SJVN Limited (SJVN) Earnings Call Transcript & Summary

May 29, 2024

NSEI IN Utilities Electric Utilities earnings 48 min

Earnings Call Speaker Segments

Operator

operator
#1

Ladies and gentlemen, good day, and welcome to the SJVN Limited Q4 FY '24 Earnings Conference Call hosted by Elara Securities Private Limited. [Operator Instructions] Please note that this conference is being recorded. I now hand the conference over to Mr. Rupesh Sankhe from Elara Securities Private Limited. Thank you, and over to you, sir.

Rupesh Sankhe

analyst
#2

Good afternoon, everyone. On behalf of Elara Securities, we welcome you all for the Q4 FY '24 conference call of SJVN. I take this opportunity to welcome the management of SJVN represented by Mr. Sushil Sharma, Chairman and Managing Director. Congratulation and all the best sir, for new role. And we also have Mr. Akhil Singh, Director of Finance. We will begin the call with a brief overview by the management followed by Q&A session. I will now hand over the call to Sushil Sharma sir for his opening remarks. Over to you, sir.

Sushil Sharma

executive
#3

Thank you. Thank you very much. A very good afternoon to all of you present here. I'm accompanied by Shri Akhileshwar Singh, Director of Finance of our company. I am extremely happy to share just with the latest commissioning of our 2 projects, Gujrai Solar project, 50-megawatt and Raghanesda Solar project 100-megawatt in quarter 4 of our financial year '23, '24. With this, our installed capacity stands at 2,377 megawatt. 50-megawatt Gujarat solar project situated in the state of Uttar Pradesh, this generate 107 million units of energy per annum. The power from this solar project is being sold through Uttar Pradesh Power Corporation Limited. We have also commissioned Raghanesda solar project, 100 megawatts in the state of Gujarat with the capacity to produce 253 million units of energy per annum. The power from this solar project is being sold to Gujarat Urja Vikas Nigam Limited. Thus, in terms of these latest additions, 150-megawatt more power has been added, which will add approximately INR 99 crores to our revenues per year. I'm happy to inform that in the month of March 2024, our honorable prime minister of India dedicated 4 of our projects, namely 75-megawatt Parasan Solar Power Project, 75-megawatt Gunrhah power project, 50-megawatt Gujrai solar power project and 60-megawatts Naitwar Mori hydro projects to the nation and also near the foundation stone of 3 projects of namely 382-megawatts Sunni Dam Hydro Electric project. 15 megawatt floating solar power project in the state of Himachal Pradesh. And 70-megawatt of solar project in the state of Assam. Also during quarter 4 of financial year 2023 and '24 as we went through its subsidiary has [ bagged ] 5 solar projects with a capacity of 2,252 megawatts through open competitive bidding process, giving you a brief review of our project. Projects as on date, 11 projects of 2,377 megawatts and 2 transmission lines are under operation, 4 hydro projects of 1,558 megawatt and 1 thermal power project of 1,320 megawatts and 12 solar projects of 2,048 megawatts are under construction. We are excited to inform that SJVN Green Energy Limited, SGL, a fully-owned subsidiary of SJVN has formed a joint venture named SGEL, Assam Renewal Energy Limited with Assam Power distribution company limited from execution of 1,000 megawatts renewable energy projects in Assam. The other JV with Mahagenco, Maharashtra State Power Generation Company Limited for acquisition of 5,000 megawatts of near energy projects is also under process of formation. As a first among PSUs, the season has also secured INR 10,000 crores construction line of credit facilities for its upcoming renewable energy projects from a group of leading domestic and international financial institutions. In the recent past, government of India has also launched PM Surya Ghar Muft Bijli Yojana, which aims to provide free electricity to INR 1 crore households in India. We are extremely happy to share that toward this scheme, SJVN has been allotted 3 states, namely Himachal Pradesh, Punjab and Arunachal Pradesh. SJVN has also been signed the responsibility of installation of rooftop solar system on government buildings and 18 ministries have also been allocated to us in this regard. You must -- also be aware that SJVN has been designated as 1 of the renewable energy implementing agencies via a ministry of new and renewable energy to [indiscernible] 500 gigawatt target by 2030. During financial 2023 and '24, SJVN has voted tenders of 9.9 gigawatt out of target given to us of 10 gigawatt capacity. The PPA and PSA's for 2, 360 megawatt has been -- has already been signed with developers and distribution companies. I'm also happy to share that SJVN is comforted with SCOR excellence award in institutional categories in January 2024 for the commitment of the company in the growth of power sector for rapid expansion and capacity addition journey. Also, SGEL, a wholly-owned subsidiary of SJVN won Prestigious Diamond Award for large-scale solar project developer of here in Uttar Pradesh in the PSC category during Uttar Pradesh annual solar awards held at SuryaCon, Luckhnow 2024 -- in February 2024. I once again repeat that SJVN is moving forward to achieve our vision of installing to 25,000 megawatt portfolio in the operation by 2030 and 50,000 megawatt by 2040. Thank you very much.

Operator

operator
#4

[Operator Instructions] The first question is from the line of Mohit Kumar from ICICI Securities.

Mohit Kumar

analyst
#5

Congratulations on a decent set of numbers.

Operator

operator
#6

Sorry to interrupt you, sir. May I request you to use the handset, please?

Mohit Kumar

analyst
#7

Is it better now? My first question is on the renewal portfolio. Can you just let us know what is the operating asset as of now? And what is the amount of projects which are on the pipeline? And any assets where you have won the bid?

Akhileshwar Singh

executive
#8

Mr. Mohit, I'm Akhileshwar Singh, Director of Finance. Presently, you might be knowing that we are operating 4 individual project under SJVN. Khirvire 47.6 megawatts, Sadla 50-megawatt in Charanka, 5.6 megawatt and 1 power project that Nathpa Jhakri 1.3 megawatt. Besides that, we are putting 4 projects in SGEL, 75-megawatt Para-san project and 75-megawatts Gujrai project and 50-megawatt, Gurhah project, plus 100-megawatt Raghanesda...

Mohit Kumar

analyst
#9

What is the pipeline, sir?

Akhileshwar Singh

executive
#10

Pipeline.

Mohit Kumar

analyst
#11

Pipeline, including the [ L1 ], sir.

Akhileshwar Singh

executive
#12

Yes, yes. I'm giving you. Including under construction is 2,048 megawatt. Please go forward.

Mohit Kumar

analyst
#13

Hello. I think number is on the lower side? Is there isomer numbers must be around 3 to 4 gigawatt.

Akhileshwar Singh

executive
#14

Yes, it is totally 7.2 gigawatt, out of that 2,048 megawatt is under construction and the balance is under the [indiscernible]. [indiscernible] 777 megawatt is under the process of [indiscernible].

Mohit Kumar

analyst
#15

Understood. What is the time line? What is the capacity of looking to install our commission in renewables in this fiscal and next fiscal?

Akhileshwar Singh

executive
#16

Next, this fiscal and next fiscal. This total capacity of about 2,048-megawatt is coming in the '24, '25. And the balance quantity of 4,777 megawatt will be commissioned in the next fiscal, '25,'26.

Mohit Kumar

analyst
#17

Understood, sir. And sir, what is the plan to -- detail plan to monetize the -- your green energy SGEL?

Akhileshwar Singh

executive
#18

In fact, we are planning to have some QIP in current year. And we are in the process of initiating the approval and thereafter, we will be almost 10% to 15% equity of SGEL will be offer to the public.

Mohit Kumar

analyst
#19

Understood. My last question is what is the timeline for Buxar and Nepal, has it changed? Or it is the same?

Sushil Sharma

executive
#20

Regarding Buxar thermal project, one unit we are going to target in quarter 3 and the second unit in quarter 4. And regarding Nepal, this 900-megawatt will be in second quarter of this next year.

Mohit Kumar

analyst
#21

Is this FY '26, right sir?

Sushil Sharma

executive
#22

October, November of 2025.

Operator

operator
#23

The next question is from the line of Apoorva Bahadur from Goldman Sachs.

Apoorva Bahadur

analyst
#24

You mentioned you're planning QIP of SGEL this year. So any sort of understanding that you can provide on what could be the size of this offering?

Akhileshwar Singh

executive
#25

Almost 10% to 15%, up to maximum 20% we will be offering of the current equity in this year.

Apoorva Bahadur

analyst
#26

Okay. So any sense on the size in terms of the amount that you're thinking?

Akhileshwar Singh

executive
#27

It will be determined that we are not in a position to tell you immediately.

Apoorva Bahadur

analyst
#28

Sure, sure. I understand. Sir, secondly, can you throw some light on the incentive in terms in this quarter? And also if there's any under recovery.

Akhileshwar Singh

executive
#29

Incentive current total incentive is INR 182 crore. Out of that capacity, incentive is INR 157.71 crores and the UI is INR 24.48 crores. Last year, it was -- total incentive was INR 253.92 crore. Out of that capacity, incentive was INR 210.29 crores and UI was INR 43.63 crores. Now the incentive, in fact, after September, the government has put on restriction for operating the plant above 100%. Earlier we were operating the plant up to 110%. But now the restriction has been put what we can only operate during the peak season. And that's why there is some less income on the incentive. So for the current quarter is concerned, current quarter the total incentive is for Q1, INR 5 crore has debt in last year same Q1 was INR 24.45 crores.

Apoorva Bahadur

analyst
#30

Only INR 5 crores in this quarter?

Akhileshwar Singh

executive
#31

Yes, yes.

Apoorva Bahadur

analyst
#32

And this is about the capacity?

Akhileshwar Singh

executive
#33

Yes.

Apoorva Bahadur

analyst
#34

And sir, you mentioned about this.

Akhileshwar Singh

executive
#35

Yeah. This capacity incentive during the quarter was INR 1.37 crores and UI was INR 3.66 crores. Last year capacity in [indiscernible] the first quarter was INR 25.36 crores for the quarter.

Sushil Sharma

executive
#36

What was our -- [indiscernible] has been declared by from June to September. So that's why we have deepened this capacity challenges -- incentive.

Apoorva Bahadur

analyst
#37

Okay, sir. And you mentioned about this restriction which the government had put on operating the plan beyond 100%. So why was this the case? I mean, what's the rationale of the government for doing this?

Sushil Sharma

executive
#38

This is the new regulations given by the CRC. It is applicable to all the partitions, all [ PCOs, hydro PCOs ].

Apoorva Bahadur

analyst
#39

Understood, sir. Sir, any under recovery that we witnessed this...

Akhileshwar Singh

executive
#40

No. There's no under recovery, but we have not achieved the green energy. In that case, we have [ TMD ] INR 41 crores against the shortfall in the generation. And that we have built to the beneficiaries.

Apoorva Bahadur

analyst
#41

And sir, at an overall portfolio number what's the shortfall?

Akhileshwar Singh

executive
#42

Shortfall in energy generation?

Apoorva Bahadur

analyst
#43

Demand energy generation.

Akhileshwar Singh

executive
#44

Yeah. Energy, demand energy has mostly 8,533 million units, we have generated 8,131.38 million unit. Almost 250 million units is shortfall.

Apoorva Bahadur

analyst
#45

And sir, we have built this entire amount, so it's all recorded in revenue or...

Akhileshwar Singh

executive
#46

It has been reported in the revenue. We have since INR 41 crores.

Apoorva Bahadur

analyst
#47

Understood, sir, sir. Sir later, there is no sort of requirement of approval from the commission for recovering this?

Akhileshwar Singh

executive
#48

No, it is as per the regulation. It is as per the regulations.

Operator

operator
#49

The next question is from the line of Aniket Mittal from SBI Mutual Fund.

Aniket Mittal

analyst
#50

In the finance statement your...

Operator

operator
#51

[Operator Instructions].

Aniket Mittal

analyst
#52

I am on the handset, am i audible?

Akhileshwar Singh

executive
#53

Yes, yes. Go ahead, but speak loud.

Aniket Mittal

analyst
#54

Sure. Sir, the depreciation and amortization line item seems to be a very big jump this quarter. Could you elaborate on that?

Sushil Sharma

executive
#55

In fact, we have gone from the impairment of some of the assets like the Sadla power project Khirvire power projects and Charanka wind power project. [indiscernible] with the capital investment was not up to the level and that's why as per the index 36, we have gone for the impairment of the assets. And total INR 138.70 crores has been booked to the impairment.

Aniket Mittal

analyst
#56

Okay. Sir, could you explain the difference of the revenue not being commenced to our expectations, why is that?

Akhileshwar Singh

executive
#57

The study for the -- in fact, if you go -- this value for this, mainly it is on account of the Sadla Wind power project. This tariff of the Sadla wind power project is INR 2.43 per unit, whereas during the period, it was commissioned in '18, '19, and the tariff was almost above INR 3. But somehow we were not having the PPA and we were compelled to sign the PPA with the Juvenile at the lower tariff. And that's why we have to go for the impairment loss. And after doing exercise, it is coming to INR 101 crore in the Sadla project. And it can be reverse in the next year. If situation will improve. And similarly, in Khirwire, the designed energy of the project was 85 million units, but it has not -- touched the energy. Maximum generation has come to 73 million units, and it is average generating per year 60 million units. That's due to less generation of the project during -- consistently during 5, 6 years. We have to take almost 10 years. You have to take the impairment. And that's why in Khirwire, it is coming to INR 34.88 crore.

Aniket Mittal

analyst
#58

Okay. The other question was around Buxar I understand earlier there were issues related to land acquisition that we were facing. What's the progress on that?

Sushil Sharma

executive
#59

We have roughly said that we are facing -- we were facing land issues. The land issue is still going on, but for this -- making this our project commissioning, we have gone for alternative arrangements. So with those alternative arrangements, we are -- we will be capable to commission the project.

Aniket Mittal

analyst
#60

Sir, could you elaborate on that what are the alternative that is going for? What's the amount of land that we still need to acquire, if any?

Sushil Sharma

executive
#61

Mainly this -- we were facing problem, this election's railway corridor and water corridor. For water corridor, government of Bihar has already given us the government land so that we can lay a pipeline on that government land. And for this railway corridor, we have taken land, some land from the railways and some land we are in the process of having agreement with some stakeholders. And with this -- this arrangement, we are able -- we will be able to run the project.

Aniket Mittal

analyst
#62

Okay. Okay. And lastly, sir, on the -- on the Arun-3 project, I think, timelines for them have kept on increasing. And I think there were some transmission-related issues that we are facing with. Could you elaborate a bit on that?

Sushil Sharma

executive
#63

Transmission related issues, actually, we -- this only issue in transmission line is the land acquisition. And we are constantly in touch with the -- even higher offices of Nepal Ministry. We are also in touch with the -- even we have requested even Prime Minister of Nepal to help us in acquiring to expedite the land acquisition process. So with these help from Nepal government, I think we will be able to commissions us on the [ starfish ] line, well in time.

Operator

operator
#64

The next question is from the line of Santhosh Kumar [indiscernible], an individual investor.

Unknown Analyst

analyst
#65

You see in the last conference call, which has been in February, you were given several targets for Buxar June '24, for Arun-3, February '25 and for Bikaner 1,000-megawatt by December 2024. Now I want to know whether there has been any slippage in these targets? And what is the renewed expectation of commissioning?

Akhileshwar Singh

executive
#66

Just answered these questions. Because of education by local farmers and disruption in our smart activities, this Buxar commissioning has been slipped to 3, 4 months from June. And because of challenge in dam area in this Arun-3 project. The commissioning target has slightly also slipped further. And in Bikaner projects, so we were facing some problem with the panels, local domestic panels. So with this -- now, I think the situation will improve by -- we'll be getting panel from June itself, and the commissioning will be done in quarter -- quarter 3 of this financial year of Bikaner 1,000 megawatts.

Operator

operator
#67

The next question is from the line of [ Arman ] from BlueSky Capital.

Unknown Analyst

analyst
#68

Am I audible?

Akhileshwar Singh

executive
#69

Yes.

Unknown Analyst

analyst
#70

In the previous call, you told a target of in 2026 around 12,000 megawatts. Right now in beginning, you told about 2,000 around, we will be installing in this financial year and next financial year. So that comes to calculation around 6,500. So which are those projects which we are -- which will bring operative index in this financial year and next financial year. And why the gap before we have the target of 12,000 megawatts and now it's only coming up to 6,500 megawatt, what's the reason behind that?

Akhileshwar Singh

executive
#71

In fact, [indiscernible] 1,000 megawatt to become a project and Arun-3 and [indiscernible] mainly because of the debt, we are lagging behind. But this slippage will be only for 5, 6 months. We will be covering almost 12,000 megawatt by pre-March '26.

Unknown Analyst

analyst
#72

Okay. And what are the reason that -- just a perspective is that we are seeing the appointment of CMD not for the years like for 4 years or 5 years has been going on for the 3 months. What is the reason for that? And when can we see a continuous standout for 5 years also for the CMD position?

Akhileshwar Singh

executive
#73

In fact, the CMD post election has already been done. And in the meantime, this charge has been given for the 3 months, and we are expecting within 3 months, the regular appointment will be issued for the national power.

Operator

operator
#74

The next question is from the line of Vipul Kumar Shah from Sumangal Investment.

Vipul Kumar Shah

analyst
#75

My question is regarding peak debt. You said we will reach 12,000 megawatts by March 2026. So at that time, what will be our peak debt.

Akhileshwar Singh

executive
#76

Peak debt.

Sushil Sharma

executive
#77

Can you repeat the question?

Akhileshwar Singh

executive
#78

He is asking about by March '26, What will be our peak debt? [indiscernible].

Sushil Sharma

executive
#79

Yes. We will be intimating -- separately after calculating our -- this debt provision.

Unknown Analyst

analyst
#80

No, my concern is it will be sizable amount and your project -- so many projects are facing delays in commissioning. So how will you service such a large debt when your -- current revenue base is relatively small in comparison to the projects SJVN undertaken.

Akhileshwar Singh

executive
#81

In fact, during the transaction, we had to pay the interest only, not the repayment of the principal amount. And that we are having sufficient projection. We will share also, in fact, it was on our website also. And the minority project in the renewable sectors, we are commissioning in next year. And from that, the revenue generations constitute, we are not seeing any problem in servicing what we take.

Unknown Analyst

analyst
#82

So 1 small suggestion, sir. Why don't you put a detailed presentation where each project when it will be implemented, plus what will be the coming requirement for each project. So that will be really helpful.

Akhileshwar Singh

executive
#83

In fact, if you require we'll share that, sharing this on the website for each project, it will be [indiscernible].

Unknown Analyst

analyst
#84

I think your peers already done it, project-wise schedule and -- so this is a suggestion, just think over it, sir.

Akhileshwar Singh

executive
#85

Okay, okay. We'll think over.

Unknown Analyst

analyst
#86

And whom should I contact regarding this debt figure?

Sushil Sharma

executive
#87

Pardon, pardon, can you repeat the question?

Unknown Analyst

analyst
#88

No, my question regarding debt you said, you will come separately on that. So I should take it with somebody in your finance department offline?

Soumendra Das

executive
#89

Okay. Okay. If I do so, and you can have my numbers compensates number, and you can put your questions so that I can get it replied by our finance department.

Unknown Analyst

analyst
#90

What's your good name, sir.

Soumendra Das

executive
#91

My name is Soumendra Das, Company Secretory.

Operator

operator
#92

The next question is from the line of Mohit Surana from Monarch Networth Capital Limited.

Mohit Surana

analyst
#93

Sir, am I audible?

Unknown Executive

executive
#94

Just please, speak loudly. Sure.

Mohit Surana

analyst
#95

Sir, my first question is with respect to the exceptional item in income statement. Are there INR 104 crore gain shown as an exceptional item for this quarter. Can you elaborate on that or the reason for that?

Akhileshwar Singh

executive
#96

In fact, [indiscernible] there was on arbitration award against the NASA having project. And that award was against us, we have provided it in the account and as per our accounting policy. But we have challenges in the court of law and the high court. And high court single judgment was in favor of us and the petitioner that other parties challenge it in the double bench and this was again decided in our favor. The provision we had made in the -- during the past, we have received -- reverse it, and now we have that content.

Mohit Surana

analyst
#97

Understood. Sir, you build an exchange notification of NTD and coming or JV with Indian Oil Corporation. Can you just elaborate on what kind of business do you intend do with them? I think this is related to green RTC?

Akhileshwar Singh

executive
#98

Yes, yes.

Mohit Surana

analyst
#99

Can you just give your thoughts on that.

Akhileshwar Singh

executive
#100

In fact, you see it in for consumer, they need a lot of power, and they have also target to become the net zero. And we've mentioned into the green sector. And with our collaboration, 50%, 50% joint venture partnership. We will be able to take more investment in the project. In hydro also and the renewal of plus the hydrogen sector also, we'll go jointly. There will be a lot of opportunity. And even in the sector of the EV charging, et cetera, we will be jointly collaborating for in and the ICL has a big size of balance sheet. It will be a very good secure both of us.

Mohit Surana

analyst
#101

So this JV is will be into green energy. Apart from that, but it will also be involved in power generation and green in hydrogen space as well.

Akhileshwar Singh

executive
#102

Yes.

Mohit Surana

analyst
#103

So any timeline when we can see some traction on the business activities in this JV?

Akhileshwar Singh

executive
#104

In fact, there is the process of taking -- before going, if there are any business ] activity, we have to take approval from the [indiscernible]. It will almost 2 to 3 months' time will be taken in that. And after that, we will start activity. We will the company. Then we will have -- after approval of the determined DTL will interpret the company and we'll start the activity. And they are very much interested in pump and storage also. And in fact, there are only be net zero with their venture in the renewable sector. we will be trying to invest like in other hydro projects, big hydro projects like Italian, we are having 3,000 megawatts, 3,097 megawatts in Arunachal, we can -- tried to develop it with their collaboration also.

Mohit Surana

analyst
#105

Understood, sir. Sir, regarding our renewable energy portfolio, solar and wind currently is around 405-megawatt on a combined basis, which is the operational capacity right now. So what is our target for on date, end of FY '25, '26 and '27 for the next 3 years? Only the similar revenue portfolio combined?

Akhileshwar Singh

executive
#106

Yes. In fact, 2,000 megawatts will be coming during the seventh years, '24, '25. Almost 1,000 megawatt against next year for '25 ,'26.

Mohit Surana

analyst
#107

Understood. And for '27, FY '27?

Akhileshwar Singh

executive
#108

For '27, I have to go work out this.

Sushil Sharma

executive
#109

But it will be more than 2 gigawatts, approximately 2 gigawatts every year we are I think approximately 2 gigawatts every year.

Mohit Surana

analyst
#110

Understood. Just 1 last question, sir. Just wanted to confirm. I think you already mentioned that the Arun-3 in Buxar project, both these projects will be commissioned by this year, right? So Arun-3 you mentioned quarter 2 of this fiscal year? And Buxar by either quarter 3 and quarter 4 of this fiscal year, is that correct?

Akhileshwar Singh

executive
#111

Arun-3 October, November next '25. In fact, not fiscal this fiscal year, Arun-3 we will be going to the second quarter of the -- third quarter of the next year, '25, '26. Buxar will be in second or third quarter -- in the third quarter or fourth quarter. First you run in third quarter, second you run in fourth quarter of current year.

Mohit Surana

analyst
#112

In this fiscal year, FY '25?

Akhileshwar Singh

executive
#113

Yes, yes. That will be '26, FY '26 -- '25, '26.

Mohit Surana

analyst
#114

Got it. Sir, just 1 last question. Regarding your regulated equity, sir, how much is the total regulated equity at this point? And how much would it be in FY '26?

Akhileshwar Singh

executive
#115

Hydro [Foreign Language] related equity amounted INR 3,372 crores. the thermal [Foreign Language] INR 3,132 crores. [Foreign Language] INR 1,494 crores.

Mohit Surana

analyst
#116

Solar is how much?

Akhileshwar Singh

executive
#117

INR 1,494 crores. Total INR 7,998 crores. [Foreign Language]. The total level is if we consider both operation and under construction, total the regulated equity is INR 15,458 crores.

Mohit Surana

analyst
#118

All right. And sir, in solar projects, do you earn an ROE of at least 12%. Is that correct?

Sushil Sharma

executive
#119

Yes.

Mohit Surana

analyst
#120

So, I mean, there have been...

Sushil Sharma

executive
#121

There may be a few projects where it will be 2 project, where it will be around 10%. But in few projects, it will be more than 15% [indiscernible] around 15% also. Average will be around 12%.

Operator

operator
#122

The next question is from the line of Bharani from Avendus Capital Private Limited. Please go ahead.

Unknown Analyst

analyst
#123

I just want to clarify that for the operational capacity, you mentioned the equity is INR 7,440 crores, right?

Akhileshwar Singh

executive
#124

Yes, yes.

Unknown Analyst

analyst
#125

So what is the split between equity in the renewables and regulated equity in hydro? How is this?

Akhileshwar Singh

executive
#126

INR 6,038 crore is in the hydro and solar wind INR 14,002 crore.

Unknown Analyst

analyst
#127

Okay. And of the 7.2 gigawatt pipeline of renewable if you mentioned, does it include the 2.2 gigawatts of projects that we won in FY '24?

Akhileshwar Singh

executive
#128

Yes.

Unknown Analyst

analyst
#129

Okay. And so all the equity required for the 7.2 gigawatts is what you just mentioned, which is INR 1,494 crores. Is that right?

Akhileshwar Singh

executive
#130

INR 15,438 crores.

Unknown Analyst

analyst
#131

That is the total equity you mentioned. I'm talking about the equity required for the 7.2 gigawatt pipeline.

Akhileshwar Singh

executive
#132

7.2 gigawatt. In fact, I think it is a lesser side because out of 7.2, 2,000 megawatts is under construction.

Unknown Analyst

analyst
#133

Okay. So the 15,438 include only for the under construction.

Akhileshwar Singh

executive
#134

Under construction.

Unknown Analyst

analyst
#135

Under construction excludes the ones -- where only tendering has happened.

Akhileshwar Singh

executive
#136

Yes.

Unknown Analyst

analyst
#137

Okay. So for the projects which are in the tendering stage, how much equity will be required, sir?

Akhileshwar Singh

executive
#138

I'll be intimating separately.

Unknown Analyst

analyst
#139

Okay. And what is your appropriate CapEx expectation in FY '25 and '26?

Akhileshwar Singh

executive
#140

Almost FY '25, INR 12,000 crores and almost similar amount or about INR 12,000 or INR 13,000 crores in the FY '26 also.

Unknown Analyst

analyst
#141

Okay. And my final question is, can you give the strength of this capacity addition in FY '25, like between hydro, thermal and renewables?

Akhileshwar Singh

executive
#142

In '24, '25, 1,320 megawatts to thermal. There is no capacity addition in the hydro. And total 3,818 megawatt including solar wind of 2,498.

Unknown Analyst

analyst
#143

2,498 plus 1,300 that's 3,700-odd for FY '25. Okay. Can you also give similar split for FY '26? Thermal, hydro and renewables.

Akhileshwar Singh

executive
#144

Hydro will be 1,176 and solar will be 4,330, totaling 5,506.

Operator

operator
#145

The next follow-up question is from the line of Mohit Kumar from ICICI Securities.

Mohit Kumar

analyst
#146

My question is on the 1,176-megawatt which you mentioned just right now, 700 megawatts is on the Arun-3, what is the balance?

Akhileshwar Singh

executive
#147

Against this '25, '26?

Mohit Kumar

analyst
#148

Yes, FY '26.

Akhileshwar Singh

executive
#149

This Dhulasidh and Luhri will be coming.

Unknown Executive

executive
#150

66-megawatt Dhulasidh and 210-megawatt Luhri-1 Hydro Electric?

Mohit Kumar

analyst
#151

210 plus 66, 276-megawatt, right? Sir, my second question is...

Unknown Executive

executive
#152

210 plus, [indiscernible].

Mohit Kumar

analyst
#153

Understood. I'll have a look. And the second question, any clarity on the timelines for PPF for the Nepal power plant?

Akhileshwar Singh

executive
#154

We are expecting we think this year we will be continue to as within 2, 3 months will be concluded.

Mohit Kumar

analyst
#155

Understood. My last question, do you think -- give an update on the [indiscernible] power plant. [indiscernible] do you think, you declare the tender, -- do you think you can tender anything in this fiscal?

Akhileshwar Singh

executive
#156

In fact this is in the survey investigation only. So we will be completing survey investigation or it will be in the process. This year, we are not going to have any tender for the construction or start of construction at [indiscernible].

Mohit Kumar

analyst
#157

You can expect something next year, sir?

Akhileshwar Singh

executive
#158

Next year we can....

Sushil Sharma

executive
#159

Next year, we can have -- because we have right now, we -- there are in the process of preparing DPR for 2,400-megawatt PSPs in Misoram. So it will take a 1.5, then after that, we will be able to award the position. And our joint venture with the Maharashtra also, there are a few projects where we can as there were already projects are under operation. And 1 dam is there we can have some renovation in our plant. Can go for the PSP. It will take some time, but -- it may be in the fiscal year '25, '26. '25, '26, we will have good numbers for PSPs.

Mohit Kumar

analyst
#160

And sir, do you are looking to award any regular hydro power plant in FY '25 -- FY 2025?

Akhileshwar Singh

executive
#161

FY '25, yes, Lower Arun 669-megawatt and the Italian project 3,097 megawatts.

Mohit Kumar

analyst
#162

Can you repeat the megawatt number again, sir?

Akhileshwar Singh

executive
#163

669-megawatt Lower Arun in Nepal. 6-6-9. And 3,097 megawatt Italian project in the Arunachal Pradesh.

Mohit Kumar

analyst
#164

So are the [indiscernible] tender out for these projects?

Akhileshwar Singh

executive
#165

Yes. Lower Arun within a month or 2, it will be a tender will be issued. And Italian, it will take at 6 months or almost 9 months or 12 months to issue the tender.

Mohit Kumar

analyst
#166

[indiscernible] awarded in a single package or some multiple packages now?

Akhileshwar Singh

executive
#167

Actually, in multiple stages.

Operator

operator
#168

The next question is from the line of Ragini Pande from Elara Capital.

Ragini Pande

analyst
#169

Sir, what would be your adjusted profit for quarter for FY '24 and for fiscal '24?

Sushil Sharma

executive
#170

[indiscernible] adjusted?

Unknown Analyst

analyst
#171

For this quarter and for fiscal '24.

Akhileshwar Singh

executive
#172

Adjusted, we are not -- adjusted profit, you are saying?

Unknown Analyst

analyst
#173

Yes, sir.

Akhileshwar Singh

executive
#174

But -- what do you mean adjusted profit. Can you please slightly elaborate?

Unknown Analyst

analyst
#175

Sir, after factoring in the nonrecurring items.

Akhileshwar Singh

executive
#176

In fact, these non-recurring item in the -- only recurring item is there. Non-recurring item.

Unknown Analyst

analyst
#177

Okay. What was the plant availability factor for your power plants -- for your hydro plants?

Akhileshwar Singh

executive
#178

Almost reaching to 100%.

Unknown Analyst

analyst
#179

Okay. And third, with respect to our new projects at this status of land and transmission availability?

Akhileshwar Singh

executive
#180

Always we are expecting to -- this transmission line, we are expecting that we will be completing the land acquisition in another 3 to 4 months. So we are -- as I earlier said, we are taking the matter to the highest authorities in the Nepal, whether it is IBM or this NEA or other key sector, even key factory we are requesting for this support on land acquisition, and they are fully committed that they will make some concerted efforts to give land to us from this private owners.

Operator

operator
#181

Ladies and gentlemen, we'll take this as a last question. I now hand the conference over to Mr. Rupesh Sankhe for closing comments.

Rupesh Sankhe

analyst
#182

We thank SJVN management for giving us an opportunity to host this call. We also thank all the investors and the analysts for joining this call. Good day and take care.

Sushil Sharma

executive
#183

Okay. Thank you. Thank you. Thank you, all of you.

Operator

operator
#184

On behalf of Elara Securities Private Limited, that concludes this conference. Thank you for joining us, and you may now disconnect your lines. Thank you.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete SJVN Limited transcript — plus 257,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to SJVN Limited earnings transcripts and 257,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in SJVN Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.