Operator
operatorGood day, everyone, and welcome to the Steel Authority of India Limited Q2 FY 2026 Post Results Conference Call, hosted by Nuvama Institutional Equities. Just a reminder that every participant line will be in listen-only mode, and once the presentation wraps up, there will be a chance for you to ask questions. If you need help at any point during the call, please signal an operator by pressing star and zero on your touch-tone phone. Kindly note that this conference is being recorded. I'll now hand things over to Mr. Ashish Kejriwal. Thank you. Over to you, Mr. Kejriwal.
Ashish Kejriwal
analystThanks, Ranju. Good morning, everyone. On behalf of Nuvama Institutional Equities, we’re glad to welcome all of you once more to the Q2 FY 2026 conference call for Steel Authority of India Limited. It’s a pleasure to have Dr. Ashok Kumar Panda, Director of Finance, with us on this call, together with his team. At this point I’d ask Dr. Panda to give his opening remarks, after which we can open the floor to questions. Sir, over to you.
Ashok Panda
executiveThank you so much. A very good morning to everyone. I extend a warm welcome to all our investors and analysts joining us for these results. This is Concur for the financial results of Steel Authority of India Limited covering Q2 and H1 2025 to 2026. Before we get to the Q and A session, allow me to give you a brief on the results for the pay year. We begin with the economic scenario, the global scenario, the intense steel scenario, and a brief account of SAIL's performance. On the economic scenario front, starting with the global economic picture, the uncertainties and volatilities have stemmed from the tariff war. That is still affecting the demand supply situation worldwide, and it has made an impact in the domestic market as well. Projections for GDP have gotten better, in line with the same for economies both individually and regionally, and this has lifted the global averages. The IMF has raised its projections for global GDP growth rate to 3.2% in 2025 and 3.1% in 2026. The projections for India have likewise been revised upwards to 6.3% by various agencies. Turning to the global steel industry front, the worldwide steel sector is weighed down by the adverse demand supply situation, as some of the largest producers are seeing demand lower in their own geographies.
Ashok Panda
executiveEconomic trends, trade policies, and technological advancements all shape the landscape. Some regions might gain from protective trade measures, but the overall effect is complicated, with the potential for higher costs, market volatility, and shifts in global trade dynamics. That's the global steel picture at present, and turning to the Indian steel picture, the Indian steel industry keeps enjoying strong demand for steel, with consumption in H1 2025 to 2026 having grown by more than 8% compared with the same period last year. This was, however, somewhat overshadowed by the growth in production, as crude steel production rose by more than 12% in this H1 compared with the same period last year. Over that same period, imports fell substantially, while exports posted an increase. Yet even so, India remains a net importer. In H1 2025 to 2026, there is a reversal in the trend of imports versus exports in this H1 compared with last year. During this time, imports came down and exports went up. Exports went up because during H1 production was more than demand in the domestic market. That is the reason there was a bit of an oversupply situation in the country, which is why exports went up.
Ashok Panda
executivePerhaps as a result of this safeguard, along with other factors, imports have fallen sharply. That has brought a measure of relief. Given the oversupply condition in Asia, pressure was building on the pricing side. Our hope is that in quarter two, and later in the latter portion of quarter three and in quarter four, demand and the economy will recover — the Indian economy will recover — and demand will rise, which would then ease conditions on the pricing side. Challenges persist where pricing is concerned. Right now, with global trends not looking very good, within India we expect improvement in the latter portion of quarter three as well as quarter four. Turning to how Steel Authority of India Limited performed as a company in quarter two and H1 FY 2025 to 2026: crude steel production was steady at 9.5 million tonnes versus 9.46 million tonnes a year earlier. For H1, sales volume stands at 9.46 million tonnes, up by around 17% from 8.11 million tonnes in H1 last year. Sales volume rose substantially during this H1 period as far as SAIL is concerned. That has also led to a reduction in borrowings.
Ashok Panda
executiveIn H1, we brought borrowings down by over INR 3,000 crore. That's the main reason the interest burden has eased significantly. Revenue from operations came in at INR 52,625 crore for this H1, up 8% versus INR 48,672 crore in the same period a year earlier. EBITDA margin was INR 5,754 crore, growing roughly 3% compared with the corresponding period last year. Profit before tax reached INR 1,443 crore, a rise of 28%, while profit after tax came to INR 1,112 crore, up 32% from the same period last year. Our debt reduction effort is still going: borrowings as of 30th September were lower by INR 3,384 crore relative to the comparable period a year ago. Looking ahead, now that the monsoon has ended and the festivities are behind us, we expect the market to see an uptick in demand, and production should be robust as demand rises. Pressure on the pricing side may soften and prices could improve. That's what we expect, given that coal prices are still range bound. That said, the rupee's depreciation against the US dollar is having some effect on the bottom line. As for the coal price index, it remains more or less range bound.
Ashok Panda
executiveWe expect margins to get better as we move ahead — that's our expectation. With that said, I'll pass things over to Mr. Kejriwal to kick off the Q and A session, please. Does that work?
Ashish Kejriwal
analystYeah. Ranger, could you open the floor for questions and answers?
Operator
operatorOkay, thank you. At this point we'll open it up for questions. If you'd like to ask one, just press star and one on your touch-tone phone. Should you want to drop out of the queue, press star and two. We ask that participants use their handsets when posing a question. Our first question is from Amit Lahoti at Emkay. Please go ahead.
Amit Lahoti
analystThank you for the chance to ask. My first question concerns capacity expansion and CapEx. At present, we are generating roughly INR 8,000 under our plan for expanding capacity. How is that capacity progressing, and what is RLB intended for?
Ashok Panda
executiveCould you say that again, please? Actually, I can't hear it well. It's quite clear.
Amit Lahoti
analystYeah.
Operator
operatorMr. Lahoti, the operator here. Lahoti's line has dropped. We'll move the next one up. That's Rahul Gupta. Go ahead, please.
Rahul Gupta
analystYeah, hi. Thanks for taking my question. I have a few questions. First, is there any particular reason that realization trends came in stronger than what we've observed with the steel pricing trend during the quarter? Has inventory liquidation played any role in this? Any color on that would be very helpful. That's my first question.
Ashok Panda
executiveSure — even if the sales price fell in quarter two, what we actually see is that realizations rose, mainly because we sold more. As you can tell, sales growth for SAIL H1 over H1 has been there — it's roughly 16% growth. That's the main reason. As you rightly put it, this brought inventory down somewhat, but production was strong as well, and at the same time, it led to a substantial decrease in borrowings.
Rahul Gupta
analystMy question is this: steel prices fell in 2Q compared with 1Q by a much larger amount than your steel realization has shown up in the numbers. Is there a particular reason for that?
Ashok Panda
executiveSo the explanation for what happened from Q1 to Q2 is that sales volume for byproducts and scrap items rose a great deal in Q2. We sold a substantial amount of those, and we also brought down our inventory of both byproducts and scrap items. That's what accounts for overall realized in quarter two.
Rahul Gupta
analystWhere does finished steel inventory stand at the moment? My recollection is that it was roughly 1.8 million as of the prior quarter.
Ashok Panda
executiveHold on, hold on—one second. As of 30th September, finished steel inventory stands at 1.9 million tonnes. What really matters is that in-process stock has dropped from 1.3 million tonnes down to 0.7 million tonnes. That's a fairly substantial cut in process stocks. Speaking of total steel inventory, comparing opening to closing: opening this year was 2.72, and closing came in at 2.69 million tonnes.
Rahul Gupta
analystUnderstood. One last question from my side: is there any news on iron? I recall that you received approval to sell it. When do you think you'll be able to clear out that very large iron ore stockpile you're holding?
Ashok Panda
executiveOkay, let me share how I see this. Really, 2 or 3 points here: we've been selling continuously from the Odisha group of mines, that is from Bolani. If my memory serves me right, they've sold roughly 0.3 million tonnes. I don't have that number in front of me at the moment, but it's approximately that. That's proceeding against the target we set. As for the Chhattisgarh group of mines, we don't have much quantity available to sell right now. Down the road, new mines are being opened up, which is Rowghat. Once production ramps up there, we can consider it. Now, turning to Jharkhand mines, a group of mines concerning the dump iron ore fines, which holds a stock of approximately 33 million tonnes. Two things are happening. First, we are dispatching, and the dispatched quantity has risen considerably. We're sending this quantity to various sister plants. For instance, in a month we dispatch roughly 60,000 to 70,000 tonnes, which works out at the rate of about 0.7 to 0.8 million tonnes per annum. We have raised the dispatches from that dump iron ore fines to various sister units. That's number one.
Ashok Panda
executiveSecond, we recently held an auction covering 1 million tonnes of dump fines, and we hope prospective customers will take part in it. Yeah, that answers your question.
Rahul Gupta
analystI really appreciate it.
Operator
operatorThanks. Our next question is from Parthiv Jhonsa at Anand Rathi. Go ahead, please.
Parthiv Jhonsa
analystGood morning, sir, and thanks for the chance to ask. My first question concerns steel sales. We saw a very strong figure in H1 and in Q2 as well. Given the overall market, could you quantify your guidance for FY 2026 and 2027, considering that no major capacity expansion from ISCO is expected over the next two to three years and that only debottlenecking-type capacity additions are anticipated? Can you provide some guidance on Q3, FY 2026 and 2027 with respect to your sales volume?
Ashok Panda
executiveOkay, give me just a second to respond to that. As you accurately noted, debottlenecking work is actually underway for FY 2026 and FY 2027. That will drive up both production volumes and sales volume. We've been putting a lot of strategy in place to grow sales on the domestic side and, to some degree, on the export side as well. You can see that in H1 we worked to bring down our steel inventory volumes overall, and that led to lower borrowings. Moving ahead into Q3 and Q4 — let me address Q3 and Q4, then FY2026 and FY2027 — for Q3 and Q4, we expect to cut saleable steel inventory by pushing sales volumes higher than production volumes. In other words, during Q3 and Q4 our production volume will rise. At the same time, the gain in sales volume needs to exceed that of the production value so that total inventory can be brought down. Now turning to FY 2026 and FY 2027. For FY 2026 and FY 2027 we will still carry a solid target relative to FY 2025 and FY 2026. On the production side, since debottlenecking efforts are ongoing across various steel plants.
Ashok Panda
executiveSome measures are already complete at IISCO Steel Plant, and we intend to implement them at Rourkela Steel Plant as well. Should market conditions improve, we'll bring one type of furnace—an old furnace—online and begin raising our volumes too. That's the sort of effort involved. That explains why volumes in FY 2026 and FY 2027 will exceed those of FY 2025 and FY 2026. Since we hold inventory of saleable steel, that too will be liquidated to a larger degree, at least by 50%, across FY 2026 and FY 2027, and on top of that comes the production volumes. This growth in sales volume will likewise occur in FY 2026 and FY 2027 relative to FY 2025 and FY 2026. That is what we expect, and our efforts point in that direction as well, since we see the steel economy in the domestic market getting better. Our economy backs that up too.
Parthiv Jhonsa
analystThat's actually quite useful, sir. My second question relates to your borrowings. We've observed borrowings declining significantly in Q2, correct? Do you anticipate this trend persisting for at least the coming two to three quarters prior to the ISCO expansion CapEx beginning, or do you think it will rise, let's say, in 2026 or by the close of 2026 and 2027?
Ashok Panda
executiveNo, I wouldn't count on that going up, since during 2025 to 26 our aim is to bring borrowings down as far as we can and get our debt-equity ratio as low as we can, which leaves us room to expand and take in ISCO expansion. That CapEx will begin ramping up from 2026 to 27. You're right that we have a goal of cutting our borrowings further. The downward momentum on borrowings will carry on quarter by quarter through this year too.
Parthiv Jhonsa
analystSure. Maybe I’ll just ask a quick question here: could you provide us with some guidance on the coal cost?
Ashok Panda
executiveWhich quarter are you referring to — Q3 or Q2? I'm not sure what you mean.
Parthiv Jhonsa
analystRegarding Q3,
Ashok Panda
executiveI mean Q3, actually, as you can see. Right, I'll just give a landed cost coal price. Just one second, give me. As we can see, in October the imported coal price in our plant units is around INR 17,300, which has gone up from the August level of INR 16,600. That means between August and October there is an increase of around INR 700. This is primarily because of depreciation of rupee with respect to USD. Now, in this month by October end, we are finding that the indices have increased a bit. Of course, the indices are range bound, but it has increased from the September level of 187 to 194. Right now, it may soften, we do not know about that, but it is varying between 185 to 195 in that range. Right now, the index is a little on the highest at 194. As you said, what about quarter three and quarter four? In quarter three and quarter four, the demand is going to pick up everywhere. We believe the imported coal price will remain a little higher as compared to what it is today. It is around INR 17,400. It may go towards INR 18,000, INR 18,001 and something like that in quarter three.
Ashok Panda
executiveI'm expecting that in quarter four, we'll just have to watch how things keep developing.
Parthiv Jhonsa
analystShould we be looking at roughly $6 to $8 of an increase when it comes to coal cost?
Ashok Panda
executiveThat's the situation. Since it moved from 180 up to 194, I think it'll stay at that level, or somewhere close to it.
Parthiv Jhonsa
analystSo, thank you for that response, sir. I really appreciate it, and I wish you the best of luck.
Ashok Panda
executiveThanks.
Operator
operatorThanks. Our next question is from Rajesh Ravi at HDFC Securities. You can go ahead. Yeah.
Rajesh Ravi
analystHello sir, can you hear me okay?
Ashok Panda
executiveYes, I can hear you.
Rajesh Ravi
analystFirst question from me: could you tell us how much NMDC contributed on volume and on revenue during this quarter, and also address the 18.5 million ton figure, or volume, that stays unchanged for FY 2026?
Ashok Panda
executiveHold on a moment while I check those numbers. The amount is in rupees. This covers the quarter. For quarter two, volume came to 3 lakh tons — roughly a lakh per month — and the amount was INR 1,500 crore.
Rajesh Ravi
analystDid you say INR 1,500 crore?
Ashok Panda
executiveYeah, that comes to 300,000 and INR 15 billion.
Rajesh Ravi
analystRight, that 18.5 figure you guided to — that stays as is for FY 2026.
Ashok Panda
executiveYes, that's still in that.
Rajesh Ravi
analystRight. You said that thanks to the highest scrap prices and everything happening during Q2, your net realization looks stronger than it would under an ordinary drop in steel prices. It’s possible that in Q3 that effect will unwind.
Ashok Panda
executiveSorry, could you repeat that?
Rajesh Ravi
analystDuring Q3, with graph sales returning to normal levels or scrap sales coming in lower, and considering that steel prices have softened even more, the drop you'd see would be larger than what you'd typically get from a standard steel price decline.
Ashok Panda
executiveLet me walk you through this. Honestly, despite the pricing pressures we're seeing at the moment, my expectation is that from mid-November or the tail end of November, the situation ought to get better and prices should firm up. If we look back at last year, around this same period, starting in December there was also an uptick in prices. December and the whole of quarter four stayed in that improving mode. So that's point one — improvement is coming. Point two, when it comes to selling our byproducts, scrap and defectives, we're putting in the effort on that front. Our momentum toward clearing out those stocks via auction — frequent auctions and so on — will be maintained. This is underway across every steel plant and at the stockyards too. We're being very aggressive about it. On that front, realization should also be quite strong through quarter three and quarter four.
Rajesh Ravi
analystOkay, okay. What's your outlook on the first part, then? You said protein coal prices are going to be up by $6-$7 this quarter.
Ashok Panda
executiveIt appears that way.
Rajesh Ravi
analystAlright, so when it comes to overall margin, how are you thinking about the second half compared with 1, 8?
Ashok Panda
executiveFor H2, there are two or three developments to expect. Actually, even if the gold price ends up somewhat elevated — something we can't determine right now — that ties back to steel and the situation in the steel market. Should it stay where it is, steel prices will rise as well. Things will even out. That's the first point. Second, during quarter three and quarter four, since our CapEx has wrapped up across all the steel plants, output will increase, and the flow through the furnaces and blast furnaces will get better. As a result, cost reduction will also materialize. In quarter three and quarter four, we can achieve stronger cost reductions. That will contribute to our profitability.
Rajesh Ravi
analystAlright, and here's a final question — I actually raised this during the last call too, about your provisional price table, the provisional price revenue table that you referenced in the footnotes. How should we interpret those figures? What exactly do you mean by the cumulative figure versus the year-to-date figures? Because looking at Q2, you cited INR 2,500 crore for the current quarter, and on a YTD basis you cited roughly INR 4,900 crore. In Q1 you had reported INR 2,600 crore. Ideally, that ought to have been INR 5,100 crore. So what is this cumulative figure you provide? Could you walk us through the calculation behind those numbers?
Ashok Panda
executiveSure, I’ll do my best to break down what real price means. This is about real pricing. All right.
Rajesh Ravi
analystUnderstood.
Ashok Panda
executiveThis is a recurring item in SAIL's P&L and balance sheet each time. Rail prices have been finalized through 2023 to 2024, while 2024 to 2025 is still being worked through. That remains on track. Separate from the finalization, the provisional price gets set by the joint pricing committee, which includes members from both SAIL and Railways. So at present, the revenue recognized under Ind AS 115 in the books of accounts rests on those provisional prices, and those provisional prices have already been established. Using that provisional price, we have completed our revenue recognition, and it aligns with current market prices. Once the 2024 to 2025 prices are finalized, the differential will also be recorded in profitability. Following that, the provisional price will be reset as well. Each time a price is finalized, the arrear amount is also placed in the P&L account, and the provisional price is reset. This is live in the notes to the accounts, which we always present as part of the disclosure.
Operator
operatorThanks, Mr. Ravi. Please get back in the queue if you have further questions. Our next question is from Pallav Agarwal of Antique Stock Broking.
Pallav Agarwal
analystHi there.
Ashok Panda
executiveYeah.
Pallav Agarwal
analystYes sir, good morning. You mentioned that you expect realizations to get better. Could you break that down for us? How did flat long prices move from Q1 to Q2, and where are spot prices right now relative to the Q2 average?
Ashok Panda
executiveOkay, so Q1 and Q2 — hold on just a second. For long products, quarter one came in at INR 54,500, while quarter two stood at INR 49,000, which works out to roughly INR 5,500 less between Q2 and Q1. That covers long products. Now on the flat side, Q1 was INR 50,400 and Q2 was INR 48,700 — meaning a drop of about INR 1,700. And if you take the average, quarter one averaged INR 51,700 versus INR 49,000 in quarter two, so that's roughly a INR 2,700 average decline in sales price NSR in quarter one and between quarter one and quarter two.
Pallav Agarwal
analystYes, sir. That was your point about it being partly offset by scrap and defective sales. So it didn’t appear in the blended realization.
Ashok Panda
executiveAnd that's partly offset too, along with the input prices as well.
Pallav Agarwal
analystWhen we provide that 18.5 guidance, it leaves out the NMDC trading volumes, since at 0.3 million tons a quarter, we might reach an annual run rate of 1 to 1.2 million tons. That 18.5 figure covers sale production only, correct?
Ashok Panda
executiveYeah, that relates to sales, production, and sale production.
Pallav Agarwal
analystAlright. We're trying to get a rough idea of how profitable the NMDC trading sales are. There's the purchase of material involved. Does that fairly represent what the purchase cost from NMDC is?
Ashok Panda
executiveYes, some of the purchase cost for NMDC does get reflected, based on an agreement of sorts. That follows along those lines.
Pallav Agarwal
analystFinally, we’ll also just go over how October spot prices compared with the Q2 average, you know. How much lower are they than that?
Ashok Panda
executiveWhich one is it that spots?
Pallav Agarwal
analystLet's go with the October price.
Ashok Panda
executiveRight. October has been pretty long. Long product prices sit at INR 50,000. INR 49,900. Flat comes in at INR 46,600. For October, we'd say flat prices have fallen roughly INR 1,200 to INR 1,300 per ton, whereas long prices held steady. So for long products, October pricing is unchanged versus September. HR coil prices are trending downward. Flat prices—flat excluding plates, the PM plates. On PM plates, pricing is more or less flat. For HR products and CR products, there's a drop of roughly INR 1,200 to INR 1,300 in October versus September.
Pallav Agarwal
analystYes, sir. Thank you very much.
Ashok Panda
executiveThanks.
Operator
operatorThanks. Just a quick reminder for everyone on the line: please keep it to 2 questions. Our next question is from Rashi at Citi. Go ahead.
Rashi Agrawal
executiveThanks. My apologies — I missed the October flat realization. Would you say that came in at INR 46,800?
Ashok Panda
executiveIt's 46,600 Indian rupees, ma'am.
Rashi Agrawal
executiveRegarding SAIL, what did the average cost come to during this quarter?
Ashok Panda
executiveIn quarter two, the average cost was INR 17,400.
Rashi Agrawal
executiveWhat was the volume of imported coal?
Ashok Panda
executiveThe figure I'm referring to — yes, imported coal comes in at INR 18,150.
Rashi Agrawal
executiveThat figure of INR 17,400 is right now hovering around INR 17,300.
Ashok Panda
executiveSo you said 17,400 in quarter two — and as far as October goes, it's basically at that same level right now.
Rashi Agrawal
executiveUnderstood. Regarding capital expenditure and debt, we have the non-India debt figures. Could you please provide the India net debt figure for September, as well as the capex projection for the year?
Ashok Panda
executiveOn CapEx — actually, on CapEx, in H1 we achieved INR 3,370 crore against INR 3,005 crore and INR 100 crore, and for this year our target is more than INR 7,500 crore of CapEx. That's on CapEx. You're referring to index and non-index. Are you talking about borrowings? Yes, you mean borrowings. Now, on borrowings, just 1 sec. Index borrowings stand at INR 33,663 crore as on 30.09.2025, and non-index borrowings are INR 26,427 crore. That's the actual borrowing. Non-index borrowing. The actual borrowing in SAIL's books, which is INR 26,427 crore, a reduction of around more than INR 3,000 crore versus the opening.
Rashi Agrawal
executiveAppreciate it.
Operator
operatorThanks. Our next question is from Sachchidanand Khedekar at Equitas. You're up.
Sachchidanand Khedekar
unknownCould you, starting with next quarter, spell out the NNBC volumes along with the revenue and cost item in the presentation? That would help us more. It would let us see how much of the gain comes from NNBC.
Ashok Panda
executiveI mean, when it comes to the quantities and the relationship, we can certainly share that so everyone has the information. The gain component is built into the system. At this point in time, it may not be possible to quantify that exactly.
Sachchidanand Khedekar
unknownAnd second, what was the amount of scrap sales during this quarter?
Ashok Panda
executiveWe do give out that information. Let me see whether I can recall it. It has risen substantially. In fact, it stands at INR 1,140 crores, versus INR 869 crores in quarter one. That is a rise of roughly INR 200 to 250 crores.
Sachchidanand Khedekar
unknownOkay, thanks a lot.
Ashok Panda
executiveAppreciate it.
Operator
operatorThanks. Our following question is from Samayavi of Avendus Spark. You have the floor.
Analyst
analystAppreciate the chance to ask. Sir, regarding value-added products, you said there was a quarter-over-quarter increase for those. Could you provide a comparable figure?
Ashok Panda
executiveOn the value-added side, total value addition stands at roughly 57%. Quarter over quarter, we've been working to raise that share of value-added products. Our expectation is that it keeps improving in quarter three and quarter four. For comparison, quarter one came in at 55%. In quarter two it moved up to 57%, and looking ahead, our target is above 60%.
Analyst
analystUnderstood, sir. And regarding those byproducts you mentioned — the ones that also went up and contributed on the realization side — is there any kind of quantum nature to those products? What's the quantum of nature?
Ashok Panda
executiveI can explain that. Really, it comes down to what's on the scrap side. Defectives, rejected material, scrap iron and steel, scrap crude, tar, slag, and other things combined. That's the kind of items involved — the waste material. Essentially, all of the waste material.
Analyst
analystDoes this quarter-over-quarter rise of INR 200 crore take in all of it, or is it just the scrap?
Ashok Panda
executiveIt covers all of it. In fact, we've been concentrating on holding regular auctions for the by-products and for steel items too. By steel, I mean the scrap items, the defective and scrap items, so that we get both stock liquidation and cash flow that frees up working capital.
Analyst
analystCan you share whatever quantum you're able to provide regarding the inventory we hold on these items, or even volumes?
Ashok Panda
executiveYes, we do — but we can share that with you afterward. At the moment, it simply isn't right here in front of me. And yes, Berlin is something we maintain as well.
Analyst
analystLike you mentioned, you're anticipating that this carries on through the following quarters as well — the other options and then the liquidation of this.
Ashok Panda
executiveYes, we're keeping that going since there's additional rejected material and defective metal still sitting in the subfloors. Our aim is to gather it into a single location and move it to the yards so auctions can be held. We're looking to bring that stock down.
Analyst
analystLet me clarify one thing about long product pricing. Across the industry, the rebar price correction has been sharper — roughly INR 6,000 to INR 7,000. Yet, as you noted, in Q1 through Q2 it was just INR 4,500. What explains that gap? Is it discounts, or some element of product mix? That's the first point. You also spoke about current long prices compared with September. If you could provide current long prices against the Q2 average, that would give us the current picture.
Ashok Panda
executiveIn October, the long price comes in at roughly INR 50,000, or INR 49,940, versus a Q2 average of INR 48,800. So that's about INR 1,100 higher. Right now, prices are running above where they were in Q2.
Operator
operatorAppreciate that, Mr. Somaya. Kindly get back in the queue if you have further questions. Our next question is from Karthik Kumar of BNP Paribas Securities. Go right ahead.
Karthik Kumar
analystHello.
Ashok Panda
executiveHello.
Karthik Kumar
analystOkay, can you hear me?
Ashok Panda
executiveYes, please.
Karthik Kumar
analystYes, thanks for the chance to ask. Sir, I just wanted to get a sense of how much volume growth we can expect in FY 2027 compared with, say, a provisional FY 2026.
Ashok Panda
executiveFor FY 2026 to 2027, we're expecting growth above 5% versus FY 2025 to 2026. At a minimum, we'll be aiming for somewhere in the 5%-7% range. That's going to come about via the bottlenecking process. The bottlenecking process.
Karthik Kumar
analystAnd past fiscal 2028, let's say, any fresh CapEx you might be considering — is there any update on that?
Ashok Panda
executiveSo mainly, capital expenditure is going to come from two sources. The first is expanding the scope, and the second is debottlenecking packages at other sites. That's why, if this year we're aiming for more than INR 7,500 crore, those figures are set to rise considerably starting next year.
Karthik Kumar
analystSure — could you provide a rough figure, something along those lines?
Ashok Panda
executiveYeah, for next year, will it be more than INR 10,000 crores? It will be in excess of INR 10,000 crores in 2026 to 2027, and after 2026 to 2027 it will be still further more.
Karthik Kumar
analystAlright, one final question. I’d like to get a clearer picture of your strategy for reducing debt over the long term. For instance, is there a particular ratio—net debt to EBITDA, perhaps—that you monitor and aim for internally?
Ashok Panda
executiveOn that front, actually, since we're now bringing the borrowings down, the debt-equity ratio on a non-index basis stands at roughly 0.46, and we want to get that lowered to 0.35 or perhaps 0.4 by year end. Following that, starting next year, as I've already mentioned, our CapEx is set to rise mainly on account of the debottlenecking projects plus the expansion projects at ISCO. That's the reason borrowings will increase. We're building headroom so we can take on more borrowings to fund our expansion projects as we move forward. The expansion projects are laid out over the next four, five years on a much larger scale.
Karthik Kumar
analystWhat proportion do you think should come from debt versus internal accrual, you know.
Ashok Panda
executiveRegarding what you're accustomed to funding? Yeah, at this moment we're looking at 50, 50%. Thank you, thank you.
Operator
operatorThanks. Our next question is from Parthiv Jhonsa at Anand Rathi. Go ahead, please.
Parthiv Jhonsa
analystHello sir, thank you for the chance to speak. I just have a very brief question about byproduct scrap sales and all of that. I think during this quarter you mentioned realizing roughly INR 1,140 crore from that category. Given that you've held some recent auctions in coal tar and, you know, where you've been, particularly in iron ore, you've gotten some better interest compared with coal. Is this figure what's expected? Considering you're going to sell more and the quantum, with every auction coming in higher and higher, should we expect this number at the level 40 to move up further in Q3?
Ashok Panda
executiveYes, it's going to rise further — higher in Q3 and Q4 as well, since this isn't only coal tar. It also includes the defective items along with iron and steel scrap, plus the slag items too. Taken all together, that makes a bundle — really a bundle combining all those plant sales.
Parthiv Jhonsa
analystOkay. Is it fair to assume that all of this INR 1,140 benefit has made its way down to EBITDA and PBT?
Ashok Panda
executiveRight, since that was reflected in the stock exchanges — the difference between the sales price and the stock valuation rate, that amount has flowed through to PBT and EBITDA.
Parthiv Jhonsa
analystIs that even possible to achieve?
Ashok Panda
executiveSince the borrowings have decreased, the drop in interest expense has also flowed through to PBT afterward.
Parthiv Jhonsa
analystYes, yes, of course. Sir, could you put a number on that positive effect — how much did it contribute to your profitability?
Ashok Panda
executiveOkay, so take an instance where realization goes up, with roughly INR 300 crore of reduction from quarter one to quarter two. At a minimum, 20%-25% of that amount has made its way into EBITDA and PBT.
Parthiv Jhonsa
analystAlright, great, great. That’s really useful, sir. Thanks a lot.
Ashok Panda
executiveAppreciate it.
Operator
operatorThanks. Our next question is from Tushar Chaudhary at Prabhudas Lilladher Private Limited. Please go ahead.
Tushar Chaudhary
analystMorning, sir. Can you hear me okay?
Ashok Panda
executiveYes, I can hear you. Good morning.
Tushar Chaudhary
analystYeah, thank you very much for the chance to ask. I'd like to hear how things stand with DPR. I believe that's for ISCO. Could you give me a bit more? I mean, walk me through more specifics on the projects that are set to come up during the second half of FY 2027.
Ashok Panda
executiveYes. For the ISCO expansion, where we're planning 4.5 million tons of additional capacity at a cost of roughly INR 36,000 crore, the major packages have already gone out to tender, and most of them are already finalized. Order placements have already happened in certain cases, and within one or two months, placement of orders for the remaining major packages will be done. Once that's finished, design engineering gets underway, and after that the physical work, supplies, and on-the-ground activities will begin there. So that means from 2026 to 2027 onward — during 2026 to 2027 there will be significant CapEx payments for the ISCO expansion packages. As far as order placements go, they're pretty much on track.
Tushar Chaudhary
analystAnd as for the remaining projects — is there any DPR activity on those?
Ashok Panda
executiveAnd as for the remaining projects, we are reviewing debottlenecking efforts at Durgapur, ISCO, Bhilai, and RSP. Those remain on schedule as well. In some instances, orders have already been issued. At Durgapur Steel Plant, for instance, the rebar mill order went out last year. Site work has already begun there. At the Durgapur blast furnace, they are likewise in the process of finalizing orders. Across all the plant units, tendering is underway. In certain cases, orders have been awarded and work has already commenced.
Tushar Chaudhary
analystAlright, sir, just one final question. Regarding the scrap, you mentioned that during Q2 we sold INR 1,140 crore worth of it.
Ashok Panda
executiveYes.
Tushar Chaudhary
analystAll right, thank you. Appreciate your assembling this. All right, thank you.
Operator
operatorThanks. Our next question is from Rajesh Ravi at HDFC Securities. You can go ahead. Yeah.
Rajesh Ravi
analystHello sir, can you hear me okay?
Ashok Panda
executiveYes, we can hear you. Go ahead, please.
Rajesh Ravi
analystRight, so this byproduct — along with the others you referenced from the annual report schedule — appears there under the category of other secondary and byproduct, and in FY 2025 that brought in revenue, or income booked, of INR 3,300 crore.
Ashok Panda
executiveYeah, that's one piece of the byproduct.
Rajesh Ravi
analystYeah, yeah, got it. Okay, so this falls under roughly INR 2,000 crore that you've brought in during the first half. Is that right?
Ashok Panda
executiveYes.
Rajesh Ravi
analystAlright, and then the second thing — I want to revisit the disclosures you provided on that provisional price table. I just want to get clear, technically speaking, what the cumulative figure there actually refers to, since that figure and the half-yearly figure don't line up. The first 2 quarters don't line up.
Ashok Panda
executiveJust one thing. If you're able to give us specifics on those figures, we'll do our best to do the same.
Rajesh Ravi
analystAll right. On slide 9 — or the results table, which is number 9 — for this quarter you cited INR 2,500 crore and Q1. The figure we had presented was INR 2,600 crore. Combined, that should come to roughly INR 5,100 crore. The half-yearly figure placed in this quarter's table is INR 4,840 crore. I've calculated the prior-year numbers as well, and comparable discrepancies show up there too. First, why does this discrepancy exist, and second, what is this cumulative-as-of-30th-September figure of INR 13,800 crore? What is that meant to indicate?
Ashok Panda
executiveAlright, so the cumulative provision to date stands at INR 13,800 million in total, and that figure covers more than just rail items. In fact, it combines both rails and defense items — anything sold to the government, essentially. Rail items make up the bulk of it. Beyond that, we also have other items, such as the quantities going to defense from the different plants, all three plants. So that INR 13,800 million takes in rails along with defense items.
Rajesh Ravi
analystSo, when it comes to those yearly and quarterly figures, how do we line them up?
Ashok Panda
executiveThe figures shift somewhat depending on the debit advices and credit advices, since those happen concurrently.
Rajesh Ravi
analystThat is my end too.
Ashok Panda
executiveThanks.
Operator
operatorThanks. Our next question is from Siddharth Khadikar at Equitas. Please go ahead.
Sachchidanand Khedekar
unknownWe'll take some follow-ups now. Starting with the employee wage revision: when should we expect the next employee wage revision to take effect?
Ashok Panda
executiveSo on the wage revision, that actually covered 2017 through 2027. The first of January 2027 is when it comes due.
Sachchidanand Khedekar
unknownAll right. As for how much more we expect employee costs to rise beyond that point.
Ashok Panda
executiveThe reason for that is we don't currently have any guideline. In fact, quantifying it isn't going to be possible for us when we lack that knowledge.
Sachchidanand Khedekar
unknownAlright, thank you.
Operator
operatorThanks. Our next question is from Vinit Thakur, who is with Plus91 AMC. Vinit, the floor is yours.
Vinit Thakur
analystHello, sir. Can you hear me? Yes, we can hear you.
Ashok Panda
executiveHello.
Vinit Thakur
analystMorning, sir. I’d just like to ask: why is there a reduction in the OPM, sir, in Q1 year on year as well?
Ashok Panda
executiveSorry, could you ask that question one more time?
Vinit Thakur
analystI noticed that OPM went down quarter over quarter. Can you give us some color on what's driving that? What's the reason for it?
Ashok Panda
executiveSo regarding the decline in OPM from Q1 to Q2 that you mentioned — that comes down mainly to two factors. The first is a lower sales price, and the second is that during Q2 we carried out certain capital repairs, and there were some problems at the Bokaro steel melting shop in quarter two. That explains the drop in OPM for quarter two. Those capital repairs have all been completed, and Bokaro is back on track as well. Starting in quarter three, we expect solid results — better numbers.
Vinit Thakur
analystCan you give us some clarity on what that figure would be? Would it return to the original level of around 12%, or should it decline to roughly 11%, as it was last quarter?
Ashok Panda
executiveMoving on to quarter three,
Vinit Thakur
analystWhat I'm referring to is Q1 of FY 2026 and the Q1 of FY 2024, Q2 of FY 2024. FY 2025 came in at around 12% and FY 2026 was around 11. I just want to know whether it would be about the same maximum number or would it be. Yes sir.
Ashok Panda
executiveThe EBITDA margin for H1 2024 to 25 was actually 12.9%, and the average for 2024 to 25 came in at 11.57%. At present, it stands at 11.01%. Our expectation is for improvement in quarter three, and even more in quarter four. In fact, quarter four should deliver a strong figure, since we consistently see things pick up considerably in quarter four. It should move toward 14, 15%, roughly that level, in quarter four. 4. In quarter three, it could stay flat or edge up slightly, depending on market conditions. As I mentioned, all the capital pads are finished. Production is set to rise, so the outlook is improving.
Vinit Thakur
analystThere's also a decrease in output that we owe. At the Bokaro plant, it comes from a cut in crude.
Ashok Panda
executiveWhen you consider crude steel alongside hot melt, the two are interconnected. That mainly comes down to the Bokaro plant — they ran into problems with steel melting shafts, and as of just 2 days ago that has been fixed. Production has now begun to pick up.
Vinit Thakur
analystAll right, sir, I really appreciate it.
Ashok Panda
executiveI appreciate that.
Operator
operatorThank you, ladies and gentlemen. That brings us to the last question for today. Our question and answer session has now ended. At this point, I'd like to pass the conference over to Ashish Kejriwal, who will offer closing comments.
Ashish Kejriwal
analystHello, and thanks to everyone. I want to express appreciation to the management for giving us the chance to hold this call, and to Dr. Ashok Kumar Panda for taking the time to answer every question patiently. Sir, would you have any closing remarks to share? That would be helpful.
Ashok Panda
executiveThanks so much. Mr. Kejriwal and every one of our members who took part here — I'd like to offer my closing remarks. For the steel industry, the second half of the financial year is invariably the strongest, and we're hoping that pattern holds this year too. At the same time, demand for steel keeps thriving, and by boosting efficiency and holding costs in check, we'll aim to lift our margins over the rest of the year. Beyond that, the company stays dedicated to sustainable performance, which includes a focus on decarbonization, better capacity utilization, added value, and reaching cost competitiveness. My thanks go to all our investors for the trust they've placed in us; I hope that trust carries forward in the future too, and we'll work to deliver improved numbers as time goes on. Thank you. Many thanks to each of you.
Operator
operatorThank you. That brings this conference to a close on behalf of Nuvama Institutional Equities. We appreciate your participation. You can disconnect your lines now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Steel Authority of India Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Steel Authority of India Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Steel Authority of India Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.