Steel Authority of India Limited (SAIL) Earnings Call Transcript & Summary
November 9, 2020
Earnings Call Speaker Segments
Operator
operatorGood day, everyone, and welcome to the Steel Authority of India Q2 FY '21 earnings conference call, brought to you by DAM Capital Advisors Ltd. <<operator_script>> Kindly be aware that this call is being recorded. I'll now turn things over to Mr. Ashish Kejriwal of DAM Capital Advisors Ltd. Thank you, and the floor is yours, sir.
Ashish Kejriwal
analystYes, thank you, Levlyn. Good evening, everyone. It's a pleasure to have with us the management team from Steel Authority of India, represented by Mr. Amit Sen, Director of Finance, together with his colleagues. At this point I'd like to invite Mr. Sen to give his opening remarks, after which we can open the floor for Q&A. Over to you, sir.
Amit Sen
executiveGood afternoon, everyone. To start, I'd like to express my gratitude to Mr. Ashish Kejriwal from IDFC for organizing this conference call, and I welcome each of you to the investor call discussing SAIL's financial results for Q2 of 2021. As you're aware, Q1 was quite poor—we posted a loss of nearly INR 2,000 crores due to COVID's impact and the company's lockdown. Q2 was, naturally, much improved. Once COVID restrictions eased, July was actually somewhat unstable since the full effects of the slowdown were still present, so the slowdown continued to affect July. August and September performed reasonably well. Regarding our Q2 financial results, as you've already observed, we achieved EBITDA before exceptional items of INR 2,098 crores; including exception items, it was INR 2,320 crores. I expect you'll have questions about these exceptional items, so we'll address that further shortly. Profit before tax for Q2 stood at INR 610 crores, and profit after tax at INR 393 crores. Our <<inaudible>> has also been quite favorable. Long-term debt to equity at Q2's close was 0.75. Our EBITDA margin came in at roughly 14%. And EBITDA per tonne of saleable steel has been approximately 5,500 bps, which means it's nearly INR 39,000 crores.
Amit Sen
executiveDuring Q2, we saw volume increase roughly 1 million tonnes versus the same quarter a year earlier. However, EBITDA stayed essentially level, and the reason is that I'm now comparing the second quarter...
Operator
operatorPardon me for cutting in, sir — operator here. We can't pick you up clearly on our end. Your audio keeps cutting out. <<inaudible>>
Amit Sen
executiveAlright, I’m not sure exactly where the line dropped, but what I was covering is that Q2 was clearly a lot stronger than Q1. In Q1, we performed very poorly. So let me just go through the numbers again. We’re repeating this, and I think you’re already familiar with it. We posted a PBT of INR 610 crore, and in Q2 of this year we sold roughly 1 million tonnes more saleable steel than we did in Q2 of the prior year. Our NSR has stayed broadly flat because — I’m actually comparing the second quarter with the second quarter, since Q1 versus Q2 is hardly a fair comparison given that Q1 was an abnormal quarter. So in Q2 of last year, our EBITDA was declining. And in Q2 of this year, it has been holding up as far as the selling price goes, but the average across both quarters has been more or less identical on a per-tonne basis. Selling price per tonne has been almost the same. But on volume, we sold 1 million tonnes more than we did in the previous Q2 of last year. There was, however, a difference in the sales mix. So in the second quarter of last year, our export sales accounted for about 7% of total sales.
Amit Sen
executiveIn Q2, exports made up roughly 16% of sales. That pulled down our overall NSR, since export prices in this second quarter ran about INR 2,000 below where they were in last year's Q2. So export prices were weak, yet with demand lacking across the entire market, we had to ship a lot abroad. On top of that, we had certain export commitments taken on in Q1 that needed to be fulfilled. Taking all of this together, we reported that figure, which of course was also supported by volume and by imported coal prices. Imported coal prices have stayed quite low. That index stood at around $107 to $110. In September, naturally, it climbed to $124 for the full month. But once more, it has eased during October. As of today, it sits at $107 to $108 again. So we enjoyed a solid benefit from imported coal prices. We gained somewhat from the rising selling price. We benefited nicely from higher demand. That was the picture. In addition, we succeeded in selling some iron ore fines. So within our profit, we also have roughly INR 100-odd crores that we made from those iron ore fines sales.
Amit Sen
executiveThis is fresh fines that we sell. We still haven't gotten permission from Jharkhand to sell this subgrade material. But we sold roughly 5 million tonnes of fresh fines in Q1, and we're selling a lot right now. In October alone, we sold about another 5 million tonnes here — 5 lakh tonnes, 5 lakh tonnes during the month of October. So altogether, through October, we've sold around 11 lakh tonnes. That's where things stand as we move forward. We're quite hopeful for a healthy Q3 and a considerably stronger Q4. Q3 has gotten off to a good start. Our October results are in. I can't disclose them, but they're reasonably good October results. In November and December, though, we're anticipating even better results. The NSRs have gone up. Prices for our <<inaudible>> have risen. Imported coal prices remain low. And demand, once again, is very strong. A few products have stable prices that aren't rising. But broadly speaking, the other products are seeing upward movement. So we expect this benefit to carry through all of Q3 and all of Q4.
Amit Sen
executiveWe're fairly optimistic that by the time 9 months are done, we'll manage to close the gap on our losses and post a profit, since we're carrying roughly INR 1,374 crores of loss carryforward as of the end of H1. So we feel confident that by the close of Q3, those losses will be eliminated and we'll show a profit. And Q4 is going to be set aside purely for profit. As you'd expect, nothing else out of the ordinary. We're also expecting a pickup in construction and infrastructure after Diwali, given that the monsoons have ended. COVID-19 is of course still with us, but based on what our marketing team is telling us and what we've observed — and the government is also announcing plenty of construction and infrastructure projects — if all of that actually comes together, then perhaps after Diwali there should be an improvement in the construction sector. And since, as we mentioned, about 60% — over 60% — of our steel is sold into that single sector, any upside there will be a big help to us. Everything we've achieved so far has come without any growth in construction. So once growth in the construction sector arrives, we think it will keep contributing to both volume and price.
Amit Sen
executiveThat covers everything I wanted to say at the start. Does anyone have questions?
Operator
operator<<operator_script>> Our first question comes from Hardik Shah, who is calling in from SBI Mutual Fund.
Hardik Shah
analystYes. So could you just tell us what the CapEx is for this year and the next one?
Amit Sen
executiveFor 2021, our capital expenditure plan stands at INR 4,000 crores, and through September we've completed roughly INR 1,475 crores of that. The government, though, has asked us to raise — to attempt to raise — our CapEx for this year up to INR 4,800 crores. So we're looking into whether that can be done. As things stand, however, the target we've published remains INR 4,000 crores for this year.
Hardik Shah
analystAnd sir, roughly where do you expect the debt to go by the end of this year and then next year? So what we're seeing is a reduction from INR 55,000 crores down to INR 50,000 crores.
Amit Sen
executiveLook, our actual debt figure, once you adjust for IND AS, stood at INR 48,200 crores as of 30th September. The number shown on the balance sheet reflects the IND AS adjustment for lease and OpEx, but the real borrowing comes to INR 48,200 crores. That's INR 3,500 crores below where it stood at the start of the quarter. So compared with 30th June, our borrowing has come down by INR 3,500 crores. And this is supported by sizable collections during July and August, when collections reached roughly INR 6,400 crores in each of those months.
Hardik Shah
analystWould that reduction come out of working capital, or does it also apply to the long term?
Amit Sen
executiveIt's a combination of both. We're bringing down both, though the long-term ones are coming down more, since those carry a higher cost. We still hold long-term loans at about 7% plus, so our priority is paying those off first. On top of that, the share of long-term loans within the overall loan portfolio has gone down. Previously, long-term loans accounted for roughly 70% of total borrowing. Now, as of 30th September, that figure stands at about -- it's under 60%.
Hardik Shah
analystGot it. Last question. What are the scheduled repayments for this year and the next one?
Amit Sen
executiveWhat does that come to for this year and the one after?
Executive
executive<<inaudible>>.
Amit Sen
executiveAlright. So the repayment commitment we had for this year stood at INR 2,600 crores. Of that amount, nearly all of it has been settled, apart from INR 44 crores, and that INR 44 crores will be paid <<inaudible>>. With that done, our long-term repayment commitment comes to an end.
Hardik Shah
analystWhat about the following year?
Amit Sen
executiveNext year, our payment schedule comes to roughly INR 2,500 crores.
Operator
operatorWe’ll go to the following question, which comes from Amit Dixit at Edelweiss.
Amit Dixit
analystI’ve got 2 questions. The first one concerns other expenses. When I look at other expenses per tonne—on a per-tonne basis—that figure has dropped quite a lot, both year over year and quarter over quarter. So I just wanted to understand whether there’s a one-off in there, or whether you’ve put in place some sustainable cost-reduction initiatives. Any light you can shed on that would be great.
Amit Sen
executiveSo when you mention the second quarter, what are you comparing it against?
Amit Dixit
analystNo, I mean the second quarter — Q2 of FY '21 compared with Q2 of FY '20, or actually Q1 of FY '21. So looking at Q1 FY '21, I realize that — well, either comparison is unfair. But even on a Y-o-Y basis, other expense came in lower this quarter.
Amit Sen
executiveTurning to expenses — I'm reviewing the specifics right now. The bulk of the savings has come from stores and spares enhancement, plus there's a saving on power and fuel. On power and fuel, we've actually saved about INR 200 crores; and on stores and spares, roughly INR 80 crores. These categories account for the major savings, really just those. Power and fuel is the main one. That's where the saving originated. And one reason for it is that saleable steel — our production volume was a bit higher this Q2 compared with the prior Q. In Q2 of this year we produced 2 lakh tonnes more than in Q2 of last year, yet we produced that at lower expenditure, lower costs. Power and fuel accounts for the bulk of the saving. <<inaudible>> specific power consumption for our saleable steel has come down, the power <<inaudible>>.
Amit Dixit
analystAlright. The next question concerns guidance for sales volume. We’ve noticed that you also published October’s sales volume. Once again, it shows a really strong rise of 21% Y-o-Y. And you said you expect a considerably improved stretch ahead. So what guidance on sales volume could you provide for this year and perhaps for next year?
Amit Sen
executiveOur sales of saleable steel.
Amit Dixit
analystYes, sir.
Amit Sen
executiveRight. So actually, the number we have in mind — our internal goal — is roughly 15.5 million.
Amit Dixit
analystIs this regarding fiscal year '21?
Amit Sen
executiveFor FY '21, yes. The target figure is 15.5 million. And we'll most likely hit it, since what we need to sell per month comes to roughly 1.55 million — something we can manage easily and that's under control.
Amit Dixit
analystAnd next year, sir — what's the outlook there?
Amit Sen
executiveAs for next year, I'm not sure. Our original goal, in fact, was 18 million. But then — so for next year, I think we'll aim to run at full capacity right from the start. And if we achieve that and demand is there to support it, our capacity stands at 18 million tonnes of saleable steel. Since we were negatively affected in Q1 — and not only Q1, but the first 4 months — we had to lower our sales target. However, next year, provided no disruptions like that occur — and if the market allows it — then we ought to be able to sell 18 million.
Operator
operatorOur following question comes from Rahul Jain, who is calling in from Systematix.
Rahul Jain
analystI also want to circle back to the capacity question. As your presentation shows, you've nearly finished the CapEx of roughly INR 60,000 crores plus. So should we take it now that we're fully commissioned, and that nothing stands in the way of hitting 20 million tonnes next year?
Amit Sen
executiveSorry, I missed that — what was it you said at the end?
Rahul Jain
analystNo, sir. So, have we finished the CapEx program, or is there something we should...
Amit Sen
executiveYes, we do. Actually, there are a few small items still remaining. However, the single major piece that remains is the fourth billet caster, which is going to add roughly 1 million tonnes to our steel capacity. That one hasn't been finished yet, since the caster's configuration needs to be changed. I believe I went over this the last time as well. It was originally designed as a beam blank caster, and we're going to convert it into a bloom-cum-beam blank caster. So we're in negotiations with the vendor. Once we settle on the price, then -- so that's the only item -- the major one still outstanding for us, plus a few small balancing items that also exist. But where capacity is concerned, 1 million tonnes is still pending due to the core project.
Rahul Jain
analystAnd sir, were you saying that the CapEx is finished as well, or will that take place once this is done?
Amit Sen
executiveWhich one?
Rahul Jain
analystRegarding the raw material expansion, that...
Amit Sen
executiveNo, no, expanding raw materials — look, we set a target of INR 10,000 crores for raw material. And honestly, we've done very little there because of various clearances. So one thing I can share with you at this moment is that, I think 2 or 3 days ago, we received the Stage-II Forest Clearance for one of the leases at Gua Mine. We have a mine in Jharkhand known as Gua Mine. It has 2 leases: the Duargaiburu lease and the Topailore lease. The Duargaiburu lease, the larger of the two, had its expansion stuck because we lacked the Forest Clearance and the final back-and-forth between the Jharkhand State Government and the <<inaudible>>. So I believe on Friday — Thursday or Friday, I think — the Jharkhand State Government has at last recommended the Stage-II Forest Clearance for Gua Mine, because <<inaudible>> it was in agreement regardless. So once that clearance comes through for the Duargaiburu lease of Gua, then at Gua Mine there is massive capacity expansion that we're planning. So that we'll be able to begin once the clearance is in hand. So that's one positive development that has taken place very recently.
Amit Sen
executiveOn top of that, we're also contracting for some MDOs at a few of the other mines, such as Taldih and a couple more, so that's all in good shape. So there, output...
Rahul Jain
analystOkay, so that INR 10,000 crore CapEx — that won't be happening? I mean, has a new figure come up for it at this point?
Amit Sen
executiveLook, with this MDO, the spending isn't on us — the Taldih MDO I mentioned, right. It's an MDO, and the whole CapEx sits with them. Well, roughly INR 115 crores has to come from us for certain power supply projects, just to bring the power to a particular point. That's it. But that's what...
Rahul Jain
analystDo you have a revised figure in mind at this point for the CapEx, compared with the actual INR 10,000 crores?
Amit Sen
executiveNo, no, no — that INR 10,000 crores is still there, since we've only used roughly INR 1,700 crores out of it. So the INR 10,000 crores stays intact — and I believe we don't even have all the approvals yet. So the Gua matter will likely be sorted out soon, toward the end of the year. But we also still have approvals pending at Chiria. Chiria holds our largest steel deposit. So that is...
Rahul Jain
analystYes. But I read somewhere that this might not actually come about, since there’s so much forest surrounding the area and that kind of thing.
Amit Sen
executiveEven so, we’re continuing to pursue that, and the mines are there and — sorry, the forest is there. Forest <<inaudible>> or whatever. But work is ongoing. Our ministry is even getting involved in it. Not only that. I believe more than. They’re also speaking with MOEFM — definitely all the other agencies as well. So our CapEx for mines hasn’t changed. It’s still INR 10,000 crores.
Rahul Jain
analystAnd then lastly, sir, how much iron ore do we expect to sell this year and next year? Are there any targets you can share?
Amit Sen
executiveHonestly, I'd say that's a tough one to answer. Up to October, we've moved roughly 11 lakh tonnes. As things stand, we're still waiting on all the approvals for subgrade. Take the <<inaudible>> mines — selling subgrade calls for 4 permissions: the State Government clearance, the EC Amendment, the CTE and the CTO, correct? Well, in Orissa we've gotten 3 of them — only the CTO remains, for the Bolani Mine. And our hope is that, sometime around the end of October, we should receive that CTO. At Bolani, the subgrade volume is huge. My understanding is 7 million tonnes sits there in Bolani. So the moment that approval comes through — everything else is already in place — we'll be in a position to begin transferring subgrade from Bolani. That said, we've already completed one subgrade auction at Barsua, which is another Orissa mine. We've sold close to — we've auctioned 1 lakh tonnes of billings. In fact, we ran 2 auctions: one at 59% Fe, another at 54% Fe. The price we secured was reasonably good. And fresh fines, naturally, we keep doing those. The difficulty is that we're restricted, since we're chasing the consumer.
Amit Sen
executiveAnd with production ramping up, we need more of our own ore, so the spare amount we have available to sell as fresh fines is fairly limited. What we can sell in meaningful volumes is the subgrade material. So I think the Orissa clearance should come at least by the end of this month. And in Jharkhand, again, there's quite a bit of movement. Many — I think the secretary of steel has spoken with the secretary in Jharkhand. <<inaudible>> there as well. In Jharkhand, there's one lease in particular, the Topailore lease, where the 3 clearances are already in place: the EC Amendment, CTE and CTO. Roughly 6 million tonnes of subgrade is available at the Topailore lease. As soon as we receive the State Government clearance, we can begin auctions for Topailore right away. So we don't want to give a number, since the clearances still aren't in place, but we're hopeful that a reasonably good quantity will be sold this year.
Operator
operatorOur following question comes from Gaurav Rateria, who is on the line from Morgan Stanley.
Gaurav Rateria
analystSir, I have two or three questions. First, semis still make up a very large share of the DSP plant, and that has been the case for the past 2, 3, 4, 5—however many years you care to look at. So if long product demand were to pick up, what would the ideal semis mix in that plant be? Or do we need to do something about allocating some CapEx to really shift that plant’s mix away from semis toward long product?
Amit Sen
executiveSo in July, we actually commissioned a new facility at the Bar and Rod Mill — that's 0.9 million tonnes. The Bar and Rod Mill, therefore, isn't fully developed yet; it's still in the ramp-up phase. Once that <<inaudible>> happens, it will take up all the billets we make. Right now, since there's an imbalance between the billets we produce and the pellets being consumed at the BRM, that's what's giving rise to some semis, as the BRM is ramping up quite fast. You brought up Bhilai, correct?
Gaurav Rateria
analystSir, I was hoping to get some clarity on the DSP, Durgapur Steel.
Amit Sen
executiveApologies, apologies — Durgapur, I misheard you as BSP. Right, so at Durgapur, once again, it's the same program. We've got, you know, a Medium Structural Mill, MSM. That mill has problems of its own. What I mean is, demand for the MSM product just isn't there. The MSM was meant to take in all of it — or most of the <<inaudible>>. But with demand missing, the MSM isn't — it's operating well under capacity. Still, we're not cutting back steelmaking, since that would push costs higher. So steelmaking continues, and it's producing a lot of semis. Some of those semis we get converted into TMT, and some get converted into other areas — the SBUs we have. The remaining semis, we sell. At the same time, our marketing team is putting in a great deal of effort to build demand for the MSM product. So if the MSM picks up, the share of semis at Durgapur will decline.
Gaurav Rateria
analystYou mentioned that November and December ought to be solid for the construction season. At the overall sales level for October, what would the semi mix be? And in November and December, what is it probably going to fall to? What's your internal expectation?
Amit Sen
executiveThe share of semis might not shift a great deal, since the reason we produce such a large volume of semis isn't tied to whether the construction sector is present or absent. It stems from demand for the output of 2 specific mills we've recently commissioned: the Medium Structural Mill in Durgapur and the USM, Universal Section Mill in Durgapur. The Durgapur plant therefore turns out the heavy surplus, which goes into project construction. And Durgapur's MSM produces medium structural. For whatever reason, demand for these products is limited. So even if construction activity strengthens, should the mix of what the market requires differ from the mix turned out at these 2 plants, our share of semis might not decline.
Gaurav Rateria
analystUnderstood, sir. So turning to the second question about receivables. Sir, the profile has shifted fairly significantly over the last 2 years. How much of that is government money that's due? And where do you expect it to come down to from INR 8,200 crores? Does it -- is it likely to decline to INR 4,500 crores or INR 5,000 crores, which was the historical normal levels?
Amit Sen
executiveOf this INR 8,200 crores of debt, INR 6,000 crores comes from railways, correct? So within that INR 6,000 crores, railway typically has roughly 2 months of supply — 2 months of reversal outstanding — which, netted at today's price, would have been approximately INR 1,600 crores. So INR 6,000 crores less INR 1,600 crores leaves INR 4,500 crores of additional receivables owed to us by railway. That has grown into an enormous worry for us, and we're pushing at every level, yet that money isn't arriving. There's one specific issue with the railway: they aren't receiving the budget for the <<inaudible>>. As a result, they can't pay us. So we have — we're guiding to about INR 4,500 crores of extra CapEx above what's normal. When will it clear? We have no idea. We're making every effort, but it keeps rising.
Gaurav Rateria
analystAlright, sir. Sir, regarding the borrowing target for the second half, did you say anything about where it might come down to by the end of fiscal '21? And in your estimate, what is it likely to come down to by the end of fiscal '22? That's my last question.
Amit Sen
executiveOkay. At the same time, I didn't bring that up. What I said was that our borrowing stood at INR 48,200 crores as of 30th September. Now, over the last 2, 3 months, our collections have been excellent. As a matter of fact, in October they were even better than that. So if we keep depleting in this manner, if volumes come down at this pace, then definitely by the time 31st March arrives, even if we leave the railway outstandings aside, we ought to drop to roughly INR 45,000 crores, somewhere around INR 45,000 crores. But then, we are hopeful that 2 things will happen: first, railways will ultimately give us some forgiveness. It can't keep piling up forever. So any money we receive from the railway will bring the outstanding down further. And on this point, I have not considered mentioning iron ore fines. So whatever we get from selling iron ore fines, if the Bolani auctions begin let us say in November, and should we receive the government clearance, together with all the other auctions going on at the RMD mines and the Bhilai mine, that will push it up further.
Amit Sen
executiveBut at this point, I'd rather not attach a figure, because honestly I don't know how much it will end up being. And I also can't say whether they'll pay or not. Still, excluding railways and excluding iron ore fines, I'm definitely — I'm actually confident that total volume will drop to INR 45,000 crores.
Operator
operatorMoving on, our following question comes from Pinakin Parekh at JPMorgan.
Pinakin Parekh
analystSir, I have 2 questions. First, I am simply attempting to grasp what the margin trend could look like during the second half of the year. You have now provided quite a favorable outlook regarding steel sales volume. Coking coal prices remain depressed. That essentially means realizations are the missing variable. Broadly speaking, sir, at this point in time, what should the third quarter rise in ASPs per tonne be relative to the second quarter? And should that whole increase in ASP per tonne flow through into margins? Or will there be some rise in other costs that would offset the margin gain? My second question is, if I examine the quarter-on-quarter performance plant by plant, IISCO has shown no improvement. There has been barely any growth in revenues, and the losses are broadly at the same level as Q1. So what is the reason behind this?
Amit Sen
executiveSo when you mention ASP, you're referring to the average selling price?
Pinakin Parekh
analystYes, sir.
Amit Sen
executiveAlright, so when you say there's no growth in ASP, what exactly does that mean? If our average ASP stays where it is right now, but customers are purchasing larger volumes, then of course we're going to see a fairly healthy H2, since our coal price will most likely stay low. Take the China versus Australia conflict — they're not taking coal from Australia. There's plenty of coal supply in Australia, which means imported coal pricing is very low. Coal accounts for about 32% of our total cost. So if coal pricing holds at its current level, and even if ASP holds where it is, with the high volumes, our H2 should be quite good. What was our EBITDA? We had EBITDA of roughly INR 2,100 crores in Q2. That should carry through. But in Q2 — so we should be at around INR 5,000 crores by H2.
Pinakin Parekh
analystWe posted INR 5,000 crores of EBITDA in H2. And sir, just to be clear, you mentioned that this holds if ASPs stay unchanged. So should ASPs stay unchanged, sir, then ASPs in the third quarter ought to be higher. What was the second quarter ASP — the average ASP for that quarter — and by how much?
Amit Sen
executiveWhen I mentioned that ASP stays flat, I mean on a quarterly basis. Obviously, for last month, ASP—well, the cycle is now heading upward. Look at August versus September: how much did price rise? It went up roughly 2,000 bps per tonne. Alright. So if I use just September's price, that figure—that would be even better.
Pinakin Parekh
analystGot it. And sir, regarding how the IISCO plant has been performing, what’s the main thing holding it back?
Amit Sen
executiveWith IISCO, the issue stems from having just one furnace. Other steel plants have several blast furnaces, so if a single unit fails, another can pick up the slack. At IISCO there is only that one furnace, and it ran into trouble. In fact, the difficulty had been building for a while. The furnace simply couldn't perform unless it was repaired. A major problem hit around September. Since that point, operations have been running well under capacity. They will award a contract to a third party to carry out the required repairs and so forth. However, given COVID and the associated travel constraints, the furnace likely won't be fixed until the end of February. So I expect it to reach full output — roughly 8,000 tonnes of bar metal per day — beginning in March. Until then, across this whole stretch, meaning 5 months, comprising 3 months of Q3 and 2 months of Q4, we'll be producing at perhaps about 5,000 to 5,500 tonnes, sir. That is what's driving costs up so sharply.
Operator
operatorOur following question comes from Vikash Singh at PhillipCapital.
Vikash Singh
analystSir, as you mentioned, you'd be returning to profitability and likely making up for the earlier losses. Sir, I just want to get clarity: once you do become profitable, what then happens with the reservation? When does it come due?
Amit Sen
executiveI did say for certain that payment will happen during this financial year. What hasn't been settled yet is the starting point. As for the amount — whether it covers the entire year or only a portion of it — we still have to work that out. That said, the payment will definitely be made.
Vikash Singh
analystIs there any expectation regarding a provision that you've already taken from that?
Amit Sen
executiveThe reserve we set aside for <<inaudible>>.
Vikash Singh
analystRegarding companies within a...
Amit Sen
executiveYour question didn't come through to me. Could you repeat that?
Vikash Singh
analystSo far, have you set aside any provision for the proposed wage revision?
Amit Sen
executiveNo, we haven't made any — in the H1 results, no provisions have been made, since we still haven't settled on the date when it will take effect. Whether it applies from a past date or prospectively, that decision hasn't been made yet. That's the reason no provision has been taken on it.
Vikash Singh
analystGot it. And sir, is there anything new on the sale of those 3 plants? If I recall correctly, you mentioned last time that talks were underway with a couple of plants regarding prospective buyers.
Amit Sen
executiveThree plants, then.
Vikash Singh
analystRight, that’s the one we were looking to sell. If my memory serves me, you mentioned on the previous call that talks were already underway with a few potential buyers. Is there any news on that front?
Amit Sen
executiveYes. In fact, this is taken care of by — a government apparatus exists for this, DIPAM, the department under the ministry of finance, along with the Inter-Ministerial Group, or IMG. So bidders have shown interest in perhaps 2 plants or 3 plants. We can't say for certain, because the manner in which DIPAM structures the asset sale involves considerable secrecy. So despite the fact that the asset belongs to us, we are not really told what precisely is going on. Only the transaction adviser and the Inter-Ministerial Group have that knowledge. But it is proceeding. So the first stage of this investment has been completed by us. We have now transitioned to the second stage. Some bidders have made the shortlist. So the information has been provided to them — the confidential information, memorandum of sale, the request for proposal. So all these documents have been handed over to them. The date for publication of their bids will now be decided by IMG. So it stands at a fairly advanced stage.
Vikash Singh
analystGot it, sir. And if I could squeeze in one final question: during Q2, how much of EBITDA came from iron ore sales?
Amit Sen
executiveDuring Q2, we brought in roughly INR 100 crores.
Vikash Singh
analystRegarding the sale of iron ore, so nearly all of it would have gone through to EBITDA. Is that the right way to understand it?
Amit Sen
executiveYeah — that INR 100 crores forms part of EBITDA.
Operator
operatorOur next question comes from Kamlesh Bagmar, who is on the line from Prabhudas Lilladher.
Kamlesh Bagmar
analystSir, one question. What was the NSR this quarter — long, flat, and the blended figure?
Amit Sen
executiveRegarding long product NSR, in Q2 it came to 40,704. Flat product stood at 36,052, and the combined average for long and flat during the second quarter was 38,059.
Kamlesh Bagmar
analystGiven what we're seeing right now, what level of NSRs should we expect for the next quarter? For instance, might it come in around INR 60,000, above the Q2 average? Where do you see NSRs landing in Q3, sir?
Amit Sen
executiveOkay. Over the second quarter, NSRs on average rose by close to 4,000, correct? So if I take September's NSR and assume it keeps going, that would put the average NSR up by INR 2,000.
Kamlesh Bagmar
analystAll right, all right, INR 2,000. All right, all right. And sir, finally, regarding iron ore fine sales, should we anticipate the same pattern? For instance, will we exceed 1 million tonne in this quarter? Or would it be as you mentioned, 5 or 6 lakhs?
Amit Sen
executiveNo, actually, what we've sold up to October is 11 lakh tonnes. That works out to 1 million tonnes now. From April through October, we've already moved 1 million tonnes of iron ore, of which 0.9 million tonnes came from RMD and roughly 0.1 million tonne, or 0.2 million tonnes, was actually sold from the Bhilai Mines. So 10.92 lakh tonnes, or 1.09 million tonnes, has already been sold.
Kamlesh Bagmar
analystAll right. Yet when you look at our NSR, it has stayed considerably below what our competitors have achieved. For instance, those companies have been posting gains of roughly INR 2,500 to INR 3,000 each quarter over the prior quarter. I'll grant that during the last quarter our long sale was in fact significantly greater, driven by a larger rail component. So what were the reasons, sir? You mention exports were higher, but not to that degree, since costs across the company were considerably greater.
Amit Sen
executiveActually, what’s the question you’re asking me? Why is it that our NSR didn’t grow as much as it did for the others?
Kamlesh Bagmar
analystYes. Indeed.
Amit Sen
executiveHonestly, I'm not certain. One reason could be the product mix, since growth differed between long and flat products. And for some products, NSR actually declined in Q2. Take TMT, for instance — TMT NSR did fall. So it varies for us. The increase wasn't uniform across all products. Some products have seen gains. In HR, for example, there's been an increase. In CR, the increase has been very large. But TMT has decreased. Structural has decreased. Long products have probably softened somewhat while flats have strengthened somewhat. Since we have both profiles, we average them out. Also, exports accounted for roughly 16% of the total in Q2. And the export NSR was very low. In fact, export NSR this quarter was considerably lower. What was it? INR 28,300, INR 28,300 per tonne — roughly INR 2,000 below Q2 of last year. So taking all of this together — the long-versus-flat balancing and the large share of exports in total sales — that's likely weighing on the overall sales NSR when you compare SAIL as a single company with, say, the <<inaudible>>.
Operator
operatorApologies, sir, but we can’t hear you.
Amit Sen
executiveThere's another factor behind the Q2 net sales retention versus Q1 — and as we correctly noted for Q1, rails made up a large share of the total amount. That pushed the overall figure up. But that's a bit misleading, right? In Q2, which is a normal quarter, rails account for roughly 10% of total sales. So with that mix, this NSR is genuinely a real NSR. If you compare it with Q1, where the rail proportion was very high, the comparison becomes somewhat distorted. That's why comparing Q2 with Q2 is better than comparing Q1 with Q2.
Operator
operatorNext up, we have a question coming from Vishal Chandak of Emkay Global Financial Services.
Vishal Chandak
analystYes. I just wanted to hear your thoughts on how you would view NMDC's Nagarnar Steel Plant. Are there any plans for you to take over running that facility as an...
Amit Sen
executiveNo, no, no. There are no plans. None at all. Definitely not. We're still working on digesting our borrowings. Beyond that, we have nothing planned.
Vishal Chandak
analystFrom an operations standpoint, are you intending to operate that plant? Or would you have no interest in merely operating the plant?
Amit Sen
executiveNo, no, that's already been set aside for sales. And I believe, following the government guideline, a PSU can't bid for it. And that's being sold via that share purchase route. So no, we're not in that. We're not in the <<inaudible>>.
Vishal Chandak
analystAlright, my second question relates to your raw material costs. On a sequential basis, if you look at raw material cost, it has actually risen even though coal costs have declined. So do you have any thoughts on that? On a per tonne basis, it has simply increased.
Amit Sen
executiveAre you referring to Q1 compared with Q2?
Vishal Chandak
analystThat's right, sir.
Amit Sen
executiveIf we look at it quarter over quarter?
Vishal Chandak
analystOn a quarterly basis.
Amit Sen
executiveDuring Q4, expenses rose. I'll take action on that. I'll look into it and get back to you.
Vishal Chandak
analystAbsolutely, sir. And finally, sir, if I could just raise one question regarding the IISCO Burnpur plant. A few years back, if you recall, after the last furnace had been fully rebuilt, what we have there is essentially a new blast furnace. It went — it got chilled. And after that a major repair came up, and then the plant was restarted. So what are the reasons we still aren't able to get the plant back to its normal capacity rate? I think it has now been more than 3 years since we recommissioned a new blast furnace. And has any penalty been levied or cost recovered from the vendor on that matter?
Amit Sen
executiveOkay, so first off, the blast furnace at Burnpur is completely new — it wasn't a rebuild of an existing furnace. And it's a really good unit. It was putting out roughly 8,000 tonnes per day, but it appears to run into some sort of issue in nearly every financial year. As a matter of fact, this marks the third occasion that this particular blast furnace has gone down. So, as you rightly pointed out, on one occasion it chilled. It had to be fully shut down, and once a blast furnace is shut down, getting it back up takes a tremendous amount of time. This time around, it hasn't been shut down. It hasn't actually chilled. But some slag, I believe, has gotten into the tuyere, and it's still running. It's running at roughly 5,000 tonnes per day, 5,500 tonnes per day. But this is a furnace capable of making 8,000-plus, 8,200 tonnes per day or thereabouts. So there's, let's say, a 3,000-tonne shortfall each day for a plant that has just a single blast furnace. So that is — it's a constraint on the whole plant, because if you're not getting hot metal, then if you have a rolling mill, what do you do?
Vishal Chandak
analystOkay, so, sir, would you say the coke rate is really high at the moment?
Amit Sen
executiveThat number is really elevated since PCI injection isn't possible for them. As a result, their consumption is entirely coke. And for IISCO, the coke rate — the coal rate automatically — is <<inaudible>>.
Vishal Chandak
analystTechnically speaking, is the real issue that the ore burden is descending onto the furnace? Is it failing to hold — isn't it not holding inside the furnace, and is that why it keeps coming down?
Amit Sen
executiveWhich one is that—the coke?
Vishal Chandak
analystNo, the iron ore burden inside the furnace isn't holding. It's simply descending. So because of that, we have to maintain the furnace's heat by using extra coal.
Amit Sen
executiveNo, actually, burden slip is what caused the problem in the first place. So that's the — there isn't a lot more I can explain about it. With the burden slip, it leads to dashing. Metal ends up getting into the tuyere, and that jams most of the tuyere. Well, that material is still sitting in the tuyere, and the air is moving through — it has moved through, but performance is well below capacity. Yet since they can't inject PCI into the furnace, or the coolers aren't working, they're unable to burn PCI. That's the other reason it's now running entirely on coke.
Vishal Chandak
analystAll right. And sir, do you have any idea by when — when might we get that furnace back to a normal situation?
Amit Sen
executiveSo at first, what they did was — one option was to have POSCO, Korea, operate it. They placed an order with POSCO, and POSCO was going to bring its team. About a hundred people were going to come from Korea. But owing to the corona virus and the design side of things, they won't be coming. So they tendered it out again, and they'll finalize that tender soon. However, this new contractor — an Indian-based contractor — will need time to mobilize, get to the site, and then carry out the repairs. So as IISCO figures it, the furnace will finally be up toward the end of February.
Vishal Chandak
analystWe’ll go ahead and start the Q&A.
Amit Sen
executiveFebruary.
Vishal Chandak
analystOkay, February.
Amit Sen
executiveSo we’ve really had just one full month at full capacity. But through February, it’ll be running at 5,000 to 5,500 per day.
Vishal Chandak
analystAll right. But have we paid any performance guarantee tax or anything like that over to POSCO? Or did we keep that money?
Amit Sen
executiveNo. Look, <<inaudible>> regarding the project — an operational deficiency is what brought it about. <<inaudible>> So none of this relates to project LP or to how the project is performing right now. That isn't the issue. The project itself is not the one with the problem.
Operator
operatorOur next question comes from Dhawal Doshi with Pinpoint Asset Management.
Dhawal Doshi
analystApologies if this comes across as a bit—well, I just wanted to get some clarity on the steel realization, right? And the audio wasn't entirely clear. I would have missed it. Sir, you mentioned INR 2,000. Is the September steel price above the Q2 average, right?
Amit Sen
executiveCorrect.
Dhawal Doshi
analystAnd what about the <<inaudible>> at present — so if I were to factor in the blended realizations we're seeing for November, how does that stack up against the Q2 average?
Amit Sen
executiveWhat would the real NSR for October come out to?
Dhawal Doshi
analystYes, October—all right.
Amit Sen
executiveIf I look at the actual NSR for October and compare it against...
Dhawal Doshi
analystThe average for Q2.
Amit Sen
executiveWith Q2 average. The Q2 average came in at 32,000. And — or was that <<inaudible>>.
Dhawal Doshi
analystSo what you're saying is that there's no increase between September and October? But out in the markets, we heard about sales happening at high prices. Tell me if I've got that wrong.
Amit Sen
executiveNo, no, you're not wrong about that. Some of our products do carry high prices. And with certain products, we've actually seen degrowth — in fact, an actual reduction.
Dhawal Doshi
analystWas that in October?
Amit Sen
executivePrices have come down in steel plates and in TMT. So the overall increase comes to INR 2,000 versus the Q2 average. September prices stand INR 2,000 above the Q2 average. If October also runs INR 2,000 above that Q2 average, it means October's NSR is broadly equal to September's NSR. That is actually the case, since some products went up. Other products came down. So the weighted average likely stays the same.
Executive
executiveThe first part was not audible.
Amit Sen
executiveThat figure came in just a bit above that level.
Dhawal Doshi
analystAll right, so what does the outlook look like from November through the end of this year? Should we expect additional increases coming your way where medium scale is concerned? My belief is that long should be performing considerably better going forward compared with flats. How do you see it?
Amit Sen
executiveSo what you're looking for is how much NSR went up during November <<inaudible>>.
Dhawal Doshi
analystLooking forward, essentially, we also heard about a hike in November. Do you anticipate additional hikes emerging?
Amit Sen
executiveHonestly, for November we're anticipating that pricing on certain products will come in above October levels. That said, on a few products we've had to leave things as they are — plates, for instance, and CR as well. The reason we're holding steady there is that we just aren't seeing that NSR growth. On other products, though, we've already pushed prices up. So we'll need to look at where we land once the month closes, and based on the actual mix we end up with, we'll see how the weighted average NSR compares with October. At this point it has risen across the board for all products. For some, it's gone up. For others, it will stay flat.
Dhawal Doshi
analystSir, my question really had to do with the outlook back in March. Do you think things are holding steady, or have prices topped out? What's your take? I'm not asking about November specifically.
Amit Sen
executiveI mean, everything is just so evenly poised, it's really tough to call. But let's imagine that what we're seeing in November carries on. I believe that's what I told someone else who asked a similar question — it's extremely difficult, since the market swings a lot. At times, things are climbing. At other times, prices are falling. If we take it that this price holds, the price we have in, let's say, October, and that price keeps going in November overall — rising, falling, or perhaps a slight increase of INR 1,000 per tonne in November — and that then persists through the remaining 4 months, that too would be pretty good.
Dhawal Doshi
analystRegarding the numbers, how much of the coking coal savings has yet to come through?
Amit Sen
executiveCoking coal savings.
Dhawal Doshi
analystYes.
Amit Sen
executiveWell, the average coal price <<inaudible>> came in at 2,400.
Dhawal Doshi
analystMy apologies. My apologies — your voice is cutting out.
Amit Sen
executiveDuring Q2, the average price of imported coal we saw was 11,400. However, when we refer to an average for Q2, it actually ranged between $107 in July and $124 in September. Then, in October and November, the figure is lower—roughly $107 to $108. Still, I need to look at the monthly average. So the monthly average will likely stay around this level or perhaps ease a bit. As a result, my average for the Q3 quarter will probably be near the Q2 quarterly average. That’s because prices climbed from $107 to $124 during Q2, whereas they are declining in Q3. We’ll have to see how the averages compare.
Dhawal Doshi
analystSo essentially, we won't see the advantage from coking coal right now until Q4, rather than Q3?
Executive
executive<<inaudible>>
Amit Sen
executiveAlright, alright, alright. Yes, that's right. So Q3 will likely be included in Q2. And the coal benefit will arise because a 2-month lag exists between shipment date and consumption date. Therefore, that benefit will probably begin to appear at the end of December or else from January, which is in Q4.
Operator
operatorOur next question comes from Rahul Jain at Systematix.
Rahul Jain
analystYes. Yes, sir. Yes. Sir, I didn’t verify that. So I was reviewing the annual report, <<inaudible>> comes to roughly INR 450 — 450 tonnes. And as for your competitors, it’s roughly 350 and 300...
Operator
operatorSir, your line is producing quite a bit of echo.
Rahul Jain
analystJust a moment. Sir, based on your annual report, the coke rate you disclosed comes to roughly 457. That figure has risen from 453. Your rivals, by contrast, sit near 370 and even 316. So I'd like to know when that number can meaningfully decline, since it's such a key piece of your productivity, correct?
Amit Sen
executiveSo actually, a year ago we ran into an issue regarding PCI availability. We couldn't secure the PCI coal. This year, naturally, PCI supply isn't short at all. So the coke rate this year is going to be considerably better than last year's, thanks to the PCI benefit. The one issue is that ISP, which consumes all coke, hasn't been able to inject this year. So across SAIL's overall coke rate, that will likely pull EBITDA down somewhat. But if that hadn't happened, this year would have come in much lower than last year.
Rahul Jain
analystRight, right. It came up again since I still see your raw material cost for the second quarter as quite high. So I'm just wondering — I've noticed that improvement measures are showing up so far. So I'm trying to see whether, probably in the second half and the year after, we can see some improvement on the cost side.
Amit Sen
executiveOn the raw material side, what we observe would verify that. But then again, at this point, coke usage at ISP would also <<inaudible>>. I'm not sure, though. All right. All right. So iron ore royalty has risen as a result of the IBM prices, even when the coal price has increased. That's right.
Rahul Jain
analystOkay. Okay. And sir, you mentioned that you'll reach 18 million tonnes and will have that capacity. Should we take it that this is the figure you'll be aiming for next year?
Amit Sen
executiveYes, that will be next year.
Rahul Jain
analystSo 18 million is the number you'd start from — and then you have a remark about sales and other items, which are...
Amit Sen
executiveBasically, the design capacity for saleable steel stands at 18 million tonnes, provided the market imposes no constraints. And 18 million tonnes is what we'll be capable of producing and selling.
Rahul Jain
analystAnd sir, what amount of inventory would we be holding at this moment, I mean, through the end of the quarter?
Amit Sen
executiveAs of September 30, that figure stood at roughly 1.1 million.
Operator
operatorLadies and gentlemen, we're going to take the final question. It comes from Vishal Chandak at Emkay Global Financial Services.
Vishal Chandak
analystI just want to make sure I have this right. On the TMT, you said there's no hike in October. But will there be one in November?
Amit Sen
executiveIn November—just a second. On TMT, you said no, right?
Vishal Chandak
analystUnderstood, sir.
Amit Sen
executiveFor TMT, we're proposing an increase, yes, in November.
Vishal Chandak
analystWhat would the amount be, sir?
Amit Sen
executiveRoughly INR 1,000.
Vishal Chandak
analystWe're at INR 1,000.
Amit Sen
executiveSo INR 1,000 is the floor. Perhaps down the road, we might be able to land on a better size for that <<inaudible>>
Vishal Chandak
analystAnd my understanding is that for flat products in November, there’s an additional INR 1,000.
Amit Sen
executiveRegarding flats and HR coil, we proposed — hold on one second — INR 1,000 on HR coil as well, but CR stays unchanged.
Operator
operatorThank you. Ladies and gentlemen, we've reached the final question. At this point, I'll turn the conference back to management for their closing remarks.
Amit Sen
executiveThank you very much. Those were good questions. In fact, we probably gain more from the additional questions than you do from us. So, <<inaudible>> I mean, every effort is being made on our side to improve performance. Whatever ground we lost in Q1 owing to the pandemic, as I mentioned, we are attempting to make up. Regarding Q2, frankly, we are not pleased with how things went. It ought to have been significantly better than it actually was. But Q3, certainly, is progressing well. It is going pretty well. And we are confident that we will close Q3, the 9 months, with a profit. And we will close the year with, I am sure, a handsome profit. So the other things we are also watching, construction activity is picking up, iron ore sales are picking up. And if god willing, if clearances come through for the sale of the subgrade, then that will be a bonanza. That will be a huge amount of income and cash that we can obtain from that, which will also assist us in reducing our borrowing. Borrowings, as we have stated, we are targeting to bring down to INR 45,000 crores by 31st March without the help of iron ore fines and <<inaudible>>.
Amit Sen
executiveHowever, should funds come in from these 2 sources as well, it will in any case free up some ad hoc payments—perhaps INR 1,000 crores, INR 2,000 crores—and whatever amount we receive from selling fines, both fresh fines and subgrade, that will lower the bulk even further. So that's what we're hoping for, and matters are looking pretty good. We're optimistic that we'll perform well, perhaps through the close of the third quarter, when we'll meet again on the next con call unless we have something to share with you.
Operator
operatorThank you. Ladies and gentlemen, that brings this conference call to a close on behalf of DAM Capital Advisors Ltd. We appreciate your participation, and you can disconnect your lines at this time. Thank you.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Steel Authority of India Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Steel Authority of India Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Steel Authority of India Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.