Steel Authority of India Limited (SAIL) Earnings Call Transcript & Summary
February 17, 2020
Earnings Call Speaker Segments
Operator
operatorGood day, everyone, and welcome to the SAIL Q3 FY '20 earnings conference call, hosted by IDFC Securities Limited. <<operator_script>> Kindly be aware that this conference is being recorded. At this point, I'll hand things over to Mr. Ashish Kejriwal. Thank you, and the floor is yours, sir.
Ashish Kejriwal
analystYes. Thanks, Ayesha. Morning, everybody. Speaking for IDFC Securities, we're glad to have all of you on this call covering Q3 FY '20 results for Steel Authority of India. It's a pleasure to have SAIL's leadership with us, represented by Mr. Amit Sen, Director of Finance, and his colleagues. So at this point I'd invite Mr. Sen to give his opening comments, after which we'll take questions from the floor. Sir, the floor is yours.
Amit Sen
executiveGood morning, everyone. To begin with, I want to thank Mr. Ashish Kejriwal from IDFC Securities for organizing this investor con-call, and I welcome all of you to this call regarding SAIL's financial results for the third quarter of '19/'20. So to start, we'll say a little about the market economy, the economy in general. The economy has not been in good shape, both globally and in India. And in fact, the third quarter has probably been the worst on many counts for steel -- for the economy in general, probably, and definitely for the steel industry. The economy was expected to grow at about 7%, but the growth rate is now projected at sub-5%. Industrial production over these 9 months has been only about 0.5%, compared with around 5% during the 9 months of last year, which shows a slowdown across all sectors of the economy. But prices and demand, which hit their lowest in the month of October, showed some signs of improvement starting in November. At least in November, the good thing was that prices stopped falling further. They didn't rise much, but they remained more or less flat.
Amit Sen
executiveAlso, prices did rise somewhat during December. Sales volume, though, began to recover in November/December, and that stronger volume pattern is still holding right now, all the way through February. And the price increase that got underway in December is in fact carrying on through January and February. So whether that improvement lasts across the entire Q4 is something we still need to watch. As things stand today, however, the picture looks favorable. Turning specifically to sales: our volumes recovered in November and December, with growth of roughly 37% over CPLY in November and 48% over CPLY in December. Finished steel inventory, which had climbed to around 2 million tonnes in October, we have succeeded in reducing to approximately 1.3 million tonnes, about the same level as on 31 March. Borrowings, which at one point in October had gone past INR 51,300 crores, have been reduced by roughly INR 700 crores as of 31 December. And we recorded a loss of around INR 430 crores BT in Q3, which mirrors all of these factors, though we are hopeful that the fourth quarter ahead will turn out well.
Amit Sen
executiveSteel is experiencing a comeback. Steel demand is on the rise. Pricing has begun to strengthen. There have been numerous budget announcements from the government, and we're quite optimistic those will drive demand higher. One of them is an investment of INR 103 lakh crores in infrastructure across the next 5 years, that national infrastructure pipeline, made up of over 6,500 projects spanning every sector. So that ought to deliver a substantial lift to steel demand. And there are developments in waterways, railways, freight corridors — all of these use steel. INR 107 lakh crore has been set aside for transport infrastructure covering highways, economic corridors, coastal and road ports. Economic activity along the riverbanks has been stimulated. 100 more airports under the UDAN scheme have been announced. So if all of this actually materializes, and we're hopeful it will, then Q4 and the year ahead, the coming year, 2021, is likely to be good. Turning to the results. Turnover in Q3 was INR 16,405 crores. EBITDA came to INR 1,184 crores, which works out to roughly INR 2,900 per tonne. PBT was minus INR 591 crores. And after accounting for deferred tax assets, the loss after tax drops to INR 430 crores.
Amit Sen
executiveSome improvement has occurred in the techno-economic parameters. The coke rate is down 5%, energy consumption is down 2.5%, and BF productivity is up 12%. CDI usage is also up 40%. Naturally, that depends on CDI availability. We do have some supply-side problems with certain suppliers, particularly the Australian ones. So, depending on how much CDI is available, we are attempting to maximize its usage. And most of the plants are now profitable — by now, of course, I mean Q4 — they are profitable. We hope this trend continues. That is my introduction. Mr. Ashish, we can begin the questions, if you would like.
Ashish Kejriwal
analystAyesha, let's go ahead and open the floor for questions.
Operator
operator<<operator_script>> Our first question comes from Amit Dixit at Edelweiss.
Amit Dixit
analystI’ve got 2 questions. The first one concerns sales volume. Now, given that sales volume has reached a pace of nearly 4 million tonnes per quarter, should we expect that in FY '21 you’ll exceed roughly 16 million tonnes? Is that a reasonable expectation?
Amit Sen
executiveThrough December, we hit 10.5 million tonnes.
Amit Dixit
analystNo, no — I mean FY '21, because we've already reached 4 million tonnes...
Amit Sen
executiveYeah. 20/21. 20/21. Definitely 20/21 — though again, look, all of this depends on market conditions and demand conditions, but given how things are improving, 16 million tonnes is what we're actually targeting in our internal plans as well.
Amit Dixit
analystAlright. Sir, my second question concerns the debt level — and interest cost as well, naturally. So when we look at the debt and interest cost on the slide, just one moment — regarding quarterly debt, what we've observed is that quarterly debt has in fact risen, yet your interest cost has moved lower.
Amit Sen
executiveYes.
Amit Dixit
analystSo I mean, could you shed just a little light on that — how did it happen?
Amit Sen
executiveYes, that's right. Total borrowing is higher due to the mismatch between inflows and outflows. But since interest rates have generally declined — repo rates have been cut and the average borrowing rate has fallen — we've taken a few steps. We've been issuing CPs, which we're getting at very competitive rates; the lowest, I believe, is 5.23%. We've also been taking loans, because our old loans had been taken at a higher rate. So we took short-term and long-term loans at very competitive rates now and repaid those older, higher-cost loans, which brought down the average interest cost across the total loan bucket. That's how total interest has come down even though borrowing, in absolute terms, has gone up.
Amit Dixit
analystSir, just a quick follow-up on that point. Is what we're seeing at the end of Q3 our peak debt? And what would the cost of funds be — I mean, the interest cost at this point versus, say, Q3 or Q2?
Amit Sen
executiveIn Q3, the average interest cost came in at 7.7%. As of today, debt stands at INR 49,200 crores. As I think I mentioned to you, peak debt had hit INR 51,300 crores at one point. It is going to decline. And since our realization has now improved, there's a — we have positive cash flows. So we keep repaying the debt on an ongoing basis. There is very little chance that the overall debt will rise above where it sits today.
Amit Dixit
analystSo you mentioned Q3 interest cost came in at 7.7% — what was that interest cost in Q2?
Amit Sen
executiveYes, that figure was 8.13%.
Amit Dixit
analystUnderstood, sir.
Amit Sen
executiveAnd just one point on this question: we're cutting our borrowings in a very deliberate manner, since the funds we have are claimed by so many parties. Vendor payments have to be made, we have these other obligations, and the loans must be repaid as well. We're trying to strike a balance among all of those. The trouble is that railways — our largest customer, in fact — face some budget limitations. Their budget, I believe, has been trimmed somewhat, by 20%, and they're sitting on a lot of our receivables. That has created a bit of pressure on our financials. Otherwise, if the railway payments had arrived the way they used to. Historically, railways have been an excellent paymaster. Had the railway money come in, our borrowings would have come down drastically, but that's not very likely at this point, yet even so, through our other collections — the non-railway ones — we're managing to bring our borrowings down.
Operator
operatorRitesh Shah from Investec Capital has the next question.
Ritesh Shah
analystSir, I have two questions. My first one concerns possible monetization of ore following the Orissa auctions — is there any particular update on that? And then a related question: how do you view the overall mining landscape in terms of demand and supply, especially considering that steel mills will hold a growing share of captive iron ore going forward?
Amit Sen
executiveOn your first question about the iron ore sale: in Orissa, the clearances are in hand. As you may recall, 2 circulars were issued — 2 separate allowances were granted to SAIL. The first permitted sales of fresh ore capped at 25% of the previous year's output. The second allowance covered subgrade ore with no cap at all. Clearance from the Orissa Government to sell the fresh ore has come through so far. 2 tenders have been uploaded. An auction for roughly 1 lakh tonnes of fresh ore takes place today. A further auction, I believe the day after tomorrow, covers about 60,000 tonnes of fresh ore. Clearance for the subgrade ore is still pending, and of that we hold many tonnes — some millions of tonnes. Clearances from the Jharkhand and Chhattisgarh governments are also yet to arrive. That is where we stand now. Your second question was — what was it about?
Ritesh Shah
analystSir, this is really about the first question. Sir, this ore — this fresh ore that you're talking about — which mine does it come from, sir?
Amit Sen
executiveFrom Bolani. The shipment taking place today — 1 lakh tonnes out of Bolani — and the one scheduled for the day after tomorrow comes from Barsua.
Ritesh Shah
analystBolani and Barsua. Alright. And sir, how are benchmark prices determined in this case? For instance, is there an IBM-notified price that serves as the benchmark, and then customers have to bid on that?
Amit Sen
executiveThat one—I honestly don't know. I can't say for certain on this. I'll follow up on it.
Ritesh Shah
analystAlright. Sir, my second question related more to SAIL. In the press release, we've also mentioned coke rates, CDI, specific energy consumption, and improvements in blast furnace productivity. Sir, I'd like to know what the eventual targets are here. So, for instance, the coke rate stands at INR 460 kg plus CHM. Sir, where do we see these, say, these 4 variables, 1 year out or 2 years out? I'm just trying to get a sense of what kind of cost savings will actually materialize once all the plants are stabilized?
Amit Sen
executiveAre you asking about the target for coke rate — the target for total cost?
Ritesh Shah
analystSir, could you break that out for us? Sir, in earlier presentations, I believe we would present things like the rise in the CC route, better coke consumption rate, CDQ, and the shift from OHF to BOF.
Amit Sen
executiveThe coke rate we were aiming for in 2021 was 419 kgs. Against that, we're sitting at 460 kgs at present, correct? So again, it depends on CDI — on the amount of CDI we receive. More CDI means the coke rate falls. Our CDI goal was 104 kgs per year. In practice, we only managed to secure <<inaudible>> roughly 74 kgs. That hinges on coal availability. So CDI ended up 30 kgs below plan. The coke rate has risen, but we will be locking in the coal we need for 2021. In a couple more days, the Empowered Joint Committee meeting is scheduled with all the coal suppliers. And we'll be tying up, I believe, the full quantity of PCI coal along with the various coal grades for the coming year. So I don't think PCI will be in short supply next year, and we should be able to hit our coke rate targets.
Ritesh Shah
analystOkay, sir, could you point out the remaining cost-reduction steps we mentioned — for instance, buying coke from outside markets? Are we still doing that? Also, you mentioned before the rise in output through the continuous casting route across production, and switching from OHF to BOF. Sir, if you could shed some light on those 3 items, I'll probably rejoin the queue after that.
Amit Sen
executiveWe have no intention of purchasing coke from external sources. There are no such plans on our side. Our coke is produced in-house. And the cost, naturally, is tied to current conditions — and at present, coke prices are quite low since imported coal prices are very low. So the most recent coal price we saw in December was roughly — the imported coal price stood at about INR 12,500 per tonne. So that has begun rising now. But — on that basis, our coke prices remain fairly low. And as for BF productivity, we are also planning — all of our large furnaces are operating at full capacity, the 3 big furnaces at Bhilai, Rourkela and HP. So productivity has improved as a result. And what else were you mentioning? The BOF routes. The production...
Ritesh Shah
analystSir, all of our production at this point is BOF, and OHF output has been fully eliminated?
Amit Sen
executiveNo, no. That’s not something we’ve done. We haven’t.
Ritesh Shah
analystWhat does that come to at the moment, sir, through OHF?
Amit Sen
executiveOnly 1 minute. Actually, OHF — we're operating that under compulsion, because at Bhilai, we acknowledge, the THF situation exists; the OHF is in fact THF. At Bhilai, the THF is there and we're compelled to keep it running since SMS-3 hasn't ramped up that much. Yet a mere 1.5% of what we produce comes via the THF route -- sorry, sorry, what figure is that?
Executive
executiveSix point seven five percent.
Amit Sen
executiveThe twin-hearth furnace route accounts for 6.75% of production. Right now, roughly 92% of output comes from BOF. But once SMS-3 at Bhilai ramps up — today it's already at about 37 hearths per day — once it gets to 45 or maybe 50 hearths per day, the TH will be shut down entirely; that route will be closed. So we're keeping it — we're forced to keep it open because the SMS-3 ramp-up is taking a bit of time.
Ritesh Shah
analystAnd sir, just one final question, as I mentioned earlier — clearly, the rise in the continuous casting route, sir, what is that figure at present? And what amount do we plan to...
Amit Sen
executiveThe figure is roughly 90%.
Ritesh Shah
analystIt's sitting at 90%. And sir, when will it reach 100%?
Amit Sen
executiveOnce the THF is phased out — and the THF route is the ingot route — that happens. When THF is gone, <<foreign_lang>> those cast ingots are also still in the picture; we do have some cast ingots that remain, and those will keep going, but the THF ingots will be phased out. So as of today, we're at 90% con cast, and how high will that go?
Executive
executivePerhaps 95%.
Amit Sen
executivePossibly 95% after the Bhilai THF is shut down.
Ritesh Shah
analystAll right, all right, that's fine. Sir, I have just one final question. Sir, once everything is commissioned, what shift in realization should we expect from the change in product mix? And is that toward the desired product mix? And is there any timeline on that?
Amit Sen
executiveLook, when it comes to the change in realization per tonne, how much that's going to go up — that's really hard to predict.
Ritesh Shah
analystSir, on a status quo basis — assuming the same HRC, CRC, and GPC rates — what's the mix we're aiming for, and how much savings would that involve? In one of the slides, we show things after the ongoing expansion, but there's no pie chart there. So if we had to assume, say, HR coil price falls from 28% to 16%, with the remaining mix as demonstrated, what would that hypothetical figure be? I'm just trying to get a sense of what profitability would look like on sales, say, a year out, once everything is fine?
Amit Sen
executiveThis is heavily outdriven. This is heavily outdriven. Look, we currently have a lot of capacity sitting idle due to a shortage of demand. So once those facilities start up and the overall product mix shifts as rail output ramps to perhaps 1.2 million or maybe 1.5 million within a year, and the HR, CR, galvanize, all the heavy wheels at IISCO, and the medium structures at Durgapur — when all of that comes online, realizations will rise. I honestly can't put a figure on how much they'll increase; it's very difficult to say.
Operator
operatorOur next question comes from Vishal Chandak, who is on the line from Emkay Global.
Vishal Chandak
analystLet me start with Bhilai Steel Plant. What's the run rate at present? And how quickly do you expect it to reach that peak capacity of 7 million tonnes?
Amit Sen
executiveFor SMS-3, that 7 million tonne capacity might come around late next year. There's still one conversion at SMS-3 awaiting commissioning, and it will be commissioned a few days from now. One casting remains, where a change order is going to happen. The remainder will be ramping up. So perhaps by the end of -- toward the end of 2021, we ought to get to full capacity -- assuming demand holds, we should get to full capacity.
Vishal Chandak
analystSo is it fair for us to assume that by 4Q FY '21, on an annualized basis, you'll be running at 7 million tonne at Bhilai?
Amit Sen
executiveCorrect — we should. Absolutely.
Vishal Chandak
analystRegarding my second question, sir, it concerns the semis we have. If I step back and examine the mix in 2009/'10, before we embarked on this huge expansion program, our semis amounted to just 9%. And at present, we're reaching approximately 21%. So what measures do we need to take here to reduce it to, say, a 10% level? Since I think 9% to 10% is somewhat unavoidable, given the extensive expansion we have across the many locations we operate in. How can you best optimize this? And what targets exist for that?
Amit Sen
executiveSo look — today, we're actually selling semis, and the reason is that a few of our finishing mills aren't operating at full capacity. Take Bhilai, for instance: the iron-rod mill has only just been commissioned, correct? And getting all 4 lines of that iron-rod mill up to full capacity is going to take some time. Until that happens, the billet we produce in SMS-3 turns into surplus. In the same way, at Durgapur, the blooms and billets from our caster aren't being taken off by the MSM because demand for MSM product is poor — that's why semis are piling up so much. The rise in the semis percentage comes mainly from a shortfall at the downstream finishing mills. So once that's sorted out — and again, I keep saying it, the finishing mills are what we put out to the market — there has to be a market that absorbs that product. So the moment we have downstream demand for our finished products, the semis will come down on their own. Selling semis isn't an ideal thought — the price we get is very low, and we actually stand to lose.
Amit Sen
executiveBut the decision we face right now is this: because demand for the finished product is low, either we go with sorted production, or we keep output at a certain level and deliberately produce semis. That's where things stand today. So if demand for the finished products rises, our finishing mills are ready and operating. All that's missing is demand. As soon as that demand arrives, the amount of semis and the share of semis will drop on their own.
Vishal Chandak
analystSir, so in that case, is it fair to think that previously, when demand was strong, the downstream mills were still going through election and commissioning, or perhaps still being constructed? And now that we're ready, going forward, once the demand picture looks better, we'd be able to monetize everything?
Amit Sen
executiveSo historically, before modernization began, we maintained a particular balance between semis — steel production — and finished output, correct? That balance existed. And so semis were, the planned semis of perhaps 8% to 9% were ready for that. Now we've planned on a larger scale. Again, a linkage exists between how much steel we produce and the finished products we produce. That same linkage has been preserved at a greater scale — on a bigger scale. What's happening now is due to weak demand at the finishing mills, which is making semis pile up. So as I said, once that issue is resolved, the semis quantity will drop on its own. Perhaps it will decline to that 10% or 9% to 10%, as was previously the case.
Vishal Chandak
analystUnderstood, sir. And sir, just to close out — following up on that last question about cutting costs, what are the main targets? Again, as you said, I know coke is one item you're examining by linking up on the CDI for next year. Is there anything else on the techno-economics side we can look at — digitalization, preventive maintenance, or anything more you could add?
Amit Sen
executiveLook, we do have annual cost reduction goals, and we assign targets across all the plants for a range of parameters. Coke rate — and really every coal-related parameter — matters most to us, since coal by itself makes up 40% of the cost. So those parameters are the critical ones for us. Beyond that, though, plenty of other techno-economic parameters carry a big cost impact, and one of them is TMI, the total metallic input in SMS. There are certain plants, Bhilai in particular, where the TMI runs very heavy. As a result, the cost of wood sheet at Bhilai is climbing relative to the other plants. So Bhilai has been handed a target to bring down the TMI, specifically the scrap within the TMI. In the same way, higher BF productivity, higher yield in the finishing mills, and more higher acceptance — meaning fewer quality rejections. Those are a few of the targets that we have taken on for the 2021 year. And if it goes through, costs will improve substantially.
Vishal Chandak
analystJust to fit this in — according to your presentation, even once the expansion is done, the continuous cast route would reach only 94% and won't get to 100%. So over there, sir, what would the bottleneck be?
Executive
executiveThis is Sai — Vishal, on the casting side. At the Durgapur and Bokaro steel plants, our casting routes haven't been slated for any modification under the present <<inaudible>>. Perhaps later, when we move toward future expansions there, we could consider it. For now, operations at Durgapur and Bokaro will keep going as they are. So ingot casting would stay in place for that 5%, 6%, perhaps.
Operator
operatorOur next question comes from Kamlesh Jain, who is on the line from Prabhudas Lilladher.
Kamlesh Bagmar
analystYes, sir. Could you share what the NSR was for the quarter? And what are the levels right now versus the prior average?
Amit Sen
executiveCould you say that question again for me? We had some interference on the line.
Kamlesh Bagmar
analystCould you give us the realized NSR for the quarter, sir? And how do current realizations compare with the average from the prior quarter?
Amit Sen
executiveDuring Q3, average NSR came to INR 35,310 per tonne, while in Q2, the figure stood at INR 37,382.
Kamlesh Bagmar
analystAnd sir, what are the realizations right now — the NSRs?
Amit Sen
executiveCould you repeat that?
Kamlesh Bagmar
analystWhat's the NSR level at present, sir?
Amit Sen
executiveOn the current realization side, during February — this month — the average NSR we've seen comes to INR 37,700.
Kamlesh Bagmar
analystSo overall, roughly speaking, an improvement of about INR 2,500 or INR 2,400?
Amit Sen
executiveYes, that’s an improvement over the Q3 average.
Kamlesh Bagmar
analystAnd then, sir, one last thing, sir: regarding coking coal, what kind of decline are you expecting for Q4, and what was it that we saw in Q3, sir?
Amit Sen
executiveNo, no, no — Q4 won’t see any decline. Our imported coal price stood at INR 12,500 in December; for January it is INR 12,200. But if you look at the latest index now, it has begun climbing. As you’re aware, there’s a 2-month lag from the FOB price — meaning what we pay when hearths are shipped from Australia — until that coal arrives at the plant, correct? So the benefit we’re enjoying today reflects a price that is 2 months old. Prices have now started to move higher. In fact, as of right now, as of this month, it has reached $150. So from this point forward, imported coal prices will increase. This INR 12,200 is likely the lowest imported coal price so far.
Kamlesh Bagmar
analystSir, but if we make an adjustment to this quarter for your price — for instance, the devaluation in rails and also that inventory revaluation of sublime — then, if you look at the EBITDA, it would be no more than, say, roughly INR 47-odd crore for this particular quarter. So how do you view this...
Amit Sen
executiveWhat makes you put that figure at around INR 47 crores?
Kamlesh Bagmar
analystEBITDA came in at around INR 47 crore, adjusted for those two items.
Amit Sen
executiveIt's going to be. I believe third-quarter EBITDA comes in at INR 1,186 crores.
Kamlesh Bagmar
analystYes, sir, that is there — but most of that EBITDA comes from prior year price revisions, and second, from the revaluation of that sublime or low-grade iron ore.
Amit Sen
executiveYes. But what does that amount to? That comes to roughly INR 950 crores.
Kamlesh Bagmar
analystYes. So if I include that…
Amit Sen
executiveThat still leaves EBITDA at around INR 250-odd crores, rather than INR 40 crores.
Kamlesh Bagmar
analystRight. But your EBITDA includes other income — I'm factoring other income into that figure.
Amit Sen
executive<<foreign_lang>>. All right. Excellent.
Kamlesh Bagmar
analystSo moving forward, if I take that INR 2,500 price improvement while costs stay the same, then we won't be seeing margins, say, climb above INR 3,000 per tonne. Is that reading correct? And if we look at last year, like, despite having, say, pressure on prices and all these things, we had done EBITDA per tonne of roughly around INR 5,000. So even compared to that, we won't be, like, say, in good operations, like, say, seeing all these improvements on the CDI, cost parameters, efficiency improvement, high scale, even then we would be lower in terms of margins per tonne basis by around 50% year-over-year, sir?
Amit Sen
executiveNo, no. That's not right. That's not right. Look, we're discussing a situation where NSR has hit its lowest possible level. So as things get better, and not just the NSR, but when volumes get better too, our cost is going to come down. So there will be a double impact on EBITDA. The price going up, volumes going up, so the income going up. Price times volume, the income going up. And the cost coming down as well. EBITDA will increase in month end.
Kamlesh Bagmar
analystOkay. And sir, regarding this price finalization — has it all come through in this quarter? Or is any portion still left?
Amit Sen
executiveNope. That 2000 price adjustment — the rail price you mean?
Kamlesh Bagmar
analystYeah, absolutely, that's right.
Amit Sen
executiveThe 2018/'19 rail price was finalized during the quarter. There's one additional revision still pending—it will likely arrive in the fourth quarter—and that's the provisional price being set for this year, '19/'20. So how much that will be, we don't know. It's up to the Railway Board, but that price delta is also going to come. And we'll be supplying roughly 13 lakh tonnes of rails to the railway this year. So we expect some income from the rail price revision again in the fourth quarter.
Operator
operatorOur next question comes from Chintan Shah, who is on the line from Investec Capital.
Chintan Shah
analystSir, how should we think about volumes for this year? And you mentioned 16 million tonnes for next year, sir — how should someone bridge from this year's volumes to next year's volumes?
Amit Sen
executiveSo this year, through these 9 months, we're at, I believe, 10.2 million tonnes of sales. And if we assume roughly 4 million tonnes come in — 10.2? 10.28, was it, or thereabouts?
Executive
executiveWe posted 10.5.
Amit Sen
executive10.5. 10.5 plus a further 4, which gives 14 million — 14.5 million is our expectation for this year. And for next year — again, as I keep saying, forecasting sales is extremely difficult for us. Everything hinges on how the market behaves and what demand looks like in the market. Our hope is that the measures the government has announced will truly take effect and actually get implemented on the ground, and that there will be some recovery in the world market. Should all of that materialize, then a sales volume of 16 million tonnes at a good price is what we expect. So we are anticipating that 16 million tonnes will happen. This year, we will probably finish at 14.5 million.
Chintan Shah
analystAlright, sir, which segment is that additional 2 million tonnes going to come from? My guess is CRC or the plate mill — or is it railway orders, or something specific you have in mind?
Amit Sen
executiveYes. The Rourkela Hot Strip Mill is now up and running. So we’re hoping that in 2021 we’ll also get some products from that Hot Strip Mill. And then there are these 2 mills — actually the 3 long-product mills that currently sit idle: IISCO’s USM, Durgapur’s MSM, and Bhilai’s Bar & Rod Mill. So if the infrastructure projects get announced — since all of these are investments driven by long products — if those projects are announced, then hopefully those 3 mills should be able to operate at least at maybe close to capacity.
Chintan Shah
analystThat's helpful. Second question, sir: could you give us a sense of how much inventory sits in the system, and what the overall figure is at Steel Authority?
Amit Sen
executiveI can't speak to the system side, but where Steel Authority is concerned, we're currently sitting at roughly 1.3 million in inventory.
Chintan Shah
analystAnd sir, what did that come to a year ago?
Amit Sen
executive1.3 million — only a touch above where we stood on 31st March.
Chintan Shah
analystSo overall it's pretty much flat — is that what you mean?
Amit Sen
executiveRight. At one point it reached 2 million, and now it's down to 1.3 million.
Chintan Shah
analystAll right. So, sir, what we're picking up from the market is that lately prices have dropped by roughly INR 750 to INR 1,000 a tonne on the HRC side. The cause is that demand is really weak. And from what we gathered, exports were among the main variables, which meant material wasn't available domestically. That's why the steel mills had pushed through a price hike. Sir, how do you read the recent price increases, let's say starting in Jan, and the demand picture as it actually stands on the ground when you factor in inventory levels?
Amit Sen
executiveAre you referring to HRC specifically, or the business overall?
Chintan Shah
analystSir, I'm essentially asking for your commentary on both flats and longs?
Amit Sen
executiveLook, demand for HR-wise has been solid. So prices are climbing, and in the export market we're fetching a better price than domestically. As a result, domestic prices have risen. And export prices are even more attractive. So HRC isn't much of an issue. On the long product side, a bit of a problem has emerged. There's been some overstocking, I think, on the part of the stockist. Demand has dipped somewhat, and that margin in the long product has come down in price.
Chintan Shah
analystAlright, sir, could you put a number on the price hikes you've observed in HRC since January, and for longs — what you mentioned, where we're seeing some softening — would you mind quantifying that as well?
Amit Sen
executiveUp through January and February?
Chintan Shah
analystYes, sir.
Amit Sen
executiveI believe it went up roughly INR 1,000 in Jan. And hold on just 1 second. There was an increase of about INR 1,600 in January compared with December, correct? Hello?
Chintan Shah
analystYes, sir. For January, HRC comes to INR 1,600.
Amit Sen
executiveWhen it comes to the increase in the flat product, comparing January with December. And then February versus January, that's another INR 1,500.
Chintan Shah
analystWow. All right. And sir, what about longs?
Amit Sen
executiveTaking January against December, the long version came in at roughly INR 2,000.
Chintan Shah
analystSo this is another increase, correct? Because for a long time, you mentioned there was some overstocking as well as price fluctuation?
Amit Sen
executiveNo, no. That's the current situation—just now. What I'm referring to is January versus December: the average NSRs for long had gone up by INR 2,000. So in January, once again, the rise came to INR 2,000. But at this point there's been a bit of a decrease from that rate—from that elevated level, some reduction is going to occur.
Chintan Shah
analystAll right, all right, all right. Great. And sir, one final question, sir. NMDC operates a steel plant — the 3 million tonne facility at Nagarnar — and they've essentially been searching for a purchaser. Sir, is there any specific — is there even a distant, remote chance where Steel Authority might actually consider this asset, given that we possess the capability — stronger capability to produce steel than NMDC?
Amit Sen
executiveI honestly don't know. As far as I'm aware, nobody has talked about this at all.
Operator
operatorMoving on, our following question comes from Pinakin Parekh, who is with JPMorgan.
Pinakin Parekh
analystYes. Sir, my first question is this: could you give us some sense of the amount currently due from Indian Railways? And how does that figure compare with where it stood on March 31?
Amit Sen
executiveAt the moment, our dues stand at roughly INR 3,700 crores.
Pinakin Parekh
analystAnd what was that earlier, sir? You mentioned that one factor behind the debt figure staying the same is the amounts owed by the Indian Railways.
Amit Sen
executiveTypically — I can't give you the exact March figure off the top of my head here, but in general, what's outstanding with Railway at any given time runs roughly INR 800 crores to INR 1,000 crores.
Pinakin Parekh
analystAlright, thank you. My second question concerns next year's supply outlook, and you brought up the 3 downstream mills: the USM, the MSM, and the Bar & Rod Mill. From what we understand, sir, one issue SAIL has dealt with over the last few years involves stabilizing those downstream mills and the demand picture — which explains why we aren't really seeing benefits from the CapEx that was spent. So, sir, looking at next year, if demand revives, could these mills ramp up? Or are the end products from these mills aimed at a very specific end market where demand hasn't developed yet, meaning it could take a few years before we see these mills ramp up? How should we think about these 3 downstream mills? Because this has apparently been the main bottleneck over the last few years as to why that sales volume isn't translating into margins.
Amit Sen
executiveAll right. So these 3 mills — USM, MSM and BRM — none of them turn out any new or novel product that hasn't been tested yet. What they produce is stuff we're already running. Take the Universal Section and IISCO again: they essentially make the high-end structural items — heavy beams, heavy angles, heavy channels — the kind that go into projects such as bridges or skyscrapers, heavy load-bearing applications. That's their output. MSM and BRM likewise turn out products that see wide use in the market. So this isn't something requiring market testing before it is, you know, before things gear up. That's not the situation. We make standard products of good quality — like the TMT products. And they're good-quality items, things already in use. The sole issue we're facing is the absence of demand. So if the infrastructure at the Sagarmala and the — that — the growth project, if all of these come through, since we make long products across the end-to-end segment, from the lowest up to the highest. We cover the whole portfolio. So if infrastructure and the construction segment pick up as we hope they will, then all 3 mills ought to be able to run at capacity.
Amit Sen
executiveNothing is fundamentally wrong with the mills themselves, and there aren't any new products we have to test. These are existing products of good quality, and they're simply waiting for demand. That's it.
Pinakin Parekh
analystGot it. Sir, my final question relates to the balance sheet. Based on the visibility we currently have on demand and pricing—assuming nothing changes in a material way—would the debt figure rise further in F '21? Or does the company think this debt level can be brought down? We're simply trying to get a sense, over the coming 1 to 2 years, of how much debt SAIL is able to reduce, if any, since so far we've only witnessed it going up.
Amit Sen
executiveLook, first of all, I said earlier that the chance of debt rising anywhere is very small, correct? The big spending we've been doing on CapEx has largely already been incurred, and now it's tapering off. So from the peak of INR 51,300 crores that we hit in October, it's basically going to head downward from here, assuming, of course, that our cash flows stay properly balanced. There's very little chance of debt climbing any further. But how far it comes down will hinge on how much collections we're able to meet. I believe that once the Railway budgetary constraint is lifted from April, that large chunk of outstanding they're holding will get liquidated, and we'll use that, along with the money we're putting in to get from the sale of fines and anything beyond our normal operations — we've earmarked that for debt reduction. And even though I can't give a number, definitely, we want to bring our debt down to as low as possible, keeping our debt to equity ratio at a very healthy level. There's a very small chance of the debt going up anymore.
Pinakin Parekh
analystAnd finally, sir, since we're still awaiting approvals from the Jharkhand and Chhattisgarh governments, and the Orissa government hasn't granted anything on subgrade fines, sir, for FY '21 as things stand right now, sir, how much iron ore does the company expect to sell — both from its existing production and from its dumps — given that, so far, the tenders have been for very, very small quantities?
Amit Sen
executiveRight. So if you look at the tenders we've put up, they actually cover 11 lakh tonnes, and we've uploaded tenders for the Jharkhand mines as well as the Orissa mines. And in every case we've added a brief note that this is contingent on receiving all the clearances. Of that 11.6 lakh tonnes we've uploaded, 1.6 lakh tonnes have materialized, and those we're good to move forward with. As for the volume we're targeting next year, it's roughly 20 million tonnes — 7 million tonnes coming from fresh fines and 13 million tonnes from old fines. That's what our plan is for next year.
Pinakin Parekh
analystAnd sir, that 20 million will be divided among all 3 states, correct?
Amit Sen
executiveRight. All 3 states. In Chhattisgarh, at the Bhilai mines, I'd say there are hardly any old fines. The old fines sit mainly in the Jharkhand mines.
Pinakin Parekh
analystGot it, sir. And sir, do you believe the state governments are going to grant those approvals? Because, I mean, such a big quantity of iron ore has to be sold — I mean, how should we think about that? What's in it for the state government to approve it quickly? Do they receive any share of the revenue?
Amit Sen
executiveThey typically receive — they receive a royalty on this. Honestly, the thing I don't get is why this is taking such a long time.
Operator
operatorWe’ll take our next question from Vikash Singh at PhillipCapital.
Vikash Singh
analystSir, my question is about this Railway price revision. So, as you mentioned, for FY '19 they've already completed it. So...
Operator
operatorVikash, sorry to cut in — could you please switch the phone over to handset mode?
Vikash Singh
analystHello?
Operator
operatorCorrect.
Vikash Singh
analystWould you say that's an improvement?
Operator
operatorYes, sir. Go right ahead.
Vikash Singh
analystYes. So with this Railway revision, if I look at the year starting from today's pricing, it's been lower. So as you mentioned, since it's on provisional pricing, is there a risk that the pricing could be revised to a lower side?
Amit Sen
executiveCould you go back to that—what was the part that came in lower?
Vikash Singh
analystIf we compare average prices now with where they stood at the beginning of FY '20, they're lower. So as you mentioned, the provisional prices had been fixed earlier, and you'd be resetting them. So regarding the Railway sales of 13 lakhs of rails, isn't there a risk that prices would be revised lower for this year as well?
Amit Sen
executiveLet me start by saying I didn’t follow the question. Our prices aren’t lower than before—they’ve gone up considerably. What I mean is this: during this financial year, '19/'20, the Chief Adviser Cost, Ministry of Railway, has finalized prices covering 4 years—'15/'16, '16/'17, '17/'18, and now '18/'19, correct? Those 4 years’ prices were revised upward, and we received the price differential, which we’ve recognized in income. In response to an earlier query, what I was attempting to explain is that the Railway Board also provides a provisional price for the current year. So as of today, we’re invoicing 2 rails at, let’s say, X price; Railway will then give us a delta on that X—it will be X plus something. That plus something will increase our income in the fourth quarter. I’m not certain I’ve grasped your question, but that’s the answer I’d like to give.
Vikash Singh
analystI just want a small clarification on this, sir. Regarding the railway pricing — that provisional pricing you receive — does that price typically hinge on whatever prices are prevailing at that moment? Or is it generally a price that the two of you negotiate with each other?
Amit Sen
executiveNo, there's no mutual negotiation involved. To start with, that price isn't provisional at all—those prices are final. So whatever price the Chief Adviser Cost has settled on for the year '18/'19 stands as final for '18/'19. It won't be reopened.
Vikash Singh
analystNo, no—I meant FY '20. So essentially, during FY '20, when you received the provisional rate, I think, let's say, the X price that you've mentioned came from Railway—which month was that in, basically? And would it be calculated using that month's average prices?
Amit Sen
executiveNo. We price things differently. At year-end — once, for instance, '19/'20 has wrapped up and our accounts have been audited, finalized, and adopted by the Board — we then submit our cost of production for rails, or our cost of sale for rails, via the Finance Ministry. So they bet our cost, and after that they add a return on it. They add a return on capital employed, and that return on capital employed plus the cost gives the price they'll set for the year. Pricing happens annually, though it's done at the close of the year. And I believe you asked me whether prices could come down in any way. Not at all — instead, we'll see a substantial price increase.
Vikash Singh
analystAlright, sir. Alright, sir. Got it, got it. And sir, my second question is about—so we’re aligned with our INR 4,000 crore CapEx guidance for this year; could you just explain what the CapEx guidance might be next year? And this 7-million tonne of fresh iron ore that we’re discussing selling—that could end up creating an iron ore requirement, correct? So from which mines would that additional production actually come?
Amit Sen
executiveTo address your initial question about CapEx: for this year, our guidance stands at INR 4,000 crores. We had already spent INR 3,500 crores as of January, so we will clearly exceed the target for '19/'20. For '20/'21, our CapEx guidance is again INR 4,000 crores. That said, I should note that our expansion projects are largely finished, correct? As a result, CapEx will mainly stem from the new projects we are undertaking. We have not halted investment. We have launched numerous new projects. Therefore, the INR 4,000 crores we are planning for '20/'21 combines realized payments on existing modernization and MEP contracts with payments still to come for the new projects — those currently in process, the non-MEP projects. So that amounts to INR 44,000 crores. That covers your first question. Your second question concerned the sale of iron ore fines.
Executive
executiveWe also have additional production.
Amit Sen
executiveOn the additional production side, our Ministry's circular said that 35% of whatever you produced during the previous month can be sold the following month, and that applies state-wise. It isn't mine-wise; it's state-wise. Take Jharkhand, for instance — if we have 4 mines there, it's looked at in totality. I can sell the whole quantity out of 1 mine as well. So our plan for the 7 million tonnes from fresh mines in '20/'21 is spread across Kiriburu, Meghahatuburu, Barsua, Bolani, Taldih — from Taldih. From these 5 mines, we intend to sell roughly 7 million tonnes of fresh fines. And the 13...
Vikash Singh
analystThat actually exceeds what you were asking for, doesn't it?
Amit Sen
executiveAbsolutely, absolutely. Look, our production will rise next year. Because of that, the amount of iron ore we need will also increase. So the mines need to deliver that, plus an additional 7 million tonnes for sale, and that is a challenge, but we intend to make it happen.
Vikash Singh
analystAll right. And sir, are there any logistical problems — any logistical bottlenecks when it comes to clearing out the old dumps or that new inventory you're referring to?
Amit Sen
executiveLook, the logistics problem really comes down to rake availability, and that's a real concern even with the planning we've done. So Railway needs to supply us with rakes not just for evacuating the ore required for our production, which heads to the plant — Railway also has to provide us with extra rakes to transport the machine we intend to sell. So that's another issue as well. So there's a logistics problem, rakes being available, rakes getting tied up with deadweight, and rake indenting is in there too.
Vikash Singh
analystSo at this point, have you received any assurance from Railway regarding rake availability? Or...
Amit Sen
executiveWe can't offer any guarantees on that front. We're currently in discussions with the Railways. But look, they need to deploy their rakes across the whole Indian railway network system. So that's the only place we can get them from. India's overall rake count is finite — it is limited. Out of that pool, we have to make things work. So rake availability is genuinely a problem.
Operator
operator<<operator_script>> Our following question comes from Prashant Kumar, who is on the line from CIMB.
Analyst
analystSir, could you tell us what export volumes were in Q3? And also, regarding export pricing compared with domestic pricing in Q3 versus what we're seeing at present — export pricing against domestic prices in Q4 — if you could shed some light on that, sir?
Operator
operatorLadies and gentlemen, we lost the connection to management, so please remain on the line while we bring them back. Ladies and gentlemen, thank you for waiting so patiently. Management is back on the line with us now. Sir, please go ahead.
Analyst
analystRegarding the realizations, sir, when comparing export volumes with domestic realization in Q3, what can you tell us?
Amit Sen
executiveI didn’t catch the first part of what you asked. We missed the first part of your question.
Analyst
analystSir, I’ll ask my question again. What were the volumes for Q3 — specifically, the export volumes in Q3? Also, how did export realizations compare with domestic realizations in Q3? And what export volumes are we looking at for Q4, along with export realizations versus domestic ones in Q4?
Amit Sen
executiveFor Q3, export sales came to 356,000 tonnes, correct, and that's roughly 2 lakh tonnes higher than Q3 of '18/'19. And what other point did you make?
Analyst
analystFor Q4, sir, what should we expect when it comes to export volumes?
Amit Sen
executiveTurning to Q4 — at present, our monthly sales volume is roughly 1.7 lakh tonnes. During January, export sales came to 1.7 lakh tonnes. So perhaps somewhere near 5 lakh tonnes, since export pricing is very attractive right now. That's why we're aiming to push export as much as possible. As a result, we expect to achieve export sales of around 5 lakh tonnes in Q4.
Analyst
analystYes, sir, that's the same thing I was hoping to get clarity on. Regarding Q3 export realization compared with domestic realization, perhaps it came at a discount. Then for Q4, export realization relative to domestic is likely at a premium. Have I got that right?
Amit Sen
executiveWell, that doesn't apply across every product. On the flat side, with HRC, we're seeing a benefit. Give me just 1 second. Actually, what — look, on the whole — I mean, against domestic, there's a decrease, but the export NSR we get on long products — semis as well as longs — sits below our domestic, while for flat product, the price we're getting beats domestic prices.
Operator
operatorAbhijit Mitra from ICICI Securities has the next question.
Abhijit Mitra
analystStarting with coking coal imports — could you give me that figure for the 9-month period? And what are the plans to sort of bring that number down, or work on it going forward?
Amit Sen
executiveGive me just a second here. Look, only 1 second, and I'll hand over that figure.
Abhijit Mitra
analystOf course.
Amit Sen
executiveTo be clear, we won't see a decrease in '20/'21, since we're anticipating larger volumes and Indian coal has a constraint, so where quantity is concerned, it will rise. Coking coal imports for the 9 months this year stand at 11.3 million tonnes.
Abhijit Mitra
analystAnd what's the amount you've drawn from BCCL?
Amit Sen
executiveRegarding BCCL, we have roughly 1.2 million in total <<inaudible>>. Only a very small portion comes from us — you could say around 1 million tonnes originated with BCCL, since our own output is quite low. The figure of 11.2 million, 11.3 million represents what we brought in through imports, plus about 1 million tonne from BCCL.
Abhijit Mitra
analystOkay, okay. And as we move ahead, BCCL supply isn't increasing at all, correct? In other words, it's still not at 100%.
Amit Sen
executiveThat's not right at all.
Abhijit Mitra
analystRight, got it. And the pricing for those is now on a yearly basis too, sort of? I mean, what — where do price levels stand for BCCL at the moment?
Amit Sen
executiveIt gets decided annually, what the price level for it will be. I'll get back to you regarding that price level. If the price has been set — INR 8,700 <<foreign_lang>>.
Abhijit Mitra
analystINR 8,700. Okay, no worries. My second question concerns profitability at the plant level. So leaving aside Bhilai, every other plant posted large losses in Q3. Now, I think what we've been seeing over the years is that extracting profit from the plants other than Bhilai is getting harder and harder. So are we planning some kind of further restructuring, or with these price increases we've seen since the end of December, how many plants have turned profitable — if you could also give me a ballpark figure, excluding Bhilai?
Amit Sen
executiveLook, first of all, Bhilai wasn't profitable. Bhilai was also running at a loss. And the profit you're seeing comes after accounting for the impact of the base price revision from the previous year. If you look at the current year's performance, Bhilai has been in loss as well. So across the 9 months, every one of the 5 integrated steel plants was in loss, given the enormous mismatch between the prices we were receiving from the market and our cost of production. In Q4, though, all the plants are in profit.
Abhijit Mitra
analystSo at today's pricing, every one of the plants has turned a profit?
Amit Sen
executiveYes. In January, every one of the plants was profitable. For February, we expect things to remain at that same level. In March, should volumes rise, profits could increase. In Q4, we will definitely be profitable, and all the plants are expected to be in profit.
Abhijit Mitra
analystRight. And what kinds of steps are you considering to lock in this profitability? Whether that's on the employee side, or on the plans to sell off the 3 alloy plants? So any kind of move that we're seeing, or that you're discussing internally, or that the government is sort of acting on that could actually...
Amit Sen
executiveOn the 3-plant disinvestment, the tendering process remains underway. Our transaction adviser SBICAP is handling that, together with DIPAM and the Ministry. We are a party to it as well, though we are not actively engaged in it. That is how the DIPAM structure is set up. That process is ongoing, research. The sale of 3 plants is still in progress. It has not concluded yet. On cost reduction over the long term. So one is cost reduction in the variable cost headwind, such as coal and power and refractory and roads and such that, for that, targets are being set. All that is going on, that is the part of bookings. On the fixed cost. So we are looking at the other elements of cost, not salary. Salary is something which we cannot touch and which we are not planning also. We may come up with the VRS scheme for reduction of manpower and even, otherwise, there is a gradual reduction in our manpower quantities over the years. Around 3,000 to 4,000 employees are retiring and our manpower strength is coming down, but that translates into saving in the salary wages cost.
Amit Sen
executiveBeyond that, on the remaining administrative expenses—security being one example, where we took on substantial costs related to the CIFL—that's an area we're reviewing. We're also reviewing plenty of other areas, such as repairs and maintenance. Certain functions we're inclined—we intend to outsource. So it's a mix of lowering the variable cost components and the fixed cost components, plus achieving greater volume. Those are the 3 levers we're focused on, and together they should have a positive overall effect on cost.
Abhijit Mitra
analystOkay, and one final question about how manpower is distributed. The Orissa mines, for instance, used to carry a very large workforce while producing almost nothing. Has that been dealt with gradually through the staff reductions that took place over the past 4, 5 years? Or is this still an area where more can be done?
Amit Sen
executiveLook, to start with, I honestly don't have the figures on hand for how many people are at our Orissa mines, though manpower has gone down across the board. So whatever headcount existed at the Barsua and Bolani mines would have decreased. But what the manpower stands at today and how that aligns with production — I don't have those numbers available right now.
Operator
operator<<operator_script>> Our following question comes from Neeta Khilnani of B&K Securities.
Neeta Khilnani
analystSir, I’d like to get a clearer picture of the raw material cost increase this quarter. What exactly is the inventory we booked in this quarter? Or is it likely the high-cost inventory that has affected our overall raw material costs?
Amit Sen
executiveYour question didn’t come through to me. Are you asking about how much raw material inventory we have?
Neeta Khilnani
analystYes. Sir, essentially, the movement in stock has kind of gone down, and we've recorded some inventory during this quarter, which is why the rise in our total raw material cost is fairly notable. Sir, I simply wanted to check: is it the high coking coal inventory that has been booked in this quarter? Or perhaps some high-cost finished steel inventory that we sold, with its cost having come through in this quarter?
Amit Sen
executiveI’m sorry—could you say the question again one more time?
Neeta Khilnani
analystYes, sir — what I’m really trying to get my head around is the rise in raw material costs, which we’re looking at together with inventory, meaning the change in stock for this quarter. Taken as a whole, that has increased pretty sharply. So I just wanted to clarify: what inventory have you recorded in this quarter?
Amit Sen
executiveAlright. First, on consumption — why is third quarter raw material consumption above the second quarter? It comes down to a higher production level. Since this is a variable cost, it goes up as the level rises, correct? That's the case as far as production goes. Then, on raw material inventory, just 1 second. Compared with 31st March and 31st December, raw material inventory has fallen by over INR 1,000 crores.
Neeta Khilnani
analystYeah, so the inventory movement of roughly INR 1,900 crores this quarter that's been recorded in the P&L — is that tied to some higher-cost inventory, perhaps coking coal stock from earlier quarters? Is that the right way to understand it?
Amit Sen
executiveHold on, just give me 1 second while I take a look at those figures.
Neeta Khilnani
analystRight, so basically what I’m referring to is the movement in the stock figure of INR 1,939 crores.
Amit Sen
executiveNo, no, consumption is official. She's referring to inventory. Inventory levels have risen. So we can't really help with — why don't you move on to your next question, and I'll come back with the recent figures in just a moment. Just 1 second. So stock accretion, depletion is INR 1,940 crores.
Neeta Khilnani
analystRight. So have we recorded it, given that our raw material — yes.
Amit Sen
executiveSo really, that INR 1,940 crores figure—that's the depletion measured against the half year, INR 1,940 crores versus the half year. The reason for this is the drawdown we saw in our finished goods inventory. Right, finished goods inventory at the half year stood at roughly 2 million tonnes, 1.9-something, close to 2 million tonnes. So it has declined. That drawdown is what shows up here.
Neeta Khilnani
analystAll right. So would the high-cost coking coal be part of that as well? Since...
Amit Sen
executiveCoking coal is quite limited, actually. We keep only around 25 to 30 days of coal stock. So the amount sitting in inventory hasn't risen. As a matter of fact, the rate has declined. So in value terms, the coking coal inventory is at a high cost, and imported coking coal has genuinely come down because the same quality is available at a lower price. That inventory — that stock deflation of INR 1,940 crores in Q3 — is mainly because of a reduction in finished goods.
Neeta Khilnani
analystAlright. Sir, my next question is this: you also brought up some CapEx outside of MEP. So will there be — do you have any big projects lined up in the pipeline? Or could you just go into more detail about what kind of CapEx this is?
Amit Sen
executiveWe do have several projects underway, in fact. That MEP was one category of project that we kicked off around 2009, '10, correct, and it has been commissioned, with us now reaching the final payments on those efforts. But that isn't where we stop. Plenty of other projects sit in the pipeline. Take, for instance, the Hot Strip Mill at Rourkela, CRM 3 at Bokaro, SMS at Bokaro, and the Steel Plant at Bokaro. So quite a few projects exist. Those weren't part of the MEP, yet they fall within our projects, within the SAIL projects, known as AMR projects. So two categories of projects exist for us. There are the ABC projects, the modernization work, where we're approaching completion. Then there are the AMR projects, which are growing. So those CapEx will come as well. And actually <<inaudible>> of Bhilai. These rank among the projects whose cash flow is going to be -- which have been planned for next year, '20/'21.
Neeta Khilnani
analystSo over the next 2 years, is our CapEx going to be above INR 2,000 crores, taking into account these and the...
Amit Sen
executiveNo, no. That figure will decrease. For '20/'21, we're planning INR 2,000 crores. For '21/'22, we have planned something around INR 3,700 crores.
Neeta Khilnani
analystAll right. So, sir, if we assume operating cash flow stays roughly around these levels, would we be in a position to repay roughly INR 3,000 crores of debt in FY '21? Is that...
Amit Sen
executiveNo, I already covered that. As you mentioned, once our CapEx liability starts declining, even if we keep cash flows where they are now, having a smaller CapEx burden means we'll end up with more surplus available to service the loans.
Neeta Khilnani
analystAll right, sir — may I fit in one final question? Our CWIP stood at roughly INR 14,000 crores as of September. Now, if you're saying most of the CapEx is done, that ought to drop quite a bit, correct?
Amit Sen
executiveRegarding CapEx, items that were capitalized are no longer sitting in CWIP. Therefore, during this financial year, apart from Bhilai's Bar & Rod Mill, no new assets have been capitalized. What remains in CWIP, then, consists of certain projects still in progress: the Hot Strip Mill at Rourkela, at roughly INR 3,500 crores, and the MSM at Durgapur, at approximately INR 1,400 crores. So a few sizable projects are still shown in CWIP, and those should be commissioned perhaps in Q4 or possibly in the first quarter of next year.
Neeta Khilnani
analystSo, with that in mind, this is going to drop pretty significantly over the coming 1 to 2 quarters?
Amit Sen
executiveSure. In that INR 14,000 crores, there are actually a few large projects — perhaps 3 or 4. And at least all of them should be commissioned over the next 2 quarters.
Operator
operatorOur following question comes from Amit Dixit, who is on the line from Edelweiss.
Amit Dixit
analystSir, I have 2 follow-up questions. The first concerns something you mentioned earlier about the NSR figures — could you break those NSRs down between flats and longs? Longs, naturally, excluding rails?
Amit Sen
executiveLongs ex rails?
Amit Dixit
analystYes.
Amit Sen
executiveThat’s going to require some work. I’ve got the long one, rails included.
Amit Dixit
analystNo, no, that's fine, that's fine, that's fine. No problem at all. You can split it either way. It doesn't matter.
Amit Sen
executiveCould you tell me precisely which number you're looking for?
Amit Dixit
analystNo. On the flats versus longs — how that split, specifically for NSR, landed between Q2 and Q3?
Amit Sen
executiveBetween Q2 and Q3 for longs. So in Q2, the average NSR we saw on longs, rails included, came to INR 39,200 crores, while flat products averaged INR 35,800 crores in that same quarter. For the third quarter, the average NSR on longs, rails included, was INR 37,000 crores. And in Q3...
Executive
executiveThe figure for Q3 comes in at INR 30,990 crores.
Amit Sen
executiveDuring Q3, flat NSR averaged INR 33,700 crores.
Amit Dixit
analystINR 33,700. That's great, sir.
Amit Sen
executiveAnd should you prefer to leave rails out, then Q3, as I mentioned, came to INR 37,080 crores, correct, with rails included; strip rails out and that figure drops to INR 31,000 crores.
Amit Dixit
analystAnd what was that same figure for Q2?
Amit Sen
executiveIn Q2?
Amit Dixit
analystYes.
Amit Sen
executiveFor Q2, I mentioned INR 39,200 crores with rails included, so excluding rails that figure comes to INR 33,400 crores.
Amit Dixit
analystAll right. Sir, for my second question, I likely missed the iron ore you put up for auction. So could you just repeat — I mean, what tonnage did you put? There were 2 tranches, if I'm not mistaken, so if you could just repeat that point, please?
Amit Sen
executiveAll right, so the tender we've submitted for the Jharkhand group of mines plus the Orissa group of mines comes to roughly 11.6 lakh tonnes in total, correct? Hello?
Amit Dixit
analystYes, yes. Can you hear me?
Amit Sen
executiveWe're looking at 11.6 lakh tonnes total, and that breaks down into 6.6 lakh tonnes of fresh fines plus 5 lakh tonnes of separate fines coming from Goa. From that, up to now, we've only cleared 1.6 lakh tonnes of fresh fines out of Orissa, and of that we'll be auctioning 1 lakh today and another 1 lakh the day after.
Amit Dixit
analystSo 1.6 lakh is going up for auction today, correct, and...
Amit Sen
executiveWhat is that? So today we'll be auctioning 1 lakh tonne from Barsua, and today we'll also be auctioning 1 lakh tonnes from Bolani. Then the 60,000 tonnes from Barsua will be auctioned the day after. As for the rest — say, 10 lakh tonnes or whatever — we still haven't received the government clearance.
Operator
operatorKamlesh Jain from Prabhudas Lilladher has the final question.
Amit Khimesra
analystAmit here. Could you shed some light on the reason other income has jumped up...
Operator
operatorSir, apologies for cutting in. Amit, could I ask you to speak up a bit, please?
Amit Khimesra
analystCould you shed some light on the reasons behind the sizable increase in other income during this quarter?
Amit Sen
executiveThe other income line hasn't really spiked. It came in at INR 277 crores during the second quarter, and INR 265 crores in the third quarter.
Amit Khimesra
analystOn the other income line...
Amit Sen
executiveWhat's your number? For Q2, I have INR 277 crores; for Q3, INR 265 crores.
Amit Khimesra
analystINR 186 crores, sir. In Q3 '19, that figure stood at INR 74 crores, and for — apologies — Q3 '20, it comes to...
Amit Sen
executiveThe third quarter of last year.
Amit Khimesra
analystAnd in the prior quarter, Q2, that figure came to INR 158.7 crores.
Amit Sen
executiveHonestly, there isn’t really anything else—probably nothing beyond what we’ve already received, aside from dividends from a few of our companies. So that’s the only item. Dividends we got in the first quarter came to roughly INR 18 crores, and that wasn’t present in the second quarter. The increase of INR 20 crores versus Q2 mainly came from dividends.
Executive
executiveThere's an increase that shouldn't really be present, so we've taken advantage of that fee write-back.
Amit Sen
executiveHello? Can you hear me?
Amit Khimesra
analystHello? Yes. Yes, sir. Hello?
Amit Sen
executiveHello?
Operator
operatorHello? Sir, go right ahead.
Amit Sen
executiveSo what I said was — look, during Q2 it was INR 158 crores, INR 158 crores. And in Q3 of this year, quarter over quarter, going from INR 158 crores up to INR 186 crores — how much is that? INR 30-odd crores, and out of that INR 18 crores came from dividends, plus some liability write-backs happened. Certain LD that had been booked against the contractors was taken into income. So items along those lines. Just regular accounting, nothing more.
Operator
operatorSince we have no more questions, I’d like to turn the conference back over to Mr. Ashish Agarwal (sic) Ashish Kejriwal for his closing remarks.
Ashish Kejriwal
analystYes. Once more, I want to express my appreciation to SAIL's management for giving us the chance to hold this call. And I wish you the best in your future endeavors, sir. Would you like to offer any closing remarks, sir?
Amit Sen
executiveIt was a pleasure speaking with all of you. The questions you raise help us take a better look at the accounts and analyze them more effectively. I hope I’ve been able to answer your questions. If not, feel free to call me back for further clarification. And one thing I want to mention — I’ve said this already — the Hot Strip Mill at Rourkela has started up. The first coil was rolled on 30th January. So for us, that’s something of a landmark. We have a lot of expectations from the new Hot Strip Mill. Hopefully, the benefit of that will come in the '20/'21 financial year. That’s all.
Operator
operatorThanks. That brings this conference to a close on behalf of IDFC Securities. We appreciate your participation, and at this point you can go ahead and disconnect your lines.
Amit Sen
executiveThanks.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Steel Authority of India Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Steel Authority of India Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Steel Authority of India Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.