SharonAI Holdings Inc. (SHAZ) Earnings Call Transcript & Summary
May 15, 2026
Earnings Call Speaker Segments
Ross Barrows
executiveGood afternoon, and thanks for joining our earnings call, where we'll go over SharonAI's operating results for the quarter that closed on March 31st, 2026. With me today are James Manning, who serves as SharonAI's Chief Executive Officer, and Tim Broadfoot, SharonAI's Chief Financial Officer. At this point, I'll read the safe harbor statement. Over the course of this conference call, we might make certain forward-looking statements as defined under the federal securities laws, and those could include statements about our expectations, plans, prospects, strategies, future operating results, and financial performance. Even though they reflect what we currently expect and rest on our present view of the industry and our business, they aren't guarantees of future performance. Such statements carry risks and uncertainties that might cause our actual results to differ materially from what those statements express, and they speak only as of today's date; for further details about factors that could impact these expectations and bring about such differences, please refer to our latest Form 10-K and Form 10-Q, along with other SEC reports we've filed with the Securities and Exchange Commission, which are available on the SEC's website as well as in the investor relations section of our website. SharonAI assumes no obligation to publicly update or revise any forward-looking statement, whether because of new information or future events. Also, on this call, we might discuss certain Non-GAAP financial measures. Reconciliations to the most directly comparable GAAP measures, plus related disclosures, can be found in today's earnings release and/or on our investor relations website. I'll now hand the call over to James.
James Manning
executiveHi everyone, and thanks for joining SharonAI's first-quarter 2026 earnings call. I'm James Manning, and I serve as Chairman, CEO, and co-founder here at SharonAI. Since this marks our initial earnings call after listing on Nasdaq, we intend to follow this format: a quick rundown of quarterly highlights, a brief explanation of what SharonAI does for those unfamiliar with our business, some detail on particular events from the quarter, and a short business outlook. At the end, we'll leave time for some Q&A. It has truly been a remarkable first quarter as we make the shift into life as a public company. Going through it in order: during January, I took over as CEO of SharonAI, succeeding Wolf Schubert, who remains involved with the SharonAI team on their North American projects. Near the end of January, we signed definitive agreements to sell Texas Critical Data Centers, and I'll cover that in more detail shortly. February brought our Nasdaq listing under the ticker code SHAZ, S-H-A-Z; through a transaction with Soar, we raised $125 million led by Lucid Capital; and we finalized our agreements with Canva, signing an MSA. In March, we signed GMI, and after that we executed the ESDS contract. As of today, we're announcing an upgrade of our data center capacity to 100 MW by early 2027. Alongside all of this, we keep building out our team and governance structures, always refining how we operate. Importantly, Ben Adams and Drew Kelton joined the board, both serving as non-executive directors. What is SharonAI? SharonAI ranks among Australia's leading NeoClouds. We provide AI-native HPC-grade compute infrastructure to our customers, aiming to serve three primary customer segments: hyperscalers, AI natives, and enterprise. Our approach involves partnering with global industry leaders to deploy the newest generation of GPU compute. Although our deployments are geographically in Australia, our customer base is genuinely global in nature. Our recent customer wins tell this story, with regional compute contracts serving global compute needs. That speaks to the desire to run mission-critical workloads in safe and secure compute environments. Australia's geographic position on the globe makes it well-suited to meet GPU compute demands, close enough for latency yet far enough away from a security standpoint. Latency stays an important factor for GPU use, though arguably less so than most people believe. Even though Australia's location on the globe is somewhat isolated, the advantages clearly outweigh the disadvantages. We're just 81 milliseconds from Singapore, 130 from Hong Kong, 165 from the West Coast of the U.S., and 225 from the East Coast. Although latency plays a role in how you think about your compute loads, the security advantages of being somewhat remote in Australia while serving that Asia Pacific region far outweigh the time differences. The key message for us, I think, is that SharonAI, despite being headquartered in Australia, is Asia Pacific focused and truly serves compute loads for the entire world. So what does a NeoCloud actually need to make it? From where we sit, there's a single problem we're addressing, and that's scarcity; we break it down into 4 broad categories. First, you've got the scarcity of compute — as one of just two NVIDIA cloud partners operating at scale in Australia, that hands us a durable edge when it comes to obtaining NVIDIA GPUs. That's not only about our relationship with them; it's also about the ties we have with our OEMs and partners such as WWT, who assist us in, you know, sourcing and standing up that compute at scale and on schedule. Then there's how you obtain power. Power scarcity is a genuine piece of the puzzle when it comes to bringing GPU compute workloads online and on time. You know, in late 2025, we locked in 50 MW with NEXTDC. As of today, you know, we've shared that we've grown that overall energy capacity in Australia to more than 100 MW for early 2027. The regulatory landscape adds further complexity to scarcity, since not every country can get hold of the newest generation of GPUs, and Australia is extremely lucky to be a close ally of the U.S; and to possess that capability to obtain the newest generation GPUs. Last of all, scarcity when it comes to talent. People matter enormously to what we do; we believe that having a deeply experienced team such as ours, with High-Performance Compute know-how, sets us apart in the market we're performing well in; it's pretty straightforward, guys. The quickest train models means the quickest inference, the finest insights, and the greatest innovation. All of that likewise calls for accelerated compute as a service, which is the definition of a NeoCloud. We're positioned squarely in between the hyperscalers and the AI natives, or the enterprises and the people consuming that data; we're the fabric binding together numerous vendors and solutions to deliver the quickest accelerated compute. We get there via our partnership-driven approach, drawing on best-in-class expertise throughout the value chain, both global and domestic, spanning the hardware, power, security, connectivity fabrics. Doing so lets us reach the market far faster and more capital efficiently than the conventional vertically integrated provider to supply that GPU as a service. Once all that infrastructure exists, commercial success demands two further elements: a truly robust go-to-market and sales strategy plus high-performance connectivity reaching those customer environments. At Sharon, we avoid trying to own everything, and we have these excellent partners who contribute that value and make sure our service offering delivers those two enormous advantages, which are the best-in-class expertise at each and every layer and the capacity to move far quicker and more capital efficiently than vertically integrated players. With scarcity addressed and partners secured, the next question is how we contract. Contract signing isn't the starting point, though. Prior to contracting, we invest a substantial amount of time behind the scenes collaborating with our DC partners, OEMs, and our internal engineering team to identify the optimal technical solution for the spaces we are operating in. After finalizing that design, we usually carry out a customer engagement process in which we speak with both the available capacity and the compute form we believe ought to be deployed. After we identify the appropriate customer for that space, we come to an agreement on principal terms, and we execute these non-binding term sheets before moving to an MSA agreement. From the moment a contract is signed, delivering the compute infrastructure to the customer can take us anywhere from 3 to 7 months. We accept delivery, we test, we deploy the compute, we confirm that everything is operational, and we hand it over to that customer. Five years is the length of most of our contracts, and generally speaking, all of them are take or pay. Although an average hourly rate might be inferred from these contracts, the take or pay nature guarantees that we get paid for 100% utilization, which provides us with clarity regarding our revenue forecast. When the term ends, we can either enter into a new multi-year contract or apply the compute to our own development compute platform. What actually got converted this quarter, and I believe we have announced 3 meaningful contracts. The first was Canva. Although it was not a financially material contract win in its current form, it did demonstrate the power and the value of the SharonAI platform and how we could give Canva both speed and output improvements.
James Manning
executiveWe have a lot of confidence in that partnership and in our ability to broaden what we offer through it as time goes on. After that, GMI Cloud was a win for us. GMI Cloud operates as an AI-native inference cloud provider based in the U.S., and following that came our biggest customer agreement so far, which was ESDS. ESDS works as an IT service provider headquartered in India, and that deal carries a total contract value of $1.25 billion across 5 years, with the revenues from those contracts anticipated to start in September of this year. Although it didn't land in this quarter, this week we came out with news of a $950 million 5-year take or pay contract with a global technology company that has a major Asia-Pacific presence, and revenue from it should begin in the third or fourth quarter of 2026. Taken together, this pushes our contracted TCV past $2.2 billion, and we anticipate an exit 2026 revenue run rate of no less than $470 million. Alongside all that momentum in customer wins, we also locked in the gain from our project in Texas, known as Texas Critical Data Centers or TCDC. In January of last year, we set up a JV alongside our partner, New Era Energy & Digital. Across 2025, we acquired more than 438 contiguous acres of land through 2 separate transactions. A non-binding LOI was signed with a hyperscaler. We completed a substantial amount of engineering design work, and after that we entered exclusivity with the hyperscaler. Toward the end of 2025, we reached an agreement to step away from that. In January, we closed it out in a transaction through which we brought in $74 million, delivering a material return for the business. These development opportunities sit outside our core business, but they have the potential to be highly profitable. Moving forward, this won't represent a material portion of our business, though we do keep the right to keep looking into further opportunities in this space; this non-dilutive capital can be recycled, and it can serve as an accelerator for our core GPU business. At this point I might just move to our outlook. We stay incredibly confident regarding the continuing growth of our core operations. We keep seeing client demand from both Australia and the rest of the world substantially exceed the GPU supply that is reaching the market at scale and in a timely manner. Being one of Australia's leading NVIDIA cloud partners, or NCPs, combined with our robust partner network, puts SharonAI in position to keep capitalizing on these strong GPU market dynamics. Today we've put out the news of this expansion of our data center capacity, going from 70 MW in 2026 to over 100 MW in early 2027; that mirrors our continued ability to lock in additional power allocation and data center capacity through our network of data center partners. Finally, and definitely not least, we've brought in significant additions to our technical and management team to back our anticipated growth. Our people are essential to our continued success. Before I wrap up, I'd just like to express thanks to everyone on the SharonAI team, our partners, investors, advisors, and all the stakeholders who have stood behind us over the last three months especially, but really across the last couple of years. The progress we've made in such a brief period genuinely thrills us, though what lies in store ahead excites us even more. Operator, could you please open up the line so we can take some questions?
Alex Frohman
analystHello, and thank you all for letting me ask. Nice work on the IPO going well and on the announcements made recently. I wanted to ask about your approach to marketing the capacity you still have left, plus the additional capacity that was just made public. It appears the initial pair of major agreements you disclosed carried 5-year terms. Is that pattern something we should anticipate going forward? I also have a few additional questions after that.
James Manning
executiveYes, of course, Alex, I appreciate the question. Let me begin with how long the contracts run, since that part is straightforward; our typical aim is deals lasting 5 years or longer. Consider the ESDS contract as an illustration — it runs 5 years and includes 2 1-year options, meaning it could extend as far as 7 years altogether. The key thing inside that agreement, and this is the model we want to copy elsewhere, is that we see the optional renewal windows landing in year 4. In year 4, a choice must be made regarding year 6. Strategically, part of our thinking is that we clearly believe pricing in the market will be stronger during the earlier periods, so the sooner we secure that renewal, the more confident we can be that those extended periods will protect us over the long haul. Broadly speaking, 5 years is what we aim for in contracts. If we're able to include those extensions and options, that's very sensible. More widely, the pattern we're noticing is that storage is turning into a truly significant element across all of these agreements. In fact, we view storage as contributing to how locked-in these customer relationships become as the term nears its end. Our strong expectation is that those customer agreements will, you know, be renewed owing to, you know, their fundamental attachment to us, because of the data we end up keeping on our equipment and devices; that's roughly how I think about renewals. My sense is renewals will happen on their own. I think storage creates stickiness and forms part of the egress component, which makes it very sensible for customers to remain with us, beyond simply having that compute capacity available. Once you reach that 5-year mark, they've already stayed with you for quite a while and they're familiar with you and, you know, ideally, and as we're observing with certain earlier customer agreements, they're already discussing that expansion. You know, that's certainly something on our minds when it comes to contract renewal. The other matter was walking through our capacity, and how we intend to contract that extra capacity. I think if you consider how we entered the market in February, we stated, look, 55 MW. We disclosed the ESDS contract, which brought us to 70 MW. We're announcing to the market today that we've signed up for another 30 MW, and I believe we've been quite open about the fact that we do have somewhat of a pipeline of energy assets, and we're kind of pairing those with customer contracts as we work through those customer contracts too. In the past I've explained how that contracting process works for us. But generally speaking, when we secure a site such as, say, M2, which is now the next major project we're concentrating on, and which is 40 MW that's publicly known, that's an enormously valuable asset. You know, having 40 MW arriving in Q4 in Australia, which is, you know, genuinely a Tier 1 nation, is ultimately a very, you know, straightforward asset to take to market and sell to end customers. It's incredibly valuable in today's market; we're actively holding discussions about that, those MW and how we position them. We've completed the design phase for that compute cluster down in Melbourne, for example. We're figuring out how we, you know, simply align the proper customer with the proper customer offtakes and get it contracted. you know, I think you'll see us sign that at, you know, in the near term, and then we'll make an announcement and we'll discuss, you know, the remaining pieces of capacity. You know, with the extra 30 MW we've announced today, part of that sits in Australia, part of that sits in New Zealand; we're considering, you know, alongside particular customers for particular end use cases, how those MW will come online in that space.
Alex Frohman
analystAll right, that's a big help. So then, regarding M2 — I'm just wondering what sorts of possibilities that opens up for you, correct? Since you've got 40 MW sitting together that you can take to market. Clearly, you could split that into 5 MW or 10 MW pieces, similar to a few of the deals we've witnessed up to now. What sorts of possibilities exist for deploying a 40 MW block that wouldn't be available with the smaller allocations?
James Manning
executiveYes. I believe you've nailed it exactly. A size like 40 MW is, you know, probably going to a single large buyer. When we discuss the profile of our customers, hyperscalers have always been present in our pipeline. We have, you know, AI natives, plus we have enterprise customers. My view is 40 MW won't get divided among many small enterprise customers. It will land in the first two categories. A hyperscaler, or a big LLM, or an AI native enterprise would be the sensible buyers for a contract of that kind. A somewhat different customer profile, a somewhat different use case. Much of this, I think, we're viewing through a storage-focused lens and, you know, we want buyers who will expand, not only in GPU compute, but also expand on the storage compute side; we are certainly holding those discussions with customers where we believe we can deliver added value over time within these contracts, since we're observing in those initial customer contracts that storage requirements are skyrocketing, and we're seeking customers where we see not merely the nominal contract value, but that growth potential across the customer lifecycle.
Alex Frohman
analystAll right, that's useful. And then finally, it's really good to see you've locked in another 30 MW of power. What's notable is that a portion of that will be located outside Australia, over in New Zealand. So I'm wondering what sort of visibility you have into getting more power further out past that 100 MW. Are you actively exploring possible data center openings in nations beyond Australia and New Zealand? I'm just attempting to get a handle on the plan here.
James Manning
executiveYeah. Well, I won't address that directly — you know, I believe the thing we've managed extremely well is avoiding getting ahead of ourselves, throughout the whole period we've been out there, ever since listing and whenever we've come to market and discussed this. As I mentioned, going back to the 55 in February, then the customer announcement of 70, and now 100 today. I think we recently ran a non-deal roadshow across North America, and we met with plenty of investors who'd taken part in the IPO. Their feedback was, "Provide us with a bit more guidance regarding megawatt." We've attempted to fulfill certain asks for some forward pipeline, and we're confident there's considerably more megawatt coming through that pipeline eventually, yet we're striving to align those megawatt with the timing of when they can be brought on, who the end customer will be, and genuinely work through something of a matching process connecting those megawatt to existing customer demand. The guidance on the megawatt we're announcing is that they're closer in time by nature, and we're genuinely attempting to locate near-term customer contracts tied to those near-term megawatt; we're going to remain within our geographic region. What we're observing is that demand for GPU compute across the region is completely exceeding the supply. We're simply concentrating on locating those premium global customers who operate in Asia-Pacific. In particular, customers that need not only raw GPU compute, but storage requirements too.
Alex Frohman
analystAll right, that's a big help. Thanks a lot.
Brett Knoblauch
analystHey, everyone. Appreciate you fielding my question. Good to see those extra contracts come through. I'd like to take a moment to discuss what visibility we might have into GPU deliveries. It seems like you're adding compute pretty fast relative to when these deals get announced. From what we hear, anything in 2026 basically ends up sold. So what edge do you have when you announce a deal, say yesterday, and claim that in 4 months you'll be able to begin producing GPU revenue?
James Manning
executiveIt shouldn't come as a shock that capacity is tight in 2026. What we observe with our OEMs depends on which form factor you're considering, and generally we're building out in GB300s. On GPU, we're roughly seeing 12 to 14 weeks. Network takes somewhat longer, though we have excellent supply chain partners, and our ties with WWT genuinely assist with that. In the end, it depends on who the end customer is — there are clearly incentives to get these things online as quickly as possible. For example, we do attempt to stay ahead of certain supply chain elements. We've pre-ordered network for the GB300 cluster, which lets us shorten part of that timeframe. On the longer lead items, we're trying to get ahead from both an engineering and a procurement standpoint. We feel fairly good about our delivery right now, and we're just working to manage it against customer expectations.
Brett Knoblauch
analystGreat. Perhaps I'll focus on the capital expenditure and how it's being funded. Between those 2 recent agreements, it seems like roughly $700 million has to go toward GPUs. What timeframe should we anticipate for that showing up in the financial results?
James Manning
executiveRegarding when the CapEx lands, we're actually already taking on a portion of it as an early signal. For example, we've gone out and made payments and placed advance orders for storage. We've placed advance orders for network as well. With certain components that have longer lead times, our aim has been to stay ahead of things. We were quite lucky with a few of those storage arrangements we secured. We locked them in before prices went up. So we managed to get in front of part of that. On the CapEx side, we've purchased storage sufficient for roughly 70,000 GPUs in order to stay ahead of things. On CapEx generally, the guidance I can offer is approximately $39 million per megawatt right now, on a fully inclusive basis. That figure includes every non-recurring data center cost. We're observing a slight shift in that area, though it remains comfortably inside what we budgeted and what we've previously shared. The order timelines we're seeing around that are quite favorable. As for the capital needed, all the equity pieces fully cover every contract announced so far. With the Oaktree note — which should close early next week — along with proceeds from the IPO and customer deposits, our position on that is reasonably solid. Domestically, we've brought on Jarden for the GPU financing path, and we hold several term sheets. The only remaining step is aligning the appropriate term sheet with what we ultimately want from financing. That's getting a lot of our attention. We're quite far along. As I mentioned, our progress is substantial enough that we're now in negotiations over term sheets for the debt portion.
Brett Knoblauch
analystGreat. Perhaps to really drive one thing home — that extra 30 MW you mentioned, coming by early 2027 — should we be thinking that by early 2027, roughly 100 MW of contracted arrangements will be signed and operating?
James Manning
executiveThe 100 MW, I believe you can count on being signed.
Brett Knoblauch
analystI love you.
James Manning
executiveWe're feeling really good about getting that 100 MW signed.
Brett Knoblauch
analystGreat. We really appreciate that, everyone. Thank you.
Michael Donovan
analystHello, everyone. Thank you. I appreciate you taking my question, and congratulations on the progress. Could you discuss the pricing trends you're observing broadly for GPU hours, and also overall customer demand for inference? You brought up storage, so how should we view customers who need storage as opposed to just bare metal compute? Thank you.
James Manning
executiveWell, every customer has their own situation and their own requirements. If I frame it in megawatt terms, from a revenue standpoint we're looking at roughly $15 million per megawatt, and that figure includes an allowance for some storage. Considering the wider NVIDIA reference architecture, a general guideline is 3 PiB of storage for a 1K cluster. What those customer contracts are now showing us are requests for 6, 9, and 12 PiB. That's 3, 4x the storage element relative to the standard GPU element on the compute clusters. From our side, storage is a fairly high margin element, you know, and it's a genuine value add proposition within the business. Thinking about that, it's really a chance for us to capture extra revenue; it's extra revenue on these contracts, not merely in year 1, but what we're observing is, you know, customers reach 6 months into a contract and say, "We need some additional storage. What are we gonna do?" At that stage, they're already hooked on your GPU platform. It's a pretty easy upsell at that moment in time. You know, I'd say that applies to, you know, broadly the technology element. As you've pointed out, I think everyone knows market pricing is very strong right now given the scarcity of compute. If you're able to bring on capacity this year, you're in a very strong position; that materially outweighing demand of supply dynamics means that, you know, we're seeing really strong customer pricing. The customers are really trying to lock in those longer term contracts 'cause I think what they're seeing is the spot prices are a lot scarier.
Michael Donovan
analystThanks for that. Now, could we spend a moment on the technology angle and where you stand with VAST Data? How crucial is that partnership, and what does it actually deliver for you?
James Manning
executiveSure. VAST handles the storage component that complements the GPU side of things. Our partnership with VAST is outstanding. Their tech stack is remarkable, and we're exploring ways to deepen that collaboration with VAST; they offer some impressive tools that let us bring AI compute into the data layer and have it operate extremely efficiently. As storage turns into the defining theme of 2026 in our view, you need a growing amount of that specialized storage and those storage tools that mesh well with your inference engine so those workloads run very efficiently for the end customer. Overall, we're earning strong margins on storage, and we want to keep seeing these customers desire additional, additional storage with each deployment, since it's a terrific value add for us on the business side.
Michael Donovan
analystExcellent. That's much appreciated.
James Manning
executiveHello, and I'd like to express my gratitude to all of you for being here on our inaugural Q1 2026 earnings call. This marks the very first such call since our Nasdaq listing, and there will be plenty more ahead. My sincere thanks go out to our employees, our team, and everyone offering support — those within the company, outside it, and of course our shareholders. When I reflect on where our business stands, it has grown enormously, and we keep witnessing demand from both Australia and the rest of the world substantially exceeding what we can supply. We have raised our anticipated data center capacity on two occasions during this year — starting at 55, moving to 70, and reaching 100 MW as of now. With capital secured, including the $350 convertible note we announced earlier, we are positioned favorably to keep expanding our customer base across the quarters ahead. We simply want to reaffirm that robust demand persists throughout the enterprise, hyperscale, research, government, and AI native segments across Australia and Asia Pac. We eagerly anticipate upcoming announcements and reconnecting with all of you on our following earnings call. Many thanks.
Operator
operatorAppreciate it. That brings us to the end of what we had scheduled for today. At this point you're free to hang up, and we hope the rest of your day goes great. Thanks so much for joining us.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete SharonAI Holdings Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to SharonAI Holdings Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in SharonAI Holdings Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.