Steel Authority of India Limited (SAIL) Earnings Call Transcript & Summary

February 17, 2020

National Stock Exchange of India IN Materials Metals and Mining earnings 80 min

Earnings Call Speaker Segments

Operator

operator
#1

Ladies and gentlemen, good day and welcome to the SAIL Q3 FY '20 Earnings Conference Call hosted by IDFC Securities Limited. [Operator Instructions] Please note that this conference is being recorded. I now hand the conference over to Mr. Ashish Kejriwal. Thank you, and over to you, sir.

Ashish Kejriwal

analyst
#2

Yes. Thank you, Ayesha. Good morning, everyone. On behalf of IDFC Securities, we welcome you all for this Q3 FY '20 earnings call of Steel Authority of India. We are happy to host SAIL's management, which is represented by Mr. Amit Sen, Director of Finance, along with his team. So now I would request Mr. Sen for his opening remarks, and then we'll open the floor for question and answer. Over to you, sir.

Amit Sen

executive
#3

Good morning, everyone. First of all, I thank Mr. Ashish Kejriwal of IDFC Securities for arranging this investor con-call, and I welcome all of you to this investor con-call on the financial result of SAIL for the third quarter of '19/'20. So first, we'll give a bit about the market economy, the economy as a whole. The economy has not been in good shape globally and also in India. And in fact, third quarter has probably been the worst on many accounts for the steel -- whole economy as a whole, probably, and definitely for the steel industry. Economy was supposed to go at -- grow at about 7%, but now the growth rate has been projected to sub-5%. The index of industrial production in these 9 months has been only about 0.5% as opposed to around 5% in the 9 months of last year, which shows a slowdown across all sectors of the economy. But the prices and demand, which reached its lowest in the month of October, and from November, there were some signs of improvement. At least in November, the good thing was that the prices didn't fall any further. They didn't grew much, but it stayed more or less flat. And then there was some growth in prices in December. But the volume of sales started picking up in November/December, and the trend of this higher volume continues even as of now, even till February. And the uptick in prices, which started from December, actually, continues into January and February. So we have to see whether this growth sustains for the whole of Q4 that we need to see. But as of now, things are looking good. So the -- coming to sale, in particular, our sales volumes picked up in November and December, growth being about 37% over CPLY in November and were 48% over CPLY in December. The finished steel inventory, which had risen to about 2 million tonnes in October, we have managed to bring it down to about 1.3 million tonnes, which is roughly at the same level that it was on 31 March. The borrowings, which had crossed INR 51,300 crores at some point, again, in October, has been brought down by about INR 700 crores till 31 December. And we have posted a loss of about INR 430 crores BT in Q3, which is a reflection of all these things, but hopefully, going forward, the fourth quarter, we expect to be good. The steel industry is making a revival. The demand of steel is picking up. Prices have started firming up. The government has made many announcements in the budget, and we are very hopeful that they will lead to an increase in demand. One of them being that investment of INR 103 lakh crores in infrastructure over the next 5 years, that national infrastructure pipeline, which comprises of more than 6,500 projects across all sectors. So this should give a big boost to the steel demand. And there are developments in the waterways, railways, freight corridors, all of these consume steel. INR 107 lakh crore has been allocated towards the transport infrastructure for highways, economic corridors, coastal and road ports. Economic activity along the riverbanks has been energized. 100 more airports under the UDAN scheme has been announced. So if all these really happen, and we are hopeful that it will happen, then Q4 and the year ahead, the next year, 2021, is likely to be good. Coming to the results. The turnover in Q3 has been INR 16,405 crores. EBITDA was INR 1,184 crores, which roughly translates to INR 2,900 per tonne. PBT was minus INR 591 crores. And after ducking for deferred tax assets, the loss after tax comes down to INR 430 crores. There was -- there has been some improvements in the techno-economic parameters. And the coke rate has come down by 5%, energy consumption by 2.5%, BF productivity has gone up by 12%. CDI usage has also increased by 40%. Of course, this is subject to the availability of CDI. So we have some supply side issues with some of the suppliers, especially the Australian suppliers. So subject to availability of CDI, we are trying to maximize the CDI usage. And most of the plants are now in profit -- of course, now means, I'm talking of Q4, are in profit. So we hope this trend to continue. So that is the introduction from my side. Mr. Ashish, we can start the questions, if you want.

Ashish Kejriwal

analyst
#4

Ayesha, we can open the floor for Q&A.

Operator

operator
#5

[Operator Instructions] The first question is from the line of Amit Dixit from Edelweiss.

Amit Dixit

analyst
#6

I have 2 questions. The first one is on sales volume. Now since we have seen that sales volume has touched a rate of almost 4 million tonnes per quarter, so do we expect that in FY '21, you will cross around 16 million tonnes? Is it a fair expectation?

Amit Sen

executive
#7

We were 10.5 million tonnes till December.

Amit Dixit

analyst
#8

No, no. I'm talking about FY '21, since we have hit 4 million tonnes...

Amit Sen

executive
#9

Yes. '20/'21. '20/'21. '20/'21, definitely -- again, see, these are all subject to market conditions, the demand conditions, but the way things are improving, we're at 16 million tonnes, is what we're actually targeting in our internal plans, also.

Amit Dixit

analyst
#10

Okay. Sir, the second question is on debt level. If you look at your -- and interest cost, of course. So if we look at the debt and interest cost on Slide number, just a sec -- so in terms of quarterly debt, we have seen that quarterly debt has actually come -- has gone up, but your interest cost has come down.

Amit Sen

executive
#11

Yes.

Amit Dixit

analyst
#12

So I mean, just a little bit of light on that, how did it happened?

Amit Sen

executive
#13

Actually, yes. So the total borrowing has gone up because of the mismatch between the inflows and outflows. But because there has been a general decline in the rate of interest, the repo rates being reduced and the average rate of borrowing which has come down. So we've done a couple of things. We've been taking CPs, which have -- which we are getting at very competitive rates, the lowest believe -- I believe, is 5.23%. And also, we've been taking loans because we had our old loans, which were taken at a higher rate. So we took short-term and long-term loans at very competitive rates now and repaid those old loans at higher costs, thereby reducing the average interest cost of the total loan bucket. So that is how the total interest has come down, even though the borrowing, in absolute term, has gone up.

Amit Dixit

analyst
#14

Sir, just a follow-up question on that. Is this the -- is this our peak debt what we are seeing in Q3 end? And what would be the cost of funds, I mean, the interest cost now compared to Q3, let us say, or Q2?

Amit Sen

executive
#15

The average interest cost in Q3 has been 7.7%. And the debt, as of today, is INR 49,200 crores. The peak debt, I think I told you, had reached INR 51,300 crores at some point. And it's going to come down. And because now our realization has improved, there's a -- we have positive cash flows. So we are continuously repaying the debt. There is very little likelihood of that -- of the overall debt increasing beyond where it is today.

Amit Dixit

analyst
#16

Okay. So when you say Q3 interest cost was 7.7%, Q2, how much it was, the interest cost?

Amit Sen

executive
#17

It was 8.13%, yes.

Amit Dixit

analyst
#18

Okay, sir.

Amit Sen

executive
#19

And just one thing on this question that we are reducing our borrowings in a very planned way because from the money that we have, there are so many claimants for that money. We have to pay our vendors, we have to do this, and we have to also repay our loans. We are trying to balance that with those things. The problem is that one of our biggest -- actually, our biggest customer, railways, they have some budgetary constraints. I believe, their budget has been reduced to some extent, by 20%, and they are holding a lot of our receivables. That has put our financials into a bit of a pressure. Otherwise, had the railway payments come, as they used to come. Railway, historically, has been a very good paymaster. If the railway payments had come, our borrowings would have reduced drastically, but that is not very likely now, but still from our other collections, non-railway collections, we are able to reduce our borrowings.

Operator

operator
#20

The next question is from the line of Ritesh Shah from Investec Capital.

Ritesh Shah

analyst
#21

Sir, I have 2 questions. First was potential monetization of ore on back of the Orissa auctions, is there any specific update over here? And basically, a related question, how do you see the overall mining scenario from a demand-supply situation, specifically given increasing share of steel mills having their captive iron ore going forward?

Amit Sen

executive
#22

Regarding the -- your first question, the sale of iron ore. In Orissa, we have got the clearances. See, it actually -- if you remember, there were 2 circulars that were given -- that's were issued, 2 differentiations given to SAIL. One was to sell fresh ore up to a limit of 25% of the last year's production. And the other differentiation was to sell subgrade ore without any limit. So far, we've got clearance from the Orissa Government for selling the fresh ore. We have 2 tenders which have been uploaded. One auction is going to take place today for about 1 lakh tonnes of fresh ore. And there's another auction, I believe, day after tomorrow, which is for about 60,000 tonnes of fresh ore. We still haven't got the clearance for the subgrade ore, of which we have many tonnes -- some millions of tonnes. And clearances are yet to come from Jharkhand and Chhattisgarh governments. So that is where we stand now. Your second question was -- what was that regarding?

Ritesh Shah

analyst
#23

Sir, in the first question itself. Sir, this ore -- fresh ore, what you are referring to, it is from which mine, sir?

Amit Sen

executive
#24

From Bolani. The one that's going to happen today, the 1 lakh tonnes from Bolani, and the one that's going to happen day after tomorrow is from Barsua.

Ritesh Shah

analyst
#25

Bolani and Barsua. Okay. And sir, how is the benchmark prices set over here? Like is it IBM-notified price, which is a benchmark price and on that customers have to bid on?

Amit Sen

executive
#26

That is -- I don't know. I'm not sure about this one. I'll come back on this.

Ritesh Shah

analyst
#27

Okay. Sir, my second question was more pertaining to SAIL. In the press release, also, we have indicated about coke rates, CDI, specific energy consumption and blast furnace productivity improvement. Sir, I wanted to know what are the eventual targets over here? So something like coke rate is at INR 460 kg plus CHM. Sir, where do we see this, like, this 4 variable, say, 1 year down the lane or 2 years down the lane? I'm just trying to understand what sort of cost savings will actually come through once all the plants are stabilized?

Amit Sen

executive
#28

Is that -- target for coke rate -- target for total cost, is that your question?

Ritesh Shah

analyst
#29

Sir, if you can break it up. Sir, I think earlier, we used to give in the presentations increase in CC route, improvement in coke consumption rate, CDQ, conversion from OHF to BOF.

Amit Sen

executive
#30

So our coke rate target this year has been 419 kgs. And as against that, we are now at 460 kgs, right? So this is, again, subject to CDI, how much of CDI we are getting. So if we get more CDI, coke rate comes down. Our CDI target was 104 kgs per year. Whereas, actually, we've managed to get coal [Audio Gap] about 74 kgs is what we could get. This is subject to coal availability. So CDI has come down by 30 kgs from what we had planned. Coke rate has gone up, but we'll be tying up the coal requirement for 2021. In another couple of days, we're going to have the Empowered Joint Committee meeting with all the coal suppliers. And we'll be tying up, I believe, the entire quantity of PCI coal and the various grades of coal for next year. So next year, I don't think there'll be a shortage of PCI, and we should be able to reach our coke rate targets.

Ritesh Shah

analyst
#31

Right. Sir, can you indicate the other cost-saving measures that we had indicated, sir, something like coke purchase from external markets? Do we still do that? Secondly, you had earlier indicated about the increase in production-wide continuous casting route, conversion from OHF to BOF. Sir, if you can highlight on these 3 variables, probably then I'll join back the queue.

Amit Sen

executive
#32

We are not planning on buying coke from outside. We don't have any plans for that. We make our own coke. And the cost, of course, depends on the current -- and right now, the coke prices are quite low because the imported coal price is very low. So the last coal price that we had in the month of December was about -- imported coal price was about INR 12,500 per tonne. So that has started moving up now. But -- so based on that, our coke prices are fairly low. And the BF productivity, also, we are planning -- all our big furnaces are running at full capacity, the 3 big furnaces in Bhilai, Rourkela and [ HP ]. So that has improved the productivity. And what else you were saying? The BOF routes. The production...

Ritesh Shah

analyst
#33

Sir, the entire production is now BOF. We have entirely phased out OHF production?

Amit Sen

executive
#34

No, no. We haven't, we haven't.

Ritesh Shah

analyst
#35

How much is that right now, sir, via OHF?

Amit Sen

executive
#36

Just 1 minute. Actually, OHF, we are doing under compulsion because, in Bhilai, we admit, we have the THF condition, the OHF is actually THF. In Bhilai, we have the THF and we are forced to run that because the SMS-3 hasn't picked up so much. But only 1.5% of our production is coming from the THF route -- sorry, sorry, how much is that?

Unknown Executive

executive
#37

6.75%.

Amit Sen

executive
#38

6.75% of the production is coming from the twin-hearth furnace route. And as of now, about 92% of the production is there from BOF. But once the SMS-3 of Bhilai ramps up, already today, it has reached about 37 hearths per day, once it reaches 45 or maybe 50 hearths per day, the TH will be completely shut down, that route will be shut down. So we are keeping it -- we have to keep it open by force because the SMS-3 ramping up is taking a little time.

Ritesh Shah

analyst
#39

Okay. And sir, last one, as I said, obviously, the increase in continuous casting route, sir, how much is it right now? And how much do we intend to...

Amit Sen

executive
#40

It's about -- it's around 90%.

Ritesh Shah

analyst
#41

It's at 90%. And sir, it will be 100% by when?

Amit Sen

executive
#42

As soon as we phase out the THF. The THF route is the ingot route. Once the THF is phased out -- [Foreign Language] that cast ingots are also there -- we have some cast ingots which are there, which will continue, but the THF ingots will get paved out. So today, we are at 90% con cast, which will go up to how much?

Unknown Executive

executive
#43

Maybe 95%.

Amit Sen

executive
#44

Maybe 95% once the Bhilai THF gets shut down.

Ritesh Shah

analyst
#45

Okay. Okay, fine. Sir, I -- just one last question. Sir, what is the change in realization that we expect because of the change in product mix once everything is commissioned? And it is to a desired product mix? And any timeline over here?

Amit Sen

executive
#46

See, change in realization per tonne, how much that will increase, very difficult to say.

Ritesh Shah

analyst
#47

Sir, on status quo basis, basically assuming same HRC, CRC, GPC rates, basically what's our desired mix? So how much would it entail on savings? Because in one of the slides, we do give post ongoing expansion, we don't give a pie over there. So sir, if we had to assume, like, say, HR coil price goes down from 28% to 16% and the balance mix as it has been demonstrated, sir, what will be the hypothetical number? I'm just trying to understand what will be the profitability be for sales, say, in a year down the lane when everything is fine?

Amit Sen

executive
#48

This is very outdriven. This is very outdriven. See, we have lots of capacities, which are right now lying idle because of lack of demand. So once those things come on stream and the total product portfolio changes with rail production ramping up to maybe, say, 1.2 million or maybe 1.5 million in a year and the HR, CR and the galvanize and all the heavy wheels of IISCO and the medium structures of Durgapur, when all these come on stream, the realization will go up. I can't, actually, put a number of that, how much it will go up, it's very hard to say.

Operator

operator
#49

The next question is from the line of Vishal Chandak from Emkay Global.

Vishal Chandak

analyst
#50

My first question is with respect to Bhilai Steel Plant. What is the run rate currently? And how soon we can expect this to be at the peak 7 million tonnes capacity?

Amit Sen

executive
#51

7 million tonne capacity maybe towards the end of next year for the SMS-3. We have one conversion still to be commissioned in SMS-3, which is going to be commissioned in a few days from now. One casting is still left, where some change order will take place. And the rest will be ramping up. So maybe by end of -- towards the end of 2021, we should be able to reach the full capacity -- demand pertaining, we should be able to reach full capacity.

Vishal Chandak

analyst
#52

So we can fairly assume that by 4Q FY '21, you will be, on an annualized basis, running at 7 million tonne at Bhilai?

Amit Sen

executive
#53

Yes, we should. Yes.

Vishal Chandak

analyst
#54

Sir, my second question was with respect to the semis that we have. If I take a step back and look at the mix in 2009/'10 before we started on this massive expansion program, our semis was to the tune of 9% only. And today, we are hitting somewhere close to 21%. So what steps do we need to take over here to bring it down to, let's say, 10% level? Because I believe 9% to 10% is kind of an unavoidable, given our vast expansion that we have in the multiple locations that we have. How best can you optimize this? And what are the targets for that?

Amit Sen

executive
#55

See, the -- today, we are making -- selling semis, actually, because some of our finishing mills are not running at full capacity. For example, in the case of Bhilai, iron-rod mill has just been commissioned, right? And it will take some time for all the 4 lines of iron-rod mill to run at full capacity. Till it does that, the billet that we're producing in SMS-3 will become surplus. Similarly, in Durgapur, the billets that we -- the blooms and billets that we make in our caster, the out-stream offtake in the MSM is not there because of the poor demand of the MSM product, which is why there's a lot of bunching up of semi taking place. The increase in the percentage of semis is mainly due to a shortfall in the downstream finishing mills. So once that is taken care, once, -- again, I'm saying for everything the finishing mills is what we put out to the market. There has to be a market to absorb that product. So once we have downstream demand for our finished products, automatically, the semis will come down. Selling semis is not an ideal thought, we get very low price for that, we actually stand to lose. But the choice that we have now is given the low demand for the finished product, either with sorted production or we maintain the production at some level and then purposely get semis. That is the situation today. So if the demand picks up for the finished products, we have our finishing mills ready and running. It's only waiting for the demand to come. Once that demand comes, the quantity of semis and the proportion of semis will automatically come down.

Vishal Chandak

analyst
#56

Sir, in that case, would it be fair to assume that in the past, when the demand was strong, the downstream mills were still under the election and commissioning stage or maybe in the construction stage? Now that we are ready, going forward, as soon as we will have the demand scenario looking better, we would be able to monetize everything?

Amit Sen

executive
#57

Actually, in the past, that is pre-start of modernization, we had a certain balance between the semis -- the steel production and the finished production, right? There was a balance. And therefore, the semis was actually, the planned semis of maybe 8% to 9% ready for that. Now we have planned at a bigger scale. Again, there is a linkage between the amount of the steel that we make and the finished products that we make. That same linkage has been maintained in a greater scale -- in a bigger scale. The problem that is now happening is because of the shortage of demand in the finishing mills, which is causing the semis to bunch up. So like I said, once that problem is taken care, the semis quantity will automatically fall. Maybe, it'll come down to that 10% or 9% to 10%, as it used to be.

Vishal Chandak

analyst
#58

Got it, sir. And sir, just last, finally, as -- just picking up on the last question, on the cost reduction front, what are the major targets? Again, as you mentioned, I know coke is something that you are looking at by bringing -- by tying up on the CDI for next year. Is there anything further on the techno-economics that we can look at in terms of digitalization, preventive maintenance or anything which you can add on?

Amit Sen

executive
#59

See, we have our annual cost reduction targets where we set targets for all the plants for various parameters. Coke rate, of course, all the coal related parameters are the most critical for us because coal alone accounts for 40% of the cost. So these set of parameters are the ones which are most critical for us. But apart from that, there are many other techno-economic parameters which have a big impact on cost, one of them will be TMI, the total metallic input in SMS. So there are some plants, especially Bhilai, where the TMI is very heavy. Because of it, the cost of wood sheet in Bhilai is going up as compared to the other plants. So Bhilai has been given a target to reduce the TMI, specifically the scrap in the TMI. Similarly, the higher BF productivity, higher yield in the finishing mills, more higher acceptance. That means less of quality rejections. These are some of the targets which have -- which we have taken for the 2021 year. And if it goes through, there will be a substantial improvement in the costs.

Vishal Chandak

analyst
#60

Squeeze in. Your presentation says that even after expansion, the continuous cast route would only be 94% and will not be moving to 100%. So what would be the bottleneck over there, sir?

Unknown Executive

executive
#61

We have been in the casting -- Vishal this is [ Sai ]. Our -- in the casting routes in Durgapur and Bokaro steel plants, which have not been planned for any change under the current [indiscernible]. Maybe as we go forward and go for the future expansions, there, we can think about this. As of now, these are going to continue at Durgapur and Bokaro. So the ingot casting would continue for maybe that 5%, 6%.

Operator

operator
#62

The next question is from the line of Kamlesh Jain from Prabhudas Lilladher.

Kamlesh Bagmar

analyst
#63

Yes, sir. Would you please provide the NSR during the quarter? And what are the current levels as compared to the previous average?

Amit Sen

executive
#64

Can you repeat that question, please? There was some disturbance in the line.

Kamlesh Bagmar

analyst
#65

Sir, would you provide the realization NSR for the quarter? And what are the realizations currently as compared to previous quarter average?

Amit Sen

executive
#66

So the average NSR during the third quarter is INR 35,310 per tonne. And in Q2, it was INR 37,382.

Kamlesh Bagmar

analyst
#67

And what are the realizations, sir, currently, NSRs?

Amit Sen

executive
#68

What was that?

Kamlesh Bagmar

analyst
#69

Current realization, sir, NSR level?

Amit Sen

executive
#70

Current realization? So in February, this month, our average NSR has been INR 37,700.

Kamlesh Bagmar

analyst
#71

INR 37,000. So broadly, say, around INR 2,500, INR 2,400 improvement?

Amit Sen

executive
#72

Yes, improvement over average of Q3.

Kamlesh Bagmar

analyst
#73

Okay. And then sir, lastly, sir, in terms of coking coal, how much fall do you expect in the Q4 and what we have seen in the Q3, sir?

Amit Sen

executive
#74

No, no, no. There will not be any fall in Q4. Our imported coal price in December was INR 12,500; in January, it is INR 12,200. But now if you notice the last index, it has started moving up. See, as you know, there's a 2-month time lag between the FOB price, that means the price at which we pay when they ship hearths at Australia till the time the coal reaches the plant, right? So the benefit that we're getting now is for a price which is 2 months' old. Now the prices have started moving up. In fact, as of now, as of this month, it has touched $150. So from now onwards, the imported coal price is going to rise. This is -- INR 12,200 is probably the lowest price of imported coal, so far.

Kamlesh Bagmar

analyst
#75

Sir, but if we adjust this quarter for your price, like, say, devaluation in the case of rails and also that inventory revaluation of sublime. So if you see the EBITDA, then it would not be more than, like, say, around INR 47-odd crore for this particular quarter. So how do you see this...

Amit Sen

executive
#76

Why do you say INR 47-odd crores?

Kamlesh Bagmar

analyst
#77

INR 47-odd crore EBITDA for -- adjusted for these 2 items.

Amit Sen

executive
#78

It will be. I think the EBITDA is INR 1,186 crores in the third quarter.

Kamlesh Bagmar

analyst
#79

Yes. Sir, that's there, but majority part of that EBITDA is coming because of prior year price revisions and secondly, because of that sublime or low-grade iron ore revaluation.

Amit Sen

executive
#80

Yes. But that is how much? That is about INR 950 crores.

Kamlesh Bagmar

analyst
#81

Yes. So if I include that...

Amit Sen

executive
#82

So that still leaves about INR 250-odd crores as the EBITDA, not INR 40 crores.

Kamlesh Bagmar

analyst
#83

Yes. But your EBITDA is inclusive of other income, sir, I'm just including other income into that.

Amit Sen

executive
#84

[Foreign Language]. Okay. Great.

Kamlesh Bagmar

analyst
#85

So going forward, if I take INR 2,500 price improvement and the cost remaining the same, so we won't be seeing that margins, like say, going above INR 3,000 per tonne. Is that reading correct? And if we see the last year, like, despite having, like say, in pressure on the prices and all these things, we had done EBITDA per tonne of roughly around INR 5,000. So even compared to that, we won't be, like, say, in good operations, like, say, seeing all these improvements on the CDI, cost parameters, efficiency improvement, high scale even then we would be lower in terms of margins per tonne basis by around 50% year-over-year, sir?

Amit Sen

executive
#86

No, no. That is not correct. That is not correct. See, we are talking of a situation where the NSR has reached its bottom-most level. So as things improve, and not only the NSR, also when the volumes improve, our cost is going to come down. So there'll be a double impact on the EBITDA. The price going up, volumes going up, so the income going up. Price into volume, the income going up. And also the cost coming down. The EBITDA will increase in [ month end ].

Kamlesh Bagmar

analyst
#87

Okay. And sir, in terms of this price finalization. So it all has come through in this quarter? Or anything -- any portion is still left?

Amit Sen

executive
#88

No. The price revision of 2000 -- the rail price you're talking about?

Kamlesh Bagmar

analyst
#89

Yes, yes, yes.

Amit Sen

executive
#90

The rail price of 2018/'19 has been finalized in the quarter. One more revision which is yet to come, which would probably come in the fourth quarter, is the provisional price being given for this year, '19/'20. So we don't know how much that will be. That depends on the Railway Board, but that delta in the price is also going to come. And we'll be supplying, say, around 13 lakh tonnes of rails to railway this year. So some income from rail price revision is expected again in the fourth quarter.

Operator

operator
#91

The next question is from the line of Chintan Shah from Investec Capital.

Chintan Shah

analyst
#92

Sir, how should one look at the volumes for this year? And you did indicate 16 million tonnes for next year, sir, how should one build a bridge from this year's volumes to next year's volumes?

Amit Sen

executive
#93

This year, see, we are, I think, 10.2 million tonnes of sales till -- for these 9 months. And assuming we get about 4 million tonnes, 10.2? 10.28 or something?

Unknown Executive

executive
#94

10.5.

Amit Sen

executive
#95

10.5. 10.5 and another 4, so 14 million -- 14.5 million is what we are expecting this year. And next year, -- again, see, I keep on repeating this, it's very difficult for us to forecast the sales. It all depends on what the market -- how the market behaves and what is the demand in the market. We are hoping that the measures announced by the government will actually fructify and they will actually come on the ground, and there'll be some revival in the world market. If all these things happen, then our sales volume of 16 million tonnes with a good price is expected. So we are expecting that 16 million tonnes to happen. This year, we'll be probably ending at 14.5 million.

Chintan Shah

analyst
#96

Okay. Sir, this incremental 2 million tonnes will come from which segment? I guess it's CRC or plate mill, anything specific or railway orders, anything specifically that you're looking at?

Amit Sen

executive
#97

Yes. The Rourkela Hot Strip Mill has started. So we are hoping for some products from the Hot Strip Mill also in 2021. And also, these 2 mills -- the 3 mills in long which are now lying idle, the USM of IISCO, the MSM of Durgapur and the Bar & Rod Mill of Bhilai. So if the infrastructure projects are announced -- because these are all long product-driven investments, if those are announced, then hopefully, these 3 mills should be able to run to at least maybe near capacity.

Chintan Shah

analyst
#98

That's helpful. Sir, secondly, can you indicate how much is the inventory in the system and overall at Steel Authority?

Amit Sen

executive
#99

I don't know about the system, but in case of Steel Authority, our inventory now is about 1.3 million.

Chintan Shah

analyst
#100

And sir, how much was it last year?

Amit Sen

executive
#101

1.3 million. Just marginally higher than the 31st March figure.

Chintan Shah

analyst
#102

Okay. It is broadly flat, you are referring to?

Amit Sen

executive
#103

Yes. It had touched 2 million at some point. Now it has come down to 1.3 million.

Chintan Shah

analyst
#104

Okay. Sir, what we hear from the market is recently, there have been price declines of about INR 750 to INR 1,000 per tonne, this is on HRC side. The reason being demand is very weak. And what we understood is exports were one of the key variables, and hence, domestically, material was not available. And because of that, the steel mills had taken a price increase. Sir, what is your reading on the recent price increases, say, from Jan and the demand situation actually on ground when you look at it in conjunction with the inventory levels?

Amit Sen

executive
#105

You're talking of HRC or as a whole?

Chintan Shah

analyst
#106

Sir, I'm looking at, basically, commentary for both flats as well as long, sir, from you?

Amit Sen

executive
#107

See, HR-wise has been a good demand. So prices are going up, we are getting a better price in the export market than what we are getting domestically. So domestic prices have gone up. And the export prices are even more lucrative. So HRC is not that much of a problem. In the long product, some issue has come up. There has been some, I think, overstocking by the stockist. There is some fall in demand, and that margin has fallen in price in the long product.

Chintan Shah

analyst
#108

Okay. Sir, can you quantify the price increases that you have seen in HRC since Jan and for longs, what you indicated, we are seeing some decline? If you could please quantify it.

Amit Sen

executive
#109

Till Jan and Feb?

Chintan Shah

analyst
#110

Yes, sir.

Amit Sen

executive
#111

I think it was -- it had increased by about INR 1,000 in Jan. And just 1 second. About INR 1,600 increase was there in January over December, right? Hello?

Chintan Shah

analyst
#112

Yes, sir. INR 1,600 for HRC in Jan.

Amit Sen

executive
#113

For increase in the flat product, January over December. And February over January is another INR 1,500.

Chintan Shah

analyst
#114

Wow. Okay. And sir, for longs?

Amit Sen

executive
#115

For long, January over December was about INR 2,000.

Chintan Shah

analyst
#116

This is, again, an increase, sir? Because you -- for long, you said there was some overstocking and price fluctuation?

Amit Sen

executive
#117

No, no. That is now. That is just now. I'm saying January over December, the average NSRs of long had increased by INR 2,000. So for January, again, the increase has been INR 2,000. But now there is some reduction from this rate, from that high level there's going to be some reduction.

Chintan Shah

analyst
#118

Okay, okay, okay. Perfect. And sir, last question, sir. NMDC, they have a steel mill, the 3 million tonne in Nagarnar, which has been -- basically, they have been scouting for a buyer. Sir, is there any particular -- is there any distant remote possibility wherein Steel Authority can actually look at this asset, given we have the capability -- better capability to manufacture steel as compared to NMDC?

Amit Sen

executive
#119

I have no idea. This -- I don't think there's been any discussion on this.

Operator

operator
#120

The next question is from the line of Pinakin Parekh from JPMorgan.

Pinakin Parekh

analyst
#121

Yes. Sir, my first question is, sir, can you give us a sense of what is the current due from Indian Railways? And how has it changed from where it was in March 31?

Amit Sen

executive
#122

Right now, our dues is around INR 3,700 crores.

Pinakin Parekh

analyst
#123

And what was this earlier, sir? Because you said that one of the reasons why the debt number has not changed is because of the dues from the Indian Railways.

Amit Sen

executive
#124

It's normally -- I can't exactly tell you off-line what the figure in March was, but generally, the outstanding with Railway at any point of time is around INR 800 crores to INR 1,000 crores.

Pinakin Parekh

analyst
#125

Sure, sir. Sir, my second question is on the outlook of supplies next year and you mentioned the 3 downstream mills: the USM, the MSM and the Bar & Rod Mill. Now sir, what we understand is that over the last few years, one of the issues SAIL has faced is in the downstream mill stabilization and the demand outlook, and which is why we are not seeing any real benefits on the CapEx done. Now, sir, in terms of next year, what -- if demand revives, can this mills ramp up? Or are the end products from this mills geared for a very specific end market where the demand is not evolved at this point of time, and hence, it could be a few years before we see this mills ramp up? How should we look at this 3 downstream mills? Because apparently, this has been the main bottleneck over the last few years in terms of why that sales volume is not translating into margins.

Amit Sen

executive
#126

Okay. So these 3 mills, the USM, MSM and the BRM, they don't make any new products or a novel product, which has not yet been tested. They are making products which are already we are running. For example, the Universal Section and IISCO again, basically make the high-end structures: heavy beams, heavy angles, heavy channels, which are used for the projects like bridges or skyscrapers or things like that, heavy load-bearing stuff. That is what they make. MSM and BRM, they also make products which are widely used in the market. So it's not something which needs to be market-tested before it is sort of -- before things gear up. That is not the case. We make normal products of good quality of high -- like the TMT products. And it's a good quality products, things which are already being used. The only problem that we're having is the lack of demand. So if the infrastructure at the Sagarmala and the -- that -- the growth project, if all of these things goes through because we make long products in the end-to-end segment, from the lowest to the highest. We cover the entire portfolio. So if the infrastructure and the construction segment improves as we hope it will, then all the 3 mills should be able to run to capacity. There is no inherent problem in the mills, as such, nor do we have any new products which we need to test. They are existing products of good quality only waiting for demand. That's all.

Pinakin Parekh

analyst
#127

Understood. And sir, my last question is, if you look at the balance sheet, sir, and based on what visibility we have in terms of the demand, in terms of the prices, I mean, we assume that things don't materially change, would the debt number increase further in F '21? Or does the company believe that this debt number can come off? I mean we are just trying to understand over the next 1 to 2 years, how much debt can SAIL reduce if it can because we have only seen debt increase?

Amit Sen

executive
#128

See, first of all, I replied earlier that there is very little possibility of debt going up anywhere, right? The major expenditures that we're having on the CapEx that has mostly been incurred, now it has been tapering off. And -- so from the peak of INR 51,300 crores that we reached in October, now it's generally going to be downward, provided, of course, that our cash flows are properly balanced. There is very little possibility of debt going up anymore. But how much it will come down to will depend on how much collections we are able to meet. I believe, when the Railway budgetary constraint is removed from April, this big chunk of outstanding which they are holding will get liquidated, and we will use that and also the money that we are putting to get from the sale of fines and anything which are beyond our normal operations, we have earmarked for debt reduction. And even though I can't give a number, but definitely, we want to bring our debt down to as low as possible, keeping our debt to equity ratio at a very healthy level. There is a very little possibility of the debt going up anymore.

Pinakin Parekh

analyst
#129

Lastly, sir, given that the approvals are still waiting from the Jharkhand and Chhattisgarh government and the Orissa government has not given on subgrade fines, sir, for FY '21 at this point of time, sir, what is the amount of iron ore that the company expects to sell across its existing production and from its dumps because so far, the tenders are of very, very small quantities?

Amit Sen

executive
#130

Yes. So actually, the tenders that we've uploaded, if you noticed, is actually for 11 lakh tonnes, and which we've uploaded tenders for the Jharkhand mines also and for the Orissa mines also. And everywhere we've put a small guidance that this is subject to getting all the clearances. Out of this 11.6 lakh tonnes that we have uploaded, 1.6 lakh tonnes have materialized, which we are good to go ahead with. The quantity that we are looking at next year is about 20 million tonnes, 7 million tonnes from the fresh fines and 13 million tonnes from the old fines. That is what we are planning for next year.

Pinakin Parekh

analyst
#131

And sir, this will be split across all the 3 states, right, the 20 million?

Amit Sen

executive
#132

Correct. All the 3 states. I think there's very little old fines in Chhattisgarh, in the Bhilai mines. The old fines are mostly in the Jharkhand mines.

Pinakin Parekh

analyst
#133

Understood, sir. And sir, do you think that the state governments will give the approvals for this? Because I mean, such a large quantity of iron ore needs to be sold, I mean, how should we look at it? What is in it for the state government to give an approval quickly? Do they get any part of the revenue?

Amit Sen

executive
#134

They tend to get -- they get royalty on this. In fact, what I fail to understand is, why it is taking so much time.

Operator

operator
#135

The next question is from the line of Vikash Singh from PhillipCapital.

Vikash Singh

analyst
#136

Sir, my question pertains to this Railway price revision. So like you said that for FY '19, they have already finished. So...

Operator

operator
#137

Vikash, sorry to interrupt, I would request you to take the phone on the handset mode?

Vikash Singh

analyst
#138

Hello?

Operator

operator
#139

Yes.

Vikash Singh

analyst
#140

Is this better?

Operator

operator
#141

Yes, sir. You can go ahead.

Vikash Singh

analyst
#142

Yes. So this Railway revision, so if I look at the year starting to today's pricing, it has been lower. So like you said that it's on the provisional pricing, is it a risk that the pricing may revise on a lower side?

Amit Sen

executive
#143

Can you come back, what was on the lower side?

Vikash Singh

analyst
#144

So if I look at the average prices versus start of FY '20 versus today, it is lower. So like you said, that the provisional prices were set previously and you would be resetting the prices. So in terms of this Railway sales of 13 lakhs of rails, so isn't there a risk that the prices would revise exactly lower for this year?

Amit Sen

executive
#145

So first of all, I didn't get the question. Our prices are not lower than what they were. They have increased substantially. What I'm trying to say is, in this financial year, '19/'20, the Chief Adviser Cost, Ministry of Railway has finalized the prices for 4 years, '15/'16, '16/'17, '17/'18 and now '18/'19, right? The prices for these 4 years have been revised upwards, and we have got the differential in price, which we have taken to income. What I was trying to say in reply to a previous query was that what Railway Board does is, they also give a provisional price for the current year. So today, we are invoicing 2 rails at, say, X price, now Railway will give us a delta on the X, it will be X plus something. That plus something will add to our income in the fourth quarter. I'm not sure if I've understood your question, but this is what I would like to reply.

Vikash Singh

analyst
#146

Just a little clarification on this, sir. So the railway pricing, the provisional pricing which you get, is that price usually depends on the prevailing prices at that point of time? Or it's usually any price which you 2 mutually negotiate at?

Amit Sen

executive
#147

No, we don't mutually negotiate. First of all, the price is not provisional. The prices are final. So the price which the Chief Adviser Cost has finalized for the year '18/'19 is final for '18/'19. It is not going to be reopened.

Vikash Singh

analyst
#148

No, no. I was talking about FY '20. So basically, in FY '20, when you got the provisional, so I think, let's say, the X price, which you have indicated from Railway that was basically in which month? And would that be based on that month's average prices?

Amit Sen

executive
#149

No. Our system of pricing is different. What we do at the end of the year, once, say, for example, '19/'20 is over and our accounts are audited and finalized and adopted by the Board, then we submit our cost of production of rails or cost of sale of rails through the Finance Ministry. So they bet our cost and then they add a return on it. They add a return on the capital employed, plus return on capital employed is the price which they will fix for the year. The pricing is done each year, but it's done at the end of the year. And I think you asked me whether there is any possibility of the prices coming down. Not at all, but we will have substantial increase in price.

Vikash Singh

analyst
#150

Okay, sir. Okay, sir. Understood, understood. And sir, second question pertains to, so we are in line with our INR 4,000 crore CapEx guidance this year, can you just explain this next year, what could be the CapEx guidance? And this 7-million tonne of fresh iron ore, which we are talking about of selling, that could happen making iron ore requirement, right? So from which mines, actually, the additional production may come?

Amit Sen

executive
#151

So your first question was regarding CapEx. This year will be -- our CapEx guidance is INR 4,000 crores. Already, we've done INR 3,500 crores in January. So definitely, we are going to overshoot our target for '19/'20. In '20/'21, again, our CapEx guidance is INR 4,000 crores. But here, I have to say that the -- our expansion projects are almost over, right? So the CapEx will mostly come from the new projects that we are taking up. We haven't stopped investing. We've taken up many new projects. So this INR 4,000 crores that we are planning for '20/'21 is a mixture of realized payment for the existing contracts of the modernization, MEP, and also the payments to be made for the new projects, which are going to be -- which we are in the process now, which are -- these are the non-MEP projects, which are there. So that is INR 44,000 crores. That was your first question. Your second question was regarding the sale of iron ore fines.

Unknown Executive

executive
#152

Additional production.

Amit Sen

executive
#153

Additional production. So the circular of our Ministry was that whatever you produced in the previous month, 35% of that you can sell in the next month, and this is state-wise. It's not mine-wise. It's state-wise. For example, in Jharkhand if we have 4 mines, it is in totality. I can sell the entire quantity from 1 mine, also. So what we are planning, the 7 million tonnes of fresh mines that we're planning for '20/'21, it is spread over Kiriburu, Meghahatuburu, Barsua, Bolani, Taldih -- from Taldih. So from these 5 mines, we are planning to sell about 7 million tonnes of fresh fines. And the 13...

Vikash Singh

analyst
#154

It's over and above your requirement, right?

Amit Sen

executive
#155

Definitely, definitely. We'll not -- see, next year, our production is going to go up. Therefore, our iron ore requirement is going to go up. So the mines have to produce that and 7 million tonnes more in order to sell, then that is a challenge, but we are planning to do it.

Vikash Singh

analyst
#156

Okay. And sir, is there any logistical issues -- is it there any logistical bottlenecks in terms of evacuating the old dumps or this new inventory which you are talking about?

Amit Sen

executive
#157

See, the logistic issue is basically the visibility of rakes, which actually is an issue even though we are planning. So Railway has to give us rakes not only to evacuate these ore that we need for our production, which will go to the plant, Railways has to give us additional debt to move the machine, which we are going to sell. So this also is an issue. So there's logistic issue, availability of rakes, tying-up rakes with the deadweight, indenting of rakes that is also there.

Vikash Singh

analyst
#158

So have you got any assurance from Railway in terms of the rake availability as of now? Or...

Amit Sen

executive
#159

We have no assurances. We are taking up with the Railways. And -- but see, they have to run their rakes in the entire Indian railway network system. So we have to get from that only. The total number of rakes in India is finite, it's limited. From there, we have to manage. So that rake availability is actually an issue.

Operator

operator
#160

[Operator Instructions] The next question is from the line of [ Prashant Kumar from CIMB. ]

Unknown Analyst

analyst
#161

Sir, what were the export volumes in Q3? And also, in terms of export pricing relative to domestic pricing in Q3 versus what we are seeing right now, export pricing versus domestic prices in Q4, if you could throw some light, sir?

Operator

operator
#162

Ladies and gentlemen, the line for the management dropped, please stay connected while we connect them back. Ladies and gentlemen, thank you for patiently waiting. We have the management reconnected. Sir, you can go ahead.

Unknown Analyst

analyst
#163

Q3. And in terms of the realizations, sir, for the export volumes versus domestic realization, sir, in Q3?

Amit Sen

executive
#164

I missed your first part of your question. First part of your question we missed it.

Unknown Analyst

analyst
#165

Sir, I'll repeat my question. What were the volumes in Q3 -- for export volumes in Q3? And also, the export realizations vis-à-vis domestic realizations in Q3? And what kind of export volumes are we eyeing in Q4 and the realizations in export volumes versus domestic in Q4?

Amit Sen

executive
#166

So in Q3, our export sales was 356,000 tonnes, right, which was about 2 lakh tonnes more than the corresponding Q3 of '18/'19. And what else did you say?

Unknown Analyst

analyst
#167

In Q4, what can we expect, sir, volumes in exports?

Amit Sen

executive
#168

In Q4? See, right now, we are selling about 1.7 lakh tonnes each month. In January, we sold 1.7 lakh tonnes through export. So maybe, what, around 5 lakh tonnes because we're getting a very good price in export. So we're trying to maximize export. So maybe around 5 lakh tonnes we'll get export sales in Q4.

Unknown Analyst

analyst
#169

Sure, sir. That's what I also wanted to understand. In terms of Q3 export realization versus domestic realization, maybe it was at a discount. And in Q4, export realization versus domestic is probably at a premium. Is this understanding correct?

Amit Sen

executive
#170

Well, not in all products. In the flat products, in the HRC, we are getting an advantage. Just 1 second. See, actually, what -- see, overall, -- I mean, if you compare with domestic, there is a decrease, but the export NSR that we are getting on long products -- semis and long products is below our domestic, but in the flat product, we're getting a price better than domestic prices.

Operator

operator
#171

The next question is from the line of Abhijit Mitra from ICICI Securities.

Abhijit Mitra

analyst
#172

First question is on the coking coal import. Can you help me with the coking coal import figure for 9 month? And what are the plans to sort of reduce this number or sort of work on this number going forward?

Amit Sen

executive
#173

Just 1 second. See, just 1 second, I'll just give you the figure.

Abhijit Mitra

analyst
#174

Sure.

Amit Sen

executive
#175

Actually, there will not be a reduction in '20/'21 because we are planning for higher volumes and there is a constraint in the Indian coal, so the -- in terms of quantity, it will go up. So our coking coal imports in 9 months this year is 11.3 million tonnes.

Abhijit Mitra

analyst
#176

And how much have you taken from BCCL?

Amit Sen

executive
#177

From BCCL, our total [indiscernible] is about 1.2 million. Very small part is from us -- you can say about 1 million tonnes has come from BCCL because our own production is very low. 11.2 million, 11.3 million is what we've imported and about 1 million tonne of BCCL.

Abhijit Mitra

analyst
#178

Right, right. And going forward, BCCL supply is not ramping up at all, is it? I mean it's still not 100%.

Amit Sen

executive
#179

No, no, no.

Abhijit Mitra

analyst
#180

Okay, okay. And the pricing for them, that is also sort of yearly now? I mean what -- at what price levels do you have for BCCL right now?

Amit Sen

executive
#181

See it's decided yearly what is the price level of it. I'll come back to you on the price level. If the price has decided -- INR 8,700 [Foreign Language].

Abhijit Mitra

analyst
#182

INR 8,700. Okay, no worries. And second question is on this plant level profitability. So barring Bhilai, all other plants make big losses in Q3. Now I think over the years, we are seeing that to sort of extract profitability of the plants other than Bhilai, it's becoming more and more difficult. So are we planning some sort of additional restructuring or these price increases that we are seeing since December end, how many plants have become profitable if you can also give me a ballpark number, barring Bhilai?

Amit Sen

executive
#183

See, firstly, Bhilai was in not profit. Bhilai also was in loss. And profit, which you are seeing is after taking the impact of base price revision of the previous year. If you take current year performance, Bhilai also has been in loss. So in the 9 months, all the 5 integrated steel plants were in loss because of the huge mismatch between the prices that we were getting from the market versus our cost of production. But in Q4, all the plants are in profit.

Abhijit Mitra

analyst
#184

So on current prices, all the plants have done profitable?

Amit Sen

executive
#185

Yes. January, all the plants were in profit. February, it's expected to stay at the same level. March, if volumes increase, profits may go up. Q4, we will be in profit, definitely, and all the plants are expected to be in profit.

Abhijit Mitra

analyst
#186

Right. And any sort of measures that you are contemplating to sort of cement on this profitability? Or it's like be it on the employee side, be it on sort of the plans of selling away the 3 alloy plants? So any sort of move that we are seeing or you're discussing internally or being sort of it's upon by the government that can actually...

Amit Sen

executive
#187

So regarding the disinvestment of 3 plants, the tendering process is still on, and that is being handled by our transaction adviser, SBICAP, along with DIPAM and the Ministry. We are also a party to it, but we are not actively engaged in it. That is the way the DIPAM structure is made. That is going on, research. The sale of 3 plants is still on. It hasn't concluded yet. Regarding the cost reduction in the long term. So one is that cost reduction in the variable cost headwind, such as coal and power and refractory and roads and such that, for that, the targets are being set. All that is going on, that is the part of bookings. Regarding the fixed cost. So we are looking at the other elements of cost, not salary. Salary which is something which we cannot touch and which we are not planning also. We may come up with the VRS scheme for reduction of manpower and even, otherwise, there is a gradual reduction in our manpower quantities over the years. Around 3,000 to 4,000 employees are retiring and our manpower strength is coming down, but that translates into saving in the salary wages cost. Otherwise, in the other administrative cost, like security where we incurred huge expenses on the CIFL, that is one area we are looking at. And many other areas, repairs and maintenance, we are looking at. Some things we tend -- we plan to outsource. So a combination of reduction in the variable cost elements as well as in the fixed cost elements and through higher volume. These are the 3 things which we are targeting which will have an overall positive impact on the cost.

Abhijit Mitra

analyst
#188

Right. And just one last question on distribution of manpower. This -- so Orissa mines used to have huge manpower and hardly produced anything. I mean it's -- has that sort of been taken care of incrementally because of this reduction in employees that have happened over the last 4, 5 years? Or that is an area which still can be addressed?

Amit Sen

executive
#189

See, first of all, I really don't have the data with me, how many people we have in the Orissa mines, but there has been a reduction in the manpower across the board. So whatever the manpower was in the Barsua, Bolani mines would have come down. But what is the manpower today and how is that commensurate with production? I don't have the data with me now.

Operator

operator
#190

[Operator Instructions] The next question is from the line of Anita Khilnani (sic) [ Neeta Khilnani ] from B&K Securities.

Neeta Khilnani

analyst
#191

Sir, I wanted to understand the raw material cost increase in this quarter a little better. So what exactly is the inventory that we have booked in this quarter? Or probably the high-cost inventory, which has impacted our overall raw material costs?

Amit Sen

executive
#192

I didn't get your question. You're asking about the inventory of raw materials?

Neeta Khilnani

analyst
#193

Yes. Sir, basically, the change in stock has sort of declined, and we have booked some inventories in this quarter because of which our overall raw material cost increase is quite significant. Sir, I just wanted to understand, is it the high coking coal inventory which has been booked this quarter? Or maybe some high-cost finished steel inventory that we sold and the cost of which has come in, in this quarter?

Amit Sen

executive
#194

See I just -- I'll ask you to repeat the question once more.

Neeta Khilnani

analyst
#195

Sure. So sir, actually, I'm trying to understand the increase in the raw material costs which we look at in conjunction with the stock, the change in stock this quarter. So that together has gone up quite significantly. So I just wanted to understand what is the -- what inventory have you booked in this quarter?

Amit Sen

executive
#196

Okay. One is regarding the consumption, why does third quarter raw material consumption is higher than the second quarter. That is because of the higher level of production. So this a variable cost, it increases with higher level, right? That is as far as the production is concerned. And coming to the inventory of raw material, just 1 second. Inventory of raw material as compared to 31st March and 31st December, it has come down by more than INR 1,000 crores.

Neeta Khilnani

analyst
#197

Yes. So the change in stock, which is about INR 1,900 crores in this quarter, which has been booked in the P&L, this relates to some high-cost inventory, maybe coking coal inventory of the earlier quarters? Is that the correct understanding?

Amit Sen

executive
#198

Just 1 second, let me just have a look at the figures.

Neeta Khilnani

analyst
#199

Okay. Essentially, I'm talking about the change in stock figure of INR 1,939 crores.

Amit Sen

executive
#200

No, no, consumption is official. She is talking about inventory. The inventory has gone up. So we can't help with -- like go to your next question, I'll come back with the [ recent figures ] in just a second. Just 1 second. So stock accretion, depletion is INR 1,940 crores.

Neeta Khilnani

analyst
#201

Correct. So have we booked because our raw material -- yes.

Amit Sen

executive
#202

So actually, this INR 1,940 crores, this is depletion as compared to half year, INR 1,940 crores as compared to half year. This is because of the depletion in our finished goods inventory. Yes, finished goods inventory in the half year, it was about 2 million tonnes, 1.9-something, almost 2 million tonnes. So that has come down. That depletion is being reflected here.

Neeta Khilnani

analyst
#203

Okay. So will that also include the high-cost coking coal? Because...

Amit Sen

executive
#204

Coking coal is very less, actually. We hold hardly about 25 to 30 days stock of coal. So the quantity in stock has not gone up. In fact, the rate has come down. So in value terms, the inventory of coking coal of that is at high cost and imported coking coal has actually reduced because the same quality at a lower price. The inventory -- that stock deflation that INR 1,940 crores in Q3, this is mainly on account of reduction in the finished goods.

Neeta Khilnani

analyst
#205

Okay. Sir, my next question is, you mentioned some non-MEP CapEx as well. Now will this -- are there some major projects that you have in pipeline? Or if you can just elaborate on the nature of this CapEx?

Amit Sen

executive
#206

Actually, we have a number of projects going on. That MEP was one set of project, which we started around, say, 2009, '10, right, which has commissioned, and we are coming to the terminal payments of those projects. But we are not stopping there. We have many other projects which are in the pipeline. For example, the Hot Strip Mill of Rourkela, CRM 3 of Bokaro and SMS of Bokaro, the Steel Plant of Bokaro. So there are so many projects. They were not included in the MEP, but they are part of the -- in our projects, in the SAIL projects, they are called AMR projects. So we have 2 kinds of projects. We have the ABC projects, the modernization project, where we are coming to an end. And then we have the AMR project, which are increasing. So those CapEx will also come. And actually [indiscernible] of Bhilai. These are some of the projects, whose cash flow is going to be -- which have been planned in the next year, '20/'21.

Neeta Khilnani

analyst
#207

Okay. So for the next 2 years, will our CapEx be higher than INR 2,000 crores, including these and the...

Amit Sen

executive
#208

No, no. It will come down. INR 2,000 crores is what we are planning in '20/'21. In '21/'22, it's something around INR 3,700 crores that we have planned.

Neeta Khilnani

analyst
#209

Okay. And sir, so assuming if operating cash flow is sort of maintained at these levels, will we be able to repay about INR 3,000 crores of debt in FY '21? Is that...

Amit Sen

executive
#210

No, I already said that. Once our CapEx liability is coming down -- as you said, even maintaining our cash flows at the current level, with less burden of CapEx, we'll have more surplus left to service the loans.

Neeta Khilnani

analyst
#211

Okay. Sir, the last question, if I can squeeze in? Our CWIP which was about INR 14,000 crores as of September, now if you are saying the majority of the CapEx is completed, that should come down significantly, right?

Amit Sen

executive
#212

The CapEx -- the things which have been capitalized have already out of CWIP. So in this financial year, other than the Bar & Rod Mill of Bhilai, nothing new has been capitalized. So what is remaining in the CWIP are some of the ongoing projects, the Hot Strip Mill of Rourkela that was about some INR 3,500 crores, then the MSM of Durgapur, which is about INR 1,400 crores. So there are some big projects which are still appearing in the CWIP, which will get commissioned in -- maybe in Q4 or maybe in the first quarter of the next year.

Neeta Khilnani

analyst
#213

Okay. So accordingly, this will come down quite substantially in the next 1 to 2 quarters?

Amit Sen

executive
#214

Absolutely. The big -- there are actually a few big projects, which are in that INR 14,000 crores, maybe 3 or 4. And all of them are likely to be commissioned within the next 2 quarters, at least.

Operator

operator
#215

The next question is from the line of Amit Dixit from Edelweiss.

Amit Dixit

analyst
#216

Sir, 2 follow-up questions. One is on -- you indicated a while back on the NSR numbers, is it possible to split these NSR between flats and longs? Longs, of course, ex rails?

Amit Sen

executive
#217

Longs ex rails?

Amit Dixit

analyst
#218

Yes.

Amit Sen

executive
#219

That will take some working. I have the long, including rails.

Amit Dixit

analyst
#220

No, no. That's fine, that's fine, which is fine. No problem. You can choose to split either ways. It doesn't matter.

Amit Sen

executive
#221

You want exactly what figure?

Amit Dixit

analyst
#222

No. The flats and longs -- the split between flats and longs as far as NSR is concerned between Q2 and Q3?

Amit Sen

executive
#223

Between Q2, Q3 longs. So in Q2, our average NSR of longs including rails was INR 39,200 crores, and in Q2, our average NSR of flat products was INR 35,800 crores. In the third quarter, NSR of -- average NSR of long, including rails, INR 37,000 crores. And in Q3...

Unknown Executive

executive
#224

Q3 is INR 30,990 crores.

Amit Sen

executive
#225

And in Q3, the average of flat NSR is INR 33,700 crores.

Amit Dixit

analyst
#226

INR 33,700. Great, sir.

Amit Sen

executive
#227

And if you want excluding rails, then third quarter, which I said, was INR 37,080 crores, right, including rails, that becomes INR 31,000 crores excluding rails.

Amit Dixit

analyst
#228

Okay. And the corresponding number in Q2?

Amit Sen

executive
#229

In Q2?

Amit Dixit

analyst
#230

Yes.

Amit Sen

executive
#231

Q2, it was -- I said INR 39,200 crores including rails, so it becomes INR 33,400 crores excluding rails.

Amit Dixit

analyst
#232

Okay. Sir, my second question is, I missed probably the iron ore that you have put in for auction. So if you can just repeat, I mean, what tonnage you have put? There were 2 tranches, if I'm not mistaken if you can just repeat that point, please?

Amit Sen

executive
#233

Okay. So total the tender that we've uploaded for the Jharkhand group of mines and the Orissa group of mines is about 11.6 lakh tonnes, right? Hello?

Amit Dixit

analyst
#234

Yes, yes. Hello?

Amit Sen

executive
#235

11.6 lakh tonnes, of which 6.6 lakh tonnes is fresh fines and 5 lakh tonnes is separate fines from Goa. Now out of that, so far, we have clearance of only 1.6 lakh tonnes of fresh fines from Orissa, which we will be auctioning 1 lakh today and 1 lakh day after.

Amit Dixit

analyst
#236

So 1.6 lakh will be auctioned, right, today and...

Amit Sen

executive
#237

That is what? So 1 lakh tonne from Barsua, we'll be auctioning today and that -- 1 lakh tonnes from Bolani, we'll be auctioning today. And the 60,000 tonnes from Barsua, we'll be auctioning day after. And the other, say, 10 lakh tonnes or whatever, we still haven't got the clearance from the government.

Operator

operator
#238

The last question is from the line of Kamlesh Jain from Prabhudas Lilladher.

Amit Khimesra

analyst
#239

Amit here. Can you just throw some light on why the other income is jumped up...

Operator

operator
#240

Sir, sorry to interrupt. Amit, I would request you to please speak a little louder.

Amit Khimesra

analyst
#241

Can you put some light on why the other income has jumped so much in this quarter?

Amit Sen

executive
#242

Other income hasn't jumped so much. It was INR 277 crores in the second quarter, INR 265 crores in third quarter.

Amit Khimesra

analyst
#243

Other income...

Amit Sen

executive
#244

What is your figure? This is a figure I'm having Q2, INR 277 crores; Q3, INR 265 crores.

Amit Khimesra

analyst
#245

INR 186 crores, sir. For Q3 '19, it was INR 74 crores and for -- sorry, Q3 '20, it is...

Amit Sen

executive
#246

Q3 last year.

Amit Khimesra

analyst
#247

And last quarter, Q2, it was INR 158.7 crores.

Amit Sen

executive
#248

See actually, there is nothing -- anything -- it's probably that we've received, except that we have received dividends from some of our companies. So that is the only thing. Dividend we received in first quarter about INR 18 crores and -- which was not there in the second quarter. Mainly that INR 20 crores increase over Q2 has come from dividends.

Unknown Executive

executive
#249

And there is a certain increase which is not supposed to be there, so we have taken the benefit of that fee write-back.

Amit Sen

executive
#250

Hello? Hello?

Amit Khimesra

analyst
#251

Hello? Yes. Yes, sir. Hello?

Amit Sen

executive
#252

Hello?

Operator

operator
#253

Hello? Sir, you can go ahead.

Amit Sen

executive
#254

So I explained that -- see, in the second quarter, INR 158 crores -- it was INR 158 crores. And in the third quarter of this year, quarter-to-quarter, INR 158 crores to INR 186 crores which is how much? INR 30-odd crores, of which INR 18 crores has come from dividends and some liabilities write-backs have taken place. Some LD which was booked on the contractors have been taken to income. So a few things like that. So normal accounting only.

Operator

operator
#255

As there are no further questions, I would now like to hand the conference over to Mr. Ashish Agarwal (sic) [ Ashish Kejriwal ] for closing comments.

Ashish Kejriwal

analyst
#256

Yes. Once again, I would like to thank the management of SAIL to give us an opportunity to hold the call. And best wishes for your future endeavors, sir. Any closing remarks, sir?

Amit Sen

executive
#257

So it was a pleasure talking to all of you. I mean the questions that you ask help us to look better at the accounts and to analyze our accounts better. And I hope I've been able to answer your questions. If I haven't, you can -- you are free to call me back and take some more clarification. And just one thing I want to say, I've already mentioned that, that the Hot Strip Mill of Rourkela has started. The first coil was rolled on 30th January. So for us, it's a bit of a landmark. And we have lots of expectations from the new Hot Strip Mill. So hopefully, the benefit of that will come in the '20/'21 financial year. That's all.

Operator

operator
#258

Thank you. On behalf of IDFC Securities, that concludes this conference. Thank you for joining us, and you may now disconnect your lines.

Amit Sen

executive
#259

Thank you.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Steel Authority of India Limited transcript — plus 248,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Steel Authority of India Limited earnings transcripts and 248,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.