Techno Electric & Engineering Company Limited (TECHNOE) Earnings Call Transcript & Summary
November 13, 2024
Earnings Call Speaker Segments
Operator
operatorGood day, everyone, and welcome to the Q2 FY25 earnings conference call for Techno Electric & Engineering Company Limited, brought to you by Asian Market Securities Limited. On this call, we may make forward-looking statements regarding the company, and those are grounded in the beliefs, opinions, and expectations held by the company as of today's date. Such statements do not constitute guarantees of future performance and carry risks and uncertainties that are hard to foresee. Actual results could vary from those expectations, projections, and similar items, whether expressed or implied. We ask that participants exercise caution when referring to these statements and remarks. As a reminder, all participant lines will be in listen-only mode, and you will have a chance to ask questions once the presentation concludes. If you need assistance during the conference call, please signal an operator by pressing star, then zero on your touch-tone phone. Please be aware that this conference has been recorded. I now hand the conference over to Mr. Suresh Sonulkar from Asian Markets Securities. Thank you, and over to you, sir.
Suraj Sonulkar
analystThanks, Jakob. Good afternoon, everyone. We at Asian Markets Securities are glad to welcome all of you to the Q2 FY25 earnings conference call for Techno Electric & Engineering Company Limited. It's a pleasure to have with us Mr. P. P. Guptaji, Managing Director, along with Mr. Ankit Saraiya, Director, representing the company. I'd now like to ask Sri Guptaji to walk us through an overview of the company's quarterly results, after which we can start the Q&A session. Guptaji, over to you.
P. P. Gupta
executiveThanks very much. Good afternoon, everyone, and welcome to our discussion of the financial results for Q2 and the half-year ended 30th September 2024. Any remarks on this call that reflect our outlook going forward, or that might be taken as a forward-looking statement, need to be considered alongside the risks facing the industry and the company. Let me begin by highlighting how we performed. Because of the inherent character of the business, our results cannot be compared quarter on quarter, and we have noted this on previous calls as well. As discussed before, H1 typically accounts for 40% of the full year, with the remaining 60% coming in H2. On that basis, we are short by roughly INR 100 crores in H1. That works out to about 40% of the INR 2,500 crores we are targeting this year. The main reason is delays by various clients — Power Grid, IndiGrid, Apraava Energy, and Adani Group — in handing over sites. However, we have now already received four sites from Adani Group and Power Grid, and we are confident of making this up in H2, given our robust order book and clear visibility of further opportunities in the T&D sector.
P. P. Gupta
executiveWe want to point out that the average order value has nearly doubled lately. So while total order value might look high, the count of sites is roughly the same or fewer. At the same time, how quickly these projects get executed is turning into the standard or the expectation for most of our customers. They're trying to recover the time they lost in acquiring land parcels and handing them over to us so the solutions can be deployed. Our most interesting recent experience in H1 involves Sikar Power Grid, where the site came to us after a delay of nearly two years, and we were asked to finish the project in nine months, versus the contract execution time of 19 months. And I'm glad to report that we succeeded in doing so, and Power Grid recognizes this achievement — the first time in the country that projects of this scale and size have been deployed in such a coordinated and integrated manner. So Techno has a proven track record and is capable of moving faster. So speed is going to be the way these solutions are deployed in the future.
P. P. Gupta
executiveAs all of you know, we've been building out a 40-megawatt data center in Chennai. Phase one of that facility is close to finished, and the SPV remains in its implementation phase. It hasn't yet reached the revenue-accretive stage, though it is certainly extremely value-accretive. Foreign entities are showing solid interest in joining this project. In the consolidated results, we strip out the financials of the SPV data center, and that accounts for the gap between standalone and consolidated results. Of course, that won't be necessary once it turns revenue-accretive. Briefly, for the first half of financial year 2025, revenue came in at roughly INR 914 CR. EBITDA was approximately INR 126.13 CR. Other income was INR 62 CR. Profit before tax is 180 CR, and profit after tax is 145 crore, which means versus 125 crore last year, that's a 16.5% increase year over year, and EPS is 17.16, up roughly 50%. Turning now to Q2 of the financial year, revenue was 495 CR, and EBITDA was around 65 CR. The EBITDA margin came in at 13.26%.
P. P. Gupta
executiveOther income stands at 28.3 CR. Profit before tax comes in at 4.28, and the company has managed to collect, as per our books, all outstanding amounts from TANGEDCO. That is a major achievement during this H1. For the quarter, the track is at 90 crore, roughly 27% year-on-year, while EPS is 7.88, an increase of about 19% year-on-year. Current investment in cash is approximately 2,600 crore, which works out to about 225 rupees per share. As of September 2024, we hold an extremely robust order book of around 9,725 crore. We have booked further business. In Q2 we booked business worth 642 crore, plus another roughly 1,100 crore of business after September through today. So we can state that our current order book is around 10,800 crore plus unexecuted. We are L1 on another 622 crore order, and both of those are very short. In addition, I would like to note that in Q1, where we were L1, every opportunity at the L1 stage converted successfully into an order. We have various bids in the pipeline and are confident of securing additional orders worth around 1,500 crore in the current financial year. That will bring our total order tally for the current financial year to around 4,000 crore.
P. P. Gupta
executiveWhat I'm describing is just how orders get executed after they're booked for this year. We'll still have sufficient orders on hand to sustain that growth momentum. The company has managed to raise capital, or finish a QIP, of 1,250 crore during the first half of this financial year. Turning now to the outlook: we've managed to overcome the bulk of our difficulties and weak spots through the close of financial year 2022 to 23. Some growth momentum showed up in 2023 to 24, and as we see it, that will carry on over the coming few years. We anticipate bigger business from transmission — mainly deployment of high-end power solutions — data centers, hyperscale MS data centers or distributed data centers, the AMI segment, and also, to some degree, digitization solutions in the power distribution space under the RDSS scheme, plus a muted presence in the AMI scheme. As for the present: after seeing negligible or mild growth in energy demand across the last 8 years, last year was the first time we saw energy growth come close to double digits. Peak load demand right now stands at roughly 240 gigawatts or more, and by 2030 that is likely to reach 400 gigawatts, which would bring per capita consumption to no less than 1,700 units by 2030, compared with 1,200 units today.
P. P. Gupta
executiveThe government is worried about satisfying this demand, and the plan is to add 80 gigawatts of conventional power capacity by building ultra-supercritical power stations, plus renewable energy deployment reaching 500 gigawatts by 2030. What all of that means is that the sector is undergoing a technological transformation and is also bringing in high-end solutions for power generation and power transmission — solutions such as supercritical power plants, 765 kV AIS, GIS transmission solutions at gigawatt scale, STATCOM solutions, VSC, HVDC solutions, and solutions supported by BESS or PSP facilities, and in these areas your company has a bigger presence than any other player in the market. Your company tends to concentrate on areas such as transmission solutions, especially high-end HVDC solutions, including STATCOMs and VSC, HVDC solutions. We are also there in hyperscale data centers. We are there in EPC. We are carrying out smart metering implementation for 2.5 million meters. We are digitizing the power distribution networks of the DISCOMs within their command areas. Every one of these verticals holds potential, and this implies a paradigm shift in how the company is positioned. From the present mix of 43% of total installed capacity, renewable energy is expected to reach about 64% by 2030, driven by a significant growth rate of around 15%-20% CAGR, as against 4% for fossil fuel.
P. P. Gupta
executiveIndia's goal is to push its renewable energy capacity past 500 gigawatts, and the 2030 target is pretty much on track to be met by that year, and the corresponding transmission infrastructure is going to be needed, which comes to nearly 4X compared with 1X for conventional power. So this keeps providing a boost to renewable power. According to the CEA report, the transmission system needed for 500 gigawatt of RE capacity will call for no less than 50,000 circuit kilometers of lines plus another 435 GW of transformation capacity. With these programs being implemented under ISTS regimes, interregional transfer capacity is set to rise to 150 gigawatts. The National Electricity Plan has already put the investment opportunity at more than INR 900 crore in this space by 2032. Power Grid will benefit the most, and since we have been among the biggest solution deployers at station level for 35 years, having successfully seen incorporation, and with the planned CapEx of INR 1.75 lakh crore up to 2030, their yearly CapEx will climb to INR 25,000 crore by 2026 from the current INR 50,000 crore a year. That leaves us optimistic about a pickup at Power Grid, and we also expect a larger inflow of orders from private players in this space, while we will likewise be pursuing some opportunities for ourselves in the TBCB space.
P. P. Gupta
executiveBeyond that, we now see a massive opportunity in STATCOM projects that are going to be deployed. Power Grid has already changed their qualification criteria, and we now qualify as a four-wheeler, with backing from the critical equipment suppliers. Data centers are also going to generate enormous extra demand for power. As I said earlier, in order to satisfy this higher demand, the government has already spoken about expanding it through conventional power as well as renewable power. Within conventional power, once again, there will be solid scope for us on the balance of plant and especially on power evacuation facilities — what we refer to as step-up facilities and grid integration for the utilities — and NTPC in particular will be one of the main beneficiaries, alongside other CPSUs in this area. On the distribution side under the RDSS plan, we observe a great deal of activity taking place, including smart meter deployment. We are also now deploying roughly 2.5 million smart meters per year — 2.5 million smart meters across the coming two years. This year, we will deploy approximately 500,000, and another 1 million each over the next two years. Since counterparty risk is somewhat higher than in transmission, we remain conservative in this space. We are seeing a slowdown in the MTD segment, especially following the NITI Aayog report, but orders in hand will keep being executed at the given pace.
P. P. Gupta
executiveThere's still going to be some business in this space — perhaps as much as 5 to 10 gigawatts a year, coming from private players as well as SEBs. On the transmission side, I've already pointed out that bidding activity covers roughly 50 to 100 gigawatts, and about four to five concessions are reaching finalization each month. I wanted to speak about our two private players. That works out to something like 40,000 CR of business, and from that we'd expect to book around 2,500 crore of business annually across the coming three to four years. Right now we hold orders of 6,500 crore in this space, and we stand L1 on another 650 crore segment — one where Power Grid has already secured the concession. So that should convert into an order during this quarter. Our projects secured in TBCB, Gokak and Gokazan, carrying total revenue visibility of 2,800 CR across the concession period, are currently under execution, and we're confident of delivering them ahead of schedule. Likewise, our smart meter rollout is proceeding in line with the program. In smart metering, we anticipate business of roughly 1,000 CR a year from deploying about a million meters annually.
P. P. Gupta
executiveLike I said, we hold orders of roughly 2.5 million meters, valued at approximately 2,500 crores. Ankit, perhaps you could say a few words on data centers? Yes, of course. Turning to data centers, my view is that several forces are at work: digitization, growing uptake of cloud services, AI, and the rollout of 5G across tier two and tier three cities as well as tier one cities, plus the government's emphasis on protecting data and making sure the nation's data stays within the nation. Each of these is driving ever-greater demand for data centers. They serve as the warehouses in which data is kept. If the data center market size in 2024 stands at close to, let's say, 1,300 to 1,400 megawatts today, then a growth rate of 15%-18% year on year is what we can expect, and by 2029 total capacity should reach roughly about 4,000 megawatts or 5,000 megawatts. Beyond our own initiatives, as mentioned earlier, construction has already begun in Chennai. It is at a very advanced stage, and commissioning work on the ground has started. We are hopeful that within another couple of months, the data center will be ready for RFS for service. Beyond that, on the hyperscale data center front, land has already been allotted to us in Kolkata by the state of West Bengal through its body known as West Bengal HIDCO.
P. P. Gupta
executiveIt's a land parcel of four acres at a client site called Bengal Silicon Valley. From next year onward, we should be rolling out the data center there. Construction work ought to kick off around the middle of next year, or toward the latter half of next year, and the build should possibly wrap up by mid-2027. That would be a data center of roughly 15 to 18 megawatts. Beyond that, we're building edge data centers through a strategic partnership with RailTel, a Navratna PSU. Construction has already begun at our first site in Gurugram — it's in Sector 44. From RailTel, we expect handover of a second site in Mumbai, right opposite the well-known St. Regis Hotel at Mahalakshmi. On the size of these sites: the Gurugram one is a smaller project of 20 racks, 200 kilowatts in total, and over time it would be expanded to close to about 1.5 to 2 megawatts. The Mahalakshmi one begins at a capacity of 560 kilowatts with 56 racks, and over a period of time that too should see daylight of about 1.5 to 2 megawatts. We've seen solid customer traction for edge data centers. In Gurugram, we're near to finalizing a few customers, fitting them within those 20 racks.
P. P. Gupta
executiveWe're also seeing interest from hyperscalers in leasing these edge data centers in selective cities, and we're working closely with a couple of such hyperscalers to deliver to their requirement. All in all, it looks exciting and, I would say, a promising time and space for this industry. Yeah. Yeah, so that's on data centers. Yeah, coming back to now taking over from what Ankit has said, overall, in the last five years, the company has successfully monetized all its deployed assets over 10, 15 years, worth about 5,000 CR in triple P model or TBCB mode. This resulted in a cash surplus, which is already discussed, and QIP has further added to the cash balance. We have sufficient financial resources to see this growth in data centers and in transmission space. During the last year, as I had mentioned, I will again like to repeat that it is just the morning that has happened, and this is the first sunshine, which will keep brightening with every passing year. We are confident to achieve, as I have repeated again, 2,500 CR plus minus during the current year, and a similar growth over next year, maybe around 3,500 CR.
P. P. Gupta
executiveWe feel sure we'll deliver EPS of roughly 35 or higher in the current year, and 50 plus for the following year, which ends in March 2026. That said, we're ready to take questions now.
Operator
operatorHello. Shall we get started with the Q&A portion?
P. P. Gupta
executiveYeah, yeah, yeah. Absolutely.
Operator
operatorCertainly. Thank you. We're moving into the question-and-answer portion now. If you'd like to pose a question, press star and one on your touch-tone phone. Should you want to drop out of the queue, press star and two. We ask participants to use hands up when asking a question. Ladies and gentlemen, we'll pause briefly while the queue is put together. Our first question comes from Abhijit at ICICI Securities. Please go ahead.
Abhijit Mitra
analystThanks for taking the question. Sir, my first one concerns revenue. In H1, we posted roughly INR 913 crores, and our target for the whole year sits at around INR 2,500 crores. That implies we need to expand at close to twice what we delivered in last year's second half as we move into H2 FY25 to hit that level of revenue, which would also translate into a run rate of about INR 800 crores, up from INR 500 crore this quarter. So what is going to produce that sort of step-up in execution across the coming two quarters? That's my first question.
P. P. Gupta
executiveShould I go ahead and respond, or would you prefer to direct your question to the other person as well?
Abhijit Mitra
analystThe second question concerns the order book. We hold roughly INR 9,700 crores in orders. Are there any slow-moving orders within that book? And if so, what quantity do those orders represent?
P. P. Gupta
executiveOkay, so first off, as I mentioned, in H1 we took a hit because the land parcels weren't available from the customers who had placed orders for our smart station deployment. At this point we've gotten four land parcels — three from Power Grid and one from Adani. We're still waiting on two additional land parcels from Apraava and HIDCO, and those should come through shortly. Now that the land parcels are in hand, though, execution will move along at a much quicker pace. And as I told you before, that's what the customer needs as well — they want the job finished within six to nine months at most, whereas previously it typically took 12 to 18 months. So with that, we're confident this weather is generally going to mean either better conditions for working in this country, both from the field side and from the factory side. And Q4 is always bigger than Q3. So by and large, our takeaway is that Q3 comes in at roughly 22%-25%, while Q4 is always around 30%-35%. So we're quite sure that with a 5% margin, we should be able to hit the bull's eye. That's number one. Number two, as far as the order book goes, there's no slow-moving order book with us as of today.
P. P. Gupta
executiveSince every one of these TBCB projects carries a COD date agreed with the customer, any delay in handing over inputs or land parcels still ends up with them expecting us to compress the execution.
Abhijit Mitra
analystOkay, sir. Okay, sir. Then finally, turning to margin: this quarter, compared with a year earlier, there is roughly 160 basis points of compression at the EBITDA level. And we have observed a rise in the cost of services and raw materials. So could you specifically point out what is driving this type of cost inflation, which is outpacing revenue growth, and what margin should we expect in the second half?
P. P. Gupta
executiveLook, the issue here—which I touched on earlier too, and I’ll say it once more—is that assessing margins on a quarter-by-quarter basis in a construction or project business is really tough. It comes down to the way you recognize revenue and the way you recognize costs. You might be somewhat conservative, or logistical, or optimistic. Often, we fail to record revenue because a bill hasn’t been issued or the work hasn’t been measured. Not all materials have been cleared as supplied either. So we’re also aware that across the year there’s always an opportunity to catch up. As a result, you’ll find that the overall margin, as I’ve said, will come in at roughly 30%-40% for the year. In one quarter it might be 1% higher; in another it might be 1% lower. But by year-end, you’ll see that it all evens out.
Abhijit Mitra
analystOkay, finally, where does our Chennai data center stand, and when should we expect it to reach commercial completion?
P. P. Gupta
executiveAnkit, do you want to take that one?
Ankit Saraiya
executiveRight. As I said during the opening remarks, we've already begun the commissioning work for the data center, and we expect to hit RFS — that's the commissioning point when customers can start taking handover of the location for those moving in — at some point around January.
Abhijit Mitra
analystOkay, okay, thanks, sir. I'll circle back to you.
Operator
operatorThanks. Our next question comes from Anurag Agarwal at Multifi Wealth, who is on the line. Go ahead, please.
Anurag Agarwal
analystHello, sir, and thanks for giving me the chance to speak. Sir, I'd like to dig a bit deeper into the smart meter rollout. How do you expect that to go? Are there any execution risks that are starting to show up?
P. P. Gupta
executiveI'm sure the answer is both yes and no. There's no real basis, but nothing new is taking place, Anurag — that much I can tell you. It was known at the time we booked the business, and it's still the case today. Since the counterparty is the DISCOM, some interruption is just a normal part of carrying out this work. But Techno has a great deal of experience when it comes to deploying these solutions. So that's the reason this year, and we also have what I'd describe as a muted presence in this segment relative to other players. As I shared with you, we don't want to do more than 1 million meters a year, with 500,000 this year, since DDF creation by the utilities was delayed, and that only happened in Q2 with us at Tripura or at Jharkhand or even with J&K, I would say. So by and large, we would not want to be very, very aggressive and optimistic like other players in this space. But our major graphic space will always be transmission, ISTS, and EPC using power generation, I would say. Our data center is now at a very, very exciting and fascinating phase for us. But even so, smart meter will have a presence. It's with our own customers. We don't want to be out of it. And secondly, let me tell you, the smart meter has not yet been declared an infra business by the government.
P. P. Gupta
executiveThere are plenty of areas that fall outside of it. You can’t split off portions of your assets to invent, or similarly to a lot of government funds. This status is given to this space, such as transmission or power generation. They aren’t the same when it comes to the regulatory framework. So there are some issues in this space, but even so, some companies are more optimistic than we are. We are not.
Anurag Agarwal
analystUnderstood. Thanks for the thorough response, sir.
Operator
operatorThanks. We'll take the next question from Nivisha at ICICI Securities. Go ahead. Thanks a lot for taking my question. Could you break down the order book, either as it stands now or at the close of Q2, across generation, transmission, distribution, and data center?
P. P. Gupta
executiveSo yeah, it's largely from transmission, I'd say. And if you'd like to note the breakdown of the total order book, you can. Transmission accounts for roughly INR 4,671 crore. From our own TBCB assets, it's around INR 687 crore. FGD comes to about INR 1,200 crore. Digitization of the distribution network for DVC is roughly INR 290 crore. And smart meter is INR 2,500 crore. And another data center — you can take about another INR 100 crore that's left. All right. Thank you very much. Thank you.
Nimit Goyal
analystWe’ll now take the next question from CA Karmit Goyal at NVEST Analytics Advisors LLP. Please proceed. Hello. Can you hear me?
Operator
operatorYes.
Nimit Goyal
analystSir, my question concerns only the diagnostics segment. First, I’d like to understand why the standalone figures differ from the consolidated figures. For instance, the consolidated figures are lower than the standalone figures. So could you please shed some light on that? What’s the reason for it?
P. P. Gupta
executiveAs we already stated, at the parent level we're the company deploying this data center in Chennai. So once you consolidate, those figures get used within the EPC space, but when you consolidate they'll show up as work in progress or as an asset in the data center subsidiary. It's only a change in nomenclature. I hope that's clear. Work carried out for your own subsidiary is utilized and reclassified as work in progress or as an asset, or whatever term you use, depending on billing.
Nimit Goyal
analystGot it, sir. So sir, when you gave that guidance of roughly 25 minutes here, does that apply to the consolidated figures or to the standalone figures?
P. P. Gupta
executiveRegarding standalone numbers.
Nimit Goyal
analystAnd if we line that up against the consolidated figures, what would that figure come out to for the whole year?
P. P. Gupta
executiveThat comes to 2250.
Nimit Goyal
analyst2250, yes. And we're still steering toward that same figure for this year, correct? Even with the difficulties we're up against. Absolutely. Understood, sir. And sir, second, as in our results too, there are substantial overdue receivables, and the auditor flagged the same as well, including those tied to long-standing projects, regulatory matters, and the arbitrations still unresolved, which carry a cumulative value of roughly 130 CR. So could you give a clear update on the particular difficulties we face in recovering these amounts, the expected timeline for the resolutions, and the potential financial impact if these amounts do not get collected?
P. P. Gupta
executiveNo — first off, 130 CR isn’t right. I don’t know where that came from. We really only have two problem items. The first is retention money that’s receivable from a private player — we built a capital power plant for them — and that amount is just 11 CR. The second is a receivable from Afghanistan, where projects were halted because of the political change. That contract is funded by ADB. ADB has now stepped up and agreed to pay what’s owed to KEC, Kalpataru, Explore, and everyone else who was involved in that CASA-1000. In Afghanistan it was called CASA-1000. The bills are being processed, and we expect all of that money to come in. It’s roughly $7 million. We’re hoping to receive it before this year ends. There’s no other issue at all in our books.
Nimit Goyal
analystAnd that amount will be in place by the close of this financial year, correct?
P. P. Gupta
executiveSure, definitely. If you look at it against total receivables, it’s under 10%. So there’s no material impact. 10% of what, sir?
Nimit Goyal
analystAnd that’s present.
P. P. Gupta
executiveI apologize.
Nimit Goyal
analystIs that 10% of the total?
P. P. Gupta
executiveI wasn't able to obtain your total means.
Nimit Goyal
analystNo — 10% of what, exactly? That's what I'm trying to get at. I didn't catch that.
P. P. Gupta
executiveWhen it comes to the receivables, that's roughly 550 to 600 CR.
Nimit Goyal
analystAnd sir, finally, you brought up something like two land parcels. We're still waiting on that, correct? Is Q3 going to follow the same pattern, or will we outperform significantly? Because to do so, we have to outperform significantly compared with what we achieved in Q1 and Q2. No, I also said we have four land parcels, versus two not received. So four is good enough to offset the loss from this H1. Those two were planned in a distributed way anyway, you could say. It was only for 25, 26. Got it, sir. Got it. That's all from my end, sir. Thanks.
P. P. Gupta
executiveThanks.
Operator
operatorThank you. Ladies and gentlemen, if you'd like to pose a question, you can press star and one. Our next question comes from Palak at MIV Investment Management. Please go ahead. Hi, sir. My question concerns our FGD business. So recently, we came across an article where it was mentioned that based on the study, a finding was made that sulfur emission from the coal-based power plant is not harmful to the environment, meaning it's not impacting the air quality. So there has been a suggested draft that the government of India may stop the FGD tenders. And from my understanding, our order book currently stands at about INR 1,000 crore. So can you help me understand the impact — what do you think about the norms?
P. P. Gupta
executiveI also told you that there's been a deceleration in this area following the NITI Aayog study and the political-level controversy over whether our AQI will include sulfur or whether it's harmful. Ramesh of Congress has stated the opposite. He previously served as environment minister. He has challenged the Ministry of Power's current decision. But apart from that, we have an existing order worth INR 1,200 crore that will keep being executed according to the program, which is under execution. And we aren't anticipating bigger business from it either, as I told you, we are also. Because we don't want to take on more than one project a year. Or perhaps now we could say one project every two years, maybe from private or SGBs. Certain critical pockets nearer to urban areas or semi-urban areas will still need to deploy according to the CA report. It's not a complete no. But yes, it will now be project-specific pilot. At the same time, the report also confirms that projects already in execution or ordered will be implemented as they are, without any interruption. So that is the current status in this space. Okay. So we aren't expecting any significant inflow from the segment.
P. P. Gupta
executiveSure. On that vertical — you're correct. But this vertical can handle balance of plant work for us at generating plants, which we used to do prior to moving over to FGDs. So mechanical auxiliary work in the balance of plant is what we'll take up now. The company's capacity is going to be redeployed across the critical super ultra super critical power plants of 80 gigawatt that NTPC, other state utilities, or CPSUs will deploy, which they are using business for now over the coming four years. Okay, sir. Understood. Thank you.
Operator
operatorThanks. Our next question comes from Srihansh Rathani at SG Securities. Your line is open. Hello, and good afternoon, sir. I have two questions regarding the data center side. First, what would the cost per megawatt be for these edge data centers? On the prior call, I believe you said it runs higher than the data centers you'd have in Chennai and Calcutta, so I just wanted to get clarity on that.
P. P. Gupta
executiveYes. Ankit, would you like to take that one?
Ankit Saraiya
executiveRight. So you could say it comes to roughly somewhere in the range of 1.75 to 2 times what a hyperscale data center costs. So one can put it at plus or minus 50 lakhs, but around 8 crores for each megawatt. Understood. Okay. Now regarding the Chennai project, how much investment remains for us to make, and how much have we put in so far? How much has already gone in? As of today, we have invested roughly 400 CR. So for phase one, what remains to be spent is only around 50 CR crore, give or take. Okay. So phase one is the 5 megawatt. Yeah. 6 megawatt. 6. Okay. My apologies. Yeah. Okay. But where grid load is concerned, it will be 10 megawatts, as you mentioned. Got it. So when do we expect this center to reach full operational capacity? By March 26. Okay. Okay. And how far along are we when it comes to finalizing customers for this data center? Ankit, so we are in discussions with potentially, I would say, a couple of customers. As of today, we are still in the final construction phase and the commissioning phase. Therefore, most of these customers want to see a project completed, which we had mentioned on the last phone call as well.
Ankit Saraiya
executiveUntil we reach completion, customers won’t feel confident planning their moves, since commissioning can always slip because of unforeseen circumstances. So I’d say the genuine search for customers would start only after the project is commissioned. That said, in the meantime we’re talking with a couple of strong customers. And in the meantime, we’re also talking with a couple of strategic partners who might potentially express interest in this project. But as of today, our main focus is on developing our in-house sales, marketing, and operations team, because Chennai is not the end of life for us. We want to keep participating in this industry through edge data centers and our upcoming data center in Kolkata. So it’s not that we’re still really scouting for a strategic partner, but rather building a team that can sustain this business for us over the long term. Got it. Just a couple of questions, if I can put in. So for these edge data centers, what’s the lead time for this construction time, and when do we expect to operationalize them from T0, for example? So construction time literally depends on the status of many things.
Ankit Saraiya
executiveSo once RailTel hands the land over to us, a few of those sites are partly built, and a few are fully built, where the only thing left for us is fitting out the electromechanical work. That means the construction timeline shifts based on what condition each particular location is in. It could be anywhere from 3 months up to 12 months. We're already building one in Gurugram, and as I said, we should have it commissioned by mid-December — end of this month or mid-December. That one will be our first edge data center to go live. We should be starting the second edge data center in Mumbai around January. That location should be handed over to us in January, since they're still clearing out the area where the plot is being handed over. We've already put in a requisition for another 15 locations so work can begin. We've started visiting those locations. Together with RailTel, we're scouting for land, looking for the most suitable option. As per the contract, I'd say we're supposed to deliver 20 locations each year. But practically speaking, I think we'll see real action and execution on these projects starting next year. This year, though, we should see our first one go live in Gurugram.
Ankit Saraiya
executiveUnderstood, thanks. Only one more question from me. Regarding the Kolkata data centers, should we anticipate the same investment per megawatt as the Chennai center, or will it be more optimized thanks to what we learned from Chennai? My sense is it would be comparable, with a saving of 5 to 10% at most. Okay. All right. Thank you. That's everything from my side. Thank you.
Operator
operatorJust a quick reminder to everyone to ask a question — you can press star and one. Our next question comes from Ashish Soni at Family Office. Please go ahead.
Ashish Soni
analystSir, how do you read the situation on the ground when it comes to transmission projects? We hear the government saying a great deal about the need for many schemes and EPCs. Beyond this land issue, though, what other challenges are you currently seeing on the ground?
P. P. Gupta
executiveOkay, so land acquisition and right of way—that's frequently an issue. There are people who raise objections about siting a tower foundation. We're not the ones building the line itself, but once a land parcel has been acquired and handed over to us, the substation is adjacent and tied to it. The trouble is that ownership across rural India is extremely fragmented, so to get 150 acres or 100 acres, you must buy out from at least 100 landowners. That means handling documentation that involves commissioner-level officials and the land revenue departments—verifying their records and authenticity. So the legal processes, plus details about who owns what and whether owners are willing to give up their parcel—all of that in India remains somewhat arbitrary and difficult. That's why there were 64 approvals from the Government of India and the credit notification. Every legal requirement is in place. Yet our courts don't operate efficiently, and the bureaucratic machinery isn't all that efficient either. Even so, I'd say we're doing the best anywhere in the world.
Ashish Soni
analystBut when you consider the delays in execution caused by all these factors, do you believe the government is stepping in—or that you folks are collaborating with them to make things better? Because we keep hearing that over the next 2 to 3 years, at minimum, a great deal of transmission is being planned. So in terms of government policy, state government, or something along those lines, do you foresee any progress in this area?
P. P. Gupta
executiveOkay, first off, I think the discussion needs to be around states, because this is highly, highly specific to each state. But if we look at the ISGS region, which is a central government project, I would say the willingness is bigger than the reality. Everyone is willing to improve, but so many government departments or government-owned ministries are involved that at times they aren't certain what might slip out here. Still, I will say there is a lot more betterment compared with a year ago or two years ago. In countries such as Europe or the U.S., unless we hold the land parcel or right of way is in place. So the tender itself takes place almost two years late. But in India, we aren't waiting for all these approvals to be in place before tendering or selling out the programs. So it's a kind of hybrid situation where the agency, together with the government, works out what to do. Challenges.
Ashish Soni
analystAlright, sir. Thank you. I appreciate the update.
Operator
operatorThanks. Our next question comes from Shekhar Singh at Beltman. Please go ahead. Yes. Hello, sir. Yes, sir. You can go ahead with your question. Yeah. So what I wanted to ask is whether you have any guidance for fiscal year 26, and is there any room for margin improvement there?
P. P. Gupta
executiveNo. Look, generally speaking, these margins — there's a lot of competition in tariff bidding these days, and with most tariff bidding, the asset owner doesn't have enough room to offer you a better price for the solution. Even so, I'd say the EBITDA Techno has delivered ranks among the best in the industry. Okay. Yeah. Yes. Yes, sir. Also, sir, could the slowdown in state government implementation of smart meters hit our targets of INR 1,000 crore revenue in the years ahead? Because we've been rather slow at rolling out smart meters in the respective states. So on smart meters, I don't think we're slow. There's a delay in creating DDF. The direct debit facility is part of the order, and they have to complete the security documentation before scheme implementation can be taken up. Because unless the state government commits to paying through banking channels from the very account it holds for revenue collection, the scheme isn't achieved at zero date. The zero date is when DTF is created. So after that, it's going all right as far as I can see, apart from a bit of interruption here or there.
P. P. Gupta
executiveSo that isn’t going to work. All right. All right, sir. Essentially, sir, we are on the right path to hit the revenue targets for 2028 of approximately 10,000 CR. Yeah. Absolutely. There’s no problem at all. Thank you. Thank you, sir. Best of luck.
Operator
operatorThank you. As a reminder to everyone on the call, please ask a question by pressing star and one. Our next question comes from Mohit Kumar at ICICI Securities. Please go ahead. Hi. Thanks for the chance. My only question is this: considering how much bidding took place during the last fiscal year and in this first half, right? So in that sense, are you seeing plenty of inquiries and opportunities, and do you think there is a fair chance we will bid this guidance of INR 1,500 crore in additional order inflow during H2?
P. P. Gupta
executiveYeah, and actually, I'd go further than that, I'd say. Truly. As I mentioned, out of 1,500, we're already L1 on 670 crore. And the board has already secured those concessions. So I believe those orders will be converted before December. That said, there's no question we might exceed this number as well. But do you think we'll exceed it by a wide margin, considering Fargate has won approximately INR 80,000 crore during the first half — INR 80,000 crore, really? That's an extremely large figure, isn't it? So we handle only station work, nothing else. So perhaps out of 80,000 crore, station work amounts to no more than 4,000 CR. 4,000 CR. Okay. Yeah. We don't provide transformer reactors — they buy those directly. There are lines. There are HVDC packages. So each of those represents a different kind of solution. But there are STATCOM packages too. There are far too many STATCOM packages, sir, correct? Yeah. STATCOM is smart these days. They've now qualified us. So we're qualified based on our own merit and experience. So we've found a bid now, KPS1, KPS2. So those bids are being evaluated. Is that correct, sir?
Ankit Saraiya
executiveNot bid yet, sir. Once the assets are qualified, they've started sending us inquiries. Okay. And from STATCOM, how many bidders do we have? Three, four? Four should be the maximum. Got it, sir. My second question: given that a large volume of bidding is taking place, of course, right? Which also means we're winning a fair number of new opportunities in TBCB, right? So how are you viewing this opportunity? Are you seeing plenty of smaller opportunities where you can take part, or do you think only larger opportunities are coming, and those larger ones don't interest us?
P. P. Gupta
executiveNo, it's larger — we're definitely not interested in that. We don't want any part of those aggressive tariff bids and RAs afterwards. But up to INR 750 crore, or perhaps where substation work is bigger than that, we might stretch to INR 1,000 crore. So that's our appetite, sir, on that front. But certainly, many other companies are now approaching us to join in, such as IndiGrid or Apraava. So we don't mind joining them as a form of risk sharing. The question is what sort of risk, or appetite for risk, you have across all this asset ownership. Because owning assets isn't Techno's business. Our business is EPC. But could one take a smaller and smaller share — a smaller and smaller shareholding — in these SPVs and still land the EPC contract? That would benefit us, right? Yeah. We've done that. We're integrated now in Dhule and Srinagar. The two concessions, the one. We've taken a 20% stake in the Dhule SPV. And we're executing, deploying their solutions. Worth roughly INR 1,000 crore. Is there any new opportunity, any fresh tender pipeline in smart meters? Are you seeing that, or is it very slow at the moment, with most of them shifting to the next fiscal?
P. P. Gupta
executiveLook, in smart meter, we're not active — let me put it that way. If a solid opportunity comes along where we can secure our price and terms, fine, that works. If not, we see counterparty risk as high. I mean, that was the case with discoms earlier on power agreements and renewable power. We were the first EPC company in EPC when we built 200 megawatts, and we went through enormous litigations with TANGEDCO across all our deals. On the EPC side, we apply the same approach. The last question is infrastructure, sir. Are you seeing some movement? Do you see some opportunity emerging that might interest you, or is it very slow? Sir, there's no perfect answer to your question. But if any sweetened opportunity appears, we won't miss it. If it's multilaterally funded or bilaterally funded, we're always there. But if any discom or any state entity wants to do a project from its own resources, we definitely won't be there. Understood, sir. Thank you all the way, sir. Thank you.
Operator
operatorThanks. Just a reminder for everyone to ask a question — you can press star and one. Again, a reminder for all participants to ask a question — press star and one. Since no more questions have come in from the participants, I'll now turn the conference over to Mr. P.P. Gupta. Thank you. And over to you, sir. Yeah.
P. P. Gupta
executiveI appreciate all of you for the very active and healthy participation and for being on the conference call with us. If you still have any query related to our performance, please drop us a mail or do visit us whenever you are in this part of the country. We now have an equally large office in Gurugram, so at the Motorola Excellence Center in Sector 14 of Gurugram. You are welcome to drop in and to see us actually at work. I thank once again everybody for joining the conference.
Operator
operatorI appreciate it. Speaking for Asian Markets Securities Limited, we’re bringing this conference to a close here. We’re grateful that you were with us, and at this point you’re free to leave the call.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Techno Electric & Engineering Company Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Techno Electric & Engineering Company Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Techno Electric & Engineering Company Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.