In the second quarter of 2026, The Southern Company reported adjusted earnings per share (EPS) of $1.13, exceeding expectations by $0.13 and reflecting a year-over-year increase of $0.21. Revenue growth was driven by increased customer demand, particularly from data centers, and the company anticipates full-year adjusted EPS to be near the top of its guidance range of $4.50 to $4.60. Management highlighted significant contracts signed, including a 3.2-gigawatt agreement with OpenAI, which positions the company favorably for future growth and economic development in the Southeast region.

What topics did The Southern Company cover?

  • Strong Demand from Data Centers: Management noted that data center usage increased by 55% compared to Q2 2025, contributing to overall customer growth. "Approximately 11,000 new electric residential customers were added in the quarter, bringing our net electric customer adds to over 40,000 in the last year."
  • Significant Contract Wins: The company secured a 3.2-gigawatt, 25-year contract with OpenAI, adding to the 3 gigawatts from Alabama Power. "These 4 projects representing 6 gigawatts of newly contracted customer load... brings our total contracts and large load agreements across our electric subsidiaries to over 17 gigawatts by the mid-2030s."
  • Infrastructure Build-Out: Management emphasized the need for additional power generation and infrastructure to support growing demand, having secured approvals for 10 gigawatts of new generation resources. "The continued success of our operating territories and attracting significant new load is driving the need for additional new power generation and infrastructure across our Southeast region."
  • Stable Customer Rates: The company maintained stable customer rates in Georgia and Alabama until 2029, which management believes enhances customer benefits. "With retail base rates held stable... we are demonstrating that when growth is done right, everyone benefits."
  • Increased Retail Electricity Sales: Year-to-date weather-normal retail electricity sales were 2.3% higher than the first half of 2025, marking the highest growth in nearly two decades. "Weather normal commercial sales grew 7.4% in the second quarter, bringing year-to-date weather normal commercial sales to 6% higher than the first half of 2025."

What were The Southern Company's July 30, 2026 results?

  • Adjusted EPS: $1.13 (vs $1.00 est, +22% YoY)
  • Full Year Adjusted EPS Guidance: $4.50 to $4.60 (maintained guidance)
  • Retail Electricity Sales Growth: 2.3% (highest growth in nearly 2 decades)
  • New Electric Residential Customers: 11,000 (net adds of over 40,000 in the last year)
  • Data Center Load: 1.2 gigawatts (up 49% year-to-date)
  • Projected Equity Needs: $1.1 billion (by 2030)

The Southern Company's strong performance in Q2 2026, driven by robust demand from data centers and significant contract wins, positions it well for future growth. The stable rate environment and proactive capital investment strategy enhance the investment thesis. Key catalysts to watch include the finalization of RFPs and the execution of new generation projects as demand continues to rise.

Earnings Call Speaker Segments

Operator

operator
#1

Good afternoon. My name is Christine, and I will be your conference operator today. At this time, I would like to welcome everyone to The Southern Company Second Quarter 2026 Earnings Call. [Operator Instructions] As a reminder, this conference is being recorded. I would now like to turn the call over to Mr. Greg MacLeod, Director of Investor Relations. Please go ahead, sir.

Greg MacLeod

executive
#2

Thank you, Christine. Good afternoon, and welcome to Southern Company's Second Quarter 2026 Earnings Call. Joining me today are Chris Womack, Chairman, President and Chief Executive Officer of Southern Company; and David Poroch, Chief Financial Officer. Let me remind you that we will make forward-looking statements today in addition to providing historical information. Various important factors could cause actual results to differ materially from those indicated in the forward-looking statements, including those discussed in our Form 10-K, Form 10-Q and subsequent securities filings. In addition, we will present non-GAAP financial information on this call. Reconciliations to the applicable GAAP measure are included in the financial information we released this morning as well as the slides for this conference call, which are both available on our Investor Relations website at investor.southerncompany.com. At this time, I'll turn the call over to Chris.

Christopher Womack

executive
#3

Thank you, Greg. Good afternoon, everyone, and thank you for joining us for today's update. As you can see from the materials that were released this morning, Southern Company continues to perform exceptionally well, which supports a very bright future. We reported strong adjusted earnings results for the second quarter with each of our businesses contributing to performance meaningfully above the estimate we provided last quarter. The extraordinary economic development momentum and demand for power across our Southeast region that we've seen for the past several years continues particularly from data centers and other large-load customers, and our utilities are capturing this growth in a way that meaningfully benefits the customers and communities we are privy to serve and support our long-term outlook. In just the last quarter, there were 3 projects across the state Alabama Power added approximately 3 gigawatts, while Georgia Power signed a 3.2-gigawatt, 25-year contract for electric service with OpenAI for its recently announced site New Savannah, Georgia. This site, which is expected to take electric service in phases beginning in 2028 features 1 gigawatt of flexible demand response, helping to support reliable energy for all customers when demand is highest. Combined, these 4 projects representing 6 gigawatts of newly contracted customer load along with agreements previously signed brings our total contracts and large load agreements across our electric subsidiaries to over 17 gigawatts by the mid-2030s. These projects are not just bringing in substantial construction work. They are creating thousands of permanent jobs and generating billions of dollars of investment for the local economies in our service territories, and we are proud to responsibly support this growth in a way that benefits the communities we serve. In Alabama, the 3 new contracts were a clear confirmation of the continued economic development momentum building across all our electric service territories and our differentiated large load capabilities. Increasingly, our vertically integrated state-regulated model supports our ability to provide reliable power with speed and is an important differentiator for our new and existing customers. Our success attracting significant growth is a testament to the benefits that this model affords all our customers. As a comprehensive one-stop shop for Power Solutions and economic development, our electric operating companies utilize long-range integrated system planning processes to coordinate timely development of generation, transmission and distribution assets through well-structured and transparent regulatory processes that are designed to serve the growth reliably. The Southeast, with its robust network of transportation and logistics infrastructure, diverse workforce and a constructive business climate continues to be highly attractive for all forms of economic development, including hyperscalers, data center developers and large industrial manufacturers. Looking ahead, the opportunities for additional new large load and data center customer growth remains robust. New projects continue to be added to our prospective pipeline, large industrial and data center projects, which remains well above 75 gigawatts. We are encouraged by the continued progression a potential large load projects in varying stages of advanced development. Beyond the 17 gigawatts already contracted, there are an additional 8 gigawatts of projects in late stages including 3 gigawatts projected to be finalized in the near term. Clearly, the benefits of our approach are resonating with both new customers and several repeat large-load customers during a time of increasing power demand. We are privileged to support this transformative growth. David, I'll now turn the call over to you for an update on our financial performance.

David Poroch

executive
#4

Thanks, Chris. And good afternoon, everyone. For the second quarter of 2026, our adjusted EPS was $1.13 per share, $0.21 higher than the second quarter of 2025 and $0.13 above our estimate. The primary drivers of our performance for the current quarter compared to last year included increased usage and customer growth along with higher AFUDC from ongoing construction projects, higher earnings from equity method investments and tax-related impacts at our state-regulated electric utilities. The improved results in the second quarter compared to the second quarter of 2025 were also supported by contributions from Southern Company Gas and some of our smaller complementary businesses, including PowerSource, where the distributed generation, backup generation and bridge power solutions markets continue to expand. This was partially offset by interest expense from higher debt balances and dilution from additional shares outstanding. A complete reconciliation of year-over-year earnings is included in the materials we released this morning. Combined with our first quarter results, our adjusted EPS for the first half of the year is $2.46 and well above our year-to-date expectations. With customer rates held stable at our 2 largest subsidiaries, this strong performance continues to be driven by increased sales and customer growth and strong execution across each of our regulated businesses and Southern Power. These results exemplify Southern Company's commit to delivering for customers and investors. Looking towards the second half of the year, we anticipate this momentum continuing and now project our full year 2026 adjusted earnings to be near or at the top of our 2026 adjusted EPS guidance of $4.50 to $4.60. Our adjusted EPS estimate for the third quarter is $1.65 per share. Turning now to retail electricity sales. Year-to-date weather normal retail electricity sales were 2.3% higher than the first half of 2025 consistent with the trends observed earlier this year. This represents the highest retail sales growth through June we've seen in nearly 2 decades. Year-to-date, weather-normal retail electricity sales are higher across all customer classes bolstered by continued residential customer additions diverse industrial and manufacturing expansions and significantly increasing usage from data centers. Approximately 11,000 new electric residential customers were added in the quarter, bringing our net electric customer adds to over 40,000 in the last year. Manufacturing and reshoring trends, particularly in Alabama in the primary metals, stone clay glass and pipeline segments supported continued industrial strength. Weather normal commercial sales grew 7.4% in the second quarter, bringing year-to-date weather normal commercial sales to 6% higher than the first half of 2025. Notably, data center usage was 55% higher compared to the second quarter of 2025 and is now up 49% year-to-date, primarily due to accelerating load ramps from our large-load customers. System-wide, our data center load now exceeds 1.2 gigawatts, an increase of more than 500 megawatts over the prior year, and we expect this trend to continue accelerating as our 17 gigawatts of contracted demand comes online. As Chris mentioned earlier, economic development activity in the Southeast continues to be strong. In the last quarter alone, announcements were made for nearly $14 billion of investment and more than 3,000 new jobs led by several new data center facilities in Alabama and a new Amazon warehouse in Georgia. The projects announced in the second quarter marked the second highest investment level ever recorded in our electric territories, underscoring the strength of regional trends in economic development and ultimately, help shape future growth opportunities. Turning to our infrastructure build-out. The continued success of our operating territories and attracting significant new load is driving the need for additional new power generation and infrastructure across our Southeast region. Over the past several years, we work constructively with regulators to meet the demand of our growing system, securing approvals for 10 gigawatts of new company-owned generation resources, including thermal, battery and solar resources as well as hundreds of miles of new transmission lines. With the first 2 of several battery sites in service and benefiting customers and work on the 3 combustion turbines and plant gates advancing towards completion in the coming quarters, we continue to execute on the construction of our portfolio of new build generation projects. As our projected incremental load needs grow beyond our system's current and expected supply of generation capacity into the next decade, we remain well positioned to respond. Ongoing requests for proposals for RFPs at both Alabama Power and Georgia Power are underway for potential additional generation resources to help ensure that we can continue to provide reliable and affordable service to all customers. These transparent and orderly processes are designed to facilitate the timely and cost-effective procurement of new generation needs in the early 2030s. To the extent the company-owned resources are selected through these active RFP processes and ultimately authorized by the respective PSCs, these new generation investments would represent substantial incremental investment upon our current base capital plan. As future capital investment opportunities materialize, we remain committed to funding incremental capital investments in a credit-supportive manner. We continue to proactively address our identified equity needs to support our path towards 17% FFO to debt by 2029. In the second quarter, we sourced an additional $700 million of equity through our at-the-market or ATM program with forward contracts that settle at our discretion through 2028. Together with a significant amount of equity previously sourced, we have reduced our projected remaining equity need by 2030 to $1.1 billion. Our proactive shareholder-friendly equity strategy, combined with our disciplined approach in the debt capital markets and access to low-cost DOE loans continues to position us well towards our goal of efficiently meeting our future financing needs and achieving our long-term credit objectives. I'll now turn the call back over to Chris.

Christopher Womack

executive
#5

Thank you, David. We are truly in transformative time for the energy industry and our nation. And Southern Company has continually demonstrated that we are executing on this extraordinary growth in a way that protects and benefits customers and communities. Last week, the Southern Company electric system was proud to formally reinforce this commitment by joining the national rate payer protects and pledge alongside several other utilities. This pledge aligns with The Southern Company systems well-established approach to serving growth in a responsible manner while maintaining rate stability and reliability for millions of households and small businesses across the Southeast. We are confident the approach we're taking will deliver lasting benefits as we deliver rate stability for our customers. Recall, the framework under which we approach contracting with large-load customers includes pricing with minimum bills to cover at least 100% of the incremental cost to serve. Large-load customers are paying their full share. We also include provisions with strong predictions in the form of termination payments, backed by significant high credit quality collateral requirements that provide an additional layer of security. This large-load contracting structure helps ensure investors and customers are protected while providing meaningful savings for existing customers. With retail base rates held stable in both Georgia and Alabama until 2029 and significant customer benefits identified and committed to based on previously signed large load contracts, we are demonstrating that when growth is done right, everyone benefits. Across our businesses, we continue to demonstrate exceptional execution and meaningful progress delivering on this growth. Southern Company has a bright future, especially when considering the strength of the Southeast economy, the likelihood of additional large-load contracts, incremental capital investment opportunities across our state-regulated utilities and our ability to capture value across the energy value chain through Southern Power, investments in Southeastern natural gas infrastructure and distributed and bridge power opportunities through complementary businesses like PowerSecure. This extraordinary growth continues to strengthen our business fundamentals and expand capital investment opportunities well into the next decade, and we continue to see momentum building in support of an improving growth outlook into the future. The success we have had in the first half of the year positions us exceptionally well to deliver on our near-term objectives while reinforcing and strengthening our confidence in our long-term outlook and our goal to be towards the top half of our long-term earnings trajectory. Ultimately, this is a long-term business in which capital is deployed to serve customers for many decades. As we deliver for the communities we serve each and every day as we work towards our goal to provide sustainable long-term growth and outstanding financial integrity year after year, we are well positioned to continue executing with a discipline that is rooted in our long-standing commitment to our customers and investors alike. As we conclude our prepared remarks today, I want to emphasize Southern Company's commitment to making the communities that we have the privilege to serve better off because we are there. as a partner to the communities and cities where we operate, we were proud to help support Atlanta's efforts over the last 2 months and hosting 8 FIFA World Cup matches on the world stage. The success was a culmination of years of hard work by local, regional and state leadership and included significant investment in local infrastructure to welcome hundreds of thousands of visitors to Atlanta. This event was an excellent showcase for the Southeastern United States and an opportunity to continue building upon the momentum that defines this region, which will have an impact that will resonate for decades to come. Operator, we are now ready to take questions.

Operator

operator
#6

[Operator Instructions] Our first question comes from the line of Nick Campanella with Barclays.

Nicholas Campanella

analyst
#7

I hope you're hearing me.

Christopher Womack

executive
#8

Nick, we can hear you, man.

Nicholas Campanella

analyst
#9

All right. Just now that you have higher visibility on attracted megawatts load ramps, specifically '28 increased, 2030 increase by a few gigawatts here below, how does that incremental sales revenue and visibility, how does that impact your ability to maybe extend or stay out further and you're kind of committed to on the regulatory front? And just maybe you can kind of talk to that a little bit.

Christopher Womack

executive
#10

Let me start then I'll turn it to David. But as we said in our prepared remarks, we do expect to be at the top half of our long-term earnings trajectory. And so as we think about that, we think about the opportunity that provides for us in terms of meeting our long-term outlook. But clearly, as we think about the rate proceedings and regulatory proceedings, those are things that conversations will have with regulatory bodies. But as we have extended our rate stability focuses in both Georgia and Alabama, we think it creates optionality for us to continue to provide rate stability for our customers. David, anything you want to add?

David Poroch

executive
#11

Yes. Thanks, Chris. And Nick, great question. As we work through these processes with the success that we've had in signing these contracts, it does give us a great deal of flexibility in enhancing the benefits for customers. Clearly, we've got the ability to look for more generation capacity through the structure processes that we have in Alabama and Georgia. And like we've talked about in the past, we are probably about 1 gig or 2 away from, if you will, selling out the capacity that we had approved in Georgia last year. So now we're going to work through that process. And the success that we've had in signing these contracts really gives us some durability toward the future and additional confidence in being able to deliver on our goals well into the next decade.

Nicholas Campanella

analyst
#12

And then maybe on the 3 gigawatts that you're finalizing -- in finalizing stages for, is that within the 2030 window? Or is it after it? And what are kind of the key milestones you still need to get through on those 3 gigs of finalizing?

David Poroch

executive
#13

Sure. No, for sure. Working through those contracts, those are likely to go into 2028 and beyond. So they'll like every other big data center project. Large-load customer have a ramp-up period. A couple of them that we're working on would initiate that ramp-up in 2028 and bring us into the next decade.

Operator

operator
#14

Our next question comes from the line of Shar Pourreza with Wells Fargo.

Shahriar Pourreza

analyst
#15

So just, Chris, on Southern Power, the existing tone agreements are going to start to roll off. I know there's obviously an opportunity to [indiscernible] capacity towards serving the hyperscalers. Can you maybe discuss how you're thinking about that opportunity set, have conversations with the hyperscalers begun with these assets? And would any opportunities be captured within your existing 75 gigawatt pipeline. I guess what does this mean to the plan, I guess, Yes?

Christopher Womack

executive
#16

Yes. And Shar, we've talked about this, I think, on a number of calls in terms of the opportunity as these contracts begin to roll off and to expire opportunity for recontracting. And so the team is now in the midst of having those conversations with a host of different counterparties that you understand our risk profile there in terms of making sure that they're creditworthy counterparties. But if you look at in terms of where they were contracted from a pricing standpoint in terms of where the market is today, we do see upside opportunities in those pricing opportunities that will contribute to the durability and the length of our long-term plan. So we've talked about this a good bit with you guys. And so that's where we are, and we're going to continue to pursue this opportunity as we move down that path and as these contracts expire and the opportunities for recontracting positions itself.

Shahriar Pourreza

analyst
#17

Got it. And these wouldn't just be typical tolling agreements, that would be the energy and capacity side, I'm assuming under...

Christopher Womack

executive
#18

Correct. Correct. Yes.

Shahriar Pourreza

analyst
#19

Got it. Got it. And then I know, Chris, your favorite topic is new nuclear, right? So I guess, would sort of lessons learned between Unit 3 and 4 and sort of this big attention now to large-scale reactors. Should there be like any financial backing from the government and hyperscalers taking on some of the cost overrun risk. Is that something Southern would be interested in building, i.e., through the PAC10? Just any color on potentially participating in this consortium? Or are you just looking to license the blueprints?

Christopher Womack

executive
#20

And you've heard me talk a lot about the importance of new nuclear, helping this country meet this incredible moment that's in front of us. I mean I do think as we look into the 2030s, this country needs to have, particularly in the mid-30s, need to have some more nuclear units in operation. I have to give a great big shout out and complement to the Trump administration. I mean, there are a number of actions they have taken on the regulatory front with bringing groups together around long lead time items, just a lot of things that they're doing, and we have a lot of conversations with them about how to make this a reality. I mean Southern is not going to be next, may be clear about that. But we're going to continue to work constructively and very -- I would say, pretty aggressive with this administration and with a lot of other parties to see how we can get this done because I do think it's important for -- from an energy policy standpoint, from the economy to meet this moment and meet this demand that we see in the marketplace today.

Shahriar Pourreza

analyst
#21

Just I guess the follow-up is, are you finding traction with the hyperscalers taking on cost overrun risk above budgeted amounts for these AP1000s?

Christopher Womack

executive
#22

I don't want to get ahead of kind of that firm conclusion. But yes, we're having conversations with them in terms of what role they can play in this conversation in this equation.

Operator

operator
#23

Our next question comes from the line of Carly Davenport with Goldman Sachs.

Carly Davenport

analyst
#24

Maybe to start, you've talked in the past about the potential for upside on the capital plan related to FERC pipeline investments. Anything new on that front in terms of timing, especially as you think about the incremental RFPs that maybe could point to some incremental gas plant builds?

David Poroch

executive
#25

Sure, Carly. Thanks. Great question. Like we've talked about with the contracts that we're signing, the growth in the Southeast region, a strong economy, we definitely see opportunities in our FERC-related pipeline -- FERC regulated, I should say, pipeline investments. We've talked about some of those, but as the opportunities continue to grow, we do see the possibility of expanded opportunities in those investments that we currently hold. So really excited about those prospects. The RFPs that we've got in place and the processes that we have in our regulated jurisdictions will help inform that, but we see great potential in the Southeast to continue to grow those investments.

Christopher Womack

executive
#26

Carly, only thing I would add is that infrastructure, I mean, across the Southeast, and we -- you've heard us say it before, is needed to support this growth. That is here and for the growth that is to come. So there is more to be done here. We think there's a real opportunity for us in terms of all the pipeline expansion opportunities to align with the news that we have that are portrayed in our RFPs.

Carly Davenport

analyst
#27

Got it. Okay. That's really helpful. And then just a follow-up on the RFPs that you have ongoing for the generation needs through 2032. Did those filings already contemplate some of the progression in the load pipeline that you've seen over the last quarter or so? And is there potential room for upside on even incremental to the incremental RFPs, if you think about the conversion of the pipeline?

David Poroch

executive
#28

Incremental to the incremental, I love that term. I have to think about how to use that. I appreciate that. But yes, the opportunities that we see there are well baked into the RFPs. We talked about our load forecast and the processes that we use to -- in a rather conservative way, project what that need could be. And as we continue to sign these contracts, that's really going to be the foundation for the RFPs that we have, both in Alabama and Georgia. And so there is certainly potential out there to go and procure more generation than we have identified right now. We just can't get ahead of the process. There's a thorough screening structure, good vetting and everybody is going to have an opportunity to participate in those processes. And so -- and also, I think it's worth reminding that as we regularly say, there's not placeholders in our capital plan. We don't get ahead of our regulators. And so obviously, you can see how the upside that we've talked about is not in our capital plan right now. So the RFPs that are open in Alabama, the RFPs that are open in Georgia, none of that is contemplated in our capital forecast at the moment.

Christopher Womack

executive
#29

One thing I would add, the open or contract in Georgia pushes us beyond our recently approved capacity by right around 1 gigawatt. So just making sure that was real clear in terms of where we are and what the upside opportunities are.

Operator

operator
#30

Our next question comes from the line of Steve D’Ambrisi with RBC Capital Markets.

Stephen D’Ambrisi

analyst
#31

Just had a quick one, kind of a follow-up on Carly's question actually. Just to put a little bit of finer point on it, is my understanding that any -- basically any new incremental load, especially large load in Alabama would drive basically incremental generation requirements. So obviously, you have the RFP outstanding. But if the load forecast is up 3 gigawatts in the quarter and then you're talking about OpenAI, at least 1 gigawatt, but I think the RFP is 2 to 6, but is a range beyond that as well. Like can you just frame is this 4 to 5-plus gigawatts of gen that we could put some type of capacity multiple on and try and estimate what the size is? Or -- obviously, I don't want to put the cart in front of the horse, but want to make sure we're level setting on what's in the plan and what the opportunity is?

David Poroch

executive
#32

Yes. Great question and really a good way to think about it. Appreciate your thought on not getting in front of the process. We're definitely focused on that. But I think the way you're thinking about it is directionally correct. We've got the newly signed contracts in Alabama. That's going to inform that. That's about 3 gigs right there, contracts signed. We're about 1 gig or so oversubscribed, if you will in Georgia based on what we've signed. And keep in mind, I think we've shared this in the past, maybe a decent rule of thumb to think about capital opportunities going forward is about $2 billion or so, a little bit above maybe related to 1 gig of new generating capacity, that kind of covers a broad range of different generating sources for us.

Stephen D’Ambrisi

analyst
#33

Okay. That's very helpful. And then just in terms of like the finalizing and late-stage pipelines that you continue to fill up. Obviously, you've seen great momentum and progression in kind of converting this. But again, like how do these finalizing gigawatts kind of filter into this RFP? And just like what's the time line for like when those loads would energize and when we have to think about resources to serve those? Just trying to like sequence it out here.

Christopher Womack

executive
#34

Sure. No. I mean those projects will vary project by project. And so as we finalize those agreements and they are certified and blessed by the commissions, they will factor those into the RFP process going forward to match up with the year in which those resources are, in fact, needed. And so as you -- as we kind of are in a position to inform as we finalize those contracts, that is information then that will be forthcoming. Once those contracts are finalized and the projects are approved and has also then as we provide you with an updated load forecast. So there are a couple of proceedings that will unveil how that all lines up and matches up with the needs and what the new opportunities are going forward.

David Poroch

executive
#35

And I might add, as we work through those processes, to the extent that the company is selected to provide that generation resource, we're going to probably start feathering in some spend also not currently contemplated in our projections in the sort of the '28 timeframe, and that will start to feather in as we build out that generation to come online in the '31, '32 time line.

Operator

operator
#36

Our next question comes from the line of Jeremy Tonet with JPMorgan.

Jeremy Tonet

analyst
#37

Just wanted to pivot to Mississippi, if I could, for a minute here. And we've had recent stakeholder conversations in the state where it seems like the state is particularly receptive to incremental data center activity more than what we usually hear. And so I was just curious, I guess, your outlook there, if you could maybe talk a little bit more on the opportunity set and what you see maybe down the pipeline there?

Christopher Womack

executive
#38

As we have said before, we've talked, I guess, a number of quarters now about seeing this momentum migrate to the west. And you're clearly seeing that now in Alabama. You see success with 500 megawatts projects in Mississippi. And as we talk about our pipeline, that also reflects that ongoing activity -- increasing activity that we also see in the Mississippi territory.

Jeremy Tonet

analyst
#39

Got it. And then just wanted to go to OpenAI again, with demand response there. Just wondering how is demand response fitting into your conversations with projects overall in the pipeline? How do you factor that into kind of your assumptions going forward?

David Poroch

executive
#40

Yes. So great question. And it does enter into all those conversations. And we'd like to see that continue along and stay flexible. It's 1 of the -- actually 1 of the great aspects that our 3 electric jurisdictions have where we're not limited to just a tariff. We can negotiate bilateral contracts that leverage the flexibility and the demands that these hyperscalers line and be able to price that right. So I think this is a great trend, and I'd like to see it continue, and it is a part of every conversation that we have.

Christopher Womack

executive
#41

One of the things I'd add there is that very early on in our conversations with hyperscalers, we begin to raise matters like technical requirements in terms of how their operations would impact the system, how would impact the grid and not just being a taker but having creating flexibility to provide benefits to the entire grid. So I think as we look at this broader conversation about data centers, and I think these things have got to be communicated more broadly in terms of the value and benefits and flexibility and how they are being supportive of the grid, as how they're being supportive of communities. I mean there's an incredibly positive narrative and story to be told here. We all have got to be, I think, a little more voice these benefits a little more stronger in terms of making sure that gets into the conversations about data centers as we hear all the conversations and the noise right now about what's going on. So just a great win-win, I think, for us as well as the customer.

Operator

operator
#42

Our next question comes from the line of Steve Fleishman with Wolfe Research.

Steven Fleishman

analyst
#43

So just -- could you just remind in Georgia for open AI and other customers who maybe aren't investment-grade credits or strong investment grade, how did the tariffs work from a credit standpoint [indiscernible] large-load tariffs?

David Poroch

executive
#44

Yes. So remember the -- if you will, the kind of 4 pillars under which we're negotiating structure these contracts in territories, you got long-term contracts and you hit it exactly the OpenAI contract is 25 years. Our minimum bills cover 100% of the incremental cost to serve. There's default provisions in there and those default payments are tied to collateral. And so we've got a lot of flexibility in terms of the forms of collateral that we can take from these counterparties. And if a [indiscernible] guarantee works for us, depending on the credit quality of the counterparty, we'll work with that. But in some instances, that they're not quite at the investment grade that we want to see, we'll look to lines of credit, we'll look to surety bonds, we'll look at other combinations. But at the end of the day, the collateral portfolio that we're going to take to back up these contracts, is going to be put us at about an A- or better position. And keep in mind, you asked specifically about OpenAI, and that's about $28 billion of collateral that will be in the aggregate time full ramp. So I think we're in a really good spot for that. And keep in mind, that's -- we have the flexibility to determine what collateral is accepted to us -- acceptable to us and puts us in a position of about A- or better. So a combination of lines of credit, surety bonds in this particular case.

Steven Fleishman

analyst
#45

Okay. That's very clear. The RFPs, could you -- and I apologize if I missed this earlier, but just can you remind us just the time lines for finalizing answers and then approvals?

David Poroch

executive
#46

Sure. So the process is going to play out through most of the rest of the summer into the fall. I think by year-end, we should have a good idea of what projects were selected through the RFP process. And then once those projects are selected, that will move into a certification process that will take place much of -- throughout much of 2027. So latter part of 2027, we'll have good clarity as to what actually gets certified. And Alabama is in a fairly similar time line. So you can kind of count on both the proceedings in Georgia and Alabama, not exactly to run in parallel, but pretty close.

Steven Fleishman

analyst
#47

Okay. And then last question just on Georgia. Maybe you guys have clearly highlighted some of the benefits, both economic and customer rate benefits of the data centers. But then I think there's still been political noise there, particularly maybe more from the Democrats mix on data centers. Can you just give us maybe a little lay of the land there? And is there any kind of appreciation growing for some of the benefits to kind of offset some of this kind of pushback -- or reported alleged pushback?

Christopher Womack

executive
#48

Steve, I would say -- I would suggest you look at the OpenAI announcement in terms of how that plays out with that community as they highlighted the project, but they also highlighted along with us in terms of the rate stability that comes along -- and benefits that come along with the project, but also how they communicated kind of the economic community benefits that align with that project. Yes, I mean, there's noise all across the country about data centers. But I think there's no moratorium across the state. And yes, there may be some moratoriums in various counties. But I think you continue to see progress, activities, projects move forward in our territory. once again, I'll say we've got to do a better job. Hyperscalers need to do a better job of explaining the benefits and value and dispelling some of the misinformation that's out there on social media. But I say you continue to see the pipeline continue to remain very full and continue to grow, and you continue to see projects advance and projects get approved all across our territory.

David Poroch

executive
#49

I'm sorry, let me clarify one thing. I said you were asking specifically about OpenAI and collateral, and I was talking about the entire portfolio, so I apologize for that. The whole portfolio of the 17 gigs, we got about $21 billion of collateral. So -- and I recognize you were speaking specifically the OpenAI contract. So I just want to clarify that for you.

Operator

operator
#50

Our next question comes from the line of Andrew Weisel with Scotiabank.

Andrew Weisel

analyst
#51

Congrats on the OpenAI deal, certainly a massive project. I want to follow up on the gigawatt of demand response, I agree that that's a great resource. I know we've seen something similar in Michigan, but am I right that this is the first time you're doing something like that? And I know that the press release talks about long-term savings for customers. Have you quantified that? And is it more about accelerating speed to market for the data center? Or does the rest of the customer base see any benefits?

Christopher Womack

executive
#52

The rest of the customer base will see benefits across the entire project. I mean what we're doing is during peak load periods, doing high demand periods, we're able to save the peak. And so as we operate this economic system on a minute-by-minute, second-by-second basis, we're always looking to put online the most economical resource to meet and serve that load. And so that is tremendous value and benefits to the entire system, having that resource be flexible. So it's an incredible value and incredible benefit to the entire grid as we operate our system.

Andrew Weisel

analyst
#53

Okay. And was this the first time you've done that for a data center?

Christopher Womack

executive
#54

Yes.

David Poroch

executive
#55

Yes, it is.

Andrew Weisel

analyst
#56

Okay. Great. Hope to see more of it. Then secondly, on equity. I know you've been pretty active. You settled $2 billion of the ATM that was priced in 2025 and your -- you've priced $700 million that will settle through '28. Are you able to give any guidance on how to think about the pace of equity and when it will actually hit over the next few years? I know there's a lot of moving parts there. And I don't expect you to get too specific, but how should we think about the year-by-year dilution and whether it will be ratable or maybe accelerated? Any color there would be very helpful.

David Poroch

executive
#57

Yes. I think you said it really well. There's a lot of moving parts in terms of making the decisions on how to draw those equity commitments. And keep in mind, they're available to us really at a few days' notice. And so we have a great deal of flexibility to manage our liquidity over that period. But we generally want to shape that in terms of kind of mirroring, if you will, our capital outlays for the construction effort that we're going to have. But it also dovetails into the plan to get near 17% FFO to debt by 2029. And I think we've settled about $2 billion recently. And that, again, like I said, kind of helps us down the path of 17% FFO to debt. And bottom line, we just -- we're going to continue to do this in the most shareholder-friendly manner that we can, protect the credit quality and continue to draw on this as needs and opportunities become available.

Operator

operator
#58

Our next question comes from the line of Julien Dumoulin-Smith with Jefferies.

Julien Dumoulin-Smith

analyst
#59

Look, I wanted to take this in the direction of rates, rate cases, et cetera. I mean, obviously, transposing this real ongoing success. How do you think about the opportunity here, Georgia and Alabama, but especially in Georgia, right? Obviously, there's a regular cadence to these cases. And obviously, there's a desire maybe at times to update tariffs and rate structure. But is there an opportunity to come back with a bigger rate credit here? I mean, obviously, the number, I think, from last year at this point was north of $0.5 billion. I mean is there a way to, again, do what you did before and effectively sidestep the revenue process here?

Christopher Womack

executive
#60

Julien, let me say, as you know, we don't get ahead of our regulators. We work very constructively with them kind of hand in hand. I mean our goal at all times is to keep rates as low as possible for our customers. And so we are thrilled with how we are delivering rate stability to our customers through '28. And so I mean, as we continue to sign these contracts, I mean, the conversation that we'll have and have other considerations about what's possible. But I'm not going to get ahead of any process or any conversation with the commission at this point in time. But yes, the growth provides us incredible opportunities to benefit customers, but also to continue to deliver rate stability. I mean I was listening to a lot of commentary yesterday after the Fed decision, a lot of commentary about inflation and electric rates going up across the country. Electric rates are not going up in our territory. We're delivering rate stability to our customers, and that's something that we are thrilled and privileged to make available and provide to our customers, that benefit. Stability is savings. One of the things I'll try to remind ourselves is that being flat or being frozen, there's real kind of nominal benefits in terms of savings for customers as we hold rates flat going forward.

Julien Dumoulin-Smith

analyst
#61

Yes. No, I mean, Clearly, you have a demonstrated track record on that front. And then Alabama, how do you think about this growth transposing itself; a, in terms of the process, like how do you take this load growth and put it into rates? Again, I know you've got this rate CMP. I mean, in theory, that's how you bring on some of the new capacity, I think it for the incremental 3 gigs. And then separately, is there some sort of equivalent thought process on that statement in particular? I guess that your comments a little generic, too.

Christopher Womack

executive
#62

Yes, you got it. I mean they'll go through those traditional proceedings in terms of getting these projects and getting the load needed to be certified through the CMP process. And so as you know, they've made some changes in the structure and size of the commission. They're going to have a new Secretary of Energy in Alabama. They've just gone through processes of kind of I would say, codifying the procedures of how we are serving signing up these contracts. So Alabama, I think, has had a very orderly process about how to approve these contracts, but also then get these projects approved by the commission and get them in the rates as well as through the RFP process. So what do we say 3 gigawatts adds to long-term benefits for customers. So great opportunities in Alabama.

Operator

operator
#63

Our next question comes from the line of Richard Sunderland with Truist Securities.

Richard Sunderland

analyst
#64

Just circling back to Southern Power, I know you had some updates last quarter on this front. Curious about kind of the tone and interest on the remaining upgrades and then the brownfield efforts, I think you tapped for an update later this year as well. Given the load trends, how is all that trending? And are you still thinking about having some sort of a Southern Power update this year?

David Poroch

executive
#65

Yes. Great question. We continue to evaluate those opportunities. I mean the conversations that we're having with our current counterparties as well as exploring opportunities with new counterparties at Southern Power are proving to be very fruitful. And we're looking forward to working through those. But keep in mind, the business model under which we operate Southern Power, right, we don't go and build something and see who shows up. So it's a very disciplined and structured process that we continue to engage in these conversations. So there's a lot of great potential out there to not just reprice the contracts that will come rolling off into the next decade, but also take advantage of the announcements that we made last quarter in terms of those up rates. And as we continue to have those conversations and explore those opportunities with the current customers at Southern Power and potential new customers, then we'll have better clarity as to when and how we can execute on the additional upgrades that we alluded to.

Christopher Womack

executive
#66

But we look forward to giving you updates on the activities that's occurring that's under consideration at Southern Power. I think there's some real opportunities there.

Richard Sunderland

analyst
#67

That's great to hear. And then I guess turning back to the script, recognizing you called out the sales growth on the quarter and thinking about some of the data center load added to the system recently. Any learnings you'd highlight from some of that ramp in the sales trends? And I guess, in particular, how that might apply to your outlook for all this load growth and running that through to the EPS growth guidance as well?

Christopher Womack

executive
#68

No, I'd start by saying, I mean, one of the things we see is that we have to work very closely with these projects in terms of what their ramp rates are. They may not be what was projected when the projects were initially approved. But we work very closely with them in terms of kind of what those ramps will be. But once again, remember, the minimum bills that we have, I mean, we've kind of somewhat what we call decouple the revenue because we do have those minimum bills from an operational standpoint. We have to work very closely with them in terms of understanding what their ramp rates are in terms of what the system implications are. But the bottom line is the load is very real. And so we know it's -- may not be there initially, but we know that is coming.

David Poroch

executive
#69

And I might add that the customers that we've been serving for a number of years, we have learned so much from their experience that has helped us inform these new contracts that we're signing. And so like Chris mentioned, the protections that we put in place for customers and the company in terms of the minimum bills, that is really, we think, going to be a distinct advantage going forward that will protect our customers and the company in terms of that type of stability that we're trying to deliver. And we've crossed over the 1,000 megawatt line this particular quarter, and the growth has just been fantastic in that portfolio of data centers and large load customers that we're currently serving, really exciting.

Operator

operator
#70

Our next question comes from the line of Travis Miller with Morningstar.

Travis Miller

analyst
#71

Going back to the OpenAI project. I wonder if you could talk a little more about what made that location unique and why both you and OpenAI decided that, that location could handle a project of this size? And then secondly, build on that, are there other areas in your service territory? Or what are the other areas where a project of that size can be constructed and operational in such a short time?

Christopher Womack

executive
#72

Yes. I mean it's -- these projects in the processes of economic development, it's a lot of -- it's a lot of courting, a lot of evaluations of sites and locations and geography, topography, location to infrastructure -- electric infrastructure facilities and other energy resources being available. And so it's not a set criteria, but there's a lot of kind of investigation of sites to see what works for the projects that these companies want to construct. And so -- and we're glad when they work out. We're also thrilled that we have a number of meaningful sites that are available for additional consideration across our entire service territory. I'm not going to give you kind of exactly where those sites are. I mean that's -- a lot of that's kind of protected, but know that we have additional opportunities for similar projects. I mean the Savannah area, the economy there is very strong with the [indiscernible] plant that is there and continues to grow and expand, the Port of Savannah that continues to kind of lead this country and activity from a shipping standpoint. So Savannah, Evvingham County, those areas have proven to be just wonderful sites for economic activity.

Travis Miller

analyst
#73

Understood. And one real quick one. In terms of meeting any future equity needs as you add to the CapEx, any interest in taking minority interest investment or another partner to meet some of those?

David Poroch

executive
#74

We look at a lot of different structures. But at the moment, we just don't see that as a need. Love the cards that we have, love the opportunities that we've had in terms of issuing the securities and the receptiveness in the marketplace. I just don't see that as a need for us at least for the foreseeable future.

Operator

operator
#75

And that will conclude today's question-and-answer session. Sir, are there any closing remarks?

Christopher Womack

executive
#76

Just let me thank everybody for joining us today. Let me conclude by saying this is an incredibly exciting first half of the year for Southern Company, and it sets us up for the rest of the year, but I also think it speaks to what a bright future we have. And so thank you for joining us today. Have a good rest of the day.

Operator

operator
#77

Thank you, sir. Ladies and gentlemen, this concludes the Southern Company Second Quarter 2026 Earnings Call. You may now disconnect.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete The Southern Company transcript — plus 248,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to The Southern Company earnings transcripts and 248,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.