances here too, just to be clear on that.
Andreas Austrell
executiveAll right. Are there any more questions here in the room? Then we can take a couple of questions from those listening online. Do you expect to book a gain on the Egypt farm-down to EBRD, and does that gain sit within the guidance?
Terje Pilskog
executiveWe probably will see a gain tied to the Obelisk farm-down, though our guidance does not factor that in.
Hans Jakob
executiveWe’ll take care of that once we close.
Andreas Austrell
executiveThere's another question about the Philippines. You mention that as a mitigating step in the Philippines, you'll reallocate BESS capacity toward existing long-term contracts, while at the same time saying the long-term effects are limited. So with that in mind, is it fair to assume you expect the ASPA tariff on new contracts to be broadly consistent with your current contracts at 2.25 Philippine peso?
Terje Pilskog
executiveAt this point, I don't think we'll say anything about exactly where prices will land, or how much volume we might move over to long-term contracts versus holding it back to sell into the reserve market. It's obviously also important to keep in mind that right now, we have 40 megawatt-hours of battery capacity in the Philippines, and we currently expect to bring one new battery online over the next couple of months and two new batteries online during next year. We'll also raise the battery capacity in the Philippines from 40 megawatt-hours to 160 megawatt-hours over the next 12 to 15 months. We will also have more capacity to operate in the ancillary services market going forward.
Andreas Austrell
executiveThanks, Terje. Actually, Anis Zgaya at ODDO BHF has two questions for us. First, on the Philippines: you're expecting only limited long-term effects from the suspension of the reserve market. What makes you confident that ancillary services earnings can bounce back after the six months suspension is over? And beyond 2026, what level of normalized earnings should we be assuming?
Terje Pilskog
executiveThere are a few factors here, and I touched on some of them during the presentation. Ancillary services are needed by the market, and right now the market—or possibly must-run facilities—is facing extra costs tied to the suspension of the market. We also think the market will grow, in the sense that more variable renewable capacity is going to come onto the grid, and as a result, ancillary services will be needed more in the future. The second point is that the marginal capacity for ancillary services is tied to diesel and heavy fuel oil generation—that capacity is very expensive and it's what sits at the margin. We've also seen historically that when changes are made and attempts are made to adjust the ancillary services market or the reserve market to manage prices, they typically impose a price cap or price ceiling, and that is at least what we currently expect the outcome to be this time around as well. Obviously, we don't know, but this is sort of what we expect at present. From that standpoint, we don't think the supply-demand situation in the ancillary services market, in the reserve market, will shift significantly. The high prices will be capped, particularly in Visayas and Mindanao.
Terje Pilskog
executiveWe think pricing will return to normal, and for what lies ahead, the right yardstick is the historical prices — not Q3 — rather than the third-quarter figures.
Andreas Austrell
executiveThanks. One more question here. Given that higher investment ambition, might we see any shift in your return thresholds or in the mix of projects, especially between renewables and storage? Or is your view that the bigger pipeline lets you double investments without sacrificing returns?
Terje Pilskog
executiveReturns are something we won’t compromise on.
Andreas Austrell
executiveUnderstood, thanks. We have one from Jørgen Lande at Danske Bank. "Good morning — just to clarify: the 2 billion annual average for equity investments that you're guiding toward 2030, is that gross, meaning before cash inflow from D&C?" Yes, that's confirmed. Yes. Yes,
Terje Pilskog
executiveThis is gross.
Andreas Austrell
executiveYes.
Terje Pilskog
executiveMoving on to the next item.
Andreas Austrell
executiveThere's one more question we received. Which one of the Ukraine facilities was impaired?
Terje Pilskog
executiveThat applies throughout the portfolio.
Andreas Austrell
executiveAlright, the next question comes from Jørgen Lande at Danske Bank, regarding the Philippines. He says that to get a handle on 2027 output volumes, if we take it that Scatec's typical net production sits at roughly 750 gigawatt-hours annually, how should we view the effect of the reserve market suspension on your 2027 production, measured as a deviation from a normal year?
Terje Pilskog
executiveYou shouldn't anticipate any effect on the overall generation we produce. That water is going to be used for making power, regardless of whether it's sold into the spot market or whether it passes through the turbines to provide incidental energy tied to the capacity we offer in the ancillary services market. In the end, every drop of water will be used to generate electricity.
Andreas Austrell
executiveYes. Okay. We have one asking, "Can you provide guidance for 2026 given the moving parts in the Philippines?" I believe we've already given that information. "Could you update us on asset rotations and when we are on there if there anything you want to add on that?"
Terje Pilskog
executiveNo, like I mentioned during the presentation, we anticipate bringing in roughly 300 million tied to the platform we set up in Egypt with EBRD, or for Egypt with EBRD. We're working on several other possible farm-downs and exits, some smaller and some larger, but we'll share more details once they materialize.
Andreas Austrell
executiveCould you give us a bit more detail on what you anticipate ancillary service earnings will look like in 2027? And over what timeframe do you think it's likely that you'll sign longer-term agreements for your BESS capacity?
Terje Pilskog
executiveMy guess is we'll share more details on 2027 at the point when we give the outlook for that year. Work is already underway to determine whether bilateral contracts for ancillary services can be secured, though offering a view this far ahead on that is quite hard.
Andreas Austrell
executiveFinal question for you: if an appealing bid came along, would you think about divesting the hydropower operation you run in the Philippines?
Terje Pilskog
executiveThat's not something I think we ought to comment on.
Andreas Austrell
executiveOne more just came in. "You're showing NOK 30.3 billion in divestment cash from Egypt. Does that tie to Obelisk?" Yes, that's correct. And one more from Andreas. Regarding the Philippines, could you just confirm that what we saw on ancillary services revenues in 2024 would be a very bottom part of the range in terms of what you should expect, because you didn't have much sales to the reserve market then?
Terje Pilskog
executiveI won't commit to a specific figure or make any promise about the exact level. I do agree that in 2020 and 2024, the market got going — we had one or two months, perhaps a month and a half, when the market was working, and then it worked for the last, I don't know, four months. In principle, that's five, six months of operations. Assuming prices stay the same and we now have six, six months of suspension, 2027 should come in a bit higher than 2024. At this point in time, as I said, we need to revisit the '27 perspective when we present the outlook. Thank you. When do you expect the Obelisk transaction to close, out of the larger transaction? The Obelisk transaction will close in Q4.
Andreas Austrell
executiveYeah. We’ve got a few more questions coming in — I think it’s 3 more. One is again from Anis Zgaya at ODDO BHF, on Tunisia. He says you had some challenges before with STEG around grid connections for new projects. I’m not sure what that refers to, but: have those issues been resolved now, or do you see bottlenecks in Tunisia when it comes to grid connection? And also, there was some load shedding and periodic power cuts during last summer’s peak demand to protect the grid. Did that affect operations or production?
Terje Pilskog
executiveMy understanding is that the question concerns Tozeur and Sidi Bouzid, the initial 2 projects. Those, I think, were commissioned somewhat behind schedule. Last summer's load shedding did not affect us at all, though clearly it affects the country heavily, along with the energy situation there. I was in Tunisia last week and spoke with the Minister of Energy, and he is seeking to push us to speed up construction of our projects so they can reach the grid and help them handle the tough conditions on the grid over the summer. Obviously, we and the authorities are cooperating to ensure we can bring more power onto the grid as fast as possible.
Andreas Austrell
executiveAll right, that was a follow-up to the earlier question on 2026 guidance. Building on that: "What about guidance for '27? Do the issues from 3Q carry over into 2027?"
Hans Jakob
executiveI believe Terje has mentioned that we'll revisit the '27 guidance, but I also think one of the key messages was that, especially in the Philippines, we see quite a few opportunities and expect less impact going forward as those compensating measures take effect.
Andreas Austrell
executiveYeah, another one specifically about future guidance for the Philippines — I think we've already covered that. There's one question: "Given NOK 0.3 billion in cash from Obelisk plus the D&C contribution and your remaining stake, wouldn't any estimate of your IRR on this investment have to be high?" I'd say yes, it is high. We aren't giving specific guidance on that. It's been a very good investment.
Terje Pilskog
executiveWell, naturally, that hinges on the method you use for figuring the return. When you figure the return on gross investment or on net investment — with net investment, it's negative, so to speak, if that makes sense, yeah.
Hans Jakob
executiveThe payback period is really brief.
Andreas Austrell
executiveI believe we've covered all the questions.
Terje Pilskog
executiveAlright.
Hans Jakob
executiveAppreciate it.
Terje Pilskog
executiveI appreciate that.
Andreas Austrell
executiveThanks a lot.
Terje Pilskog
executiveI appreciate that.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Scatec ASA transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Scatec ASA earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Scatec ASA or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.