Techno Electric & Engineering Company Limited (TECHNOE) Earnings Call Transcript & Summary
May 29, 2025
Earnings Call Speaker Segments
Operator
operatorLadies and gentlemen, good day, and welcome to the Techno Electric & Engineering Company Limited Q4 FY '25 Earnings Conference Call hosted by Asian Market Securities Limited. [Operator Instructions] Please note that this conference is being recorded. I now hand the conference over to Mr. Suraj Sonulkar from Asian Market Securities Private Limited. Thank you, and over to you, sir.
Suraj Sonulkar
analystThanks, Navya. Good afternoon, everyone. On behalf of Asian Market Securities, we welcome you all to the Q4 FY '25 Earnings Conference Call of Techno Electric & Engineering Company Limited. We have with us today, Mr. P. P. Gupta, Chairman and Managing Director; and Mr. Ankit Saraiya, Director, representing the company. I request Gupta Ji to take us through overview of the company quarterly results, and then we shall begin with the Q&A session. Over to you, Gupta Ji.
Padam Gupta
executiveThank you, Suraj. Very good afternoon to all of you, and welcome, everyone, to discuss Techno Electric financial results for Q4 and year-ended 31st March 2025. Anything said on this call, which reflects our outlook for the future or that could be construed as a forward-looking statement must be reviewed in conjunction with the risks that the industry and in turn, our company faces. Let me highlight our performance. When we look at the Q4 '25, the total revenue of the company stands at INR 812 crores, up by 68% year-on-year, probably better than any of the previous quarters. EBITDA for the company stands at INR 102 crores, up by 74% year-on-year. The EBITDA margin is at 12.64%. The other income is INR 69.75 crores compared to INR 30.86 crores last year, up by 126%. The profit before tax is INR 167.18 crores compared to INR 83 crores last year. The PAT is at INR 132 crores, up by 91% year-on-year and EPS is at INR 11.42 per share. If we look at the whole year at the close of the year, the revenue stands above INR 2,400 crores, that is 2.04 times up by 43% year-on-year, which is so far all-time high for the company. The EBITDA for the company is at INR 328 crores, up by 45% year-on-year. The EBITDA margin is at 13.66%. The other income is at INR 175 crores, up by 34% year-on-year. The profit before tax is at INR 485 crores, up by 45% year-on-year. The profit after tax for the company stands at INR 428 crores compared to INR 269 crores, up by 59%. The EPS is at INR 37.65 compared to INR 25 last year. We have been getting compressed schedules due to delays in acquiring land parcels by our customers for setting up of the facilities and they want their projects to be operational as per COD dates, forming part of their concession agreements. They are ready to even incentivize us to achieve these compressed schedules. We are pleased to share with you that we have commissioned a 20-bay, 765/400 kV Prestigious Sikar Substation of grid comprising 99 elements of transformer, oblique reactor, that is equivalent to 3 gigawatts of transforming capacity and 1.2 gigawatts of reactive capacity. A project of the power grid in a record time of 9 months. First time in the country which otherwise would have taken in the past, normally 2 years or more. Similarly, now we are bettering the time line on the behest of power grid in setting up of a prestigious 33-way substation of 765/400 kV at Dausa comprising 28 elements of transformer and reactors which are equivalent to 3 gigawatts of transforming capacity and another 2 gigawatts of reactive capacity. This is a wonderful journey for the company. I'll say a compressed schedule increases the productivity of the resources deployed, which includes mechanized construction equipment, skilled labor forces, and the cost of bulk procurement of local inputs, materials. The compressed schedule further helps in optimizing the establishment costs and thereby increasing working capital efficiency. This is now being practiced in other ongoing projects at Bidar, Kharagpur, Lakadia, Anandapur, and many more. During the year we have successfully commissioned projects at 17 locations all over the country. Apart from this, in spite of increasing the revenue, we did not let our balance sheet stretch in terms of the working capital requirement due to better capital management, focus on cash flows, and efficient utilization of resources. Additionally, we have been able to convert our efficiencies into cash. This is evident from the numbers that our cash flow from the operational results, which you may have observed that the company is cash positive by INR 837 crores compared to a negative of INR 337 crores in the previous year. This was possible as we have been able to convert trade receivables into cash, there was hardly any increase of debtors compared to previous year despite increase in revenue by almost 50%. The customers often spoke the performance and this has gone a long way. I'm further pleased to share with you that the current investment value, which is cash and cash equivalent as of the year-end stands at around more than INR 2,500 crores, that is about INR 220 or INR 225 per share. Techno has been able to garner the better operating margins consistently over the years in this space compared to peers. We have been able to convert the profits into cash on our balance sheet and have one of the efficient working capital management processes in practice. The reasons are simple but needs to be practiced meticulously like speed of execution, thereby ensuring timely completion of project, the timely collection of receivables, including closing of the projects and realization of retention money, avoiding interest-yielding advance from the clients, better credit terms from the vendors backed by commitment to pay in time, so that the cost of procurement is within acceptable limits. Due to better working capital efficiency, we have been able to be a debt-free company since beginning. We have never borrowed for our EPC business other than for our own asset deployment businesses. Apart from that, over the past year, 5 years, as you know, we have monetized most of the assets in renewable power, transmission assets, and have collected cash of INR 1,500 crores. But additionally, we also collected INR 1,250 crores out of the QIP, which we want to. We have a program of about almost about INR 10,000 crores in hand to be deployed in next 3 years. Out of this, we have already deployed about INR 1,250 crores in last 2 years as CapEx in our SPVs for setting up of data centers, including edge data centers, AMI projects, and transmission projects acquired in TEEC remote and also execution in partnership with IndiGrid at Dhule and Ishanagar. The company is pleased to inform that Chennai Data Center Phase 1 is nearly complete, and Edge Data Center at Gurgaon is ready for operations. We expect during the year to deploy Edge Data Center at 10 locations and also deploy smart meters of more than 1 million in number, and we plan to successfully complete substations of 765/400/220 kV levels at more than 20 locations countrywide in EPC mode and for our own concessions. You will be happy to know that we are deploying 220 kV GIS substation in the highest altitude of the country at Ladakh and Kashmir, at 4 locations. And our labor never vanished during the Pakistan war. The patriotism was also high degree in our labor force working very close to Pakistan border and China borders. The order book momentum for bidding and order intake has increased in the second half of the year for the sector and as well as for the Techno. We have robust order book at around INR 11,000 crores as of March 2025, which is highest in the history of the company. We are L1 in orders worth INR 800 crores already. We have received orders worth INR 2,000 crores plus in Q4 itself, which takes the order for the year in total to more than INR 4,150 crores, and our guidance for the year was around INR 3,500 crores. We expect the order book momentum to continue, and the order intake in this year is also expected to be around the same level. This simply reflects we will have enough orders in hand to keep on the growth momentum for next 2 years. Our Board have already announced a dividend of INR 9 per share, which should be to the delight of all of you. Building on the growth momentum witnessed in the last 2 years, as you all know and as we mentioned in our last Q3 meet, that our monthly revenue of INR 75 crores in financial year '23 is presently at INR 200 crores now. And this is further planned to be enhanced to INR 300 crores per month in the current year. That is the target of the company of INR 3,500 crores to INR 3,600 crores this year. This confidence stems from our already achieved performance in last 2 years successfully. With this, the ratio of order backlog to execution will also come down to 3 to 3.5, which is the industry norm. In the meantime, the company will continue to grow up its strategic presence in data center space, and the total deployed capacity by the end of the year is expected to be around 25 megawatts and at least 50 megawatts by '27. We are pleased to inform that Chennai data center has been considered eligible for deployment of AI-based applications, including clouds. The outlook is very, very promising, continues to be promising. India's energy landscape is undergoing a significant transformation, from historical sluggish energy demand growth over last decade to now registering nearly double-digit growth driven by peak load targets scaling from 260 gigawatt to an ambitious 400 gigawatt by 2030, or latest by 2032. To bridge this demand-supply gap, strategic investments are being channeled into advanced transmission systems, mostly at 765 kV, backed by STATCOM's VSC HVDC, where we enjoy a strong market position. On the distribution front, massive smart metering rollout under RDSS and new reform-linked distribution system strengthening schemes will drive digitization, efficiency, and private sector participation, which may be another area of focus for us. The generation segment has also revived meaningfully with the government deciding to add another 80 gigawatt of thermal capacity but mostly through supercritical and ultra-supercritical technologies in place to have the emissions in control, opening up substantial opportunities on the balance of plant and power evacuation infrastructure and switchyards on grid connectivity to this generative capacity. Simultaneously, the data center ecosystem is undergoing a paradigm shift driven by AI, cloud 5G, data localization imperatives. The market is expected to more than double by 2030. Our investment in hyperscale Edge Data Centers in Chennai, Kolkata, and across Tier 2, 3 cities via rail are very timely and strategically positioned to be value accretive and capitalize on this. We believe this convergence of energy transformation and digital infrastructure. I will again repeat this. We believe this convergence of energy transformation and digital infrastructure offers a multi-year high-growth opportunity. Techno Electric is strategically aligned, technically equipped, and financially sound to scale alongside India's ambitious, India's aspirations in both these mission-critical sectors. So Techno is very differently placed than many other companies in transmission line work. Let me give you a brief outlook and opportunities, sector by sector. The key drivers for the transmission sector are integration of 500 gigawatt to grid needs almost 50,000 circuit kilometers of transmission lines. But more importantly is 433,000 MPA transformation capacity, all-time high in the country. The national electricity plan as we say this is INR 9.2 lakh crore CapEx by 2022. The power grid has already announced a CapEx of INR 1 lakh crores in next 3 years in ongoing 3 years with INR 1.75 lakh crores by 2030. In the finance budget, the Finance Minister budget speech of 2025, the government will incentivize the electricity distribution companies on augmentation of interstate transmission capacity amid efforts to improve financial health and capacity of power fronts. And additional borrowing of 0.5% of GSDP will be allowed to states contingent upon these reforms. This would bring an estimated opportunity of another INR 1.5 lakh crores over next 2 years. The EPC opportunities in the segment. The TBCB model of projects will increasing private participation continues. The high-end technologies like 765 kV AIS/GIS solutions backed by STATCOM or VSC HVDC will be the necessity to sustain this energy transformation and injection of renewable power in the grid. Interregional corridor strengthening, green energy corridors for RE evacuation, if your market for Techno will comprise on the pipeline of INR 40,000 crores currently out of which Techno's potential will not be less than INR 2,500 crores to INR 3,000 crores per year and for the next 4 years. We currently have orders worth of INR 7,500 crores in transmission segment, EHV transmission segment. And we, as you know, we also have 2 concessions in TBCB in Gogamukh and Bokajan with a total revenue of INR 2,800 crores over the concession period and also are aggregating 2 concessions in partnership with IndiGrid and Dhule and Ishanagar. The various programs in the country of distribution side are our RDSS scheme, which is called Revamped Distribution Sector Systems scheme is INR 300,000 crores plus, the Reforms-Linked Distribution Scheme of INR 16,000 crores, which is largely going to be implemented on PPP of the privatization model and this will; and our focus area will continue to be grid modularizations like GIS, AMI, SCADRs as we are doing for DVC presently in the DVC command area, the smart grid deployments, loss reduction and power quality improvement solutions, advanced smart metering solutions, where we are already executing about 2.5 million meters. And there is another about 1 million, at least about 100 million more to be deployed over next 2 to 3 years. And we will have a market share of almost around 1% to 2% in this. This offers us a high margin, actually O&M scope and the total X model because the very good session involves CapEx plus operations that are driven DISCOM transformations to manage their own supply side management. And as you already know that we are executing now 2.5 million meters, which concessions we have won. We are expecting further of concessions of another 0.5 million meters or 1 million, 0.5 million to 1 million meters per year basis. Thermal generation, we have already talked about 80 gigawatt in the pipeline to be completed by 2030 which will then facilitate both more of injection of renewable power and also facilitate peak demand of 200 megawatt. Focus on the supercritical and ultra-supercritical plants technologies, EPC scope on balance of plant, air quality control systems like FGD, carbon capturing as well as ESPs of digitized and modern based on modern technologies to ensure acceptable emission levels globally to 14 mg OD. And similarly, this opportunity is also expected to be no less than almost about INR 1 lakh crore over 7 years. In the renewable generation side, I would say there will be more opportunities in the solar plus storage, hybrid systems, wind farm EPCs. And we are yet to deploy another about 300 gigawatt with balance in 6 years. Government made land, even RE parks or floating solar parks, the EPC opportunity is INR 3 lakh crore to INR 4 lakh crore and the budget for '26 significantly increased allocation to MNRE to by 39% in this segment. On the FGD side, I will say that the DCEA has come back on its earlier report where they have given fresh dates to this sector, commencing completion from '27 onwards, progressively depending on the location of the generating plant. This industry may eventually see a 5 to 10 gigawatt per year scope, both from the private and state electricity boards. Our present order of INR 1,450 crores is progressing promptly. Coming on data centers, the digitization and cloud services are key reasons for growth of data centers alongside developments like 5G. Major growth drivers for data centers in India are public cloud adoption, data localization, policy incentives, digital transformation, technology developments that is rollout of 5G, AI in 5G and VR, increased adoption by the enterprise technology markets, IoT, Big Data and cloud computing. All these are very progressive and promising. Ankit, would you like to take over now?
Ankit Saraiya
executiveYes, sure. So, we are in as everyone is aware, we are in advanced stages of completing our project of 24 megawatt data center in Chennai. We have incurred an investment of almost INR 450 crores in the project. While we have faced delays due to regulatory and permitting approvals, also due to supply chain disruptions, but having overcome all of them, we are now very close to commissioning our first phase of Chennai, which is approximately 5.6 megawatts. We are in the final phase of testing and also onboarding a few customers as we speak. Our pipeline in Chennai data center is growing. We currently have a pipeline of almost INR 80 crores to INR 100 crores and while having additional conversations with other cloud players and potential AI customers. The unique proposition that we provide through our Chennai data center is that it is designed for higher density of racks on an average compared to the industry. And additionally, being a water-cooled data center or the only water cool data center in Chennai and that region, we are uniquely placed to provide racks specifically for AI services or AI-related activities, giving us a unique position in the industry. We are currently engaged with multiple banks, content delivery networks, domestic cloud players and receiving positive feedback from them. We have recently participated in an RFP by a global bank, and we hope that will be concluded in next 3 to 4 months' time. Recent advancements in AI has obviously fueled the demand of data center, but more precisely the density of power required for rack. What earlier we used to practice on an average at 6 kilowatt or 8 kilowatts per rack, now people have started talking 25 to 40 kilowatts per rack and going higher as we speak. This requires substantially higher resources per data center and data centers have to be designed to meet those specific requirements, which we are very well placed to provide. India AI mission has recently commenced and first round of empanelment has been concluded, and we are hopeful that with more empanelment coming through in round 2 and 3, we will have interest from multiple stakeholders to utilize our infrastructure as we call our facility AI ready. We are established and further establishing channel partners, distribution engine for reaching the wider market and as well as reaching global market. Coming to Edge Data Center, we are aware that RailTel has awarded us with a concession to build Edge Data Centers in 102 cities. Last Saturday itself, we powered on our first Edge Data Center in Gurgaon, which is a small capacity of 200 kilowatts, but goes a long way because it's our first data center, which has truly got powered on and appreciated by RailTel as well. And we are hopeful that the capacity of 200 kilowatt, at least 75% of it would be utilized by RailTel immediately, and we anticipate leasing out the remaining 25%, which is 5 lakhs within 3 months. We have started execution of our second Edge Data Center in Mumbai, which is close to about INR 50 lakhs, 450-odd kilowatt of density, and it should be completed hopefully by November '25 or maximum December. And we are in discussion with large conglomerates to lease out the capacity immediately on commissioning. We are also going ahead with discussion with a few hyperscalers for contracting at least 4 to 5 Edge Data Centers in multiple locations across India. We have already shown our interest to RailTel to develop edge data centers in the city of Gandhinagar, Indore and Bhopal, and we are hopeful of getting the possession of the land very soon to begin expanding our facilities in these very cities as well. We target to also start our execution this year in the city of New Delhi and Hyderabad as part of our Edge Data Center concession with RailTel. For Edge Data Centers, we have created an extensive network of channel partners and distribution partners, and we have started receiving active interest through these partners for occupying space within the Edge Data Center ecosystem. We have also started execution of a data center in Kolkata. We have finalized the master plan, and we have started with preconstruction activities. And very soon, we'll be applying for building plan approvals to begin full-fledged construction. In totality, we have a funnel of more than INR 100 crores including Chennai and Edge Data Centers in discussion with multiple nature customers, whether they are cloud, CDN, AI, et cetera.
Padam Gupta
executiveThank you, Ankit. So overall, I would like to say that during the current year, we are targeting a top line of INR 3,500 crores and an EPS of no less than INR 50. And in the year '26, '27, our target will be around INR 4,500 crores with an EPS of no less than INR 75. With this, now we can allow the question and answers.
Operator
operator[Operator Instructions] The first question is from the line of Sandeep Agarwal from Naredi Investment.
Sandeep Agarwal
analystSir, my first question is regarding the period in various segments like Smart Meter data center and small edge data center business.
Padam Gupta
executiveYou see these 2 are different businesses altogether. Smart Meter is a concession-based projects. Their period is prefixed by the government itself. That they pay over 94 months we call PMPM Per Meter Per Month post commissioning immediately on achieving SAT or Go Live, they pay us around 15% depending on the location of the project. That is how the demand is in the concession projects. Coming to data center is totally a market-driven activity, and it goes with the market dynamics. By and large, we anticipate a data center payback should be no more than 5 years in my view. But because of the challenge of growing and changing technologies, applications, usages, they are all part of it. Ankit, would you like to add something to it?
Ankit Saraiya
executiveNo. Sir I think you're on the point, the payback period for data centers is about 5 years.
Sandeep Agarwal
analystFollow-up there; per megawatt revenue per annum is INR 11 crores to INR 12 crores. Is this estimate is correct?
Ankit Saraiya
executiveYou can take it at around INR 8 crores to INR 10 crores.
Sandeep Agarwal
analystINR 8 crores to INR 10 crores. Okay. Sir, just another question is just bookkeeping. I want to know the detail of other current asset line item, which is INR 814 crores approx.
Padam Gupta
executiveWhat is the status of current assets?
Sandeep Agarwal
analystStatus of current INR 814 crores.
Padam Gupta
executiveI think when you get the balance sheet, you will find the details in that. They are in the normal course of business. There is no exception in it. They keep rotation in rotation with the execution as it happens.
Sandeep Agarwal
analystIt increased from last year, INR 250 crores approx to INR 814 crores. So just want to know what is...
Padam Gupta
executiveYou are asking on contract assets basically not current assets. The contract asset is basically the investment in data centers and AMI or TBCB schemes. They are yet to be built out. That is what we call contract assets. They are not capitalized in our SPVs but work on behalf of SPVs by the Holdco in deploying them. So that is a CapEx you can say indirectly carried out by the company in setting up these facilities like data center, INR 400 - INR 500 crores by now, meters, another INR 400 crores by now. So it is that amount.
Operator
operator[Operator Instructions] We take the next question from the line of [ CA Garvit Goyal from Invest Analytics Advisory ].
Unknown Analyst
analystCongrats for a decent execution in the quarter. Sir, earlier you have guided for INR 3,600 crores revenue in FY '26. I think in opening remarks, now you said INR 3,500 crores. So can you please clarify this?
Padam Gupta
executiveNo, I could not get the question, INR 3,500 crores.
Garvit Goyal
analystLast con call, I think you mentioned INR 3600 crores.
Padam Gupta
executive[indiscernible] is not a big issue between us. INR 3,500 crores or INR 3,600 crores, almost there.
Unknown Analyst
analystI was just getting, so that guidance we have given, given the challenges like land allocation and we are doing it very efficiently. So how exactly do you plan to achieve this guidance? Like which segment will contribute the most to this growth? And is it entirely from the existing order book standing today or a portion of it will be via the new incremental orders that we expect in FY '26? So that's my first question.
Padam Gupta
executiveLook, this role of land acquisition is often performed by the asset owner. It is not in our scope, #1. #2, our job starts once they hand over the land parcel to us. So, most of these orders are already around 3 to 6 months old. And customers as per our information, are fairly advanced acquiring land parcels. And we have taken that into consideration already. But you must take into view that larger execution has happened in last year, it will be in the same in current year also, like 40-60 with the H1 of the current year will be 40% and H2 of the current year will be 60%. So, it will go in the same pattern.
Unknown Analyst
analystGot it. And which segment will contribute to this majorly?
Padam Gupta
executiveSo, it will all be from transmission, FGD, meter deployments, all will be element of it. By and large if you want to take the break, you can take transmission will be INR 2,500 crores, transmission and distribution, FGD INR 500 crores, meter will be another INR 500 crores. 1 million and plus meters will be deployed as I [indiscernible]. So total will be INR 3500 crores, INR 3600 crores.
Unknown Analyst
analystGot it. And secondly, on the data center, like you earlier guided Chennai Data center was expected to be by March '25. And similarly, Mumbai was to start construction in April and was expected to be commissioned by August '25. But while you mentioned about Chennai, can you please update on why Mumbai data center is getting delayed now? And further, can you also confirm like earlier, you were speaking about revenue generation from Chennai data center, particularly from Q2 this year. Now that the time line is intact?
Padam Gupta
executiveAnkit, would you like to answer that?
Ankit Saraiya
executiveYes. So firstly, we do expect to start generating revenue in Chennai from Q2 this year. And so that is pretty much as expected. But Mumbai never got delayed because Mumbai was never within our plans earlier. We have very recently got the possession of a location in Mumbai to RailTel only about, you can say, 3 weeks back, and we have almost completed the civil work over there, and we are in line to commission our Mumbai data center by November. So, it was something new that came up to us. It was not a planned location.
Operator
operatorWe take the next question from the line of Deepak Poddar from Sapphire Capital.
Deepak Poddar
analystSir, I just wanted to understand, I mean, in terms of from data center, what sort of revenue we are targeting for this year and next year, FY '26 and FY '27? And what sort of margin we can expect in data center?
Padam Gupta
executiveYou can take conservatively, let me put it, our this year target will be about INR 100 crores. And next year target will be at least INR 300 crores to INR 350 crores.
Deepak Poddar
analystINR 300 crores to INR 350 crores. And what sort of margin we can see here?
Padam Gupta
executiveGenerally, EBITDA is very high in these projects. I say you can take around 80%.
Deepak Poddar
analyst80%?
Padam Gupta
executiveYes, yes.
Deepak Poddar
analystOkay. And the revenue that you have said in terms of INR 3,500 crores and INR 4,500 crores, this includes the data center? Or is it over and above this?
Padam Gupta
executiveYou see this year, we have not included. That is why 35 or 36 debate remains, as you must have heard of your colleagues. Next year, it includes up to 3.
Deepak Poddar
analystOkay. Understood. So next year, your FY '27, your margins you will see a big jump in your margin, right, because of this data center?
Padam Gupta
executiveAbsolutely. It should be. That is why I said which differentiate us from the other T&D players.
Deepak Poddar
analystAnd what is the general EPC margin range you look at? I mean this 14%, 15% is what general EPC margin?
Padam Gupta
executive14, 15 is short rather, it should be at least better by 100 notches, 100 bps over last year as commodities have been cooled down, but it depends on truck and tariffs.
Deepak Poddar
analystYou are talking about margin in EPC, right, 15% to 16%...
Padam Gupta
executiveIt's all commodity pricing. Supply chain is under pressure. A lot of exports are happening on the supply equipment, and export prices are better to the manufacturer than domestic market prices. So all type of challenges are there. But nevertheless, our efficient and productivity will stand us out.
Operator
operatorWe take the next question from the line of Vikram Datwani from Nuvama Institutional Equities.
Vikram Datwani
analystCongratulations on a good set of numbers. Two questions from my side. Sir, could you please give us your expectation of consolidated EBITDA margin for the next 2 years, considering data centers will be revenue accretive. So, how much would that impact your margins positively? That is my first question. And my second question is on the FY '27 EPS guidance. Just wanted to reconcile that INR 75 figure, would that also include any monetization of assets or any arbitration awards that you're expecting? Or would that be only from business, and monetization will be over and above this figure?
Padam Gupta
executiveFirstly, you see data center is a new subject to us, and ability to set up we have enjoyed. We have a great marketing team now. But the numbers we will be yet to be experienced to be honest. So, we cannot say the EBITDA as a consol. But overall, you can say as EBITDA, is experienced at 20% should continue on an overall basis at the company level. Whether it comes out of treasury will come down, and data center may add more to it. But definitely, we have not considered any monetization that will be over and above this in any case. But there are not great disputes we are carrying in our company with the clients, but something is often a way of life, I will say, that does not impact much financially. But there may be a significant collection out of the discontinued business. So that will be over and above this, like it has happened in last year also. The EPS of INR 4 is happening out of the discontinued business. So we are yet to get some more money from wind business.
Operator
operatorWe take the next question from the line of Samarth Khandelwal from ICICI Securities.
Samarth Khandelwal
analystSir, congratulations on a strong quarter. Sir, I just wanted to understand when we say 1 megawatt of a data center, so 1 megawatt on 100% capacity generation, we say 8.7 million units of kilowatt hours of electricity would be generated. So, in how much time does a 1 megawatt would be the energy cost for a 1-megawatt data center?
Padam Gupta
executiveFirstly, you see, these are energy-consuming solutions, not generative. So, please correct it. And when we talk of the revenue, generally power cost is a pass-through cost here. What we talk is only a lease rental of the facility provided to the users.
Samarth Khandelwal
analystSir, I understood. That is why INR 8 crores per annum was saving quite low. I just wanted to understand the energy cost.
Padam Gupta
executiveEnergy is a pass-through. We don't make some money, but we don't take it as a part of INR 8 crores. That is over and above. Ankit, can you elaborate more to it?
Ankit Saraiya
executiveSo in terms of top line or expense, we do not consider energy as a revenue or an expense because it's largely a pass-through to the customer at the cost. So when we talk about a top line of INR 8 crores to INR 10 crores per megawatt, it is largely out of lease rental. It doesn't include energy, and neither would the expenses would include energy.
Operator
operatorWe take the next question from the line of Prathamesh Sawant from Mirae Asset Capital Markets.
Prathamesh Sawant
analystSir, just wanted to understand if you can throw more light on the Smart Meter business. So what kind of CapEx outlay are we seeing over here? How has our execution been so far, and the outlook for the current year?
Padam Gupta
executiveI will say that we are conservative, and our engagement is very nominal. As I told you earlier, we are having presence of more than 5% in this segment, till date, we have commissioned 7 lakh meters out of a concession received for 2.5 million meters by us, and the schedule is to complete by September '26. In '25, '26, we are targeting to do 1 million meters more. So we are on track. On an average, we do about 400 meters in different pockets. And they are in cost control.
Prathamesh Sawant
analystSo sir, how are we funding this project like anything, because it is CapEx intensive. So, how do we plan to fund it?
Padam Gupta
executiveYou see we are funding internally, number one, from our own resources. As I told you, we have already invested about INR 400 crores in this. And another outgo this year will be about INR 500 crores on this activity. So we have sufficient accruals. It is out of internal accruals, you can say. We'll be able to take time being. And once the schemes are complete and going, we may like to see exit at that time.
Prathamesh Sawant
analystSo we won't be raising any debt for this, sir?
Padam Gupta
executiveWe don't want to raise any debt. We'll be monetizing straight away.
Prathamesh Sawant
analystAnd we are expecting 15% IRR on these projects, as you mentioned.
Padam Gupta
executiveMinimum... Maybe more...
Prathamesh Sawant
analystOkay. And sir, like a few calls back, you had mentioned about the Mumbai data center, so which was like somewhere near St. Regis. So, just any update on that?
Padam Gupta
executiveAnkit, can you...
Ankit Saraiya
executiveAs I mentioned that we've been handed over that location only about 3 weeks back. And we started the construction activities over there. The civil work is almost coming to conclusion, and we'll hopefully commission at least 400 kilowatts of capacity over there by November '25.
Prathamesh Sawant
analystSir, just one last question to you. So, if we look at data center per se as a separate entity, what will be the line item below the EBITDA? Like how do we see the depreciation and the interest cost to that?
Padam Gupta
executiveThey are all internally funded as of now, so there is no interest cost per se. But definitely, there will be depreciation as per the norms.
Operator
operator[Operator Instructions] We take the next question from the line of Ravi Naredi from Naredi Investments.
Ravi Naredi
analystSir, we are awaiting investor presentation as you are nice promoter. So, we thought you give maximum disclosure, but we disappoint on this part. First of all, congratulations for ever highest top line and bottom line in history of company. Sir, CapEx plus investment plan in next 2 to 3 years in Smart Meter, data center, what will be our CapEx?
Padam Gupta
executiveFor the current year, we have already given in my presentation. That this year we plan to invest about INR 1,250 crores, which will comprise of INR 500 crores of Meters and INR 500 crores in Data Centers and another INR 250 crores in our TBCB projects. Similarly, going forward over the 5 years, we have already said we'll be investing about INR 10,000 crores, with a larger 80% belonging to data centers. Maybe you did not hear me in my presentation. We said by 2030, we'll be doing INR 10,000 crores of CapEx and 80% will be on data centers by and large. And we intend completing about 250 megawatts, including edge and hyperscale and another, you can say the project will be done by 1000 in TBCB. Depending on change here and there. But as of now, this is the program with the company.
Ravi Naredi
analystSir, the company is now so big. We want to meet personally to you. So, is it available in Kolkata or Gurgaon?
Padam Gupta
executiveSir, we are in both the places. For Data Center and Smart Meter, you are welcome in Gurgaon office, Ankit sits there. And I'm Kolkata. You are welcome in either place.
Operator
operatorWe take the next question from the line of [ Shreyansh Gattani from SG Securities ].
Unknown Analyst
analystI had a couple of questions. So, one was on the EPC. You mentioned in your opening remarks that to execute on the compressed timelines, you're getting like additional incentives from customers. So, what exactly are we seeing? Is that in terms of like better working capital, like better receivables? Or is it like additional margin that we are getting? If you could just give some color on that?
Padam Gupta
executiveYou see apart from all these [Technical Difficulty] [Presentation]
Padam Gupta
executiveSorry, there was a disruption.
Unknown Analyst
analystNo problem, sir.
Padam Gupta
executiveCan you repeat your question, sir?
Unknown Analyst
analystYes. So, my question was, you mentioned in your opening remarks that you're getting some additional incentives for executing in the compressed time line. So just wanted to get some color on that. Whether it's like better receivables that you'll be getting? Or is it going to be like in terms of higher margins as such?
Padam Gupta
executiveNo, the incentive is additional payout over and above the contracted price. 2% to 5% of the contract value, but we account it in our books only as and when received.
Unknown Analyst
analystSo, would that mean like we would see higher margins for this financial year because of this incentive?
Padam Gupta
executiveYes. Obviously, if it happens, yes, for that portion of the top line.
Unknown Analyst
analystSir, second question is on the data center side. So just wanted to understand the customer onboarding and customer acquisition cycle. So how long does it take once our data center is ready if we have a customer agreement signed for them to get onboarded and for us to start generating revenues? So just wanted to understand the whole process.
Ankit Saraiya
executiveTypically, once we've onboarded a customer, it can take anywhere between 2 to 3 months for them to move into the data center and for us to start generating revenue against that contract.
Unknown Analyst
analystSo is there any hardware change that need to be done or...
Ankit Saraiya
executiveNo. It is just their own time line for migrating the equipment to our data center and stabilizing them and also to provision power for their requirement.
Unknown Analyst
analystSo, for the Kolkata data center like for Chennai, I remember last year also, we mentioned that we are trying to get customers, but like eventually, we ended up waiting until the end of the completion and now, even after we commission, it will take like 2 months. So, is that something that we are looking to change or is that how the industry is operating like we wait until the whole data center is ready for us to start gathering customers?
Ankit Saraiya
executiveSo, you see, in this industry, it's difficult to onboard customers unless you have reaching completion of a data center, because with the given options, our customer is always more comfortable moving into a commission data center, which is readily available and most of the customers come out with their requirements only about 3 to 4 months in advance of their actual need. So, for that very reason, most of the time, it is -- these activities start towards completion of the project and go on for at least 6 months before the capacity is truly leased out.
Unknown Analyst
analystUnderstood. So, just last question...
Operator
operatorI am so sorry to interrupt but maybe request that you rejoin the queue for follow-up question.
Unknown Analyst
analystYes. Thank you.
Operator
operatorThank you. Next question is from the line of Shrey Gandhi from CR Kothari Stock Broking.
Shrey Gandhi
analystThank you for the opportunity and congratulations on the great set of numbers. My question is regarding the CapEx outlier that you mentioned, INR 10,000 Cr in next 5 years. So how do you plan to fund that CapEx? And how much time frame are we going to looking at the fundraising part?
Padam Gupta
executiveSo presently, we are planning to do it a lot of internal accruals and cash available with us by and large. And also, it will be supplemented by monetization of the completed assets to begin with the TBCB followed with Smart Meters. But data center, we like to hold on for a while. And maybe a bit of a debt in data center is ultimately called for at the SPV level.
Shrey Gandhi
analystAnd another question is on FGD and Smart Meter side. Are we facing any slowdown in order intake in FGD? And what is the competitive landscape looking like in Smart Meters? Because it is a clustered segment, I think. So, what is your take on it?
Padam Gupta
executiveAs I told you, probably we are one of the smartest players in this segment with the exposure of only 2.5 million meters among, you can say, about 12 million, 13 million meters in execution by, in the market, maybe not 10 million meters, 100 million meters to my mind in execution by now. And then we'll continue to focus only in the pockets where we are good to deliver time out and also able to deal with the utility properly. So, we are not looking for a business ultimately more than another 2.5 million spread over next 4 to 5 years. So overall, book size may be about 5 million meters by 2030 or '28 or complete of the scheme.
Shrey Gandhi
analystOkay. And on FGD side, is there any slowdown in the author intake? Because of regulatory?
Padam Gupta
executiveYes. Regulatory was there. Government was bit confused because the CapEx involved in setting up these solutions is very high. It's almost INR 1 Cr per megawatt. So that was a huge detriment to the government. Currently now government has reached it and on selective basis, they want to revise this, comply these requirements on emissions on SO2 or NO2. So, the revised target starts from '27 onwards. And as we all know the generating capacity, majority generating capacity is in private hands. So obviously, the call has to be taken by SCBs and private because the capacity, lot of capacity has happened in already in the central sector. Additionally, I will say that the whatever new generation capacity is coming in market, 70 - 80 gigawatt, it is all with FGD only. It is not without FGD at the greenfield level itself. So, we are hopeful of this market to continue at least for next 10 years, but in its own proportion.
Shrey Gandhi
analystAnd another question in regarding the depreciation for data center. You said it will be based on industry norms. So, what will be the percentage if you can share in terms of gross look or maybe what kind of impact?
Padam Gupta
executiveI think we are yet to discover that number. We will deep dive and find out, yet we are not ready with this number to speak because it will depend on age of technology more than that, how you value it.
Operator
operatorWe'll take the next question from the line of [ Spasht from Indira Securities ].
Unknown Analyst
analystSir my question is regarding the data center part. In the last quarter, you said that you are going to use an OpEx model for the data center part. And the current guidance that you have given about the margin, I'm quite confused. Can you give some light on that?
Padam Gupta
executiveAnkit have you understood the question.
Ankit Saraiya
executiveNo, Spasht, your voice wasn't clear. I couldn't get the question.
Unknown Analyst
analystOkay. So, in the last quarter, you said that you are going to use an OpEx model for the data center. And with the current, the beta margins that you have given, it is quite confusing to understand how you will be generating a 80% EBITDA with using an OpEx model. Can you tell me about it?
Ankit Saraiya
executiveWhat do you mean by OpEx model? I'm not clear what was said in the last quarter. But most of the projects, so let me, most of the projects is undertaken as a CapEx right now, and it will be capitalized in the books of the respective SPV.
Unknown Analyst
analystAnd just that in the last quarter, you said that the infrastructure that you're going to use for the data center part, it is going to be updating expenditure parts?
Ankit Saraiya
executiveNo. But it will be funded through either project finance or it will be funded through any other medium. The data center infrastructure.
Padam Gupta
executiveSir, the OpEx model systems are all in concession contracts. Somewhere we are confusing. I have always maintained your Smart Meter and your data TBCB projects are OpEx model. They are concession. They are government that shows you payment month on month and per meter basis or per month of use basis. But Data Center is your own asset, and you have multiple users deployed in the data center within the overall capacity. So that is a CapEx model only.
Unknown Analyst
analystI understood, sir. It's just that the kind of services that you sell in the last quarter, it was quite confusing with how it is going to be for the infrastructure part because right now, as you said, that other customers, it is going to take 2 to 3 months with their requirements about the success and the power details. And we are just starting with the highest intensity, so it is fine.
Padam Gupta
executiveYou see, there are multiple type of practices in this sector. It is custom to build, build to custom use, general purpose use and then made to use of respective occupiers. So, and depending on the application, the changes have to be incorporated either by the asset owner or by the user. Ankit, can you elaborate more on it?
Ankit Saraiya
executiveSo, Spasht, if your question is about why does it take 2 to 3 months to onboard a customer, generally because you have to provision the power and infrastructure specific to the customer's requirement. So, once a customer contract has been signed, it can generally take the customer to migrate his equipment to your data center about couple of months and possibly about a month for us to just prepare the data center for his equipment to come and get established, but that doesn't require any additional CapEx. It's part of the operations.
Operator
operatorWe take the last question from the line of [ Ashish Soni from the Family Office ].
Unknown Analyst
analystSo this monetization model for RailTel is not clear because you said that Gurgaon as data center 75% will be used by RailTel, but I think Bombay you're saying it is rather susceptible. So, I'm not clear on that. So, what's the agreement with RailTel on that please?
Ankit Saraiya
executiveThe agreement with RailTel is a revenue share model. With whatever revenue the data center generates, a percentage of that revenue goes to RailTel and the remaining of it comes to us through an escrow account. So, the revenues will largely come out of any customer. It can be a third customer, whether a private company or a public company or RailTel itself. So, the data center is open to service all kinds of customers. It is not that RailTel is assuring a revenue or is going to leave the space on back-to-back basis.
Unknown Analyst
analystAnd other thing is, based on your learning from Chennai data center, what are the learnings you want to apply to like Calcutta and the subscription data center in terms of, one is cost because I think I heard it was almost INR 4.50 crores cost. And in terms of technological advancement in this area, if you can give some qualitative aspects, what's the learning you want to apply for Calcutta and subscription data centers in terms of cost and technical advancement in this field?
Ankit Saraiya
executiveIf you ask me, I think customers in this industry push you for technical advancement because of their unique use cases that they come up with. And in last 1.5, 2 years, we are seeing a lot more demand for AI related services from customers, and which is pushing us to deploy technologies which can accommodate very high dense rack, any racks going above 25 kilowatt and on an average about 50 kilowatt, which in Chennai we had designed at 10 kilowatt, though it was even at that time or even today 10 kilowatt rack is considered a higher dense rack and compared to what it used to get designed. So, one is that one may have to plan for higher density racks to get accommodated. And I would believe that we should be able to bring down our project cost by 5 odd percent in comparison to Chennai.
Unknown Analyst
analystAnd regarding approach, I think it got delayed. So, anything on that we can improve?
Ankit Saraiya
executiveI think that is something which is more like a post major risk over here. One can't do much beyond the particular point. Yes, so these are largely percent driven, yes.
Operator
operatorThank you. Ladies and gentlemen, in the interest of time, that was the last question. I would now like to hand the conference over to Mr. Gupta Ji for closing comments.
Padam Gupta
executiveYes. Thank you, ma'am. I thank everyone for joining the conference call if you have any questions left with you regarding our performance, please send us an email and we'll be happy to revert. Contact Man is Mr. Vijay Jain in our office, whose details are available on our website. And similarly, if you happen to be on either on Kolkata or Gurgaon site, you are welcome to drop in our office via a personal interactive. And definitely, we are very, very grateful and appreciate your participation. And thank you very much.
Operator
operatorOn behalf of Asian Markets Securities Private Limited, that concludes this conference. Thank you for joining us and you may now disconnect your lines.
This call discussed
For developers and AI pipelines
Programmatic access to Techno Electric & Engineering Company Limited earnings transcripts and 32,000+ others is available through the
EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.