Techno Electric & Engineering Company Limited (TECHNOE) Earnings Call Transcript & Summary
February 12, 2025
Earnings Call Speaker Segments
Operator
operatorGood day, everyone, and welcome to the Q3 FY25 earnings conference call for Techno Electric & Engineering Company Limited, hosted by Asian Markets Securities. I'd like to remind everyone that all participant lines will remain in listen-only mode, and following the presentation there will be a chance for you to ask questions. If you require assistance at any point during this conference, please signal the operator by pressing star and then zero on your touch-tone phone. Please be aware that this conference is being recorded. I'll now turn the conference over to Mr. Suraj Sonulkar of Asian Markets Securities. Thank you, and over to you, sir.
Suraj Sonulkar
analystThanks, Dory. Good afternoon, everyone. Speaking for Asian Markets Securities, we're glad to have all of you join the Q3 FY25 earnings conference call of Techno Electric & Engineering Company Limited. Joining us today are Mr. P.P. Gupta, Chairman and Managing Director, and Mr. Ankit Saraiya, Director, representing the company. I'd ask Gupta to walk us through an overview of the company's quarterly results, and after that we'll move on to the Q&A session. Gupta, over to you.
P. P. Gupta
executiveThank you, dear. A very good afternoon to all of you, and I welcome everyone to discuss Techno Electric's financial results for this quarter, Q3, and the nine months ended 31st December 2024. Anything said on this call that reflects our outlook for the future, or that could be construed as a forward-looking statement, must be reviewed in conjunction with the risks that the industry and company faces. Let me highlight our performance. As you all know, the company has an SPV to set up a 40-MW grid-load data center at Chennai. The asset is nearing completion, staged for the phase I, but still not revenue-accretive, but value-accretive. It is consolidated. The consolidated results will knock off the financials of the SPV of data center. Let me now take up the Q3 results for financial year 2025. The total revenue for this year for EPC business is INR 676 crore, up by 85% year-on-year. The EBITDA for the company stands at INR 99.22 crore, up by 120% year-on-year. EBITDA margin for the company is at 14.68%. Other income for Q3 is at INR 43.86 crore, compared to around INR 42 crore last year. The profit before tax for this quarter is at INR 138 crore, up by 71% year-on-year.
P. P. Gupta
executiveProfit after tax came in at INR 105 crore, a rise of 35%, while earnings per share for this quarter stand at Rs. 9. Turning to the nine-month figures, revenue reached INR 1,590 crores — close to INR 1,600 crore, marking a 33% increase, up 33% year-on-year. EBITDA is INR 225 crore, which is 34% higher year-on-year. The EBITDA margin came to 14.17%, versus 13.4% a year ago. Other income amounted to INR 105 crore. Profit before tax reached INR 318 crore, up 27%. Profit before tax is INR 250 CR, an increase of 24%, and EPS is roughly 22, against 19 last year. Our current investment value — that is, cash or cash equivalent — is approximately INR INR 2,500 CR, or Rs. 220 per share. Order intake and bidding momentum has stayed very strong, both for the sector and for techno as well, and we hold a robust order book of roughly INR 9,700 crore as of December 2024. Orders valued at INR 1,100 CR were received during this quarter, bringing this year's tally to approximately INR 750 CR. We are further along on about INR 1,600 crore of business, which we expect to materialize within this quarter.
P. P. Gupta
executiveMost of these are power substations or grids located at Karur, Bidar, Chitradurga, and Madhugiri, or involve private players such as Adani or Sterlite. A number of bids are in the pipeline, and we're confident of securing further orders worth roughly another INR 2,000 CR this year, which would bring the company's total order book booked during this year to approximately INR 3,500 crore. We expect to end the year with an unexecuted order backlog of almost about 10,000 CR+, marking the first time in the company's history. That essentially mirrors post-order execution for the current year. With growth on a year-on-year basis, we'll have sufficient orders in hand to sustain the growth momentum. During the year, the company successfully raised a QIP of INR 1,250 crore in the current financial year, so we now have many new reputed investors on board. On the outlook, I'd say the growth momentum we had in financial year 2024 — as I shared with you, in 2022 to 23 we were averaging INR 75 crore per month, which improved to INR 125 crore in financial year 2024 — and this year we are targeting INR 200 crore per year from INR 125 crore last year, and for this financial year we should expect a top line of around INR 2,400 crore, and generally Q4 accounts for about 30% of the top line, and this will tally with the revenue already achieved in Q3.
P. P. Gupta
executiveFor the coming year, our target is to push that further up to INR 300 crore each month for financial year 2026. We anticipate bigger business in transmission and data centers. As all of you are aware, looking back, energy growth was nearly negligible across the last eight years, and as recently as 2023 — over the past two years, we have been witnessing strong energy demand, with growth running at close to double digit. The grid's present peak load demand is around 240 GW, and that figure is expected to reach 400 GW by 2030, which would lift per capita consumption from 1,250 units to 1,750 units by 2030. To satisfy this demand, power plant capacity is slated for enhancement both in conventional power by 80 GW and also through renewable energy, or energy transformation, to hit a target of 500 GW by 2030, and this was reaffirmed by PM yesterday at the India Energy Week. All of this implies that transmission in renewable power, as I would like to share with you, is 4X over 1X in conventional power, so all this means the sector is now full of — is now transforming by deploying all the transmission capacity as required for renewable power, and is now transforming by deploying high-end solutions, namely 765 kV AIS, GIS transmission solutions, STATCOM solutions, VSC HVDC solutions, best BESS facilities to make the renewable power eligible to be base load power, and where your company has a larger presence than any other entity in this marketplace, particularly in building these stations.
P. P. Gupta
executiveAt the moment, your company concentrates on these areas: transmission solutions — mostly 765 kV or 400 kV AIS and GIS — smart metering, FGD (what we refer to as AQI solutions), digitization or modernization of DISCOM power distribution networks, and also hyperscale edge data centers. Renewables make up 43% of total installed capacity today, and that share should reach roughly 64% by 2030; deployment growth runs at about 16% CAGR versus 4% for fossil fuels. This year's budget gives the renewable power sector a significantly bigger allocation — nearly 40% above last year — now standing at about INR 25,000 crore. The CEA transmission report, covering how to integrate 500 GW of renewable capacity into the grid by 2030, pinpoints multiple transmission links totaling approximately 50,000 circuit km of lines plus another INR 4.5 lakh MVA of transformer capacity. With these ISTS additions, interregional capacity will rise to about 168 GW by 2032. The national electricity plan, in transmission alone, offers an investment opportunity of roughly INR 10 lakh crore over the coming 7 to 8 years.
P. P. Gupta
executiveBeyond that, I'd note that in the budget you've reviewed, the government has also begun focusing at the same time on constructing intra-state transmission systems, and for that they've set aside an extra 0.5% of GSDP — gross state domestic product — for all states combined, which would lift the estimated opportunity by another INR 1.5 lakh crore. States have set a deadline of March 25 for turning in their proposals so the Ministry of MNRE and MoP can scrutinize them. Beyond that, we're now also seeing opportunities in STATCOMs, which in the past we pursued together with overseas partners. Power grid has revised the qualification criteria, and we now qualify on our own merit to back power grid on this critical mission. Data centers are likewise going to generate substantial additional power demand. As was said earlier, the government has additionally allotted 80 GW of hydro and thermal capacity to expand the generation segment. In addition, balance of plant and switchyard facilities deployment plus grid integration will present an opportunity. NTPC and DVC have each issued tenders for grid integration and switchyard deployment at four locations. On the distribution side, a great deal of activity is going to happen under the RDSS going forward.
P. P. Gupta
executiveSmart metering is now being carried out at full scale, and the distribution losses of the DISCOMs that it is meant to contain are already visible. We are also concentrating on reinforcing power distribution networks to make them smarter and more intelligent through modernization as well as digitization. So the RDSS likewise includes an allocation of funds for city modernization, which will present opportunity in this segment too. Roughly 22.24 crore meters sit at various stages of award or deployment. Of that figure, to my knowledge, approximately 130 million meters have been ordered out, and only around 20 million stand installed till date. The Finance Minister, in our budget for the current year, also stated that the government will be incentivizing electricity distribution and augmentation of infrastructure transmission capacity, with efforts to improve the financial health of power firms and their capacity. I believe this will open up new opportunities for investors. The budget document also disclosed that reform-based distribution schemes, which carry an allocation of about INR 16,000 crore as well, are strictly aimed at inviting private investment in this segment. I trust your company is firmly placed and is competent to take part in this program. Basically, all of this implies that the government is looking at providing financial reforms that are reform-based, with the objective of ensuring 24/7 quality and sustainable power supply for all and a financially viable power sector.
P. P. Gupta
executiveThe government also offers this pathway to DISCOMs when they take up reform packages, shift ownership of distribution companies, or adopt different franchise models at the distribution level, multiple supply franchises included. Beyond that, we are certain that energy storage solutions such as battery, gas, or public storage amounting to no less than 20% of this capacity will be needed, and on top of that, numerous types of capacity-compatible power management solutions in the grid will have to provide additional support, and we observe substantial activity in which Techno is fully qualified and technically competent to take part. In the FGD segment, we are seeing slow movement, with the government having finally extended the implementation period by three years, and this is encouraging states to now place orders for the packages that were expensed over the last year, more than a year, and we expect that five to 10 GW per year should be ordered out by the State Electricity Board, plus a bit from the private sector as well in this space. Our FGD order is progressing very normally in Rajasthan. In the transmission segment, TBCB bidding is underway for almost 50 GW, 50 to 100 GW now, and a great deal of bidding is in progress.
P. P. Gupta
executiveRight now, what we're seeing is that each month, four to five concessions get awarded to one player or another in this space, and the most recent entrant is Reliance — Reliance, Mukesh Ambani's company, is also in this space. So it's very exciting to know that one more resourceful company has joined this segment, and that they find this space exciting and rewarding. Total bids open for transmission come to around INR 40,000 crore, of which Techno is expected to book orders of roughly INR 2,500 crore per year over the next two to four years. We currently hold orders worth more than about INR 6,000 crore for transmission in this space, without our own orders in TBCB, and we are advancing another roughly INR 1,600 crore worth of orders in this segment. As you know, we are also successfully executing two concessions with a revenue stream of INR 2,800 crore over the concession period. Similarly, we also have one concession for deploying 2.5 million smart meters. In the metering segment, we expect to receive orders worth about a million meters every year, and we have already secured orders worth about 2.5 million, with an investment target of INR 2,500 crore in this space.
P. P. Gupta
executiveWe’ve already deployed roughly 500,000 of that so far. When it comes to data centers, our view is that digitization along with cloud-based services—both public and private—is the biggest factor driving data center growth and demand, in addition to other drivers like 5G transmission and the many more ISPs or IoTs in this area. The Indian data center market is projected at around 2 GW by 2025 and over 7 GW by 2030. There’s significant expansion being planned here, which could build up at a CAGR of at least 20%, and in money terms that could mean close to $2 billion of investment each year, rising to $5 billion by 2030. The growth drivers here are public cloud adoption, local data localization, policy incentives, digital transformation, and technological advances that enable rollout of 5G and AI—and we’re seeing greater adoption of AI, and 5G and virtual reality will transform this space. IoT, big data, and cloud computing will be the next phase. Turning to our own Techno data centers, I’d say we’re now at a very advanced stage of being ready for operations for the first phase of the 24 MW IT load hyperscale data center at Techno, and it’s now nearing completion with total capital involvement of about INR 450 crore.
P. P. Gupta
executiveThis project has experienced some hold-ups because of regulatory matters and permissions that need to be secured from local authorities. Still, I'd describe it as a state-of-the-art effort — the first of its kind undertaken by Techno — and it ranks among the finest in this space within the country. It will be ready for service by March 26, and we anticipate leasing it out in one of the coming years. We have Ankit here — would you like to speak now? Yes, sure. Let me briefly explain where things stand with our Chennai data center: as was mentioned, we're very near to reaching ready for service. We should be able to hit RFS on this project by March 25, with the first phase of 5.6 MW up and available to serve customers. Our hope is to lease that capacity within the first three to six months after commissioning. That said, this project has certainly been delayed for a number of reasons — though the causes aren't directly attributable to us, stemming largely from the regulatory requirements and permissions needed to get the project operational. On top of that, supply chain disruptions occurred because of certain crises that unfolded in the Red Sea, along with a shortage of semiconductors. Ultimately, though, we pushed through, and we now see a possible ready for service by March 25, which falls somewhere during the next month.
P. P. Gupta
executiveThat said, with the project rollout now at its final stages, our engagement with prospective customers has grown deeper and broader. We're holding in-depth talks with certain major global cloud players, and their feedback has been highly favorable. On the domestic front, we've approached customers in the BFSI segment, a number of content delivery network operators, some domestic cloud players, and some public sector enterprises, and every single one of them has given us a very, very encouraging response. In particular, we can point to significant interest from a public sector bank and a multinational private sector bank, and both are putting us through a formal evaluation process, which ought to wrap up in the coming quarter. On top of that, we think AI has genuinely lifted the industry to greater heights and bigger opportunities. We're seeing a very large surge in demand for data centers, especially for AI purposes, and our Chennai facility is very much AI ready — possibly one of the only data centers that are truly AI ready, thanks to the designed rack density and the cooling technology we've used. Against this backdrop, we've drawn significant interest from companies in the artificial intelligence field, and one of them is a unicorn that is actively in discussions with us for an initial 2 MW-3 MW lease to start with, which could potentially lead to consumption of the entire data center.
P. P. Gupta
executiveBeyond that, I believe everyone is aware, in some form or another, of the IndiaAI Mission, which launched recently, and some players are waiting for impanelment. We're talking with several of these players about providing our data center for their infrastructure needs, and since this facility is genuinely AI ready, we consistently rank among the most preferred partners. In addition, we've begun establishing a very deep and strong network of distributors and channel partners, through which we're reaching medium and small enterprises nationwide for their data center needs, and we've seen positive and significant interest from all kinds of enterprises via our partners, and we're working closely with them to engage these companies on their digital transformation journey. Also, as we mentioned, we are to execute edge data centers across 102 cities together with the RailTel Corporation, and we're very close to commissioning our first edge data center in Gurgaon. That should take place within the next 7 to 10 days. We could perhaps say that 50% of that capacity is very near to being leased, or one might assume it is almost leased.
P. P. Gupta
executiveAs for the other 50% of capacity, we're actively talking with enterprises and the public sector, and we expect to have the full 100% at Gurgaon leased out within a month of commissioning this project. It's a small edge data center — 200 kW. Mumbai is the next site we intend to commission. Construction on that project gets underway by the first week of April, and commissioning should happen in August 2025. Mumbai is clearly the most preferred market for data centers, and we're right in the heart of the city — in South Mumbai itself, at Mahalakshmi. You couldn't ask for a better data center location, and we're in close talks with one of India's large conglomerates to lease them 100% of the Mumbai capacity starting from the commissioning date itself. Beyond that, we're speaking with global hyperscalers about contracting at least four to five data centers across tier two and tier three cities. As the next step, in addition to Gurgaon and Mumbai, we're looking to begin developing data centers in Gandhinagar, Bhopal, Guwahati, Bhubaneswar, and Hyderabad, with those constructions starting at some point during 2025 itself.
P. P. Gupta
executiveSeparately from that, a bit outside the RailTel contract, we plan to commission a very small edge data center in Calcutta, driven by significant interest from a global CDN player. This will let us, for the first time, not only offer co-location services but also move into bare metal services, since that is what the customer requires. We look forward to engaging with that customer soon on a contractual basis and getting this data center up and running within the next four to five months. As for our Calcutta data center, we have begun the pre-construction activities. The design and engineering consultant has been onboarded. The project management consultant has been onboarded. The local consultants for building plan approvals, fire approvals, and other approvals as required have been onboarded, and we have even started very basic construction of the compound wall at this location, and we are hopeful of commissioning the Calcutta project by mid to end of 2027. Separately, and excitingly, we are now getting up to start our services and Infrastructure as a Service space. We are launching services in the Infrastructure as a Service space by providing private cloud services.
P. P. Gupta
executiveWe’re currently talking with a couple of customers about what they need for private cloud, and we’re very near to signing those contracts and delivering cloud services under a private cloud model in the second or third quarter of financial year 2026. Right now, I’d say we have an active funnel of more than 10 MW, including some key cloud opportunities. On the organization front, we recently brought in Mr. Amit Agarwal as president of data centers. Previously, he served as chief business officer for the Iron Mountain and WebWerks joint venture, and we are putting together a considerably large sales and marketing organization so that we can reach the market 100% on our own, and to support that setup, we recently opened our Mumbai office at Lower Parel. That covers the data center side, and we’ll be glad to take questions in Q&A. Thank you. As all of you know, over the last five years, the company has successfully built and monetized assets in renewable power generation and transmission. We were the first BOOT IPP in renewable power, or the triple P model, in transmission, and all of those assets have been monetized, which gives us cash that, together with QIP cash, now stands at INR 2,500 CR, to be deployed in the company’s next phase of growth.
P. P. Gupta
executiveAnd as I said, over the past 3 years the company has grown nearly four-fold, going from INR 75 CR per month to INR 300 CR by March 2026. That's the goal, with INR 200 CR per month during the current year. And we reaffirm that our EPS for this year will be no less than INR 35 Rs as committed, and for next year, or the current year — what I mean is 25, 26 — it will be almost 50+. So with that, I invite the questions, and we'll be glad to detail further.
Operator
operatorThanks a lot. At this point we'll move into the question-and-answer portion. To ask a question, you can press star and one on your touch-tone phone. Should you want to take yourself out of the queue, just press star and two. We ask participants to use their handsets when posing a question. Ladies and gentlemen, we'll pause briefly now while the queue is put together. Our first question comes from Resham Jain of DSP Asset Managers. Please go ahead.
Resham Jain
analystHi, good evening. My question is about data centers. Given that several things are happening in Chennai—a new plant or new setup coming in Kolkata, and then multiple edge data centers—over the next five years, what kind of revenue, EBITDA, and capital employed will go into data centers? If you could just give us a broad directional sense, how are you thinking about that?
P. P. Gupta
executiveResham, first off, that's a really mature question to be putting to a young person, I have to say. And second, on average, if all goes according to projections, data center will become the face of the company going forward — that's how we're projecting it. And if not within five years, then at least by 2030, we should have capacity of no less than 250 MW, and at least at these locations, no fewer than 100 countrywide, edge data centers included. And we will definitely be looking at revenue of no less than, I'd say, almost about INR 250 million — INR 250 million per year, if not more, from this capacity. With that, Ankit, would you like to add anything more?
Ankit Saraiya
executiveSure, absolutely. So the way things are moving right now, it's really hard to pin down, because this industry is extremely dynamic. Resham, if you look at what's taken place in the industry over the last 15 days—from U.S. $500 billion for AI infrastructure, then the announcement of the largest data centers in Jamnagar, and then what we all heard about from China, which is DeepSeek—that's how dynamic and disruptive this industry is. And ultimately, when we talk about the infrastructure for any such application, it's data centers only. In an industry this disruptive, it becomes very, very difficult for us to be very predictable in nature about what we can feel it would be in the next four to five years. But in the most conservative sense, as P.P. Gupta put it up, we should see at least 200 MW-250 MW come in by Techno Electric and at least $250 million of revenue flowing in from data center and its allied services. But let me say that the way this industry is unfolding, it's highly—it has immense opportunity, and one has to keep unlocking them and growing with them.
Ankit Saraiya
executiveAnd in the end, it could turn out to sound and take shape in a way that's quite different from what all of us picture right now.
Resham Jain
analystGot it — that's very clear. And sir, my second question concerns the transmission business. During the last year, there were particular kinds of supply chain difficulties, where obtaining material itself was not easy. Are you observing that some of those difficulties are easing, and how does the execution appear from where you sit?
P. P. Gupta
executiveThose difficulties are going to stay, and they will keep going in number one. Techno is probably the oldest participant in this segment, and the ties we have with all these suppliers are of a partnership nature. Today we are consuming no less than 10% of the supply chain in this segment in the market, and by next year that is likely to reach 15%. We are hopeful that, despite all these challenges, we'll be able to get priority from our partners. Supply chain will remain a concern for the overall market, but not challenging, I would say. Largely the land parcels, where we got delayed in the first half of the year, while the land parcels are becoming difficult for the concessionaires to arrange and hand over to us for the deployment of the facility. That is one delay in the first two quarters. Now, all those are available, except one or two still to be given by corporate and a private player. But now we mostly have that land, have those land parcels, and hence you see the growth in the output also.
Resham Jain
analystUnderstood, sir. Thank you very much. Wishing you all the best, sir.
Operator
operatorThanks. Our following question comes from Saurabh Shah at AUM. Go right ahead.
Saurabh Shah
analystHello, sir. Are you able to hear me?
P. P. Gupta
executiveYeah. Yeah, welcome.
Saurabh Shah
analystHey there. I'd like to go over with you the orders we've got for those edge-type data centers, plus the other government contracts. On the margin side, how do you see them shaking out, considering how your contracts are structured and the procurement environment you're seeing and so on? Execution could stretch out over a longer period.
P. P. Gupta
executiveWe hold edge data center concessions for 20 years, with an option to extend another five years. These are revenue-sharing arrangements with RailTel, and margins will be entirely driven by the tariffs or leasing rentals at which we can deploy these facilities and by the applications for which they can be deployed. As Ankit already told you, these are somewhat developing, disruptive but rewarding situations. Because of that, margins are hard to state in a concession, since in this case they will all be measured as an IRR on the investment, and we hope that IRR will be no lower than 20%. Ankit, would you like to add anything?
Ankit Saraiya
executiveYes. Since these are BOT contracts — a type of BOT arrangement running 20 to 25 years — you really have to evaluate them through the lens of cash flow and IRR. And we hope to hit high teens or early 20s in IRR on these projects. So there isn't really any upfronting of margin as an EPC that we could genuinely compare against a transmission EPC that we also do. Right. Well, you've tracked this company for many years, and historically we've been extremely careful to make sure we take on high margin projects. So this appears a bit more open-ended than the question of pricing and all of that, and to some degree it isn't within our control. So I just wanted to check how you all were viewing that decision. Oh, this will be. I can assure you it is more rewarding than our EPCs. That's what I'll say.
Saurabh Shah
analystAlright, thank you, sir.
Operator
operatorThanks. We’ll take the next question from Abhijit Mitra at ICICI Securities. Please go ahead.
Abhijit Mitra
unknownYeah, thanks for giving me the chance. Sir, to start with, regarding the data center business, how much capital have we already put in? And looking ahead, what's the plan for allocating capital to the Chennai data center?
P. P. Gupta
executiveSo far, we've put INR 450 CR to work. That covers phase I, plus perhaps another INR 25 CR or so, give or take, for balancing items as we close things out. And we'll only move on to the next phase once this one has been fully deployed. So you could say we'll be spending roughly another INR 500 CR to INR 600 CR across the coming two years. By March 2026, let's say, the Chennai data center will see a further INR 600 CR. But that won't kick off until the second half of next year.
Abhijit Mitra
unknownOkay, so about the revenue accretion from that capital we've already put to work — the INR 450 crore — we're expecting that revenue accretion to come maybe from H2 FY26 or FY27. Is that the right way to understand it?
P. P. Gupta
executiveNo. It runs from 2025 through 2026. For Q2, you could say it will begin flowing.
Abhijit Mitra
unknownOkay, and regarding the non-hyperscale data centers — the edge facilities such as Gurgaon, Mumbai, and the RailTel sites — what does the capital allocation plan look like for those? Is there a defined plan for capital allocation there, or is it more that whenever we spot a good opportunity in edge data centers, we'll pursue it?
Ankit Saraiya
executiveNo. So let me — yeah. Please. So let me make this clear for you, starting with Chennai and then moving to the edge data centers. As was said, Chennai data centers ought to begin generating revenues starting in the second quarter of financial year 2026. From here on, you can expect INR 200 crore to INR 250 crore of CapEx allocated to the Chennai data center each year to expand the phases until we have commissioned the full 24MW. That said, revenues will begin flowing from the second quarter of financial year 2026. On the edge data centers, clearly, it hinges on how the industry takes shape, but our target is at minimum, as the contract requires, we must establish 20 locations annually. Practically speaking, though, we assume we will be starting somewhere between 8 and 12 locations each year, and that stems from the contract we hold with RailTel. The locations we pick, however, will determine the CapEx required, since not every location will be a data center of the same size. Each site could differ. For example, Gurgaon was a smaller one at 200 kW, whereas Mumbai is bigger, scaling to roughly a bit over half a megawatt.
Ankit Saraiya
executiveIn the same way, the facilities we're talking about in Gandhinagar and Indore could each reach roughly a megawatt on average. Bhopal, likewise, might come in at around a megawatt. So the size differs from one location to another. They aren't all identical. And how much CapEx we spend will be set by how many locations we take on during a year. Still, under any scenario, we expect to see no less than INR 150-odd crores up to INR 200 crores in CapEx each year, once the RailTel project is running under smooth operating procedure.
P. P. Gupta
executiveBut I might add that, as you correctly noted, some of these will be driven by opportunities, and which ones get priority will be determined by the opportunity itself. As Ankit mentioned, CapEx will come to roughly INR 200 CR ± each year, depending on the capacity mix in each pocket.
Ankit Saraiya
executiveOkay, sir. So basically, roughly 8 to 10 to 12 sites per year when it comes to the edge data center, and every one of those would average somewhere between 500 kW and 1 MW.
Abhijit Mitra
unknownYes, that's exactly right. To begin with. But as that location warms up over the years, they'll keep building. They'll grow further into the capacity.
Ankit Saraiya
executiveOkay, okay.
Abhijit Mitra
unknownAlso, the second thing—regarding the T&D EPC business, I didn’t get the order inflow figure. Could you say it again for Q3 and for the nine months of FY25? Yeah. This year, as I mentioned, overall order intake is going to be roughly INR 3,500 CR. So far we’ve already booked orders of approximately INR 750 CR, or INR 1,800 CR. And for this quarter, it’s about INR 1,100 CR.
P. P. Gupta
executiveWe also hold the L1 position on a further INR 1,600 CR, and that will turn into orders. Concessions have already been won by the developers. So it's nearly a formality — they acquire the SPV and the land parcel, and then corporate releases the orders. Lately, their belief is that until they have a land parcel, they'll prefer to hold off issuing the LOI. But they are committed to issuing it. So it will come to roughly INR 3,500 crore this year. And we should end the year with an order backlog of INR 10,000 CR+. Right.
Abhijit Mitra
unknownSo this INR 3,500 CR is basically all clean EPC?
P. P. Gupta
executiveYes. For sure. EPC. All right.
Abhijit Mitra
unknownAnd how about the portion outside T&D — for instance, power generation or the smart metering business?
P. P. Gupta
executiveNo. So as you're aware, we're carrying out the FGD order. Roughly INR 1,250 CR of it remains unexecuted. Completing that will take a further two years. Beyond that, we also have a business on the distribution side—digitizing or modernizing the distribution network—for which we're doing about INR 300 crore for DVC. And we anticipate more business in this area. In a similar vein, we're deploying smart meters. That's an additional business worth INR 2,500 crore. We have our own TBCB projects too, with a CapEx of approximately INR 700 crore ±.
Abhijit Mitra
unknownOkay, sir. Thanks a lot for taking the question. That's everything from my side. Thank you, sir.
Operator
operatorThanks. Ladies and gentlemen, so that management can take questions from everyone waiting in the queue, we ask that each participant please limit themselves to two questions. You're welcome to rejoin the queue for follow-up questions. Our next question comes from the line of CA Garvit Goyal with Nvest Analytics. Please go ahead.
CA Garvit Goyal
analystHello. Can you hear me? Yes, sir, we can hear you. Go ahead. Good evening, sir. Congratulations on a decent set of numbers. My question is only about the data center. As you said, starting in Q2 FY26, the Chennai data center will begin adding to revenue. So I just want to know what contribution is anticipated in FY26 from that data center to our top line?
P. P. Gupta
executiveTo be honest, that’s not something we’ve looked at. Should it materialize, that would be additional upside — you can count on that. On average, though, our expectation is that we should at minimum aim for roughly INR 100 CR, with a range of anywhere from INR 50 CR to INR 100 CR for the year.
CA Garvit Goyal
analystGot it, sir. And second, regarding guidance — for this year, our guidance stands at INR 250 CR on a consolidated basis. So can we be confident about hitting that guidance?
P. P. Gupta
executiveWe need to hit roughly INR 800 CR in Q4.
CA Garvit Goyal
analystSo do we have enough confidence to hit that figure, sir? And then, secondly, regarding next year — I believe earlier you gave guidance of 50 for EPS. And this time, in the opening remarks, if I heard correctly, you said 45. So what's behind that decrease?
P. P. Gupta
executiveNo, 45 hasn't come up from me. First off, what I said was that this year our average should come to INR 200 CR. And Q4 typically accounts for roughly 30% of the top line. So as a Q4, it will definitely land somewhere at INR 750 CR-INR 800 CR. And 35 will be the EPS. For Q 2025, 2026, I stated that our top line will be around INR 300 crore each month. So you can expect a top line of roughly INR 3,500, INR 3,600 crore, along with an EPS of INR 50 rupees. That is what I reaffirmed.
CA Garvit Goyal
analystUnderstood. Understood. I believe I misheard that. Still, I think those figures stand on their own. What about the consolidated top line, sir? Sir, on a consolidated basis there isn't a very large difference, since they relate solely to our own concessions. They're basically just an accounting requirement, as it were. So it won't be very different, I'd say, at least for next year. And what's the margin guidance, sir?
P. P. Gupta
executiveEBITDA will land in that same 30% to 40% area. You can go with 40%, plus or minus.
CA Garvit Goyal
analystUnderstood, sir. Thanks so much, sir. Appreciate it.
Operator
operatorThanks. Our following question comes from Murtuza with Avendus Capital. You have the floor.
Murtuza Arsiwalla
analystHello. Someone already responded to what I asked. Thanks.
Operator
operatorThanks. We'll take the next question, and it comes from Ashish Soni with Family Office. Go ahead, sir. On the data center services you plan to provide, I believe you mentioned quite a broad range of offerings. So is there any specific service—since you laid out the whole scope—what is our thinking when it comes to leasing out, and what kinds of services? Because that part wasn't clear to me.
P. P. Gupta
executiveAnkit, would you like to take that one?
Ankit Saraiya
executiveYeah. So in data centers, it's always the most fundamental offering that—hello?
P. P. Gupta
executiveAnkit, can you hear us? Ankit, sir, are you able to hear us? Looks like his connection dropped. Sir, could you ask your question again? Regarding data centers, I believe Ankit brought up the range of services. Since he referred to many customer conversations, what's our view? Which services do you plan to prioritize, and is there a specific reason for that? I'm just trying to get clarity, because I heard co-location mentioned. I also heard infrastructure as a service. So I'd just like to understand that more clearly.
Ankit Saraiya
executiveCan everyone hear me at this point?
P. P. Gupta
executiveYou visited our Delhi office. Ankit, have you returned?
Ankit Saraiya
executiveYeah. Can you hear me okay?
P. P. Gupta
executiveYes. You can hear us now.
Ankit Saraiya
executiveRight. So, as I was saying, beyond co-location services—which is the core offering we intend to deliver—we're now also aiming to grow into bare-metal services and infrastructure as a service. Infrastructure as a service can encompass cloud services. Pardon? Why cloud services? Sir, your line isn't clear. Hello?
P. P. Gupta
executiveYes, sir. Go right ahead. Is everything clear at this point? Sir, the floor is yours, sir.
Ankit Saraiya
executiveRight. So, as I mentioned earlier, when it comes to infrastructure as a service, bare-metal offerings are part of it. Cloud services are in there too, along with private cloud services and white glove services, among other things. Let me get a bit more granular. For Chennai specifically, which of those services are you looking to sell? And then perhaps on the next round, for Kolkata, which services do you want to sell? Because in terms of interest, I've heard plenty of interest coming from many customers. So what's our view on that? When we discuss any data center, we'll construct our services portfolio around it. So across every data center we launch — be it Chennai, be it Kolkata, or be it the edge data centers — we'll have the operational bandwidth to deliver all of these services out of each of those data centers. So that's fine. What I'm trying to get at is this: when we go to lease it out to customers, what's our preference regarding what we want to sell? Because right now, from what I hear, there are plenty of customers already in the pipeline. So how are you selecting these services and customers?
P. P. Gupta
executiveWe want to serve every kind of customer. We're not restricting ourselves to a specific customer segment or one that favors a specific service type. For example, in Chennai today, we're in talks about co-location service. We're also discussing bare metal services. Likewise, in Kolkata, we're discussing bare metal service with a content delivery network, and we're in discussions with a couple of customers about private cloud services from a data center in Gurgaon and Mumbai. So it varies by customer and by requirements. Is there a strategy to secure a reference for each of these services with a strong customer, or is it a profitability criterion? I'm trying to understand that strategy from management. On profitability, we're not compromising when delivering any of these services. Each of them is equally or more profitable than the others. Management has no preference when it comes to picking which service we favor over another. Okay. Okay. Thanks. I'll do that.
Operator
operatorThanks. Our next question comes from Rohit Singh at Nvest Analytics. Rohit Singh, your line is now unmuted — go ahead with your question.
Rohit Singh
analystYeah, I've already gotten the answer to my question.
Operator
operatorThanks. Our next question comes from Somil Shah at Paras Investments. Go right ahead.
Somil Shah
analystMy question is only about the data center business. We've recently been hearing that DeepSeek entering this industry is going to hurt data center companies. So I just wanted to get your thoughts on that. Are we seeing any negative impact on our business?
P. P. Gupta
executiveAnkit, take a look at DeepSeek and how it has been developed. Honestly, in my view this is a very, very positive development rather than a negative one. I do understand where the negativity comes from, but you have to appreciate that with a technology this disruptive, one that has only recently been innovated, disruptions of this kind are simply a way of life, and we will see more of them showing up in the news from time to time. And these disruptions are actually very, very good for any industry, because the more affordable and accessible a technology becomes, the cake size increases, the market size increases, and therefore demand always remains at peak. So a disruption never causes a lack of demand. So if tomorrow infrastructure requirements come down and prices for the end consumer improve, we'll see more market participation, and therefore the cake size of the industry will automatically increase. That is exactly what happened in the telecom sector when Jio entered. While they were able to run on bare minimum infrastructure and bring down the cost of telecom services for the end customer, the entire market size went up by possibly four times.
Somil Shah
analystI mean, what we're actually seeing is an effect that's positive, not one that's negative.
P. P. Gupta
executiveNo. Definitely. Yeah. Okay. Okay.
Somil Shah
analystThen as my last question, sir: we've been guiding INR 50 EPS for FY26 and INR 75 EPS for FY27. And on one of the calls, we even said that we expect INR 25 to INR 30 EPS just from the data center business by FY27, FY28. So would that come on top of our INR 75 Rs guidance for FY27?
P. P. Gupta
executiveNo, no, no. Going forward, the data center is going to be included in that INR 75.
Somil Shah
analystAll right, all right, all right. That's all I have to share. Thanks, and best of luck.
Ankit Saraiya
executiveEquity value is going to look different. Where EPS is concerned, yes, but equity value isn’t — it will stay within the subsidiary on a standalone basis. Sorry, I’m not following. One piece relates to revenue, and the other is an equity value test. That’s because valuations differ across businesses, be it transmission, AI, or data centers. What I’m getting at is that the equity value component isn’t included in EPS. EPS is based purely on revenue. So essentially, you’re saying that thanks to the data center business, we can achieve a higher valuation. Is that what you meant? No, no, no. That’s not what I’m saying.
P. P. Gupta
executiveThe EBITDA we produce from any revenue we bring in is going to look quite different from what the transmission business delivers. That's the reason 50 turns into 75. That's the narrative I'm trying to get across. Okay. Okay. So the growth would come from the data center side. Right. Right. In 27. Understood. Understood. On an EPS basis, please, the top line might not grow proportionately.
Somil Shah
analystAlright. Alright, thanks.
Operator
operatorThanks. Our next question comes from Sam Sangwan at Finvestors.com. Go ahead, sir. Congratulations on reporting such a solid set of numbers. Honestly, my question has already been answered — it was about the data center impact of DeepSeek, meaning AI advancements within the data center business — but I believe you've already covered that. Thank you. Our next question comes from Lakshay Agarwal at Growth Sphere Ventures LLP. Go ahead.
Lakshay Agarwal
analystHi there, and thanks for taking my question. I'd like to address this one to Ankit, sir. I just wanted to get some clarity, because we have two data centers that we're working on — the one in Chennai and the one in Kolkata. Previously, with both of them, the plan was for us to handle only the EPC portion, but at this point we're putting our focus on co-location. So I just wanted to understand, on a per-megawatt basis, what rental figure are we looking at — whether calculated monthly or annually — and what margins do we expect to see from that?
Ankit Saraiya
executiveYeah. If you’re looking at a pure co-location service with no infrastructure as a service involved, then you can assume a rental of roughly INR 10 CR–INR 12 CR for each MW of commissioned capacity per year in that scenario.
Lakshay Agarwal
analystOkay. Regarding the margin profile for that same thing, how much would operating it require?
Ankit Saraiya
executiveMargins for EBITDA came in at roughly 80%.
Lakshay Agarwal
analystAlright. Next, you mentioned we're also developing infrastructure as a service, so what's the extra cost needed on a per-megawatt basis to get those servers installed and everything? And on top of that, what rental could we expect for the same?
Ankit Saraiya
executiveBroadly speaking, there are two ways to set up infrastructure as a service: one is largely CapEx-based, and the other is OpEx-based. For infrastructure as a service, we would probably go with a more OpEx-style model instead of CapEx.
Lakshay Agarwal
analystSure — could you expand a little more on the OpEx side? When we talk about OpEx, does that mean we'll be leasing? Are we actually going to rent the servers themselves, or what's the plan for how we'd do that?
P. P. Gupta
executiveYeah. It's possible to get the hardware, plus the technology built on top of it for these kinds of services, more through a lease arrangement or more of a subscription arrangement from technology service providers — and then offer it to the end customer at a higher margin.
Lakshay Agarwal
analystAll right, that's clear. Now regarding our edge data centers — is this purely a build-operate-transfer arrangement, or are we going to handle management on RailTel's behalf as well?
P. P. Gupta
executiveNo, it's a build-operate-transfer structure, and at the end of 25 years the asset goes back to RailTel. During those first 25 years, we're responsible for operating and maintaining these assets, plus bringing in customers for them, delivering O&M services or whatever other service we choose, and after that the revenue is shared with RailTel.
Ankit Saraiya
executiveOh, that's what they call the DBFOT model. It stands for develop, finance, own, operate, and transfer once the concession period is over.
Lakshay Agarwal
analystAlright, got it. And sir, would it be possible for us to come see the Chennai data center?
P. P. Gupta
executiveYes, of course. You're very welcome. We'd actually be delighted to have you come see one of our edge data centers over in Gurgaon — it's just about commissioned at this point.
Lakshay Agarwal
analystAlright, sure. I'll get in touch about that same thing. Thanks very much. Best of luck.
Ankit Saraiya
executiveIf you come by our Gurgaon office, you'll gain a deeper understanding of the business.
Rohit Singh
analystAll right, that’s sure to be quite useful. Thanks.
Operator
operatorChinmay Kabra from Emkay Global Financial Services has the next question. The line is yours — go ahead.
Chinmay Kabra
analystYeah. Hi, sir. To pick up where the last participant left off, I just wanted to get a handle on the rentals we're projecting from the IaaS services we'll be offering. And I really just wanted to understand when we might be planning to get the IaaS service up and running on a full-fledged basis.
P. P. Gupta
executiveAnkit, I don’t quite follow what you’re asking. Which services are you referring to?
Ankit Saraiya
executiveRegarding the costing side, you brought up that there are 2 models, CapEx and OpEx. I wanted to get a handle on the rentals we're projecting from the IaaS services we'll be providing. So it'll be hard to really capture these services in the numbers, since there are only a few opportunities of that kind. And in percentage terms for revenue contribution, they're being offered. Sir, I'm sorry, I can't hear you.
P. P. Gupta
executiveOkay. You're cutting out partway through, sir. Can you hear me? Is this clearer? Much clearer now, sir — go right ahead.
Ankit Saraiya
executiveYeah. So if we talk about value-added services or anything delivered on top of infrastructure as a service, it's really hard right now to put a revenue figure on that or a margin figure on that, since those opportunities are limited for us at present. And building them will take time. And at least for the first year or two, they'll contribute only a few percentage points to the co-location services.
Chinmay Kabra
analystGot it. And regarding the IaaS services we intend to offer — since we'll be sourcing both the hardware and the technology — do we have any plans around whether that sourcing will come from outside India or from within India itself?
P. P. Gupta
executiveLook, at present, the bulk of this technology can be found in India. Both international companies and a few local ones offer these platforms. So, based on what the end customer needs, we might source from either side, since certain customers prefer domestic providers because of regulations and rules in neighboring countries. Meanwhile, other customers lean toward global players given how much of the technology they hold. So it would truly vary according to customer preference.
Chinmay Kabra
analystAlright, understood. I just wanted to squeeze in one final question if that's okay. Of course. So I'd like to get a handle on the smart metering business — specifically, how many smart meters do we have that have actually been granted operation go live status, and also, is the money coming in for installing those smart meters, is that flowing along without issues?
P. P. Gupta
executiveYes, it's moving along quite well. In Madhya Pradesh, at Indore, we've already completed roughly 1.5 lakh meters; there's another batch of about 1.75 lakh meters, plus around 2.75 lakh meters in Srinagar and Jammu and Kashmir. Those are performing very well, with no issues. The Ministry of Power holds review meetings each week with all the state DISCOMs, and they're quite serious about ensuring there are no missteps in smart meter deployment and payments.
Chinmay Kabra
analystGot it, sir. Thanks.
Operator
operatorThanks. And with that, ladies and gentlemen, we'll treat that as the final question for today. At this point I'd like to pass the conference back to management for closing remarks. Sir, over to you. Yeah. Thanks a lot. I want to say to everyone that you have my thanks for being on the conference call.
P. P. Gupta
executiveShould you have any remaining questions about how we performed, just send us an email. If you find yourself over on that side of the city, we would be very glad to have you stop by. Our data center and smart meter operations are run out of the Gurgaon office, located on MG Road. Whenever you are in that part of town, you are welcome to come visit. Once again, I thank every one of you for being on the call.
Operator
operatorThanks. That wraps up this conference on behalf of Asian Markets Securities. We appreciate everyone for being with us. You can now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Techno Electric & Engineering Company Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Techno Electric & Engineering Company Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Techno Electric & Engineering Company Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.